227
TADS Data Reporting Training 2017 TADS Data Reporting Training November, 2017

TADS Data Reporting Training - NERC€¢ kV lines shared with other utilities within or across state boundary • All TOs with a share of ownership should report element in 2.X forms

Embed Size (px)

Citation preview

TADS Data Reporting Training

2017 TADS Data Reporting TrainingNovember, 2017

RELIABILITY | ACCOUNTABILITY2

Agenda

Day 1 Day 2

What is TADS Introduction & Review

TADS Mechanics• Accessing the portal• Checklist• Inventory• Outage and Event report

Coding continued• Outage modeData Validation

Lunch Lunch

Coding• Event code and types• Fault Type• Initiation code• Cause code (Initiating and sustained)

Review, Examples, Discussion

RELIABILITY | ACCOUNTABILITY3

Instructors and Contributors

• Instructors• Brian Starling – Project Manager• Kurt Weisman – Reliability Performance Consultant• Maggie Peacock – Analyst, WECC Performance Analysis• Mark Matthews – Lead Engineering Technologist• Michael Bocovich – Principal System Protection Engineer• Scott Clemons – System Engineer• Tammy Norwood – Transmission Engineer

• Contributors• Brantley Tillis – Director of Transmission Performance• Rich Quest – Retired

RELIABILITY | ACCOUNTABILITY4

Welcome

• Introduction of Attendees• Your name• Company• TADS Experience

• NERC Performance Analysis Staff• Donna Pratt – Performance Analysis Manager, Data Analytics• Jack Norris –Engineer and TADS Liaison• Svetlana Ekisheva – Senior Manager, Statistical Analysis and Outreach • Margaret Pate – Reliability Risk Analysis Control Liaison• Lee Thaubald – Technical Analyst• David Till – Senior Manager, Performance Analysis

RELIABILITY | ACCOUNTABILITY5

Turning Technologies

1. Press any button to turn the clicker onIcons in the upper corners of the screen indicates it is on (Figure 2)

2. When ready to vote press the black letter button that corresponds to your answer

3. Your answer has been submitted when you see your letter with a checkmark on the screen (Figure 3)

Figure 2: Clicker is on

Figure 3: Vote submittedFigure 1: Clicker

RELIABILITY | ACCOUNTABILITY6

<1 Year 1-2 Years 2-4 Years 4+ Years I’ve never reported

TADS data before

0% 0% 0% 0% 0%

How many years have you reported TADS?

A. <1 YearB. 1-2 YearsC. 2-4 YearsD. 4+ YearsE. I’ve never reported TADS

data before

RELIABILITY | ACCOUNTABILITY7

Yes No No, I reportannually

0% 0% 0%

Have you reported your Q3 TADS Data?

A. YesB. NoC. No, I report annually

RELIABILITY | ACCOUNTABILITY8

What is NERC?

• November 9, 1965 Northeast black out• 30 million people affected• $100 million of economic losses (~$770 million today)

• 1967 Federal Power Commission investigation, recommends “council on power coordination”.

• 1968 Regional groups formed NERC• August, 2003 Largest blackout in North America to date• April, 2006 NERC designated as Electric Reliability Organization (ERO) by FERC as well

as most Canadian provincial authorities

RELIABILITY | ACCOUNTABILITY9

NERC Regional Entities (REs)

RELIABILITY | ACCOUNTABILITY10

What is TADS?

A - Availability

S - System

T - Transmission

D - Data

RELIABILITY | ACCOUNTABILITY11

What is being collected through TADS?

• Basic Company Information (Forms 1.x)• Inventory Information (Forms 2.x and 3.x)• Event Information (Form 5)• Automatic Outage Information (Forms 4.x)• Non-Automatic Outage Information (Forms 6.x)

RELIABILITY | ACCOUNTABILITY12

Where is TADS Data Being Used?

• Annual State of Reliability (SOR)• Key Findings• Chapter 3: Severity Risk Assessment and Availability Data Systems• Chapter 4: Reliability Indicator Trends• Appendix B: Statistical Analysis of Transmission Data

• Technical & Statistical Papers• Performance Analysis of North American AC Circuits on Common Structures Using TADS and CEA

Outage Statistics (IEEE PMAPS, Pending)• Transmission Availability Data Systems Reporting and Data Analysis (IEEE PMAPS, 2016)• Research on Common-Mode and Dependent Outage Events in Power Systems – A Review (IEEE

PACME, 2016)• North American AC Circuit Outages Initiated by Transmission Equipment Failures and Human Error

(IEEE PES, 2016)

RELIABILITY | ACCOUNTABILITY13

Module 1Access to the OATI portal

RELIABILITY | ACCOUNTABILITY14

Login

To log into the TADS OATI web portal go to:www.nerc.oati.com

If you have forgotten your password email [email protected]

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY15

Module 2Activate and Updating the Checklist

RELIABILITY | ACCOUNTABILITY16

M2 – Review Contents of the Checklist

Access the Tranmission Owner (TO) checklist• Transmission (TADS) > Forms > Checklist

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY17

M2 – Review Contents of the Checklist

• Select the new reporting year• Click Apply

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY18

M2 – Review Contents of the Checklist

• Click on the “Update Checklist or Completion Status” button located at the bottom of the checklist form.

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY19

M2 – Review Contents of the Checklist

• Click the “Yes” radio button to attest the entity is a reporting TO for the year.

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY20

M2 – Review Contents of the Checklist

The checklist expands once yes is selected• Exempt forms with your reason for exemption

(see next two slide)

• Mark forms as completed(after data has been entered)

• Validate data(after data has been entered)

• Modify to save• Start reporting data

Checklist image shortened to fit

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY21

M2 – Review Contents of the Checklist

Mark outage forms (4.1 – 6.4) exempt for any inventory not owned.• Select the “Yes” radio button under exempt.• Add a reason to the “Reason” box. Note: the completed column will automatically

mark as complete for that form.

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY22

M2 – Review Contents of the Checklist

Mark outage forms (4.1 – 6.4) exempt for any quarter that did not experience an outage• Select the “Yes” radio button under exempt.• Add a reason to the “Reason” box. Note: the completed column will automatically

mark as complete for that form.

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY23

M2 – Review Contents of the Checklist

Mark outage forms complete once data has been entered

Click Modify to validate and save

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY24

Module 3ContactsForm 1.2

RELIABILITY | ACCOUNTABILITY25

M3 – Creating Contacts (Form 1.2)

TO Contacts• Establishes contact information for TADS reporter or Transmission Owner• Provides information for other company contacts (supervisor, operator, analysts, etc.)• Is different from TADS portal access (anyone can be a TADS contact no certificate

needed)• Must be “reviewed” once a year• Should be kept up-to-date through out the year

RELIABILITY | ACCOUNTABILITY26

M3 – Creating Contacts (Form 1.2)

Click on the “Needs Review” or “Reviewed” link to open the TO Contacts form

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY27

M3 – Creating Contacts (Form 1.2)

Click on “New Contact” to add a new contact(click on the hyperlinked name to edit a contact)

Fill out the form

NOTE: Contacts can not be deleted, instead the active checkmark is removed.

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY28

Module 4Shared InventoryForms 2.1 & 2.2

RELIABILITY | ACCOUNTABILITY29

M4 – Shared Inventory (Forms 2.1 & 2.2)

Shared Inventory Forms• Designed to ensure only one TO reports outage information for elements jointly

owned• kV lines shared with other utilities within or across state boundary• All TOs with a share of ownership should report element in 2.X forms

• Element ID MUST be unique across all entities included in any form 2.X

• Provide primary Reporting TO given NERC ID, Company Name, Region, and Country

RELIABILITY | ACCOUNTABILITY30

M4 – Shared Inventory (Forms 2.1 & 2.2)

Click on the “Needs Review” or “Reviewed” link to open the 2.1 or 2.2 forms

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY31

M4 – Shared Inventory (Forms 2.1 & 2.2)

Click “Add” to open the 2.X form and add shared inventory

Fill in the formClick “Enter” to save

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY32

Module 5Inventory

Forms 3.1, 3.2 and 3.3

RELIABILITY | ACCOUNTABILITY33

M5 – Accessing the Inventory (Form 3.x)

Inventory Forms 3.1, 3.2, and 3.3.• Click the “Needs Review” for

inventory on forms 3.x• Click on “Inventory Detail” to access

the current year’s inventory• Add, modify, and delete inventory

from the inventory detail form for the current year

• Once up-to-date click the “Review” button on the inventory summary form.

• NOTE: Inventory can still be added, modified and retired throughout the year.OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY34

M5 – Line Inventory (Form 3.1)

Form 3.1 required fields• Circuit type• kV – voltage class group• Element Identifier – An alphanumeric name

that identifies the element which is outaged; Must be unique and be consistent from year to year (i.e., A1001)

• From Bus/To Bus – The line end points• In Service Date – In service date if known or

1/1/YY inventory was added to TADS• Number of Terminals

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY35

M5 – Transformer Inventory (Form 3.3)

Form 3.3 required fields• Element identifier – see previous slide• Transformer location – The physical

location of the transformer• High Side kV – Higher voltage side

(primary); Determines how it is reported• Low Side kV – Lower voltage side

(secondary); Determines if transformer is reportable

• In Service Date – In service date if known or 1/1/YY inventory was added to TADS

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY36

Monthly Quarterly Annually Never

0% 0% 0% 0%

How often do I indicate I am reporting & update my contacts?

A. MonthlyB. QuarterlyC. AnnuallyD. Never

M5 – Example

RELIABILITY | ACCOUNTABILITY37

Do I report my transformer based off of low side or high side?

• Transformers are classified as TADS reportable based on their lower or secondary voltage classification. Transformers with secondary or lower winding voltages greater than 100kV, or are included in the BES through the inclusion criteria are reportable.

• Once a transformer has been classified as reportable, it is entered into the inventory based on its high side or primary winding voltage class.

• Examples:• A 500kV to 230kV transformer would be entered into TADS as a 400-599kV• A 500kV to 138kV transformer would be entered into TADS as a 400-599kV• A 500kV to 765kV transformer would be entered into TADS as a 600-799kV

RELIABILITY | ACCOUNTABILITY38

If I cut circuit A in the middle of the year to make

If I cut circuit 100 in the middle of the year to make a new circuit 100 & new circuit 101 what is the process?

Station A Station BLine 100 (230kV) 33 miles Station C

Line 100 (230kV) 22 miles Line 101 (230kV) 11 miles

Element Identifier From Bus To Bus Length In Service Date Retirement Date Precursor

100 Station A Station B 33.0 2/29/2012 11/2/2017

100-2 Station A Station C 22.0 12/5/2017 100

101 Station B Station C 11.0 12/7/2017 100

Each Element ID,must be unique. Even if the operating number is reused, they element id reported to TADS must be a unique id.

RELIABILITY | ACCOUNTABILITY39

Resourceshttp://www.nerc.com/pa/RAPA/tads/Pages/default.aspx

[email protected]

RELIABILITY | ACCOUNTABILITY40

Resources For Outage Reporting

Always check the NERC website for the most recent versions!!TADS Data Reporting InstructionsTADS Definitions - Appendix 7TADS FAQTADS Bulk Upload Workbook

RELIABILITY | ACCOUNTABILITY41

Resources Continued – NERC TADS Outage Reporting Quick Reference Guide

RELIABILITY | ACCOUNTABILITY42

Module 6Automatic Outage Reporting

Forms 4.X

RELIABILITY | ACCOUNTABILITY43

A. B. C. D.

0% 0% 0% 0%

M6 – Reporting Duties

A. I gather outage information and I enter the data into webTADS

B. I gather outage information, but someone else enters it into webTADS

C. I don’t gather outage information, but I do enter it into webTADS

D. I’m not involved in TADS, I’m here for free food or because my boss made me come for some reason

RELIABILITY | ACCOUNTABILITY44

M6 – Determination: Is it an automatic outage?

RELIABILITY | ACCOUNTABILITY45

M6 – Automatic Outage

Automatic Outage:An outage that results from the automatic operation of a switching device, causing an Element to change from an In-Service State to a not In-Service State.

Single-pole (phase) tripping followed by successful AC single-pole (phase) reclosing is not an Automatic Outage.

In-Service State:An Element that is energized and connected at all its terminals to the system.

RELIABILITY | ACCOUNTABILITY46

M6 – In-Service State Example from Appendix 7

• AC Circuit A is bound by the two breakers• Transformer A is bound by a breaker and a disconnect switch• AC Circuit B is bound by a breaker and a disconnect switch• Transformer B is bound by a breaker and a disconnect switch.

230 kV

AC Circuit A

AC Circuit B

Transformer A

Transformer B

500 kV

RELIABILITY | ACCOUNTABILITY47

M6 – In-Service State Example from Appendix 7

• AC Circuit A reports an outage – one terminal is disconnected• Transformer A reports an outage – both terminals are disconnected• AC Circuit B DOES NOT report an outage – both terminals are connected• Transformer B reports an outage – one terminal is disconnected

230 kV

AC Circuit A

AC Circuit B

Transformer A

Transformer B

500 kV

A 230 kV bus fault opens the designated breakers.

RELIABILITY | ACCOUNTABILITY48

M6 – Determination: Is it momentary or sustained?

RELIABILITY | ACCOUNTABILITY49

M6 – Momentary or Sustained

Momentary Outage:An Automatic Outage with an Outage Duration less than one minute.

If the circuit recloses and trips again within less than a minute of the initial outage, it is only considered one outage. The circuit would need to remain in service for longer than one minute between the breaker operations to be considered as two outages.

Sustained Outage:An Automatic Outage with an Outage Duration of a minute or greater.

RELIABILITY | ACCOUNTABILITY50

M6 – Portal or bulk upload form

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY51

M6 – Outage Id Code

A unique alphanumeric identifier assigned by the Transmission Owner to identify the reported outage of an Element. The Outage Id code is assigned by the TOCan be alphanumericMust be unique across years (can’t use the id “Outage 1” in 2016 and then again in 2017)Examples: ACRO-YYYY-00000, INYY-00, YYYY_00000, or 00000 (where the number is usually from the entities outage system)

RELIABILITY | ACCOUNTABILITY52

M6 – Determination: Event Id & Form 5

Reference Module 8 for details about creating and assigning event Ids

NOTE: Form 5 data must be entered into the portal before the system will accept form 4.X data

RELIABILITY | ACCOUNTABILITY53

M6 – TO Element Identifier

The TO Element Identifier is the unique name assigned by the TO to TADS elements and reported via the 3.X formsReference Module 5 for details about inventory reportingElement Inventory data must be entered into the portal before an outage can be reported

NOTE: When using the bulk upload form – The portal will accept an uploaded outage even if the TO Element identifier does not exist in the portal. However this will generate a fatal error that has to be corrected before reporting can be complete.E.g. TO Element identifier is in the inventory as Line_A but entered in the upload form as Line-A.

RELIABILITY | ACCOUNTABILITY54

M6 – Determination: Fault Type

Reference Module 9 for details about creating and assigning fault type

RELIABILITY | ACCOUNTABILITY55

M6 – Determination: Outage Initiation Code

Reference Module 10 for details on how to select and report the outage initiation code.

The Outage Initiation Code describes where the outage was initiated on the power system.

RELIABILITY | ACCOUNTABILITY56

M6 – Outage Start Date and Time

The date and time rounded to the minute that the outage of the element started.Start Date is entered as mm/dd/yyyy

Portal entry allows data reporters to enter the date via a calendar interface

Time is entered as hh:mm in 24 hour clock or “military time” format.For example, 2 pm would be entered as 14:00

To report outages that extend past the end of the quarter, data reporters should extend the length of the outage to the end of the quarter and update each quarter until the end of the outage. Extending an outage across years will be covered below.

RELIABILITY | ACCOUNTABILITY57

M6 – Outage Time Zone

This is the time zone associated with the reported outage’s date and time.Outages should be reported as the time zone of where they occur or converted to GMT/UTC. webTADS stores data in GMT time.Time zones are offered as standard or prevailing time. Standard time is runs from November to March. Daylight Savings time runs March to November Prevailing time is the time on an automatically updated clock, such as a cellphone or a computer and

adjusts to accommodate daylight saving.

Be consistent in how you select and enter your time zones!

RELIABILITY | ACCOUNTABILITY58

M6 – Setting your default time zone in the OATI portal

Administration > User Configuration > User optionsSelect your time zoneSelect reason for changeClick Save

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY59

M6 – Outage Duration

The outage duration expressed as hours and minutes hhhh:mmEnter zero “0” for a momentary outage

Workbook Note: Be careful when pasting duration values in the TADS workbook as excel may translate the data to a date format and cause errors in the upload or accepted data.

RELIABILITY | ACCOUNTABILITY60

M6 – Determination: Initiating Cause Code

Reference Module 10 for details on how to select and report the outage initiating cause code.

The Initiating Cause Code best describes the initiating cause of the outage. E.g. what caused the outage.

RELIABILITY | ACCOUNTABILITY61

M6 – Determination: Sustained Cause Code

Reference Module 10 for details on how to select and report the outage initiating cause code.

The Sustained Cause Code best describes cause that contributed to the longest duration. Note: Momentary outages do not have a Sustained Cause Code (designated as NA- Momentary).

RELIABILITY | ACCOUNTABILITY62

M6 – Determination: Outage Mode

Reference Module 12 for details on how to select and report the outage mode code.

The Outage Mode Code describes whether an Automatic Outage is related to other Automatic Outages.

RELIABILITY | ACCOUNTABILITY63

M6 – Determination: Outage Continuation Code

RELIABILITY | ACCOUNTABILITY64

M6 – Outage Continuation Code

0 = Outage began and ended within the same reporting period1 = Outage began in the reporting period but continued into the next reporting period2 = Outage started in a previous reporting period

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY65

M6 – Reporting outages across years

If an outage begins in a reporting calendar year and continues beyond the end of the year, two separate Outage Durations will be input.

Step 1 - For the reporting year when the outage started:• Create an unique Outage ID• Create an unique Event ID• Input the Outage Start Time and calculate an Outage Duration from the Outage Start

Time until the end of the year (December 31 12:59 p.m. GMT/UTC) • Outage Continuation Flag is “1 = Outage began in the reporting period but continued

into the next reporting period”

RELIABILITY | ACCOUNTABILITY66

M6 – Reporting outages across years

If an outage begins in a reporting calendar year and continues beyond the end of the year, two separate Outage Durations will be input.

Step 2 - For the next reporting year:• Create an unique Outage id• Use the same Event ID from last year• Outage Start Time is January 1, 00:00 GMT/UTC of that reporting year and calculate

duration*• Outage Continuation Flag is “2 = Outage started in a previous reporting period”

*Note: if the outage continues to the subsequent reporting year, the Outage Duration is entered as 8760:00, or 8784:00 for a leap year and step 2 is repeated.

RELIABILITY | ACCOUNTABILITY67

Module 7Operational Outage Reporting

Form 6.X

RELIABILITY | ACCOUNTABILITY68

M7 – Determination: Is it an operational outage?

RELIABILITY | ACCOUNTABILITY69

M7 – Determination: Non-Automatic Outage

Non-Automatic Outage:An outage that results from the manual operation (including supervisory control) of a switching device, causing an Element to change from an In-Service State to a not In-Service State. Includes outages caused by personnel during on-site maintenance, testing, inspection, construction, or commissioning activities.

Operational Outage:Non-Automatic Outage for the purpose of avoiding an emergency (i.e., risk to human life, damage to equipment, damage to property) or to maintain the system within operational limits and that cannot be deferred. Includes Non-Automatic Outages resulting from manual switching errors.

RELIABILITY | ACCOUNTABILITY70

M7 – Determination: Non-reportable Non-Automatic Outages

TADS reporting exclusions (current for the 2017 reporting year):Planned OutagesOperational Outages less than 200 kV

RELIABILITY | ACCOUNTABILITY71

M7 – Automatic vs Non-Automatic Outages

Field Automatic Outages Non-Automatic

TADS Elements All BES 200 kV and above

Momentary and Sustained Momentary (200kV+ only) and Sustained (All BES)

Momentary and Sustained(Outages of any duration)

Outage Id Yes Yes

Event Id Yes No

TO Element Id Yes Yes

Fault Type Yes No

Outage Initiation Code Yes No

Start Time & Date Yes Yes

Duration Yes Yes

Cause Code Initiating and Sustained Operational

Outage Mode Yes No

Outage Continuation Code Yes Yes

RELIABILITY | ACCOUNTABILITY72

M7 – Portal or bulk upload form

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY73

M7 – Outage Id Code

A unique alphanumeric identifier assigned by the Transmission Owner to identify the reported outage of an Element. The Outage Id code is assigned by the TOCan be alphanumericMust be unique across years (can’t use the id “Outage 1” in 2016 and then again in 2017)Examples: ACRO-YYYY-00000, INYY-00, YYYY_00000, or 00000 (where the number is

usually from the entities outage system)

RELIABILITY | ACCOUNTABILITY74

M7 – TO Element Identifier

The TO Element Identifier is the unique name assigned by the TO to TADS elements and reported via the 3.X formsReference Module 5 for details about inventory reportingElement Inventory data must be entered into the portal before an

outage can be reported

E.g. TO Element identifier is in the inventory as Line_A but entered in the upload form as Line-A.

RELIABILITY | ACCOUNTABILITY75

M7 – Non-Automatic Outage Type

Assigns a non-automatic outage type. Select Operational.Hold over from the collection of planned outage.

Workbook Note: If Planned is selected in the bulk upload workbook you will receive an error when importing.

RELIABILITY | ACCOUNTABILITY76

M7 – Outage Start Date and Time

The date and time rounded to the minute that the outage of the element started.Start Date is entered as mm/dd/yyyy

Portal entry allows data reporters to enter the date via a calendar interface

Time is entered as hh:mm in 24 hour clock or “military time” format.For example, 2 pm would be entered as 14:00

To report outages that extend past the end of the quarter, data reporters should extend the length of the outage to the end of the quarter and update each quarter until the end of the outage.

Extending an outage across years will be covered below.

RELIABILITY | ACCOUNTABILITY77

M7 – Outage Time Zone

This is the time zone associated with the reported outage’s date and time.Outages should be reported as the time zone of where they occur or converted to

GMT/UTC. webTADS stores data in GMT time.Time zones are offered as standard or prevailing time. Standard time is runs from November to March. Prevailing time is the time on an automatically updated clock, such as a cellphone or a computer and

adjusts to accommodate daylight saving.

Be consistent in how you select and enter your time zones!

RELIABILITY | ACCOUNTABILITY78

M7 – Setting your default time zone in the OATI portal

Administration > User Configuration > User optionsSelect your time zoneSelect reason for changeClick Save

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY79

M7 – Outage Duration

The outage duration expressed as hours and minutes hhhh:mm

Workbook Note: Be careful when pasting duration values in the TADS workbook as excel may translate the data to a date format and cause errors in the upload or accepted data.

RELIABILITY | ACCOUNTABILITY80

M7 – Determination: Operational Cause Code

RELIABILITY | ACCOUNTABILITY81

M7 – Determination: Outage Continuation Code

RELIABILITY | ACCOUNTABILITY82

M7 – Outage Continuation Code

0 = Outage began and ended within the same reporting period1 = Outage began in the reporting period but continued into the next reporting period2 = Outage started in a previous reporting period

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY83

M7 – Reporting outages across years

If an outage begins in a reporting calendar year and continues beyond the end of the year, two separate Outage Durations will be input.

Step 1 - For the reporting year when the outage started:• Create an unique Outage ID• Create an unique Event ID• Input the Outage Start Time and calculate an Outage Duration from the Outage Start

Time until the end of the year (December 31 12:59 p.m. GMT/UTC) • Outage Continuation Flag is “1 = Outage began in the reporting period but continued

into the next reporting period”

RELIABILITY | ACCOUNTABILITY84

M7 – Reporting outages across years

If an outage begins in a reporting calendar year and continues beyond the end of the year, two separate Outage Durations will be input.

Step 2 - For the next reporting year:• Create an unique Outage id• Use the same Event ID from last year• Outage Start Time is January 1, 00:00 GMT/UTC of that reporting year and calculate

duration*• Outage Continuation Flag is “2 = Outage started in a previous reporting period”

*Note: if the outage continues to the subsequent reporting year, the Outage Duration is entered as 8760:00, or 8784:00 for a leap year and step b is repeated.

RELIABILITY | ACCOUNTABILITY85

A. B. C. D.

0% 0% 0% 0%

M7 – Non-Automatic Outage Question

A. Outage IDB. Event IDC. Element IDD. Duration

Non-automatic outages entered into form 6.X do NOT require which of the following fields?

RELIABILITY | ACCOUNTABILITY86

Module 8Event Codes and Types

Form 5.0

RELIABILITY | ACCOUNTABILITY87

M8 – Event Identification (ID) Code

• Event ID Codes must be created on Form 5 before outages can be entered on Form 4.x.

• An Event associated with a Single Mode Outage will have one Event ID Code.• Each outage in a related set of two or more outages (e.g., Dependent Mode,

Dependent Mode Initiating, Common Mode, Common Mode Initiating) shall be given the same Event ID Code.

• For outages within a single TO, the TO assigns its own Event ID Code.• webTADS tracks each TO’s Event ID codes over multiple years and does not permit

the same Event ID to be used twice by any given TO.• Any pattern of alphanumeric characters may be used on Form 5 to define the Event

ID code. Example: 1-2017 or A-2017• Each year a new Form 4.x Outage ID Code is required, however, for outages due to

an Event which started in the prior year, the prior year Form 5 Event ID code must be used on the current year Form 4.x.

RELIABILITY | ACCOUNTABILITY88

M8 – Event Identification (ID) Code New

• Click on Transmission (TADS)• Select Forms• Select Event ID Codes 5.0

RELIABILITY | ACCOUNTABILITY89

M8 – Event Identification (ID) Code New

• Click on Add Event ID Code

RELIABILITY | ACCOUNTABILITY90

M8 – Event Identification (ID) Code New

• Enter unique Event ID Code

RELIABILITY | ACCOUNTABILITY91

M8 – Event Identification (ID) Code New

• Select correct Event Type Number

RELIABILITY | ACCOUNTABILITY92

• Enter brief Description• Disturbance Report• Click on Enter

M8 – Event Identification (ID) Code New

RELIABILITY | ACCOUNTABILITY93

• Click on OK

M8 – Event Identification (ID) Code New

RELIABILITY | ACCOUNTABILITY94

• A new Event ID Code is created

M8 – Event Identification (ID) Code New

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY95

M8 – Event Identification (ID) Code Edit

• Click on Edit to Modify existing Event Code ID

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY96

• Modify data as needed• Click on Modify

M8 – Event Identification (ID) Code Edit

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY97

• Click on OK

M8 – Event Identification (ID) Code Edit

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY98

• Event ID Code is Modified

M8 – Event Identification (ID) Code Edit

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY99

M8 – Event Identification (ID) Code NMU

TOs (or Regional Entities) coordinate a unique NERC wide (NMU) Event ID code on Form 5 if outages affect two or more Reporting TO’s. • Open Form 5• Click the Filter Options Icon on the right hand side of the screen• In the filtering options menu click the Company

drop down menu and select “NERC Event ID Codes”• Click Apply

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY100

M8 – Event Identification (ID) Code NMU

• Click “Add Event ID Code” to create the next NMU number• Fill out the form and share the NMU with the other effected TOs

NOTE: The Event ID Code, Event Type number and event description will be public to any TO in TADS but the TO information will remains confidential

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY101

M8 - Normal Clearing Event Type Numbers

Which of these isn’t an actual event code?

Event Type Number Descriptions: Events with Normal ClearingChoice Event Type No. Description

A 5 Single bus section fault or failure resulting in one or more Automatic Outages.B 6 Single internal circuit breaker fault resulting in one or more Automatic Outages.

C 11Automatic Outage of a single Element not covered by Event Type Numbers 05 and 06.

D 13 Automatic Outage of two or more Elements within one NCCBS.E 21 Automatic Outage of two or more Elements within two NCCBS.

F 31

Automatic Outages of two or more TADS adjacent AC Circuits or DC Circuits on common structures. To qualify as Event Type Number 31 the Automatic Outages must be the direct result of the circuits occupying common structures.

G 49Automatic Outage(s) with Normal Clearing not covered by Event Type Numbers 05 through 31 above.

RELIABILITY | ACCOUNTABILITY102

M8 - Normal Clearing Event Type Numbers

Which of these isn’t an actual event code?Event Type Number Descriptions: Events with Abnormal Clearing

Choice Event Type No. Description

A 60Breaker Failure: One or more Automatic Outages with Delayed Fault Clearing due to a circuit breaker being stuck, slow to open or failure to interrupt current.

B 61

Dependability (failure to operate): One or more Automatic Outages with Delayed Fault Clearing due to failure of a single Protection System (primary or secondary backup) under either of these conditions: a. failure to initiate the isolation of a faulted power system Element as designed, or within its designed operating time, or b. In the absence of a fault, failure to operate as intended within its designed operating time. (Item b is a very rare type of event.)

C 62

Security (unintended operation): One or more Automatic Outages caused by improper operation (e.g. overtrip) of a Protection System resulting in isolating one or more TADS Elements it is not intended to isolate, either during a fault or in the absence of a fault.

D 63Bus Failure: Improper operation of a Protections System resulting in a Single Bus section interruption.

E 90 Automatic Outage(s) with Abnormal Clearing not covered above.

RELIABILITY | ACCOUNTABILITY103

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. 05 – Bus Section FaultB. 06 – Circuit Breaker FaultC. 11 – Automatic of Single not covered

in 05 or 06D. 13 – Two or more Elements within

one NCCBS.E. 31 – Two or more adjacent AC Circuits

on common structuresF. 60 – Breaker Failure to Operate

What is the Event Type No. for the Event?A fault occurs on Line A-B.

Station A

Station B

Line A-B

Line B-C

M8 – Example 1Event Type

RELIABILITY | ACCOUNTABILITY104

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. 05 – Bus Section FaultB. 06 – Circuit Breaker FaultC. 11 – Automatic of Single not covered

in 05 or 06D. 13 – Two or more Elements within

one NCCBS.E. 31 – Two or more adjacent AC Circuits

on common structuresF. 60 – Breaker Failure to Operate

What is the Event Type No. for the Event?A fault on AC Circuit ‘A-X’.

M8 – Example 2Event Type

Station A

Station B

Terminal X

Line X-BLine A-X

RELIABILITY | ACCOUNTABILITY105

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. 05 – Bus Section FaultB. 06 – Circuit Breaker FaultC. 11 – Automatic of Single not covered

in 05 or 06D. 31 – Two or more adjacent AC Circuits

on common structuresE. 60 – Breaker Failure to OperateF. 61 – Dependability – Failure to

Operate

What is the Event Type No. for the Event?

Tornado destroys a rivers crossing tower shared by 3 lines.

M8 – Example 3Event Type

TL-C1

TL-C2

TL-C3

TL-C4

Station A

TL-A2

Station C

TL-D2

TL-D1

Station D

TL-A1

TL-A3

RELIABILITY | ACCOUNTABILITY106

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. 05 – Bus Section FaultB. 06 – Circuit Breaker FaultC. 11 – Automatic of Single not covered

in 05 or 06D. 31 – Two or more adjacent AC Circuits

on common structuresE. 60 – Breaker Failure to OperateF. 61 – Dependability – Failure to

Operate

What is the Event Type No. for the Event?

Lines TL-A1, TL-A2, and TL-A3 share a common river crossing tower. Lightning strikes TL-A1. The breaker at Station A is stuck closed so the breakers on TL-A2 and TL-A3 open to clear fault.

M8 – Example 4Event Type

TL-C1

TL-C2

TL-C3

TL-C4

Station A

TL-A2

Station C

TL-D2

TL-D1

Station D

TL-A1

TL-A3

RELIABILITY | ACCOUNTABILITY107

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. 05 – Bus Section FaultB. 06 – Circuit Breaker FaultC. 11 – Automatic of Single not covered

in 05 or 06D. 31 – Two or more adjacent AC Circuits

on common structuresE. 61 – Dependability – Failure to

OperateF. 62 – Security – unintended operation

What is the Event Type No. for the Event?

Lines TL-A1, TL-A2, and TL-A3 share a common river crossing tower. Lightning strikes TL-A1. The breaker at Station D operates due to an improper relay setting.

M8 – Example 5Event Type

TL-C1

TL-C2

TL-C3

TL-C4

Station A

TL-A2

Station C

TL-D2

TL-D1

Station D

TL-A1

TL-A3

RELIABILITY | ACCOUNTABILITY108

Module 9Fault TypeForm 4.X

RELIABILITY | ACCOUNTABILITY109

M9 – Fault Type

The descriptor of the fault, if any, associated with each Automatic Outage of an Element. 1. No fault 2. Phase-to-phase fault (P-P) 3. Single phase-to-ground fault (P-G) 4. Phase-to-phase-to-ground (P-P-G), 3P, or 3P-G fault 5. Unknown fault type

NOTE for TADS purposes the Fault Type chosen should be:based on TO best judgment of what occurredrepresent the worst impact on system dynamic stability

RELIABILITY | ACCOUNTABILITY110

M9 – Fault Type

If an Element has an Automatic Outage and its Outage Initiation Code is: Element-Initiated - report Fault Type 1-5 as appropriate. Other Element-Initiated - report Fault Type 1, No fault the Fault Type will be reported for the other Element that initiated the outage

AC Substation-Initiated or AC/DC Terminal Initiated - If fault occurred on BES AC equipment report Fault Type 2-5 as appropriate. If a fault did not occur OR if a fault occurred on non-BES AC equipment report type 1, No fault.

Other Facility-Initiated or Protection System-Initiated - report Fault Type 1, No fault.

RELIABILITY | ACCOUNTABILITY111

M9 – No Fault, Fault Type

No Fault: An outage occurs and no electrical short circuit was present to cause the outage on the element being reported. Over/Under voltage, overload, RAS schemes, Dependent Mode outages, Protection System

component failures would be coded as no fault.

A BES 500kV line tripped because of incorrect relay settings during a 3 phase fault on a 230kV line a bus away. The outage record for the 500kV line would be selected as no fault.

RELIABILITY | ACCOUNTABILITY112

M9 – Single phase to ground fault (P-G)

This fault occurs when a single phase conductor short circuits to the earth (ground) neutral point. Typical targets would include Ground, Neutral, Ground Inst, Z1 G, Carrier Ground, Z2 G, Ground Time,

etc. However if any multi-phase or phase pair targets are indicated this would not be a single phase to ground fault.

Bird contamination on a bottom phase of a vertical constructed circuit causes a flash from the bottom line conductor to tower. Relay targets were Ground Inst and Carrier Ground.

RELIABILITY | ACCOUNTABILITY113

M9 – Phase to Phase fault (P-P)

This fault type occurs when any two phase wires short circuit to each other without contacting the earth ground plain or the third phase in the circuit. Typical targets could be AB, BC, CA, Zone 1 Phase, Zone 2 Phase, A and B Time, B and C Time, C and A

Time. If any ground targets are indicated, it is not a Phase to Phase fault.

A tree branch breaks cleanly from the tree and falls into two phase wires on a horizontal circuit.

RELIABILITY | ACCOUNTABILITY114

M9 – Phase to Phase to Ground, 3P, or 3P-G Fault

This fault type occurs when any two phase wires short circuit to each other and earth neutral or ground at the same time. Or when all three phase wires short to each other by themselves or with ground contact.

A transmission crossarm breaks and drops all three phase wires to the ground. All three phase wires make contact with the earth at the same time causing a 3 phase fault.

RELIABILITY | ACCOUNTABILITY115

M9 – Best methods to determine fault type

Fault recorder/Digital Relay records While not always available, records from remote stations could indicate which phases were involved

and provide the best information for determining fault type.

Relay Targets While usually available, may be cumbersome to evaluate when multiple events have occurred before

the targets are obtained from a station.

Patrol Results When relay targets or fault records are not available, patrol results can tell what the fault type was

damage reports or repairs made.

RELIABILITY | ACCOUNTABILITY116

M9 – Example 1

Lightning causes a single phase to ground fault on a 500kV AC Circuit which causes an outage to the circuit. A BES 500/230kV transformer is connected to the circuit at one of the circuit’s terminals. When an outage occurs on the 500kV line, the transformer must also be outaged.

Element Fault Type

500kV Line Single Phase to Ground Fault

500/230kV Transformer No Fault

RELIABILITY | ACCOUNTABILITY117

M9 – Example 2

A 230kV wooden crossarm breaks and drops all three wires to the ground. One wire makes contact first and the line protection trips the circuit breakers, outaging the line before the other two phase wires make contact with the earth or each other. When the line recloses the breakers, all three phase wires are making contact with the earth.

Element Fault Type

230kV line Phase-to-phase-to-ground (P-P-G), 3P, or 3P-G fault

RELIABILITY | ACCOUNTABILITY118

M9 – Example 3

A Non BES 345/23kV transformer is connected to a BES 345kV line. The protection on the non BES transformer misoperates and sends a trip signal to outage the BES 345kV line.

Element Fault Type

345kV Line No Fault

RELIABILITY | ACCOUNTABILITY119

M9 – Single pole tripping

A 500kV line has an A-G fault and trips out the A phase portion of the circuit, however the remaining phase B and C remained energized. The A phase pole successfully reclosed after 10 seconds.

Element Fault Type

Single pole outages are not reportable.

RELIABILITY | ACCOUNTABILITY120

Module 10Initiation Code

RELIABILITY | ACCOUNTABILITY121

M10 – Initiation Code

This is not the Initiating cause codeThe Outage Initiation Codes describe where an Automatic Outage was initiated on the power system.Element-Initiated Outage

• An Automatic Outage of an Element that is initiated on or within the Element that is outaged.

Other Element-Initiated Outage • An Automatic Outage of an Element that is initiated by another Element and not by the Element that

is outaged.

AC Substation-Initiated Outage • An Automatic Outage of an Element that is initiated on or within AC Substation facilities. (Note: By

the definition of “AC Substation” in Section A, Protection System Equipment is not part of the AC Substation; it is therefore included in “Protection System-Initiated Outage.”)

RELIABILITY | ACCOUNTABILITY122

M10 – Initiation Code

AC/DC Terminal-Initiated Outage • An Automatic Outage of an Element that is initiated on or within AC/DC Terminal facilities. (Note: By

the definition of “AC/DC Terminal” in Section A, Protection System Equipment is not part of the DC Terminal; it is therefore included in “Protection System-Initiated Outage.”)

Protection System-Initiated Outage • An Automatic Outage of an Element that is initiated on or within the Protection System. (Note: This

includes Automatic Outages due to the failure of a Protection System element initiated by protection equipment (including, but not limited to: incorrect protection settings, wiring errors, miscoordination, Protection System related Human Error, etc.) causing the protection system to misoperate.

Other Facility-Initiated Outage • An Automatic Outage that is initiated on or within other facilities. “Other facilities” include any

facilities not includable in any other Outage Initiation Code. (Note: An Automatic Outage initiated on a Transformer that is not an Element is considered an AC Substation or an AC/DC Terminal-Initiated Outage since the Transformer would be considered part of an AC Substation or AC/DC Terminal.)

RELIABILITY | ACCOUNTABILITY123

A fault on an AC Circuit. Big 3 Electric is responsible for reporting outages

on Line A-B. A fault occurred in Standard Power section of line. What is the Outage Initiation Code for Line A-B?

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. Element-InitiatedB. Other Element-InitiatedC. AC Substation-InitiatedD. Protection System InitiatedE. Other Facility InitiatedF. None of the above

Q

M10 – Example 1Ownership Change

Big 3 Electric Company

Line A-BStation A Station B

Standard Power Ownership Change

RELIABILITY | ACCOUNTABILITY124

Bus Fault. A fault occurs on the bus at Station B. What is the Outage Initiation Code for Line A-B?

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. Element-InitiatedB. Other Element-InitiatedC. AC Substation-InitiatedD. Protection System InitiatedE. Other Facility InitiatedF. None of the above

Q

M10 – Example 2

Station A

Station B

Line A-B

RELIABILITY | ACCOUNTABILITY125

A fault on AC Circuit ‘A-X’. What is the Outage Initiation Code for Line X-B?

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. Element-InitiatedB. Other Element-InitiatedC. AC Substation-InitiatedD. Protection System InitiatedE. Other Facility InitiatedF. None of the above

Q

M10 – Example 3

Station A

Station B

Terminal X

Line X-BLine A-X

RELIABILITY | ACCOUNTABILITY126

Bus Fault. A fault occurs on the 69-kV bus at Station B. What is the Outage Initiation Code for 230-kV Line

A-B?

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. Element-InitiatedB. Other Element-InitiatedC. AC Substation-InitiatedD. Protection System InitiatedE. Other Facility InitiatedF. None of the above

Q

M10 – Example 4

Station A

Station B

Line A-B230-kV 69-kV

230/69kV

RELIABILITY | ACCOUNTABILITY127

Non-element Transformer Fault. A fault inside the non-element 230/69-kV

Transformer at Station B. What is the Outage Initiation Code for 230-kV Line

A-B?

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. Element-InitiatedB. Other Element-InitiatedC. AC Substation-InitiatedD. Protection System InitiatedE. Other Facility InitiatedF. None of the above

Q

M10 – Example 5

Station A

Station B

Line A-B230-kV 69-kV

RELIABILITY | ACCOUNTABILITY128

Element Transformer Fault. A fault inside the BES 230/115-kV Transformer at

Station B. The Outage Initiation Code for Line A-B is ‘Other

Element-Initiated’.

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. Element-InitiatedB. Other Element-InitiatedC. AC Substation-InitiatedD. Protection System InitiatedE. Other Facility InitiatedF. None of the above

Q

M10 – Example 6

Station A

Station B

Line A-B230-kV 115-kV

230/115kV

RELIABILITY | ACCOUNTABILITY129

Human Error An employee turns the wrong handle and

accidently opens the breaker at Station B on Line A-B. What is the Outage Initiation Code for Line A-B

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. Element-InitiatedB. Other Element-InitiatedC. AC Substation-InitiatedD. Protection System InitiatedE. Other Facility InitiatedF. None of the above

Q

M10 – Example 7

Station A

Station B

Line A-B

RELIABILITY | ACCOUNTABILITY130

A fault occurs on Line A-B. The breaker on Line B-C erroneously opens due to

relays having the wrong settings. What is the Outage Initiation Code for Line B-C?

A. B. C. D. E. F.

0% 0% 0% 0% 0% 0%

A. Element-InitiatedB. Other Element-InitiatedC. AC Substation-InitiatedD. Protection System InitiatedE. Other Facility InitiatedF. None of the above

Q

M10 – Example 8

Station A

Station B

Line A-B

Line B-C

RELIABILITY | ACCOUNTABILITY131

Module 11aInitiating Cause Code

Form 4.X

RELIABILITY | ACCOUNTABILITY132

M11 – Initiating and Sustained Cause Codes

An Initiating Cause Code that describes the initiating cause of the outage.A Sustained Cause Code that describes the cause that contributed to the longest duration of the outage.

RELIABILITY | ACCOUNTABILITY133

Resources Reminderhttp://www.nerc.com/pa/RAPA/tads/Pages/default.

[email protected]

RELIABILITY | ACCOUNTABILITY134

M11a – Which Cause Code to Pick

When analyzing event… Examine each Element independently Ask “Why did the interrupting device operate?”

• Weather, excluding lightning• Lightning• Environmental• Fire

• Contamination• Foreign interference• Vandalism, terrorism, malicious acts

• Vegetation

• Human error

• Failed AC Substation equipment• Failed Protection System equipment• Failed AC Circuit equipment• Failed DC Circuit equipment• Failed AC/DC Terminal equipment

• Power system condition• Unknown• Other

RELIABILITY | ACCOUNTABILITY135

Station A Station BLine A-B

A lightning strike on an AC Circuit.What is the Initiating Cause Code?

A. B. C. D.

0% 0% 0% 0%

A. LightningB. Failed AC Circuit equipmentC. Weather, excl. lightningD. Foreign interference

Q

M11a – Example 1

RELIABILITY | ACCOUNTABILITY136

A lightning strike on an AC Circuit.What is the Initiating Cause Code?

A. B. C. D.

0% 0% 0% 0%

A. LightningB. Failed Protection System equipmentC. Foreign interferenceD. Other

Q

M11a – Example 2Ownership Change

Big 3 Electric Company

Line A-BStation A Station B

Standard Power Ownership Change

RELIABILITY | ACCOUNTABILITY137

Station A Station BLine A-B

LOADStandard Electric

Ownership Change

A lightning strike on a circuit tap.What is the Initiating Cause Code?

A. B. C. D.

0% 0% 0% 0%

A. LightningB. Power System ConditionC. Foreign interferenceD. Environmental

Q

M11a – Example 3Customer Tap Fault

RELIABILITY | ACCOUNTABILITY138

A lightning strike on an AC CircuitAsk yourself, why did the breaker at Terminal ‘X’ open? It opened because …

What is the Initiating Cause Code for Line A-X?

A. B. C. D.

0% 0% 0% 0%

A. FireB. LightningC. Failed AC Circuit EquipmentD. Not TADS Reportable

Q

M11a – Example 4a

Station BStation A

Terminal X

RELIABILITY | ACCOUNTABILITY139

A lightning strike on an AC CircuitAsk yourself, why did the breaker at Terminal ‘X’ open? It opened because …

What is the Initiating Cause Code for Line X-B?

A. B. C. D.

0% 0% 0% 0%

A. Not TADS ReportableB. Failed Protection System EquipmentC. LightningD. Other

Q

M11a – Example 4b

Station BStation A

Terminal X

RELIABILITY | ACCOUNTABILITY140

A sleeve failure occurs on an Line #1 and the conductor breaks and falls into underbuilt Line #2.

What is the Initiating Cause Code for Line #1?

A. B. C. D.

0% 0% 0% 0%

A. Failed AC Circuit EquipmentB. Not TADS ReportableC. LightningD. Other

Q

M11a – Example 5aUnderbuilt

Station A Station BLine #1

Line #2

(Underbuilt)

RELIABILITY | ACCOUNTABILITY141

A sleeve failure occurs on an Line #1 and the conductor breaks and falls into underbuilt Line #2.

What is the Initiating Cause Code for Line #2?

A. B. C. D.

0% 0% 0% 0%

A. Foreign interferenceB. LightningC. AC Circuit EquipmentD. Not TADS reportable

Q

M11a – Example 5bUnderbuilt

Station A Station BLine #1

Line #2

(Underbuilt)

RELIABILITY | ACCOUNTABILITY142

Line #1 (161-kV) was interrupted for 4 minutes during a storm with very high winds due to a Distributor’s underbuilt conductor blowing into a guy wire. The guy wire was burned in two upon contact with the 13kv underbuilt. The wind blew the upper section of the lose guy wire into the 161KV TL causing the line to operate to lock out causing a four minute TL outage.

What is the Initiating Cause Code for Line #1?

A. B. C. D.

0% 0% 0% 0%

A. Failed AC Circuit EquipmentB. OtherC. Weather, excl. lightningD. Foreign interference

Q

M11a – Example 6aUnderbuilt

Station A Station BLine #1

Line #2(Underbuilt)

RELIABILITY | ACCOUNTABILITY143

Line #1 (161-kV) was interrupted for 4 minutes during a storm with very high winds due to a Distributor’s underbuilt conductor blowing into a guy wire. The guy wire was burned in two upon contact with the 13kv underbuilt. The wind blew the upper section of the lose guy wire into the 161KV TL causing the line to operate to lock out causing a four minute TL outage.

What is the Initiating Cause Code for Line #2?

A. B. C. D.

0% 0% 0% 0%

A. Foreign interferenceB. LightningC. Not TADS reportableD. Other

Q

M11a – Example 6bUnderbuilt

Station A Station BLine #1

Line #2(Underbuilt)

RELIABILITY | ACCOUNTABILITY144

Lightning struck Line A-C and because of configuration, other lines became de-energized even though their breakers didn’t operate:

What is the Initiating Cause Code for Line A-C?

A. B. C. D.

0% 0% 0% 0%

A. Failed AC Circuit EquipmentB. LightningC. UnknownD. Power System Condition

Q

M11a – Example 7aLines de-energized by fault on another line

TL-1

TL-2

TL-3

TL-4

Station ALine A-C

Station C

Fault caused lines to become De-energized due to abnormal system configuration

Power System Condition Automatic Outages caused by power system conditions such as instability, overload trip, out-of-step, abnormal voltage, abnormal frequency, or unique system configurations (e.g., an abnormal terminal configuration due to existing condition with one breaker already out of service).

RELIABILITY | ACCOUNTABILITY145

Lightning struck Line A-C and because of configuration, other lines became de-energized even though their breakers didn’t operate:

What is the Initiating Cause Code for Line TL-1, TL-2, TL-3, and TL-4?

A. B. C. D.

0% 0% 0% 0%

A. Power System ConditionB. OtherC. Failed Protection System EquipmentD. Lightning

Q

M11a – Example 7bLines de-energized by fault on another line

TL-1

TL-2

TL-3

TL-4

Station ALine A-C

Station C

Fault caused lines to become De-energized due to abnormal system configuration

Power System Condition Automatic Outages caused by power system conditions such as instability, overload trip, out-of-step, abnormal voltage, abnormal frequency, or unique system configurations (e.g., an abnormal terminal configuration due to existing condition with one breaker already out of service).

RELIABILITY | ACCOUNTABILITY146

Lightning struck Line A-C and a breaker failed to open due to breaker issue.

What is the Initiating Cause Code for Line A-C?

A. B. C. D.

0% 0% 0% 0%

A. LightningB. Failed Protection System EquipmentC. Failed AC Circuit EquipmentD. Failed Substation Equipment

Q

M11a – Example 8aBreaker fails to clear fault

TL-1

TL-2

TL-3

TL-4

Station ALine A-C

Station C

Failed to open for fault due to breaker issue

RELIABILITY | ACCOUNTABILITY147

Lightning struck Line A-C and a breaker failed to open due to breaker issue.

What is the Initiating Cause Code for TL-1, TL-2, TL-3 …?

A. B. C. D.

0% 0% 0% 0%

A. OtherB. LightningC. Weather, excl. lightningD. Failed Substation Equipment

Q

M11a – Example 8bBreaker fails to clear fault

TL-1

TL-2

TL-3

TL-4

Station ALine A-C

Station C

Failed to open for fault due to breaker issue

RELIABILITY | ACCOUNTABILITY148

A Potential Transformer catastrophically fails causing bus fault.

What is the Initiating Cause Code for all lines?

A. B. C. D.

0% 0% 0% 0%

A. Failed AC Circuit EquipmentB. Failed Protection System EquipmentC. Failed AC Substation EquipmentD. Power System Condition

Q

M11a – Example 9Potential Transformer

TL-1

TL-2

TL-3

TL-4

Station ALine A-C

Station C

RELIABILITY | ACCOUNTABILITY149

Failed line capacitor voltage transformer (CCVT or CVT) secondary fails causing voltage loss to relay

What is the Initiating Cause Code for all lines?

A. B. C. D.

0% 0% 0% 0%

A. Failed AC Circuit EquipmentB. Failed Protection System EquipmentC. Failed AC Substation EquipmentD. Power System Condition

Q

M11a – Example 10Potential Transformer

TL-1

TL-2

TL-3

TL-4

Station DLine D-E

Station E

RELIABILITY | ACCOUNTABILITY150

Lightning strikes 69-kV busWhat is the Initiating Cause Code for all lines?

A. B. C. D.

0% 0% 0% 0%

A. LightningB. OtherC. Failed AC Substation EquipmentD. Foreign interference

Q

M11a – Example 11Non-BES Faults

TL-1

TL-2

TL-3

TL-4

Station ALine A-C

Station C

69-kV230-kV

RELIABILITY | ACCOUNTABILITY151

Breaker fails to clear fault on 69-kV systemAgain, ask yourself why did the breaker for the Element open?

What is the Initiating Cause Code for Line D-E?

A. B. C. D.

0% 0% 0% 0%

A. OtherB. Failed AC Circuit EquipmentC. Failed AC Substation EquipmentD. Failed Protection System Equipment

Q

M11a – Example 12Non-BES Faults

TL-1

TL-2

TL-3

TL-4

Station DLine D-E

Station E

69-kV230-kV

RELIABILITY | ACCOUNTABILITY152

M11a – Vegetation(Exceptions)

Vegetation Exceptions (as contained in FAC-003-1)

Outages that fall under the exclusions should be reported under another Cause Code and not the Vegetation Cause Code.

Outside the right of way that result from natural disasters. Examples include:

Human or Animal activity. Examples include:

• Earthquakes• Fires• Tornados• Hurricanes• Landslides• Wind shear• Major storms as defined either by the TO or an

applicable regulatory body• Ice storms• Floods

• Logging• Animal severing tree• Vehicle contact with tree• Arboricultural activities• Horticultural activities• Agricultural activities• Removal or digging of vegetation

RELIABILITY | ACCOUNTABILITY153

M11a – Human Error: Automatic OutageInterruptions with ‘Faults’ Examples

Human Error: Automatic Outages caused by any incorrect action traceable to employees and/or contractors for companies operating, maintaining, and/or providing assistance to the Transmission Owner will be identified and reported in this category.

Station A Station BLine A-B

Human Error Automatic Outage Examples Not Human Error Examples• Electrician hangs ground on wrong (energized) line.• Contractor cuts tree into energized line.• Company or contractor bucket-truck contacts line.

• Employee flying a kite on his day off and it contacts 230-kV line is NOT Human Error (Foreign Interference).

• Customer or distribution company bucket truck contacts line (Foreign Interference).

RELIABILITY | ACCOUNTABILITY154

M11a – Human Error: Automatic OutageProtection System; No ‘Fault’ Examples

Line A-B has lightning strike and the Line B-C relay ‘overtrips’ for fault on another line due to:

• Wrong settings, Wiring error, or Switch in wrong position

Line A-B would have an initiating cause of Lightning and Line B-C would have an initiating cause of Human Error

Station A

Station B

Line A-B

Line B-C

Station C

RELIABILITY | ACCOUNTABILITY155

M11a – Human Error: Operational Outage

These are reported on Form 6.1 (or 6.3):• During planned switching, electrician operates wrong handle.

• Work plan was wrong• Electrician didn’t correctly follow work plan

• Someone bumps a relay in the switch house• During relay testing, accidently trips line• Dispatcher remotely opens wrong breaker• Electrician shorts out wiring behind panel while working

RELIABILITY | ACCOUNTABILITY156

Module 11bSustained Cause Codes

Form 4.X

RELIABILITY | ACCOUNTABILITY157

M11b – Sustained Cause Code

A Sustained Cause Code that describes the cause that contributed to the longest duration of the outage. For Sustained Cause, ask yourself what caused the ‘longest duration’ of the outage to the Element.

RELIABILITY | ACCOUNTABILITY158

M11b – Sustained Cause Code

Most of time if the Initiating Cause is one of these, then the Sustained Cause will be different, probably failed equipment (emphasis on ‘most’)…• Weather, excluding lightning• Lightning• Environmental• Fire• Vandalism, terrorism, malicious actsRemember, ask yourself what caused the ‘longest duration’ of the outage to the Element or “what did you have to fix?”

RELIABILITY | ACCOUNTABILITY159

M11b – Sustained Cause Code

Most of time if the Initiating Cause is one of these, then the Sustained Cause will be the same (emphasis on ‘most’)…• Failed AC Substation equipment• Failed Protection System equipment• Failed AC Circuit equipment• Failed DC Circuit equipment• Failed AC/DC Terminal equipment• Power system condition• Unknown• OtherRemember, ask yourself what caused the ‘longest duration’ of the outage to the Element or “what did you have to fix?”

RELIABILITY | ACCOUNTABILITY160

M11b – Sustained Cause Code

If the Initiating Cause is one of these, then the Sustained Cause could be anything …• Contamination• Foreign interference• Vegetation• Human errorRemember, ask yourself what caused the ‘longest duration’ of the outage to the Element.

RELIABILITY | ACCOUNTABILITY161

A lightning strike on an AC Circuit. Automatic reclosing fails to operate resulting in a 5 minute outage. The Initiating Cause Code is Lightning.

What is the Sustained Cause Code?

A. B. C. D.

0% 0% 0% 0%

A. LightningB. Failed AC Circuit EquipmentC. Failed Protection System EquipmentD. Failed AC Substation Equipment

Q

M11b – Example 1Reclosing Example

Station A Station BLine A-B

RELIABILITY | ACCOUNTABILITY162

A lightning strike on an AC Circuit. Automatic reclosing is intentionally disabled (or is not present) resulting in a 27 minute outage. The Initiating Cause Code is Lightning.

What is the Sustained Cause Code?

A. B. C. D.

0% 0% 0% 0%

A. LightningB. Failed AC Circuit EquipmentC. OtherD. Failed AC Substation Equipment

Q

M11b – Example 2Reclosing Example

Station A Station BLine A-B

RELIABILITY | ACCOUNTABILITY163

A tornado destroys a transmission tower on an AC Circuit resulting in a 5 day outage. The Initiating Cause Code is Weather.

What is the Sustained Cause Code?

A. B. C. D.

0% 0% 0% 0%

A. LightningB. Weather, excl. lightningC. OtherD. Failed AC Circuit Equipment

Q

M11b – Example 3“Weather-Weather”? Example

Station A Station BLine A-B

RELIABILITY | ACCOUNTABILITY164

M11b – Sustained Cause Code Other Failed AC Circuit equipment Examples

Other examples where the sustained cause code would be Failed AC Circuit equipment:• Fire destroys transmission pole• Hurricane destroys transmission tower• Car hits transmission pole• Employee accidently saws down transmission pole rather than tree• Alien spacecraft crashes into transmission line

RELIABILITY | ACCOUNTABILITY165

A tree on the right-of-way, falls on a sunny, calm day into the transmission line. The tree is leaning into the conductor, but no equipment damage. It takes 3 hours to remove the tree. The Initiating Cause Code is Vegetation.

What is the Sustained Cause Code?

A. B. C. D.

0% 0% 0% 0%

A. UnknownB. VegetationC. Failed AC Circuit EquipmentD. Foreign interference

Q

M11b – Example 4Vegetation Example

Station A Station BLine A-B

RELIABILITY | ACCOUNTABILITY166

A tree on the right-of-way, falls on a sunny, calm day into the transmission line. The tree breaks the conductor. It takes 3 hours to repair the conductor. The Initiating Cause Code is Vegetation.

What is the Sustained Cause Code?

A. B. C. D.

0% 0% 0% 0%

A. UnknownB. VegetationC. Failed AC Circuit EquipmentD. Foreign interference

Q

M11b – Example 5Vegetation Example

Station A Station BLine A-B

RELIABILITY | ACCOUNTABILITY167

A tree is cut into the energized line, breaking the conductor. It takes 3 hours to repair the conductor. The Initiating Cause Code is Human Error (4.1).

What is the Sustained Cause Code?

A. B. C. D.

0% 0% 0% 0%

A. UnknownB. VegetationC. Failed AC Circuit EquipmentD. Foreign interference

Q

M11b – Example 6Vegetation Example

Station A Station BLine A-B

RELIABILITY | ACCOUNTABILITY168

A tree is cut into the energized line by your utility employee, conductor doesn’t break, leans into line. It takes 3 hours to remove the tree. The Initiating Cause Code is Human Error (4.1).

What is the Sustained Cause Code?

A. B. C. D.

0% 0% 0% 0%

A. Human ErrorB. VegetationC. Failed AC Circuit EquipmentD. Foreign interference

Q

M11b – Example 7Vegetation Example

Station A Station BLine A-B

RELIABILITY | ACCOUNTABILITY169

Module 12Outage Mode

Form 4.X

RELIABILITY | ACCOUNTABILITY170

M12 – Outage Mode

The Outage Mode Code describes whether an Automatic Outage is related to other Automatic Outages.

Single Mode OutageDependent Mode Initiating OutageDependent Mode OutageCommon Mode OutageCommon Mode Initiating Outage

RELIABILITY | ACCOUNTABILITY171

M12 – Outage Mode CodeSingle Mode Outage

An Automatic Outage of a single Element that occurred independent of any other Automatic Outages (if any).

RELIABILITY | ACCOUNTABILITY172

M12 – Outage Mode CodeCommon Mode

One of two or more Automatic Outages with the same Initiating Cause Code and where the outages are not consequences of each other and occur nearly simultaneously (i.e., within cycles or seconds of one another).

• Bus Fault

TL-1

TL-2

TL-3

TL-4

Station ALine A-C

Station C

RELIABILITY | ACCOUNTABILITY173

M12 – Outage Mode CodeCommon Mode

One of two or more Automatic Outages with the same Initiating Cause Code and where the outages are not consequences of each other and occur nearly simultaneously (i.e., within cycles or seconds of one another).

• Single ‘Cause’ (Lighting, Tornado, etc.), near simultaneous:• Do they share tower (River Crossing?) – Common Mode• Are they in close proximity, share ROW – Common Mode

TL-C1

TL-C2

TL-C3

TL-C4

Station A

TL-A2

Station C

TL-D2

TL-D1

Station D

TL-A1

TL-A3

RELIABILITY | ACCOUNTABILITY174

M12 – Outage Mode CodeDependent Mode

Two or more outagesOne outage can be non-Element; hence not all Dependent Mode outages will have an associated

Dependent Mode Initiating OutageDependent Mode Outage must be a result of another outage. Initiating Outage: Single Element: Dependent Mode Initiating Outage Multiple Elements with same Cause at the same time and not consequences of each other: Common

Mode Initiating Outage

Resulting Outage: Single Element: Dependent Mode Outage Multiple Elements with same Cause at the same time and not consequences of each other: Common

Mode Outage Multiple Elements with same Cause at the same time and are consequences of each other: Dependent

Mode Outage

RELIABILITY | ACCOUNTABILITY175

M12 – Outage Mode CodeDependent Mode -‘classic’ relay misoperation

Line A-B experiences a fault and Line B-C erroneously trips (relay overtrips) at Station C.• Line A-B – Dependent Mode Initiating Outage• Line B-C – Dependent Mode Outage

Station A

Station B

Line A-B

Line B-C

Station C

RELIABILITY | ACCOUNTABILITY176

M12 – Outage Mode CodeDependent Mode - sharing common breaker

Lightning strikes Line A-X:• Line A-X: Dependent Mode Initiating • Line X-B: Dependent Mode

Station BStation A

Terminal X

RELIABILITY | ACCOUNTABILITY177

Lightning strikes Line A-B and Line C-D a few seconds apart. They don’t share ROW or any equipment. All lines are BES elements.

What is the Outage Mode Code for Line A-B?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 1aTwo Interruptions During a Storm

Station C

Station A Station B

Line A-B

Line B-C

Station D

Line C-D

+ 5 seconds

RELIABILITY | ACCOUNTABILITY178

Lightning strikes Line A-B and Line C-D a few seconds apart. They don’t share ROW or any equipment. All lines are BES elements.

What is the Outage Mode Code for Line C-D?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 1bTwo Interruptions During a Storm

Station C

Station A Station B

Line A-B

Line B-C

Station D

Line C-D

+ 5 seconds

RELIABILITY | ACCOUNTABILITY179

Station A Station B

Line A-B

Line B-C

Station D

Line C-D

Station C

Fault on Line B-C. Two separate relay issues (Protection System) at Station A and Station D. All lines are BES elements.

What is the Outage Mode Code for Line B-C?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 2aTwo Interruptions During a Storm

RELIABILITY | ACCOUNTABILITY180

Station A Station B

Line A-B

Line B-C

Station D

Line C-D

Station C

Fault on Line B-C. Two separate relay issues (Protection System) at Station A and Station D. All lines are BES elements.

What is the Outage Mode Code for Line A-B?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 2bTwo Interruptions During a Storm

RELIABILITY | ACCOUNTABILITY181

Station A Station B

Line A-B

Line B-C

Station D

Line C-D

Station C

Fault on Line B-C. Two separate relay issues (Protection System) at Station A and Station D. All lines are BES elements.

What is the Outage Mode Code for Line C-D?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 2cTwo Interruptions During a Storm

RELIABILITY | ACCOUNTABILITY182

Line D-E has fault and breaker at E fails to open. The bus at Station E Clears fault. All lines are BES elements.

What is the Outage Mode Code for Line D-E?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 3a

Breaker fails to open for fault

TL-1

TL-2

TL-3

TL-4

Station DLine D-E

Station E

RELIABILITY | ACCOUNTABILITY183

Line D-E has fault and breaker at E fails to open. The bus at Station E Clears fault. All lines are BES elements.

What is the Outage Mode Code for TL-1, TL-2, TL-3, TL-4?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 3b

Breaker fails to open for fault

TL-1

TL-2

TL-3

TL-4

Station DLine D-E

Station E

RELIABILITY | ACCOUNTABILITY184

Bus at Station E has fault. A relay on Line D-E misoperates. All lines are BES elements.

What is the Outage Mode Code for Line D-E?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 4aBus Fault

Breaker fails to open for fault

TL-1

TL-2

TL-3

TL-4

Station DLine D-E

Station E

RELIABILITY | ACCOUNTABILITY185

Bus at Station E has fault. A relay on Line D-E misoperates. All lines are BES elements.

What is the Outage Mode Code for lines TL-1, TL-2…?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 4bBus Fault

Breaker fails to open for fault

TL-1

TL-2

TL-3

TL-4

Station DLine D-E

Station E

RELIABILITY | ACCOUNTABILITY186

Lightning strikes river crossing tower on lines TL-A1, TL-A2 and TL-A3. Breaker on TL-A3 fails to open resulting in TL-D1 and TL-D2 opening. All lines are BES elements.

What is the Outage Mode Code for Line TL-A3?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 5aCommon Mode

TL-C1

TL-C2

TL-C3

TL-C4

Station A

TL-A2

Station C

TL-D2

TL-D1

Station D

TL-A1

TL-A3

Breaker fails to open for fault

Lightning strike on river crossing tower

RELIABILITY | ACCOUNTABILITY187

Lightning strikes river crossing tower on lines TL-A1, TL-A2 and TL-A3. Breaker on TL-A3 fails to open resulting in TL-D1 and TL-D2 opening. All lines are BES elements.

What is the Outage Mode Code for Line TL-A1 and TL-A2?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 5bCommon Mode

TL-C1

TL-C2

TL-C3

TL-C4

Station A

TL-A2

Station C

TL-D2

TL-D1

Station D

TL-A1

TL-A3

Breaker fails to open for fault

Lightning strike on river crossing tower

RELIABILITY | ACCOUNTABILITY188

Lightning strikes river crossing tower on lines TL-A1, TL-A2 and TL-A3. Breaker on TL-A3 fails to open resulting in TL-D1 and TL-D2 opening. All lines are BES elements.

What is the Outage Mode Code for Line TL-D1 and TL-D2?

A. B. C. D. E.

0% 0% 0% 0% 0%

A. Single Mode OutageB. Dependent Mode Initiating OutageC. Dependent Mode OutageD. Common Mode OutageE. Common Mode Initiating Outage

Q

M12 – Example 5cCommon Mode

TL-C1

TL-C2

TL-C3

TL-C4

Station A

TL-A2

Station C

TL-D2

TL-D1

Station D

TL-A1

TL-A3

Breaker fails to open for fault

Lightning strike on river crossing tower

RELIABILITY | ACCOUNTABILITY189

Test your knowledge

RELIABILITY | ACCOUNTABILITY190

Test Your Knowledge – Example 1

Galloping conductors on a double circuit structure carrying a 138kV line (Line X-Y) and a 230kV line (Line A-B) resulted in momentary outages to both lines.

Fields Form 4.1 Line A-B Form 4.1 Line X-Y Form 5.0

Fault Type

Event Type Number

Outage Initiation Code

Initiating Cause Code

Sustained Cause Code

Outage Mode Code

RELIABILITY | ACCOUNTABILITY191

Test Your Knowledge – Example 1 Answers

Galloping conductors on a double circuit structure carrying a 138kV line (Line X-Y) and a 230kV line (Line A-B) resulted in momentary outages to both lines.

Fields Form 4.1 Line A-B Form 4.1 Line X-Y Form 5.0

Fault Type P-P Fault Not reportable

Event Type Number

11

Outage Initiation Code Element-Initiated Not reportable

Initiating Cause Code Weather Not reportable

Sustained Cause Code NA – Momentary Not reportable

Outage Mode Code Single Mode Not reportable

RELIABILITY | ACCOUNTABILITY192

Test Your Knowledge – Example 2

Motor operated disconnect control circuit misoperates and opens the disconnect. For this example, motor operated disconnect is located on the circuit. Breakers do not operate and there is not a BES fault.

Fields Form 4.1 Line A-B Form 5.0

Fault Type

Event Type Number

Outage Initiation Code

Initiating Cause Code

Sustained Cause Code

Outage Mode Code

RELIABILITY | ACCOUNTABILITY193

Test Your Knowledge – Example 2 Answers

Motor operated disconnect control circuit misoperates and opens the disconnect. For this example, motor operated disconnect is located on the circuit. Breakers do not operate and there is not a BES fault.

Fields Form 4.1 Line A-B Form 5.0

Fault Type No Fault

Event Type Number

90

Outage Initiation Code Element-Initiated

Initiating Cause Code Failed AC Circuit Eq.

Sustained Cause Code Failed AC Circuit Eq.

Outage Mode Code Single Mode

RELIABILITY | ACCOUNTABILITY194

Test Your Knowledge – Example 3

A 138 kV two-terminal transmission line experiences an outage due to bird contamination which resulted in a single phase to ground fault. The faulted line trips and successfully returns to an in-service state in less than one minute. On an adjacent 138 kV three-terminal line one remote breaker opens due to failed communication system and failed to return to an in-service state due to a failed reclosing scheme.

C-O-C C-O-C

C-O

C CLine 6 Line 7

RELIABILITY | ACCOUNTABILITY195

Test Your Knowledge – Example 3 continued

A 138 kV two-terminal transmission line experiences an outage due to bird contamination which resulted in a single phase to ground fault. The faulted line trips and successfully returns to an in-service state in less than one minute. On an adjacent 138 kV three-terminal line one remote breaker opens due to failed communication system and failed to return to an in-service state due to a failed reclosing scheme.

Fields Form 4.1 Line 6 Form 4.1 Line 7 Form 5.0

Fault Type

Event Type Number

Outage Initiation Code

Initiating Cause Code

Sustained Cause Code

Outage Mode Code

RELIABILITY | ACCOUNTABILITY196

Test Your Knowledge – Example 3 Answers

A 138 kV two-terminal transmission line experiences an outage due to bird contamination which resulted in a single phase to ground fault. The faulted line trips and successfully returns to an in-service state in less than one minute. On an adjacent 138 kV three-terminal line one remote breaker opens due to failed communication system and failed to return to an in-service state due to a failed reclosing scheme.

Fields Form 4.1 Line 6 Form 4.1 Line 7 Form 5.0

Fault Type No fault Not reportable

Event Type Number

62

Outage Initiation Code Protection System Not reportable

Initiating Cause Code Failed Protection System Not reportable

Sustained Cause Code AC substation equipment Not reportable

Outage Mode Code Single Mode Not reportable

RELIABILITY | ACCOUNTABILITY197

Test Your Knowledge – Example 4

A 138 kV three-terminal line experiences a single phase to ground fault due to lightning. The fault was cleared correctly but one terminal did not close due to a faulty recloser.

C-O

C-O-C C-O-CLine 6

RELIABILITY | ACCOUNTABILITY198

Test Your Knowledge – Example 4

A 138 kV three-terminal line experiences a single phase to ground fault due to lightning. The fault was cleared correctly but one terminal did not close due to a faulty recloser.

Fields Form 4.1 Line 6 Form 5.0

Fault Type

Event Type Number

Outage Initiation Code

Initiating Cause Code

Sustained Cause Code

Outage Mode Code

RELIABILITY | ACCOUNTABILITY199

Test Your Knowledge – Example 4 Answers

A 138 kV three-terminal line experiences a single phase to ground fault due to lightning. The fault was cleared correctly but one terminal did not close due to a faulty recloser.

Fields Form 4.1 Line 6 Form 5.0

Fault Type P-G

Event Type Number

11

Outage Initiation Code Element initiated

Initiating Cause Code Lightning

Sustained Cause Code Failed AC substation equipment

Outage Mode Code Single mode

RELIABILITY | ACCOUNTABILITY200

Test Your Knowledge – Example 4Modified with Transformer

A 138 kV three-terminal line experiences a single phase to ground fault due to lightning. The fault was cleared correctly but one terminal did not close due to a faulty recloser.

C-O

C-O-C C-O-CLine 6

RELIABILITY | ACCOUNTABILITY201

Test Your Knowledge – Example 5

Breaker Fault. A fault occurs on the 69-kV line B-C.

How should this be coded?

Station A

Station B

Line A-B230-kV 69-kV

Line B-C

RELIABILITY | ACCOUNTABILITY202

Test Your Knowledge – Example 6

A technician applies settings to a relay and the settings result in an immediate trip. The relay issued the trip at the exact moment when the relay accepted the settings after the technician loaded and implemented the settings.

How should this be coded?

RELIABILITY | ACCOUNTABILITY203

Test Your Knowledge – Example 7

Two circuits exist in parallel both originating from Substation A and running through switching station B, which contains no terminal circuit breakers, before traveling on to two separate remote substations. Whenever a communication link outage of the circuits’ protection system occurs one of the parallel lines has to be opened.

How should this be coded?

RELIABILITY | ACCOUNTABILITY204

Test Your Knowledge – Example 8

Single P-G fault on the Bus due to contamination, no damage resulted.At what point are the individual outages over?Which line(s) should this outage be reported for?How would this be coded?

RELIABILITY | ACCOUNTABILITY205

Test Your Knowledge – Example 8 Answers

Single P-G fault on the Bus due to contamination.The individual outages are over when corresponding line breakers are placed in-service.Individual outages should be reported on all three lines under the same event.

Fields Form 4.1 L1, L2, L3 Form 5.0

Fault Type Single P-G

Event Type Number

05

Outage Initiation Code AC Substation initiated

Initiating Cause Code Contamination

Sustained Cause Code Contamination

Outage Mode Code Common Mode

RELIABILITY | ACCOUNTABILITY206

Test Your Knowledge – Example 9

Lines L4 and L5 are located on a common structure. A single lightning strike hits both circuits causing them to each experience a single phase to ground fault. Both breakers automatically reclose successfully and simultaneously.How would this be coded?

RELIABILITY | ACCOUNTABILITY207

Test Your Knowledge – Example 9 Answers

Fields Form 4.1 L4, L5 Form 5.0

Fault Type Single P-G

Event Type Number

31

Outage Initiation Code Element-Initiated

Initiating Cause Code Lightning

Sustained Cause Code NA – Momentary

Outage Mode Code Common Mode

Lines L4 and L5 are located on a common structure. A single lightning strike hits both circuits causing them to each experience a single phase to ground fault. Both breakers automatically reclose successfully and simultaneously.

RELIABILITY | ACCOUNTABILITY208

Test Your Knowledge – Example 10

A relay Misoperates causing a 230/345 kV transformer outage.How would you code this?

RELIABILITY | ACCOUNTABILITY209

Test Your Knowledge – Example 10 Answers

Fields Form 4.3 TF1 Form 5.0

Fault Type No-Fault

Event Type Number

11

Outage Initiation Code Protection System-Initiated

Initiating Cause Code Failed Protection System Equipment

Sustained Cause Code Failed Protection System Equipment

Outage Mode Code Single Mode

A relay Misoperates causing a 230/345 kV transformer outage.

RELIABILITY | ACCOUNTABILITY210

Test Your Knowledge – Example 11

A conductor breaks causing a phase to phase fault. The breaker on one end of the line fails to operate due to a relay Misoperation causing breakers on lines L2 and L3 to open.How would you code this?

RELIABILITY | ACCOUNTABILITY211

Test Your Knowledge – Example 11 Answers

Fields Form 4.1 L1 Form 4.1 L2, L3 Form 5.0

Fault Type P-P Fault No fault

Event Type Number

60

Outage Initiation Code

Element-Initiated Protection System-Initiated

Initiating Cause Code

Failed AC CircuitEquipment

Failed Protection System Equipment

Sustained Cause Code

Failed AC CircuitEquipment

Failed ProtectionSystem Equipment

Outage Mode Code

Dependent Mode Initiating

Dependent Mode

A relay Misoperates causing a 230/345 kV transformer outage.

RELIABILITY | ACCOUNTABILITY212

Module 13Validating Your Data

RELIABILITY | ACCOUNTABILITY213

M13 – Validation ErrorsForm 3.1 AC & DC Circuit Detailed Inventory Data

• Invalid Retirement Date. 'Retirement Date' must be within the reporting period range.• Change/Reconfiguration Date is missing• Mismatched Precursor Elements. Precursor Elements does not belong to provided

Voltage Class (KV) or Circuit Type. • Duplicate Element Identifier in the file• Circuit Type is missing• Invalid KV • In Service date cannot be set after the Outage(s) creation date on this inventory.

Either adjust the Inventory In Service date or Outage start date• Circuit Mileage is missing• Invalid To Bus

RELIABILITY | ACCOUNTABILITY214

M13 – Validation ErrorsForm 3.3 AC/DC BtB Converter Detailed Inventory Data

• High Side kV is missing• Low Side kV is missing • Duplicate Element Identifier in the file • Invalid Retirement Date. 'Retirement Date' must be within the reporting period range.• Invalid Change/Reconfiguration Date. 'Change/Reconfiguration Date' must not be in

the future or must be prior to the 'Retirement Date'. • Invalid High or Low Side Voltage• Invalid Three Phase Rating

RELIABILITY | ACCOUNTABILITY215

M13 – Validation ErrorsForm 4.1 AC Circuit Detailed Automatic Outage Data

• Warning - For Outage ID [] associated with Event ID [], 'Failed Protection System Equipment' was entered as the 'Initiating Cause Code.' Therefore the cause of this outage is likely to be abnormal clearing (per NERC definition of Normal Clearing). However, the associated Event Type number entered on Form 5 is less than 50, which are 'Normal Clearing' event types. Warning: Please consider entering an abnormal clearing Event Type Number on Form 5, or do not enter 'Failed Protection System Equipment' as the 'Initiating Cause Code' for this Outage.

• Event ID Code not in Form 5 of current period• Outage ID Code [] has the Outage Continuation field entered as Continues into next

period with a Start Date/Time = MM/DD/YYYY HH:MM [] timezone. However, the entered DURATION does not equal the HH:MM [] timezone [the EOYCD] remaining in the given reporting year. Enter a DURATION equal to HH:MM [the EOYCD], or change your data entry in the Outage Continuation Field.

RELIABILITY | ACCOUNTABILITY216

M13 – Validation Errors Form 4.1 AC Circuit Detailed Automatic Outage Data (cont’d)

• For a '0' duration outage, the Sustained Outage Cause Code must be 'N/A -Momentary'. Please enter this Sustained cause code OR change the Duration to a number greater than zero.

• For a duration outage greater than '0', the Sustained Outage Cause Code CAN NOT be 'N/A - Momentary'.

• Outage duration overlap other outage(s) in the XML with the same element.• Duplicate Event ID Code and Element Identifier• In XML file, Same Event ID Code is used with another outage having one of them as a

Single mode outage• Invalid Sustained Cause Code

RELIABILITY | ACCOUNTABILITY217

• Outage Duration is invalid. (hhhh:mm) Max Duration: XXX:XX• Invalid Fault Type• Outage Duration is invalid. Format is hhhh:mm• Sustained Cause Code is missing• Outage continuation flag is missing (0,1,2)• Outage Mode is missing• Outage Duration is out of range in [] timezone. (Max duration: XXX:XX)• Initiating Cause Code is missing• Invalid Initiating Cause Code

M13 – Validation Errors Form 4.1 AC Circuit Detailed Automatic Outage Data (cont’d)

RELIABILITY | ACCOUNTABILITY218

M13 – Validation Errors Form 4.3 Transformer Detailed Automatic Outage

Data

• Event ID Code not in Form 5 of current period• A transformer outage has been entered with zero outage duration, indicating the

outage was momentary. Momentary transformer outages are rare. Please verify that the outage duration should be zero. If OK, please proceed. If not, enter a duration greater than or equal to 1 minute.

• Warning - For Outage ID [] associated with Event ID [], 'Failed Protection System Equipment' was entered as the 'Initiating Cause Code.' Therefore the cause of this outage is likely to be abnormal clearing (per NERC definition of Normal Clearing). However, the associated Event Type number entered on Form 5 is less than 50, which are 'Normal Clearing' event types. Warning: Please consider entering an abnormal clearing Event Type Number on Form 5, or do not enter 'Failed Protection System Equipment' as the 'Initiating Cause Code' for this Outage.

RELIABILITY | ACCOUNTABILITY219

M13 – Validation Errors Form 4.3 Xformer Detailed Automatic Outage Data (cont’d)

• Outage continuation flag is missing (0,1,2)• Outage Initiation Code Name is missing• Outage Mode is missing• Fault Type is missing• Invalid Outage Initiation Code Name• Outage Duration is invalid. Format is hhhh:mm• Outage ID Code [] has the Outage Continuation field entered as Continues into next

period with a Start Date/Time = MM/DD/YYYY HH:MM [] timezone. However, the entered DURATION does not equal the HH:MM [] timezone [the EOYCD] remaining in the given reporting year. Enter a DURATION equal to HH:MM [the EOYCD], or change your data entry in the Outage Continuation Field.

• Sustained Cause Code is missing

RELIABILITY | ACCOUNTABILITY220

M13 – Validation ErrorsForm 5.0 ID Code and Event Type Number Data

• Duplicate Event ID Code• Disturbance Report Filed flag is missing• Event Type ID is missing• Event ID Code is missing• Warning - Event ID Code Found. Will not be updated on Append Action.• Event ID Code exists in another Reporting Period: 2016

RELIABILITY | ACCOUNTABILITY221

M13 – Validation ErrorsForm 6.1 AC Circuit Detailed Non‐Automatic Outage Data

• Warning - An old version of xml schema is uploaded. We will not be processing extra field (Planned Cause Code) in the file.

• Outage Duration is invalid. (hhhh:mm) Max Duration: XXX.XX• Outage duration overlap existing outage(s) with the same element.• Planned Outage Cause Code CANNOT be 'NA'• Planned outages are not allowed from year 2016 and forward.• Outage Duration is missing or zero• Outage Duration is invalid. Format is hhhh:mm• For the selected 'Outage Continuation Code', the Outage Duration is out of range

(Minimum Duration: XXX:XX)

RELIABILITY | ACCOUNTABILITY222

M13 – Validation ErrorsForm 6.1 AC Circuit Detailed Non‐Automatic Outage Data (cont’d)

• Outage continuation flag is missing (0,1,2)• Outage Duration is out of range in [] timezone. (Max duration: XXX.XX)• Outage duration overlap other outage(s) in the XML with the same element• Outage ID Code [] has the Outage Continuation field entered as Continues into next

period with a Start Date/Time = MM/DD/YYYY HH:MM [] timezone. However, the entered DURATION does not equal the HH:MM [] timezone [the EOYCD] remaining in the given reporting year. Enter a DURATION equal to HH:MM [the EOYCD], or change your data entry in the Outage Continuation Field.

• Operational Cause Code is missing

RELIABILITY | ACCOUNTABILITY223

M13 – Validation Errors6.3 Xformer Detailed Non‐Automatic Outage Data

• Warning - An old version of xml schema is uploaded. We will not be processing extra field (Planned Cause Code) in the file.

• Outage Duration is invalid. Format is hhhh:mm• Outage Duration is missing or zero• Planned Cause Code is missing• Planned Outage Cause Code CANNOT be 'NA'• Planned outages are not allowed from year 2016 and forward.

RELIABILITY | ACCOUNTABILITY224

M13 – Validation Errors Common Data Validation Errors

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY225

M13 – Validation Errors Common Data Validation Errors (cont’d)

• The excel sheet will allow an AC outage to have the initiating cause code of Failed AC/DC Terminal Equipment to be selected but this is an invalid cause code for AC circuits. It is only valid for DC circuits (not sure if this is something we should just have NERC fix but it has caused issues.

OATI Proprietary Notice: All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved.

RELIABILITY | ACCOUNTABILITY226

Questions & Examples from Audience

RELIABILITY | ACCOUNTABILITY227

Advanced Examples from FAQ