Upload
lamtu
View
257
Download
4
Embed Size (px)
Citation preview
1 - Classification: Internal 2011-05-24
Subsea processing
IFEA seminar: Subsea Kraftforsyning
Stavanger, 25 mai 2011
2 - Classification: Internal 2011-05-24
Subsea Processing
• Introduction to Subsea Processing
− Why, where, what is subsea
processing
− Key drivers
• Key technologies
− How they work
− Relevant experience in Statoil
• Subsea processing future needs and
requirement for subsea HV power
3 - Classification: Internal 2011-05-24
Subsea in Statoil
• Today more than 50% of
Statoil production is from
subsea production systems
• Statoil has approximately
480 subsea wells
• Number of wells increasing
with new tie-in projects to
existing facilities
• Subsea processing used to
increase recovery
Tyrihans
Tordis
Troll Pilot
Åsgard
Gullfaks
Ormen Lange
Lufeng
4 - Classification: Internal 2011-05-24
What is subsea processing?
Manipulating the well stream between wellhead and
host.
By:− Hydrocarbon boosting
− Separation systems
− Gas compression
− (Raw seawater injection)
Prerequisites and enablers:− Long distance / high voltage power
− Advanced process monitoring and control
− Cost-efficient installation, maintenance and retrieval
Technology
Asset
Infrastructure
Pipelines
InfrastructureInfrastructure
Pipelines
5 - Classification: Internal 2011-05-24
Why subsea processing in Statoil?
• Benefits:
− Increased hydrocarbon recovery
− Accelerated production
− Reduced CAPEX / OPEX
− HSE
• These benefits typically become more significant in fields with:
− Deeper water
− Longer step-out / distance
− Lack of infrastructure
− Harsher environments
• Enabling technology (e.g. ultra-deepwater, ”tight, deep reservoirs” and difficult fluids)
480 subsea wellsmore than 50% of Statoil’s total production.
7 - Classification: Internal 2011-05-24
Effect of subsea boosting:
• Accelerated Production
• Increased Total Recovery
• Shorter Recovery Time
Time
Pro
du
cti
on
Normal Production
Profile
Boosted Production
Profile
time
8 - Classification: Internal 2011-05-24
Pfwh Inflow
Performance
Relation
(IPR)
System
Resistance
Curve
Q1
Natural
Flow
Q2
MPP
Discharge
pressure
Curve
Boosted
Flow
dQ
(Flow
Increase)
Subsea Processing Principle (Boosting)
dPrequired
MPP must be able to
Pump Q2 with dP
Q
10 - Classification: Internal 2011-05-24
Less dP required with separation, for a given inflow & pipeline ID
dP Requirement
Boosting
Without
water
With
water
System
Resistance
Curve
without
water
System
Resistance
Curve
with water
Natural
Flow
With
water
Natural
Flow
Without
water
dQinflow - Boosting
Qinflow
Inflow
Performance
Relation (IPR)
With water
Pfwh
Subsea Processing Principle (Separation & Boosting)
Removal
of water
(separation)
12 - Classification: Internal 2011-05-24
Statoil subsea processing historystepwise development
1996
Gullfaks
First multiphase
Pumps (topsides, part
of Framo
commercialisation)
2003
Norne
Technology
program
Subsea
separation
concept
developments
1986
Start Poseidon
multiphase pump
development
1997
Lufeng
Subsea
pumps
2000
Troll
Subsea water
removal and
injection
2007
Tordis
Subsea water
removal &
injection, oil &
gas boosting
2009
Tyrihans
Subsea raw
seawater
injection (ready
for operation)
2005
Troll Pipe
separator
Qualifications
Subsea water
removal
Lufeng Operation 1997 - 2009
Tordis 2007
Tyrihans
SRSWI
Troll Pilot 10 years -
2009
Pipe separator
13 - Classification: Internal 2011-05-24
Statoil experience with subsea pumps
PoseidonIFP,Total, Statoil
LufengGullfaks A
topside
Troll Pilot
TordisTyrihans
19861994
19971999
20072009
0,4 MW 0,4 MW 1,6 MW 2,3 MW 2,7 MW
14 - Classification: Internal 2011-05-24
Subsea pumps – applications today:
Well stream boosting
− Multiphase boosting
• Helico axial
• Twin screw
− Centrifugal/Hybrid/ESP (limited GVF)
Subsea separation and boosting
− Centrifugal
− Hybridcombination of MP and centrifugal
− ESP
Water injection
− Centrifugal
15 - Classification: Internal 2011-05-24
Lufeng field development
• Distance to host: 1 km
• Water Depth: 330 m
• Pumps: 5x0.4MW (SPP)
• Flow: 20 000 m3/d
• Drive system: 5x VSD
• Subsea power: Direct drive
• Prod. start-up : 1997
• Prod. Shut-down: 2009
Subsea pumps:
- Enabeled field development
- Extended field life from 5 to 12 years
16 - Classification: Internal 2011-05-24
Statoils experience with subsea separation
Troll Pilot
1999 Tordis
2007
Norne Technology
Program
2003-5
Pazflor
Totaloperator
2011
Troll pipe separator
qualifications
2005
17 - Classification: Internal 2011-05-24
Troll Pilot field development
• Distance to host: 2 km
• Water Depth: 350 m
• Pump: 1.8MW (SPP)
• Flow: 63,000BBLD (25,000BBLD oil)
• Drive system: VSD
• Subsea power: Direct drive
• Prod. start-up : 2000
Installed 1999
Started 2000
Still stable and profitable operation after
10 years on the seabed
Currently injecting 20 000 bbl/d ->
increasing oil capacity at Troll C
18 - Classification: Internal 2011-05-24
Troll Pilot
Operational experience2000: Electrical earth fault in wet mate
connector during first start-up –Fixed in 2001
2003: Pump required intervention
2003: Inductive level instrument lost function, due to an
electrical jumper
2005/06 The inductive level detector jumper replaced
2007: Pump upgrade
From 2008 100% availability
19 - Classification: Internal 2011-05-24
Tordis SSBI field development
SSBI station
WI Well
PLIM
Existing Tordis subsea
• Distance to host: 12 km
• Water Depth: 210 m
• Pumps: 2x2.3MW (SPP+MPP)
• Flow: 189,000BBLD (57,000BBLD oil)
• Drive system: 2x VSD
• Subsea power: Direct drive
• Prod. start-up : 2007
Ambition: Increase oil recovery from 49% to 55% (~36.5 Million bbl)
20 - Classification: Internal 2011-05-24
Tordis
Operational Experience
Tordis without SSBI:
− Oil: 25000 bpd
− Total Liquid: 130000 bpd
− Water cut: 80 %
Tordis including SSBI:
− Oil: 40000 bpd
− Total liquid 180000 bpd
− Water cut: 80 %
− Water inj: 65000 bpd
100% availability of subsea processing station
Sand handling system working properly
Oil content way below specified 1000 ppm
21 - Classification: Internal 2011-05-24
Statoils experience with subsea water injection
Tyrihans
RSWIinstalled
2009
2011
SWIT
Phase 1
(Statoil not part of JIP)
2010
SWIT
Phase 2
22 - Classification: Internal 2011-05-24
22
W (SRSWI)
•Distance to host: 40 km
•Water Depth: 270 m
•Pumps: 2x2.5MW SPP
•Flow: 88,000BBLD
•Drive system: 2 x topside VSD’s
•Subsea power: 2 x subsea
transformers
•Prod. start-up : 2011
Tyrihans SRSWI field development
Experience transfere:
•Integrated control system
•Pumps 100 % available since installation
•Awaiting injection well
23 - Classification: Internal 2011-05-24
Subsea Compression
Gullfaks SCS
Åsgard Subsea Compression
Ormen Lange SCS Pilot
Snøhvit future development
2014?
- Topside experience, KBS etc
- Compact compressor
- Compact gas scrubbers
- Power system
- All electric control systems
- Material testing
24 - Classification: Internal 2011-05-24
Ongoing subsea compression projects
Field Gullfaks Åsgard Ormen Lange *
Planned Installed 2014 / 15 2014 2016
Design life (yrs) 20 30 30
Depth (m) 135 260 850
Tieback (km) 15 40 - 50 120
No of units 2 2 4
Pressure boost (bar) 30 50 60-70
Power (MW) 10 20 58
VSD Topside Topside Subsea
* Operated by Shell
25 - Classification: Internal 2011-05-24
Subsea Compression…. Not only a submerged compressor
Picture from Ormen Lange Pilot
Subsea process equipment Subsea power equipment
27 - Classification: Internal 2011-05-24
Future needs
Subsea power distribution and subsea VSDs,
Larger dP pumpsLonger step outs
Deeper waters
Colder
Future needs
Environments
Heavier fluids
Larger hydrostatic pressures
Deeper reservoirs
500 km step-outs 3000 m water depth 100 MW power
28 - Classification: Internal 2011-05-24
Longer step outs
New areas - e.g. Barents sea
− limited infrastructure
− larger step out distances from hostToday: Tyrihans ca 43 km – > 200 km
− Limited volumes in place
long tie backs if
• separation to transport quality
• cost allows
Impact for Subsea power:
− High dP pumps to overcome
long distance transportation
− Subsea coalesher
− Local subsea water injection
Larger motors to reduce
number of pump units
Subsea power
distribution
Larger motors, subsea VSD and HV power
distribution, Local power?,
29 - Classification: Internal 2011-05-24
Deeper: GoM drivers
P
• Statoil leases in deep water (1500-3000 m)
• Large volumes in place;
low initial recovery factor
• Paleogene reservoirs:
− Relatively low GOR
− Relatively low bubble point
− Low permeability
low(er) operating pressure
− Deep reservoirs; 7000 m below seabed
High shut-in pressure; casing, penetrators
• Seabed pumps from first oil
• (Single phase followed by High dP MPP/hybrid pumps)
• Subsea ESPs and subsea HV power distribution
SPPMPP
ESP
Needs:
• Increased reliability/regularity
• Reduced intervention costs
• Subsea “HIPPS”
30 - Classification: Internal 2011-05-24
Colder
• Arctic areas
− Long distance power supply
− Subsea HV power distribution
− Lager pumps/motors to reduce number of
units
− Separation to transport quality
• Heavier fluids
− Lager motors
− In-field flowline heating
− Subsea HV power distribution
− Subsea coalesher
− SLPS
31 - Classification: Internal 2011-05-24
Ambitions for subsea processing
and subsequent subsea HV power
Ambitions
• Efficient transport of conditioned well streams over long
distances
− in long term up to 500 km utilizing separation, liquid
boosting and wet gas compression.
• Develop abilities to access resources in deep water and
harsh environments.
− Also heavy oil prospects
• Ensure that subsea gas compression is an integral part of
future developments in accessing the international gas
value chain
• Maintain production rates in the Norwegian Continental
Shelf through deployment of subsea processing as a major
part of Statoil’s increased hydrocarbon recovery initiative.
Needs for subsea HV power
• Efficient subsea power transmission systems
• Reliable/ high endurance rotating machinery and subsea HV power equipment
• Advanced processing systems will require additional utility systems -> power and power distribution
• Cost effective solutions (not only key equipment, but pipes, power lines, umbilicals and distribution systems etc)
• Subsea HV power distribution and control
• Lager units; e.g up to 5-6 MW pumps, 15 MW compressors
• Smaller units – within existing technology
• Smaller compressor units; 3-6 MW
• Subsea distribution and power control (host platform is weight and space limited)
We seek your ideas to meet our ambitions…
33 - Classification: Internal 2011-05-24
Subsea processing – at IFEA Subsea power conference 2011
Birgitte Nordheim Tveter
Principle Engineer, subsea processing
www.statoil.com
Thank you