EQUIPMENT FOR SUBSEA DECOMMISSIONING
HYDRAULIC SUBSEA CI4500 AF CI19500
Weight in Air 5,000 kg 19,400 kg
Jaw Depth (C) 750 mm 1,300 mm
Jaw Opening (B) 740 mm 1,225 mm
Max Shear Capacity 14” OD Pipe 24” OD Pipe– 20” OD Pipe + 50mm
reinforced concrete coating
Designed for cutting up to 250m water depth pipe lines, risers, ca-
bles and flexibles.
Operating subsea and on the deck.
Cutting time 1 minute
We have 15 years experience in supplying and servicing steel processing equip-
ment in the Australian market
An increasing number of oil and gas fields in Australia are reaching the end of
their economical feasible production life. Consequently decommissioning activity
will increase as production infrastructure needs to be removed. To cater for this
growing industry Decomm Rentals has custom designed a number of subsea tools
and auxiliary equipment to its rental fleet.
Fugro TSM_ Woodside
Persephone Riser Removal– Phase 1 Mattress Removal
All equipment is fitted with a ROV panel for
subsea contingencies. NATA tested rigging, full
bunding and engineering support.
Decomm shears come complete with spare
cutting blades and a landing frame to ensure
safe retrieval on the deck. Qualified Decomm
offshore personnel is optional. With the
downline spooler also available for safe
handling of the down line.
HYDRAULIC SUBSEA
GRAB
RV500– 5P
Weight in Air 1,140 kg
Load Capacity 3,500 kg
Max. Tine Opening 1,930 mm
Holding Capacity 14” OD Pipe
Fugro TSM_ Woodside
Persephone Riser Removal– Phase 1
R56 Grab also available.
Please contact Decomm
Rentals for further details
www.decomm.com.au
+61 (0)8 9362 4304
DECOMM RENTALS REFERENCES
Contractor: Fugro TSM
Client: Woodside
Vessel Name: REM Etive
Project: Persephone Riser Removal–
Equipment: CI4500 AF Shear; RV500 Grab
OD of the Line: 16 inch
Length: 400m, cut in to 5m length
Year of Execution: December 2014
Water Depth: 125m
Metquip Rentals Pty. Ltd.
Trading as
Contractor: Fugro TSM/ Greatships
Client: Apache Energy Ltd
Vessel Name: Southern Ocean/ Mamta
Project: Legendre Decommissioning
Equipment: CI300 Shear; RV500 Grab
OD of the Line: 8 inch
Length: 2.5 km, cut in 11.5m lengths
Year of Execution: July 2010– February 2011
Water Depth: On deck