21
NTS. 32-L-4 32L04SE9489 2.4728 SUNDAY LAKE 010 Report on the Geophysical Surveys Performed on SUNDAY LAKE 1-81 Sunday Lake Area Porcupine Mining Division REr 3 o U/v. April 26, 1982 Timmins, Ontario L.A.Waddell Noranda Exploration Co. Ltd,

RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

NTS. 32-L-4

32L04SE9489 2.4728 SUNDAY LAKE010

Report on the

Geophysical Surveys

Performed on

SUNDAY LAKE 1-81

Sunday Lake Area

Porcupine Mining Division

REr3 o

U/v.

April 26, 1982 Timmins, Ontario

L.A.WaddellNoranda Exploration Co. Ltd,

Page 2: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

- l -

Sunday Lake 1-81

Introduction:

The property consists of 16 contiguous unpatented mining

claims numbered P-599086 to P-599101 inclusive situated adjacent to survey mileage post 173 along the Ontario-Quebec Provincial

boundary.

The claim group is located approximately 110 miles northeast of Cochrane, Ontario.

Access :

The most practical means of access is by helicopter from

La Sarre, Quebec which is about 90 miles to the south.

Topography:

The property is generally of low relief, however a slight rise

in elevation is evident near central area where outcrop occurs.

Drainage is to the south from a small lake along the west border

of the group but reverts to north flowing from lakes along north

border of the claims. Spruce is the most abundant tree type found.

Linecutting:

Baseline 0+00 was cut with an Azimuth of N45 W through the

173 mile post along Ontario-Quebec border for a distance of 6000' west and 1600' east. Traverse lines were cut normal to the base

line at 400 foot intervals. Three tie lines were cut parallel to the baseline at 12+00 north, 30+00 south and 38+00 south to pro vide more accurate control of the grid. The baseline, tie lines and traverse lines were all chained and picketed at 100 foot

intervals.

In all 17.2 miles of line was cut, chained and picketed by

R. Mainville, contractor, of Senneterre, Quebec in the period

Feb. 10-15, 1982

Page 3: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

- 2 -

gnetic Survey:

1) Assessment Data

The instrument used was a McPhar M-700 Fluxgate Magneto meter. Base readings were taken along the baseline and all read

ings were then adjusted relative to the base readings. Readings

were taken at the base control stations at periodic intervals to

discern day-to-day and diurnal drift. Any changes noted in the magnetic intensity were then applied as factors and progressive

adjustments were made to each reading taken during that specific period of time.

Some 1039 stations were read by Noranda personnel in the period Feb. 15-18, 1982.

2) Magnetic Results

The results of the magnetic survey are shown on the prints

accompanying this report.

Geological mapping has shown the property to be situated near the contact of basic volcanic tuff and a large body of gabbro.

The magnetic anomaly, on lines 52 and 56 west, near small lake and the spot mag high at 6+00 south on line 16 west are thought

to be caused by gabbroic rock.

Two linear anomalies trending in a slightly north easterly

direction are possibly caused by diabase dykes. These trend from 38+00 south on 54 west to 19+00 south on line 44 west and from

38+00 south on line 28 west to 28+00 south on line 20 west.

The magnetic anomaly trending from 5+00 south on line 00 to 10+00 south on line 12 east was intersected by a drill hole in

1974 and found to be caused by massive sulphides within a mafic

tuff.

A second magnetic zone trending from 12+00 south on line

12 west to 19 south on line 8 east was also drilled in 1974 and

found to be caused by massive sulphides in a mafic tuff.

Page 4: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

- 3 -

A narrow, shallow magnetic source, trending from 17+00

south on line 48 west to 11+00 south on line 32 west, can be seen to be closely associated with a HEM conductor. No evidence of

drilling or trenching has been found to fully explain this zone.

HEM Survey:

1) Assessment Data

The instrument used was an Apex MaxMin II Horizontal Loop

unit.

The instrument consists of a transmitting coil and a

receiving coil connected by a reference cable either 200, 300, 400 or 600 feet in length.

The transmitting coil produces a primary electromagnetic

field (e.m.f.) at either 111, 222, 444, 888, 1777 Hz which is

capable of inducing a current within a conductive body. This

current in turn produces its own e.m.f. which is termed the

"secondary". The receiving coil measures the total intensity of

the primary e.m.f. plus any resultant secondary e.m.f. It also

breaks the received signal down to an in-phase component and

quadrature component by means of the reference cable.

The two coils are used as an in-line system traversing

across the presumed geological strike. If the two coils straddle

a conductor, the primary and resultant secondary field oppose each

other causing a decrease in total field strength of a negative reading. In shallow overburden, a positive shoulder will occur

when both coils are just off to one side of the conductor.

An indication of the conductivity of the body can be obtained by measuring the ratio of the in-phase to the out-of-phase,

As the conductivity of the body decreases the stronger the out-of-

phase component will be.

The range of penetration of the priamry field is normally

considered to be approximately one-half the coil separation;

however, other factors such as conductive overburden and topography must also be taken into consideration.

Page 5: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

- 4 -

Some 1454 readings at frequencies of 444 and 1777 Hz were taken contemporaneously with the magnetic work by Noranda personnel.

2) HEM Results

The results of the HEM survey are shown on prints accom panying this report.

Two zones of conductivity were located. The north con ductor trends from 18 south on line 44 west to 9+00 south on line 16 east. It is north dipping, shallow and has magnetic association along eastern half. The strongest section on its western half is located on lines 32 and 36 west. The conductor at this location lies along the flank of a very narrow magnetic high.

The second zone trends from 174-00 south on 24 west to

19+50 south on 8 east. It is north dipping and has magnetic association.

Conclusion and Recommendations

Two conductors were located on the claim group. Assess ment information has shown that drilling has been performed by Amoco Canada Petroleum Co. Ltd. in 1974.

This drilling has explained the cause of conductivity for the eastern portion of the north conductor and also explained cause of shorter southern conductor.

Further work should be done on conductor located on lines 32 and 36 west.

Since there is shallow cover at this location trenching may explain this conductive source. If not an X-ray hole sould be attempted on line 36 west.

Respectfully submitted,

L.A. WaddellNoranda Exploration Co. Ltd.

Page 6: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

Ministry otNaturalResources

Ontario

Report of Work(Geophysical, Geological, Geochemical and Expenditures)

The Mining32Le4SE9409 2.4728 SUNDAY LAKE

Typu of Survoy(s)

Geophysical (Magnetic k Electromagnetic)

300

Claim Holder(s) ~

Noranda Exploration Company, Limited (No Personal Liability)

Sunday Lake AreaProtpoctor'i Licence No.

Survey Company

Noranda Crew

A-3l* 38T

Name and Address of Author (of Geo-Tcchnical report)

Mr. L.A. Waddell, P.O. Box 1205, Timmins, Ontario PUN 7J5

Survey Dates (llnecutting to office)

10 .02 .82 26 , 02 82Day l Mo. l Yr. Day | Mo. | Yr.

Total Miles of line Cut

17.2

Special Provisions Credits RequestedInstructions

For first survey:

Enter 40 days. (This Includit line cutting)

For each additional survey: using the same grid:

Enter 20 days (for each)

Geophysical

- Electf omegnetic

- Mignttomottr

- Radiometric

- Other

Geological

Geochemical

Days per Claim

Uo

20

Man DaysInstructions

Complete reverse iide End enter total(s) here

Geophysical

- Electromagnetic

- fvlagnstometer

- Radiometric

- Other

Geological

Geochemical

Days perClaim

Airborne Credits

Note: Special provisions credits do not apply to Airborne Surveys.

Electromagnetic

Manric:orr,elcr

RacJiomttric

Days per Claim

Expenditures (excludes power stripping)Typo of Work Pc-formcd

Performed on CUim(s)

Coir.;!i'.ion of Expenditure Days Credits

Total ExpendituresTotal

Days Credits

le::. Days C't^itfi may c c epponicncd EI the claim holder'i cl-.o::t. Enter number of days credits per claim selected in coljmns st right.

Rcpc't Complt-ud;tc c' Report

Feb. 26/82Agent (Signature)

Ctrl -'r?.:ion Vctifvinci R'.port

Mining Claims Traversed (List in numerical sequence)Mining Claim

Prefix

P

Number

59908659908759908859908959909059909159909259909359909U599095599096599097599098599099599100599101

Expend. Dayi Cr.

60606060606060606060606060606060

Mining CloimPrefix

R I1

Number

t ————— ~

f

MAR 1 6 1982M1NIN

|

fa LANDS SEC

;i

ixpend, Days Cr.

D-

riXfctlION

For Office Use- OnlyTots' Days Cr. D^e Rccorato Recorded

Total number of mining cl.ilms covered by thli ropta-**")r.'0rk.

ifHmfi

BtgRcgioiiftat'Mlfflffg'Refcordor

l l :.--:~; ct't.'y tt,at l ha 1.e a persons! t'.d intimi'.e knowledge of the ftcts set forth in the Rcpc't cf Work sr.riexed hc'cio, having performed the work cr ,: :'.fc::-:3 tint durln; crd/or D'tc- i:; correction end the snrexod revert is true.

Name i-.s Posts' Adcress of Person Cc-nifying

Mr. L.A. Waddell

P.O. Box 1205, Timmins, OntarioDate Certified

Feb. 26/82Certified byj

1SC2 ill 21 /

RECORDED

1.4AK b

Roeoipt No......

1 i ..' J.'.M v

Page 7: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

Ministry of Natural Resources

GEOPHYSICAL - GEOLOGICAL - GEOCHEMICAL TECHNICAL DATA STATEMENT

File.

TO BE ATTAOMV.D AS AN APPENDIX TO TECHNICAL REPOI'.TI ACJ S SilCnVN HERE NEED NOT BE REPEATED IN REPORT

TECHNICAL REPORT MUST CONTAIN INTERPRETATION, CONCLUSIONS ETC.

Type of Survcy(s) Geophysical (Electromagnetic ft Magnetic)

Township or Area,Sunday Lake Area___________________ Claim Holdcr(s)Noranda Exploration Company, Limited_____

Suite hOO, 55 Yonge Street, Toronto, Ontario

Survey Company Noranda Crew.^^^———————,—^—-^ Author of Report Mr. L.A. Waddell___________________Address of Autho; P.O. Box 1205, Timmins, Ontario

Covering Dates of Suivtry Feb. 10-26, 1982(iinectittirig to office)

Total Miles of Line Cv.t. 17.2

SPECIAL PROVISIONS CREDITS REQUESTED

ENTER 40 days (includes line cutting) for first survey.ENTER 20 days for each additional survey using same grid.

Geophysical

—Electromagnetic.—Magnetometer—.

DAYS"" claim

-Other-Geological.

AIRBORNE CREDITS (Special provision credits do not apply to airborne surveys)

Magnetometer. .Electromagnetic . . Radiometric(enter days per claim)

Apr. 26/82\ftjfoT ''of

Res. Gcol. .Qualifications.Previous Surveys

File No. Type Date Claim Holder

MINING CLAIMS TRAVERSEDList numerically

599086(prefix)

P(number)

599087

P

P

..?.?.?.9.?.?..599089599090

599091

pp

599092

599093

599091*

p p

599096

.P., pL p

.5.9.9.100.

TOTAL CLAIMS. 16

Page 8: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

GEOPHYSICAL TECHNICAL DATA

x'l) SURVEYS -- If more than one survey, specify data for each type of survey

Number of Stations.

Station interval———

Profile scale —————.

1039 .Number of Readings HEM100'

.Linel" s 20*

Contour interval. 200 gammas

SI

Instrument McPhar M-TOO Fluxgate Magnetometer

Mag 1039

P Accuracy - Scale constant 20 gammas per scale division_______________________________ Diurnal correction method c ^-osed loops of less than l hour duration and progressive factoring.

Base Station check-in interval n,™,r*\ 2 hours or lessBase Station location and value Line 00/Baseline 1502 gammas

Instrument Apex Parametrics MaxMin II HEM\~lIvf

zo?^. - rs

B

Coil configuration -Toil sep.-i ration

Accuracy. .

Method:

Frenuenry

horizontal loop150 meters (U92')2io per scale division

Q Fixed transmitter Q Shoot back IS In line CD Parallel line MiU Hz, 1777 Hz

(specify V.L.F. station)

Parameters measured In-phase and out-o f-phase component of secondary electromagnetic field.

Instrument

Scale constant

Corrections made.

O Base station value and locution

Elevation accuracy.

tLtV)

Instrument

Method C

Parameters

i Time Domain

On time ^-——.

Off timetime

Integration time .

Power.

Electrode array

z. Electrode spacing .

Type of electrode

f~l Frequency Domain

_ Frequency _____

_ Range ________

Page 9: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

1983 02 17Ministry ofNaturalResources

Technical Assessment

Work CreditsOntario

File

2.4728

Recorded Holder

NORANDA EXPLORATIONTownship or Area

SUNDAY LAKE AREA

Type of survey and number of Assessment days credit per claim Mining Claims Assessed

Geophysical

Electromagnetic

Magnetometer

Radiometric ^

Induced polarization .

Section 86 (18)

Geological -

Geochemical

.days

. days

. days

.days

.days

. days

. days

P 599086 to 94 inclusive

599096 to 100 inclusive

Man days CD

Special provision 1*1

Airborne CD

Ground 0

d Credits have been reduced because of partial

coverage of claims.

LJ Credits have been reduced because of corrections

to work dates and figures of applicant.

Special credits under section 86 (15a) for the following mining claims

10 days

P 599101

20 days

P 599095

No credits have been allowed for the following mining claims

l_j not sufficiently covered by the survey l_l Insufficient technical data filed

The Mining Recorder may reduce the above credits if necessary in order that the total number of approved assessment days recorded on each claim does not exceed the maximum allowed as follows: Geophysical 80; Geological 40; Geochemical 40; Section 86(18)-60:

828

Page 10: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

1983 02 17Ministry o! Natural

sourcesOntario

Technical Assessment

Work Credits

File

2.4728

Recorded HolderNORANDA EXPLORATION CO LIMITED

Township or AreaSUNDAY LAKE

Type of survey and number of Assessment days credit per claim

Geophysical

Electromagnetic .

Magnetometer.

Radiometric _

20

Induced polarization .

Section 86 (18) -

Geological ^^^^

Geochemical.

.days

. days

.days

.days

.days

. days

. days

Man days CD

Special provision Ix

Airborne CD

Ground IX

CD Credits have been reduced because of partial

coverage of claims.

Credits have been reduced because of corrections

to work dates and figures of applicant.

Mining Claims Assessed

P 599086 to 94 inclusive 599096 to 100 inclusive

Special credits under section 86 (15a) for the following mining claims

5 days

P 599101

10 days

P 599095

No credits have been allowed for the following mining claims

l_l not sufficiently covered by the survey l l Insufficient technical data filed

The Mining Recorder may reduce the above credits if necessary in order that the total number of approved assessment days recorded on each claim does not exceed the maximum allowed as follows: Geophysical 80; Geological 40; Geochemical 40; Section 86(181-60:

Page 11: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

Ontario

Ministry oi GeotechnicalReloulces RePOrt

Approval

. H-"7^8

Mining Lands Comments

To: Geophysics

Comments

.pproved (] Wish to tee again with correctionSignet

JTo: Geology - Expenditures

Comments

[~] Approved [ | Wish to see again with correctionsDate Signature

To: Geochemistry

Comments

[ l Approved [ | Wish to see again with correctionsDate Signature

j [TO: Mining Lands Section, Room 6462, Whitney Block. (Tel: 5-1380)

1593 (81/10)

Page 12: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

1983 03 17 2.4728

Mining RecorderMinistry of Natural Resources60 Wilson AvenueTimmins, OntarioP4N 2S7

Dear Sir:

RE: Geophysical (Electromagnetic ft Magnetometer) Surveyon Mining Claims P 599086 et al 1n the Sunday Lake Area

The Geophysical (Electromagnetic S Magnetometer) Survey assessment work credits as listed with my Notice of Intent dated February 17, 1983 have been approved as of the above date.

Please Inform the recorded holder of these mining claims and so Indicate of your records.

Yours very truly,

E.F. AndersonDirectorLand Management Branch

Whitney Block, Room 6450Queen's ParkToronto, OntarioM7A 1W3Phone: 416| 1965 1380

A. Barr:se

cc: Noranda Exploration Co Ltd Timmins, Ontario Attn: Mr. L.A. Uaddell

cc: Resident Geologist Timmins, Ontario

Page 13: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

Ministry ofNaturalResources

Ontario 8

1983 02 17

Your file:

Our file: 2.4728

Mining RecorderMinistry of Natural Resources60 fi son AvenueTimmins, OntarioP4N 2S7

Dear Sir:

Enclosed are two copies of a Notice of Intent with state ments listing a reduced rate of assessment work credits

to be allowed for a technical survey. Please forward one copy to the recorded holder of the claims and retain the other. In approximately fifteen days from the above date,

a final letter of approval of these credits will be sent to you. On receipt of the approval letter, you may then

change the work entries on the claim record sheets.

Yours very truly,

E.F. AndersonDirectorLands Administration BranchWhitney Block, Room 6450Queen's ParkToronto, OntarioM?A 1W3Phone: 416/965-1316

A. Barr:se

cc: Noranda Exploration Co Limited Timmins, Ontario Attn: Mr. L.A. Wadden.

cc: Mr. G.H. FergusonMining ft Lands Commissioner Toronto, Ontario

For further Information, 1f required, please contact Mr. F.W. Matthews at 416/965-1380.

845 (6/79)

Page 14: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

Ministry ofNaturalResources

Notice of Intent

for Technical ReportsOntario

1983 02 17

2.4728

An examination of your survey report indicates that the requirements of The Ontario Mining Act have not been fully met to warrant maximum assessment work credits. This notice is merely a warning that you will not be allowed the number of assessment work days credits that you expected and also that in approximately 15 days from the above date, the mining recorder will be authorized to change the entries on his record sheets to agree with the enclosed statement. Please note that until such time as the recorder actually changes the entry on the record sheet, the status of the claim remains unchanged.

If you are of the opinion that these changes by the mining recorder will jeopardize your claims, you may during the next fifteen days apply to the Mining and Lands Commissioner for an extension of time. Abstracts should be sent with your application.

If the reduced rate of credits does not jeopardize the status of the claims then you need not seek relief from the Mining and Lands Commissioner and this Notice of Intent may be disregarded.

If your survey was submitted and assessed under the "Special Provision-Performance and Coverage" method and you are of the opinion that a re-appraisal under the "Man-days" method would result in the approval of a greater number of days credit per claim, you may, within the said fifteen day period, submit assessment work breakdowns listing the employees names, addresses and the dates and hours they worked. The new work breakdowns should be submitted direct to the Lands Management Branch, Toronto. The report will be re-assessed and a new statement of credits based on actual days worked will be issued.

8-4S (32^5)

Page 15: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

1982 05 17

Mining RecorderMinistry of Natural Resources60 Wilson AvenueTimmins, OntarioP4N 2S7

2.4728

Dear Sir:

We have received reports and maps for a Geophysical (Electro magnetic and Magnetometer) Survey submitted under Special Provisions (credit for Performance and Coverage) on Mining Claims P 599086 et al In the Sunday Lake Area.

This material will be examined and assessed and a statement of assessment work credits will be Issued.

Yours very truly,

E.F. AndersonDirectorLand Management Branch

Whitney Block, Room 6450Queen's ParkToronto, OntarioM7A 1W3Phone: 416/965-1316

J. Skura/amc

cc: Noranda Exploration Co. Ltd. Timmins, Ontario Attn: Mr. L.A. Waddell

Page 16: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

Noranda Exploration Company, Limited (no persona/ /jabifily)

P.O. Box 1205,Timmins.Ont. P4N 7J5

noranda

April 29, 1982

Mr. E.F. Anderson, DirectorLand Management Branch,Room 6450,Whitney Block, Queen's Park,TORONTO, OntarioM7A 1W3

Dear Mr. Anderson:

Please find enclosed reports and maps in duplicate

covering geophysical surveys performed on three proper ties, Sunday lake 1-81, 2-81, and 3-81, a]l situated in

the Sunday Lake Area of the Porcupine Mining Division.

Yours truly,

LAW/bn L.A. Waddell encls.

Am t o 1982

MINING

Page 17: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

lit

x*

,x

001 ~U~~

SbTU

x

3.X

S^

xX"

xxx

x±x

Page 18: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

Wes

t of

Su

nday

La

ke

Are

a-M

. 30

04

CO o c "O

Q OD Q < O)

CD Q l OJ o

o

ro

Crt

C K > Z

O Z O S O

x i n m

co

•D ^ Z

o -n Z

o

c i O

OJ o

o OJ

o z. t- o TJ

O

O T!

X O w

m 33 rn

w OJ ro

0, •**

Q

Ji

^

O o

oJ'

IT

) m

P S

'—

(D

52

l

l w

W

> Z o >

z

o o

i r

s r

C/)

c

T)

J O c D ea

O -H

t/*

Z nz m

> y

2 z

^3

5

r-

OLO

m

^

y;T

^

r-

w-

o 5

s s

o

w

Z

*"

o

O

C

S

n

O30

z

m

nI"

z

Z

>.c*

i:

i/i

-4D

C

) m

m

m

^ -

O

O > o

iS I r*

-n

"~

P!

o zO

c O Z

Or—

m

m

O

n m Z n x

m

82

SI

x *-

rn

Page 19: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

r6O

Ws

/

56W

o

I2W

TTv.

~f

~

529C

96

' 99

1C

-O

"K..

LO

CA

TIO

N

PLA

N

Su

nd

ay

L

ak

e

1-8

1Sc

ale

t";

264O

'

I6E

^

LE

GE

ND

INST

RU

MEN

T:

McP

ttar

Flux

gate

M-r

ooR

EA

DIN

GS

: D

irectly

in

gam

mas

C——

50

OIs

om

ag

ne

tic

Con

tour

s

Magnetic

De

pre

ss i o

n

C*~

Magnetic

Base

S

tation

m,

Conto

ure

d

at:

2OO

gam

mas

No.

o

f re

adin

gs:

IO39

Da

tes

of

Surv

ey:

O

32L04SE9409 E.4728 SUNDAY LAKE

21

0

RE

VIS

ED

PRO

J.N

9N

T. 5

.D

WG

. N

2

Mag

netic

S

urve

yS

un

da

y Lake

1-8

1i-T

fi f

A

PR

OJE

CT

:SU

RVE

YED

BY

'......

. D

ATE

:D

RAW

N

BY

L..

....

'..'J

.*tf.

^?/7

. S

CA

LE

NORA

NDA

EXPL

ORAT

ION

CO. L

TDO

FF

ICE

: T

im m

w s,

Ont

.

un

Page 20: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

/J1

6O

W

8E

I2E

I6E

\

a

'. *9t

95

•^

?9tC

-;3

, 19

SO9?

5"

*C9t

J f!.

L

i*

LO

CA

TIO

N

PLA

N

Sunday

Lake

1-8

1S

ca

le

-'-

264Q

INS

TR

UM

EN

T:

Max-M

in

H

f 444

H?

.J

RE

AD

ING

S'

In

perc

enta

ge

l,\-

Pha

se :

P

lotted

clo

se

ra

tne

fine

Cu

t o

f P

hase;

" re

mo

te

from

th

e l

int

Pro

f ne

Scale

: l

"- 20

*56

, (p

lus

to le

ft,

mi n

u*

to r

ight}

ir--

Phase

: S

olid L

ine

; O

ut

uf

Phase]

Dashed

ue

fin

ed

C

onducfc

r

_l-fe

rrsd

Co

nd

ucto

r ^x

is

^^

O

Are

a

of

Conducts

-it/

.Vo

of

Re

ad

ing

s:

72

7

In -

^fia

se

, 727

Out

of

Phase

Da

fss

o?

S

u rvey

Co.'.

' S

ep

ara

tio

n;

ISO

M

ett

rs

('4

92

')

<

3aue4SE94ag

2.47

28 S

UNDA

Y LAKE

220

RE

VIS

ED

PRO

J.N

?N

T. 5

,D

WG

.N2

H.E

M

Su

rvey

Sunday

Lake

l-8t

PR

OJE

CT

:S

UR

VE

YE

D

DR

AWN

BY

DA

TE ALE

NORA

NDA

EXPL

ORA

TIO

N CO

. LTD

OF

FIC

E^

Tt.T

.rr.

Ont

.

Page 21: RPT ON THE GEOPH SUR PERFORMED ON SUNDAY LAKE 1-81...599090 599091 p p 599092 599093 599091* p p 599096.P., p L p.5.9.9.100. TOTAL CLAIMS. 16. GEOPHYSICAL TECHNICAL DATA x'l) SURVEYS

/

56W

H

x

V*

^^r

f -s

t i/

f--s*

P-5

99G

9?i*

*L *

.^

VA

fcX

-

l o l

o-

5*9G

86 ,

5S9O

8T t

599

08S

599Q

89

599O

9Q'

599O

95

5990

5M

599O

S3

. S9

9O92

\ 5

99

09

t I

i i

' l

S990

96

. 59S

O97

j

5390

08

S9

9tO

O

59

90

99

St/

ftfa

/ L

Q*e

LO

CA

TIO

N

PL

AN

Su

nd

ay

La

ke

1S

cale

/"

- 2

64

0'

I2E

I6E

INS

TR

UM

EN

T:

Max-M

in n

RE

AD

ING

S:

In

pe

rce

nta

ge

IN

Pha

se :

P

lotted

clo

se

to

the

Ou

t of

Ph

ase

: "

rem

ote

fr

om

ft)

e l

/ae

Pro

file

S

cale

: t"

? 2

O%

; (p

lus

to l

eft

, m

inu

s to

rig

ht)

In

-Phase

-

Solid

Lin

e;

Out

of

Ph

ase

, D

ash

ed

De

fin

ed

C

onducto

r A

xis

Infe

rred

Co

nd

uct

or

AMIS

Are

a of

Conductivity

No

of

Re

ad

ing

s:

727

In -

Ph

ase

, 727 O

ut o

f P

hase

Oat

es

of

Surv

ey:

Coil

Se

pa

ratio

n;

ISO

Ue

ter*

(4

93')

<

32L04SE9409 2.4728 SUNDAY LAKE

230

RE

VIS

ED

PRO

J.N2

N.T

.S.

DWG.

N2

HE

M

Sur

vey

Sunday

La

ke

1-8

1O

fi ta

r i C

PR

OJ

EC

T:

Zets

ur

Lo

t*

Are

a

SU

RV

EY

ED

BY-

- D

RAW

ND

ATE:

,.S

CA

LE

-

NORA

NDA

EXPL

ORAT

ION

CO. L

TD.

OF

FIC

E-

^ Ti

m/it

ins j

Ont

.

m