18
S2C11NEM47 2.1159 WATTBJ 010 3 2 8 1973 REPORT ON THE GEOPHYSICAL INVESTIGATION OF THE POCKET POND PROPERTY HAIKIRK AND WATTEN TOWNSHIPS RAINY RIVER DISTRICT, ONTARIO February 23, 1973. Thunder Bay, Ontario. K. Howard Poulsen, B.Se, M. W. BARTLEY AND ASSOCIATES LTD.

RPT ON THE GEOPH OF THE POCKET POND PROP

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: RPT ON THE GEOPH OF THE POCKET POND PROP

S2C11NEM47 2.1159 WATTBJ010

3 2 8 1973

REPORT

ON

THE GEOPHYSICAL INVESTIGATION

OF

THE POCKET POND PROPERTY

HAIKIRK AND WATTEN TOWNSHIPS

RAINY RIVER DISTRICT, ONTARIO

February 23, 1973.

Thunder Bay, Ontario.

K. Howard Poulsen, B.Se,

M. W. BARTLEY AND ASSOCIATES LTD.

Page 2: RPT ON THE GEOPH OF THE POCKET POND PROP

INTRODUCTION

Subsequent to initial geological investigation, the Pocket Pond

property underwent a geophysical exploration program during the Spring

of 1972. The program consisted of complete Radem (Vlf) E.M. and

magnetic coverage coupled with considerable coverage with the

horizontal loop E.M. method over the areas of greatest interest. As

a result of geophysical and preliminary geological work, a diamond

drilling program was initiated to delineate several targets. This

report summarizes the results of the geophysical surveys and their

correlation to geological features. Technical data is presented as an

appendix to the report in the form of a "Technical Data Statement".

M. W. BARTLEY AND ASSOCIATES LTD.

Page 3: RPT ON THE GEOPH OF THE POCKET POND PROP

2.

CONCLUSIONS

As a result of the performance of the above mentioned surveys,

fourteen distinct Radem (VLF) anomalies were discovered, ten of which

were confirmed by the Horizontal Loop survey. Of these latter anomalies,

five were tested by diamond drilling and in each case significant

quantities of sulfide material were encountered. A sixth anomaly had

been drilled by Noranda Mines Ltd. in 1966. In addition to the electro

magnetic conductors, seven ma^or magnetic anomalies were located. These

appear to be related to pyrrhotite concentrations associated with the

conductors, mafic intrusive rocks, and magnetic oxide facies iron

formation.

RECOMMENDATIONS

In light of the good correlation between the electromagnetic

conductors located and the sulfide material encountered by diamond

rolling to date, it is recommended that any contemplated further

drilling programs include plans to test those electromagnetic conductors

as yet untested, vith priority to be given to E.M. anomalies H14, R4

and R7. In addition, it is suggested that detailed geological mapping'

be undertaken to determine the stratigraphic and structural control

of the conductors and sulfide occurrences.

M. W. BARTLEY AND ASSOCIATES LTD.

Page 4: RPT ON THE GEOPH OF THE POCKET POND PROP

GENERAL GEOLOGY

The Pocket Pond property straddles a major contact between acidic

and mafic lithologies. The former, represented by quartz-feldspar-

biotite schists represent sedimentary and/or tuffaceous units. The

latter, in some locations, has the appearance of massive andesite

or basalt while closely related phases have the appearance of horn

blende gabbro and diorite. Structurally, the property lies on the

north limb of an easterly plunging antiform. The units strike

approximately 2900 in the property area while dips are variable to the

north. Sulfide occurrences in some respects appear to be related to

acid-mafic transitions in lithology.

THE RADEM (VLF) SURVEY

Numerous dip angle crossovers were located during the course of

the survey and the major ones have been correlated and labelled as

conductors RI through R14 and are represented on an enclosed map. In

general, the crossovers are well defined and likely represent accumu

lations of sulfides or graphite in parallel zones. A few crossovers

of broad extent and poor resolution are likely due to conductive

overburden and are not considered in the report. The major anomalies

and their features are summarized in Table 1.

M. W. BARTLEY AND ASSOCIATES LTD.

Page 5: RPT ON THE GEOPH OF THE POCKET POND PROP

THE HORIZONTAL LOOP SURVEY

The results of this survey, depicted on an enclosed plan, more or

less confirm the existence of many of the conductors outlined by the

Had em method. Labelled HI through H10, these anomalies are referred to

in Table 1. The mean ratio of in-phase to quadrature response (l/Q) is

quoted as a relative estimate of conductivity thickness for the conductor.

THE MAGNETIC SURVEY

Seven major magnetic anomalies (Ml through M6) vere encountered

(see magnetic plan). In addition to those anomalies which are

directly correlated to E.M. conductors, anomaly M2 is tentatively

explained as representing a magnetic oxide facies iron formation.

Magnetic anomalies M3 and M? likely represents the western extension

of a mafic intrusive body.

Respectfully submitted,

fK. "rn -KHP:mm K. Howard Poulsen, B. Se

February 23, 1973.

Approved :

M. W. Bartley, P. Eng.

M. W. BARTLEY AND ASSOCIATES LTD.

Page 6: RPT ON THE GEOPH OF THE POCKET POND PROP

Had em Anomaly

RI

R2

R3

R4

R5

R6

R7

R8

R9

RIO

Rn

R12

R13

R14

Approximate Length

60,(XXH feet

1,400 feet

800* feet

400 feet

800+ feet

80CH- feet

400+ feet

200 feet

400' (?)

400f-800*

?

400 feet

400+ feet

400 feet

TABLE 1

SUMMARY OF RESULTS

Corresponding Magnetic Hor.Loop Anomaly Correlation

HI (I/Q = 20+) Ml

H2

H3 (I/Q = 20+) M4

not covered -

H5 (I/Q = 20+) M6 ?

nil M2

not covered -

H8 (I/Q = 20*) M5

weak

H10 (I/Q = 4)

nil

H4 ? (I/t^ 6)

not covered magnetic low

5.

Geological Correlation

d.d.h. - 47 feet massive and diss. sulfides

graphite- sulfide- carbonate intersection (48 feet)

NORANDA hole N66 ?

-

25 feet massive sulfides

-

-

multiple mineralized bands

-

mixed sulfides

-

-

-

M. W. BARTLEY AND ASSOCIATES LTD.

Page 7: RPT ON THE GEOPH OF THE POCKET POND PROP

KENORA MINING WV.

ECEIVEOEr " ST?

PHOIMTARlO

THE MINING ACT REPORT OF WORK

' quired for **ch typ* of work to b* recorded.

To the Recorder of ..........K^orft........... .......... ........... ........... ........................... .............Mining Division

..........................................T-452......................Miner's Licence

.J?or4er..cj.u*a.. toady.none of Recorded Holder

Post Office Address

B f* *YP? O* wock not before reported to be applied on the following contiguous claims VV^Xi^UT V\Tu3|p K\ . "Xo ft\

Claim No. Days Claim No. Days Claim No. Days

K.313927

K.J03928

5.3039Z9

UIUS23

All the work was i

.2Q..

.2Q..

.20..

.2Q..

.29...

.20...

performed an Mini

K.313945

K.313.9A6

K.3X3959

K..3U9.60

K..313961

K..3UL9&ng Claim (s) . ....

2a.. K..JL3963 -2CL-.

20... K.JU396i. 20...

?0 K 3im?li ?o

20.

20... ............. .......

.....ahavw...................................................................

READ CAREFULLY: THE FOLLOWING INFORMATION is REQUIRED BY THE MINING RECORDER.

For Manual Wark. Stripping or Opening up of Mines, Sinking Shafts or Other Actual Mining Operations - Names andaddresses of the men who performed the work and the dates and hours of their employment.For Diamond and other Cora Drilling - Footage. No. and angle of holes and diameter of core. Nome and address ofowner or operator of drill. Dotes when drilling wot done. Signed core log and sketch in duplicate.Far Compressed Air or Other Power Driven or Mechanical EquipmentType of drill or equipment. Names and addresses of men engaged in operating equipment and the dates and hours of

For Power Stripping - Type of equipment. Name and address of owner or operator. Amount expended. Dotes on whichwark was dene. Proof of actual cost must be submitted within 30 days of recording.With each of the above types of work sketches are required to show the location and extent of the work in relationto the nearest claim post. In the case of diamond or other core drilling the sketch must be submitted in duplicate.Far Geological and Geophysical Survey - The names and addresses of men employed as well os dates. Type ofinstrument used in the case of geophysical survey. Reports and maps in duplicate must be filed with the Ministerwithin 60 days of recording.For Land Survey - the name and address of Ontario Land surveyor.

The Required Information is os Follows; (Attach a list if this space is insufficient)

900

2ae O

(In the case of geological and/or geophysical survey (s) where more than 18 claims are involved attach a schedule) J

o

Survey by: Joe Hodge, K.R. #L, Devlin, Ontario (Party Chief). June 1972. iInstrument: Crone Radem *~Supervision by: M.W. Bartley 6 Associates Ltd., Thunder Bay (P), Ontario. -

Data fW fi *x~ ^**^ ^j-^^^y• •••••••••••* *e** ^*- **|"*~* f **t " *** **** ••••••••••••••••••••••••*

Signature of Recorded Holder or Agent _____M. VI. Bartley tt Associates Ltd.

The Mining Act Certificate Verifying Report of Work

(Post Office Address)hereby certify:

1. That l have a personal and intimate knowledge of the facts set forth in the report of work annexed h to, having performed the work or witnessed same during and/or after its completion.

2. That the annexed report is true.nrmvwvu iw|m*i i* nw. m

.27............19 .72.......................................^..\.CT....Sioncrtuit

M.W. Bartley 6 Associates Ltd.

Page 8: RPT ON THE GEOPH OF THE POCKET POND PROP

File.

b, (kC

GEOPHYSICAL - GEOLOGICAL - GEOCHEMICAL TECHNICAL DATA STATEMENT

TO BE ATTACHED AS AN APPENDIX TO TECHNICAL REPORTFACTS SHOWN HERE NEED NOT BE REPEATED IN REPORT

TECHNICAL REPORT MUST CONTAIN INTERPRETATION, CONCLUSIONS ETC.

RECEIVED

F r-. 26 1973

Type of Survey___

Township or Area___Hglk"' 1''k TVp,——————————————————— Claim holder(s) _____Bnrrityr Git.ies Ready Mi y Cement Ltd.

____ Frvr*t. Frances. Qnt.arin.——^^^^-^^^^^^

Author of Rppnrt M. W . Rar*lgy_________________Address____________?31 AH-.rniT- St.., Thiinftey Ray (P)^ Ont.

Mav 1Q7? -Covering Dates i

Total Miles of Line cut.(linccutting to office)

+ f l.?5 mi.

SPECIAL PROVISIONS CREDITS REQUESTED

ENTER 40 days (includes line cutting) for first survey.

ENTER 20 days for each additional survey using same grid.

Geophysical

—Electromagnetic.

—Magnetometer——

DAYS per claim

-Other.

Geological.

Geochemical.

AIRBORNE CREDITS (Special provision credits do not apply to airborne surveys)

Magnetometer. .Electromagnetic. . Radiometric(enter days per claim)

HATR- Den. ?7 f lQ79 Sir.N ATI TP F-

PROJECTS SECTION Res. Geol.^^—^^ Qualifications.

Previous Surveys

Checked by. .date.

GEOLOGICAL BRANCH.

Approved by- -date.

GEOLOGICAL BRANCH.

Approved by. -date.

MINING CLAIMS TRAVERSED List numerically

ClC 313927^.••••^^tr*******^^*yij^*i i i i if 1 11111 i i i 111 i(prefix)- 7ft (niW*er) v.

K 313929

K ^13230. B * * * * a r VWf***^* m f *

Y2-~K 313933

K 313934

•^••••••*^TMV**^fcj^*a***a*************'****

.JK...3m63l

C O'J'.J'.c

TOTAL CLAIMS 13

Page 9: RPT ON THE GEOPH OF THE POCKET POND PROP

Show instrument technical data in each space for type of survey submitted or indicate "not applicable"

GEOPHYSICAL TECHNICAL DATA

GROUND SURVEYS

Number of Stations _________ /*23 ___________________ Number of Readings

Station interval

Line spacingProfile scale or Contour intervals l** = SQ& ———-———-^——

(specify for each type of survey)

MAGNETIC

Instrument

Accuracy - Scale constant

Diurnal correction method

Base station location

ELECrRQMAGNETIC

Instrument ____________ McPhar VHEMCoil configuration ________ Hnri gont.al Loop

Coil separation __________ 7 DO

Accuracy _____________ 12a

Method: CD Fixed transmitter d Shoot back SI In line d Parallel line

Frequency ^^————^^^^—^—^——————^^^^^^^—^^—^^^^—^—^——-^^^^^—^^^^^—-——^^^^^^^—(specify V.L.F. station)

Parameters measured ______ f i pi H gt.Tpng-r.Vi inphagp anri

GRAVITY

Instrument

Scale constant.

Corrections made.

Base station value and location.

Elevation accuracy__________________ INDUCED POLARIZATION - RESISTIVITY

Instrument_____________________Time domain_____________________________ Frequency domain.

Frequency———————————————————————————————— Range________

Electrode array——

Electrode spacing.

Type of electrode.

Page 10: RPT ON THE GEOPH OF THE POCKET POND PROP

File.

Jgu y}

(d UEU-c

GEOPHYSICAL - GEOLOGICAL - GEOCHEMICAL TECHNICAL DATA STATEMENT

TO BE ATTACHED AS AN APPENDIX TO TECHNICAL REPORTFACTS SHOWN HERE NEED NOT BE REPEATED IN REPORT

TECHNICAL REPORT MUST CONTAIN INTERPRETATION. CONCLUSIONS ETC.

Type of Survey.Township or Area HallHrlf

Claim holder(s)———Rorder ( rc f-

Fort Frances. Ont.aTin.

M. BartleAuthor of Repnrt

Address _____ 231 Arthur St., Thiinrim- Ray (P), Ont.aT-ir..

Covering Dates of Survey-

Total Miles of Line cut—

May 1972 - December 1972(linccutting to office)

9. S 4- (l.?. 1) mi. baseline)

SPECIAL PROVISIONS CREDITS REQUESTED

ENTER 40 days (includes line cutting) for first survey.

ENTER 20 days for each additional survey using same grid.

Geophysical

—Electromagnctic.

—Magnetometer-—

—Radiometric——

—Other—.——^

DAYS per claim

LO

Geological.

Geochemical.

AIRBORNE CREDITS (Special provision credits do not apply to airborne surveys)

Magnetometer. .Electromagnetic. . Radiometric(enter days per claim)

HATF- n^n. 37, 197-? SIGNATURE:—^!— - '- Alll

PROJECTS SECTION Res. Geol. ———^—— Qualifications.Previous Surveys

by. .date.

r.Fomoir.Ai. BRANCH

by. -date.

GEOLOGICAL BRANCH.

Approved by. -date.

MINING CLAIMS TRAVERSEDList numerically

CTlosaS^(prefix) ——— (number)

...............JL..31322&.........................

K -ms^ ^ C'""""

K 313933..... .....................'"CI

K 313^34

K 313945*^r\s^^^

...............K...313246.........................

...............K...313252.........................

...............^....3132,6^........................

..............K...313161........................K 313962

K 313963

r

K 313964^ 1

K 314024

.. ......,..........................±.....U-r.l 1 0, C- ^-f.

C-^'-J-.r-l/ikl ^ Crt^ \

iC

IL+

'i' ^^^:.i.....j..^..:.^::.rjr.........l.......-r j*::. c i ^- 3 /^........................................; .................

~ — "~^ """S i 1 ^ ^J/j i •''"i ; ' i r

T OTAI CI AIMS 15

\

sS88

CV

.H

IV

i.^

•w

Page 11: RPT ON THE GEOPH OF THE POCKET POND PROP

Show instrument technical data in each space for type of survey submitted or indicate "not applicable*

GEOPHYSICAL TECHNICAL DATA

GROUND SURVEYS

Number of Stations—

Station interval____

Line spacing——————

570 .Number of Readings100* (50* fnT-MX)*

Profile scale or Contour intervals. c.i. - looo y(specify for cadi type of survey)

MAGNETIC

Instrument

Accuracy - Scale constant

Diurnal correction methodRase station Inratinn

Sharpe A-^

20 y /scale div.

T*ennrMipat.T on of has** .i^. -t~— i ~2Jd^-f-^^-^ tf^ti-A v^'/i-^

1 ^-KX)E, 1+OOS

ELECTROMAGNETIC

Instrument________

Coil configuration.

Coil separation——

Accuracy^—--^—. Method:

Frequency^^-^—

CZI Fixed transmitter O Shoot back O Inline d Parallel line

(specify V.L.F. station)

Parameters measured. GRAVITY

Instrument______

Scale constant.

Corrections made-

Base station value and location.

Elevation accuracy.LXDUCED POLARIZATION

Instrument——-^—^—^——

RESISTIVITY

Time domain.

Frequency——

Power____

Frequency domain.

. Range^.^^—^^-—

Electrode array

Electrode spacing.

Type of electrode.

Page 12: RPT ON THE GEOPH OF THE POCKET POND PROP

Fii. ^//s-yGEOPHYSICAL - GEOLOGICAL - GEOCHEMICAL

TECHNICAL DATA STATEMENT RECEIVED

OFFICE USE ONLY

TO BE ATTACHED AS AN APPENDIX TO TECHNICAL REPORT ft- d Z * 3 ' FACTS SHOWN HERE NEED NOT BE REPEATED IN REPORT

TECHNICAL REPORT MUST CONTAIN INTERPRETATION. CONCLUSIONS ETC. F.?- cT'ON^

Typp "f Survey Electromagnetic (VUF")

Township or A"M Halkirk Twp.*"laim h"M*T(s) Border Cities Ready Mi ir Cement. T/Krt .

Fort Frances^ Ontario.

Amh^r "f tt"p"n M- w- BartleyAHHrecc 231 Arthur St., Thunder Bay (P\ Ontario-Covering Dates of Survey May 1972 - December 1972

(linecutting to office) T^l Milocnf I.int-rnt 9-5 + ( l-PS mi- baseline)

SPECIAL PROVISIONS DAYSCREDITS REQUESTED r;POphysir,, ""

\\ ~* l VA4-Electromagnetic .20 .ENTER 40 davs (includesv ' line cutting) for first Magnetometer —————————survey. —Radiometric —————————— ENTFR 20 days for each -Otheradditional survey using n^l,,ai™lsame grid.

Geotherm ra 1 .

AIRBORNE CREDITS (Special provision credits do not apply to airborne surveys)

Magnptom'' t*'r F.|i"rtrorr|apnptir RnHinmetrir(enter days per claim) ^ —

nATF.- Dec. 27. 1972 SIGN ATI MI F- f . fJ . 1 e^J^-oJi^^^M.l(^ut ^r^fe^fe"^^. .Lt^

PROJECTS SECTIONRes Geol Oiuilifiratmn.: b3..3fc//

! \~^Prfvjoiis Siirvpy* 1— ' ^

Cber\crt\ hv rfatp

OFOinr.irAi. RRANPH

ApprovpH hy datp

GKntnr.irAi RKANPH

Approver] hv H^t^

MINING CLAIMS TRAVERSED List numerically

...................du-^iaaa^j...................!..(prefix) ~ ~- | (nuiofKf).fc ^

K OT Tooo "1 I JifcQ * **

jc 313930K 3330^

K 31^/fc

....................K...3.13.9.45.........................

(jr 313946^

....................JK...313.9^9.........................

....................JB:...3^6Q........................

K 313961

J8L 313.962 . .

K 313963

K 313364

,...................K...31AP^........................

lOo'C .c \V-to/f^.-'-J.^x.^.V

r -r- j - " - o l — "? x^— x

| X? ~^G J ~ :|^-1-?,

— l o-S H^y/D r . ^ ~~( :rt

TOTAI CLAIMS 15 ^

5

M

io3

V1

v\

Page 13: RPT ON THE GEOPH OF THE POCKET POND PROP

Show instrument technical data in each space for type of survey submitted or indicate "not applicable"

GEOPHYSICAL TECHNICAL DATA

GROUND SURVEYS

Number of Stations______9 08_____________________Number of Readings.

Station interval__________5Q feet————————————————————————————————

Line spacing___________A.QQ feet

Profile scale or Contour intervals____l" -- LO—(specify for each type of survey)

MAGNETIC

Instrument .—^————^^^^^—————^^^—^——^^—^^———Accuracy - Scale constant—

Diurnal correction method.

Base station location———.

ELECTROMAGNETIC

Instrument___________Onng

Coil configuration.

Coil separation ——o

Accuracy____________l

Method: 03 Fixed transmitter d Shoot back d Inline d Parallel line

Frequency___________Seattle Waghingt.on (Vlf),^^——-^^—^———^^-————^^^^—^————-^^(specify V.L.F. station)

Parameters measured____dip angle - degrees_________________________________GRAVITY

Instrument________________________________________________________________

Scale constant____________________________________________________________Corrections made.

Base station value and location.

Elevation accuracy———^^——^—^^——^— INDUCED POLARIZATION - RESISTIVITY

Instrument——^—^^—.^^—.———^.^————-

Time domain_____________________________ Frequency domain.

Frequency_______________________________ Range———^—^—

Power_______________________________________________Electrode array——

Electrode spacing.

Type of electrode.

Page 14: RPT ON THE GEOPH OF THE POCKET POND PROP

i r

THE TOWNSHIPS' . OF

HALKIRK, 8 FARRINGTON

DISTRICT OF RAINY RIVER . 4

KENORAMINING DIVISION ,*

SCALE:HNCH*40CHAHSte

V

• I40TI 1314081 1*14011 1140*6

LEGEND|it(4i 1111*44. .-L....

PATENTED LANJ) CROWN LAND 8AUE LEASES i LOCATED LAND LICENSE OF OCCUPATION MINING RIGHTS ONLY SURFACE RIGHT! ONLY ROADSIMPROVED ROADS KING'S HIGHWAYS RAILWAYS POWER LINES MARSH ON MUM

1IIWO J li MM tilt**

—.-—i————- ~-— — "T

QEODETIC 8TATI

400"r*v'*rvotion to Dtpt. of L.fn F

Flooded land ihovn thu*:J4J40Z l4|M

All Ulood* IQ Rt^V tqk* wltftilroiip from •taking undtr Ste. 3-9 Sub M Minln4 Act .

__ __________ i^ ^ t___\ ___ ^"'T

WitlHII fl Mf fi IfOftl

4) of tht Mining Act ( R 8 o larojf FIU O^o

4ii l*ti* 11/10 7 Tt

4*ZTf 1492TS Il4*tr* S4MIO

MINIMA IAM04DATE OF ISSUCCHAPPIE

180.'IMO KktI72XT*

MAR l 1973

MINIITHY OF NATURAL

PLAN NO.-M.208ONTARIO

DEPARTMINT OP MIMftr AND NORTHERN AffMRt f

seciiNc:ee47 s n sa WATTEN

Page 15: RPT ON THE GEOPH OF THE POCKET POND PROP

rf- - *

THE TOWNSHiaOF "

Obikoba Lake Area (M.9 87 615

-^

ATTEDSTRltT OF

RAINY RIVER

MINING

.LEGENDWTEWTED ^ LAN47

SALE•^LEASESi *.^

LICENSE OF OCOfPATfON FHGHTS.

SURf^CE plOHTS OWLY^;ROADSIMPROVED ROA06

334633 j 302751 .

\tt ~**.*--3 "8vyL^L'-S)! i^StK^/Jm X

. 7 3*4*33 ' \ ~ \^-' j^?" 314119 3 i4*l4V.

Jlroui^t At4DC'. Surface Right* R

LJnwflercao Ar* jH-{|ectt*am fh- Best Inf

^tet Sj Consult

9v.' Off

Plan Qt Land* ft'. For**t*

ttWRItf- T^ *

HSR

- - --'-^.

23 22

- -na

//vr- V r

-rii .*- ^^ ,^ ^^ JS*

Sondpoint IslancLPROVINCIAL

S, A-.ONTARIO

NTMiNT Of iMiitS tORTHEW A

52CIINE***/ 2.1)59 *ATT9I

Page 16: RPT ON THE GEOPH OF THE POCKET POND PROP

313 W

RAINEY/ARMSTRONG PROPE RTY, 8 WATTENHALKIRK RIVER DISTRICT

**" K 3/3964 ,

/\RH2 f" S l/-*. X

R-13

^p*^^^/

I^?^*^B^P

R-14A^l:..

Nj~

f\"

R-ll XTO HIGHWAY NO M

MAP SYMBOLS

E M. PROFILE SCALE

l INCH ^ 4O e DIP ANGLE

( l ) INSTRUMENT usco. CRONE RAOEM. TUMEO TO THE

SEATTLE. WASHINGTON. STATION'S FREQUENCY.

(2) SURVEY CONDUCTED av J. HODGE DURING APRIL. 1972.

ia 'f for MI

WET SWAMP

GRAVEL ROAD

CLAM POST ( LOCATED, MFERREO )

\

MWBARTLEY AND ASSOCIATESTHUNDER BAY, ONTARIO

fc.

ARMSTRONG PROJECT

ELECTROMAGNETIC SURVEY

REVISIONS

Ntt

1

2

DATE BY

DRAWN BY- E. GROOTENBOER

DATE: MAY, 1972

SCALE t 1 INCH * ZOO FEET

DRAWING NOu A- 1K J^\ . f rtA'^t-L J.^^y- ' z,.,^.

2.1159 VATT9I 220 j "—-- x.

Page 17: RPT ON THE GEOPH OF THE POCKET POND PROP

ARMSTRON PROPE RT Y, HALKIRK a WATTEN T W PS RAINY RIVER DISTRICT

f \\ ••f ' If

MAP SYMBOLSBASE LINE

PICKET UNE

EM STXnON WITH W-PHASE AND QUADRATURE READMGS M %

CONDUCTOR AXIS

CREEK

WET

GRAVEL ROAD

NOTE(l) INSTRUMENT USED, He PH Aft V HEM UNIT ,

NORMAL HELD STRENGTH, RANGE O —

FIELD STRENGTH, COIL SEPARATION ZOO*M VK BARTLEY AND ASSOCIATES

TNUMOER BAY, OMTARK)

(Z) SURVEY CONDUCTED BY J.HODGE DURING ARMSTRONG PROJECT

HORIZONTAL LOOP SURVEY

CLAW POST ( LOCATED, •t-90% O

PROFILE SCALE

Page 18: RPT ON THE GEOPH OF THE POCKET POND PROP

o o o

44 ft

o o4 40 IW

o o4

Oo4o

o o4 (D

o o4

o o4

o o4

o o4 o

Ui

o o4

o o4

tot

OO

wOo4-

O O

O M

O O4

Oo4

ARMSTRONG PROPE RTYHALKIRK a WATTEN TWPS., RAINEY RIVER DISTRICT

............. A\ -^

c K E

TO NIC HW AY MO. M

-~e -/..*4-* ^X.

BASE L INE

fi

L

MAP SYMBOLS

l*7S*

MAGNETIC CONTOU

CONTOUR OUTLININ

RELATIVE MAGNETIC INTENSITY THAN 47.OOO GAMMAS*

J RELATIVE MAGNETIC INTENSITY NEGATIVEWITH MAGNETIC INTENSITY M GAMMAS

.V NEGATIVE MAGNETIC INTENSITY

NOTE.

(l ) INSTRUMENT USED, SHARPE A-2 NAGNETOMETEN SENSITIVITY. 20 GAMMAS PER SCALE DIVISION RANGE. * T.OOO GAMMAS

(2) SURVEY CONDUCTED NY J. HODGE DURING APRIL. 1972.

CLAM POST c

MW BARTLEY AND ASSOCIATESTHUNDER DAY. ONTARIO

ARMSTRONG PROJECT

MAGNETICCONTOUR PLAN

CONTOUR INTERVAL LOOO***.

S

NO.

1

2

ORAM

DATE

SCAl

OHAIT•rr

REVISIONS

OATE

M DY: E.GN001

l: MAY, W7I

f: 1 INCH s 2

i i ivv ^'^^ 9f ™

? ^i.

DY

•ENDOER

00 FEET

k*^*J

V ______

l i