Rate analsis Chapter No. 10 Flooring)

Embed Size (px)

Citation preview

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    1/66

    CHAPTER NO. 10

    FLOORING

    i) Rates for all finished works include the removal of surplus debris, unused

    material and by products.material and by products.

    ii) For handling of all types of material for short lead including carriage upto

    3 chains (90m) nothing is to be paid as extra. Where handling and carriage

    involves an extra lead beyond 3 chains, (90m) carriage for whole of the distance

    should be paid

    DESCRIPTION OF ITEM

    1 Laying Muram flooring consisting of 1" (25m) layer of fine powdery or flakey variety of Muram

    laid over 6" (150mm) good hard layer of Muram spreaded over 9" (225mm) thick sub base

    comprising of hand packed rubble or broken bricks properly watered and rammed provided

    over well rammed earth

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 9" thick rubble or broken hard bricks 80.00 Cft 560.00 Per 100 Cft 448.00

    2 6" Hard Muram 55.00 Cft 520.00 Per 100 Cft 286.00

    3 1" Fine Powdery Muram 9.00 Cft. 550.00 Per 100 Cft 49.50

    Total 783.50

    Contractor's Profit & Overheads 20 Percent 156.70

    Total 940.20

    LABOUR

    Mason 0.50 No. 300.00 per day 150.00

    Coolies 3.00 Nos. 140.00 per day 420.00

    Bahishti 0.5 No. 160.00 Per day 80.00

    Total 650.00Sundries 10 Percent 65.00

    Total 715.00

    Contractor's Profit & Overheads 20 Percent 143.00

    Total 858.00

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 858.00 Say 858.00

    Labour Rate Per Sqm. Rs. 92.32 Say 92.30

    Composite Rate per 100 Sft. Rs. 1,798.20 Say 1798.20

    Composite Rate per Sqm. Rs. 193.49 Say 193.50

    Page 1

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    2/66

    DESCRIPTION OF ITEM

    2 Earth flooring consisting of 6" thick consolidated layer of moistured

    earth including ramming

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Earth (Loose measured) 50.00 Cft 150.00 Per 100 Cft 75.00

    Contractor's Profit & Overheads 20 Percent 15.00

    Total 90.00

    LABOUR

    Mason 0.125 No. 300.00 Per day 37.50

    Coolly 1.00 No. 140.00 Per day 140.00

    Bahishti 0.25 No. 160.00 Pay day 40.00

    Total 217.50

    Sundries 10 Percent 21.75

    Total 239.25

    Contractor's Profit & Overheads 20 Percent 47.85

    Total 287.10

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 287.10 Say 287.10

    Labour Rate Per Sqm. Rs. 30.89 Say 30.90

    Composite Rate per 100 Sft. Rs. 377.10 Say 377.10

    Composite Rate per Sqm. Rs. 40.58 Say 40.60

    Page 2

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    3/66

    DESCRIPTION OF ITEM

    3 Providing, laying, watering and ramming brick ballast 1" - 2" gauge mixed with

    25% sand, for floor foundation, complete in all respects.

    Detail Unit Rate Per 100 Cft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Brick Ballast 100.00 Cft 560.00 Per 100 Cft 560.00

    2 Sand 25.00 Cft 350.00 Per 100 Cft 87.50

    Total 647.50

    Contractor's Profit & Overheads 20 Percent 129.50

    Total 777.00

    LABOUR

    Coolies 3.10 No. 140.00 per day 434.00

    Bahishti 0.10 No. 160.00 Per day 16.00

    Total 450.00

    Sundries 10 Percent 45.00

    Total 495.00

    Contractor's Profit & Overheads 20 Percent 99.00

    Total 594.00

    ITEM RATE

    Labour Rate Per 100 Cft. Rs. 594.00 Say 594.00

    Labour Rate Per Cum Rs. 209.80 Say 209.80

    Composite Rate per 100 Cft. Rs. 1,371.00 Say 1371.00

    Composite Rate per Cum. Rs. 484.24 Say 484.25

    Page 3

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    4/66

    4 Mud Flooring

    DESCRIPTION OF ITEM

    Mud flooring consisting of 6" thick consolidated layer of moistured earth and

    finished off with 1" mud plaster and gobri leeping.

    Detail Unit Rate Per 100 Sft.

    RateQty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Earth for filling 50.00 Cft 150.00 Per 100 Cft 75.00

    2 Earth for Mud Plaster 10.00 Cft 150.00 Per 100 Cft 15.00

    3 Bhoosa 34 lbs (15.44 Kg.) 2.00 Kg. 30.88

    4 Fine Clay for Gobri Leeping 0.75 Cft. 150.00 Per 100 Cft 1.13

    5 Cow Dung 0.75 Cft. (5.44 Kg.) 50.00 Per 100 Kg. 2.72

    Total 124.73

    Contractor's Profit & Overheads 20 Percent 24.95

    Total 149.67

    LABOUR

    Mason 0.25 No. 300.00 Per day 75.00

    Coolies 2.00 No. 140.00 Per day 280.00

    Bahishti 0.25 No. 160.00 Per day 40.00

    Total 395.00Sundries 10 Percent 39.50

    Total 434.50

    Contractor's Profit & Overheads 20 Percent 86.90

    Total 521.40

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 521.40 Say 521.40

    Labour Rate Per Sqm. Rs. 56.10 Say 56.10

    Composite Rate per 100 Sft. Rs. 671.07 Say 671.05

    Composite Rate per Sqm. Rs. 72.21 Say 72.20

    Page 4

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    5/66

    5 Brick Flooring

    DESCRIPTION OF ITEM

    Dry brick paving laid flat, sand grouted including preparation of bed by watering, ramming and

    bringing the same to proper camber by " mud plaster

    Detail Unit Rate Per 100 Sft.

    RateQty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Brick 9" 350 Nos. 1200.00 Per 1000 No. 420.00

    2 Sand 5 Cft. 350.00 Per 100 Cft 17.50

    3 " Mud Plaster (Good earth) 6 Cft. 150.00 Per 100 Cft 9.00

    Total 446.50

    Contractor's Profit & Overheads 20 Percent 89.30

    Total 535.80

    LABOUR FOR 125 SFT.

    Mason 0.50 No. 300.00 Per day 150.00

    Coolies 1.00 No. 140.00 Per day 140.00

    Bahishti 0.05 No. 160.00 Per day 8.00

    Total 298.00

    Sundries 10 Percent 29.80

    Total 327.80Contractor's Profit & Overheads 20 Percent 65.56

    Total 393.36

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 314.69 Say 314.70

    Labour Rate Per Sqm. Rs. 33.86 Say 33.85

    Composite Rate per 100 Sft. Rs. 850.49 Say 850.50

    Composite Rate per Sqm. Rs. 91.51 Say 91.50

    Page 5

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    6/66

    DESCRIPTION OF ITEM

    6 Dry brick on edge paving sand grouted including preparation of bed by watering,

    ramming and bringing the same to proper camber by thick mud plaster

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Brick 9" (including wastage) 525 Nos. 1200.00 Per 1000 Nos. 630.00

    2 " thick mud plaster (good earth) 6 Cft. 150.00 Per 100 Cft 9.00

    2 Sand 6 Cft. 350.00 Per 100 Cft 21.00

    Total 660.00

    Contractor's Profit & Overheads 20 Percent 132.00

    Total 792.00

    LABOUR

    Mason 0.67 No. 300.00 Per day 201.00

    Coolies 1.50 No. 140.00 Per day 210.00

    Bahishti 0.08 No. 160.00 Per day 12.80

    Total 423.80

    Sundries 10 Percent 42.38

    Total 466.18

    Contractor's Profit & Overheads 20 Percent 93.24Total 559.42

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 559.42 Say 559.40

    Labour Rate Per Sqm. Rs. 60.19 Say 60.20

    Composite Rate per 100 Sft. Rs. 1,351.42 Say 1351.40

    Composite Rate per Sqm. Rs. 145.41 Say 145.40

    Page 6

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    7/66

    DESCRIPTION OF ITEM

    7 Grouting 4" dry brick work with cement mortar ratio 1:5

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement 0.70 Bag 230.00 Per Bag 161.00

    2 Sand 4.50 Cft. 350.00 Per 100 Cft 15.75

    Total 176.75

    Contractor's Profit & Overheads 20 Percent 35.35

    Total 212.10

    LABOUR FOR 125 SFT

    Mason 0.50 No. 300.00 Per day 150.00

    Coolies (Unskilled) 0.50 No. 140.00 Per day 70.00

    Bahishti 0.50 No. 160.00 Per day 80.00

    Total 300.00

    Sundries 10 Percent 30.00

    Total 330.00

    Contractor's Profit & Overheads 20 Percent 66.00

    Total 396.00

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 316.80 Say 316.80

    Labour Rate Per Sqm. Rs. 34.09 Say 34.10

    Composite Rate per 100 Sft. Rs. 528.90 Say 528.90

    Composite Rate per Sqm. Rs. 56.91 Say 56.90

    Page 7

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    8/66

    DESCRIPTION OF ITEM

    8 Flat brick flooring laid in 1:6 cement mortar over a bed of3/4" thick cement mortar 1:6

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Bricks 9" size 350 Nos. 1200.00 Per 1000 No. 420.00

    2 Cement (for laying) 0.50 Bag 230.00 Per Bag 115.00

    3 Cement (for bedding mortar) 0.80 Bag 230.00 Per Bag 184.00

    4 Sand for laying 4.00 Cft. 350.00 Per 100 Cft 14.00

    5 Sand for bedding mortar 6.00 Cft. 350.00 Per 100 Cft 21.00

    Total 754.00

    Contractor's Profit & Overheads 20 Percent 150.80

    Total 904.80

    LABOUR FOR 125 SFT.

    Mason 0.75 No. 300.00 Per day 225.00

    Coolies 1.50 No. 140.00 Per day 210.00

    Bahishti 0.50 No. 160.00 Per day 80.00

    Total 515.00

    Sundries 10 Percent 51.50

    Total 566.50

    Contractor's Profit & Overheads 20 Percent 113.30Total 679.80

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 543.84 Say 543.85

    Labour Rate Per Sqm. Rs. 58.52 Say 58.50

    Composite Rate per 100 Sft. Rs. 1,448.64 Say 1448.65

    Composite Rate per Sqm. Rs. 155.87 Say 155.85

    Page 8

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    9/66

    DESCRIPTION OF ITEM

    9 Brick on edge flooring laid in 1:6 cement mortar over a bed of 3/4" thick cement mortar (1:6)

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Bricks 9" size 525 Nos. 1200.00 Per 1000 No. 630.00

    2 Cement for laying 0.85 Bag 230.00 Per Bag 195.50

    3 Cement for bedding mortar 0.88 Bag 230.00 Per Bag 202.40

    4 Sand for laying 7.00 Cft. 350.00 Per 100 Cft 24.50

    5 Sand for bedding mortar 6.00 Cft. 350.00 Per 100 Cft 21.00

    Total 1,073.40

    Contractor's Profit & Overheads 20 Percent 214.68

    Total 1,288.08

    LABOUR FOR 125 Sft.

    Mason 1.00 No. 300.00 Per day 300.00

    Coolies 2.00 No. 140.00 Per day 280.00

    Bahishti 0.50 No. 160.00 Per day 80.00

    Total 660.00

    Sundries 10 Percent 66.00

    Total 726.00

    Contractor's Profit & Overheads 20 Percent 145.20Total 871.20

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 696.96 Say 696.95

    Labour Rate Per Sqm. Rs. 74.99 Say 75.00

    Composite Rate per 100 Sft. Rs. 1,985.04 Say 1985.05

    Composite Rate per Sqm. Rs. 213.59 Say 213.60

    Page 9

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    10/66

    DESCRIPTION OF ITEM

    10 Brick tiles (12"x6"x2") laid in (1:6) cement mortar, over a bed of 3/4" thick cement mortar (1:6)

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Tiles 12"x6"x2" 210 Nos. 1250.00 Per 1000 No. 262.50

    2 Cement 1.10 Bag 230.00 Bag 253.00

    4 Sand 8.00 Cft. 350.00 Per 100 Cft 28.00

    Total 543.50

    Contractor's Profit & Overheads 20 Percent 108.70

    Total 652.20

    LABOUR

    Mason 0.75 No. 300.00 Per day 225.00

    Coolies 1.50 No. 140.00 Per day 210.00

    Bahishti 0.50 No. 160.00 Per day 80.00

    Total 515.00

    Sundries 10 Percent 51.50

    Total 566.50

    Contractor's Profit & Overheads 20 Percent 113.30

    Total 679.80

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 679.80 Say 679.80

    Labour Rate Per Sqm. Rs. 73.15 Say 73.15

    Composite Rate per 100 Sft. Rs. 1,332.00 Say 1332.00

    Composite Rate per Sqm. Rs. 143.32 Say 143.30

    Page 10

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    11/66

    DESCRIPTION OF ITEM

    11 Brick tiles (9" x 4" x 1") laid flat in 1:3 cement mortar over a bed of 3/4" thick cement mortar (1:6)

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Tiles 9"x4"x1" 350 Nos. 1050.00 Per 1000 No. 367.50

    2 Cement 1.40 Bag 230.00 Bag 322.00

    4 Sand 12.00 Cft. 350.00 Per 100 Cft 42.00

    Total 731.50

    Contractor's Profit & Overheads 20 Percent 146.30

    Total 877.80

    LABOUR

    Mason 1.00 No. 300.00 Per day 300.00

    Coolies (Unskilled) 1.50 No. 140.00 Per day 210.00

    Bahishti 0.50 No. 160.00 Per day 80.00

    Total 590.00

    Sundries 10 Percent 59.00

    Total 649.00

    Contractor's Profit & Overheads 20 Percent 129.80

    Total 778.80

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 778.80 Say 778.80

    Labour Rate Per Sqm. Rs. 83.80 Say 83.80

    Composite Rate per 100 Sft. Rs. 1,656.60 Say 1656.60

    Composite Rate per Sqm. Rs. 178.25 Say 178.25

    Page 11

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    12/66

    DESCRIPTION OF ITEM

    12 Cement tiles (8"x8"x") laid fiat in 1:2 cement mortar over 3/4" thick bed of cement mortar 1:2

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement tiles (8"x8"x3/4") 240 Nos. 7.00 Per No. 1,680.00

    2 Cement 1.87 Bags 230.00 Per Bag 430.10

    4 Sand 4.70 Cft. 350.00 Per 100 Cft 16.45

    Total 2,126.55

    Contractor's Profit & Overheads 20 Percent 425.31

    Total 2,551.86

    LABOUR FOR 200 SFT.

    Mason 1.25 No. 300.00 Per day 375.00

    Coolies (Unskilled) 2.00 No. 140.00 Per day 280.00

    Bahishti 0.34 No. 160.00 Per day 54.40

    Total 709.40

    Sundries 10 Percent 70.94

    Total 780.34

    Contractor's Profit & Overheads 20 Percent 156.07

    Total 936.41

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 468.20 Say 468.20

    Labour Rate Per Sqm. Rs. 50.38 Say 50.40

    Composite Rate per 100 Sft. Rs. 3,020.06 Say 3020.05

    Composite Rate per Sqm. Rs. 324.96 Say 324.95

    Page 12

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    13/66

    DESCRIPTION OF ITEM

    13 Cement concrete tiles laid in 1:2 cement mortar over 3/4" thick bed of cement mortar 1:2

    a) 12" x 12" x 1"

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement concrete tiles (1" thick) 105 Nos 11.00 Each 1,155.00

    2 Cement for bedding and laying of 1:2 ratio 1.85 Bags 230.00 Per Bag 425.50

    4 Sand 4.67 Cft. 350.00 Per 100 Cft 16.35

    Total 1,596.85

    Contractor's Profit & Overheads 20 Percent 319.37

    Total 1,916.21

    LABOUR FOR 200 SFT

    Mason 1.25 No. 300.00 Per day 375.00

    Coolies 2.00 No. 140.00 Per day 280.00

    Bahishti 0.34 No. 160.00 Per day 54.40

    Total 709.40

    Sundries 10 Percent 70.94

    Total 780.34

    Contractor's Profit & Overheads 20 Percent 156.07Total 936.41

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 468.20 Say 468.20

    Labour Rate Per Sqm. Rs. 50.38 Say 50.40

    Composite Rate per 100 Sft. Rs. 2,384.42 Say 2384.40

    Composite Rate per Sqm. Rs. 256.56 Say 256.55

    Page 13

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    14/66

    b) 9" x 9" x 3/4"

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement concrete tiles 186 Nos 8.00 Each 1,488.002 Cement for bedding and laying of 1:2 1.86 Bags 230.00 Per Bag 427.80

    4 Sand 4.67 Cft. 350.00 Per 100 Cft 16.35

    Total 1,932.15

    Contractor's Profit & Overheads 20 Percent 386.43

    Total 2,318.57

    LABOUR FOR 200 SFT.

    Mason 1.25 No. 300.00 Per day 375.00

    Coolies 2.00 No. 140.00 Per day 280.00

    Bahishti 0.34 No. 160.00 Per day 54.40

    Total 709.40

    Sundries 10 Percent 70.94

    Total 780.34

    Contractor's Profit & Overheads 20 Percent 156.07

    Total 936.41

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 468.20 Say 468.20

    Labour Rate Per Sqm. Rs. 50.38 Say 50.40

    Composite Rate per 100 Sft. Rs. 2,786.78 Say 2786.80

    Composite Rate per Sqm. Rs. 299.86 Say 299.85

    Page 14

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    15/66

    c) 6" x 6" x 3/4"

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement concrete tiles 420 Nos 6.50 Each 2,730.002 Cement for bedding and laying of 1:2 ratio 1.90 Bags 230.00 Per Bag 437.00

    4 Sand 4.74 Cft. 350.00 Per 100 Cft 16.59

    Total 3,183.59

    Contractor's Profit & Overheads 20 Percent 636.72

    Total 3,820.31

    LABOUR FOR 200 SFT.

    Mason 1.25 No. 300.00 Per day 375.00

    Coolies 2.00 No. 140.00 Per day 280.00

    Bahishti 0.34 No. 160.00 Per day 54.40

    Total 709.40

    Sundries 10 Percent 70.94

    Total 780.34

    Contractor's Profit & Overheads 20 Percent 156.07

    Total 936.41

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 468.20 Say 468.20

    Labour Rate Per Sqm. Rs. 50.38 Say 50.40

    Composite Rate per 100 Sft. Rs. 4,288.51 Say 4288.50

    Composite Rate per Sqm. Rs. 461.44 Say 461.45

    Page 15

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    16/66

    DESCRIPTION OF ITEM

    14 Coloured cement tiles (8"x8"3/4") of approved dark shade laid flat in 1:2 cement

    mortar over 3/4" bedding mortar of 1:2

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Tiles 240 Each 7.00 Each 1,680.00

    2 Cement 1.87 Bag 230.00 Per Bag 430.10

    3 Sand 4.70 Cft. 350.00 Per 100 Cft 16.45

    4 Pigment 0.67 Lbs (0.30 Kg.) 70.00 Per Kg. 21.00

    Total 2,147.55

    Contractor's Profit & Overheads 20 Percent 429.51

    Total 2,577.06

    LABOUR FOR 200 SFT.

    Mason 1.25 No. 300.00 Per day 375.00

    Coolies 2.00 No. 140.00 Per day 280.00

    Bahishti 0.34 No. 160.00 Per day 54.40

    Total 709.40

    Sundries 10 Percent 70.94

    Total 780.34

    Contractor's Profit & Overheads 20 Percent 156.07Total 936.41

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 468.20 Say 468.20

    Labour Rate Per Sqm. Rs. 50.38 Say 50.40

    Composite Rate per 100 Sft. Rs. 3,045.26 Say 3045.25

    Composite Rate per Sqm. Rs. 327.67 Say 327.65

    Page 16

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    17/66

    DESCRIPTION OF ITEM

    15 Providing and laying topping of cement concrete (1:2:4) including

    surface finishing and dividing into panels.

    a) 1" (25mm) Thick

    Detail Unit Rate Per 100 Sft.

    RateQty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement 1.50 Bags 230.00 Per Bag 345.00

    2 Sand 3.70 Cft. 350.00 Per 100 Cft 12.95

    3 Shingle 7.40 Cft. 1000.00 Per 100 Cft 74.00

    4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 12.01

    Total 443.96

    Contractor's Profit & Overheads 20 Percent 88.79

    Total 532.75

    LABOUR

    Mason 1.00 No. 300.00 Per day 300.00

    Coolies 0.50 No. 140.00 Per day 70.00

    Bahishti 0.10 No. 160.00 Per day 16.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 461.00Sundries 10 Percent 46.10

    Total 507.10

    Contractor's Profit & Overheads 20 Percent 101.42

    Total 608.52

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 608.52 Say 608.50

    Labour Rate Per Sqm. Rs. 65.48 Say 65.50

    Composite Rate per 100 Sft. Rs. 1,141.28 Say 1141.30

    Composite Rate per Sqm. Rs. 122.80 Say 122.80

    Page 17

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    18/66

    b) 1" (30mm) Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement 1.85 Bags 230.00 Per Bag 425.50

    2 Sand 4.60 Cft. 350.00 Per 100 Cft 16.10

    3 Shingle 9.20 Cft. 1000.00 Per 100 Cft 92.00

    4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 12.01

    Total 545.61

    Contractor's Profit & Overheads 20 Percent 109.12

    Total 654.73

    LABOUR

    Mason 1.00 No. 300.00 Per day 300.00

    Coolies 0.50 No. 140.00 Per day 70.00

    Bahishti 0.10 No. 160.00 Per day 16.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 461.00

    Sundries 10 Percent 46.10

    Total 507.10

    Contractor's Profit & Overheads 20 Percent 101.42

    Total 608.52

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 608.52 Say 608.50

    Labour Rate Per Sqm. Rs. 65.48 Say 65.50

    Composite Rate per 100 Sft. Rs. 1,263.25 Say 1263.25

    Composite Rate per Sqm. Rs. 135.93 Say 135.95

    Page 18

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    19/66

    c) 1" (40mm) Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement 2.20 Bags 230.00 Per Bag 506.002 Sand 5.50 Cft. 350.00 Per 100 Cft 19.25

    3 Shingle 11.00 Cft. 1000.00 Per 100 Cft 110.00

    4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 12.01

    Total 647.26

    Contractor's Profit & Overheads 20 Percent 129.45

    Total 776.71

    LABOUR

    Mason 1.00 No. 300.00 Per day 300.00

    Cooly (Unskilled) 1.00 No. 140.00 Per day 140.00

    Bahishti 0.15 No. 160.00 Per day 24.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 539.00

    Sundries 10 Percent 53.90

    Total 592.90

    Contractor's Profit & Overheads 20 Percent 118.58

    Total 711.48

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 711.48 Say 711.50

    Labour Rate Per Sqm. Rs. 76.56 Say 76.55

    Composite Rate per 100 Sft. Rs. 1,488.19 Say 1488.20

    Composite Rate per Sqm. Rs. 160.13 Say 160.15

    Page 19

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    20/66

    d) 13/4" (45mm) Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement 2.55 Bags 230.00 Per Bag 586.502 Sand 6.50 Cft. 350.00 Per 100 Cft 22.75

    3 Shingle 12.80 Cft. 1000.00 Per 100 Cft 128.00

    4 Form Work (Kail Wood) 0.040 Cft. 350.00 Per Cft. 14.00

    Total 751.25

    Contractor's Profit & Overheads 20 Percent 150.25

    Total 901.50

    LABOUR

    Mason 1.00 No. 300.00 Per day 300.00

    Cooly 1.00 No. 140.00 Per day 140.00

    Bahishti 0.15 No. 160.00 Per day 24.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 539.00

    Sundries 10 Percent 53.90

    Total 592.90

    Contractor's Profit & Overheads 20 Percent 118.58

    Total 711.48

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 711.48 Say 711.50

    Labour Rate Per Sqm. Rs. 76.56 Say 76.55

    Composite Rate per 100 Sft. Rs. 1,612.98 Say 1613.00

    Composite Rate per Sqm. Rs. 173.56 Say 173.55

    Page 20

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    21/66

    e) 2" (50mm) Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement 3.00 Bags 230.00 Per Bag 690.002 Sand 7.40 Cft. 350.00 Per 100 Cft 25.90

    3 Shingle 14.70 Cft. 1000.00 Per 100 Cft 147.00

    4 Form Work (Kail Wood) 0.040 Cft. 350.00 Per Cft. 14.00

    Total 876.90

    Contractor's Profit & Overheads 20 Percent 175.38

    Total 1,052.28

    LABOUR

    Mason 1.00 No. 300.00 Per day 300.00

    Cooly 1.50 No. 140.00 Per day 210.00

    Bahishti 0.20 No. 160.00 Per day 32.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 617.00

    Sundries 10 Percent 61.70

    Total 678.70

    Contractor's Profit & Overheads 20 Percent 135.74

    Total 814.44

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 814.44 Say 814.45

    Labour Rate Per Sqm. Rs. 87.63 Say 87.65

    Composite Rate per 100 Sft. Rs. 1,866.72 Say 1866.70

    Composite Rate per Sqm. Rs. 200.86 Say 200.85

    Page 21

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    22/66

    f) 2" (55mm) Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement 3.30 Bags 230.00 Per Bag 759.002 Sand 8.40 Cft. 350.00 Per 100 Cft 29.40

    3 Shingle 16.50 Cft. 1000.00 Per 100 Cft 165.00

    4 Form Work (Kail Wood) 0.046 Cft. 350.00 Per Cft. 16.00

    Total 969.40

    Contractor's Profit & Overheads 20 Percent 193.88

    Total 1,163.27

    LABOUR

    Mason 1.00 No. 300.00 Per day 300.00

    Cooly 1.60 No. 140.00 Per day 224.00

    Bahishti 0.20 No. 160.00 Per day 32.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 631.00

    Sundries 10 Percent 63.10

    Total 694.10

    Contractor's Profit & Overheads 20 Percent 138.82

    Total 832.92

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 832.92 Say 832.90

    Labour Rate Per Sqm. Rs. 89.62 Say 89.60

    Composite Rate per 100 Sft. Rs. 1,996.19 Say 1996.20

    Composite Rate per Sqm. Rs. 214.79 Say 214.80

    Page 22

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    23/66

    g) 2" (60mm) Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement 3.65 Bags 230.00 Per Bag 839.502 Sand 2.20 Cft. 350.00 Per 100 Cft 7.70

    3 Shingle 18.35 Cft. 1000.00 Per 100 Cft 183.50

    4 Form Work (Kail Wood) 0.051 Cft. 350.00 Per Cft. 18.00

    Total 1,048.70

    Contractor's Profit & Overheads 20 Percent 209.74

    Total 1,258.44

    LABOUR

    Mason 1.00 No. 300.00 Per day 300.00

    Cooly 2.00 No. 140.00 Per day 280.00

    Bahishti 0.25 No. 160.00 Per day 40.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 695.00

    Sundries 10 Percent 69.50

    Total 764.50

    Contractor's Profit & Overheads 20 Percent 152.90

    Total 917.40

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 917.40 Say 917.40

    Labour Rate Per Sqm. Rs. 98.71 Say 98.70

    Composite Rate per 100 Sft. Rs. 2,175.84 Say 2175.85

    Composite Rate per Sqm. Rs. 234.12 Say 234.10

    Page 23

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    24/66

    h) 2 3/4" (70mm) Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement 4.00 Bags 230.00 Per Bag 920.002 Sand 10.00 Cft. 350.00 Per 100 Cft 35.00

    3 Shingle 20.20 Cft. 1000.00 Per 100 Cft 202.00

    4 Form Work (Kail Wood) 0.051 Cft. 350.00 Per Cft. 18.00

    Total 1,175.00

    Contractor's Profit & Overheads 20 Percent 235.00

    Total 1,410.00

    LABOUR

    Mason 1.00 No. 300.00 Per day 300.00

    Cooly 2.00 No. 140.00 Per day 280.00

    Bahishti 0.25 No. 160.00 Per day 40.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 695.00

    Sundries 10 Percent 69.50

    Total 764.50

    Contractor's Profit & Overheads 20 Percent 152.90

    Total 917.40

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 917.40 Say 917.40

    Labour Rate Per Sqm. Rs. 98.71 Say 98.70

    Composite Rate per 100 Sft. Rs. 2,327.40 Say 2327.40

    Composite Rate per Sqm. Rs. 250.43 Say 250.45

    Page 24

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    25/66

    i) 3" (75mm) Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement 4.40 Bags 230.00 Per Bag 1,012.002 Sand 11.00 Cft. 350.00 Per 100 Cft 38.50

    3 Shingle 22.00 Cft. 1000.00 Per 100 Cft 220.00

    4 Form Work (Kail Wood) 0.057 Cft. 350.00 Per Cft. 20.02

    Total 1,290.52

    Contractor's Profit & Overheads 20 Percent 258.10

    Total 1,548.62

    LABOUR

    Mason 1.00 No. 300.00 Per day 300.00

    Cooly 2.00 No. 140.00 Per day 280.00

    Bahishti 0.25 No. 160.00 Per day 40.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 695.00

    Sundries 10 Percent 69.50

    Total 764.50

    Contractor's Profit & Overheads 20 Percent 152.90

    Total 917.40

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 917.40 Say 917.40

    Labour Rate Per Sqm. Rs. 98.71 Say 98.70

    Composite Rate per 100 Sft. Rs. 2,466.02 Say 2466.00

    Composite Rate per Sqm. Rs. 265.34 Say 265.35

    Page 25

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    26/66

    DESCRIPTION OF ITEM

    16 Providing and laying conglomerate flooring (two coat work) with top layer of " thick

    wearing surface, consisting of one part of cement and two parts of stone chips passing

    3/16" sieave, over bottom layer of cement concrete 1:3:6 including surface finishing and

    dividing in panels:-

    a) 1" (40mm) Thick

    Detail Unit Rate Per 100 Sft.Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    i) " Thick Topping

    1 Cement 1.25 Bags 230.00 Per Bag 287.50

    2 Sand 3.00 Cft. 350.00 Per 100 Cft 10.50

    ii) 1" Thick Bedding 1:3:6

    Cement 1.08 Bags 230.00 Per Bag 248.40

    Sand 3.83 Cft. 350.00 Per 100 Cft 13.41

    Shingle 7.67 Cft. 1000.00 Per 100 Cft 76.70

    Total 636.51

    Contractor's Profit & Overheads 20 Percent 127.30

    Total 763.81

    LABOUR

    i) " Thick Topping

    Mason 0.50 No. 300.00 Per day 150.00

    Cooly 0.25 No. 140.00 Per day 35.00

    Bahishti 0.05 No. 160.00 Per day 8.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    ii) 1" Thick Bedding 1:3:6

    Mason 0.80 No. 300.00 Per day 240.00

    Cooly 0.50 No. 140.00 Per day 70.00Bahishti 0.15 No. 160.00 Per day 24.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 677.00

    Sundries 10 Percent 67.70

    Total 744.70

    Contractor's Profit & Overheads 20 Percent 148.94

    Total 893.64

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 893.64 Say 893.65

    Labour Rate Per Sqm. Rs. 96.16 Say 96.15

    Composite Rate per 100 Sft. Rs. 1,657.45 Say 1657.45

    Composite Rate per Sqm. Rs. 178.34 Say 178.35

    Page 26

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    27/66

    b) 1 3/4" (45mm) Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    i) " Thick Topping

    1 Cement 1.25 Bags 230.00 Per Bag 287.50

    2 Sand 3.00 Cft. 350.00 Per 100 Cft 10.50

    ii) 1" Thick Bedding 1:3:6

    Cement 1.35 Bags 230.00 Per Bag 310.50

    Sand 4.06 Cft. 350.00 Per 100 Cft 14.21

    Shingle 8.12 Cft. 1000.00 Per 100 Cft 81.20

    Total 703.91

    Contractor's Profit & Overheads 20 Percent 140.78

    Total 844.69

    LABOUR

    i) " Thick Topping

    Mason 0.50 No. 300.00 Per day 150.00

    Cooly 0.25 No. 140.00 Per day 35.00Bahishti 0.05 No. 160.00 Per day 8.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    ii) 1" Thick Bedding 1:3:6

    Mason 0.80 No. 300.00 Per day 240.00

    Cooly 0.50 No. 140.00 Per day 70.00

    Bahishti 0.15 No. 160.00 Per day 24.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 677.00

    Sundries 10 Percent 67.70

    Total 744.70

    Contractor's Profit & Overheads 20 Percent 148.94

    Total 893.64

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 893.64 Say 893.65

    Labour Rate Per Sqm. Rs. 96.16 Say 96.15

    Composite Rate per 100 Sft. Rs. 1,738.33 Say 1738.35

    Composite Rate per Sqm. Rs. 187.04 Say 187.05

    Page 27

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    28/66

    c) 2" (50mm) Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    i) " Thick Topping

    1 Cement 1.25 Bags 230.00 Per Bag 287.50

    2 Sand 3.00 Cft. 350.00 Per 100 Cft 10.50

    ii) 1" Thick Bedding 1:3:6

    Cement 1.63 Bags 230.00 Per Bag 374.90

    Sand 5.75 Cft. 350.00 Per 100 Cft 20.13

    Shingle 11.50 Cft. 1000.00 Per 100 Cft 115.00

    Total 808.03

    Contractor's Profit & Overheads 20 Percent 161.61

    Total 969.63

    LABOUR

    i) " Thick Topping 1:2

    Mason 0.50 No. 300.00 Per day 150.00

    Cooly 0.25 No. 140.00 Per day 35.00Bahishti 0.05 No. 160.00 Per day 8.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    ii) 1" Thick Bedding 1:3:6

    Mason 1.00 No. 300.00 Per day 300.00

    Cooly 1.00 No. 140.00 Per day 140.00

    Bahishti 0.20 No. 160.00 Per day 32.00

    Carpenter 0.30 No. 300.00 Per day 90.00

    Total 830.00

    Sundries 10 Percent 83.00

    Total 913.00

    Contractor's Profit & Overheads 20 Percent 182.60

    Total 1095.60

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,095.60 Say 1095.60

    Labour Rate Per Sqm. Rs. 117.89 Say 117.90

    Composite Rate per 100 Sft. Rs. 2,065.23 Say 2065.25

    Composite Rate per Sqm. Rs. 222.22 Say 222.20

    Page 28

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    29/66

    DESCRIPTION OF ITEM

    17 Add extra in cement concrete floor topping, if finished with pigment and polishing

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL1 Grey Cement for Finishing 1/16" Thick 0.40 Bags 230.00 Per Bag 92.00

    2 Pigment 4.5 Lbs (2.04 Kg.) 70.00 Per Kg. 142.80

    3 Polish 0.5 Lbs (0.23 Kg.) 212.00 Per Kg. 48.76

    Total 283.56

    Contractor's Profit & Overheads 20 Percent 56.71

    Total 340.27

    LABOUR FOR 150 SFT.

    Mason 0.50 No. 300.00 Per day 85.00

    Cooly (Skilled) 0.50 No. 140.00 Per day 42.50

    Total 127.50

    Sundries 10 Percent 12.75

    Total 140.25

    Contractor's Profit & Overheads 20 Percent 28.05

    Total 168.30

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 112.20 Say 112.20

    Labour Rate Per Sqm. Rs. 12.07 Say 12.05

    Composite Rate per 100 Sft. Rs. 452.47 Say 452.45

    Composite Rate per Sqm. Rs. 48.69 Say 48.70

    Page 29

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    30/66

    DESCRIPTION OF ITEM

    18 Extra labour for each storey above ground floor for moasic, conglomerate, tilesstone and wooden floor

    Detail Unit Rate Per 100 Sft.Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    LABOUR FOR 125 SFT.

    Cooly for carriage of material 0.75 No. 140.00 Per day 105.00Sundries 10 Percent 10.50Total 115.50Contractor's Profit & Overheads 20 Percent 23.10Total 138.60

    ITEM RATE

    Labour Rate per 100 Sft. Rs. 110.88 Say 110.90Labour Rate per Sqm. Rs. 11.93 Say 11.95

    DESCRIPTION OF ITEM

    19 Flag stone flooring laid in lime mortar 1:2 over 3/4" bedding mortar in plat formsand floors etc.

    a) 2" (50mm) Thick

    Detail Unit Rate Per 100 Sft.Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Dressed Stone 2'x2'x2" 25.00 Nos. 35.00 Each 875.002 Lime 1.3 Mds (48.5 Kg.) 2.00 Per Kg. 97.003 Sand 5.00 Cft. 350.00 Per 100 Cft 17.504 Steel 0.76 Kg. 17.00 Per Kg. 12.995 Charcoal 1.75 Kg. 4.00 Per Kg. 7.01

    Total 1,009.50Contractor's Profit & Overheads 20 Percent 201.90Total 1,211.40

    LABOUR

    Mason 2.50 No. 300.00 Per day 750.00Coolies 3.00 No. 140.00 Per day 420.00Bahishti 0.12 No. 160.00 Per day 19.20Blacksmith 0.10 No. 170.00 Per day 17.00Bollow Man 0.10 No. 75.00 Per day 7.50Total 1,213.70Sundries 10 Percent 121.37Total 1335.07Contractor's Profit & Overheads 20 Percent 267.01Total 1602.08

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,602.08 Say 1602.10Labour Rate Per Sqm. Rs. 172.38 Say 172.40Composite Rate per 100 Sft. Rs. 2,813.48 Say 2813.50Composite Rate per Sqm. Rs. 302.73 Say 302.75

    Page 30

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    31/66

    b) 3" (75mm) Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Dressed Stone 2'x2'x3" 25.00 Nos. 45.00 Each 1,125.002 Lime 1.42 Mds (53 Kg.) 2.00 Per Kg. 106.00

    3 Surkhi 5.00 Cft. 350.00 Per 100 Cft 17.50

    4 Steel 0.75 Kg. 17.00 Per Kg. 12.75

    5 Charcoal 1.81 Kg. 4.00 Per Kg. 7.24

    Total 1,268.49

    Contractor's Profit & Overheads 20 Percent 253.70

    Total 1,522.19

    LABOUR

    Mason 2.50 No. 300.00 Per day 750.00

    Cooly 3.00 No. 140.00 Per day 420.00

    Bahishti 0.12 No. 160.00 Per day 19.20

    Blacksmith 0.10 No. 170.00 Per day 17.00

    Bollow Man 0.10 No. 75.00 Per day 7.50

    Total 1,213.70

    Sundries 10 Percent 121.37

    Total 1335.07

    Contractor's Profit & Overheads 20 Percent 267.01

    Total 1602.08

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,602.08 Say 1602.10

    Labour Rate Per Sqm. Rs. 172.38 Say 172.40

    Composite Rate per 100 Sft. Rs. 3,124.27 Say 3124.25

    Composite Rate per Sqm. Rs. 336.17 Say 336.15

    Page 31

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    32/66

    DESCRIPTION OF ITEM

    20 Asphalt flooring including preparation of proper base, remelting, setting out and

    finishing complete

    a) 1" Thick Topping

    Detail Unit Rate Per 100 Sft.

    RateQty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Asphalt 2.36 Cwt (119.90 Kg.) 14.00 Per Kg. 1,678.60

    2 Steam Coal 0.5 Md (18.66 Kg.) 12.00 Per Kg. 223.92

    3 Fine Aggregate 9.00 Cft. 1500.00 Per 100 Cft 135.00

    4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 11.97

    Total 2,049.49

    Contractor's Profit & Overheads 20 Percent 409.90

    Total 2,459.39

    LABOUR

    Mason for Setting out and laying 0.25 No. 300.00 Per day 75.00

    Coolies 2.00 No. 140.00 Per day 280.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 430.00

    Sundries 10 Percent 43.00Total 473.00

    Contractor's Profit & Overheads 20 Percent 94.60

    Total 567.60

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 567.60 Say 567.60

    Labour Rate Per Sqm. Rs. 61.07 Say 61.05

    Composite Rate per 100 Sft. Rs. 3,026.99 Say 3027.00

    Composite Rate per Sqm. Rs. 325.70 Say 325.70

    Page 32

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    33/66

    b) " Thick Topping

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Asphalt 1.20 Cwt (60.960 Kg.) 14.00 Per Kg. 853.442 Steam Coal 0.25 Md (9.33 Kg.) 12.00 Per Kg. 111.96

    3 Fine Aggregate 4.51 Cft. 1500.00 Per 100 Cft 67.61

    4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 11.90

    Total 1,044.91

    Contractor's Profit & Overheads 20 Percent 208.98

    Total 1,253.89

    LABOUR

    Mason 0.20 No. 300.00 Per day 60.00

    Coolies 1.50 No. 140.00 Per day 210.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 345.00

    Sundries 10 Percent 34.50

    Total 379.50

    Contractor's Profit & Overheads 20 Percent 75.90

    Total 455.40

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 455.40 Say 455.40

    Labour Rate Per Sqm. Rs. 49.00 Say 49.00

    Composite Rate per 100 Sft. Rs. 1,709.29 Say 1709.30

    Composite Rate per Sqm. Rs. 183.92 Say 183.90

    Page 33

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    34/66

    c) " Thick Topping

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Asphalt 0.60 Cwt (30.48 Kg.) 14.00 Per Kg. 426.722 Steam Coal 0.25 Md (8.58 Kg.) 12.00 Per Kg. 102.96

    3 Fine Grit 2.51 Cft. 1500.00 Per 100 Cft 37.61

    4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 11.90

    Total 579.19

    Contractor's Profit & Overheads 20 Percent 115.84

    Total 695.02

    LABOUR

    Mason 0.17 No. 300.00 Per day 51.00

    Cooly 1.00 No. 140.00 Per day 140.00

    Carpenter 0.25 No. 300.00 Per day 75.00

    Total 266.00

    Sundries 10 Percent 26.60

    Total 292.60

    Contractor's Profit & Overheads 20 Percent 58.52

    Total 351.12

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 351.12 Say 351.10

    Labour Rate Per Sqm. Rs. 37.78 Say 37.80

    Composite Rate per 100 Sft. Rs. 1,046.14 Say 1046.15

    Composite Rate per Sqm. Rs. 112.56 Say 112.55

    Page 34

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    35/66

    DESCRIPTION OF ITEM

    21 1 3/8" thick mosaic flooring consisting of 3/8" mosaic topping of one part of

    cement and marble powder in the ratio 3:1 and two parts of marble chips laid

    over 1" thick flooring of 1:2:4 cement concrete including rubbing and polishing

    complete.

    a) Using Grey Cement

    Detail Unit Rate Per 100 Sft.

    RateQty Per Unit (Rs.) Amount (Rs.)

    MATERIAL for mosaic topping, rubbing & polishing

    1 Cement For 3/8" topping 0.94 Bag 230.00 Per Bag 216.20

    2 Marble Chips 3.00 Cwt (152.40 Kg.) 1.00 Per Kg. 152.40

    3 Corborandom Stone 3.00 Nos. 35.00 Each 105.00

    4 Wax Polish 0.5 Lbs (0.23 Kg.) 635.00 Pack. of 3 Kg 48.68

    5 Linen and Cotton 0.40 Kg. 25.00 P. Kg. 10.00

    6 Marble Powder 0.31 Cwt (15.75 Kg.) 80.00 Per 100 Kg. 12.60

    7 Tatric Acid 0.34 Lbs (0.15 Kg.) 65.00 Per Kg. 9.75

    Total 554.63Contractor's Profit & Overheads 20 Percent 110.93

    Total 665.56

    MATERIAL for 1" thick 1:2:4 concrete

    1 Cement 1.50 Bags 230.00 Per Bag 345.00

    2 Sand 3.70 Cft. 350.00 Per 100 Cft 12.95

    3 Shingle 7.40 Cft. 1000.00 Per 100 Cft 74.00

    4 Form Work 0.034 Cft. 350.00 P. Cft. 12.00

    Total 443.95

    Contractor's Profit & Overheads 20 Percent 88.79

    Total 532.74Total Material 1,198.30

    LABOURfor mosaic topping

    Mason for Laying 1.50 No. 300.00 Per day 450.00

    Coolies 1.25 No. 140.00 Per day 175.00

    Coolies (skilled for rubbing) 5.00 Nos. 160.00 Per day 800.00

    Bahishti 0.75 No. 160.00 Per day 120.00

    Total 1,545.00

    Sundries 10 Percent 154.50

    Total 1699.50

    Contractor's Profit & Overheads 20 Percent 339.90Total 2039.40

    LABOURfor 1" Thick 1:2:4 Concrete

    As per Item 15(a) 608.52

    Total Labour 2,647.93

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 2,118.34 Say 2118.35

    Labour Rate Per Sqm. Rs. 227.93 Say 227.95

    Composite Rate per 100 Sft. Rs. 3,316.64 Say 3316.65Composite Rate per Sqm. Rs. 356.87 Say 356.85

    Page 35

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    36/66

    b) Using White Cement

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL for 3/8"

    1 Cement (White) 0.94 Bag 345.00 Per Bag 324.302 Marble Poweder 0.31 Cwt (15.75 Kg.) 80.00 Per 100 Kg. 12.60

    3 Marble Chips 3.00 Cwt (152.40 Kg.) 1.00 Per Kg. 152.40

    4 Carborandom Stone 3.00 Nos. 35.00 Each 105.00

    5 Wax Polish 0.50 Lbs (0.23 Kg.) 635.00 Packet 3 Kg 48.68

    6 Linen Cotton etc. 0.40 Kg. 25.00 P. Kg. 10.00

    7 Tar Taric Acid 0.34 Lbs (0.15 Kg.) 65.00 Per Kg. 9.75

    Total 662.73

    Contractor's Profit & Overheads 20 Percent 132.55

    Total 795.28

    Add for cement concrete 1" thick

    As per Item 15(a) Material 532.75

    Total Material 1,328.03

    LABOUR

    Mason for Laying 1.50 No. 300.00 Per day 450.00

    Coolies 1.25 No. 140.00 Per day 175.00

    Coolies (skilled for rubbing) 5.00 Nos. 160.00 Per day 800.00Bahishti 0.75 No. 160.00 Per day 120.00

    Total 1,545.00

    Sundries 10 Percent 154.50

    Total 1699.50

    Contractor's Profit & Overheads 20 Percent 339.90

    Total 2039.40

    Add Labour for 1" thick C.C. topping 1:2:4

    As per item No. 15(a) 608.52

    Total Labour 2,647.92

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 2,118.34 Say 2118.35

    Labour Rate Per Sqm. Rs. 227.93 Say 227.95

    Composite Rate per 100 Sft. Rs. 3,446.37 Say 3446.35

    Composite Rate per Sqm. Rs. 370.83 Say 370.85

    Page 36

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    37/66

    DESCRIPTION OF ITEM

    22 1" thick mosaic flooring consisting of " mosaic topping of one part of

    cement and marble powder in the ratio of 3:1 and two parts of marble chips laid

    over 1" thick flooring of 1:2:4 cement concrete including rubbing and polishing

    complete.

    a) Using Grey Cement

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Grey Cement for " Topping 1.27 Bag 230.00 Per Bag 292.10

    2 Marble Chips 3.00 Cwt (152.40 Kg.) 1.00 Per Kg. 152.40

    3 Carborandom Stone 2.00 Nos. 35.00 Each 70.00

    4 Wax Polish 0.50 Lbs (0.23 Kg.) 635.00 Packet 3 Kg 48.68

    5 Linen Cotton etc. 0.72 Kg. 25.00 P. Kg. 18.006 Tar Taric Acid 0.34 Lbs / (0.15 Kg.) 65.00 Per Kg. 9.75

    7 Marble Poweder 0.42 Cwt (21.34 Kg.) 80.00 Per 100 Kg. 17.07

    Total 608.01

    Contractor's Profit & Overheads 20 Percent 121.60

    Total 729.61

    Add Material for 1" thick cement concrete

    Topping as per Item 15(a) 532.75

    Total Material 1,262.35

    LABOUR FOR 125 SFT.

    Mason for Laying 1.50 No. 300.00 Per day 450.00

    Coolies 1.25 No. 140.00 Per day 175.00

    Coolies (skilled for rubbing and Polishing) 5.00 Nos. 160.00 Per day 800.00

    Bahishti 0.75 No. 160.00 Per day 120.00

    Total 1,545.00

    Sundries 10 Percent 154.50

    Total 1699.50

    Contractor's Profit & Overheads 20 Percent 339.90Total 2039.40

    Add Labour for 1" thick cement concrete

    Topping as per Item 15(a) 608.52

    Total Labour 2,647.92

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 2,118.34 Say 2118.35

    Labour Rate Per Sqm. Rs. 227.93 Say 227.95Composite Rate per 100 Sft. Rs. 3,380.69 Say 3380.70

    Composite Rate per Sqm. Rs. 363.76 Say 363.75

    Page 37

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    38/66

    b) Using White Cement

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Cement White 1.27 Bag 345.00 Per Bag 438.152 Marble Powder 0.42 Cwt (21.34 Kg.) 80.00 Per 100 Kg. 17.07

    3 Marble Chips 4.16 Cwt (211.33 Kg.) 1.00 Per Kg. 211.33

    4 Carborandom Stone 3.00 Nos. 35.00 Each 105.00

    5 Wax Polish 0.50 Lbs (0.23 Kg.) 635.00 Packet 3 Kg 48.68

    6 Linen Cotton etc. 0.72 Kg. 25.00 P. Kg. 18.00

    7 Tar Taric Acid 0.34 Lbs (0.15 Kg.) 65.00 Per Kg. 9.75

    Total 847.99

    Contractor's Profit & Overheads 20 Percent 169.60

    Total 1,017.58

    Add for material of 1" thick cement concrete

    Topping as per Item No. 15(a) 532.75

    Total Material 1,550.33

    LABOUR FOR 125 SFT.

    Mason for Laying 1.50 No. 300.00 Per day 450.00

    Coolies 1.25 No. 140.00 Per day 175.00

    Coolies (skilled for rubbing and Polishing) 5.00 Nos. 160.00 Per day 800.00Bahishti 0.75 No. 160.00 Per day 120.00

    Total 1,545.00

    Sundries 10 Percent 154.50

    Total 1699.50

    Contractor's Profit & Overheads 20 Percent 339.90

    Total 2039.40

    Add labour for 1" thick cement concrete

    Topping as per Item No. 15(a) 608.52

    Total Labour 2,647.92

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 2,118.34 Say 2118.35

    Labour Rate Per Sqm. Rs. 227.93 Say 227.95

    Composite Rate per 100 Sft. Rs. 3,668.66 Say 3668.65

    Composite Rate per Sqm. Rs. 394.75 Say 394.75

    Page 38

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    39/66

    DESCRIPTION OF ITEM

    23 Providing and laying floor of mosaic marble chips tiles 1" thick of approved quality and shade

    laid in white cement and pigment over 3/4" bedding of cement sand mortar 1:2, incluidng

    finishing and polishing complete.

    Detail Unit Rate Per 100 Sft.

    RateQty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Mosaic marble tiles 12"x12"x1" 105 Nos. 15.00 Each 1,575.00

    2 Cement Grey 1.69 Bags 230.00 Per Bag 388.70

    3 Sand 4.00 Cft. 350.00 Per 100 Cft. 14.00

    4 Pigment 1.00 Lbs (0.45 Kg.) 70.00 Per Kg. 31.50

    5 White Cement 0.08 Bag 345.00 Per Bag 27.60

    Total 2,036.80

    Contractor's Profit & Overheads 20 Percent 407.36

    Total 2,444.16

    LABOUR

    Mason 1.84 No. 300.00 Per day 552.00

    Coolies 2.80 No. 140.00 Per day 392.00

    Bahishti 0.34 Nos. 160.00 Per day 54.40

    Total 998.40Sundries 10 Percent 99.84

    Total 1098.24

    Contractor's Profit & Overheads 20 Percent 219.65

    Total 1317.89

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,317.89 Say 1317.90

    Labour Rate Per Sqm. Rs. 141.80 Say 141.80

    Composite Rate per 100 Sft. Rs. 3,762.05 Say 3762.05

    Composite Rate per Sqm. Rs. 404.80 Say 404.80

    Page 39

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    40/66

    DESCRIPTION OF ITEM

    24 Laying floor of approved white glazed tile 1/4" thick in white cement 1:2 over

    3/4" thick cement mortar 1:2 complete.

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Tile (Glazed) 6"x6"x" including 5% breakage 420 No. 9.00 Each 3,780.00

    2 White Cement for laying 0.10 Bag 345.00 Per Bag 34.50

    3 Grey Cement for Bed 2.16 Bag 230.00 Per Bag 496.80

    4 Sand 5.20 Cft. 350.00 Per 100 Cft. 18.20

    Total 4,329.50

    Contractor's Profit & Overheads 20 Percent 865.90

    Total 5,195.40

    LABOUR

    Masons 2.00 No. 300.00 Per day 600.00

    Coolies 4.00 No. 140.00 Per day 560.00

    Bahishti 0.50 No. 160.00 Per day 80.00

    Total 1,240.00

    Sundries 10 Percent 124.00

    Total 1364.00Contractor's Profit & Overheads 20 Percent 272.80

    Total 1636.80

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,636.80 Say 1636.80

    Labour Rate Per Sqm. Rs. 176.12 Say 176.10

    Composite Rate per 100 Sft. Rs. 6,832.20 Say 6832.20

    Composite Rate per Sqm. Rs. 735.14 Say 735.15

    Page 40

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    41/66

    DESCRIPTION OF ITEM

    25 Laying floors of a approved coloured glazed tiles 1/4" thick laid in white

    cement and pigment on a bed of 3/4" thick cement mortar 1:2

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Coloured glazed tiles 6"x6" including 5% breakage 420 No. 11.00 Each 4,620.00

    2 White Cement 0.10 Bag 345.00 Per Bag 34.50

    3 Grey Cement 2.16 Bag 230.00 Per Bag 496.80

    4 Pigment 1.00 Lb/0.45 Kg. 70.00 Per Kg. 31.50

    5 Sand 5.20 Cft 350.00 Per 100 Cft. 18.20

    Total 5,201.00

    Contractor's Profit & Overheads 20 Percent 1,040.20

    Total 6,241.20

    LABOUR

    Masons 2.00 No. 300.00 Per day 600.00

    Coolies 4.00 No. 140.00 Per day 560.00

    Bahishti 0.50 No. 160.00 Per day 80.00

    Total 1,240.00

    Sundries 10 Percent 124.00Total 1364.00

    Contractor's Profit & Overheads 20 Percent 272.80

    Total 1636.80

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,636.80 Say 1636.80

    Labour Rate Per Sqm. Rs. 176.12 Say 176.10

    Composite Rate per 100 Sft. Rs. 7,878.00 Say 7878.00

    Composite Rate per Sqm. Rs. 847.67 Say 847.65

    Page 41

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    42/66

    DESCRIPTION OF ITEM

    26 Rubbing and polishing old grit/mosaic floor including repairing voids, un-even

    surface complete in all respects.

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Carborandum Stone 0.50 No. 35.00 Each 17.50

    2 Wax Polish 0.50 Lb (0.23 Kg.) 635.00 acket of 3 Kg 48.68

    3 Tartric Acid 0.34 Lb (0.162 Kg.) 65.00 Per Kg. 10.50

    4 Cotton waste cloth etc. 0.72 Kg. 25.00 P. Kg. 18.00

    Total 94.68

    Contractor's Profit & Overheads 20 Percent 18.94

    Total 113.62

    LABOUR FOR 125 SFT.

    Skilled Cooly for rubbing and polishing 1.00 No. 160.00 Per day 160.00

    Cooly 1.00 No. 140.00 Per day 140.00

    Bahishti 0.25 No. 160.00 Per day 40.00

    Total 340.00

    Sundries 10 Percent 34.00

    Total 374.00

    Contractor's Profit & Overheads 20 Percent 74.80Total 448.81

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 359.05 Say 359.05

    Labour Rate Per Sqm. Rs. 38.63 Say 38.65

    Composite Rate per 100 Sft. Rs. 472.67 Say 472.65

    Composite Rate per Sqm. Rs. 50.86 Say 50.85

    Page 42

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    43/66

    DESCRIPTION OF ITEM

    27 Rubbing and Polishing grit floor, including repairing voids, uneven surface

    complete in all respects.

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Carborandum Stone 1.50 No. 35.00 Each 52.50

    2 Wax Polish 0.5 Lb (0.23 Kg.) 635.00 acket of 3 Kg 48.68

    4 Cotton waste cloth etc. 0.08 Kg. 25.00 P. Kg. 2.00

    Total 103.18

    Contractor's Profit & Overheads 20 Percent 20.64

    Total 123.82

    LABOUR FOR 125 SFT.

    Cooly 1.00 No. 140.00 Per day 140.00

    Cooly Skilled 1.00 160.00 160.00

    Bahishti 0.40 No. 160.00 Per day 64.00

    Total 364.00

    Sundries 10 Percent 36.40

    Total 400.40

    Contractor's Profit & Overheads 20 Percent 80.08

    Total 480.48

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 384.38 Say 384.40

    Labour Rate Per Sqm. Rs. 41.36 Say 41.35

    Composite Rate per 100 Sft. Rs. 508.20 Say 508.20

    Composite Rate per Sqm. Rs. 54.68 Say 54.70

    Page 43

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    44/66

    DESCRIPTION OF ITEM

    28 Cleaning and washing mosaic or marble floor with caustic soda mixture

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    1 Caustic Soda 1 Lb (0.45 Kg.) 65.00 Per Kg. 29.25

    2 Hassein Cloth 0.5 Yard (0.46 m) 12.00 Per Metre 5.52

    Total 34.77

    Contractor's Profit & Overheads 20 Percent 6.95

    Total 41.72

    LABOUR FOR 150 SFT.

    Mason 0.25 No. 300.00 Per day 75.00

    Bahishti 0.12 No. 160.00 Per day 10.20

    Total 85.20

    Sundries 10 Percent 8.52

    Total 93.72

    Contractor's Profit & Overheads 20 Percent 18.74

    Total 112.46

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 74.98 Say 75.00

    Labour Rate Per Sqm. Rs. 8.07 Say 8.05

    Composite Rate per 100 Sft. Rs. 116.70 Say 116.70

    Composite Rate per Sqm. Rs. 12.56 Say 12.55

    Page 44

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    45/66

    DESCRIPTION OF ITEM

    29 Shisham wood boarding or strips flooring 3/4" thick (sawn to required sizes)

    tongued and grooved or splayed rebated fixed with brass screws on deedar wood

    battens 1"x2" placed at 12" centre to centre including two coats of bitumen laid

    hot on the base.

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Shisham Wood

    100 x3/4' x

    1/12' 6.25 Cft.

    Add 5% rebate 0.31 Cft.

    Total 6.56 Cft.

    Add 60% Wastage 3.94 Cft.

    Total 10.50 Cft. 300.00 Per Cft. 3,150.00

    Deodar Wood Battens

    11 x 10' x 1/8' x 1/6' 2.29 Cft.

    Add 50% Wastage 1.15 Cft.

    Total 3.44 Cft. 500.00 Per Cft. 1,720.00

    Bitumen 35 Lbs (15.89 Kg.) 14.00 Per Kg. 222.46

    Fire Wood 0.125 Lbs (4.67 Kg.) 2.75 Per Kg. 12.84

    Brass Screws 2" 7.00 Dozen 8.00 Per Dozen 56.00

    Sand Paper Sheet 1.50 Dozen 72.00 Per Dozen 108.00

    Total 5,269.30

    Contractor's Profit & Overheads 20 Percent 1,053.86

    Total 6,323.16

    LABOUR FOR 300 SFT.

    Carpenters 10.00 No. 300.00 Per day 3,000.00

    Coolies 5.00 No. 160.00 Per day 800.00

    Total 3,800.00

    Sundries 10 Percent 380.00

    Total 4180.00

    Contractor's Profit & Overheads 20 Percent 836.00

    Total 5016.00

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,672.00 Say 1672.00

    Labour Rate Per Sqm. Rs. 179.91 Say 179.90

    Composite Rate per 100 Sft. Rs. 7,995.16 Say 7995.15

    Composite Rate per Sqm. Rs. 860.28 Say 860.30

    Page 45

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    46/66

    DESCRIPTION OF ITEM

    30 Decdar wood boarding or strips flooring 3/4" thick (sawn to required

    sizes)tongued and grooved or splayed rebated fixed with brass screws on

    deodar wood battens 1"x2" placed at 12" c/c including two coats of bitumens

    laid hot on the base.

    Detail Unit Rate Per 100 Sft.

    RateQty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Deodar wood planks 100 x 3/4' x 1/12' 6.25 Cft.

    Add 5% for rebate 0.31 Cft.

    Total 6.56 Cft.

    Deodar wood batten 11x10' x 1/6' x 1/8' 2.29 Cft.

    Total 8.85 Cft.

    Add 50% Wastage 4.43 Cft.

    Total 13.28 Cft. 500.00 Per Cft. 6,640.00

    Bitumen 34 Lbs (15.44 Kg.) 14.00 Per Kg. 216.16

    Fire Wood 0.125 Mds (4.67 Kg.) 2.75 Per Kg. 12.84

    Brass Screws 2" long 7.00 Dozen 8.00 Per Dozen 56.00

    Sand Paper 1.00 Dogen 72.00 Per Dozen 72.00

    Total 6,997.00

    Contractor's Profit & Overheads 20 Percent 1,399.40

    Total 8,396.40

    LABOUR FOR 200 SFT.

    Carpenters 6.00 No. 300.00 Per day 1,800.00

    Coolies 6.00 No. 140.00 Per day 840.00

    Total 2,640.00

    Sundries 10 Percent 264.00

    Total 2904.00

    Contractor's Profit & Overheads 20 Percent 580.80

    Total 3484.80

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,742.40 Say 1742.40

    Labour Rate Per Sqm. Rs. 187.48 Say 187.50

    Composite Rate per 100 Sft. Rs. 10,138.80 Say 10138.80

    Composite Rate per Sqm. Rs. 1,090.94 Say 1090.95

    Page 46

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    47/66

    DESCRIPTION OF ITEM

    31 Teakwook boarding or strips flooring " thick (Sawn to required sized)

    tongued and grooved screwed on deodar wood battens 1" x 2" size, placed at 12"

    centre to centre including 2 coats of bitumen laid hot on the base.

    Detail Unit Rate Per 100 Sft.

    RateQty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Teak Wood (100x' x1/12' 4.20 Cft.

    Add 5% for rebate 0.20 Cft.

    Total 4.40 Cft.

    Add 20% Wastage 0.88 Cft

    Total 5.28 Cft. 1400.00 Per Cft. 7,392.00

    Deodar wood 11x10' x 1/8' x 1/6' 2.29 Cft.

    Add. 50% Wastage 1.15

    Total 3.44 Cft. 500.00 Cft. 1,720.00

    Bitumen 34 Lbs (15.44 Kg.) 14.00 Per Kg. 216.16

    Sand Paper 2.00 Dozen 72.00 Per Dozen 144.00

    Fuel Wood 0.125 Mds (4.67 Kg.) 2.75 Per Kg. 12.84

    Total 9,485.00

    Contractor's Profit & Overheads 20 Percent 1,897.00Total 11,382.00

    LABOUR FOR 300 SFT.

    Carpenters 10.00 No. 300.00 Per day 3,000.00

    Coolies 5.00 No. 140.00 Per day 700.00

    Total 3,700.00

    Sundries 10 Percent 370.00

    Total 4070.00

    Contractor's Profit & Overheads 20 Percent 814.00

    Total 4884.00

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,628.00 Say 1628.00

    Labour Rate Per Sqm. Rs. 175.17 Say 175.15

    Composite Rate per 100 Sft. Rs. 13,010.00 Say 13010.00

    Composite Rate per Sqm. Rs. 1,399.88 Say 1399.90

    Page 47

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    48/66

    DESCRIPTION OF ITEM

    32 Shisham wood block flooring 1" thick cut to required size, fixed on a layer of

    asphalt bitumen laid on base

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Shisham Wood of best quality 8.33 Cft.

    100 x 1/12' sawan to required size

    Add 100 % Wastage 8.33 Cft.

    Total 16.66 Cft. 300.00 Per Cft. 4,998.00

    Bitumen for laying and dipping blocks 80 Lbs (36.32 Kg.) 14.00 Per Kg. 508.48

    Primer 5.00 Lbs (2.27 Kg.) 13.00 Per Kg. 29.51

    Fire Wood 0.25 Md (9.33 Kg.) 2.75 Per Kg. 25.66

    Sand Paper 2.00 Dozen 72.00 Per Dozen 144.00

    Total 5,705.65

    Contractor's Profit & Overheads 20 Percent 1,141.13

    Total 6,846.78

    LABOUR FOR 200 SFT.

    Carpenters 6.00 No. 300.00 Per day 1,800.00Coolies 5.00 No. 140.00 Per day 700.00

    Total 2,500.00

    Sundries 10 Percent 250.00

    Total 2750.00

    Contractor's Profit & Overheads 20 Percent 550.00

    Total 3300.00

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,650.00 Say 1650.00

    Labour Rate Per Sqm. Rs. 177.54 Say 177.55

    Composite Rate per 100 Sft. Rs. 8,496.78 Say 8496.80

    Composite Rate per Sqm. Rs. 914.25 Say 914.25

    Page 48

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    49/66

    DESCRIPTION OF ITEM

    33 Teak wood block 1" thick cut to required size fixed on a layer of asphalt bitumen laid on base

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Teak wood for blocks 1" 8.33 Cft.

    thick sawn to size 100 x1/12'

    Add 40% Wastage 3.33 Cft.

    Total 11.66 Cft. 1400.00 Per Cft. 16,324.00

    Bitumen 80 Lbs (36.32 Kg.) 14.00 Per Kg. 508.48

    Primer 5.00 Lbs (2.27 Kg.) 13.00 Per Kg. 29.51

    Fuel Wood 0.125 Lbs (4.67 Kg.) 2.75 Per Kg. 12.84

    Sand Paper 2.00 Dozen 72.00 Per Dozen 144.00

    Total 17,018.83

    Contractor's Profit & Overheads 20 Percent 3,403.77

    Total 20,422.60

    LABOUR FOR 300 SFT.

    Carpenters 10.00 No. 300.00 Per day 3,000.00

    Coolies 5.00 No. 140.00 Per day 700.00Total 3,700.00

    Sundries 10 Percent 370.00

    Total 4070.00

    Contractor's Profit & Overheads 20 Percent 814.00

    Total 4884.00

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,628.00 Say 1628.00

    Labour Rate Per Sqm. Rs. 175.17 Say 175.15

    Composite Rate per 100 Sft. Rs. 22,050.60 Say 22050.60

    Composite Rate per Sqm. Rs. 2,372.64 Say 2372.65

    Page 49

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    50/66

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    51/66

    b) Kikar Wood

    Detail Unit Rate Per 100 Sft. (Per Inch Thickness)

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Kikar Wood = 100 x 1 8.33 Cft.12

    Wastage 30% 2.50 Cft.

    Total 10.83 Cft. 250.00 Per Cft. 2,707.50

    Bitumen 34 Lbs (15.44 Kg.) 14.00 Per Kg. 216.16

    Total 2,923.66

    Contractor's Profit & Overheads 20 Percent 584.73

    Total 3,508.39

    LABOUR FOR 150 SFT.

    Carpenter 1.00 No. 300.00 Per day 300.00

    Coolies 3.00 No. 140.00 Per day 420.00

    Mason 1.00 No. 300.00 Per day 300.00

    Total 1,020.00

    Sundries 10 Percent 102.00

    Total 1122.00

    Contractor's Profit & Overheads 20 Percent 224.40

    Total 1346.40

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 897.60 Say 897.60

    Labour Rate Per Sqm. Rs. 96.58 Say 96.60

    Composite Rate per 100 Sft. Rs. 4,405.99 Say 4406.00

    Composite Rate per Sqm. Rs. 474.08 Say 474.10

    Page 51

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    52/66

    DESCRIPTION OF ITEM

    35 Tile skirting laid in 1:2 cement mortar over 3/4" thick cement mortar 1:2 including

    cement washing and filling joints complete.

    a) Cement Tiles

    Detail Unit Rate Per 100 Sft.

    RateQty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Cement tiles 8"x8" including 5% breakage 240 No. 7.00 Each 1,680.00

    and Wastage

    Cement for laying and pointing cement tiles 2.45 Bags 230.00 Per Bag 563.50

    Sand 6.00 Cft. 350.00 Per 100 Cft. 21.00

    Pigment 1 Lb (0.45 Kg.) 70.00 Per Kg. 31.50

    Total 2,296.00

    Contractor's Profit & Overheads 20 Percent 459.20

    Total 2,755.20

    LABOUR FOR 150 SFT.

    Masons 1.56 No. 300.00 Per day 468.00

    Coolies 2.50 No. 140.00 Per day 350.00

    Bahishti 0.34 No. 160.00 Per day 54.40

    Total 872.40Sundries 10 Percent 87.24

    Total 959.64

    Contractor's Profit & Overheads 20 Percent 191.93

    Total 1151.57

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 767.71 Say 767.70

    Labour Rate Per Sqm. Rs. 82.61 Say 82.60

    Composite Rate per 100 Sft. Rs. 3,522.91 Say 3522.90

    Composite Rate per Sqm. Rs. 379.07 Say 379.05

    Page 52

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    53/66

    b) Mosaic Tiles

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Tiles 6"x6"x3/4" 420 No. 6.50 Each 2,730.00

    Cement 2.54 Bag 230.00 Per Bag 584.20

    Sand 6.00 Cft 350.00 Per 100 Cft. 21.00

    Pigment 1 Lbs (0.45 Kg.) 70.00 Per Kg. 31.50

    White Cement 0.08 Bag 345.00 Per Bag 27.60

    Total 3,394.30

    Contractor's Profit & Overheads 20 Percent 678.86

    Total 4,073.16

    LABOUR

    Masons 2.00 No. 300.00 Per day 600.00

    Coolies 2.50 No. 140.00 Per day 350.00

    Bahishti 0.25 No. 160.00 Per day 40.00

    Total 990.00

    Sundries 10 Percent 99.00

    Total 1089.00

    Contractor's Profit & Overheads 20 Percent 217.80

    Total 1306.80

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,306.80 Say 1306.80

    Labour Rate Per Sqm. Rs. 140.61 Say 140.60

    Composite Rate per 100 Sft. Rs. 5,379.96 Say 5379.95

    Composite Rate per Sqm. Rs. 578.88 Say 578.90

    Page 53

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    54/66

    DESCRIPTION OF ITEM

    36 Providing grey cement skirting or dado 3/8" thick including rounding of corner and

    straightening of top edge and finishing to smooth surface after plastering

    a) 1:2 Cement Sand Mortar

    Detail Unit Rate Per 100 Sft.

    RateQty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Cement 0.96 Bag 230.00 Per Bag 220.80

    Sand 2.50 Cft. 350.00 Per 100 Cft. 8.75

    Total 229.55

    Contractor's Profit & Overheads 20 Percent 45.91

    Total 275.46

    LABOUR FOR 125 SFT.

    Masons 2.50 No. 300.00 Per day 750.00

    Coolies 1.50 No. 140.00 Per day 210.00

    Bahishti 0.34 No. 160.00 Per day 54.40

    Total 1,014.40

    Sundries 10 Percent 101.44

    Total 1115.84

    Contractor's Profit & Overheads 20 Percent 223.17Total 1339.01

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,071.21 Say 1071.20

    Labour Rate Per Sqm. Rs. 115.26 Say 115.25

    Composite Rate per 100 Sft. Rs. 1,346.67 Say 1346.65

    Composite Rate per Sqm. Rs. 144.90 Say 144.90

    Page 54

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    55/66

    b) 1:3 Cement Sand Mortar

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Cement 0.66 Bag 230.00 Per Bag 151.80Sand 2.55 Bag 350.00 Per 100 Cft. 8.93

    Total 160.73

    Contractor's Profit & Overheads 20 Percent 32.15

    Total 192.87

    LABOUR FOR 125 SFT.

    Masons 2.50 No. 300.00 Per day 750.00

    Coolies 1.50 No. 140.00 Per day 210.00

    Bahishti 0.34 No. 160.00 Per day 54.40

    Total 1,014.40

    Sundries 10 Percent 101.44

    Total 1115.84

    Contractor's Profit & Overheads 20 Percent 223.17

    Total 1339.01

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 1,071.21 Say 1071.20Labour Rate Per Sqm. Rs. 115.26 Say 115.25

    Composite Rate per 100 Sft. Rs. 1,264.08 Say 1264.10

    Composite Rate per Sqm. Rs. 136.01 Say 136.00

    Page 55

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    56/66

    c) Extra if skirting or dado is finished with pigment of any colour

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Pigment 6 Lbs (2.72 Kg.) 70.00 Per Kg. 190.40Contractor's Profit & Overheads 20 Percent 38.08

    Total 228.48

    LABOUR FOR 200 SFT.

    Cooly for mixing 0.50 No. 140.00 Per day 70.00

    Sundries 10 Percent 7.00

    Total 77.00

    Contractor's Profit & Overheads 20 Percent 15.40

    Total 92.40

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 46.20 Say 46.20

    Labour Rate Per Sqm. Rs. 4.97 Say 4.95

    Composite Rate per 100 Sft. Rs. 274.68 Say 274.70

    Composite Rate per Sqm. Rs. 29.56 Say 29.55

    Page 56

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    57/66

    DESCRIPTION OF ITEM

    37 White glazed tiles " thick dado jointed in white cement and laid over 1:2 cement

    sand mortar 3/4" thick including finishing complete

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Tiles 6"x6"x" 420 No. 9.00 Each 3,780.00

    White Cement 0.10 Bag 345.00 Per Bag 34.50

    Grey Cement 2.16 Bag 230.00 Per Bag 496.80

    Sand 5.20 Cft. 350.00 Per 100 Cft. 18.20

    Total 4,329.50

    Contractor's Profit & Overheads 20 Percent 865.90

    Total 5,195.40

    LABOUR

    Mason 2.50 No. 300.00 Per day 750.00

    Coolies 5.00 No. 140.00 Per day 700.00

    Bahishti 0.50 No. 160.00 Per day 80.00

    Total 1,530.00

    Sundries 10 Percent 153.00

    Total 1683.00Contractor's Profit & Overheads 20 Percent 336.60

    Total 2019.60

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 2,019.60 Say 2019.60

    Labour Rate Per Sqm. Rs. 217.31 Say 217.30

    Composite Rate per 100 Sft. Rs. 7,215.00 Say 7215.00

    Composite Rate per Sqm. Rs. 776.33 Say 776.35

    Page 57

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    58/66

    DESCRIPTION OF ITEM

    38 Glazed tile dado " thick dado laid in pigment over 1:2 cement sand mortar3/4" thick

    including finishing

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Tiles 6"x6"x" 420 No. 9.00 Each 3,780.00

    White Cement 0.10 Bag 345.00 Per Bag 34.50

    Grey Cement 2.16 Bag 230.00 Per Bag 496.80

    Pigment 0.67 Lb (0.30 Kg.) 70.00 Per Kg. 21.00

    Sand 5.00 Cft. 350.00 Per 100 Cft. 17.50

    Total 4,349.80

    Contractor's Profit & Overheads 20 Percent 869.96

    Total 5,219.76

    LABOUR

    Mason 2.50 No. 300.00 Per day 750.00

    Coolies 5.00 No. 140.00 Per day 700.00

    Bahishti 0.50 No. 160.00 Per day 80.00

    Total 1,530.00

    Sundries 10 Percent 153.00

    Total 1683.00Contractor's Profit & Overheads 20 Percent 336.60

    Total 2019.60

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 2,019.60 Say 2019.60

    Labour Rate Per Sqm. Rs. 217.31 Say 217.30

    Composite Rate per 100 Sft. Rs. 7,239.36 Say 7239.35

    Composite Rate per Sqm. Rs. 778.96 Say 778.95

    Page 58

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    59/66

    DESCRIPTION OF ITEM

    39 Masaic dado or skirting with one part of cement and marble powder in the ratio of

    3:! and two parts of marble chips, laid over " thick cement plaster 1:3 including

    rubbing and polishing complete with finishing:

    a - i) Using Grey Cement 3/8" Thick

    Detail Unit Rate Per 100 Sft.Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Grey Cement 0.94 Bags 230.00 Bag 216.20

    Marble Powder 0.31 Cwt. (15.75 Kg.) 80.00 Per 100 Kg. 12.60

    Marble Chips 3.00 Cwt.(152.40 Kg.) 1.00 Per Kg. 152.40

    Carbordum Stone 3 No. 35.00 Per Kg. 105.00

    Wax Polish 0.5 Lbs (0.23 Kg.) 635.00 Packet 3 Kg. 48.68

    Tartric Acid 0.34 Lbs (0.15 Kg.) 65.00 Per Kg. 9.75

    Total 544.63

    Contractor's Profit & Overheads 20 Percent 108.93

    Total 653.56

    LABOUR

    Mason 2.00 No. 300.00 Per day 600.00

    Coolies 2.00 No. 140.00 Per day 280.00Skilled Cooly 5.00 No. 160.00 Per day 800.00

    Bahishti 1.00 No. 160.00 Per day 160.00

    Total 1,840.00

    Sundries 10 Percent 184.00

    Total 2024.00

    Contractor's Profit & Overheads 20 Percent 404.80

    Total 2428.80

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 2,428.80 Say 2428.80

    Labour Rate Per Sqm. Rs. 261.34 Say 261.35

    Composite Rate per 100 Sft. Rs. 3,082.36 Say 3082.35

    Composite Rate per Sqm. Rs. 331.66 Say 331.65

    Page 59

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    60/66

    a-ii) Using Grey Cement " Thick

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    Cement 1.27 Bags 230.00 Bag 292.10Marble Powder 0.42 Cwt. (21.34 Kg.) 80.00 Per 100 Kg. 17.07

    Marble Chips 3 Cwt. (152.40 Kg.) 1.00 Per Kg. 152.40

    Carboradom Stone 3 No. 35.00 Each 105.00

    Wax Polish 0.5 Lbs (0.23 Kg.) 635.00 Packet 3 Kg. 48.68

    Linion Cloth 0.72 Kg. 25.00 P. Kg. 18.00

    Tartric Acid 0.34 Lbs (0.15 Kg.) 65.00 Per Kg. 9.75

    "cement plaster under neath

    Cement 0.88 Bag 230.00 Bag 202.40

    Sand 3.40 Cft. 350.00 Per 100 Cft. 11.90

    Total 857.31

    Contractor's Profit & Overheads 20 Percent 171.46

    Total 1,028.77

    LABOUR

    Mason 2.00 No. 300.00 Per day 600.00

    Cooly 2.00 No. 140.00 Per day 280.00Skilled Cooly 5.00 No. 160.00 Per day 800.00

    Bahishti 1.00 No. 160.00 Per day 160.00

    Total 1,840.00

    Sundries 10 Percent 184.00

    Total 2024.00

    Contractor's Profit & Overheads 20 Percent 404.80

    Total 2428.80

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 2,428.80 Say 2428.80

    Labour Rate Per Sqm. Rs. 261.34 Say 261.35

    Composite Rate per 100 Sft. Rs. 3,457.57 Say 3457.55

    Composite Rate per Sqm. Rs. 372.03 Say 372.05

    Page 60

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    61/66

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    62/66

    b-ii) Using White Cement (" thick)

    Detail Unit Rate Per 100 Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    MATERIAL

    i) Thick

    White Cement 1.27 Bags 345.00 Bag 438.15

    Marble Powder 0.42 Cwt. (21.34 Kg.) 80.00 Per 100 Kg. 17.07

    Marble Chips 3 Cwt. (152.40 Kg.) 1.00 Per Kg. 152.40

    Carboradom Stone 3 No. 35.00 Each 105.00

    Wax Polish 0.5 Lbs (0.23 Kg.) 635.00 Packet 3 Kg. 48.68

    Linion Cloth 0.72 Kg. 25.00 P. Kg. 18.00

    Tartric Acid 0.34 Lbs / 0.15 Kg. 65.00 Per Kg. 9.75

    ii) "cement plaster 1:3 under neath

    Grey Cement 0.88 Bag 230.00 Bag 202.40

    Sand 3.40 Cft. 350.00 Per 100 Cft. 11.90

    Total 959.35

    Contractor's Profit & Overheads 20 Percent 191.87

    Total 1,151.22

    LABOUR

    Mason 2.00 No. 300.00 Per day 600.00

    Skilled Cooly 5.00 No. 160.00 Per day 800.00

    Coolies 2.00 No. 140.00 Per day 280.00

    Bahishti 1.00 No. 160.00 Per day 160.00

    Total 1,840.00

    Sundries 10 Percent 184.00

    Total 2024.00

    Contractor's Profit & Overheads 20 Percent 404.80

    Total 2428.80

    ITEM RATE

    Labour Rate Per 100 Sft. Rs. 2,428.80 Say 2428.80

    Labour Rate Per Sqm. Rs. 261.34 Say 261.35

    Composite Rate per 100 Sft. Rs. 3,580.02 Say 3580.00

    Composite Rate per Sqm. Rs. 385.21 Say 385.20

    Page 62

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    63/66

    DESCRIPTION ITEM

    40 Rubber Flooring, consisting of 12"x12"x1/8" rubber tiles laid on firm foundation

    Detail Unit Rate Per Sft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    (Assume for 100 Sft.)

    MATERIAL

    Rubber tiles (12"x12"x1/8") 105 Nos. 40.00 Each 4,200.00

    including 5% wastage

    Adhesive mixutre (10 Lbs) (4.56 Kg.) 4.56 Kg. 120.00 Kg. 547.20

    Brushes etc. 0.04 No. 100.00 Each 4.00

    Total 4,751.20

    Contractor's Profit & Overheads 20 Percent 950.24

    Total 5,701.44

    LABOUR

    Mason 1.00 No. 300.00 Per day 300.00

    Coolies 1.50 No. 140.00 Per day 210.00

    Total 510.00

    Sundries 10 Percent 51.00

    Total 561.00Contractor's Profit & Overheads 20 Percent 112.20

    Total 673.20

    ITEM RATE

    Labour Rate Per Sft. Rs. 6.73 Say 6.75

    Labour Rate Per Sqm. Rs. 72.44 Say 72.45

    Composite Rate per Sft. Rs. 63.75 Say 63.75

    Composite Rate per Sqm. Rs. 685.91 Say 685.90

    Page 63

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    64/66

    DESCRIPTION OF ITEM

    41 Providing and Fixing Glass Strip 5mm thick and 1" wide

    for dividing mosaic flooring into panels.

    Detail Unit Rate Per Rft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    (Assume for 100 Rft.)

    MATERIAL

    Glass Strips 1" wide

    5mm Thick 100.00 Rft.

    Wastage 10% 10.00 Rft.

    Total 110.00 Rft. 220.00 Per 100 Rft 242.00

    Contractor's Profit & Overheads 20 Percent 48.40

    Total 290.40

    ITEM RATE

    Composite Rate per Rft. Rs. 2.90 Say 2.90

    Composite Rate per R.M. Rs. 9.53 Say 9.55

    Note : Labour for fixing already included in item 15 & 22 of this chapter

    Page 64

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    65/66

    DESCRIPTION OF ITEM

    42 Providing and fixing marble strip of any shade for dividing the mosaic flooring into pannels.

    a) Size 1" x 3/8"

    Detail Unit Rate Per Rft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    (Assume for 100 Rft.)

    MATERIAL

    Marble Strip 1" x 3/8" 100.00 Rft.

    Wastage 10% 10.00 Rft.

    Total 110.00 Rft. 4.00 Per Rft. 440.00

    Contractor's Profit & Overheads 20 Percent 88.00

    Total 528.00

    ITEM RATE

    Composite Rate per Rft. Rs. 5.28 Say 5.30

    Composite Rate per R/M Rs. 17.32 Say 17.30

    Note Labour already included in item 15, 16 and 22 of this chapter.

    Page 65

  • 8/9/2019 Rate analsis Chapter No. 10 Flooring)

    66/66

    b) Size 1" x "

    Detail Unit Rate Per Rft.

    Rate

    Qty Per Unit (Rs.) Amount (Rs.)

    (Assume for 100 Rft.)

    MATERIAL

    Marble Strips 1" x " 100.00 Rft.

    Wastage 10% 10.00 Rft.

    Total 110.00 Rft. 3.00 Per Rft. 330.00

    Contractor's Profit & Overheads 20 Percent 66.00

    Total 396.00

    ITEM RATE

    Composite Rate per Rft. Rs. 3.96 Say 3.95

    Composite Rate per R/M Rs. 12.99 Say 13.00

    Note Labour already included in item 15, 16 and 22 of this chapter.