Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

Embed Size (px)

Citation preview

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    1/37

    DESCRIPTION OF ITEM NO 1: Loading or unloading into or from Railway

    Wagons lead within one chain Shingle, sand,

    ballast, surkhi ashes, kankar, brick bats, coal.

    Lime or 1000 Nos. tiles size 12"x6"x2" or

    9"x4"x1" properly laid and stacked.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 1250 Bricks

    Labour

    Unskilled Cooly 1.00 No 140.00 P. Day 140.00

    Total 140.00

    Sundries 10.00 Percent 14.00

    Total 154.00

    Contractor's Profit & Overheads 20.00 Percent 30.80

    Total 184.80

    Item Rates

    Labour Rate Per 100 Cft Rs. 147.84 Say 147.85

    Labour Rate Per Cum Rs. 52.22 Say 52.20

    H PTER N .

    LOADING UNLOADING AND STACKING

    Unit Rate (British System) per 100 Cft

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    2/37

    DESCRIPTION OF ITEM NO 2: Loading or unloading bricks into or from Railway

    Wagons laid and stacked lead within one chain.

    a) Bricks 10" size.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 1250 Bricks

    Labour

    Unskilled Cooly 1.25 No 140.00 P. Day 175.00

    Total 175.00

    Sundries 10.00 Percent 17.50

    Total 192.50

    Contractor's Profit & Overheads 20.00 Percent 38.50

    Total 231.00

    Item Rates

    Labour Rate Per 1000 Nos Rs. 184.80 Say 184.80

    Unit Rate (British System) per 1000 Nos

    Page 2

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    3/37

    Item No. 2 Loading or unloading bricks into or from Railway

    Wagons laid and stacked lead within one chain.

    b) Bricks 9" or smaller size.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 1250 Bricks

    Labour

    Unskilled Cooly 1.00 No 140.00 P. Day 140.00

    Total 140.00

    Sundries 10.00 Percent 14.00

    Total 154.00

    Contractor's Profit & Overheads 20.00 Percent 30.80

    Total 184.80

    Item Rates

    Labour Rate Per 1000 Nos Rs. 147.84 Say 147.85

    Unit Rate (British System) per 1000 Nos

    Page 3

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    4/37

    DESCRIPTION OF ITEM NO 3: Loading or unloading into or from Railway

    Wagons cement in bags (from inside or outside

    the go-down) and stacking within one chain.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Bags

    Labour

    Unskilled Cooly 1.25 No 140.00 P. Day 175.00

    Total 175.00

    Sundries 10.00 Percent 17.50

    Total 192.50

    Contractor's Profit & Overheads 20.00 Percent 38.50

    Total 231.00

    Item Rates

    Labour Rate Per 100 Bags Rs. 184.80 Say 184.80

    Unit Rate (British System) per 100 Bags

    Page 4

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    5/37

    DESCRIPTION OF ITEM NO 4: Loading or unloading into of from Railway

    Wagons empty cement bags (from inside or

    outside the go-down) and stacking.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Nos.

    Labour

    Unskilled Cooly 0.12 No 140.00 P. Day 16.80

    Total 16.80

    Sundries 10.00 Percent 1.68

    Total 18.48

    Contractor's Profit & Overheads 20.00 Percent 3.70

    Total 22.18

    Item Rates

    Labour Rate Per 100 Nos Rs. 22.18 17.74 Say 17.75

    125

    Unit Rate (British System) per 100 Nos

    Page 5

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    6/37

    DESCRIPTION OF ITEM NO 5: Loading or unloading into or from Railway

    Wagons (from inside or outside the go-down) and

    stacking white lime in bags.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Mds

    Labour

    Unskilled Cooly 0.75 No 140.00 P. Day 105.00

    Total 105.00

    Sundries 10.00 Percent 10.50

    Total 115.50

    Contractor's Profit & Overheads 20.00 Percent 23.10

    Total 138.60

    Item Rates

    Labour Rate Per 100 Mds Rs. 110.88 Say 110.90

    Labour Rate Per 100 Kg Rs. 2.97 Say 2.95

    Unit Rate (British System) per 100 Mds

    Page 6

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    7/37

    DESCRIPTION OF ITEM NO 6: Loading or unloading into or from Railway

    Wagons structural steel, joists, broad, narrow or

    meter gauge rail and rail fastening etc.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Ton

    Labour

    Unskilled Cooly 0.60 No 140.00 P. Day 84.00

    Total 84.00

    Sundries 10.00 Percent 8.40

    Total 92.40

    Contractor's Profit & Overheads 20.00 Percent 18.48

    Total 110.88

    Item Rates

    Labour Rate Per Ton Rs. 88.70 Say 88.70

    Labour Rate per Tonne Rs. 87.30 Say 87.30

    Unit Rate (British System) per Ton

    Page 7

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    8/37

    DESCRIPTION OF ITEM NO 7: Loading or unloading 45 gallons drum full into

    or from Railway Wagons lead upto one chain.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Labour

    Unskilled Cooly 0.06 No 140.00 P. Day 8.40

    Total 8.40

    Sundries 10.00 Percent 0.84

    Total 9.24

    Contractor's Profit & Overheads 20.00 Percent 1.85

    Total 11.09

    Item Rates

    Labour Rate Per Each Rs. 11.09 Say 11.10

    Unit Rate (British System) per Each

    Page 8

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    9/37

    DESCRIPTION OF ITEM NO 8: Loading or unloading packages or stock of all

    sorts upto I cwt. except cement in jute or paper

    bags.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Labour

    Unskilled Cooly 0.03 No 140.00 P. Day 4.20

    Total 4.20

    Sundries 10.00 Percent 0.42

    Total 4.62

    Contractor's Profit & Overheads 20.00 Percent 0.92

    Total 5.54

    Item Rates

    Labour Rate Per Each No. Rs. 5.54 Say 5.55

    Unit Rate (British System) per Each

    Page 9

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    10/37

    DESCRIPTION OF ITEM NO 9: Loading or unloading sleepers other than wooden

    including stacking lead within one chan in.

    a) Broad gauge sleepers.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Nos.

    Labour

    Unskilled Cooly 2.50 Nos 140.00 P. Day 350.00

    Total 350.00

    Sundries 10.00 Percent 35.00

    Total 385.00

    Contractor's Profit & Overheads 20.00 Percent 77.00

    Total 462.00

    Item Rates

    Labour Rate Per 100 Nos Rs. 369.60 Say 369.60

    Unit Rate (British System) per 100 Nos

    Page 10

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    11/37

    Item No. 9 Loading or unloading sleepers other than wooden

    including stacking load within one chan in.

    b) Metre guage and narrow guage sleepers.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Nos

    Labour

    Unskilled Cooly 1.25 No 140.00 P. Day 175.00

    Total 175.00

    Sundries 10.00 Percent 17.50

    Total 192.50

    Contractor's Profit & Overheads 20.00 Percent 38.50

    Total 231.00

    Item Rates

    Labour Rate Per 100 Nos Rs. 184.80 Say 184.80

    Unit Rate (British System) per 100 Nos

    Page 11

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    12/37

    DESCRIPTION OF ITEM NO 10: Loading or unloading timber logs or timber for

    shuttering into or from Railway Wagons of any

    gauge including stacking, lead within one chain.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 20 Ton

    Labour

    Unskilled Cooly 5.00 Nos 140.00 P. Day 700.00

    Total 700.00

    Sundries 10.00 Percent 70.00

    Total 770.00

    Contractor's Profit & Overheads 20.00 Percent 154.00

    Total 924.00

    Item Rates

    Labour Rate Per Ton Rs. 46.20 Say 46.20

    Per Tonne Rs. 45.47 Say 45.45

    Unit Rate (British System) per Ton

    Page 12

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    13/37

    DESCRIPTION OF ITEM NO 11: Loading or unloading bhoosa in Railway Wagons

    lead upto 150 feet.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Mds

    Labour

    Unskilled Cooly 3.00 Nos 140.00 P. Day 420.00

    Total 420.00

    Sundries 10.00 Percent 42.00

    Total 462.00

    Contractor's Profit & Overheads 20.00 Percent 92.40

    Total 554.40

    Item Rates

    Labour Rate Per 100 Mds. Rs. 443.52 Say 443.50

    Labour Rate Per 100 Kg Rs. 11.88 Say 11.90

    Unit Rate (British System) per 100 Mds

    Page 13

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    14/37

    DESCRIPTION OF ITEM NO 12: Loading or unloading timber scrap or wooden

    plugs into or from Railway Wagons and stacking

    within one chain lead.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 1.25 Ton

    Labour

    Unskilled Cooly 0.50 No 140.00 P. Day 70.00

    Total 70.00

    Sundries 10.00 Percent 7.00

    Total 77.00

    Contractor's Profit & Overheads 20.00 Percent 15.40

    Total 92.40

    Item Rates

    Labour Rate Per Ton Rs. 73.92 Say 73.90

    Labour Rate Per Tonne Rs. 72.75 Say 72.75

    Unit Rate (British System) per Ton

    Page 14

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    15/37

    DESCRIPTION OF ITEM NO 13: Loading or unloading pitching stone or spawl

    from Railway Wagons of any gauge (including

    clearing 5 feet away from the rail)

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Cft.

    Labour

    Unskilled Cooly 0.37 No 140.00 P. Day 51.80

    Total 51.80

    Sundries 10.00 Percent 5.18

    Total 56.98

    Contractor's Profit & Overheads 20.00 Percent 11.40

    Total 68.38

    Item Rates

    Labour Rate Per 100 Cft Rs. 54.70 Say 54.70

    Labour Rate Per Cum Rs. 19.32 Say 19.30

    Unit Rate (British System) per 100 Cft

    Page 15

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    16/37

    DESCRIPTION OF ITEM NO 14: Loading or unloading building stone (including

    clearing 5 feet away from rails)

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Cft.

    Labour

    Unskilled Cooly 0.48 No 140.00 P. Day 67.20

    Total 67.20

    Sundries 10.00 Percent 6.72

    Total 73.92

    Contractor's Profit & Overheads 20.00 Percent 14.78

    Total 88.70

    Item Rates

    Labour Rate Per 100 Cft Rs. 70.96 Say 70.95

    Labour Rate Per Cum Rs. 25.06 Say 25.05

    Unit Rate (British System) per 100 Cft

    Page 16

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    17/37

    DESCRIPTION OF ITEM NO 15: Unloading oil, bitumen tar etc.

    a) Crude oil (to be pumped from tank wagon, into

    tank).

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 1250 GallonsLabour

    Unskilled Cooly 1.25 No 140.00 P. Day 175.00

    Total 175.00

    Sundries 10.00 Percent 17.50

    Total 192.50

    Contractor's Profit & Overheads 20.00 Percent 38.50

    Total 231.00

    Item Rates

    Labour Rate Per 1000 Gln. Rs. 184.80 Say 184.80

    Labour Rate Per 100 Liters Rs. 4.07 Say 4.05

    Unit Rate (British System) per 1000 Gln

    Page 17

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    18/37

    Item No. 15 Unloading oil, bitumen tar etc.

    b) Crude oil (drained by gravity).

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 1250 Gallons

    Labour

    Unskilled Cooly 1.25 No 140.00 P. Day 175.00

    Total 175.00

    Sundries 10.00 Percent 17.50

    Total 192.50

    Contractor's Profit & Overheads 20.00 Percent 38.50

    Total 231.00

    Item Rates

    Labour Rate Per 1000 Gln. Rs. 184.80 Say 184.80

    Labour Rate Per 100 Liters Rs. 4.07 Say 4.05

    Unit Rate (British System) per 1000 Gln

    Page 18

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    19/37

    Item No. 15 Unloading oil, bitumen tar etc.

    c) Crude oil materials from Railway Wagons.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Cft

    Labour

    Unskilled Cooly 0.16 No 140.00 P. Day 22.40

    Total 22.40

    Sundries 10.00 Percent 2.24

    Total 24.64

    Contractor's Profit & Overheads 20.00 Percent 4.93

    Total 29.57

    Item Rates

    Labour Rate Per 100 Cft Rs. 23.65 Say 23.65

    Labour Rate Per Cum Rs. 8.35 Say 8.35

    Unit Rate (British System) per 100 Cft

    Page 19

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    20/37

    Item No. 15 Unloading oil, bitumen tar etc.

    d) Fuel oil from tank into empty drums and stacking

    within one chain.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 45 TonLabour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per Ton Rs. 65.71 Say 65.70

    Labour Rate Per Tonne Rs. 64.67 Say 64.65

    Unit Rate (British System) per Ton

    Page 20

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    21/37

    Item No. 15 Unloading oil, bitumen tar etc.

    e) Petrol (2 gallon tin)

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Nos

    Labour

    Unskilled Cooly 0.63 Nos 140.00 P. Day 88.20

    Total 88.20

    Sundries 10.00 Percent 8.82

    Total 97.02

    Contractor's Profit & Overheads 20.00 Percent 19.40

    Total 116.42

    Item Rates

    Labour Rate Per 100 Nos Rs. 93.14 Say 93.15

    Unit Rate (British System) per 100 Nos

    Page 21

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    22/37

    Item No. 15 Unloading oil, bitumen tar etc.

    f) Kerosine oil (4 gallons tin).

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Nos

    Labour

    Unskilled Cooly 1.25 Nos 140.00 P. Day 175.00

    Total 175.00

    Sundries 10.00 Percent 17.50

    Total 192.50

    Contractor's Profit & Overheads 20.00 Percent 38.50

    Total 231.00

    Item Rates

    Labour Rate Per 100 Nos Rs. 184.80 Say 184.80

    Unit Rate (British System) per 100 Nos

    Page 22

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    23/37

    DESCRIPTION OF ITEM NO 16: Removing and stacking within one chain lead.

    a) Stones, Spawl, Brick Bats, shingle, sand, lime.

    Surki, ashes, Kankar & Coal etc.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 CftLabour

    Unskilled Cooly 0.50 No 140.00 P. Day 70.00

    Total 70.00

    Sundries 10.00 Percent 7.00

    Total 77.00

    Contractor's Profit & Overheads 20.00 Percent 15.40

    Total 92.40

    Item Rates

    Labour Rate Per 100 Cft Rs. 73.92 Say 73.90

    Labour Rate Per Cum Rs. 26.11 Say 26.10

    Unit Rate (British System) per 100 Cft

    Page 23

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    24/37

    Item No. 16 Removing and stacking within one chain lead.

    b) Bricks

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 15,000 Nos

    Labour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per 1000 Nos Rs. 197.12 Say 197.10

    Unit Rate (British System) per 1000 Nos

    Page 24

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    25/37

    Item No. 16 Removing and stacking within one chain lead.

    c) Broad gauge wooden sleepers

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 2,500 Nos

    Labour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per 100 Nos Rs. 118.27 Say 118.25

    Unit Rate (British System) per 100 Nos

    Page 25

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    26/37

    Item No. 16 Removing and stacking within one chain lead.

    d) Metre gauge or narrow gauge wooden sleepers.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 4,200 Nos

    Labour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per 100 Nos Rs. 70.40 Say 70.40

    Unit Rate (British System) per 100 Nos

    Page 26

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    27/37

    Item No. 16 Removing and stacking within one chain lead.

    e) Rails, girders, pipes, cement etc.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 90 Ton

    Labour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per Ton Rs. 32.85 Say 32.85

    Labour Rate Per Tonne Rs. 32.33 Say 32.35

    Unit Rate (British System) per Ton

    Page 27

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    28/37

    Item No. 16 Removing and stacking within one chain lead.

    f) Bridge and crossing timber etc.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 750 Nos

    Labour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per 100 Nos Rs. 394.24 Say 394.25

    Unit Rate (British System) per 100 Nos

    Page 28

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    29/37

    DESCRIPTION OF ITEM NO 17: Loading into Wagons Girders, Rails, permanent

    way material (except wooden sleepers) iron work,

    M.S. Bars, Pipes, etc. including lead one chain

    and stacking inside Wagons.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 40 TonLabour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per Ton Rs. 73.92 Say 73.90

    Labour Rate Per Tonne Rs. 72.75 Say 72.75

    Unit Rate (British System) per Ton

    Page 29

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    30/37

    DESCRIPTION OF ITEM NO 18: Unloading from Wagons Girders, Rails,

    permanent way material (except wooden sleepers)

    iron work, M.S. Bars, Pipes, etc. lead upto one

    chain but excluding stacking.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 70 TonLabour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per Ton Rs. 42.24 Say 42.25

    Labour Rate Per Tonne Rs. 41.57 Say 41.55

    Unit Rate (British System) per Ton

    Page 30

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    31/37

    DESCRIPTION OF ITEM NO 19: Loading into Wagons, wooden broad gauge

    sleepers including one chain lead and stacking.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 1,000 Nos

    Labour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per 100 Nos Rs. 295.68 Say 295.70

    Unit Rate (British System) per 100 Nos

    Page 31

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    32/37

    DESCRIPTION OF ITEM NO 20: Unloading wooden broad gauge sleepers from

    Wagons including one chain lead and stacking.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 2,100 Nos

    Labour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per 100 Nos Rs. 140.80 Say 140.80

    Unit Rate (British System) per 100 Nos

    Page 32

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    33/37

    DESCRIPTION OF ITEM NO 21: Loading metre gauge or narrow gauge wooden

    sleepers including one chain lead and stacking

    inside Wagons.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 2,000 Nos

    Labour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per 100 Nos Rs. 147.84 Say 147.85

    Unit Rate (British System) per 100 Nos

    Page 33

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    34/37

    DESCRIPTION OF ITEM NO 22: Unloading metre gauge or narrow gauge wooden

    sleepers including one chain lead but excluding

    stacking

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 3,800 Nos

    Labour

    Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

    Total 2,240.00

    Sundries 10.00 Percent 224.00

    Total 2,464.00

    Contractor's Profit & Overheads 20.00 Percent 492.80

    Total 2,956.80

    Item Rates

    Labour Rate Per 100 Nos Rs. 77.81 Say 77.80

    Unit Rate (British System) per 100 Nos

    Page 34

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    35/37

    DESCRIPTION OF ITEM NO 23: Loading Bridge and grossing timber including

    one chain lead and stacking.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Nos

    Labour

    Unskilled Cooly 4.00 Nos 140.00 P. Day 560.00

    Total 560.00

    Sundries 10.00 Percent 56.00

    Total 616.00

    Contractor's Profit & Overheads 20.00 Percent 123.20

    Total 739.20

    Item Rates

    Labour Rate Per 100 Nos Rs. 591.36 Say 591.35

    Unit Rate (British System) per 100 Nos

    Page 35

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    36/37

    DESCRIPTION OF ITEM NO 24: Unloading Bridge and crossing timber including

    one chain lead but excluding stacking.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 125 Nos

    Labour

    Unskilled Cooly 2.00 Nos 140.00 P. Day 280.00

    Total 280.00

    Sundries 10.00 Percent 28.00

    Total 308.00

    Contractor's Profit & Overheads 20.00 Percent 61.60

    Total 369.60

    Item Rates

    Labour Rate Per 100 Nos Rs. 295.68 Say 295.70

    NOTE :

    Rate for loading and unloading for Mobile trucks/ boats, item 1-15 will be 80%

    of the rate of Railway Wagons.

    Unit Rate (British System) per 100 Nos

    Page 36

  • 8/9/2019 Rate analsis Chapter No. 2 (Loading, Unloading, Stacking)

    37/37

    DESCRIPTION OF ITEM NO 25: Loading or unloading bitumen, asphalt or tar in

    drums, into or from Railway Wagons lead upto

    one chain.

    Detail

    Qty Rate

    Per Unit (Rs.) Amount (Rs.)

    Rate Analysis for 25 Ton

    Labour

    Unskilled Cooly 6.00 Nos 140.00 P. Day 840.00

    Total 840.00

    Sundries 10.00 Percent 84.00

    Total 924.00

    Contractor's Profit & Overheads 20.00 Percent 184.80

    Total 1,108.80

    Item Rates

    Labour Rate Per Ton Rs. 44.35 Say 44.35

    Labour Rate Per Tonne Rs. 43.65 Say 43.65

    Unit Rate (British System) per Ton