Upload
morgan-nichols
View
214
Download
2
Embed Size (px)
Citation preview
Project WECC-0100 UpdateReliability Subcommittee
February 2014
TPL-001-4 Effective Dates
• FERC Acceptance October 17, 2013• January 1, 2015
– R1 – maintain System models– R7 – PC and TP study responsibilities
• January 1, 2016 – R2 – prepare annual Planning Assessment – R3 – steady state studies– R4 – stability studies– R5 – TP and PC criteria for voltage and transient performance– R6 – TP and PC criteria to identify system instability for ...– R8 – Distribution of Planning Assessment results
• January 1, 2021 – NCLL no longer allowed as corrective action plan for certain Contingencies listed in Standard
Project WECC-0100 Scope
• WECC Board approved retirement of WR1, WR2, WR4, WR5 upon effective date of NERC TPL-001-4
• WR3 (voltage stability margin), TPL-001-4 R5 and R6– R5 – criteria for acceptable ss voltage limits, post-contingency
voltage deviations, and transient voltage response– R6 – criteria or methodology used in analysis to identify System
instability for conditions such as Cascading, voltage instability, or uncontrolled islanding
• TPL-001-4 is the Standard – Reliability need is for TP’s and PC’s to have a criteria per R5 and R6
• Regional Business Practice is a Criteria to help meet the Standard where consistency in WECC is important
Voltage Instability Criteria
Alternatives being discussed:• Existing Criteria: At a minimum, verify power flow
convergence at 105% and 102.5% of (base/reference) transfer or load levels - Solution Divergence => Voltage Instability
• Concern about Existing Criteria: specifying a particular methodology, not truly VS margin; questionable VS Test – myriad reasons for solution divergence
• Alternative Criteria: Demonstrate actual margins (real and reactive) > minimum by using post-contingency P-V and V-Q analyses (as per “WECC Voltage Stability Criteria – Guideline”)
• Other?
Transient Voltage Performance
Alternatives being discussed:• Apply extrinsic documents by reference
– Apply PRC-024 generator LVRT curve to generator busses to ensure resources stay connected for planning contingencies
– Apply PRC-024 generator LVRT curve to generator and load busses to demonstrate acceptable performance, evaluate risk
– Apply PRC-024 generator LVRT curve to generator busses and something else to load busses to demonstrate acceptable performance
• Drafting concerns– As “extrinsic” documents such as PRC-024 change – so does the WECC-0100
document– Incorporation by reference means WECC loses control of administration
• Operational concerns– Concern raised about expected ride thru of loads (that is NCLL)– Concern raised about expectations of ride thru of loads for 3-Phase faults– FIDVR considerations
• Other?
Steady State Voltage and Voltage Deviations
Alternatives being discussed:• Steady state voltage limits are individual system
dependent, if an individual system does not have a criteria then specify a default for those systems
• Voltage deviation may be covered by transient voltage response if a voltage ride-through type curve (e.g. PRC-024) is utilized
Instability for Cascading and Uncontrolled Islanding
Cascading and Uncontrolled Islanding not allowed for planning contingencies
Alternatives being discussed:• Point to existing NERC Glossary definitions• Create a “criteria or methodology” (R6) to identify/detect
the potential for its occurrence, e.g.– Post-contingency Line loading exceeds relay
loadability setting (determined in PRC-023)… potential trigger for thermal cascading
– Poorly damped rotor-angle oscillations or unstable power swings… potential trigger for uncontrolled system separation