WECC Reliability Coordination Familiarization WECC Reliability Coordinators

WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

Embed Size (px)

Citation preview

Page 1: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

WECCReliability Coordination

Familiarization

WECC

Reliability Coordinators

Page 2: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

Glossary of TermsWECC – Western Electricity Coordinating Council

Formed 14 August 1967 WECC continues to be responsible for coordinating and promoting electric system reliability.

NERC - Since 1968, the North American Electric Reliability Corporation (NERC) has been committed to ensuring the reliability of the bulk power system in North America.

FERC – Federal Energy Regulatory Commission

EHV – Extra High Voltage ≥

345 kV

Page 3: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

•Extreme COLD weather•Inadequate Energy Resources•Insufficient Fuel (Deliveries hampered)

January 1994 Eastern Interconnection experienced significant power outages (including WASHINGTON DC…)

After-the-Fact investigations revealed:•There were resources available in the Midwest, but…•Frequency was low, but… Not everybody knew Why!

INADEQUATE COMMUNICATION!

1994 - NERC Blue Ribbon Task Force commissioned, which recommended creation of the NERC Security Process Task Force (SPTF).

RELIABILITY COORDINATION

1996 – NERC SPTF Recommended Creating Regional Reliability Plan for EACH region in NERC!

Page 4: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

RELIABILITY COORDINATION

Eastern Interconnection

Western Interconnection

ERCOT

Page 5: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

8 NERC Reliability Entities

Page 6: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

“WECC”Largest of the 8 NERC Regions

(1.8 million square miles)

14 Western states, 2 Canadian provinces,1 Mexican state (Portion)

153 member systems33 Control Areas71 million people

•Peak Demand(S) 125,040 MW (W) 114,680 MW•Generation169,208 MW

•Transmission 115,743 Circuit Miles

Stats based on 2001 data

Page 7: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

35 Balancing Authorities (BAs)

Page 8: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

1996 – WECC experiences Interconnection break up!(July 2 and August 10)

RELIABILITY COORDINATION

Page 9: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

January 1997 WECC Security Process Task Force published the Regional Reliability Plan.

CMRC (CISO) PNSC (BPA)

RDRC (WACM)

RELIABILITY COORDINATION

•Implementation of the WECC EHV Data Pool

•Approved by WECC BOT December 1997, and implemented on January 1, 1998.

•Created Regional Reliability Coordinators in each of the three (3) WECC Sub regions

Rocky Mtn.(WAPA)

Desert SW(APS)MAY 1999

COMBINEDRocky Mtn.

(WAPA)Desert SW

(APS)

INDEPENDENCE

The Reliability Coordinator Serves the interest of the Interconnection. Acts in the interests of the overall Interconnection before any other entity (Control Area, etc.).

Page 10: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

Three (3) Sub-Regions

Pacific Northwest (PNSC)

California/Mexico (CMRC)

Rocky Mountain/Desert Southwest (RDRC)

CMRC

RELIABILITYCOORDINATOR

AREAS

RDRC

PNSC

38%

26%

36%

LOAD

33%

22%

45%

GENERATION

23%

23%

54%

TRANSMISSION(Circuit Miles)

RELIABILITY COORDINATION

Page 11: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August
Page 12: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

• FREQUENCY– Reliable Sources– Key Points in the System

Voltage

GenerationFrequency

WECC EHV Data Pool

• VOLTAGE– 500 kV– 345 kV– 230 kV

• GENERATION– > 200 MW Voltage

FrequencyGeneration

Page 13: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

FIGURE 2EXISTING WSCC KEY TRANSMISSION LINES & PATHS

(See WSCC-Wide Key Facility List-Transmission for path description.)

345 KV500 KV

KEY TRANSFER PATHS

•SCHEDULES

WECC EHV Data Pool

•LIMITS•ACTUALS

Page 14: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

Responsibilities (NERC Policy 9; Appendix 9B)

-Planning for next-day operations, including reliability analyses and identifying special operating procedures that might be needed.-Analyzing current day operating conditions, -Adequate Resources (RESERVES)-Implementing INTERCONNECTION-wide relief procedure(TLR- Eastern & USF-WECC), or local procedures to mitigate overloads on the transmission system.-Notification.Interconnection facility status, “Energy Emergency Alert Levels.”-Provide Coordination & Direction during restoration efforts impacting the Interconnection.

RELIABILITY COORDINATION

Authority to provide emergency assistance. •Each RELIABILITY COORDINATOR must have the authority to take or direct whatever action is needed to mitigate an energy emergency within their Reliability Area.

INDEPENDENCE - STANDARDS OF CONDUCT – CONFIDENTIALITYThe Reliability Coordinator Serves the interest of Reliability Area and Interconnection. Must act in the interests of the reliability of the overall Reliability Area / Interconnection before any other entity (Control Area, Purchasing-Selling Entity, etc.).

Page 15: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

• WECC EHV Data Pool –10 to 60 second refresh rate • EMS / SCADA Systems –10 second scan rate • WAMS –Wide Area Monitoring System / Phasor

Measurement System 0.05 second scan rate • PI Displays & Data Historian (65,000 ICCP) • State Estimator Model (1Min) • Contingency Analysis (5 Min) • Voltage Stability / VAR Management • Real Time Dynamic Stability Analysis

Tools to Monitor the WECC System

Page 16: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

RELIABILITY COORDINATION

Electric System Security Data•Transmission data.

•Status•MW or ampere loadings•MVA capability•Transformer tap and phase angle settings•Key voltages

•Generator data.•Status•MW and MVAR capability•MW and MVAR net output•Status of automatic voltage control facilities

•Operating reserve•CONTROL AREA Demand•Interchange (Scheduled and Actual)•Area Control Error (ACE) and Frequency

Operational Information

Page 17: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August
Page 18: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

Frequency Disturbances and

Excursions

-1.782

Page 19: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

System Voltage

WECC EHV SYSTEM VOLTAGES

Regional Perspective

Page 20: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

Big PicturePerspectiveOperating Reserves

Key Transfer paths

Page 21: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

ConclusionRELIABILITY COORDINATION

What do Reliability Coordinators do?

Monitor & Analyze:•Reliability “Health of the system”•Established NERC & WECC Criteria (Rules)•Evaluate•Predict •and COMMUNICATE.

Page 22: WECC Reliability Coordinators - University of Colorado ...cs.uccs.edu/~cs691/smartSecureGrid/ssgworkshop/WECC RC...WECC – Western Electricity Coordinating Council Formed 14 August

Questions

RELIABILITY COORDINATION