Upload
bela-bela
View
216
Download
0
Embed Size (px)
Citation preview
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
1/95
20041
PMBOK Guide 2004
Terminology Flash Cards
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
2/95
20042
PMBOK Guide 2004 Changes
Activity Duration
The time in calendar units between the start andfinish of a schedule activity.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
3/95
20043
PMBOK Guide 2004 Changes
Sub-network
A subdivision of a project schedule networkdiagram, usually representing a subproject or awork package.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
4/95
20044
PMBOK Guide 2004 Changes
Request Seller Responses [Process]
The process of obtaining information, quotations,bids, offers,or proposals, as appropriate.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
5/95
20045
PMBOK Guide 2004 Changes
Plan Contracting [Process]
The process of documenting the products,services, and results requirements andidentifying potential sellers.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
6/95
20046
PMBOK Guide 2004 Changes
Program Management Office (PMO)
The centralized management of a particular
program or programs such that corporatebenefit is realized by the sharing of resources,methodologies, tools, and techniques, andrelated high-level project management focus.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
7/9520047
PMBOK Guide 2004 Changes
Procedure
A series of steps followed in a regular definitiveorder to accomplish something.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
8/9520048
PMBOK Guide 2004 Changes
Decomposition [Technique]
A planning technique that subdivides the projectscope and project deliverables into smaller,more manageable components, until the
project work associated with accomplishing theproject scope and providing the deliverables isdefined in sufficient detail to support executing,monitoring and controlling the work.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
9/9520049
PMBOK Guide 2004 Changes
Direct and Manage Project Execution [Process]
The process of executing the work defined in theproject management plan to achieve theprojects requirements as defined in the project
scope statement.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
10/95200410
PMBOK Guide 2004 Changes
Develop Project Scope Statement (Preliminary)
[Process]
The process of developing the preliminary projectscope statement which provides a high levelscope narrative.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
11/95200411
PMBOK Guide 2004 Changes
Analogous Estimating [Technique]
An estimating technique that uses the values ofparameters, such as scope, cost, budget, andduration or measures of scale.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
12/95200412
PMBOK Guide 2004 Changes
Select Sellers [Process]
The process of reviewing offers, choosing fromamong potential sellers, and negotiating awritten contract with a seller.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
13/95200413
PMBOK Guide 2004 Changes
Opportunity
A condition or situation favorable to the project, a
positive set of circumstances, a positive set ofevents, a risk that will have a positive impacton project objectives, or a possibility forpositive changes.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
14/95200414
PMBOK Guide 2004 Changes
Path Convergence
The merging or joining of parallel schedulenetwork paths into a single node in a projectschedule network diagram.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
15/95200415
PMBOK Guide 2004 Changes
Change Control Board (CCB)
A formally constituted group of stakeholdersresponsible for reviewing, evaluating,approving, delaying, or rejecting changes tothe project, with all decisions and
recommendations being recorded.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
16/95200416
PMBOK Guide 2004 Changes
Process
A set of interrelated actions and activitiesperformed to achieve a specified set ofproducts, results, or services.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
17/95200417
PMBOK Guide 2004 Changes
Configuration Management System [Tool]
A collection of formal documented proceduresused to apply technical and administrativedirection and surveillance to verify project
deliverables conform to requirements. Itincludes the documentation, tracking systems,and defined approval levels necessary forauthorizing and controlling changes.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
18/95200418
PMBOK Guide 2004 Changes
Level of Effort (LOE)
Support-type activity that does not readily lenditself to the measurement of discreteaccomplishments.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
19/95200419
PMBOK Guide 2004 Changes
Monitoring and Controlling Processes [Process
Group]
Those processes performed to measure andmonitor project execution so that correctiveaction can be taken when necessary to controlthe execution of the phase or project.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
20/95200420
PMBOK Guide 2004 Changes
Contingency Reserve [Output/Input]
The amount of funds, budget, or time neededabove the estimate to reduce the risk ofoverruns of project objectives to a levelacceptable to the organization.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
21/95200421
PMBOK Guide 2004 Changes
Effort
The number of labor units required to complete aschedule activity or work breakdown structurecomponent.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
22/95
200422
PMBOK Guide 2004 Changes
Work Performance Information [Output/Input]
Information and data on the status of the project
schedule activities being performed toaccomplish the project work, collected as partof the Direct and Manage Project Executionprocesses.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
23/95
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
24/95
200424
PMBOK Guide 2004 Changes
Contract Closure [Process]
The process of completing and settling thecontract, including resolution of any open itemsand closing each contract.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
25/95
200425
PMBOK Guide 2004 Changes
Reserve
A provision in the project management plan tomitigate cost and/or schedule risk.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
26/95
200426
PMBOK Guide 2004 Changes
Bottom-up Estimating [Technique]
A method of estimating a component of work bydecomposing the work into more detail andaggregating the estimates for the more detailedpieces of work.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
27/95
200427
PMBOK Guide 2004 Changes
Co-location [Technique]
An organizational placement strategy where theproject team members are physically locatedclose to one another in order to improvecommunication, working relationships, and
productivity.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
28/95
200428
PMBOK Guide 2004 Changes
Contract Statement of Work (SOW)[Output/Input]
A narrative description of products, services, orresults to be supplied under contract.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
29/95
200429
PMBOK Guide 2004 Changes
Cost of Quality (COQ) [Technique]
Determining the costs incurred to ensure quality.Prevention and appraisal costs (cost of
conformance) include costs for qualityplanning, control and assurance. Failure costs(cost of non-conformance) include costs torework, costs of warranty work, and loss of
reputation.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
30/95
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
31/95
200431
PMBOK Guide 2004 Changes
Closing Processes [Process Group]
Those processes performed to formally terminateall activities of a phase or project, and transferthe completed product to others or close acancelled project.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
32/95
200432
PMBOK Guide 2004 Changes
Bar Chart [Tool]
A graphic display of schedule-related information.Also called a Gantt chart.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
33/95
200433
PMBOK Guide 2004 Changes
Budget
The approved estimate for the project or anywork breakdown structure component or anyschedule activity.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
34/95
200434
PMBOK Guide 2004 Changes
Control Account (CA) [Tool]
A management control point where theintegration of scope, budget, actual cost, and
schedule takes place, and where themeasurement of performance will occur.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
35/95
200435
PMBOK Guide 2004 Changes
Cost-Plus-Fee (CPF)
A type of cost reimbursable contract where thebuyer reimburses the seller for the sellers
allowable costs for performing the contractwork and seller also receives a fee calculatedas an agreed upon percentage of the costs.The fee varies with the actual cost.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
36/95
200436
PMBOK Guide 2004 Changes
Communication
A process through which information isexchanged among persons using a commonsystem of symbols, signs, or behaviors.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
37/95
200437
PMBOK Guide 2004 Changes
Crashing [Technique]
A specific type of project schedule compressiontechnique performed by taking action todecrease the total project schedule duration
after analyzing a number of alternatives todetermine how to get the maximum scheduleduration compression for the least additioncost.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
38/95
200438
PMBOK Guide 2004 Changes
Create Work Breakdown Structure (WBS)[Process]
The process of subdividing the major projectdeliverables and project work into smaller,more manageable components.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
39/95
200439
PMBOK Guide 2004 Changes
Critical Path Method (CPM) [Technique]
A schedule network analysis technique used to
determine the amount of scheduling flexibilityon various logical network paths in the projectschedule network, and to determine theminimum total project duration.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
40/95
200440
PMBOK Guide 2004 Changes
Defect Repair
Formally documented identification of a defect ina project component with a recommendation toeither repair the defect or completely replacethe component.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
41/95
200441
PMBOK Guide 2004 Changes
Flowcharting [Technique]
The depiction in a diagram format of the inputs,process actions, and outputs of one or moreprocesses within a system.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
42/95
200442
PMBOK Guide 2004 Changes
Develop Project Charter [Process]
The process of developing the project charter.The Project Charter formally authorizes aproject.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
43/95
200443
PMBOK Guide 2004 Changes
Grade
A category or rank used to distinguish items thathave the same functional use, but do not sharethe same requirements for quality.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
44/95
200444
PMBOK Guide 2004 Changes
Discipline
A field of work requiring specific knowledge and
that has a set of rules governing work conduct.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
45/95
200445
PMBOK Guide 2004 Changes
Dummy Activity
A schedule activity of zero duration used to show
a logical relationship in the arrow diagrammingmethod.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
46/95
200446
PMBOK Guide 2004 Changes
Earned Value (EV)
The value of completed work expressed in terms
of the approved budget assigned to that work .
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
47/95
200447
PMBOK Guide 2004 Changes
Develop Project Team [Process]
The process of improving the competencies and
interaction of team members to enhanceproject performance.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
48/95
200448
PMBOK Guide 2004 Changes
Critical Chain Method [Technique]
A schedule network analysis technique that
modifies the project schedule to account forlimited resources.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
49/95
200449
PMBOK Guide 2004 Changes
Design Review [Technique]
A management technique used for evaluating theproposed design of the system or product to
ensure that the system or product meets thecustomer requirements, or to assure that thesystem or product will perform successfully,can be produced, and can be maintained.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
50/95
200450
PMBOK Guide 2004 Changes
Executing Processes [Process Group]
Those processes performed to complete the
work defined in the project management planto accomplish the project objectives defined inthe project scope statement.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
51/95
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
52/95
200452
PMBOK Guide 2004 Changes
Monitor and Control Project Work [Process]
The process of monitoring and controlling theprocesses required to initiate, plan, execute,and close a project to meet the performanceobjectives defined in the project managementplan and project scope statement.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
53/95
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
54/95
200454
PMBOK Guide 2004 Changes
Ground Rules [Tool]
A list of acceptable and unacceptable behaviors
adopted by a project team to improve workingrelationships, effectiveness, andcommunication.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
55/95
200455
PMBOK Guide 2004 Changes
Manage Stakeholders [Process]
The process of managing communications to
satisfy the requirements of, and resolve issueswith, project stakeholders
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
56/95
200456
PMBOK Guide 2004 Changes
Human Resource Planning [Process]
The process of identifying and documenting
project roles, responsibilities and reportingrelationships, as well as creating the staffingmanagement plan.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
57/95
200457
PMBOK Guide 2004 Changes
Imposed Date
A fixed date imposed on a schedule activity or
schedule milestone, usually in the form of astart no earlier than or finish no later than
date.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
58/95
200458
PMBOK Guide 2004 Changes
Develop Project Management Plan [Process]
The process of documenting the actions
necessary to define, prepare, integrate, andcoordinate all subsidiary plans into a projectmanagement plan.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
59/95
200459
PMBOK Guide 2004 Changes
Methodology
A system of practices, techniques, procedures,
and rules used by those who work in adiscipline.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
60/95
200460
PMBOK Guide 2004 Changes
Monitor
Collect project performance data with respect toobjectives, produce performance measures,and report and disseminate performanceinformation.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
61/95
200461
PMBOK Guide 2004 Changes
Near-Critical Activity
A schedule activity that has low total float.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
62/95
200462
PMBOK Guide 2004 Changes
Project Summary Work Breakdown Structure(PSWBS) [Tool]
A work breakdown structure for the project that isonly developed down to the subproject level ofdetail within some legs of the WBS, and wherethe detail of those subprojects are provided byuse of contract work breakdown structures.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
63/95
200463
PMBOK Guide 2004 Changes
Materiel
The aggregate of things used by an organization
in any undertaking, such as equipment,apparatus, tools, machinery, gear, material,and supplies.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
64/95
200464
PMBOK Guide 2004 Changes
Planning Package
A WBS component below the control account
with known work content but without detailedschedule activities.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
65/95
200465
PMBOK Guide 2004 Changes
Network Path
Any continuous series of schedule activities
connected with logical relationships in a projectschedule network diagram
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
66/95
200466
PMBOK Guide 2004 Changes
Planning Processes [Process Group]
Those processes performed to define and mature
the project scope, develop the projectmanagement plan, and identify and schedulethe project activities.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
67/95
200467
PMBOK Guide 2004 Changes
Scope Control [Process]
The process of controlling changes to the projectscope.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
68/95
200468
PMBOK Guide 2004 Changes
Project Management Process Group
A logical grouping of the project managementprocesses described in the PMBOK guide.
The 5 project management process groups areinitiating processes, planning processes,executing processes, monitoring andcontrolling processes, and closing processes.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
69/95
200469
PMBOK Guide 2004 Changes
Initiating Processes [Process Group]
Those processes performed to authorize and
define the scope of a new phase or project orthat can result in the continuation of haltedproject work.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
70/95
200470
PMBOK Guide 2004 Changes
Program Management
The centralized coordinated management of aparticular program to achieve the programs
strategic objectives and benefits.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
71/95
200471
PMBOK Guide 2004 Changes
Portfolio Management [Technique]
The centralized management of one or moreportfolios, which includes identifying,
authorizing, managing, and controlling projects,programs, and other related work, to achievespecific strategic business objectives.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
72/95
200472
PMBOK Guide 2004 Changes
Schedule Model
A model used in conjunction with manual
methods or project management software toperform schedule network analysis to generatethe project schedule for use in managing theexecution of a project.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
73/95
200473
PMBOK Guide 2004 Changes
Rolling Wave Planning [Technique]
A form of progressive elaboration planning wherethe work to be accomplished in the near term is
planned in detail at a low level of the workbreakdown structure, while the work far in thefuture is planned at a relatively high level of thework breakdown structure.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
74/95
200474
PMBOK Guide 2004 Changes
Three-Point Estimate [Technique]
An analytical technique that uses three cost or
duration estimates to represent the optimistic,most likely, and pessimistic scenarios.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
75/95
200475
PMBOK Guide 2004 Changes
Project Management Process
One of 44 processes, unique to projectmanagement and described in the PMBOKguide.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
76/95
200476
PMBOK Guide 2004 Changes
Technical Performance Measurement[Technique]
A performance measurement technique thatcompares technical accomplishments during
project execution to the project managementplans schedule of planned technical
achievements.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
77/95
200477
PMBOK Guide 2004 Changes
Retainage
A portion of a contract payment that is withheld
until contract completion to ensure fullperformance of the contract terms.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
78/95
200478
PMBOK Guide 2004 Changes
Voice of the Customer [Technique]
A planning technique used to provide products,services, and results that truly reflect customer
requirements by translating those customerrequirements into the appropriate technicalrequirements for each phase of project productdevelopment.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
79/95
200479
PMBOK Guide 2004 Changes
Earned Value Technique (EVT) [Technique]
A specific technique for measuring theperformance of work for a work breakdown
structure component, control account, orproject. Also referred to as the earning rulesand crediting method.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
80/95
200480
PMBOK Guide 2004 Changes
Manage Project Team [Process]
The process of tracking team member
performance, providing feedback, resolvingissues, and coordinating changes to enhanceproject performance.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
81/95
200481
PMBOK Guide 2004 Changes
Failure Mode and Effect Analysis (FMEA)[Technique]
An analytical procedure in which each potential
failure mode in every component of a productis analyzed to determine its effect on thereliability of that component and the reliabilityof the product or system.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
82/95
200482
PMBOK Guide 2004 Changes
Scope Creep
Adding features and functionality without
addressing the effects on time, costs andresources, or without customer approval.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
83/95
200483
PMBOK Guide 2004 Changes
Reserve Analysis [Technique]
An analytical technique to determine the
essential features and relationships ofcomponents in the project management plan toestablish a reserve for the schedule duration,budget, estimated cost, or funds for a project.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
84/95
200484
PMBOK Guide 2004 Changes
Fast Tracking [Technique]
A specific project schedule compression
technique that changes network logic tooverlap phases that would normally be done insequence or to perform schedule activities inparallel.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
85/95
200485
PMBOK Guide 2004 Changes
Special Cause
A source of variation that is not inherent in the
system, is not predictable, and is intermittent.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
86/95
200486
PMBOK Guide 2004 Changes
Activity Attributes [Output/Input]
Multiple attributes associated with each schedule
activity that can be included within the activitylist.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
87/95
200487
PMBOK Guide 2004 Changes
Path Divergence
Extending or generating parallel schedule
network paths from a single node in a projectschedule network diagram.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
88/95
200488
PMBOK Guide 2004 Changes
Enterprise Environmental Factors [Output/Input]
Any or all external environmental factors and
internal organizational environmental factorsthat surround or influence the projects
success.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
89/95
200489
PMBOK Guide 2004 Changes
Pareto Chart [Tool]
A histogram, ordered by frequency of occurrence,
that shows how many results were generatedby each identified cause.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
90/95
200490
PMBOK Guide 2004 Changes
Risk Register [Output/Input]
The document containing the results of the
qualitative risk analysis, quantitative riskanalysis, and risk response planning.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
91/95
200491
PMBOK Guide 2004 Changes
Control Account Plan (CAP) [Tool]
A plan for all the work and effort to be performedin a control account. Each CAP has a
definitive statement of work, schedule, andtime-phased budget.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
92/95
200492
PMBOK Guide 2004 Changes
Value Engineering
A creative approach used to optimize project life
cycle costs, save time, increase profits,improve quality, expand market share, solveproblems, and/or use resources moreeffectively.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
93/95
200493
PMBOK Guide 2004 Changes
Virtual Team
A group of persons with a shared objective who
fulfill their roles with little or no time spentmeeting face to face.
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
94/95
200494
PMBOK Guide 2004 Changes
Exception Report
Document that includes only major variations
from the plan (rather than all variations)
8/3/2019 pmbok2004flashcards-090803215824-phpapp01
95/95
PMBOK Guide 2004 Changes
Workaround [Technique]
A response to a negative risk that has occurred.Distinguished from a contingency plan in that a
workaround is not planned in advance of theoccurrence of the risk event.