pmbok2004flashcards-090803215824-phpapp01

Embed Size (px)

Citation preview

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    1/95

    20041

    PMBOK Guide 2004

    Terminology Flash Cards

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    2/95

    20042

    PMBOK Guide 2004 Changes

    Activity Duration

    The time in calendar units between the start andfinish of a schedule activity.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    3/95

    20043

    PMBOK Guide 2004 Changes

    Sub-network

    A subdivision of a project schedule networkdiagram, usually representing a subproject or awork package.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    4/95

    20044

    PMBOK Guide 2004 Changes

    Request Seller Responses [Process]

    The process of obtaining information, quotations,bids, offers,or proposals, as appropriate.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    5/95

    20045

    PMBOK Guide 2004 Changes

    Plan Contracting [Process]

    The process of documenting the products,services, and results requirements andidentifying potential sellers.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    6/95

    20046

    PMBOK Guide 2004 Changes

    Program Management Office (PMO)

    The centralized management of a particular

    program or programs such that corporatebenefit is realized by the sharing of resources,methodologies, tools, and techniques, andrelated high-level project management focus.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    7/9520047

    PMBOK Guide 2004 Changes

    Procedure

    A series of steps followed in a regular definitiveorder to accomplish something.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    8/9520048

    PMBOK Guide 2004 Changes

    Decomposition [Technique]

    A planning technique that subdivides the projectscope and project deliverables into smaller,more manageable components, until the

    project work associated with accomplishing theproject scope and providing the deliverables isdefined in sufficient detail to support executing,monitoring and controlling the work.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    9/9520049

    PMBOK Guide 2004 Changes

    Direct and Manage Project Execution [Process]

    The process of executing the work defined in theproject management plan to achieve theprojects requirements as defined in the project

    scope statement.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    10/95200410

    PMBOK Guide 2004 Changes

    Develop Project Scope Statement (Preliminary)

    [Process]

    The process of developing the preliminary projectscope statement which provides a high levelscope narrative.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    11/95200411

    PMBOK Guide 2004 Changes

    Analogous Estimating [Technique]

    An estimating technique that uses the values ofparameters, such as scope, cost, budget, andduration or measures of scale.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    12/95200412

    PMBOK Guide 2004 Changes

    Select Sellers [Process]

    The process of reviewing offers, choosing fromamong potential sellers, and negotiating awritten contract with a seller.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    13/95200413

    PMBOK Guide 2004 Changes

    Opportunity

    A condition or situation favorable to the project, a

    positive set of circumstances, a positive set ofevents, a risk that will have a positive impacton project objectives, or a possibility forpositive changes.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    14/95200414

    PMBOK Guide 2004 Changes

    Path Convergence

    The merging or joining of parallel schedulenetwork paths into a single node in a projectschedule network diagram.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    15/95200415

    PMBOK Guide 2004 Changes

    Change Control Board (CCB)

    A formally constituted group of stakeholdersresponsible for reviewing, evaluating,approving, delaying, or rejecting changes tothe project, with all decisions and

    recommendations being recorded.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    16/95200416

    PMBOK Guide 2004 Changes

    Process

    A set of interrelated actions and activitiesperformed to achieve a specified set ofproducts, results, or services.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    17/95200417

    PMBOK Guide 2004 Changes

    Configuration Management System [Tool]

    A collection of formal documented proceduresused to apply technical and administrativedirection and surveillance to verify project

    deliverables conform to requirements. Itincludes the documentation, tracking systems,and defined approval levels necessary forauthorizing and controlling changes.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    18/95200418

    PMBOK Guide 2004 Changes

    Level of Effort (LOE)

    Support-type activity that does not readily lenditself to the measurement of discreteaccomplishments.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    19/95200419

    PMBOK Guide 2004 Changes

    Monitoring and Controlling Processes [Process

    Group]

    Those processes performed to measure andmonitor project execution so that correctiveaction can be taken when necessary to controlthe execution of the phase or project.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    20/95200420

    PMBOK Guide 2004 Changes

    Contingency Reserve [Output/Input]

    The amount of funds, budget, or time neededabove the estimate to reduce the risk ofoverruns of project objectives to a levelacceptable to the organization.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    21/95200421

    PMBOK Guide 2004 Changes

    Effort

    The number of labor units required to complete aschedule activity or work breakdown structurecomponent.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    22/95

    200422

    PMBOK Guide 2004 Changes

    Work Performance Information [Output/Input]

    Information and data on the status of the project

    schedule activities being performed toaccomplish the project work, collected as partof the Direct and Manage Project Executionprocesses.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    23/95

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    24/95

    200424

    PMBOK Guide 2004 Changes

    Contract Closure [Process]

    The process of completing and settling thecontract, including resolution of any open itemsand closing each contract.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    25/95

    200425

    PMBOK Guide 2004 Changes

    Reserve

    A provision in the project management plan tomitigate cost and/or schedule risk.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    26/95

    200426

    PMBOK Guide 2004 Changes

    Bottom-up Estimating [Technique]

    A method of estimating a component of work bydecomposing the work into more detail andaggregating the estimates for the more detailedpieces of work.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    27/95

    200427

    PMBOK Guide 2004 Changes

    Co-location [Technique]

    An organizational placement strategy where theproject team members are physically locatedclose to one another in order to improvecommunication, working relationships, and

    productivity.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    28/95

    200428

    PMBOK Guide 2004 Changes

    Contract Statement of Work (SOW)[Output/Input]

    A narrative description of products, services, orresults to be supplied under contract.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    29/95

    200429

    PMBOK Guide 2004 Changes

    Cost of Quality (COQ) [Technique]

    Determining the costs incurred to ensure quality.Prevention and appraisal costs (cost of

    conformance) include costs for qualityplanning, control and assurance. Failure costs(cost of non-conformance) include costs torework, costs of warranty work, and loss of

    reputation.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    30/95

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    31/95

    200431

    PMBOK Guide 2004 Changes

    Closing Processes [Process Group]

    Those processes performed to formally terminateall activities of a phase or project, and transferthe completed product to others or close acancelled project.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    32/95

    200432

    PMBOK Guide 2004 Changes

    Bar Chart [Tool]

    A graphic display of schedule-related information.Also called a Gantt chart.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    33/95

    200433

    PMBOK Guide 2004 Changes

    Budget

    The approved estimate for the project or anywork breakdown structure component or anyschedule activity.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    34/95

    200434

    PMBOK Guide 2004 Changes

    Control Account (CA) [Tool]

    A management control point where theintegration of scope, budget, actual cost, and

    schedule takes place, and where themeasurement of performance will occur.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    35/95

    200435

    PMBOK Guide 2004 Changes

    Cost-Plus-Fee (CPF)

    A type of cost reimbursable contract where thebuyer reimburses the seller for the sellers

    allowable costs for performing the contractwork and seller also receives a fee calculatedas an agreed upon percentage of the costs.The fee varies with the actual cost.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    36/95

    200436

    PMBOK Guide 2004 Changes

    Communication

    A process through which information isexchanged among persons using a commonsystem of symbols, signs, or behaviors.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    37/95

    200437

    PMBOK Guide 2004 Changes

    Crashing [Technique]

    A specific type of project schedule compressiontechnique performed by taking action todecrease the total project schedule duration

    after analyzing a number of alternatives todetermine how to get the maximum scheduleduration compression for the least additioncost.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    38/95

    200438

    PMBOK Guide 2004 Changes

    Create Work Breakdown Structure (WBS)[Process]

    The process of subdividing the major projectdeliverables and project work into smaller,more manageable components.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    39/95

    200439

    PMBOK Guide 2004 Changes

    Critical Path Method (CPM) [Technique]

    A schedule network analysis technique used to

    determine the amount of scheduling flexibilityon various logical network paths in the projectschedule network, and to determine theminimum total project duration.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    40/95

    200440

    PMBOK Guide 2004 Changes

    Defect Repair

    Formally documented identification of a defect ina project component with a recommendation toeither repair the defect or completely replacethe component.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    41/95

    200441

    PMBOK Guide 2004 Changes

    Flowcharting [Technique]

    The depiction in a diagram format of the inputs,process actions, and outputs of one or moreprocesses within a system.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    42/95

    200442

    PMBOK Guide 2004 Changes

    Develop Project Charter [Process]

    The process of developing the project charter.The Project Charter formally authorizes aproject.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    43/95

    200443

    PMBOK Guide 2004 Changes

    Grade

    A category or rank used to distinguish items thathave the same functional use, but do not sharethe same requirements for quality.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    44/95

    200444

    PMBOK Guide 2004 Changes

    Discipline

    A field of work requiring specific knowledge and

    that has a set of rules governing work conduct.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    45/95

    200445

    PMBOK Guide 2004 Changes

    Dummy Activity

    A schedule activity of zero duration used to show

    a logical relationship in the arrow diagrammingmethod.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    46/95

    200446

    PMBOK Guide 2004 Changes

    Earned Value (EV)

    The value of completed work expressed in terms

    of the approved budget assigned to that work .

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    47/95

    200447

    PMBOK Guide 2004 Changes

    Develop Project Team [Process]

    The process of improving the competencies and

    interaction of team members to enhanceproject performance.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    48/95

    200448

    PMBOK Guide 2004 Changes

    Critical Chain Method [Technique]

    A schedule network analysis technique that

    modifies the project schedule to account forlimited resources.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    49/95

    200449

    PMBOK Guide 2004 Changes

    Design Review [Technique]

    A management technique used for evaluating theproposed design of the system or product to

    ensure that the system or product meets thecustomer requirements, or to assure that thesystem or product will perform successfully,can be produced, and can be maintained.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    50/95

    200450

    PMBOK Guide 2004 Changes

    Executing Processes [Process Group]

    Those processes performed to complete the

    work defined in the project management planto accomplish the project objectives defined inthe project scope statement.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    51/95

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    52/95

    200452

    PMBOK Guide 2004 Changes

    Monitor and Control Project Work [Process]

    The process of monitoring and controlling theprocesses required to initiate, plan, execute,and close a project to meet the performanceobjectives defined in the project managementplan and project scope statement.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    53/95

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    54/95

    200454

    PMBOK Guide 2004 Changes

    Ground Rules [Tool]

    A list of acceptable and unacceptable behaviors

    adopted by a project team to improve workingrelationships, effectiveness, andcommunication.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    55/95

    200455

    PMBOK Guide 2004 Changes

    Manage Stakeholders [Process]

    The process of managing communications to

    satisfy the requirements of, and resolve issueswith, project stakeholders

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    56/95

    200456

    PMBOK Guide 2004 Changes

    Human Resource Planning [Process]

    The process of identifying and documenting

    project roles, responsibilities and reportingrelationships, as well as creating the staffingmanagement plan.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    57/95

    200457

    PMBOK Guide 2004 Changes

    Imposed Date

    A fixed date imposed on a schedule activity or

    schedule milestone, usually in the form of astart no earlier than or finish no later than

    date.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    58/95

    200458

    PMBOK Guide 2004 Changes

    Develop Project Management Plan [Process]

    The process of documenting the actions

    necessary to define, prepare, integrate, andcoordinate all subsidiary plans into a projectmanagement plan.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    59/95

    200459

    PMBOK Guide 2004 Changes

    Methodology

    A system of practices, techniques, procedures,

    and rules used by those who work in adiscipline.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    60/95

    200460

    PMBOK Guide 2004 Changes

    Monitor

    Collect project performance data with respect toobjectives, produce performance measures,and report and disseminate performanceinformation.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    61/95

    200461

    PMBOK Guide 2004 Changes

    Near-Critical Activity

    A schedule activity that has low total float.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    62/95

    200462

    PMBOK Guide 2004 Changes

    Project Summary Work Breakdown Structure(PSWBS) [Tool]

    A work breakdown structure for the project that isonly developed down to the subproject level ofdetail within some legs of the WBS, and wherethe detail of those subprojects are provided byuse of contract work breakdown structures.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    63/95

    200463

    PMBOK Guide 2004 Changes

    Materiel

    The aggregate of things used by an organization

    in any undertaking, such as equipment,apparatus, tools, machinery, gear, material,and supplies.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    64/95

    200464

    PMBOK Guide 2004 Changes

    Planning Package

    A WBS component below the control account

    with known work content but without detailedschedule activities.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    65/95

    200465

    PMBOK Guide 2004 Changes

    Network Path

    Any continuous series of schedule activities

    connected with logical relationships in a projectschedule network diagram

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    66/95

    200466

    PMBOK Guide 2004 Changes

    Planning Processes [Process Group]

    Those processes performed to define and mature

    the project scope, develop the projectmanagement plan, and identify and schedulethe project activities.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    67/95

    200467

    PMBOK Guide 2004 Changes

    Scope Control [Process]

    The process of controlling changes to the projectscope.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    68/95

    200468

    PMBOK Guide 2004 Changes

    Project Management Process Group

    A logical grouping of the project managementprocesses described in the PMBOK guide.

    The 5 project management process groups areinitiating processes, planning processes,executing processes, monitoring andcontrolling processes, and closing processes.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    69/95

    200469

    PMBOK Guide 2004 Changes

    Initiating Processes [Process Group]

    Those processes performed to authorize and

    define the scope of a new phase or project orthat can result in the continuation of haltedproject work.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    70/95

    200470

    PMBOK Guide 2004 Changes

    Program Management

    The centralized coordinated management of aparticular program to achieve the programs

    strategic objectives and benefits.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    71/95

    200471

    PMBOK Guide 2004 Changes

    Portfolio Management [Technique]

    The centralized management of one or moreportfolios, which includes identifying,

    authorizing, managing, and controlling projects,programs, and other related work, to achievespecific strategic business objectives.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    72/95

    200472

    PMBOK Guide 2004 Changes

    Schedule Model

    A model used in conjunction with manual

    methods or project management software toperform schedule network analysis to generatethe project schedule for use in managing theexecution of a project.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    73/95

    200473

    PMBOK Guide 2004 Changes

    Rolling Wave Planning [Technique]

    A form of progressive elaboration planning wherethe work to be accomplished in the near term is

    planned in detail at a low level of the workbreakdown structure, while the work far in thefuture is planned at a relatively high level of thework breakdown structure.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    74/95

    200474

    PMBOK Guide 2004 Changes

    Three-Point Estimate [Technique]

    An analytical technique that uses three cost or

    duration estimates to represent the optimistic,most likely, and pessimistic scenarios.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    75/95

    200475

    PMBOK Guide 2004 Changes

    Project Management Process

    One of 44 processes, unique to projectmanagement and described in the PMBOKguide.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    76/95

    200476

    PMBOK Guide 2004 Changes

    Technical Performance Measurement[Technique]

    A performance measurement technique thatcompares technical accomplishments during

    project execution to the project managementplans schedule of planned technical

    achievements.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    77/95

    200477

    PMBOK Guide 2004 Changes

    Retainage

    A portion of a contract payment that is withheld

    until contract completion to ensure fullperformance of the contract terms.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    78/95

    200478

    PMBOK Guide 2004 Changes

    Voice of the Customer [Technique]

    A planning technique used to provide products,services, and results that truly reflect customer

    requirements by translating those customerrequirements into the appropriate technicalrequirements for each phase of project productdevelopment.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    79/95

    200479

    PMBOK Guide 2004 Changes

    Earned Value Technique (EVT) [Technique]

    A specific technique for measuring theperformance of work for a work breakdown

    structure component, control account, orproject. Also referred to as the earning rulesand crediting method.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    80/95

    200480

    PMBOK Guide 2004 Changes

    Manage Project Team [Process]

    The process of tracking team member

    performance, providing feedback, resolvingissues, and coordinating changes to enhanceproject performance.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    81/95

    200481

    PMBOK Guide 2004 Changes

    Failure Mode and Effect Analysis (FMEA)[Technique]

    An analytical procedure in which each potential

    failure mode in every component of a productis analyzed to determine its effect on thereliability of that component and the reliabilityof the product or system.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    82/95

    200482

    PMBOK Guide 2004 Changes

    Scope Creep

    Adding features and functionality without

    addressing the effects on time, costs andresources, or without customer approval.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    83/95

    200483

    PMBOK Guide 2004 Changes

    Reserve Analysis [Technique]

    An analytical technique to determine the

    essential features and relationships ofcomponents in the project management plan toestablish a reserve for the schedule duration,budget, estimated cost, or funds for a project.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    84/95

    200484

    PMBOK Guide 2004 Changes

    Fast Tracking [Technique]

    A specific project schedule compression

    technique that changes network logic tooverlap phases that would normally be done insequence or to perform schedule activities inparallel.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    85/95

    200485

    PMBOK Guide 2004 Changes

    Special Cause

    A source of variation that is not inherent in the

    system, is not predictable, and is intermittent.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    86/95

    200486

    PMBOK Guide 2004 Changes

    Activity Attributes [Output/Input]

    Multiple attributes associated with each schedule

    activity that can be included within the activitylist.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    87/95

    200487

    PMBOK Guide 2004 Changes

    Path Divergence

    Extending or generating parallel schedule

    network paths from a single node in a projectschedule network diagram.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    88/95

    200488

    PMBOK Guide 2004 Changes

    Enterprise Environmental Factors [Output/Input]

    Any or all external environmental factors and

    internal organizational environmental factorsthat surround or influence the projects

    success.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    89/95

    200489

    PMBOK Guide 2004 Changes

    Pareto Chart [Tool]

    A histogram, ordered by frequency of occurrence,

    that shows how many results were generatedby each identified cause.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    90/95

    200490

    PMBOK Guide 2004 Changes

    Risk Register [Output/Input]

    The document containing the results of the

    qualitative risk analysis, quantitative riskanalysis, and risk response planning.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    91/95

    200491

    PMBOK Guide 2004 Changes

    Control Account Plan (CAP) [Tool]

    A plan for all the work and effort to be performedin a control account. Each CAP has a

    definitive statement of work, schedule, andtime-phased budget.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    92/95

    200492

    PMBOK Guide 2004 Changes

    Value Engineering

    A creative approach used to optimize project life

    cycle costs, save time, increase profits,improve quality, expand market share, solveproblems, and/or use resources moreeffectively.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    93/95

    200493

    PMBOK Guide 2004 Changes

    Virtual Team

    A group of persons with a shared objective who

    fulfill their roles with little or no time spentmeeting face to face.

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    94/95

    200494

    PMBOK Guide 2004 Changes

    Exception Report

    Document that includes only major variations

    from the plan (rather than all variations)

  • 8/3/2019 pmbok2004flashcards-090803215824-phpapp01

    95/95

    PMBOK Guide 2004 Changes

    Workaround [Technique]

    A response to a negative risk that has occurred.Distinguished from a contingency plan in that a

    workaround is not planned in advance of theoccurrence of the risk event.