Phase I Preliminary Plans Pedestrian Walkway Planning Subcommittee (PWP) Stow Planning Board Meeting October 19, 2010

Phase I Preliminary Plans Pedestrian Walkway Planning Subcommittee (PWP) Stow Planning Board Meeting October 19, 2010

Embed Size (px)

Citation preview

Phase I Preliminary PlansPedestrian Walkway Planning

Subcommittee (PWP) Stow Planning Board Meeting

October 19, 2010

Big picture – Walkway Planning in 2 phases

• Phase I - Connect existing walkways along 117 Corridor – Short-term – Plan, design, and construct a few sections of walkway

along the 117 corridor

• Phase II - Prioritize other walkway and maintenance projects– Longer-term – Create a list of recommended projects– Plan for construction including design, maintenance, and

funding.

Phase I Status• Phase I moving along as planned– Upper Common has been taken out off the table

for Phase I construction

• Community Survey Results– 85% supportive of increased walkability

• Phase I Land Survey Results – No major obstacles to construction– A little extra expense in a few places

Status Update (con’t)• Open considerations – Snow removal

• Recent MA Supreme Court Ruling • Need clarification on Stow’s official position/intent

– Crosswalk locations• Town Hall / Town Building• Rt. 62 / 117 Intersection• Harvard Rd.• Hudson Rd

– Parking• Concur with Safety Officer recommendations• Provides safe pedestrian access to overflow parking

Thank you.

EXTRAS

Phase I - Planning • Proposed location of planned walkways:– Public inventory on Google maps http://maps.google.com/ – Research and document feasibility (e.g. physical, legal)– Sample of planned walkway designs from Acton/Sudbury

Walkway Plans, MAPC

• Communication with town and key groups:– Agreement to proceed from Planning Board and Selectmen– Open meetings:

• Benefits and barriers for proposed walkways• Hearings as necessary

Phase I - Implementation

Walkway Design:– Acquire design services either through professional

contract or as a student project

• Walkway Construction:– Contract construction services through a standard bidding

process

• Walkway Funding:– Design: existing walkway fund (~$249k)