Upload
nguyenhanh
View
215
Download
3
Embed Size (px)
Citation preview
1/8/2014
1
Photo by Lovena, Harrisburg, PA
Sustainable Site Development and Conservation Design Considerations for Stormwater Control
Robert Pitt, P.E., Ph.D., BCEE, D.WREDepartment of Civil, Construction, and Environmental EngineeringThe University of Alabama
Conservation Design Approach for New Development
• Better site planning to maximize soil and water resources and topography of site
• Emphasize water conservation and beneficial uses of stormwater on site
• Encourage infiltration of runoff at site• Treat water at critical source areas• Treat runoff that cannot be infiltrated at
site
1/8/2014
2
Roof Runoff Control Options
• Downspout disconnections
• Rain gardens
• Green roofs
• Beneficial use of roof runoff
Directly connected roof drainDisconnected roof drain
One of the simplest and most effective approaches for the control of stormwater is to reduce the amount of impervious areas that are directly connected to the drainage system. This can be accomplished by using less paved and roof areas (hard to do and meet design objectives), disconnect the impervious areas, or reduce the runoff from the impervious areas by infiltration, or other, methods. Reducing the runoff volume also reduces the pollutant discharges, reduces peak flows, and reduces combined sewer overflows.
1/8/2014
3
Roof drain disconnections
Burnsville, Minnesota, Rainwater Gardens
97% Runoff Volume Reduction
An example of the dramatic runoff volume reductions possible through the use of conservation design principles (17 rain gardens, at about $3,000 each, at 14 homes in one neighborhood)
Land and Water, Sept/Oct. 2004
.
1/8/2014
4
Rain Garden Designed for Complete Infiltration of Roof Runoff
Green roof, Portland, OR
1/8/2014
5
Green RoofingExtensive Green Roof
• Lighter
• <6” media depth
• Planted with sedums or native plant species
• Saturated weights from 12-50lbs/sq.ft.
Intensive Green Roof• Heavier• >12” media depth• Wider variety of
plants which need more care and irrigation
• Saturated weights from 80-100lbs/sq.ft.
Urban Heat Island Effect – Atlanta, GA
Urban Temp. - Day Suburban Temp. - Day
Images Courtesy of NASA
Urban Temp. - NightSuburban Temp. - Night
Can a green roof make an urban area look like a suburban area?
1/8/2014
6
Central Alabama
Average daily EToreference conditions (inches/day) (irrigated alfalfa)
January 0.035
February 0.048
March 0.072
April 0.102
May 0.156
June 0.192
July 0.186
August 0.164
September 0.141
October 0.096
November 0.055
December 0.036
Evapotranspiration (ET) is the major rain abstraction mechanism available for green roofs, besides some detention storage and evaporation.
Plant Crop Coefficient Factor (Kc)
Root Depth
(ft)
Cool Season Grass (turfgrass)
0.80 1
Common Trees 0.70 3
Annuals 0.65 1
Common Shrubs
0.50 2
Warm Season Grass
0.55 1
Prairie Plants (deep rooted)
0.50 6
Recent results showing green roof runoff benefits compared to conventional roofing (data from Shirley Clark, Penn State –Harrisburg)
Greater than 65% volume reductions due to ET
1/8/2014
7
Prince George’s County phot
Beneficial use of stormwater as a local resource needs to be seriously considered
Calculated Benefits of Various Roof Runoff Controls (compared to typical directly connected residential pitched roofs)
Annual roof runoff volume reductions
Birmingham, Alabama
(55.5 in. annual rain)
Seattle, Wash. (33.4 in.)
Phoenix, Arizona (9.6 in.)
Flat roofs instead of pitched roofs 13% 21% 25%
Cistern for reuse of runoff for toilet flushing and irrigation
(10 ft. diameter x 5 ft. high)
66 67 88
Planted green roof (but will need to irrigate during dry periods)
75 77 84
Disconnect roof drains to loam soils 84 87 91
Rain garden with amended soils
(10 ft. x 6.5 ft.)
87 100 96
1/8/2014
8
Pavement Runoff Control Options
• Bioretention
• Biofiltration (with underdrains)
• Porous Pavement
Infiltration/Biofiltration
• Infiltration trenches
• Infiltrating swales
• Infiltration ponds
• Porous pavement
• Percolation ponds
• Biofiltration areas (rain gardens, etc.)
1/8/2014
9
Small depressions graded near parking lots or buildings for infiltration (older method, using regular turf grass) (MD and WI).
Portland, Oregon, bioretention areas to capture and treat parking lot runoff.
1/8/2014
10
Parking lot medians easily modified for bioretention (OR and MD).
Larry Coffman
Larry Coffman
Recent Bioretention Retrofit Projects in Commercial and Residential Areas in Madison, Wisconsin
1/8/2014
11
Neenah Foundry Employee Parking Lot Grass Filter/Biofilter, Neenah, Wisconsin
Bioretention and biofiltration areas having moderate capacity
Surface overflow
Portland, Oregon
1/8/2014
12
Stormwater filters and bioretention areas in ultra urban setting (Melbourne, Australia)
Street-side tree biofilters in downtown area (Melbourne, Australia)
1/8/2014
13
Porous paver blocks have been used in many locations to reduce runoff to combined sewer systems, thereby reducing overflow frequency and volumes (Sweden, Germany, and WI).
Not recommended in areas of heavy automobile use due to groundwater contamination (provide little capture of critical pollutants, plus most manufactures recommend use of heavy salt applications instead of sand for ice control).
Essen, Germany
Singapore
Singapore
Austin, TX
Davos, SwitzerlandZurich
1/8/2014
14
Temporary parking or access roads supported by turf meshes, or paver blocks, and advanced porous paver systems designed for large capacity.
Soil modifications for rain gardens and other biofiltration areas can significantly increase treatment and infiltration capacity compared to native soils.
(King County, Washington, test plots)
1/8/2014
15
Grass Filtering of Stormwater Sediment
Runoff from Pervious/
impervious area
Trapping of sedimentsand associated pollutantsReducing velocity of
runoff
Infiltration
Reduced volume and treated runoff
Sedimentparticles
Particulate Removal in Shallow Flowing Grass Swales and in Grass Filters
1/8/2014
16
Head (0ft)
Date: 10/11/2004
2 ft
25 ft
6 ft
3 ft
116 ft
75 ft
TSS: 10 mg/L
TSS: 20 mg/L
TSS: 30 mg/L
TSS: 35 mg/L
TSS: 63 mg/L
TSS: 84 mg/L
TSS: 102 mg/L
Large capacity grass swales and channels designed for both conveyance and water quality objectives.
1/8/2014
17
Grass Swales Designed to Infiltrate Large Fractions of Runoff (Alabama).
Also incorporate grass filtering before infiltration
Swales can be both interesting and fit site development objectives.
Street Edge Alternative (SEA St) Seattle, WA
Tuscaloosa, AL
1/8/2014
18
WI DNR photo
Conventional curbs with inlets directed to site swales
WI
MS
Treatment of Flows in Excess of Infiltration Capacity
• Wet detention ponds, stormwater filters, or correctly-sized critical source area controls needed to treat runoff that cannot be infiltrated.
1/8/2014
19
Wet Detention Ponds
Suspended Solids Control at Monroe St. Detention Pond, Madison, WI (USGS and WI DNR data)
Consistently high TSS removals for all influent concentrations (but better at higher concentrations, as expected)
1/8/2014
20
Wet detention pondsThe regional swales will direct excess water into the ponds.
Typical pond section:
The pond surface areas vary from 0.5 to 1% of the drainage areas, depending on the amount of upland infiltration. The ponds have 3 ft. of standing water above 2 ft. of sacrificial storage. The live storage volume provides necessary peak flow control.
Treatment of Runoff from Critical Source Areas
• Flow diversion
• Treatment trains having combinations of effective unit processes targeted to pollutants of interest
• Pollution prevention through the use of non-contaminating exposed materials
1/8/2014
21
Critical Source Area ControlCovering fueling area
Berm around storage tanks
correctly-sized critical source area controls needed to treat runoff originating from heavily contaminated areas
Austin sand filter
MCTT
1/8/2014
22
Multi-Chambered Treatment Train (MCTT) for stormwater control at large critical source areas
Milwaukee, WI, Ruby Garage
Maintenance Yard MCTT Installation
Pilot-Scale MCTT Test
Results
Ruby Garage MCTT samplesinfluent effluent
1/8/2014
23
Upflow filter insert for catchbasins
Able to remove particulates and targeted pollutants at small critical source areas. Also traps coarse material and floatables in sump and away from flow path.
Upflow FilterTM
Pelletized Peat, Activated Carbon, and Fine Sand
y = 2.0238x0.8516
R2 = 0.9714
0
5
10
15
20
25
0 5 10 15 20
Headloss (inches)
Flo
w (
gp
m)
Performance Plot for Mixed Media on Suspended Soilds for Influent Concentrations of 500 mg/L, 250mg/L, 100 mg/L and 50 mg/L
0
100
200
300
400
500
600
Influent Conc. Effluent Conc.
Su
sp
en
de
d S
oil
ds
(m
g/L
)
High Flow 500
Mid Flow 500
Low Flow 500
High Flow 250
Mid Flow 250
Low Flow 250
High Flow 100
Mid Flow 100
Low Flow 100
High Flow 50
Mid Flow 50
Low Flow 50
High Zinc Concentrations have been Found in Roof Runoff for Many Years at
Many Locations• Typical Zn in stormwater is about 100 g/L, with industrial
area runoff usually several times this level.• Water quality criteria for Zn is as low as 100 g/L for
aquatic life protection in soft waters, up to about 5 mg/L for drinking waters.
• Zinc in runoff from galvanized roofs can be several mg/L• Other pollutants and other materials also of potential
concern.• A cost-effective stormwater control strategy should include
the use of materials that have reduced effects on runoff degradation.
1/8/2014
24
2005: Testing Frame Set-Ups at Penn State-Harrisburg and the University of Alabama at Birmingham
Six frames and 12 panels being tested at each site
Examples Utilizing these Concepts• Retrofitted bioretention and wet ponds at big box
commercial development in VT
• Beneficial use of stormwater at university in AL
• Multi-faceted conservation design at residential development in WI
• Multi-faceted conservation design at industrial site in AL
• Large rain garden at transportation corridor in WI
• Green infrastructure retrofitted in combined sewer area in MO
• Groundwater effects with dry wells in NJ
1/8/2014
25
Big box development stormwater management options.
Summary of Measured Areas• Totally connected impervious areas: 25.9 acres
– parking 15.3 acres
– roofs (flat) 8.2 acres
– streets (1.2 curb-miles and 33 ft wide) 2.4 acres
• Landscaped/open space 15.4 acres
• Total Area 41.3 acres
1/8/2014
26
Stormwater Controls• Biofiltration areas (parking lot islands)
– 52 units of 40 ft by 8 ft– Surface area: 320 ft2
– Bottom area: 300 ft2
– Depth: 1 ft – Vertical stand pipe: 0.5 ft. dia. 0.75 ft high– Broad-crested weir overflow: 8 ft long, 0.25 ft wide
and 0.9 ft high– Amended soil: sandy loam
• Also examined wet detention ponds
Runoff Volume Changes
Base conditions
With biofiltration
Runoff volume (106 ft3/yr)
2.85 1.67
Average Rv 0.59 0.35
% reduction in volume
n/a 41%
1/8/2014
27
Birmingham Southern College Campus (map by Jefferson County Stormwater Management Authority)
Birmingham Southern College Fraternity Row
Acres % of Total
Roadways 0.24 6.6%
Parking 0.89 24.5
Walks 0.25 6.9
Roofs 0.58 16.0
Landscaping 1.67 46.0
Total: 3.63 100.0
1/8/2014
28
Supplemental Irrigation Inches per month (example)
Average Use for 1/2 acre (gal/day)
Late Fall and Winter (Nov-March)
1 to 1-1/2 230 - 340
Spring (April-May) 2 to 3 460 - 680
Summer (June-August)
4 910
Fall (Sept-Oct) 2 to 3 460 - 680
Total: 28 (added to 54 inches of rain)
Capture and Reuse of Roof Runoff for Supplemental Irrigation
Tankage Volume (ft3) per 4,000 ft2 Building
Percentage of Annual Roof Runoff used for Irrigation
1,000 56%
2,000 56
4,000 74
8,000 90
16,000 98
1/8/2014
29
Combinations of Controls to Reduce Runoff Volume
Total Annual Runoff (ft3/year)
Increase Compared to Undeveloped Conditions
Undeveloped 46,000 --
Conventional development 380,000 8.3X
Grass swales and walkway porous pavers
260,000 5.7
Grass swales and walkway porous pavers, plus roof runoff disconnections
170,000 3.7
Grass swales and walkway porous pavers, plus bioretention for roof and parking area runoff
66,000 1.4
Elements of Conservation Design for Cedar Hills Development
(near Madison, WI, project conducted by Roger Bannerman, WI DNR and USGS)
• Grass Swales
• Wet Detention Pond
• Infiltration Basin/Wetland
• Reduced Street Width
1/8/2014
30
Available at: http://pubs.usgs.gov/sir/2008/5008/pdf/sir_2008-5008.pdf
The most comprehensive full-scale study comparing advanced stormwater controls conducted.
90% of the site runoff is associated with rains between 0.2 and 3 inches in depth. These are the events that need attention when trying to reduce runoff at this site. 50% of the rains, by count, are less than 0.15 inches in depth.
1/8/2014
31
Parallel study areas, comparing test with control site
ExplanationWetpond Infiltrations BasinSwalesSidewalkDrivewayHousesLawnsRoadwayWoodlot
N
500 0 500 1000 Feet
Cedar Hill Site Design, Crossplains WI
1/8/2014
32
Roger Bannerman
Initially installed infiltration area had preferential flow paths and compacted soils
Deep Tilled to 18 inches and Planted Native Plants to Restore Infiltration
Infiltration Basin with Compacted Soils
Roger Bannerman
1/8/2014
33
WI DNR photos
Reductions in Runoff Volume for Cedar Hills (calculated using WinSLAMM
and verified by site monitoring)Type of Control Runoff
Volume, inches
Expected Change (being monitored)
Pre-development 1.3
No Controls 6.7 515% increase
Swales + Pond/wetland + Infiltration Basin
1.5 78% decrease, compared to no
controls
15% increase over pre-development
1/8/2014
34
Water Year
Construction
Phase
Rainfall
(inches)
Volume Leaving
Basin (inches)
Percent of Volume
Retained (%)
1999 Pre-construction 33.3 0.46 99%
2000 Active construction 33.9 4.27 87%
2001 Active construction 38.3 3.68 90%
2002
Active construction (site is
approximately 75% built-out)
29.4 0.96 97%
Monitored Performance of Controls at Cross Plains Conservation Design
Development
WI DNR and USGS data
1/8/2014
35
Aerial Photo of Site under Construction (Google Earth)
• On-site bioretention swales• Level spreaders• Large regional swales• Wet detention ponds• Critical source area controls• Pollution prevention (no Zn!)• Buffers around sinkholes•Extensive trail system linking water features and open space
1/8/2014
36
Conservation Design Elements for North Huntsville, AL, Industrial Park
• Grass filtering and swale drainages
• Modified soils to protect groundwater
• Wet detention ponds
• Bioretention and site infiltration devices
• Critical source area controls at loading docks, etc.
• Pollution prevention through material selection (no exposed galvanized metal, for example) and no exposure of materials and products.
• Trail system throughout area.
1/8/2014
37
A new industrial site in Huntsville, AL, has 52 approximately two acre individual building sites. Each of the sites will be served with a grass-lined bioretention channel that will carry site water to a larger swale system. The slopes of the channels vary from about 1 to 6.5%. The peak flow from each construction site was calculated to be about 16 ft3/sec (corresponding to the Huntsville, AL, 25 yr design storm of 6.3 inches for 24 hours). The on-site swales will also have modified soils to increase the CEC and organic matter content to protect groundwater resources.
1/8/2014
38
Slope Bare soil shear stress (lb/ft2)
Unvegetated mat shear stress, effect on soil (lb/ft2)
Safety factor (allowable shear stress of 0.05 lb/ft2)
Maximum velocity with mature vegetation (ft/sec)
1% 0.14 0.012 4.2 3.1
3% 0.28 0.023 2.2 4.8
5% 0.42 0.035 1.4 5.5
6.5% 0.46 0.039 1.3 6.4
The bare swale soil has an allowable shear stress of about 0.05 lb/ft2. The calculated values for unprotected conditions are all much larger. Therefore, a North American Green S75 mat was selected, having an allowable shear stress of 1.55 lb/ft2 and a life of 12 months. Check dams are needed when slopes are >5% due to high velocities.
Annual Runoff Volume (ft3/year)
Drainage Area
Proposed Stormwater Components
Base Conditions
With Controls
A Pond, swale, and site bioretention
6.3 x 106 2.5 x 106 (61%)
B Small pond and swale 5.4 x 106 1.7 x 106 (69%)
C Pond and swale 2.5 x 106 0.83 x 106 (68%)
D (including off-site area)
Off-site pond, swale, and site bioretention
11 x 106 5.8 x 106 (50%)
Total site 25 x 106 11 x 106 (56%)
Different site subareas have different combinations of controls. Base conditions are for conventional development.
Calculated using WinSLAMM and 40 years of rain records
1/8/2014
39
Annual Particulate Solids Discharges
(lb/year)
Drainage Area
Proposed Stormwater Components
Base Conditions
With Controls
A Pond, swale, and site bioretention
98,000 4,400 (96%)
B Small pond and swale 54,000 3,800 (93%)
C Pond and swale 19,000 1,200 (94%)
D (including off site area)
Off-site pond, swale, and site bioretention
120,000 9,250 (92%)
Total site 290,000 19,000 (93%)
Conventional Development
Conservation Design
1/8/2014
40
Conventional Development
Conservation Design
Sediment Reductions
Volume Reductions
1/8/2014
41
City of Lodi, Columbia County WI
Paved Area = 20%
Drainage Basin Area = 16 acres
Lodi, Wisconsin, Transportation Area Rain Garden
John Voorhees
Overflow Weirs
Lodi Rain Garden Features
Cell A
Cell B
Cell C
Access Path
Sitting Area
Flow Diversion Structure
Inlet
John Voorhees
1/8/2014
42
To Rain Garden
Overflow to Creek
Flow Diversion Structure
J h V
Rain Garden Backfill Material
Growing Media
Aggregate for Water Storage
Underdrain Pipe Sends Excess Water to Creek
John Voorhees
1/8/2014
43
Soil/Peat/Sand Mixing
John Voorhees
Cell B
Cell A
John Voorhees
1/8/2014
44
Cell B Cell C
Cell A
John Voorhees
Prairie Plants
Planting Plan
Cell ACell B
Cell C
Scrubs
John Voorhees
1/8/2014
45
Lodi rain garden vegetation (Planted in Spring 2004);
excellent cover 6 to 15 months after planting
Fall 2004
Summer 2005
Spring 2005 John Voorhees
Lodi, WI, Rain Garden CostsPipe Underdrain and Endwalls $700
Flow Regulation Structure $3000
Plants $2200
Shrubs $450
Backfill $11600
Excavation $2200
Select Crushed Material/Riprap $3850
Storm Sewer and Manholes $3500
Total $4.70/sf $27500
John Voorhees
1/8/2014
46
Appropriate Combinations of Controls
• No single control is adequate for all problems
• Only infiltration reduces water flows, along with soluble and particulate pollutants. Only applicable in conditions having minimal groundwater contamination potential.
• Wet detention ponds reduce particulate pollutants and may help control dry weather flows. They do not consistently reduce concentrations of soluble pollutants, nor do they generally solve regional drainage and flooding problems.
• A combination of biofiltration and sedimentation practices is usually needed, at both critical source areas and at critical outfalls.
Combinations of Controls Needed to Meet Many Stormwater Management Objectives
• Smallest storms should be captured on-site for reuse, or infiltrated
• Design controls to treat runoff that cannot be infiltrated on site
• Provide controls to reduce energy of large events that would otherwise affect habitat
• Provide conventional flood and drainage controls
1/8/2014
47
Pitt, et al. (2000)
• Smallest storms should be captured on-site for reuse, or infiltrated
• Design controls to treat runoff that cannot be infiltrated on site
• Provide controls to reduce energy of large events that would otherwise affect habitat
• Provide conventional flood and drainage controls
Combinations of Controls Needed to Meet Many Stormwater Management Objectives