KCRC East Rail ExtensionContract No. TCC-400 Tai Wai Station
No.25 EM&A Report
Prepared for
Maeda Corporation
By
Environmental Management Division
Hong Kong Productivity Council
7th March 2003
KCRC East Rail Extensions
Contract No. TCC-400 Tai Wai Station
(Project Code: 01016494)
No. 25 EM&A Report
Quality Index
Date Reference No. Originator Approved by
7th March 2003 01016494/Mrep25 Daniel Sum K. L. Tsang
TABLE OF CONTENTS
EXECUTIVE SUMMARY
1. INTRODUCTION
1.1 Scope of the Report1.2 Structure of the Report
2. PROJECT INFORMATION
2.1 Background2.2 Site Description2.3 Project Organisation2.4 Project Work Program
3. MONITORING & AUDIT REQUIREMENTS
3.1 Environmental Monitoring and Audit3.2 Air Quality3.3 Noise3.4 Action and Limit Levels3.5 Event/Action Plan
4. IMPLEMENTATION STATUS ON ENVIRONMENTAL PROTECTION REQUIREMENTS
5. ENVIRONMENTAL LICENCING AND PERMITTING REQUIREMENTS
6. MONITORING RESULTS
6.1 Air Quality6.2 Noise
7. AUDIT RESULTS
7.1 Air Quality7.2 Noise7.3 Waste Management7.4 Site Inspection by ET7.5 Site Inspection by IEC7.6 Site Inspection by EPD
8. COMPLAINTS, NOTIFICATIONS OF SUMMONS AND SUCCESSFUL PROSECUTIONSDURING THE REPORTING PERIOD
9. FUTURE KEY ISSUES
10. COMMENTS, RECOMMENDATIONS AND CONCLUSIONS
LIST OF APPENDICES
Appendix A Contact Details of the Project Organization
Appendix B Tentative Work Program
Appendix C Details of Environmental Sensitive Receivers
Appendix D Calibration Records of High Volume Air Samplers, Real-time Aerosol Monitor and
Weather Station
Appendix E Calibration Records of Sound Level Meter and Calibrator
Appendix F Event/Action Plan for Air Quality and Noise
Appendix G Implementation Status of Environmental Protection Requirements
Appendix H 1-hr. and 24-hr. TSP Monitoring Results
Appendix I Graphical Presentation of 1-hr. and 24-hr. TSP Monitoring Results
Appendix J Wind Data Monitoring Results
Appendix K Noise Monitoring Results
Appendix L Graphical Presentation of Noise Monitoring Results
Appendix M Environmental Monitoring Schedules from February to May 2003
Appendix N Complaint Handling Procedures and Corrective and Preventive Actions
Appendix O Complaint Log Book and Corrective and Preventive Action Request Log Book
Appendix P Work Site (Not to Scale)
Appendix Q Organization Structure and Lines of Communications of the Tai Wai Station
Project Team for Environmental Management
Appendix R Air Quality Monitoring Station AM1 and Noise Monitoring Station NM2
Appendix S Cumulative Statistics on Notification of Summons and Successful Prosecutions
EXECUTIVE SUMMARY
This is the No.25 EM&A Monthly Report for the East Rail Extensions - Tai Wai to Ma On Shan (MOSRail) for Contract TCC-400 Tai Wai Station (the Project). This report summarizes the monitoring worksfrom 1st to 28th February 2003.
Summary of Construction Works During the Reporting Period
The major construction works during normal daytime (i.e. Monday to Saturday exclude public holidaysfrom 0700 to 1900 hr) included construction of super-structure at Area 1, building services installation atArea 1 and 2, drainage works at Area 6 as well as construction of pile cap at Area 12.
The major construction works during restricted hours from 17 th to 19th February 2003 (i.e. all days from2300 to 0700 hr of the next day) included erection of tower crane at Area 13 and 14. MAEDA hasmaintained valid construction noise permit during the said period.
Air Quality
For 1-hr. TSP monitoring, a total of 12 sets of measurement were carried out during the reporting period andall measurement results were below the corresponding Action/Limit Levels. No Notification ofExceedance was issued during the reporting period.
For 24-hr. TSP monitoring, a total of four sets of measurement were carried out during the reporting periodand all measurement results were below the corresponding Action/Limit Levels. No Notification ofExceedance was issued during the reporting period.
Noise
For Daytime noise measurement (i.e. 0700 to 1900 hr Monday to Saturday exclude public holidays) interms of LAeq(30min), a total of four sets of measurement were carried out during the reporting period. Two setsof measurement results on 12th and 18th February exceeded the Limit Level of 70 dB(A) and one set ofmeasurement on 24 th February exceeded the corresponding Limit level (65dB(A)) during the schoolexamination period. Based on the observation by the monitoring team, the dominant noise sources duringthe said monitoring periods were the bored piling works for the KCRC property as well as the traffic noisealong Che Kung Miu Road which were not related to the project activities.
For Night-time noise measurement (i.e. Any day 2300 – 0700 on the next day) in terms of LAeq(5min), a totalof one set comprising three consecutive 5-minute measurement was carried out on 19th February 2003 andall measurement results exceeded the Limit Level (40 dB(A)). Based on the on-site observation made bythe sampling team during the measurement, the dominant noise source for elevated measurement result wasthe traffic noise along Che Kung Miu Road. In view of this, the exceedance was not related to the projectactivities.
Waste Management
For Excavated Materials, 10 m3 of the inert excavated materials were arranged to be reused at the site forfilling. At the time of reporting, about 10 m3 were stored at Area 6 & 8 of the site.
On the other hand, about 137 m3 C&D Waste were produced at the site during the reporting period andabout 132 m3 were collected by licenced collector for disposal. At the time of reporting, about 9 m3 werestored at the Area 1, 2, 8 & 10 of the site.
For General Refuse, about 2.2 ton were produced at the site during the reporting period in which 2 ton werecollected by the licenced collectors for disposal and 0.2 ton were arranged to be reused at the site. At the
time of reporting, about 1.1 ton were stored at Area 7, 8 and site office.
Site Inspection
Site inspections conducted by the ET were carried out on 6th, 13th, 18th and 27th February 2003. The majorfindings are summarized as follows:
Item Findings Proposed Mitigation Measures Environmental Outcome1 Accumulation of sediment was
observed at the U-channel atArea 8 and 10
MAEDA has arranged theclearance of sedimentaccordingly
The accumulated sediment wasremoved
2 Stagnant water inside thedesilting tank at Area 1, 8 and12 which might be potentialsource for mosquito breeding
MAEDA have arranged toremove the water
The stagnant water wasremoved
IEC Audit was carried out on 19 th February 2003 and the major observations are as follows:Item Findings Proposed Mitigation Measures Environmental Outcome
1 Accumulation of sediment wasobserved at the U-channelconnected to Shing Mun River
MAEDA has arranged theclearance of sedimentaccordingly
The accumulated sediment wasremoved on 21st February 2003
2 Backoe emitting water smoke MAEDA has arranged Backoeoff-site for maintenance
The Backoe was removed
Site inspection was conducted by EPD on 25th February 2003 and no particular comments were givenduring the visit.
Complaint Log
No complaints were received by the ER, the Contractor and ET during the reporting period.
Notification of Summons and Successful Prosecutions
No notification of summons were received during the reporting period.
Future Key Issues
The tentative program of major site activities as well as the impact prediction and control measures for thenext three months are summarized as follows:
Construction Works Major ImpactPredication
Control Measures
Construction of super-structure at Area 1
l Noise impact l Schedule work time to avoid persistent noisyoperation
l Control the number of plants
l Deployment of noise barrier
Earthworks at Area 6 l Generation of siltywastewater
l Gullies and the footing of hoardings will besealed to avoid untreated wastewater drainedinto the existing drainage system.
l Effluent will be diverted to the sedimentationtank (WetSep) at Area 8 for proper treatmentbefore discharge.
Construction of super-structure at Area 12
l Noise impact l Schedule work time to avoid persistent noisyoperation
l Control the number of plants
l Deployment of noise barrier
Construction of viaductacross Mei Tin Road
l Noise impact l Schedule work time to avoid persistent noisyoperation
l Control the number of plants
l Deployment of noise barrier
KCRC Web Site
The monthly EM&A reports and monitoring data can be accessed on the web athttp://www.env-ere.kcrc.com.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 1
INTRODUCTION
1.1 Scope of the Report
This is the No.25 EM&A Monthly Report for the KCRC East Rail Extensions – Tai Wai to Ma On Shan
(MOS Rail) TCC-400 Tai Wai Station (the Project). This report is prepared by the Environmental
Management Division of Hong Kong Productivity Council (HKPC) for submission to Maeda
Corporation.
This report summarizes the monitoring works from 1 st to 28th February 2003.
1.2 Structure of the Report
The structure of the report is as follows:
Section 1: INTRODUCTION – details the scope and structure of the report.
Section 2: PROJECT INFORMATION – summarizes the background and scope of theproject, project organization, construction programme and the construction worksundertaken during the reporting period.
Section 3: MONITORING & AUDIT REQUIREMENTS – summarizes the monitoringprogrammes, Action and Limit Levels, Event Action Plans, environmentalmitigation measures as recommended in the EIA Report and relevantenvironmental requirements.
Section 4: IMPLEMENTATION STATUS ON ENVIRONMENTAL PROTECTIONREQUIREMENTS – summarizes the implementation of environmental protectionmeasures during the reporting period.
Section 5: ENVIRONMENTAL LICENCE AND PERMITTING REQUIREMENTS –summarizes the environmental licences and permits obtained or being appliedduring the reporting period.
Section 6: MONITORING RESULTS – reports the monitoring results obtained in thereporting period.
Section 7: AUDIT RESULTS – summarizes the audit findings in the reporting period.
Section 8: COMPLAINTS, NOTIFICATIONS OF SUMMONS AND SUCCESSFULPROSECUTIONS DURING THE REPORTING PERIOD – summarizes thecomplaints, notifications of summons and successful prosecutions recorded duringthe reporting period.
Section 9: FUTURE KEY ISSUES – summarizes the future key issues as reviewed from theworks programme and work method statements.
Section 10: COMMENTS, RECOMMENDATIONS AND CONCLUSIONS
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 2
2. PROJECT INFORMATION
2.1 Background
Maeda Corporation (MAEDA) has been commissioned by the Kowloon-Canton Railway Corporation
(KCRC) to undertake the construction of Tai Wai Station, which is one of the stations of the East Rail
Extension’s – Tai Wai to Ma On Shan (MOS Rail).
The contract award date of the Tai Wai Station Project is 27 th November 2000. The construction works of
the Project begin on 19th February 2001. The Project is scheduled to complete by February 2005.
2.2 Site Description
Tai Wai Station is located in a rather dense urban environment, surrounded by schools and residential
high-rises building.
The work site is shown on Appendix P.
2.3 Project Organisation
Appendix Q presents the organization structure of the Project, identifies key members of the Project
Team with environmental responsibilities, and illustrates their lines of communication. The phone and
fax numbers of contact persons at the EPD, KCRC, IEC, MAEDA and HKPC are documented in
Appendix A.
2.4 Project Work Program
The tentative work program for the whole Project is presented in Appendix B. The details of the
construction activities are shown in Table 2.1. The summary of the implementation of environmental
mitigation measures at the site is reported in Section 4 of this Report. The details of the environmental
sensitive receivers are shown in Appendix C.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 3
Table 2.1 - List of Site Activities in February 2003
Area Details of Construction Works1 Construction for superstructure
Wall pastering and painting
Floor screeding
Blockwall erection
Installation of Ticket Office
Installation of roller shutter
Building services installation
Waterproofing for track slab and roof
2 Building services installation
Wall plastering and painting
Floor screeding
Installation of roller shutter, door frame and windows
6 Drainage works
10 Erect of working platform
11 Hoarding erection
12 Construction of pile cap and super-structure
Drainage works
Backfilling and de- stressing anchors
13 & 14 Construction of Railway bridge and Platform bridge
Erection of tower crane*
Note*: Construction works were carried out from 17th to 19 th February 2003 during night time and the Contractor has
maintained valid Construction Noise Permit.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 4
3. ENVIRONMENTAL MONITORING & AUDIT
3.1 Environmental Monitoring & Audit
The monitoring of the environmental impact is carried out by the independent Environmental Team (ET).
The monitoring work includes air quality monitoring of 1-hr and 24-hr total suspended particulate (TSP)
at one selected dust monitoring location, and noise monitoring of LAeq(5min) noise impact at one selected
noise monitoring location.
The environmental monitoring schedule in the reporting period is shown in Appendix M.
3.2 Air Quality
Monitoring Locations
According to Appendix J of the Particular Specification of East Rail Extensions Tai Wai Station Contract
No. TCC-400, one Air Sensitive Receiver (ASR) close to the Tai Wai Station had been identified as
possible location for conducting the monitoring programme. The location is shown in Appendix R and
listed in Table 3.1 below.
Table 3.1 - Air Sensitive Receiver Identified as Possible Location
for Air Quality Monitoring
ASR No. Station I. D. Description Measurement Condition
24 AM1 Grandway Garden, Block 2TSP sampler was set up at the
podium adjacent to Block 2 whichwas about 5 m above ground (whichis adjacent to Tsuen Nam Road and
Mei Tin Road)
Note:
Following the receipt of complaint from the resident of Grandway Garden on 23rd March 2001 regarding the noise
generated from the operation of HVS, the monitoring location was relocated which was about 25 m from the original
location and the subsequent sampling at the new location was carried out since 28 th March 2001.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 5
Wind data monitoring should be carried out at conspicuous location for logging wind speed and wind
direction near the dust monitoring location. Weather station has been established at the roof of the site
office in Area 8 and the wind data monitoring began on 2nd April 2001.
Monitoring Parameters and Frequency
The measurement conditions were in compliance under section 2.5.3 of the approved MOS EM&A
Manual.
Monitoring parameters for air quality monitoring includes 1-hr and 24-hr Total Suspended Particulates
(TSP) at one monitoring location. On the other hand, wind monitoring (wind speed and wind direction)
shall be carried out at conspicuous location for logging wind speed and wind direction near to the air
quality monitor station.
24-hr TSP monitoring shall be carried out once every six days where construction works are carried out.
On the other hand, three sets of 1-hr TSP monitoring shall be carried out once every six days where
construction works are carried out. Wind data monitoring shall be monitored continuously.
Monitoring Methodology
24-hr TSP level is to be measured in accordance with the standard high volume sampling method as set
out in Title 40 of the Code of Federal Regulations (40CFR), Chapter 1 (Part 50), Appendix B. This
method involves the drawing of air at a controlled rate into a high volume sampler (HVS) fitted with a
pre-conditioned and pre-weighted filter paper of size 8” x 10”. After sampling for 24 hours, the filter
paper with retained particles is to be folded in half lengthwise, placed in a labelled plastic bag and
returned to the ET’s laboratory for drying in a desiccator before being weighed on an electronic balance
with accuracy to 0.1 mg. Other information including the elapsed-timer meter reading for start and stop
of the HVS, identification and weight of the filter paper should be recorded on the field data record sheet.
The 24-hr TSP levels are then calculated from the ratio of the mass of particles retained on the filter paper
to the total volume of air sampled in accordance with the method as set out in Title 40 of the Code of
Federal Regulations (40CFR), Chapter 1 (Part 50), Appendix B. All the collected samples shall be kept
in good condition for 6 months before disposal. 24-hr TSP monitoring shall not be normally undertaken
in heavy rainy weather.
1-hr TSP level is to be measured with a handheld real-time aerosol monitor. This meter uses optical
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 6
sensors to analyze the incoming air stream, providing real time readout of particulate concentrations.
1-hr TSP monitoring shall not be normally undertaken in heavy rainy weather.
The wind sensors for wind speed and wind direction monitoring shall be installed at an elevated level 10
m above ground so that they are clear of obstructions or turbulence caused by the buildings. The wind
data shall be captured by a data logger and to be downloaded for processing at least once per month.
Field information such as general meteorological conditions and any significant adjacent dust producing
sources at each monitoring location are to be recorded during monitoring.
Monitoring Equipment
24-hr TSP level is to be measured with high volume samplers conforming to the requirements of 40CFR
Part 50. For 1-hr TSP measurement, a handheld real-time aerosol monitor is to be used. Wind data in
terms of wind speed and direction is to be measured using wind data monitor set up at conspicuous
location which is to be agreed by ER. Details of the monitoring equipment are given in Table 3.2.
Table 3.2 - Air Quality Monitoring Equipment
Parameter Equipment Model
24-hr TSPMeasurement
GRASEBY GMWS-2310-105 High VolumeAir Sampling System
1-hr TSPMeasurement
DustTrak Aerosol Monitor or Laser DustMonitor LD-1(L)
Wind data Davis Weather Monitor II or equivalent
Equipment Calibration
High volume samplers are to be calibrated with orifice calibrator. Five-point calibration is to be carried
out on a bi-monthly basis or after changing of carbon brush. For the handheld real-time aerosol monitor,
span check is to be conducted on a monthly basis. The electronic balance used for the weighing of filter
paper is to be calibrated regularly with a traceable weight standard. The wind data monitoring equipment
shall be re-calibrated once every six months. The methods of calibration of the said equipment are
referred to the instruction manuals provided by the manufacturers respectively.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 7
The calibration records of the high volume air sampler, handheld real-time aerosol monitor and weather
station are shown in Appendix D.
3.3 Noise
Monitoring Locations
According to Appendix J of the Particular Specification of East Rail Extensions Tai Wai Station Contract
No. TCC-400, one Noise Sensitive Receiver (NSR) close to the Tai Wai Station had been identified as
possible location for conducting noise monitoring for baseline purpose and for the construction phase.
The location is listed in Table 3.3 below and is also depicted in Appendix R.
Table 3.3 - Noise Monitoring Locations
MonitoringLocation
MonitoringParameters
Description Frequency MeasurementCondition
NM2 LAeq(30 min) interms of sixconsecutivesets of LAeq(5
min)
Ng Yuk SecondarySchool
Once every six daysduring the
monitoring period
Roof-top building;façade measurementfacing Che Kung Miu
Road, 20 m aboveground
Note:
Monitoring station shall be at a point 1 m from the exterior of the sensitive receiver building facade
Monitoring Parameters and Frequency
The measurement conditions were in compliance under section 3.5.3 of the approved MOS EM&A
Manual.
Impact monitoring shall be carried out at the designated monitoring station during construction phase of
the project. The regular monitoring frequency of each station on a basis of once every six days when
noise generating activities are underway is as follows:
l One set of LAeq (30 min) as six consecutive LAeq (5min) between 0700 – 1900 hours on normal
weekdays;
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 8
l One set of LAeq (15min) as three consecutive LAeq (5min) between 1900 – 2300 hours on normal
weekdays (only if construction works is carried out during these hours);
l One set of LAeq (15min) as three consecutive LAeq (5min) between 2300 – 0700 hours of next day on
normal weekdays and holidays (only if construction works is carried out during these hours);
l One set of LAeq (15min) as three consecutive LAeq (5min) between 0700 – 2300 hours on holidays (only
if construction works is carried out during these hours).
On the other hand, the statistical results such as the L10 and L90 shall be obtained for reference.
Monitoring Methodology
Noise measurement shall be carried out at the assessment point located at about 1 m from the exterior of
the building façade. Field information such as general meteorological conditions and any dominant
noise sources at each monitoring location are to be recorded during monitoring. Wind speed
measurements are to be taken with a portable wind speed meter during monitoring. Noise measurement
is not to be conducted under a steady wind exceeding 5m/s or gust exceeding 10 m/s. Noise monitoring
is not conducted in the presence of fog and rain as well.
Monitoring Equipment
Sound level meters (SLMs) are to comply with specifications of the International Electrical Commission
Publication 651:1979 (Type 1) and 804:1995 (Type 1). Wind shield is to be fitted on the monitor during
use. Details of the monitoring equipment used for noise monitoring are summarized in Table 3.4:
Table 3.4 - Noise Monitoring Equipment
Equipment Function Equipment Model Used
Noise Level Measurement RION Precision Integrating Sound Level Meter NL-18
Calibration of Sound LevelMeter
RION Sound Level Calibrator NC-73
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 9
Equipment Calibration
Before and after each measurement, the reading of SLM is to be checked with the acoustic calibrator and
the measurements can only be accepted as valid if the calibration levels from before and after the noise
measurement agree to within 1.0 dB. Also, calibrations of the SLM and acoustic calibrator are to be
carried out annually. The calibration certificates of the SLMs and calibrator are shown in Appendix E.
3.4 Action and Limit Levels
Action and Limit levels of Air Quality
Baseline measurement of 1-hr. and 24-hr. TSP at one monitoring location were conducted in August and
September 2000. According to Section 2.7 of the EM&A Manual for MOS Rail (prepared by Binnie
Black & Veatch Hong Kong Limited dated January 2001), the Action/Limit Levels for the monitoring
location were established with the baseline results. The Action/Limit Levels of 1-hr. and 24-hr. TSP is
shown in Table 3.5.
Table 3.5 - 24-hr. and 1-hr. TSP Action and Limit Levels
Level (µg/m3) AM1
24-hr. TSP
Baseline Level
64.4
(32.9 – 106.0)
24-hr. TSP
Action Level
172
24-hr. TSP
Limit Level
260
1-hr. TSP
Baseline Level
282
(251 – 352)
1-hr. TSP
Action Level
367
1-hr. TSP
Limit Level
500
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 10
Note:
1. The detailed monitoring results are referred to the Baseline Monitoring Report (Final) prepared by Binnie
Black & Veatch Hong Kong Limited
2. Values presented in backets are the range of the measurement results
Action and Limit Levels of Noise
The Action/Limit Levels for construction noise as stipulated in the EM&A Manual are given in Table
3.6.
Table 3.6 - Noise Action and Limit Levels
Time Period Action Level Limit Level
0700 - 1900 hours onweekdays
When one documented complaint isreceived
70(1) dB(A)
1900 - 2300 hours onweekdays, and 0700 -2300 hours on general
holidays includingSundays
When one documented complaint isreceived
55(2) dB(A)
2300 - 0700 hours of alldays
When one documented complaint isreceived
40(2) dB(A)
Note:
1. Limit Level will be revised to 65 dB(A) during school examination period.
2. For works carried out within Designated Areas during restricted hours, Limit Levels given here are
suggestive only, given that Local Control Division of EPD will reserve the right to determine appropriate
Areas Sensitively Ratings and Limit Levels in the form of CNP conditions on a case by case basis. The
Contractor shall obtain a copy of Technical Memorandum on Noise from Construction Work in Designated
Areas for reference.
3.5 Event/Action Plan
The Event/Action Plan for Air Quality and Noise are shown in Appendix F.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 11
4. IMPLEMENTATION STATUS ON ENVIRONMENTAL PROTECTION
REQUIREMENTS
The Contractor implemented various environmental mitigation measures as stipulated in the EIA Report
and the environmental requirements as stipulated in the Environmental Permit and Environmental
Management Plan. The implementation status during the reporting period is summarized in Appendix G.
In case of identification of non-conformance during the implementation of environmental mitigation
measures, remedial measures will be summarized in the Corrective and Preventive Action Request
(CPAR) form issued by the QA/QC & Environmental Engineer. The cumulative log of the CPAR is
summarized in the CPAR Logbook as shown in Appendix O of the Report.
5. ENVIRONMENTAL LICENCING AND PERMITTING REQUIREMENTS
The status of permit, licence and notification to EPD for all relevant environmental issues in this project
is summarized in Table 5.1 and Table 5.2 as of the reporting period.
Table 5.1 – Summary of the status of permit, licence and notification to EPD
as of the Reporting PeriodDescription Submission Date Issued Date Expiry
DateStatus
Further Environmental Permit(FEP)
(FEP No. FEP-01/039/2000)
22-Nov-00 21-Dec-00 -- Issued
Effluent Discharge Licence 29-Dec-00 27-Apr-01 26-Apr-06 IssuedApplication of Variation ofEffluent Discharge Licence
(Permit No. 2659)
30-Jan-02 14-May-02 26-Apr-06 Issued
Notification of ConstructionWork under APCO:
General Work 26-Nov-02 -- -- RenewDemolition of Happy Dragon
Creation Park23-Jan-00 31-Jan-01 -- Notified
Registration as Chemical WasteProducer pursuant to WDO
01-Feb-01 22-Mar-01 -- Issued
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 12
Table 5.2 - Summary of the status of CNP Application as of the Reporting Period
CNP Details Period SubmissionDate
IssuedDate
ExpiryDate
Status
Extension forErection and
dismantling H-beamacross Mei Tin Road
at Area 14(GW-TN0007-2003)
Any day from 2300- 0700 of the next
day
31-Dec-02 17-Jan-03 17-Jul-03 Issued
Extension forerection of
scaffolding at Area 1(GW-TN0016-2003)
Any day from 2300- 0700 of the next
day
7-Jan-02 24-Jan-03 21-Jul-03 Issued
Dismantling the catchfencing at Area 12
Any day from 2300- 0700 of the next
day
20-Feb-03 -- -- Acknowledgedreceipt
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 13
6. MONITORING RESULTS
6.1 Air Quality
1-hr. TSP Measurement
The 1-hr. TSP measurement results of the air monitoring location AM1 are detailed in Appendix H and
are also presented graphically in Appendix I . Table 6.1 summarizes the 1-hr. TSP measurement results
for the air monitoring location AM1.
Table 6.1 - 1-hr. TSP Measurement Results at AM1 in February 2003
1-hr. TSP (µg/m3)Range of
Measurements
Action Level(µg/m3)
No. ofExceedance
Limit Level(µg/m3)
No. ofExceedance
75-157 367 Nil 500 Nil
24-hr. TSP Measurement
The 24-hr. TSP measurement results of the air monitoring location AM1 are detailed in Appendix H and
presented graphically in Appendix I. Table 6.2 summarizes the 24-hr. TSP measurement results for the
air monitoring location AM1.
Table 6.2 - 24-hr. TSP Measurement Results at AM1 in February 2003
24-hr. TSP (µg/m3)Range of
Measurements
Action Level(µg/m3)
No. ofExceedance
Limit Level(µg/m3)
No. ofExceedance
68-98 172 Nil 260 Nil
The wind data recorded throughout the monitoring period is enclosed in Appendix J.
Weather and other Influencing Factors During the Monitoring Period
Details of the weather and other influencing factors as may be observed during the monitoring works for
1-hr. and 24-hr. TSP during the monitoring period are shown in Appendix H.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 14
6.2 Noise
Based on the site diary, daytime construction works during normal working days (i.e. any day not being
holiday between 0700 – 1900 hr) and erection of tower crane from 17th to 19th February 2003 (i.e. any day
between 2300 – 0700 hr of the next day) were carried out during the reporting period. During this
reporting period, four sets of Daytime measurements and one set of Night-time measurement were
carried out respectively.
Daytime noise measurement results of LAeq(30min) and Night-time noise measurement results of LAeq(5min)at
NM2 are summarized in Table 6.3a and 6.3b respectively below and shown in Appendix K of this Report.
The measurement results are also presented graphically in Appendix L. Details of the weather and other
influencing factors during the monitoring period are shown in Appendix K.
Table 6.3a - LAeq(30min) Measurement Results at NM2 in February 2003
Calculated Construction NoiseLAeq(30min), dB(A)1
Range of Measurements
Limit Level dB(A) No. of Exceedance
68.4-71.2 70 Three
Table 6.3b - LAeq(5min) Measurement Results at NM2 in February 2003
Calculated Construction NoiseLAeq(5min), dB(A)1
Range of Measurements
Limit Level dB(A) No. of Exceedance
53.9-56.5 40 Three(2)
Note:
1. Calculated construction noise is derived from the measured noise levels from the sound level meter and the
baseline noise data
2. The measurement exceedances occurred on the sampling day on 19th February 2003.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 15
7. AUDIT RESULTS
7.1 Air Quality
The 1-hr. and 24-hr. TSP measurements at the air monitoring location AM1 were all below the
corresponding Action/Limit Levels.
7.2 Noise
For Daytime noise measurement (i.e. 0700 to 1900 hr Monday to Saturday exclude public holidays) in
terms of LAeq(30min), a total of five sets of measurement were carried out on 3rd ,9th , 15th , 21st and 27th
January 2003 during the reporting period and all measurement results were below the Limit Level (70
dB(A))..
For Night-time noise measurement (i.e. Any day 2300 – 0700 on the next day) in terms of LAeq(5min), a total
of one set comprising three consecutive 5-minute measurement was carried out on 16th January 2003 and
all measurement results exceeded the Limit Level (40 dB(A)). Based on the on-site observation made by
the sampling team during the measurement, the dominant noise source for elevated measurement result
was the traffic noise along Che Kung Miu Road. In view of this, the exceedance was not related to the
project activities.
7.3 Waste Management
Wastes from this Project include construction and demolition (C&D) waste, excavated materials,
chemical waste, asbestos waste, contaminated materials and general refuse. The EIA Study has
determined that with appropriate mitigation measures, impact from wastes would not become
unacceptable. The waste management issue covers the handling of C&D waste, excavated materials,
chemical waste, asbestos waste, contaminated materials and general refuse.
Based on the information provided by MAEDA according to the relevant handling records for the Waste
Management Plan of this project, the quantity and handling practices of different categories of waste are
summarized in Table 7.1.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 16
Table 7.1 - Summary of Different Categories of Waste during the Reporting Period
Material Type QuantityProduced inReporting
Period
Handling Practices HandlingQuantitiesas of 28 th
February2003
Accumulatedhandling
Quantities as of28th February
2003
StorageLocations
(if applicable)
StorageQuantity as of28th February
2003
To be delivered to publicfilling barging point for thegovernment approvedpublic filling barging point(PFBP) at Kai Tak
0 m3 12030 m3 Area 6
To be reused at the site forfilling
10 m3 4105 m3 Area 6 & 8
Excavatedmaterials
0 m3
To be delivered and reusedat the Contractor's own
outlets, MTRC #603 – BackHill Tunnel
0m3 250 m3 --
10 m3
To be delivered to publicfilling barging point for thegovernment approvedpublic filling barging pointat Kai Tak
0 m3 1994 m3C&D waste(inert waste)
0 m3
To be recycled at site 0 m3 132 m3
Area 8 5 m3
5 m3 To be recycled at site 5 m3 492 m3 Area 8 2 m3
0.5 ton To be returned to supplier(steel bar)
0 ton 473.61 ton Area 8 0.5 tonC&D waste
(non-inert waste)
132 m3 Collected by licencedcollector for disposal
132 m3 4076 m3 Area 2, Area 1& Area 10
2 m3
Chemical waste 0 L To be collected by licencedwaste collector for disposal
0 L 2701 L ChemicalWaste StorageArea in Area 8
10.5 L
Asbestos waste Nil n.a. n.a. n.a. n.a. n.a.Contaminated
materialNil n.a. n.a. n.a. n.a. n.a.
2 ton Collected by licenced
collector for disposal
2 ton 169 ton Area 7 1 tonGeneral waste
0.2 tonTo be recycled or reused0.2 ton4.7 tonArea 8, site
office
0.1 ton
Note:
1. No asbestos waste and contaminated materials were identified at the site during the reporting period and
therefore no specific handling practices for the said wastes were carried out.
2. The transportation of the C&D waste, excavated materials, chemical waste and general waste were
arranged by trucks.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 17
7.4 Site Inspection by ET
Site inspections conducted by the ET were carried out on 6th, 13th, 18th and 27th February 2003. The
following major observations were made by the ET:
l Accumulation of sediment was observed at the U-channel at Area 8 (6th, 13th, 18th and 27th February
2003) and Area 10 (6th and 13thFebruary 2003). MAEDA has arranged the clearance of sediment
accordingly.
l Stagnant water inside the desilting tank at Area 12 (18th February 2003), U-channel at Area 8 and
inside the super-structure at Area 1(27th February 2003) and which might be potential source for
mosquito breeding. MAEDA have arranged to remove the water accordingly.
MAEDA has carried out the said remedial measures accordingly for the said observations and they were
found effective for the improvement of the environmental performance of the construction site during
subsequent weekly inspection by ET.
7.5 Site Inspection by IEC
Site inspections conducted by the IEC was carried out on 19th February 2003 and the major comments
were as follows:
Non-compliances:
l Nil.
Observations:
l Accumulation of sediment was observed at the U-channel connected to Shing Mun River. MAEDA
has arranged the clearance of sediment accordingly
l Backoe emitting water smoke was observed. For this. MAEDA has removed the Backoe
accordingly.
The said follow-up action carried out by MAEDA was reviewed by ET during the subsequent site visit.
ET was in general satisfied with the effectiveness of the mitigation measures and the environment was
improving.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 18
7.6 Site Inspection by EPD
Site inspection was conducted by EPD on 25th February 2003 and no particular comments were given
during the visit.
8. COMPLAINTS, NOTIFICATION OF SUMMONS AND SUCCESSFUL PROSECUTIONS
DURING THE REPORTING PERIOD
No complaints were received by the ER, the Contractor and ET during the reporting period.
The cumulative statistics on the notification of summons and successful prosecutions are shown in
Appendix S.
KCRC East Rail Extensions TCC-400Tai Wai Station
Prepared for Maeda CorporationNo.25 EM&A Monthly Report
Environmental Management DivisionHong Kong Productivity Council
GPS\EMA\01006494\MREP25.DOCPage 19
9. FUTURE KEY ISSUES
The tentative program of major site activities as well as the impact prediction and control measures for
the next three months are summarized in Table 9.1 as follows:
Table 9.1 Tentative Program of Major Site Activities for the Next Three Months
Construction Works Major ImpactPredication
Control Measures
Construction of super-structure at Area 1
l Noise impact l Schedule work time to avoid persistentnoisy operation
l Control the number of plants
l Deployment of noise barrier
Earthworks at Area 6 l Generation of siltywastewater
l Gullies and the footing of hoardingswill be sealed to avoid untreatedwastewater drained into the existingdrainage system.
l Effluent will be diverted to thesedimentation tank (WetSep) at Area 8for proper treatment before discharge.
Construction of super-structure at Area 12
l Noise impact l Schedule work time to avoid persistentnoisy operation
l Control the number of plants
l Deployment of noise barrier
Construction of viaductacross Mei Tin Road
l Noise impact l Schedule work time to avoid persistentnoisy operation
l Control the number of plants
l Deployment of noise barrier
The tentative environmental monitoring schedule from March to May 2003 is shown in Appendix M .
10. COMMENTS, RECOMMENDATIONS AND CONCLUSIONS
The environmental monitoring results indicated that the operations of the site activities by the Contractor
during the reporting period were in general comply with the relevant environmental requirements except
on the implementation of mitigation measures as mentioned in the findings as shown in Section 7.4 and
7.5 of the Report.