Upload
others
View
11
Download
0
Embed Size (px)
Citation preview
Ministry of Industry and Trade
General Directorate of Energy
German Development Cooperation
GRID INTEGRATION OF WIND POWER IN VIETNAM
ON THE EXAMPLE OF BINH THUAN PROVINCE
10/2012
GIZ/MoIT Wind Energy Project
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
2
Prepared by Vietnam Institute of Energy – 6/ 2012
Contents
CHAPTER 1. INTRODUCTION.....................................................................................................................3
1.1. LEGAL FRAMEWORK FOR THE STUDY .........................................................................................3 1.2. CURRENT STATUS AND PLANNED REGIONAL WIND POWER DEVELOPMENT .......................3
1.2.1 Programme of wind power development in Vietnam ..................................................................3 1.2.2 Current status and planned wind power development of Binh Thuan province .........................4
1.3. CURRENT STATUS AND PLANNED REGIONAL ELECTRICAL NETWORK DEVELOPMENT ......6 1.3.1 Power source ..............................................................................................................................6 1.3.2 220kV network ............................................................................................................................7 1.3.3 110kV network ............................................................................................................................7
1.4. POWER DEVELOPMENT PROGRAMME OF BINH THUAN PROVINCE ..................................... 12 1.4.1 Load forecast ........................................................................................................................... 12 1.4.2 Power source development programme .................................................................................. 12 1.4.3 Electrical network development programme ............................................................................ 13
1.5. STUDY OBJECTIVES ..................................................................................................................... 17 2.1. DIAGRAM OF CURRENT CONNECTION ...................................................................................... 18 2.2. MODEL FOR WIND POWER PLANT.............................................................................................. 18 2.3. MODEL ASSUMPTIONS ................................................................................................................ 21
2.3.1 Electric load .............................................................................................................................. 21 2.3.2 Power source ........................................................................................................................... 21 2.3.3 Electrical network ..................................................................................................................... 21 2.3.4 Some of applicable standards on transmission and distribution network in Vietnam .............. 21
2.4. IMPACTS ON LOADING CAPACITY OF REGIONAL ELECTRICAL NETWORK .......................... 24 2.4.1 Normal operating mode, without Tuy Phong wind power plant ............................................... 24 2.4.2 Normal operating mode, with Tuy Phong wind power plant (30MW) ...................................... 26
2.5. IMPACTS ON VOLTAGE VARIATION AT CONNECTION POINTS AND ADJASCENT NODES .. 29 2.6. IMPACTS ON SHORT-CIRCUIT CURRENT .................................................................................. 29 2.7. IMPACTS ON HARMONIC ............................................................................................................. 30
2.7.1 Harmonic wave overlapping ..................................................................................................... 30 2.7.2 Impacts of harmonic on electrical system ................................................................................ 31 2.7.3 Special simulations .................................................................................................................. 31 2.7.4 Study results of 300MW wind power plant in Binh Thuan province ......................................... 32
2.8. IMPACTS ON FLICKER .................................................................................................................. 32 2.8.1 Flicker ....................................................................................................................................... 32 2.8.2 Study results at 30MW wind power plant in Ninh Thuan province .......................................... 33
3.1. EXPECTED CONNECTION DIAGRAM .......................................................................................... 34 3.1.1 Alternative 1 ............................................................................................................................. 35 3.1.2 Alternative 2 ............................................................................... Error! Bookmark not defined. 3.1.3 Alternative 3 ............................................................................... Error! Bookmark not defined.
3.2. MODEL FOR WIND POWER PLANT.............................................................................................. 39 3.3. MODEL ASSUMPTIONS ................................................................................................................ 40
3.3.1 Power load ............................................................................................................................... 40 3.3.2 Power source ........................................................................................................................... 40 3.3.3 Electrical network ..................................................................................................................... 40 3.3.4 Some applicable standards on transmission and distribution network in Vietnam .................. 41
3.4. IMPACTS OF WPP ON LOADING CAPACITY OF LOCAL ELECTRICAL NETWORK .................. 41 3.4.1 Normal operating mode, with Tuy Phong 30 MW WPP ........................................................... 41 3.4.2 Normal operating mode, with 340MW of wind power .............................................................. 46 3.4.3 Failure mode ............................................................................................................................ 75
3.5. IMPACTS ON SHORT-CIRCUIT CURRENT .................................................................................. 79 3.6. IMPACTS OF HARMONIC ON ELECTRICAL SYSTEM ................................................................. 82
3.6.1 Input assumptions .................................................................................................................... 82 3.6.2 Results of harmonic calculation ............................................................................................... 82
3.7. IMPACTS ON FLICKER .................................................................................................................. 82 4.1. CONCLUSIONS .............................................................................................................................. 84 4.2. RECOMMENDATIONS ................................................................................................................... 85
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
3
Prepared by Vietnam Institute of Energy – 6/ 2012
CHAPTER 1. INTRODUCTION
1.1. LEGAL FRAMEWORK FOR THE STUDY
Economic Contract No. 83110458 between German Development Cooperation (GIZ) and Vietnam
Institute of Energy (IE).
Power development master plan of Binh Thuan province in the period 2011-2015, with the vision to 2020,
developed in November 2011.
National power development master plan in the period 2011-2020, with the vision to 2030, approved by
the Prime Minister under Decision No. 1208/QD-TTg dated July 21st, 2011.
Electricity law, taking effect on July 1st, 2005.
Circular No. 12/2010/TT-BCT dated April 15th, 2010 approved by Ministry of Industry and Trade
“Stipulating transmission power system”.
Circular No. 32/2010/TT-BCT dated July 30th, 2010 approved by Ministry of Industry and Trade
“Stipulating distribution power system”.
1.2. CURRENT STATUS AND PLANNED REGIONAL WIND POWER DEVELOPMENT
1.2.1 Programme of wind power development in Vietnam
Nowadays, with seriously environmental pollution and exhausted fossil energy sources, many countries in
the world have started to study various forms of renewable energy to replace traditional forms of energy.
Renewable energy is very diverse, for example wind energy, solar energy, tidal energy, geothermal
energy and biomass energy. According to [1], the Vietnamese Government has prioritized policy to
developing power generated from renewable energy resource, gradually increase the density of this
energy resource. It is expected that total capacity of wind power source will increase from the insignificant
level (about 31 MW) at present to nearly 1,000 MW by 2020 and nearly 6,200 MW by 2030.
Vietnam is located in the range of 80 ÷ 23
0 Northern latitude in the area of monsoon tropical climate, with
two main seasons a year, the regions having good wind potential only account for 2% of the territorial
area, mostly coastal regions and highlands, most of the other regions have wind regime of 2 – 4 m/s.
Wind potential in some coastal regions and islands which have wind speed of over 4 m/s (at the altitude
of 12m above the ground) can apply wind power sources [1]. According to World Bank’s report wind
potential in Vietnam at the altitude of 65m is as follows:
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
4
Prepared by Vietnam Institute of Energy – 6/ 2012
Table Error! No text of specified style in document..1 Wind energy potential according to the WB report (2001)
Characteristic
Wind speed (m/s)
Low
(< 6)
Average
(6 – 7)
Relative high
(7 – 8)
High
(8 – 9)
Very high
(> 9)
Area (km2) 197,342 100,361 25,679 2,178 113
Area (%) 60.6 30.8 7.9 0.7 0.0
Potential (MW) 401,444 102,716 8,748 452
Wind potential in Vietnam concentrates mostly in the southern central coastal region and southern coastal
provinces such as Tra Vinh and Soc Trang.
1.2.2 Current status and planned wind power development of Binh Thuan province
Binh Thuan province has 4 topographical forms: sand hill and coastal sand dune, alluvial delta, hill region
and low mountainous regions. Natural area of the province is 7,812.9km2 including 49,644.8 ha of unused
land. With the above terrain and existing natural conditions Binh Thuan has much potential for renewable
energy. Considering wind potential Binh Thuan province has abundant wind all year, high wind speed is
very beneficial to wind power development.
From 1998 to 2000 tens of households in Tuy Phong district used household power-generating wind fans
but the efficiency was not high due to lack of experience in equipment repair and maintenance.
From 2006 to 2010 Binh Thuan province gave priority to wind power in its development objective with a
series of big wind power projects. At present, in Binh Thanh commune, Tuy Phong district are 20 wind
power turbines with total capacity of 30MW (1.5MW per turbine) which have been generating power to
supply for 100kW electric network of the province.
According to [2], wind potential of Binh Thuan province has the following characteristics:
Binh Thuan is a province with great wind energy potential which is capable of developing wind power at
industrial scale in all districts/towns except for Duc Linh and Tanh Linh districts.
According to wind atlas the most potential districts/towns are coastal districts/towns in the East, namely
Tuy Phong, Bac Binh, Phan Thiet, Southern Ham Thuan, Northern Ham Thuan, Tham Tan and La Gi.
Table Error! No text of specified style in document..2 Local distribution of technical and economic wind resource potential ịn Binh Thuan province (PECC3 2011)
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
5
Prepared by Vietnam Institute of Energy – 6/ 2012
Region Commune, town/district Area (ha) Planned capacity (MW)
R1 Vĩnh Tân, Vĩnh Hảo, Phước Thể, Liên Hương, Bình
Thạnh, Chí Công, Phong Phú, Phan Rí, Phan Hoà 4,512 301
R2 Hoà Phú, Phan Rí Thành, Chợ Lầu, Hoà Thắng 7,526 502
R3 Hoà Thắng, Hồng Phong, Thiện Nghiệp, Mũi Né,
Hàm Tiến, Phú Long 4,381 292
R4 Tiến Thành, Hàm Mỹ, Hàm Kiện, Hàm Cường,
Thuận Quý, Tân Thành 5,181 345
R5 Tân Tiến, Tân Bình, Phước Lộc, Tân Phước 1,205 80
R6 Hồng Thái, Lương Sơn, Sông Bình, Sông Luỹ, Bình
Tân, Hồng Liêm 744 50
Total 23,549 1,570
Total area of economic – technical wind potential of Binh Thuan is 23,549ha, accounting for 3% of total
area of the province allocated by wind speed as presented in the above table. Total installed wind power
capacity in the planning period is estimated to be 1,570MW.
Table Error! No text of specified style in document..3 Local distribution of wind speed (PECC3 2011)
District Wind speed (m/s) Area (ha) Location (commune, town)
Tuy Phong
6.0 – 6.5 3,357 Phong Phú, Vĩnh Tân, Vĩnh Hảo, Phú Lạc, Hoà Minh, Chí Công, Hoà Phú
6.5 – 7.0 3,380 Phong Phú, Vĩnh Tân, Vĩnh Hảo, Phú Lạc, Phước Thể, Liên Hương, Bình Thạnh, Hoà Minh, Chí Công, Phan Rí Cửa, Hoà Phú
7.0 – 7.5 1,525 Vĩnh Tân, Vĩnh Hảo, Phú Lạc, Phước Thể, Liên Hương, Bình Thạnh, Chí Công, Hoà Phú
7.5 – 8.0 463 Phước Thể, Liên Hương, Bình Thạnh
8.0 – 8.5 31 Bình Thạnh
Bắc Bình
6.0 – 6.5 22,726
Phan Hoà, Phan Rí Thành, Phan Hiệp, Chợ Lầu, Hoà Thắng, Hồng Phong, Hồng Thái, Lương Sơn, Sông Luỹ, Bình Tân, Bình An, Hải Ninh, Phan Thanh, Sông Bình
6.5 – 7.0 5,060 Phan Hoà, Phan Rí Thành, Phan Hiệp, Chợ Lầu, Hoà Thắng, Hồng Phong, Hồng Thái,
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
6
Prepared by Vietnam Institute of Energy – 6/ 2012
Lương Sơn, Sông Luỹ, Bình Tân
7.0 – 7.5 4,140 Hoà Thắng
7.5 – 8.0 1,013 Hoà Thắng
Hàm Thuận Bắc 6.0 – 6.5 10,844
Hàm Tri, Thuận Hoà, Hàm Liên, Hàm Hiệp, Ham Chính, Hàm Đức, Hồng Sơn, Hồng Liêm, Phú Long
6.5 – 7.0 86 Hồng Liêm, Phú Long
Phan Thiết
6.0 – 6.5 3,406 Thiện Nghiệp, Mũi Né, Tiến Thành
6.5 – 7.0 4,152 Thiện Nghiệp, Mũi Né, Tiến Thành
7.0 – 7.5 325 Thiện Nghiệp, Mũi Né
Hàm Thuận Nam
6.0 – 6.5 8,380 Hàm Mỹ, Hàm Cường, Thuận Quý, Tân Thành, Tân Thuận, Hàm Minh, Hàm Thạnh, Mường Mán
6.5 – 7.0 2,169 Hàm Mỹ, Hàm Kiện, Hàm Cường, Thuận Quý, Tân Thành
La Gi
6.0 – 6.5 3,206 Tân Tiến, Tân Bình, Bình Tân, Tân Phước, Tân Thiện, Tân Hải, Tân An
6.5 – 7.0 1,205 Tân Tiến, Tân Bình, Bình Tân, Phước Hội, Phước Lộc, Tân Phước, Tân Thiện
Total potential wind power capacity is 1,570MW including 12 investment projects which have been
registered and approved by Binh Thuan Provincial People’s Committee. These 12 projects are located in
four regions having financial wind potential, namely 1, 2, 3, 4.
1.3. CURRENT STATUS AND PLANNED REGIONAL ELECTRICAL NETWORK DEVELOPMENT
1.3.1 Power source
Power source supplied for Binh Thuan province is mainly from the national electric network [4] including:
Ham Thuan Hydroelectric Plant (consisting of two 150MW units), generates electricity to the network
through three 220kV lines: line 271 to Da Mi Hydroelectric Plant, line 272 to Long Thanh station and line
273 to Bao Loc station. In addition, the plant generates electricity to 110kV network through three lines:
line 173 to Duc Linh station, line 172 and line 171 to Phan Thiet station.
Da Mi Hydroelectric Plant (consisting of two 87.5MW units) generates electricity to 220kV network
including 2 lines: line 271 to Ham Thuan Hydroelectric Plant, line 272 to Long Thanh 220kV transformer
station.
Dai Ninh 300MW Hydroelectric Plant.
Bac Binh 33MW Hydroelectric Plant.
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
7
Prepared by Vietnam Institute of Energy – 6/ 2012
Binh Thuan wind power plant 1 (phase 1, capacity of 30 MW).
Da Nhim Hydroelectric Plant (consisting of four 40MW units) generates electricity to 220kV network
through 2 lines: line 271 to Bao Loc, line 272 to Nha Trang station; generates electricity to 110kV network
including 3 lines: line 171 to Duc Trong, line 172 to Thap Cham and line 173 to Cam Ranh.
Phu Quy island district currently has 1 Diesel power plant (belonging to EVN) with a capacity of 5x500kW
and nearly 30 generators which are owned by customers with total capacity of approximately 1MW.
1.3.2 220kV network
According to [3], Binh Thuan province currently has three 220kV transformer stations and five 220kV
lines, specifically as follows:
Table Error! No text of specified style in document..4 220 kV transmission grid systems in Binh Thuan province
No. DZ Voltage (kV) Diameter (mm) Circuit × km
1 Long Thành – Đa Mi 220 AC400 1 × 124
2 Long Thành – Hàm Thuận Hydropower 220 AC400 1 × 140.79
3 Đa Mi Hydropower – Hàm Thuận Hydropower 220 AC400 1 × 15
4 Hàm Thuận Hydropower – Bảo Lộc 220 AC400 1 × 29
5 Hàm Thuận Hydropower – Phan Thiết 220 AC400 1 × 55
Existing 220kV transformer stations are:
Ham Thuan 220kV hydroelectric station (63MVA).
Dai Ninh 220kV hydroelectric station (63MVA).
Phan Thiet 220kV station (125MVA).
Ham Thuan 220kV hydroelectric station (63MVA) and Dai Ninh 220kV hydroelectric station (63MVA) are
normaly in full load (80.5% - 85.7%). Phan Thiet 220kV station (125MVA) put into operation in July 2010
is now overloaded (14.4%-20.8%) and has to be supported by Ham Thuan station (63MVA).
1.3.3 110kV network
At present, Binh Thuan province is supplied with power from the following 110kV stations:
Phan Thiet 110/22/15kV station - (40+63MVA) is supplied with power from Ham Thuan-Phan Thiet and
Thap Cham-Phan Thiet 110kV lines.
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
8
Prepared by Vietnam Institute of Energy – 6/ 2012
Luong Son 110/22kV station – 25MVA is supplied with power from Thap Cham-Luong Son and Ham
Thuan - Phan Thiet - Luong Son 110kV lines.
Phan Ri 110/22kV station - (16+25MVA) is supplied with power from Thap Cham - Phan Ri, Ham Thuan -
Phan Thiet - Phan Ri 110kV lines and Dai Ninh - Phan Ri hydroelectric plant.
Ham Tan 110/22kV station – 40MVA is supplied with power from Ba Ria - Long Dat - Xuyen Moc - Ham
Tan 110kv lines (source from Ba Ria 220kV station) and Phan Thiet - Ham Thuan Nam - Ham Tan 110kv
lines.
Duc Linh 110/22kV station – 25MVA is supplied with power from Ham Thuan -Duc Linh and Xuan Truong
- Duc Linh 110kV hydroelectric plant.
Ham Thuan Nam 110/22kV station (2x40MVA) is supplied with power from Ham Tan - Ham Thuan Nam
and Phan Thiet- Ham Thuan Nam 110kV lines.
Mui Ne 110/22kV-40MVA station is supplied with power from Phan Thiet - Mui Ne 110kV line.
Table Error! No text of specified style in document..5 Existing operation of 110 kV transformers in Binh Thuan province
No. Transformer Machine Voltage
(kV) Capacity
(MVA) Pmax (MW)
Load (%)
1 Phan Thiết
T1 110/22 40 38.5 103.7
T2 110/22 63 58.2 101.8
2 Lương Sơn T1 110/22 25 20.8 96.0
3 Phan Rí
T1 110/22 25 19.5 83.4
T2 110/22 16 - -
4 Hàm Tân T1 110/22 40 37.0 99.7
5 Đức Linh T1 110/22 25 18.9 81.2
6 Hàm Thuận Nam
T1 110/22 40 38.2 104.1
T2 110/22 40 30.3 82.7
7 Mũi Né T1 110/22 40 23.6 65.9
Total 354
220/110kV high voltage source station - 45MVA Binh Thuan wind power plant 1.
110kV transformer stations are currently in full load and overload such as Phan Thiet station (both
machines are overloaded, T1: 101.8% and T2: 103.7%), Luong Son station 96%, Phan Ri station 83.4%,
but there is a standby 16MVA machine. For Thuan Nam station (2x40MVA) because of being controlled 2
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
9
Prepared by Vietnam Institute of Energy – 6/ 2012
machines bear load of 82.7%-104.1% in peak months (blue dragon fruit crop in 6-8 months/year). In other
locations load is very low T2 is not operated and T1 bears 8.3MV load.
Table Error! No text of specified style in document..6 Existing operation of 110 kV transmission grids in Binh Thuan province
No. Grid No. Circuits Diameter Length (km) Pmax (MW)
1 220kV Phan Thiết – Phan Thiết 2 AC-185 1.0 81.9/78.2
2 Hàm Thuận – Phan Thiết 2 ACSR-185 57.06 44.0/37.9
3 Phan Rí – Phan Thiết 1 AC-185 67.4 29.3
4 Phan Thiết – Mũi Né 1 ACSR-185 1.0 24.5
5 Phan Thiết – Thuận Nam 1 ACSR-185 27.4 70.1
6 Thuận Nam – Hàm Tân 1 ACSR-185 34.0 54.4
7 TĐ Hàm Thuận – Đức Linh 1 ACSR-185 53.0 18.9
8 Xuyên Mộc – Hàm Tân 1 ACSR-185 47.9 67.1
9 Đại Ninh – Phan Rí 1 AC-240 40.0 37.0
10 Ninh Phước – Phan Rí 1 ACSR-185 56.1 22.0
11 Nhánh rẽ Thuận Nam 2 ACSR-185 0.1 67.4/54.4
12 Xuân Trường – Đức Linh 1 ACSR-185 24.6 -
13 Nhánh rẽ Lương Sơn 1 ACSR-185 0.5 20.8
The above table shows that at present among 110kV lines supplying power for Binh Thuan province,
some lines are in full load such as Phan Thiet 220kV – Phan Thiet 110kV, Phan Thiet – Thuan Nam
110kV.
According to [3], current electric network map and principle diagram of Binh Thuan province are shown in
the following figure.
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
10
Prepared by Vietnam Institute of Energy – 6/ 2012
Figure Error! No text of specified style in document..1 Current power transmission system of Bình Thuận province
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
11
Prepared by Vietnam Institute of Energy – 6/ 2012
Figure Error! No text of specified style in document..2 Curent power grid system diagram of Bình Thuận province
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
12
Prepared by Vietnam Institute of Energy – 6/ 2012
1.4. POWER DEVELOPMENT PROGRAMME OF BINH THUAN PROVINCE
1.4.1 Load forecast
Load of Binh Thuan province is divided into 5 parts, load forecast by 2015 is based on:
Power consumption and load development trend in the past.
Socio-economic development planning of the province in the next 5-10 years.
Results of load forecast according to [3] are as follows:
Table Error! No text of specified style in document..7 Load forecasting until 2015 in Binh Thuan province (PECC3 2011)
No. Sector Load forecast (MW)
2010 2015
1 Agro - Forestry - Firshery 256.2 452.3
2 Industry - Construction 202.4 704.1
3 Commerical Services 66.3 224.5
4 Management and residential consumers 435.8 771.9
5 Other activities 22.5 49.6
6 Total commercial power 983.2 2,202.4
7 Pmax (MW) 270 524
By 2015, demand for commercial power of the province is expected to increase by 2 times, maximum
capacity also doubled.
1.4.2 Power source development programme
The following power source development programme of Binh Thuan province is only limited to the
projects operated from present to 2015. According to [1], [3], the following power source projects will be
put into operation:
Vinh Tuan thermoelectric plant 2, units 1&2, 2x600MV operated in 2014 and connected by 220kV and
500kV voltage levels.
Wind power plants. According to [3] – page 131, potential wind power plants according to planning are
705MW including 30MW be operated. The feasibility of projects will depend on the actual situation and
financial ability of investors. In this study, according to [5], recommended total wind power source in the
region by 2015 is 340MW (approximately 1/2 of planned volume and the most feasible projects),
specifically as follows:
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
13
Prepared by Vietnam Institute of Energy – 6/ 2012
Table 1.8 Wind power projects applying in this study
Project name Capacity (MW) Owner
Tuy Phong project 120 REVN
Phú Lạc project 50 Thuận Bình Wind power JSC
Phước Hữu project 50 EAB Viet Windpower
Hòa Thắng project 120 PV Power
According to [3], wind power plants will be connected to 22kV bus bar through 22/110kV transformer
generated to 110kV network and transmitted to consumption stations in the region.
1.4.3 Electrical network development programme
In order to meet highly increasing demand for electric load transmission and distribution electric
networks in Binh Thuan province need to be improved and upgraded. According to [3], by 2015, 100kV
electric network items which need to be upgraded and improved in the period 2011-2015 are as follows:
Table 1.9 110 kV stations in Bình Thuận province planned until 2015
No. 110 kv Station Capacity (MVA) Status
1 Vĩnh Hảo industrial zone 63 Build
2 TBA Hòa Thắng 40 Build
3 TBA Ma Lâm 40 Build
4 TBA KCN Sơn Mỹ 40 Build
5 TBA Hàm Kiệm 63 Build
6 TBA Tân Thành 25 Build
7 TBA Phan Rí 25+63 Increase capacity
8 TBA Lương Sơn 25+63 Increase capacity
9 TBA Hàm Tân 40+63 Increase capacity
10 TBA Phan Thiết 2x63 Increase capacity
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
14
Prepared by Vietnam Institute of Energy – 6/ 2012
11 TBA Thuận Nam 2x63 Increase capacity
12 TBA Mũi Né 2x40 Increase capacity
110 kV line
Improve Phan Ri – Dai Ninh line, circuit 2 ACKP240 – 43 km
Build Luong Son – Hoa Thang – Mui Ne 110kV line, double circuit, pre-suspending 1 circuit, AC240-
25.9 km.
Shunt line to Vinh Hao industrial zone, double 110kV circuit, AC240-0.5 km.
Build Ham Thuan – Phan Thiet hydroelectric line AC400 - 57 km.
Build circuit 2 of Phan Thiet – Ham Tan – Son My line AC400 – 71 km
Build circuit 2 of Phan Thiet – Mui Ne line AC240 – 25 km.
Build Han Kiem – Than Thanh – Ham Tan line AC240 – 52 km.
Electric network map and principle of Binh Thuan province in 2015 are in the following figure:
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
15
Prepared by Vietnam Institute of Energy – 6/ 2012
Figure Error! No text of specified style in document..3 Map of planned power transmission system until 2015 of Bình Thuận province
Grid Integration of Wind Power in Vietnam on the example of Binh Thuan Province – GIZ/MoIT Wind Energy Project
16
Prepared by Vietnam Institute of Energy – 6/ 2012
Figure Error! No text of specified style in document..4 Planned power grid system diagram until 2015 of Bình Thuận province
17
Newly built, upgraded and improved items of transformer station and line will be important input to
simulate the electric network of Binh Thuan province in the study into impacts of wind power plants on
electric system.
1.5. STUDY OBJECTIVES
The main objectives of the grid study are as follows:
• To review the situation of the existing transmission network and planned transmission network
reinforcements (both short-term and long-term) in the BinhThuan province.
• To carry out a grid connection study for the existing 30MW wind farm in the BinhThuan
province.
• To identify the challenges associated with the development of wind power in the BinhThuan
province until the year 2015.
• To give recommendations for further studies that should be conducted to better understand the
impact that the future wind power development in Vietnam will have on the grid.
18
CHAPTER II. EXPERIENCE IN CONNECTING 30 MW WIND
POWER PLANT IN BINH THUAN PROVINCE
2.1. DIAGRAM OF CURRENT CONNECTION
According to project [6], Tuy Phong wind power plant is located in Lien Huong commune, Tuy Phong
district, Binh Thuan province, 1.5km away from Phan Ri – Ninh Phuoc 110kV line. Phase 1 of Tuy
Phong wind power plant (capacity of 30MW) has been operated with 20 units, 1.5MW each, the plant is
connected to the system by supplying 110kV voltage through Tuy Phong 110kV (45MVA) station,
transitionally connecting to Phan Ri – Ninh Phuoc 110kV line. According to [7], the current connection
diagram of Tuy Phong wind power plant is presented in the following figure.
Figure Error! No text of specified style in document..5 Grid-connected diagram of Tuy Phong wind power plant
2.2. MODEL FOR WIND POWER PLANT
According to [6], the detailed connection diagram of 20 wind turbines is in the following figure.
19
Figure Error! No text of specified style in document..6 Grid-connected diagram of Tuy Phong wind
turbines
There 20 wind turbines are divided into 4 blocks which are connected by 22kV cable lines which are
connected to 22kV bus bar of Tuy Phong station through 22/110 kV transformer generating to regional
110kV network.
According to [8], current wind turbines are FL D77 type, capacity of 1,500kW.
Technical parameters of this type of turbine are in the following figures.
Figure 2.7 Power curve of FL MD 77 turbine
Table 2.10 Technical parameters of FL MD 77 turbine
No. Items Value
1 Rotor
Nominal power 1,500 kW
Diameter/ Swept area 77 m/ 4,657 m2
Power control Pitch
Speed 9.2 – 17.3 rd/min
Hub height 61.5 m – 85 m – 100 m/ 111.5 m
2 Gear box Combined spur wheel/planet;
stages: 3; Multiplication: 1 : 104
3 Generator
Design Double-fed three-phase
20
asynchronous machine
Voltage (frequency) 690 V (50/60 Hz)
Converter system Puls-width modulated IGBT
4 Brake system
Main brake Blade angle adjustment
2nd
brake system Disk brake
5 Tower Tubular tower
6 Control
Start wind 3.0 m/s
Stop wind 20 m/s
Survival speed 50.1 m/s
7 Weights
Rotor 33,400 kg
Nacelle 56,000 kg
Tower 93,000 – 260,000 kg
This is Doubly-Fed Induction Generator (DFIG) with the diagram as follows:
Figure Error! No text of specified style in document..8 Doubly-Fed Induction Generator in a wind
turbine
21
2.3. MODEL ASSUMPTIONS
The model used for calculation in 2011 is 500 – 220 – 110 kV electrical system of Vietnam in which 110
kV network is only used for Binh Thuan province.
2.3.1 Electric load
The load in Binh Thuan province is supposed to be located at 110kV bus bars. The load value of
stations is compliant with actual statistics [3].
Capacity factor of the load at 110kV bus bar in Binh Thuan province: compliant with the average actual
value, cosφ= 0.95
2.3.2 Power source
Current power source and connection are taken from actual data [7], data of generating units are taken
from database set [1].
For wind turbines data are taken from technical parameters of German Fuhrleander FL MD77 – 1,500
kW wind turbine.
2.3.3 Electrical network
Data on the electrical network used for simulation such as connection point, conductor cross- section,
loading capacity, length, resistance, reactance, susceptance are taken from database of [1], [3] and
[7].
2.3.4 Some of applicable standards on transmission and distribution network in
Vietnam
When connecting any power plant to the electric system it is necessary to conform to regulations
promulgated under Circular No. 12/2010/TT-BCT [9] stipulating transmission system and Circular No.
32/2010/TT-BCT[10] stipulating distribution system.
Some of specific regulations are:
Table Error! No text of specified style in document..11 Admissible voltage variation at connection point
Voltage (kV) Operating mode
Normal operation Single failure mode
22
500 475 ÷ 525 450 ÷ 550
220 209 ÷ 242 198 ÷ 242
110 104 ÷ 121 99 ÷ 121
For 35kV, 22kV distribution networks:
In normal operating mode admissible operating voltage at the connection point is permitted to fluctuate
in comparison with nominal voltage as follows:
At connection point with power user: ±5%;
At connection point with power plant: +10% and -5%.
During single failure mode or stable operation restoration after failure admissible voltage fluctuation at
connection point with power user directly affected by failure is in the range of +5% and –10% compared
with nominal voltage.
Harmonic in transmission network:
Admissible maximum value of total voltage deformation level (calculated by % of nominal voltage)
caused by high-order harmonic components for 110kV, 220kV and 500kV voltage levels should be 3%
or less.
Admissible maximum value of total load deformation level (calculated by % of nominal voltage) for
110kV, 220kV and 500kV voltage levels should be 3% or less.
Harmonic in distribution network:
Table Error! No text of specified style in document..12 The harmonic distortion in distribution network
Voltage (kV) Total harmonic distortion Individual harmonic distortion
110 3,0% 1,5%
Medium and low 6,5% 3,0%
Voltage flicker:
Admissible maximum voltage flicker in transmission network is set out as follows.
Table Error! No text of specified style in document..13 Voltage flicker on transimission network
Voltage (kV) Plt95% Pst95%
110, 220, 500 0,6 0,8
For distribution network, in normal operating mode, voltage flicker at all connection points should not
exceed the limit set out in the following table:
Table Error! No text of specified style in document..14 Voltage flicker on distribution network
23
Voltage (kV) Admissible flicker
110 Pst95% = 0,80
Plt95% = 0,60
Medium Pst95% = 1,00
Plt95% = 0,80
Low Pst95% = 1,00
Plt95% = 0,80
Regulations on short-circuit current:
On transmission network short-circuit current should not exceed the values set out in following table:
Table Error! No text of specified style in document..15 Short-circuit current on trasmission network
Voltage (kV) Admissible maximum value (kA)
500 40
220 40
110 31,5
For distribution network admissible maximum short-circuit current is set out in following table:
Table Error! No text of specified style in document..16 Admissible maximum short-circuit current on distribution network
Voltage (kV) Admissible maximum value (kA)
Medium 25
110 31,5
Admissible load operating mode on transmission network (according to [9] article 56):
Transmission system operates in the emergency mode when: load level of any electric equipment in
transmission network or electric equipment connected to transmission network exceeds norm value but
no less than 110% of norm value at which this equipment, in the event of overload, may lead to the
extreme emergency operating mode.
Transmission system operates in the extreme emergency mode when: load level of any equipment in
transmission network or electric equipment connected to transmission network is more than 110% of
norm value at which this equipment, in the event of overload, may lead to partial disintegration of the
electric system.
24
2.4. IMPACTS ON LOADING CAPACITY OF REGIONAL ELECTRICAL NETWORK
2.4.1 Normal operating mode, without Tuy Phong wind power plant
In this mode, calculation results of active power, reactive power trend distribution of 110kV network at
220/110 kV transformers and 110kV lines without Tuy Phong wind power plant are presented in the
following table. Detailed diagram is given in the appendix:
It can be seen that in this operating mode only transformer station of Ham Thuan 220/110kV
hydroelectric plant is overloaded, 110kV lines operate normally within admissible limits.
25
26
2.4.2 Normal operating mode with Tuy Phong wind power plant (30MW)
In this mode, calculation results of active capacity, reactive capacity trend distribution of 110kV network
at 220/110 kV transformers and 110kV lines with Tuy Phong wind power plant are presented in the
following table. The calculation applies to 2 cases: maximum load in rainy season and minimum load in
dry season. The detailed diagram is given in the appendix:
The table of results shows that in maximum mode in rainy season Tuy Phong wind power plant (30MW)
connected to the electric network of Binh Thuan province reduces load of transmission lines and cuts
down load for two 220/110kV transformer stations, namely Ham Thuan and Dai Ninh hydroelectric
plants (since Tuy Phong wind power plant supplies power directly for local load, thus reducing power
flow mobilized from the system). In minimum mode in dry season all lines and 220kV transformer
stations operate normally within admissible limits.
27
28
29
2.5. IMPACTS ON VOLTAGE VARIATION AT CONNECTION POINTS AND ADJASCENT NODES
After calculating the capacity trend results of voltage at connection points of wind power plant and
adjacent nodes in modes are obtained: maximum load in rainy season without wind power plant;
maximum mode in rainy season with Tuy Phong wind power plant (30MW); minimum mode in dry
season with Tuy Phong wind power plant (30MW). Results of 220kV and 110kV voltage comparison
are presented in the following table. The detailed diagram is given in the appendix.
The table shows that voltage at most of 220kV and 110kV voltage nodes falls within the range of
+10%/-5% Udm. Voltage at some nodes is improved when there is a wind power plant operating such as
Ninh Phuoc, Ninh Son, Mui Ne and Phan Ri, etc.
2.6. IMPACTS ON SHORT-CIRCUIT CURRENT
Using PSS/E programme short circuit current at nodes with or without wind power plant can be
calculated as follows.
Table 2.11 Short-circuit current at nodes without and with wind power plant
Node number
Node Voltage (kV)
Without Tuy Phong wind plant
With Tuy Phong wind plant (30 MW)
Difference (%)
3 phase short circuit current (A)
1 phase short circuit current (A)
3 phase short circuit current (A)
1 phase short circuit current (A)
3 phase short circuit current (A)
1 phase short circuit current (A)
54201 TĐ Hàm Thuận 220 13947 13083 13978 13118 0.22% 0.26%
54202 Phan Thiết 2 220 5186 3367 5205 3415 0.35% 1.39%
54205 TĐ Đại Ninh 220 11751 11281 11782 11314 0.26% 0.30%
54206 TĐ Đa My 220 11032 9877 11048 9889 0.14% 0.12%
54305 Hàm Tân 110 3730 2047 3730 2048 -0.01% 0.03%
54306 Thuận Nam 110 4399 2406 4404 2413 0.10% 0.29%
54308 Phan Thiết 110 8288 5647 8352 5755 0.77% 1.88%
54309 Mũi Né 110 3385 1897 3388 1904 0.07% 0.32%
54311 Lương Sơn 110 4569 2678 4721 3064 3.21% 12.59%
54312 Phan Rí 110 4602 2815 4872 3664 5.53% 23.16%
54313 Tuy Phong WPP 110 3585 2079 3950 3713 9.24% 44.00%
30
54316 TĐ Bắc Bình 110 4113 4092 4158 4136 1.09% 1.07%
54318 Rẽ Lương Sơn 110 4644 2729 4802 3132 3.27% 12.85%
54321 TC 110kV Hàm Thuận 110 5687 4751 5691 4755 0.08% 0.10%
54322 TC 110kV Phan Thiết 2 110 8380 5768 8442 5872 0.74% 1.78%
54323 TĐ Đại Ninh 110 4505 4543 4565 4620 1.32% 1.68%
Calculation results show that 3 phase short-circuit current at nodes increases slightly up to 9.24% at
Tuy Phong node the node currently connected to Tuy Phong wind power plant (30MW). 1 phase short-
circuit current increases greatly, up to 44% also at Tuy Phong node. In conclusion, connection of wind
power plant to the electric system increases short circuit current at connection points and adjacent
nodes.
2.7. IMPACTS ON HARMONIC
With wind turbines using digital converter these converters will generate harmonics during continuous
operation of turbine. Two important parameters to be considered are current of each harmonic and total
current of all harmonics. According to IEC 61400-21, standard on wind turbine harmonics with
amplitude of less than 0.1% of basic harmonic it can be skipped.
2.7.1 Harmonic wave overlapping
Normally, in a wind farm are many wind power generating units. During continuous operation of each
wind power generating unit using digital converter, various volumes of harmonics will be generated
depending on location and capacity of such unit. In extreme case when harmonics are in the same
phase angle the amplitude of harmonic will be biggest. In case of different types of wind turbines it is
difficult to determine harmonic volume simultaneously generated by these turbines. So, wind power
standard IEC 61400-21 suggests a formula to estimate value of each harmonic type.
β
β
∑=
Σ
=
wtN
i i
ih
hn
II
1
, (1)
Wherein: WtN - number of wind turbines at main connection points;
ΣhI - total current of level h harmonic at main connection points (PCC);
in - increasing rate of transformer of turbine i;
ihI , - level h harmonic wave current of turbine i;
β - exponent, given in following table.
31
Harmonic number β
h < 5 1.0
5 ≤ h ≤10 1.4
h > 10 2.0
In the event wind turbines have the same capacity and the same type of control, harmonics will have
the same phase angle and factor β = 1 should be used with every harmonic.
Formula (1) does not consider using transformers with various line winding groups, it is possible to
eliminate a certain number of harmonics. In the event of using these transfomers it is necessary to
further work out their impacts (for example: transformer with triangle winding group may emilinate
harmonics which are multiple of 3 such as 3, 6, 9, etc.)
2.7.2 Impacts of harmonic on electrical system
Main impacts of harmonic on electric system are normally capacity loss, electric power quality,
equipment overload such as capacitor, reactor and especially resonance and fluctuation in the system.
With wind power plants directly connected to electric system through a short cable the whole plant can
be seen as an unit at the main connection point. Harmonic current of this source is calculated by
formula (1). Voltage harmonics are calculated by current value multiplies impedance at connection
points in the system.
With wind power plants connected to the system through long cable (wind turbines are located on the
beach) it is advisable to study more carefully impacts of harmonics on the system since resonance is
highly possible. Resonance frequency may change due to operating conditions of transmission
network. Therefore, harmonics of voltage noise should be calculated at the highest level of total
resonance at connection points of PCC which can be shown by using formula (1) to calculate impacts
of all wind turbines in the plant on voltage harmonic noise.
In extreme case, the calculation of voltage harmonic noise will be applied to designe harmonic filter if it
is necessary.
2.7.3 Special simulations
In some cases, filters are used right at wind turbines to avoid resonance that may damage turbine.
In other cases, level 3, 6, 9… harmonics may appear which are zero sequence waves. Since the
standard IEC 61400-21 requires simulation only at low side of generator end transformer, in this case,
study is needed to point out the problems that may arise by these harmonics by measuring and
simulating harmonics at high side of transformer. (Zero sequence harmonics may cause triangle coil of
this transformer to be overloaded).
32
2.7.4 Study results of 300MW wind power plant in Binh Thuan province
Binh Thuan wind power plant is the first big capacity wind power plant in Vietnam using 15 FL 1500kW
wind turbines made by Fuhrlander. These wind turbines have IGBT-PMW converters with capacity of
30% turbine capacity. Major strength of this converter is that it creates relatively small harmonic
volume.
With wind power plant in Binh Thuan province the main connection point is 2kV side of the wind power
plant. Since this plant has small capacity it can be considered that above system is linear and has very
big capacity compared to the wind power plant. Therefore, major study results are as follows:
The biggest harmonic is level 4 harmonic with current value of 0.7% Idm.
Total current of all harmonics is 1.1% Idm.
Total voltage of all harmonics is 0.17% Udm.
The biggest voltage harmonic is level 5 harmonic, with value of 0.09% Udm.
It can be seen that calculated values of harmonics are very small and fall within admissible range of
IEC 61000-3 standard.
2.8. IMPACTS ON FLICKER
2.8.1 Flicker
According to definition of electric power quality flicker is a quantitative characteristic for human feeling
under the pressure of light flickering in a time unit. Major cause of light flickering is change in voltage
amplitude of luminaries for difference reasons (mostly due to change in active capacity big reaction of
source or load). This phenomenon is quite popular when using air turbine equipment, due to following
reasons:
• Continuous change in wind turbine capacity, wind speed.
• Processes of turning on/off of wind turbine.
Flicker of wind turbine is normally calculated according to IEC 61400-21 standard. According to this
standard, short-term flicker - Pst and long-term flicker Plt should be calculated. These values should be
smaller than admissible value Pst < 1.3 Plt <1; To calculate flicker values the following parameters are
needed:
• Short circuit capacity at connection point Sn;
• The angle between resistance and reactance at connection point ψ;
• Flicker factor c(ψk);
• Pitch factor of flicker, frequency kf;
• Conversion factor of voltage kU;
• The number of most short-term turn-off times N10;
• The number of most long-term turn-off times N120;
In case of continuous operation, flicker is calculated by the following formula:
33
k
n
akltstS
ScPP ).,( νψ== (2)
For the plant with N similar turbines stltst PNPP == ΣΣ
In case of operation in turn-off mode:
k
n
kfstS
SkNP ).(..18
31,0
10 ψ= (3)
k
n
kfltS
SkNP ).(..8
31,0
120 ψ= (4)
If calculation results do not meet the standards on voltage flickers some measures are needed to
reduce flicker to below admissible value. The most popular measure is using high quality and fast
reaction voltage adjusters such as FACTS (SVC or STATCOM).
2.8.2 Study results at 30MW wind power plant in Ninh Thuan province
Results of short-circuit current calculated are as follows:
System High supply
(Max. regime)
Low supply
(Min. regime)
Short-circuit capacity Sk (MVA) 420 252
Angle X/R (DEGREE 0) 77.2 76.6
Results of flicker calculated are as follows:
System Pst = Plt
(continous)
Pst (switch) Plt (switch)
Start up at cut in wind
speed
Start up at rated wind
speed
Start up at cut in wind
speed
Start up at rated wind
speed
High supply 0.0480 0.0304 0.0486 0.0257 0.0411
Low supply 0.0799 0.0506 0.0809 0.0428 0.0685
Short-term and long-term flickers are stipulated differently according to standards or grid code of each
country. Normally, values range from 0.3 to 1.3. Calculation results show that flicker values of Binh
Thuan wind power plant are quite far from admissible values. Therefore, Binh Thuan 30 MW wind
power plant can operate normally without back end measures to meet the requirements concerning
voltage flicker.
34
CHAPTER 3. CONNECTING 340 MW WIND POWER
PLANT IN 2015 TO ELECTRICAL NETWORK IN BINH THUAN
PROVINCE
3.1. EXPECTED CONNECTION DIAGRAM
According to section 1.4.2, there are 4 most feasible locations for building wind power plant in Binh
Thuan province from present to 2015, namely:
+ Tuy Phong 12 MW wind power plant (including 30 MW being operated)
+ Phu Lac 50 MW wind power plant
+ Phuoc Huu 50 MW wind power plant
+ Hoa Thang 120 MW wind powr plant
Locations of four wind power plants are presented the following map.
Figure Error! No text of specified style in document..9 Locations of wind power plants
The electrical network of Binh Thuan province in 2015 is compliant with [3].
Based on locations of wind power plants local electrical network development programme three
connection alternatives are suggested:
35
Alternative 1:
+ 110kV transformer station of Hoa Thang wind power plant (120MW) transitionally connected to Luong
Son – Phan Ri 110V line.
+ 110kV transformer station of Tuy Phong wind power plant (120MW), with capacity increased to
2x63MVA.
+ 110kV transformer station of Phu Lac wind power plant (50MW) transitionally connected to Tuy
Phong 110kV line – Vinh Hao industrial zone.
+ 110kV transformer station of Phuoc Huu wind power plant (50MW) transitionally connected to Ninh
Phuoc – Thap Cham 110kV line.
Alternative 2:
+ 110kV transformer station of Hoa Thang wind power plant (120MW) connected to Hoa Thang 110kV
transformer station by 110kV line.
+ 110kV transformer station of Tuy Phong wind power plant (120MW), capacity increased to 2x63MVA,
in addition one 110kV line is connected to Phan Ri 110kV transformer station, forming 2 circuits.
+ 110kV transformer station of Phu Lac wind power plant (50MW) transitionally connected to Tuy
Phong 110kV line – Vinh Hao industrial zone.
+ 110kV transformer station of Phuoc Huu wind power plant (50MW) transitionally connected to Ninh
Phuoc – Thap Cham 110kV line.
Alternative 3:
+ 110kV transformer station of Hoa Thang wind power plant connected to Hoa Thang 110kV
transformer station and Phan Ri 110kV transformer station through 2 single lines.
+ 110kV transformer station of Phu Lac wind power plant (50MW) transitionally connected to Tuy
Phong 110kV line – Vinh Hao industrial zone.
+ 110kV transformer station of Phuoc Huu wind power plant (50MW) transitionally connected to Ninh
Phuoc – Thap Cham 110kV line.
Connected diagram of these alternatives are the following:
36
37
38
39
3.2. MODEL FOR WIND POWER PLANT
It is assumed that wind turbines have the same capacity of 2.000 kW, 6 turbines are connected into 1
group transmitting to 22/110kV station.
Table 3.17 Technical parameters of 2000 kW turbine
No. Items Value
1 Rotor
Nominal power 2,000 kW
Diameter/ Swept area 92.5 m/ 6,720 m2
Power control Pitch
Speed 7.8 – 15.0 rd/min (+12.5%)
Blade 3 blades, 42.2 m
2 Gear box Combined spur wheel/planet
Multiplication 1 : 120
3 Generator
Design Double-fed three-phase asynchronous
machine
Voltage (frequency) 690 V
Speeed 900 – 1800 rd/min
Ingress Protection Rating IP 54
4 Brake system Blade angle adjustment
5 Tower
Design Tubular tower with steel
Hub height 78.5 m/ 80 m/ 100 m
6 Control
Start wind 3.0 m/s
Rated wind 11.2 m/s
40
Stop wind 24.2 m/s
Figure 3.2 Power curve of 2,000 kW DFIG
3.3. MODEL ASSUMPTIONS
Calculation assumptions are presented in Chapter 2.
3.3.1 Power load
Power loads in Binh Thuan and Ninh Thuan provinces are supposed to be located at 110kV bus bars.
The load value of stations are taken according to provincial power development master plan [3].
Capacity factor of load at 110kV bus bar in Binh Thuan province: is compliant with current average
value, cosφ= 0.95.
3.3.2 Power source
Expected power source and connection are take from actual data of [1],[7], data on generating units are
taken from database set of [1].
For wind turbines, data are taken from technical parameters of 2.000 kW turbine.
3.3.3 Electrical network
Data on electrical network are used for simulation such as connection points, conductor cross-section,
loading capacity, length, resistance, reactance, capacitance of line are taken from database of [1], [3]
and [7].
41
3.3.4 Some applicable standards on transmission and distribution network in Vietnam
See in section 2.3.4
3.4. IMPACTS OF WPP ON LOADING CAPACITY OF LOCAL ELECTRICAL NETWORK
3.4.1 Normal operating mode, with Tuy Phong 30 MW WPP
In this mode, it is supposed that the electric network of Binh Thuan province in 2015 is not connected to
three above-mentioned wind power plants except for existing Tuy Phong wind power plant. After
calculating capacity trend distribution results are obtained as in the following table and the detailed
calculation diagram is presented in the appendix.
Table Error! No text of specified style in document..2 Active capacity of DZ 220 kV and 110 kW networks of Bình Thuận (without new WPPs)
No. Lines Voltage (kV)
Diameter/Capacity MBA (MVA)
Admissible operating flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity (%)
Remark
Maximum load regime, rainy season, with Tuy Phong wind power only
1 TBA 220/110kV Hàm Tân 2
220 1x250 250 117+55 j 52%
2
TBA 220/110kV Phan Thiết 2
220 125+250 375 232+85 j 66%
3
TBA 220/110kV TĐ Hàm Thuận
220 63 63 48+21 j 83%
4 TBA220/110kV TĐ Đại Ninh
220 2x63 126 -68-5 j 54%
5 TĐ Hàm Thuận - TĐ Đa Mi
220 AC400 825 400 19-4 j 6%
6 Hàm Tân 2 - KCN Sơn Mỹ
110 AC240 605 2 117+47 j 109% Overload
7 KCN Sơn Mỹ - Hàm Tân
110 AC240 605 10 68+35 j 66%
42
8 KCN Sơn Mỹ - Phan Thiết
110 AC240 605 64 -18+2 j 16%
9 KCN Sơn Mỹ - Xuyên Mộc
110 AC240 605 36 46+1 j 40%
10 Hàm Tân - Tân Thành
110 AC240 605 30 1+5 j 4%
11 Hàm Tân - Thuận Nam
110 AC185 510 34 11+9 j 15%
12 Thuận Nam - Hàm Kiệm
110 AC185 510 14 -45-8 j 47%
13 Hàm Kiệm - Tân Thành
110 AC240 605 22 14-2 j 12%
14 Hàm Kiệm - Phan Thiết
110 AC185 510 15 -94-18 j 98%
15 Phan Thiết - Phan Thiết 2
110 3xAC185 1530 29 -178-53 j 64%
16 Phan Thiết - Rẽ Lương Sơn
110 AC185 510 33 7+15 j 17%
17 Phan Thiết 2 - Mũi Né
110 AC185 510 25 39+21 j 46%
18 Mũi Né - Hòa Thắng
110 AC240 605 13 -4+6 j 6%
19 Lương Sơn - Hòa Thắng
110 AC240 605 13 28+2 j 24%
20
TĐ Hàm Thuận - Phan Thiết 2
110 AC185 510 58 -1+6 j 6%
21 Ma Lâm - Phan Thiết 2
110 AC185 510 13 -14+3 j 15%
22 TĐ Hàm Thuận - Ma Lâm
110 AC185 510 45 8+9 j 12%
23 TĐ Hàm Thuận - Tánh Linh
110 AC185 510 33 41+1 j 42%
24 Đức Linh - Tánh Linh
110 AC185 510 20 -29+3 j 30%
43
25 Đức Linh - Xuân Lộc
110 AC185 510 41 -11+8 j 14%
26 Rẽ Lương Sơn - Lương Sơn
110 2xAC185 1020 0,5 77+18 j 41%
27 Rẽ Lương Sơn - Phan Rí
110 AC185 510 14 -70-2 j 72%
28 Phan Rí - TĐ Đại Ninh
110 2xAC185 1020 43 -98-20 j 51%
29 TĐ Bắc Bình - TĐ Đại Ninh
110 AC150 445 5 33+20 j 46%
30 Phan Rí - Tuy Phong
110 AC185 510 2 -22-1 j 23%
31 Tuy Phong - CN Vĩnh Hảo
110 AC185 510 13 7+7 j 10%
Results of capacity trend calculation in 2015 show that all 220kV transformer stations operate normally
except for the fact that 220kV transformer station of Ham Thuan hydroelectric plant is in heavy load
(83%). Among 110kV transmission lines only Ham Tan 110kV line 2 – Son My industrial zone is
overloaded (109%).
44
45
Table Error! No text of specified style in document..3 Voltage variation at connection points and adjacent nodes in 2015 (without new WPPs)
Node number Node Voltage
(kV)
Without new WPPs
Node voltage (kV) Difference (%)
Maxium load, rainy season
53201 TĐ Đa Nhim 220 231 4.76%
54201 TĐ Hàm Thuận 220 231 4.76%
54202 Phan Thiết 2 220 225 2.22%
54204 Hàm Tân 2 220 224 1.79%
54205 TĐ Đại Ninh 220 231 4.76%
54206 TĐ Đa My 220 231 4.76%
59201 Long Bình 220 225 2.22%
53302 Ninh Phước 110 110 0.00%
53303 Tháp Chàm 110 111 0.90%
53304 TC110kV TĐ Đa Nhim 110 112 1.79%
53305 Ninh Sơn 110 111 0.90%
53306 TC110kV Tháp Chàm 110 111 0.90%
54301 KCN Sơn Mỹ 110 108 -1.85%
54302 Đức Linh 110 108 -1.85%
54303 Tánh Linh 110 109 -0.92%
54304 Ma Lâm 110 109 -0.92%
54305 Hàm Tân 110 106 -3.77%
54306 Thuận Nam 110 104 -5.77%
54307 Hàm Kiệm 110 106 -3.77%
54308 Phan Thiết 110 109 -0.92%
54309 Mũi Né 110 106 -3.77%
54310 Hòa Thắng 110 106 -3.77%
54311 Lương Sơn 110 106 -3.77%
54312 Phan Rí 110 109 -0.92%
54313 Tuy Phong WPP 110 108 -1.85%
46
Node number Node Voltage
(kV)
Without new WPPs
Node voltage (kV) Difference (%)
Maxium load, rainy season
54314 CN Vĩnh Hảo 110 108 -1.85%
54315 Tân Thành 110 105 -4.76%
54316 TĐ Bắc Bình 110 114 3.51%
54318 Rẽ Lương Sơn 110 106 -3.77%
54319 TC110kV Hàm Tân 2 110 109 -0.92%
54321 Hàm Thuận 110 111 0.90%
54322 Phan Thiết 2 110 109 -0.92%
54323 TĐ Đại Ninh 110 114 3.51%
The voltage at all nodes fall within admissible limits except for Thuan Nam node is lower (-5.77%)
compared to admisible operating limits in normal operating mode +10%/-5% Udm.
3.4.2 Normal operating mode, with 340MW of wind power
3.4.2.1 Alternative 1
Table Error! No text of specified style in document..4 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (PA 1)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow
(P + Q j)
(MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with 340 MW wind power
1 TBA
220/110kV Hàm Tân 2
220 1x250 250
104+59 j
48%
2 TBA
220/110kV Phan Thiết 2
220 125+250 375
177+90 j
53%
3 TBA
220/110kV TĐ Hàm Thuận
220 63 63
41+23 j 75%
4 TBA220/110kV
TĐ Đại Ninh 220 2x63 126
37-6 j 30%
47
5 TĐ Hàm
Thuận - TĐ Đa Mi
220 AC400 825 400 27-5 j 9%
6 Hàm Tân 2 - KCN Sơn Mỹ
110 AC240 605 2 104+52
j 101% Overload
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 59+38 j 61%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -27+5 j 24%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 50-0 j 43%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -4+7 j 7%
11 Hàm Tân - Thuận Nam
110 AC185 510 34 6+11 j 13%
12 Thuận Nam -
Hàm Kiệm 110 AC185 510 14 -49-6 j 51%
13 Hàm Kiệm - Tân Thành
110 AC240 605 22 19-3 j 17%
14 Hàm Kiệm - Phan Thiết
110 AC185 510 15 -103-15
j 107% Overload
15 Phan Thiết - Phan Thiết 2
110 3xAC185 1530 29 -144-64
j 54%
16 Phan Thiết -
Rẽ Lương Sơn 110 AC185 510 33
-45+31 j
56%
17 Phan Thiết 2 -
Mũi Né 110 AC185 510 25 6+28 j 29%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13
-36+14 j
34%
19 Lương Sơn - Hòa Thắng
110 AC240 605 13 62-4 j 54%
20 TĐ Hàm
Thuận - Phan Thiết 2
110 AC185 510 58 -7+8 j 11%
21 Ma Lâm -
Phan Thiết 2 110 AC185 510 13 -19+5 j 20%
22 TĐ Hàm
Thuận - Ma Lâm
110 AC185 510 45 2+11 j 12%
23 TĐ Hàm
Thuận - Tánh Linh
110 AC185 510 33 46-1 j 47%
48
24 Đức Linh - Tánh Linh
110 AC185 510 20 -33+6 j 35%
25 Đức Linh - Xuân Lộc
110 AC185 510 41 -16+11
j 20%
26 Rẽ Lương Sơn - Lương Sơn
110 2xAC185 1020 0,5 110+12
j 57%
27 Hòa Thắng WPP - Rẽ
Lương Sơn 110 AC185 510 22 164+3 j 169% Overload
28 Phan Rí - Hòa Thắng WPP
110 AC185 510 20 47-3 j 48%
29 Phan Rí - TĐ Đại Ninh
110 2xAC185 1020 43 4-28 j 15%
30 TĐ Bắc Bình - TĐ Đại Ninh
110 AC150 445 5 33+20 j 46%
31 Phan Rí - Tuy
Phong 110 AC185 510 2
-100+16
j 104% Overload
32 Phú Lạc WPP - Tuy Phong
110 AC185 510 9 -17-1 j 18%
33 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 66-1 j 68%
34 CN Vĩnh Hảo -
Ninh Phước 110 AC185 510 28 42-10 j 44%
35 Ninh Phước - Phước Hữu
WPP 110 AC185 510 6 31-14 j 35%
36 Tháp Chàm - Phước Hữu
WPP 110 AC185 510 9
-79+13 j
82%
Minimum load regime, dry season, with 340 MW wind power
1 TBA
220/110kV Hàm Tân 2
220 1x250 250
30+17 j 14%
2 TBA
220/110kV Phan Thiết 2
220 125+250 375
27+24 j 10%
3 TBA
220/110kV TĐ Hàm Thuận
220 63 63
4+4 j 9%
4 TBA220/110kV
TĐ Đại Ninh 220 2x63 126
90+1 j 71%
5 TĐ Hàm Thuận - TĐ Đa
220 AC400 825 400 18-4 j 6%
49
Mi
6 Hàm Tân 2 - KCN Sơn Mỹ
110 AC240 605 2 30+17 j 30%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 17+13 j 19%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -14+2 j 12%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 20-1 j 17%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -4+2 j 4%
11 Hàm Tân - Thuận Nam
110 AC185 510 34 0+4 j 4%
12 Thuận Nam -
Hàm Kiệm 110 AC185 510 14 -21-1 j 22%
13 Hàm Kiệm - Tân Thành
110 AC240 605 22 10-2 j 9%
14 Hàm Kiệm - Phan Thiết
110 AC185 510 15 -43-3 j 44%
15 Phan Thiết - Phan Thiết 2
110 3xAC185 1530 29 -24-22 j 11%
16 Phan Thiết -
Rẽ Lương Sơn 110 AC185 510 33
-54+15 j
58%
17 Phan Thiết 2 -
Mũi Né 110 AC185 510 25
-22+11 j
25%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13 -38+6 j 33%
19 Lương Sơn - Hòa Thắng
110 AC240 605 13 47-2 j 41%
20 TĐ Hàm
Thuận - Phan Thiết 2
110 AC185 510 58 -10+3 j 11%
21 Ma Lâm -
Phan Thiết 2 110 AC185 510 13 -15+3 j 16%
22 TĐ Hàm
Thuận - Ma Lâm
110 AC185 510 45 -7+4 j 8%
23 TĐ Hàm
Thuận - Tánh Linh
110 AC185 510 33 21-4 j 22%
24 Đức Linh - Tánh Linh
110 AC185 510 20 -16+4 j 17%
50
25 Đức Linh - Xuân Lộc
110 AC185 510 41 -10+5 j 12%
26 Rẽ Lương Sơn - Lương Sơn
110 2xAC185 1020 0,5 65+4 j 34%
27 Hòa Thắng WPP - Rẽ
Lương Sơn 110 AC185 510 22 125-0 j 129% Overload
28 Phan Rí - Hòa Thắng WPP
110 AC185 510 20 7-12 j 14%
29 Phan Rí - TĐ Đại Ninh
110 2xAC185 1020 43 75+6 j 39%
30 TĐ Bắc Bình - TĐ Đại Ninh
110 AC150 445 5 16-4 j 19%
31 Phan Rí - Tuy
Phong 110 AC185 510 2
-100+1 j
103% Overload
32 Phú Lạc WPP - Tuy Phong
110 AC185 510 9 -16+3 j 17%
33 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 66-1 j 68%
34 CN Vĩnh Hảo -
Ninh Phước 110 AC185 510 28 56-5 j 58%
35 Ninh Phước - Phước Hữu
WPP 110 AC185 510 6 51-7 j 53%
36 Phước Hữu WPP - Tháp
Chàm 110 AC185 510 9 -99-1 j 102% Overload
51
52
53
54
Results of capacity trend calculation in maximum load mode show that:
220kV transformer station of Ham Thuan wind power plant is no longer in heavy load.
Ham Ta 2 110kV line – Son My industrial zone is still overload 101% (having reduced 10% compared to
that without wind power).
Ham Kiem – Phan Thiet 110kV line is overload 70%.
110kV line of Hoa Thang – Re Luong Son wind power is heavily overloaded 169%.
Phan Ri – Tuy Phong 110kV line is slightly overloaded 104%.
Results of capacity trend calculation in minimum load mode shows that:
110kV line of Hoa Thang – Re Luong Son wind power plant is heavily overloaded 129%.
110kV line of Phan Ri – Tuy Phong wind power plant is slightly overloaded 103%.
110kV line of Phuoc Huu – Thap Cham wind power plant is slightly overloaded 102%.
Table Error! No text of specified style in document..5 Voltage variation at connection points and adjacent nodes in 2015 (PA1)
Node number Node
With wind power (Total: 340 MW)
Node voltage
(kV)
Difference (%)
Node voltage
(kV) Difference (%)
Maxium load, rainy season
Minimum load, dry season
53201 TĐ Đa Nhim 231 4.76% 231 4.76%
54201 TĐ Hàm Thuận 231 4.76% 231 4.76%
54202 Phan Thiết 2 225 2.22% 231 4.76%
54204 Hàm Tân 2 224 1.79% 231 4.76%
54205 TĐ Đại Ninh 231 4.76% 231 4.76%
54206 TĐ Đa My 231 4.76% 231 4.76%
59201 Long Bình 225 2.22% 232 5.17%
53302 Ninh Phước 113 2.65% 118 6.78%
53303 Tháp Chàm 112 1.79% 116 5.17%
53304 TC110kV TĐ Đa Nhim 112 1.79% 114 3.51%
53305 Ninh Sơn 112 1.79% 115 4.35%
53306 TC110kV Tháp Chàm 112 1.79% 116 5.17%
53307 Phước Hữu WPP 113 2.65% 117 5.98%
54301 KCN Sơn Mỹ 108 -1.85% 114 3.51%
55
Node number Node
With wind power (Total: 340 MW)
Node voltage
(kV)
Difference (%)
Node voltage
(kV) Difference (%)
Maxium load, rainy season
Minimum load, dry season
54302 Đức Linh 108 -1.85% 114 3.51%
54303 Tánh Linh 109 -0.92% 114 3.51%
54304 Ma Lâm 109 -0.92% 114 3.51%
54305 Hàm Tân 106 -3.77% 113 2.65%
54306 Thuận Nam 104 -5.77% 113 2.65%
54307 Hàm Kiệm 105 -4.76% 113 2.65%
54308 Phan Thiết 109 -0.92% 114 3.51%
54309 Mũi Né 106 -3.77% 114 3.51%
54310 Hòa Thắng 106 -3.77% 115 4.35%
54311 Lương Sơn 107 -2.80% 115 4.35%
54312 Phan Rí 113 2.65% 118 6.78%
54313 Tuy Phong WPP 114 3.51% 120 8.33%
54314 CN Vĩnh Hảo 113 2.65% 119 7.56%
54315 Tân Thành 105 -4.76% 113 2.65%
54316 TĐ Bắc Bình 115 4.35% 116 5.17%
54318 Rẽ Lương Sơn 107 -2.80% 115 4.35%
54319 TC110kV Hàm Tân 2 109 -0.92% 114 3.51%
54321 Hàm Thuận 111 0.90% 115 4.35%
54322 Phan Thiết 2 109 -0.92% 115 4.35%
54323 TĐ Đại Ninh 115 4.35% 115 4.35%
54324 Hòa Thắng WPP 112 1.79% 119 7.56%
54225 Phú Lạc WPP 114 3.51% 120 8.33%
The voltage at most nodes falls within admissible operating limit in normal operating conditions +10%/-
5% Udm, except for:
+ In maximum load mode in rainy season the voltage at Thuan Nam node is lower than admissible level
(-5.77%).
56
3.4.2.2 Alternative 2
Table Error! No text of specified style in document..6 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (PA 2)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with 340 MW wind power
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
96+57 j 45%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
142+79 j 43%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
36+21 j 66%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
10-5 j 9%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 27-6 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 95+51 j 94%
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 53+38 j 57%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -31+5 j 27%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 52+0 j 45%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -6+7 j 8%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 3+12 j 13%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -52-6 j 54%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 22-3 j 19%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -109-15 j 113% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -125-69 j 49%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -47+20 j 53%
57
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -18+15 j 24%
18 Mũi Né - Hòa Thắng 110 AC240 605 13 -87+15 j 77%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -3-6 j 6%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -11+8 j 14%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -23+5 j 24%
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 -2+11 j 12%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 49-1 j 50%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -36+6 j 38%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -19+12 j 23%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 45+10 j 24%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 118+7 j 90%
28 Phan Rí - Rẽ Lương
Sơn 110 AC185 510 14 97-1 j 100%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 -22-24 j 17%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+18 j 44%
31 Phan Rí - Tuy
Phong 110 2xAC185 1020 16
-123+10 j
64%
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 6-3 j 7%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 43+2 j 44%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 18-6 j 20%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 8-8 j 12%
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 -57+7 j 59%
Minimum load regimei, dry season, with 340 MW wind power
58
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
23+17 j 11%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
-3+17 j 5%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
0+3 j 5%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
68+1 j 54%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 18-4 j 6%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 23+17 j 25%
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 12+13 j 15%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -18+2 j 16%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 22-1 j 19%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -6+2 j 5%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 -3+4 j 5%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -23-1 j 24%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 12-2 j 11%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -48-3 j 49%
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 0-21 j 7%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -49+8 j 51%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -33+5 j 34%
18 Mũi Né - Hòa Thắng 110 AC240 605 13 -89+4 j 77%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -17-4 j 15%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -13+3 j 14%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -18+3 j 19%
59
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 -10+4 j 11%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 23-4 j 24%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -19+5 j 20%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -12+6 j 14%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 1+2 j 1%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 118+10 j 90%
28 Phan Rí - Rẽ Lương
Sơn 110 AC185 510 14 51-4 j 53%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 53+8 j 28%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 16-8 j 21%
31 Phan Rí - Tuy
Phong 110 2xAC185 1020 16 -122-9 j 63%
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 5+4 j 7%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 44+0 j 45%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 35-3 j 36%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 31-4 j 32%
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 -79-6 j 82%
Results of capacity trend calculation show that:
In maximum load mode during rainy season:
Ham Kien – Phan Thiet 110kV line is overloaded 113%.
Phan Ri – Re Luong Son 110kV line is in full load 110%.
In minimum load mode during dry season:
Thap Cham 110kV line – Phuoc Huu wind power plant is in full load 82%.
In comparison with Alternative 1:
Phan Ri – Tuy Phong 110kV line is no longer overloaded (reducing from 104% to 64%).
60
61
62
63
Table Error! No text of specified style in document..7 Voltage variation at connection points and adjacent nodes in 2015 (PA2)
Node number Node Voltage
(kV)
With wind power (total: 340 MW)
Node voltage
(kV)
Difference (%)
Node voltage
(kV)
Difference (%)
Maxium load, rainy season
Minimum load, dry season
53201 TĐ Đa Nhim 220 231 4.76% 231 4.76%
54201 TĐ Hàm Thuận 220 231 4.76% 231 4.76%
54202 Phan Thiết 2 220 226 2.65% 231 4.76%
54204 Hàm Tân 2 220 225 2.22% 231 4.76%
54205 TĐ Đại Ninh 220 231 4.76% 231 4.76%
54206 TĐ Đa My 220 231 4.76% 231 4.76%
59201 Long Bình 220 225 2.22% 232 5.17%
60201 Bà Rịa 220 225 2.22% 230 4.35%
53302 Ninh Phước 110 113 2.65% 118 6.78%
53303 Tháp Chàm 110 112 1.79% 116 5.17%
53304 TC110kV TĐ Đa
Nhim 110 112 1.79% 115 4.35%
53305 Ninh Sơn 110 112 1.79% 115 4.35%
53306 TC110kV Tháp
Chàm 110 112 1.79% 116 5.17%
53307 Phước Hữu WPP 110 113 2.65% 118 6.78%
54301 KCN Sơn Mỹ 110 108 -1.85% 114 3.51%
54302 Đức Linh 110 108 -1.85% 114 3.51%
54303 Tánh Linh 110 109 -0.92% 114 3.51%
54304 Ma Lâm 110 109 -0.92% 115 4.35%
54305 Hàm Tân 110 106 -3.77% 114 3.51%
54306 Thuận Nam 110 104 -5.77% 113 2.65%
54307 Hàm Kiệm 110 106 -3.77% 114 3.51%
54308 Phan Thiết 110 109 -0.92% 115 4.35%
54309 Mũi Né 110 109 -0.92% 116 5.17%
64
Node number Node Voltage
(kV)
With wind power (total: 340 MW)
Node voltage
(kV)
Difference (%)
Node voltage
(kV)
Difference (%)
Maxium load, rainy season
Minimum load, dry season
54310 Hòa Thắng 110 110 0.00% 117 5.98%
54311 Lương Sơn 110 109 -0.92% 116 5.17%
54312 Phan Rí 110 113 2.65% 118 6.78%
54313 Tuy Phong WPP 110 114 3.51% 119 7.56%
54314 CN Vĩnh Hảo 110 113 2.65% 119 7.56%
54315 Tân Thành 110 106 -3.77% 114 3.51%
54316 TĐ Bắc Bình 110 116 5.17% 116 5.17%
54318 Rẽ Lương Sơn 110 109 -0.92% 116 5.17%
54319 TC110kV Hàm Tân
2 110 109 -0.92% 114 3.51%
54321 Hàm Thuận 110 111 0.90% 115 4.35%
54322 Phan Thiết 2 110 110 0.00% 115 4.35%
54323 TĐ Đại Ninh 110 115 4.35% 116 5.17%
59301 Xuân Trường 110 109 -0.92% 114 3.51%
60301 Xuyên Mộc 110 105 -4.76% 113 2.65%
60302 Bà Rịa 110 107 -2.80% 113 2.65%
54324 Hòa Thắng WPP 110 112 1.79% 119 7.56%
54225 Phú Lạc WPP 110 114 3.51% 119 7.56%
The voltage at most nodes falls within admissible operating limit of +10%/-5% Udm, except for Thuan
Nam node (-5,77%) is lower than admissible limit.
3.4.2.3 Alternative 3
Table Error! No text of specified style in document..8 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (PA 3)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
65
Maximum load regime, rainy season, with 340 MW wind power
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
95+58 j 45%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
138+79 j
42%
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63
35+21 j 65%
4 TBA220/110kV
TĐ Đại Ninh 220 2x63 126
6-5 j 6%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 27-6 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 95+51 j 94%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 53+38 j 57%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -32+5 j 28%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 52-0 j 45%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -7+7 j 9%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 3+12 j 13%
12 Thuận Nam -
Hàm Kiệm 110 AC185 510 14 -52-6 j 54%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 22-3 j 19%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15
-110-15 j
114% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29
-123-69 j
48%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -47+20 j 53%
17 Phan Thiết 2 -
Mũi Né 110 AC185 510 25 -21+15 j 27%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13 -94+17 j 83%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -13-4 j 12%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -11+8 j 14%
66
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -24+5 j 25%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 -3+11 j 12%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 49-1 j 50%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -37+7 j 39%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -19+12 j 23%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 36+12 j 20%
27 Hòa Thắng WPP
- Hòa Thắng 110 AC300 690 15 135+7 j 103% Overload
28 Hòa Thắng WPP
- Phan Rí 110 AC240 605 13 -17-1 j 15%
29 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 87-0 j 90%
30 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 -26-25 j 19%
31 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+18 j 44%
32 Phan Rí - Tuy
Phong 110 2xAC185 1020 16 -126+8 j 65%
33 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 9-3 j 10%
34 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 41+3 j 42%
35 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 16-6 j 18%
36 Ninh Phước - Phước Hữu
WPP 110 AC185 510 6 6-8 j 10%
37 Tháp Chàm - Phước Hữu
WPP 110 AC185 510 9 -55+7 j 57%
Minimum load regime, dry season, with 340 MW wind power
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
24+17 j 12%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
0+17 j 5%
67
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63
1+3 j 5%
4 TBA220/110kV
TĐ Đại Ninh 220 2x63 126
71+1 j 56%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 18-4 j 6%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 24+17 j 26%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 12+13 j 15%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -18+2 j 16%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 22-1 j 19%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -6+2 j 5%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 -3+4 j 5%
12 Thuận Nam -
Hàm Kiệm 110 AC185 510 14 -23-1 j 24%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 12-2 j 11%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -48-3 j 49%
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -1-21 j 7%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -49+9 j 51%
17 Phan Thiết 2 -
Mũi Né 110 AC185 510 25 -32+5 j 33%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13 -85+5 j 74%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -11-3 j 10%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -13+3 j 14%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -18+3 j 19%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 -10+4 j 11%
23 TĐ Hàm Thuận - 110 AC185 510 33 23-4 j 24%
68
Tánh Linh
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -18+5 j 19%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -12+6 j 14%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 7+3 j 4%
27 Hòa Thắng WPP
- Hòa Thắng 110 AC300 690 15 107+7 j 82%
28 Hòa Thắng WPP
- Phan Rí 110 AC240 605 13 11+6 j 11%
29 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 58-3 j 60%
30 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 55+10 j 29%
31 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 16-11 j 23%
32 Phan Rí - Tuy
Phong 110 2xAC185 1020 16 -121-7 j 62%
33 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 4+3 j 5%
34 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 46+1 j 47%
35 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 37-2 j 38%
36 Ninh Phước - Phước Hữu
WPP 110 AC185 510 6 32-3 j 33%
37 Tháp Chàm - Phước Hữu
WPP 110 AC185 510 9 -81-6 j 84%
Results of capacity trend calculation show that:
In maximum load mode, in rainy season:
Ham Kien – Phan Thiet 110kV line is overloaded 114%.
110kV line of Hoa Thang wind power plant is overloaded 103%.
In comparison with Alternative 1, the number of overloaded 110kV lines reduces to 2 lines (compared
to 4 lines in Alternative 1).
69
70
71
Table Error! No text of specified style in document..9 Voltage variation at connection points and adjacent nodes in 2015 (PA 3)
Node number Node Voltage
(kV)
With wind power (Total: 340 MW)
Node voltage
(kV)
Difference (%)
Node voltage
(kV)
Difference (%)
Maximum load, rainy season
Minimum load, dry season
53201 TĐ Đa Nhim 220 231 4.76% 231 4.76%
54201 TĐ Hàm Thuận 220 231 4.76% 231 4.76%
54202 Phan Thiết 2 220 226 2.65% 231 4.76%
54204 Hàm Tân 2 220 225 2.22% 231 4.76%
54205 TĐ Đại Ninh 220 231 4.76% 231 4.76%
54206 TĐ Đa My 220 231 4.76% 231 4.76%
59201 Long Bình 220 225 2.22% 232 5.17%
60201 Bà Rịa 220 225 2.22% 230 4.35%
53302 Ninh Phước 110 113 2.65% 118 6.78%
53303 Tháp Chàm 110 112 1.79% 116 5.17%
53304 TC110kV TĐ Đa
Nhim 110 112 1.79% 115 4.35%
53305 Ninh Sơn 110 112 1.79% 115 4.35%
53306 TC110kV Tháp
Chàm 110 112 1.79% 116 5.17%
53307 Phước Hữu WPP 110 113 2.65% 118 6.78%
54301 KCN Sơn Mỹ 110 108 -1.85% 114 3.51%
54302 Đức Linh 110 108 -1.85% 114 3.51%
54303 Tánh Linh 110 109 -0.92% 114 3.51%
54304 Ma Lâm 110 109 -0.92% 115 4.35%
54305 Hàm Tân 110 106 -3.77% 114 3.51%
54306 Thuận Nam 110 104 -5.77% 113 2.65%
54307 Hàm Kiệm 110 106 -3.77% 114 3.51%
54308 Phan Thiết 110 109 -0.92% 115 4.35%
54309 Mũi Né 110 109 -0.92% 116 5.17%
72
Node number Node Voltage
(kV)
With wind power (Total: 340 MW)
Node voltage
(kV)
Difference (%)
Node voltage
(kV)
Difference (%)
Maximum load, rainy season
Minimum load, dry season
54310 Hòa Thắng 110 110 0.00% 117 5.98%
54311 Lương Sơn 110 109 -0.92% 116 5.17%
54312 Phan Rí 110 112 1.79% 118 6.78%
54313 Tuy Phong WPP 110 113 2.65% 119 7.56%
54314 CN Vĩnh Hảo 110 113 2.65% 119 7.56%
54315 Tân Thành 110 106 -3.77% 114 3.51%
54316 TĐ Bắc Bình 110 116 5.17% 116 5.17%
54318 Rẽ Lương Sơn 110 109 -0.92% 116 5.17%
54319 TC110kV Hàm Tân
2 110 109 -0.92% 114 3.51%
54321 Hàm Thuận 110 111 0.90% 115 4.35%
54322 Phan Thiết 2 110 110 0.00% 115 4.35%
54323 TĐ Đại Ninh 110 115 4.35% 116 5.17%
59301 Xuân Trường 110 109 -0.92% 114 3.51%
60301 Xuyên Mộc 110 105 -4.76% 113 2.65%
60302 Bà Rịa 110 107 -2.80% 113 2.65%
54324 Hòa Thắng WPP 110 112 1.79% 118 6.78%
54225 Phú Lạc WPP 110 113 2.65% 120 8.33%
The voltage at most nodes falls within admissible limits of +10%/-5% Udm. Except for Thuan Nam node
(-5,77%) is lower than admissible limits.
In normal operating mode Ham Kiem – Phan Thiet 110kV line is frequently overloaded at peak hours in
three Alternatives. It is proposed to increase the section of Ham Kiem – Phan Thiet 110kV line to AC-
240 with a length of 14.8km.
Thus, the voltages at nodes of Binh Thuan’s electrical network improve better and are in admissible
limits when those wind power plants are in operation. Detailed voltages are presented in the table
below:
73
Node number
Node Voltage
(kV)
Alternative 1 Alternative 2 Alternative 3
Node
voltage
(kV)
Difference
(%)
Node
voltage
(kV)
Difference
(%)
Node
voltage
(kV)
Difference
(%)
Node
voltage
(kV)
Difference
(%)
Node
voltage
(kV)
Difference
(%)
Node
voltage
(kV)
Difference
(%)
Maximum load, rainy season
Minimum load, dry season
Maximum load, rainy season
Minimum load, dry season
Maximum load, rainy season
Minimum load, dry season
53201 TĐ Đa Nhim 220 231 4,76% 231 4,76% 231 4,76% 231 4,76% 231 4,76% 231 4,76%
54201 TĐ Hàm Thuận 220 231 4,76% 231 4,76% 231 4,76% 231 4,76% 231 4,76% 231 4,76%
54202 Phan Thiết 2 220 225 2,22% 231 4,76% 226 2,65% 231 4,76% 226 2,65% 231 4,76%
54204 Hàm Tân 2 220 224 1,79% 231 4,76% 225 2,22% 231 4,76% 225 2,22% 231 4,76%
54205 TĐ Đại Ninh 220 231 4,76% 231 4,76% 231 4,76% 231 4,76% 231 4,76% 231 4,76%
54206 TĐ Đa My 220 231 4,76% 231 4,76% 231 4,76% 231 4,76% 231 4,76% 231 4,76%
59201 Long Bình 220 225 2,22% 232 5,17% 225 2,22% 232 5,17% 225 2,22% 232 5,17%
60201 Bà Rịa 220 225 2,22% 230 4,35% 225 2,22% 230 4,35% 225 2,22% 230 4,35%
53302 Ninh Phước 110 113 2,65% 118 6,78% 113 2,65% 118 6,78% 113 2,65% 118 6,78%
53303 Tháp Chàm 110 112 1,79% 116 5,17% 112 1,79% 116 5,17% 112 1,79% 116 5,17%
53304 TC110kV TĐ Đa Nhim 110 112 1,79% 114 3,51% 112 1,79% 115 4,35% 112 1,79% 115 4,35%
53305 Ninh Sơn 110 112 1,79% 115 4,35% 112 1,79% 115 4,35% 112 1,79% 115 4,35%
53306 TC110kV Tháp Chàm 110 112 1,79% 116 5,17% 112 1,79% 116 5,17% 112 1,79% 116 5,17%
53307 Đ.Gió Phước Hữu 110 113 2,65% 117 5,98% 113 2,65% 118 6,78% 113 2,65% 118 6,78%
54301 KCN Sơn Mỹ 110 108 -1,85% 114 3,51% 108 -1,85% 114 3,51% 108 -1,85% 114 3,51%
54302 Đức Linh 110 108 -1,85% 114 3,51% 108 -1,85% 114 3,51% 108 -1,85% 114 3,51%
54303 Tánh Linh 110 109 -0,92% 114 3,51% 109 -0,92% 114 3,51% 109 -0,92% 114 3,51%
54304 Ma Lâm 110 109 -0,92% 114 3,51% 109 -0,92% 115 4,35% 109 -0,92% 115 4,35%
54305 Hàm Tân 110 106 -3,77% 113 2,65% 106 -3,77% 114 3,51% 106 -3,77% 114 3,51%
54306 Thuận Nam 110 104 -5,77% 113 2,65% 104 -5,77% 113 2,65% 104 -5,77% 113 2,65%
54307 Hàm Kiệm 110 105 -4,76% 113 2,65% 106 -3,77% 114 3,51% 106 -3,77% 114 3,51%
74
54308 Phan Thiết 110 109 -0,92% 114 3,51% 109 -0,92% 115 4,35% 109 -0,92% 115 4,35%
54309 Mũi Né 110 106 -3,77% 114 3,51% 109 -0,92% 116 5,17% 109 -0,92% 116 5,17%
54310 Hòa Thắng 110 106 -3,77% 115 4,35% 110 0,00% 117 5,98% 110 0,00% 117 5,98%
54311 Lương Sơn 110 107 -2,80% 115 4,35% 109 -0,92% 116 5,17% 109 -0,92% 116 5,17%
54312 Phan Rí 110 113 2,65% 118 6,78% 113 2,65% 118 6,78% 112 1,79% 118 6,78%
54313 Đ.Gió Tuy Phong 110 114 3,51% 120 8,33% 114 3,51% 119 7,56% 113 2,65% 119 7,56%
54314 CN Vĩnh Hảo 110 113 2,65% 119 7,56% 113 2,65% 119 7,56% 113 2,65% 119 7,56%
54315 Tân Thành 110 105 -4,76% 113 2,65% 106 -3,77% 114 3,51% 106 -3,77% 114 3,51%
54316 TĐ Bắc Bình 110 115 4,35% 116 5,17% 116 5,17% 116 5,17% 116 5,17% 116 5,17%
54318 Rẽ Lương Sơn 110 107 -2,80% 115 4,35% 109 -0,92% 116 5,17% 109 -0,92% 116 5,17%
54319 TC110kV Hàm Tân 2 110 109 -0,92% 114 3,51% 109 -0,92% 114 3,51% 109 -0,92% 114 3,51%
54321 Hàm Thuận 110 111 0,90% 115 4,35% 111 0,90% 115 4,35% 111 0,90% 115 4,35%
54322 Phan Thiết 2 110 109 -0,92% 115 4,35% 110 0,00% 115 4,35% 110 0,00% 115 4,35%
54323 TĐ Đại Ninh 110 115 4,35% 115 4,35% 115 4,35% 116 5,17% 115 4,35% 116 5,17%
59301 Xuân Trường 110 109 -0,92% 114 3,51% 109 -0,92% 114 3,51% 109 -0,92% 114 3,51%
60301 Xuyên Mộc 110 105 -4,76% 113 2,65% 105 -4,76% 113 2,65% 105 -4,76% 113 2,65%
60302 Bà Rịa 110 107 -2,80% 113 2,65% 107 -2,80% 113 2,65% 107 -2,80% 113 2,65%
54324 Đ.Gió Hòa Thắng 110 112 1,79% 119 7,56% 112 1,79% 119 7,56% 112 1,79% 118 6,78%
54225 Đ.Gió Phú Lạc 110 114 3,51% 120 8,33% 114 3,51% 119 7,56% 113 2,65% 120 8,33%
75
3.4.3 Failure mode
3.4.3.1 Alternative 1
+ Failure of Phan Thiet 110kV line – Phan Thiet 2 (maximum load mode, rainy season, maximum
generated wind power):
It is supposed that Phan Thiet 3 circuit 110kV line – Phan Thiet 2 fails the remaining two lines operate
normally. Results of capacity trend calculation are presented in the following table, the detailed diagram
is given in the appendix:
Results of capacity trend calculation show that:
Ham Tan 2 110kV line – Son My industrial zone is slightly overloaded 101%.
Ham Kiem – Phan Thiet 110kV line is slightly overloaded 107%.
110kV line of Hoa Thang – Re Luong Son wind power plant is heavily overloaded 173%, it should be
considered to build circuit 2.
Phan Ri – Tuy Phong 110kV line is slightly overloaded 104%.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
+ Failure of Luong Son – Hoa Thang 110kV line (maximum load mode, rainy season, maximum
generated wind power):
It is supposed that Luong Son – Hoa Thang 110kV line fails. Results of capacity trend calculation are
presented in the following table, the detailed diagram is given in the appendix.
Results of capacity trend calculation show that:
Ham Tan 2 110kV line – Son My industrial zone is overloaded 102%.
Ham Kien – Phan Thiet 110kV line is overloaded 106%.
110kV line of Hoa Thang – Re Luong Son wind power plant is heavily overloaded 151%.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
+ Failure of 110kV line of Phuoc Huu – Thap Cham wind power plant (minimum load mode, dry
season, maximum generated wind power).
It is supposed that 110kV line of Phuoc Huu – Thap Cham wind power fails. Results of capacity trend
calculation are presented in the following table, the detailed diagram is given in the appendix.
Results of capacity trend calculation show that:
220kV transformer station of Dai Ninh hydroelectric plant is overloaded 114%, because of additionally
loading nearly 50MV of generated capacity of wind power plants to the system.
110kV line of Hoa Thang – Re Luong Son wind power plant is heavily overloaded 170%, which cannot
be operated, circuit 2 should be strengthened.
Phan Ri – Tuy Phong 110kV line is heavily overloaded 202%, which cannot be operated, circuit 2
should be strengthened.
76
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
+ Failure of Luong Son – Phan Thiet 110kV line (minimum load mode, dry season, maximum
generated wind power).
It is supposed that Luong Son – Phan Thiet 110kV line circuit fails. Results of capacity trend calculation
are presented in the following table, the detailed diagram is given in the appendix.
Results of capacity trend calculation show that:
110kV line of Hoa Thang – Luong Son wind power plant is overloaded 105%.
110kV line of Phuoc Huu – Thap Cham wind power plant is overloaded 112%.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
Recommendations for Alternative 1:
Additionally build 110kV line of Hoa Thang – Re Luong Son wind power plant, forming 2 circuits.
Additionally build Phan Ri – Tuy Phong 110kV line, forming 2 circuits.
Additionally build 110kV line of Phuoc Huu – Thap Cham wind power plant, forming 2 circuits.
Additionally build Phan Thiet – Re Luong Son 110kV line, forming 2 circuits.
3.4.3.2 Alternative 2
+ Failure of Thap Cham 110kV line – Phuoc Huu wind power plant (maximum load mode, rainy
season, maximum generated wind power):
It is supposed that Thap Cham 110kV line – Phuoc Huu wind power fails. Results of capacity trend
calculation are presented in the following table, the detailed diagram is given in the appendix.
Results of capacity trend calculation in failure moade show that:
Phan Ri – Re Luong Son 110kV line is overloaded 128%. To repair, it is necessary to reduce
generation of Tuy Phong, Phuoc Huu and Phu Lac wind power plants.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
+ Failure of Phan Ri – Re Luong Son 110kV line exposure (maximum load mode, rainy season,
maximum generated wind power).
It is supposed that Phan Ri – Tuy Phong 110kV line exposes. Results of capacity trend calculation are
presented in the following table, the detailed diagram is given in the appendix.
Results of capacity trend calculation in failure mode show that:
Ham Tan 2 110kV line – Son My industrial zone is slightly overloaded 103%.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
+ Failure of Luong Son – Phan Thiet 110kV line (minimum load mode, dry season, maximum
generated wind power).
It is supposed that Luong Son – Phan Thiet 110kV line fails. Results of capacity trend calculation are
presented in the following table, the detailed diagram is given in the appendix.
77
Results of capacity trend calculation show that:
Mui Ne – Hoa Thang 110kV line is slightly overloaded 105%.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
+ Failure of Thap Cham - Phuoc Huu 110kV line exposure (minimum load mode, dry season,
maximum generated wind power).
It is supposed that Thap Cham – Phuoc Huu 110kV line fails. Results of capacity trend calculation are
presented in following table, detailed calculation are given in the appendix.
Results of capacity trend calculation show that:
Phan Ri – Tuy Phong 110kV line is overloaded 102%.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
Conclusions and recommendations for Alternative 2:
At peak load, if a 110kV circuit at 2 conducting ends of Phan Ri – Tuy Phong or Han Kiem – Phan
Thiet, Tuy Phong, Phu Lac and Phuoc Huu wind power plants should reduce generation to ensure
loading capacity of the lines. With currently advanced communication and information technology, it is
absolutely able to install an inter-system between stations to perform this.
3.4.3.3 Alternative 3
+ Failure of Tham Cham – Phuoc Huu 110kV line exposure (maximum loading mode, rainy
season, maximum generated wind power).
It is supposed that Thap Cham – Phuoc Huu 110kV line fails. Results of capacity trend calculation are
presented in the following table, the detailed diagram is given in the appendix.
Results of capacity trend calculation in failure mode show that:
Hoa Thang 110kV line is overloaded 115%.
Phan Ri – Re Luong Son 110kV line is overloaded 104%.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
+ Failure of double circuit exposure of Phan Ri – Tuy Phong wind power plant (maximum load
mode, rainy season, maximum generated wind power).
It is supposed that double circuit of 110kV line of Phan Ri – Tuy Phong wind power plant fails. Results
of capacity trend calculation are presented in the following table, the detailed calculation is given in the
appendix.
Results of capacity trend calculation in failure mode show that:
110kV line of Hoa Thang wind powre plant is overloaded 101%.
Phan Ri – Tuy Phong 110kV line is overloaded 121%.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
78
+ Failure of Phan Ri – Luong Son 110kV line exposure (maximum load mode, rainy season,
maximum generated wind power).
It is supposed that Phan Ri – Luong Son 110kV line exposes. Results of capacity trend calculation are
presented in the following table, the detailed diagram is given in the appendix.
Results of capacity trend calculation in failure mode show that:
110kV line of Hoa Thang wind power plant is overloaded 145%.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
+ Failure of 110kV line of Hoa Thang wind power plant (maximum load mode, rainy season,
maximum generated wind power).
It is supposed that 110kV line of Hoa Thang wind power plant exposes. Results of capacity trend
calculation are presented in the following table, the detailed diagram is given in the appendix.
Results of capacity trend calculation in failure mode show that:
110kV line of Hoa Thang – Phan Ri wind power plant is overloaded 103%.
Phan Ri – Re Luong Son 110kV line is heavily overloaded 175%, which cannot be operated.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
+ Failure of 110kV line of Hoa Thang – Phan Ri wind power plant (maximum load mode, rainy
season, maximum generated wind power).
It is supposed that 110kV line of Hoa Thang – Phan Ri wind power plant exposes. Results of capacity
trend calculation are presented in the following table, the detailed diagram is given in the appendix.
Results of capacity trend calculation in failure mode show that: lines in wind power area bear load within admissible limits.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
+ Failure of Luong Son – Phan Thiet 110kV line exposure (minimum load mode, dry season,
maximum generated wind power).
It is supposed that Luong Son – Phan Thiet 110kV line exposes. Results of capacity trend calculation
are presented in the following table, the detailed diagram is given in the appendix.
Results of capacity trend calculation show that:
- Mui Ne – Hoa Thang 110kV line is slightly overloaded 102%.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
+ Failure of Thap Cham – Phuoc Huu 110kV line (minimum load mode, dry season, maximum
generated wind power).
It is supposed that Thap Cham – Phuoc Huu 110kV line exposes. Results of capacity trend calculation
are presented in the following table, the detailed diagram is given in the appendix.
Results of capacity trend calculation show that:
- Phan Ri – Tuy Phong 110kV line is overloaded 103%.
The voltage at all nodes falls within admissible operating limit in failure mode ±10%Udm.
79
Conclusions and recommendations for Alternative 3:
- Additionally build a Phan Ri – Re Luong Son 110kV line, section AC-240, length of 14km in order to avoid overload (75%) in the event of Hoa Thang – Hoa Thang wind power plant failure.
- In the event of failure of one 110kv circuit in one of two Phan Ri – Tuy Phong or Han Kiem – Phan Thiet lines, Tuy Phong, Phu Lac and Phuoc Huu wind power plants should reduce generation to ensure loading capacity of the lines.
3.5. IMPACTS ON SHORT-CIRCUIT CURRENT
Contributing to short circuit current of wind power plant when short circuit at bus bar of transformer
station is connected in the following cases:
+ There is only 30MW of existing Tuy Phong wind power plant
+ There is 340MW of connected wind power plan according to Alternative 1.
+ There is 340MW of connected wind power plan according to Alternative 2.
+ There is 340MW of connected wind power plan according to Alternative 3.
80
Table 3.10 Short-circuit current at connection points and adjacent nodes in 2015.
Node
number Node
Voltage
(kV)
Only Tuy Phong
WPP (30 MW)
340 MW WPPs
(PA 1)
Difference (%)
(PA 1)
340 MW WPPs
(PA 2)
Difference (%)
(PA 2)
340 MW WPPs
(PA 3)
Difference (%)
(PA 3)
3-phase
short
circuit
current
(A)
1-phase
short
circuit
current
(A)
3-phase
short
circuit
current
(A)
1-phase
short
circuit
current
(A)
3-phase
short
circuit
current
(A)
1-phase
short
circuit
current
(A)
3-phase
short
circuit
current
(A)
1-phase
short
circuit
current
(A)
3-phase
short
circuit
current
(A)
1-phase
short
circuit
current
(A)
3-phase
short
circuit
current
(A)
1-phase
short
circuit
current
(A)
3-phase
short
circuit
current
(A)
1-phase
short
circuit
current
(A)
54501 NMNĐ Vĩnh Tân 500 9833 8208 9825 8199 -0.09% -0.11% 9842 8214 0.09% 0.07% 9842 8213 0.08% 0.07%
54201 TĐ Hàm Thuận 220 19423 17153 19394 17107 -0.15% -0.27% 19496 17202 0.38% 0.28% 19499 17203 0.39% 0.29%
54202 Phan Thiết 2 220 15652 9836 15608 9822 -0.28% -0.14% 16014 10250 2.26% 4.03% 16075 10267 2.64% 4.19%
54204 Hàm Tân 2 220 13803 8158 13739 8121 -0.47% -0.46% 13975 8307 1.23% 1.80% 14004 8314 1.43% 1.88%
54205 TĐ Đại Ninh 220 14680 13722 14688 13696 0.06% -0.19% 14783 13789 0.69% 0.48% 14854 13845 1.17% 0.89%
54206 TĐ Đa My 220 13329 11335 13294 11296 -0.26% -0.34% 13339 11333 0.08% -0.02% 13340 11333 0.08% -0.02%
54208 TC 220kV NMNĐ Vĩnh Tân 220 24396 26478 24467 26531 0.29% 0.20% 24570 26647 0.71% 0.63% 24569 26645 0.71% 0.63%
53201 TĐ Đa Nhim 220 13766 10982 13802 11009 0.27% 0.25% 13870 11067 0.76% 0.77% 13880 11071 0.82% 0.81%
53202 220kV Tháp Chàm 220 17892 12796 18000 13035 0.60% 1.83% 18120 13127 1.26% 2.52% 18124 13128 1.28% 2.53%
54225 Phú Lạc WPP 110
5806 5676
7150 6835
7755 7233
54301 KCN Sơn Mỹ 110 10635 7594 10502 7499 -1.27% -1.27% 10802 7728 1.54% 1.72% 10832 7737 1.82% 1.84%
54302 Đức Linh 110 4805 2732 4758 2704 -0.99% -1.03% 4815 2735 0.20% 0.10% 4816 2734 0.22% 0.08%
54303 Tánh Linh 110 4549 2654 4492 2620 -1.26% -1.31% 4568 2661 0.43% 0.26% 4570 2661 0.47% 0.26%
54304 Ma Lâm 110 6197 3736 6076 3661 -1.99% -2.06% 6350 3814 2.41% 2.06% 6378 3820 2.84% 2.21%
54305 Hàm Tân 110 7806 4704 7689 4633 -1.53% -1.54% 7943 4790 1.72% 1.79% 7966 4795 2.01% 1.89%
54306 Thuận Nam 110 5717 3137 5606 3075 -1.98% -1.99% 5846 3208 2.21% 2.23% 5867 3212 2.56% 2.34%
54307 Hàm Kiệm 110 7775 4481 7621 4392 -2.02% -2.02% 8034 4631 3.23% 3.24% 8084 4641 3.83% 3.45%
81
54308 Phan Thiết 110 14506 10616 14247 10458 -1.82% -1.51% 15665 11637 7.40% 8.77% 15950 11740 9.06% 9.57%
54309 Mũi Né 110 6054 3441 5847 3366 -3.54% -2.22% 9333 6116 35.13% 43.74% 9858 6275 38.59% 45.17%
54310 Hòa Thắng 110 5744 3257 5505 3195 -4.34% -1.93% 8288 6082 30.69% 46.45% 9443 6521 39.17% 50.06%
54311 Lương Sơn 110 7014 4174 6692 4214 -4.81% 0.97% 8478 5406 17.27% 22.80% 8528 5430 17.76% 23.13%
54312 Phan Rí 110 7048 5468 7480 5971 5.79% 8.43% 8959 7320 21.34% 25.30% 10989 9366 35.87% 41.62%
54313 Tuy Phong 110 5453 5864 6514 6892 16.29% 14.92% 8341 8607 34.63% 31.87% 9488 9627 42.53% 39.09%
54314 KCN Vĩnh Hảo 110 4729 3618 5220 4187 9.40% 13.60% 6242 4903 24.23% 26.20% 6600 5060 28.34% 28.49%
54315 Tân Thành 110 5327 2960 5226 2903 -1.92% -1.93% 5434 3019 1.98% 1.98% 5451 3022 2.28% 2.07%
54316 TĐ Bắc Bình 110 6296 5880 6217 5733 -1.26% -2.57% 6773 6221 7.05% 5.48% 7104 6425 11.37% 8.48%
54318 Rẽ Lương Sơn 110 7099 4241 6773 4291 -4.80% 1.17% 8555 5457 17.02% 22.29% 8595 5480 17.41% 22.62%
54319 TC 110kV Hàm Tân 2 110 10962 8429 10832 8330 -1.20% -1.19% 11116 8568 1.39% 1.62% 11144 8578 1.63% 1.74%
54321 TĐ Hàm Thuận 110 7094 5680 6987 5589 -1.54% -1.62% 7191 5739 1.34% 1.03% 7207 5745 1.56% 1.14%
54322 TC 110kV Phan Thiết 2 110 15231 11676 14972 11506 -1.73% -1.48% 16310 12645 6.62% 7.66% 16601 12760 8.26% 8.50%
54323 TC 110kV TĐ Đại Ninh 110 7433 7386 7398 7264 -0.47% -1.67% 8103 7931 8.27% 6.88% 8603 8296 13.60% 10.97%
54324 Hòa Thắng WPP 110
6482 6401
5701 5945
9212 8831
53302 Ninh Phước 110 5141 3543 5426 4407 5.26% 19.60% 6069 4901 15.29% 27.70% 6172 4948 16.71% 28.39%
53303 110kV Tháp Chàm 110 6749 5562 7071 6217 4.56% 10.53% 7600 6672 11.20% 16.63% 7660 6704 11.89% 17.04%
53304 TC 110kV TĐ Đa Nhim 110 6139 5686 6087 5618 -0.84% -1.21% 6289 5805 2.39% 2.05% 6301 5813 2.57% 2.18%
53305 Ninh Sơn 110 5450 3995 5436 3980 -0.25% -0.36% 5688 4164 4.19% 4.08% 5705 4171 4.46% 4.24%
53306 TC 110kV Tháp Chàm 110 6806 6061 7045 6456 3.39% 6.12% 7527 6891 9.58% 12.04% 7576 6921 10.17% 12.42%
53307 Phước Hữu WPP 110
5929 5498
6563 6066
6650 6117
82
Results of short circuit current calculation show that:
Alternative 1, three phase short circuit current increases up to 16.87% at Tuy Phong node, one phase
short circuit current increases up to 15.03% at Tuy Phong node.
Alternative 2, three phase short circuit current increases up to 35.16% at Mui Ne node, one phase short
circuit current increases up to 46.46% at Hoa Thang node.
Alternative 3, three phase short circuit current increases up to 42.93% at Tuy Phong node, one phase
short circuit current increases up to 50.06% Hoa Thang node.
3.6. IMPACTS OF HARMONIC ON ELECTRICAL SYSTEM
3.6.1 Input assumptions
In this case, it is possible to consider the main connection point of the plant as Phan Ri 110kV station,
from this station are two 110kV lines to the station of Dai Ninh hydroelectric plant. Calculation results
are based on the following assumptions:
• 220kV system above Dai Ninh plant is considered to be great.
• Ignoring the impacts of harmonic on other 220kV stations (in this case, harmonic will have the
most impact on the system).
• The lines are replaced by p diagram.
• Wind turbines are similar and have 2MW capacity, the system consists of 155 wind turbines.
• The transformer is replaced by transformer impedance.
• 200kV system is replaced by impedance.
• Ignoring surface effect.
• The main connection point of the plant is 110kV side of Phan Ri station.
• The connection cables in the plant are considered as the sole condenser.
3.6.2 Results of harmonic calculation
Therefore, the main results of the study are as follows:
• The biggest harmonic is level 4 harmonic with current value of 0.6% Idm.
• Total current of all harmonics is approximately 0.94% Idm.
• Total voltage of all harmonics is 0.56% Udm.
• The biggest voltage harmonic is level 4 harmonic, with value of 0.45% Udm.
It can be seen that values of calculated harmonics are very small and fall within admissible range of
IEC 61000-3 standard.
3.7. IMPACTS ON FLICKER
Results of short circuit calculation are presented in following table.
System High supply
(Max. regime)
Low supply
(Min. regime)
Short-circuit Power Sk (MVA) 1531.1 918.6
Ange X/R (degree °) 71.7 70.6
83
Results of flicker calculation are presented in the following table.
System Pst = Plt
(continuous)
Pst (switch) Plt (switch)
Start up at cut in wind speed
Start up at rated wind speed
Start up at cut in wind speed
Start up at rated wind speed
High supply 0.0416 0.0170 0.0272 0.0144 0.0230
Low supply 0.06938 0.0284 0.0454 0.0240 0.0384
In this case, the flicker still falls within admissible limits.
The deformation of voltage harmonic at connection points in comparison with current standards.
84
CHAPTER 4. CONCLUSIONS AND RECOMMENDATIONS
4.1. CONCLUSIONS
The appearance of Tuy Phong wind power plant (30MW) in the transmission electrical network of Binh
Thuan province has impacts on loading capacity of the network and the voltage at connection points. If
generated wind power is maximum, it will reduce the load for two 220kV transformer stations, Ham
Thuan and Da Nhim hydro electric plants due to the capacity of Tuy Phong wind power plant supplying
for local load and reducing the capacity mobilized from the system. For the voltage at connection points
wind turbines are able to improve voltage (better), since these turbines are able to adjust voltage within
narrow range (compared to normal power plant). When connecting wind power plant to the system, the
short circuit current at connection points and surrounding joints tends to increase but still below current
admissible limits.
The calculation of harmonic wave and voltage flicker shows that the impact of 30MW wind turbine on
the system is very small, within admissible limits.
When connecting 340MW wind power plants to the system of Binh Thuan province, overload is
possible, 110kV lines discharging the capacity of wind power plant at the moments of maximum and
minimum load. The electrical system should be improved and upgraded to ensure the loading capacity
of lines, but avoid wasteful investments should be avoided. Alternative 1 has weak structure of
electrical network, lots of new lines should be built compared to the other two Alternatives. Alternative 3
has bigger volume of investment than Alternative 2. Alternative 2 has the least investment capital (only
02 circuits of Hoa Thang – Hoa Thang and Tuy Phong – Phan Ri wind power plant lines should be
additionally built). However, in the event of N-1 failure at the end of Phan Ri to Phan Thiet line, Tuy
Phong, Phu Lac and Phuoc Huu wind power plants should reduce generation to avoide overload of
remaining lines. This can completely be done by establishing inter-control system among stations.
The voltage of local electrical network is improved when connected wind power plants are available,
since DFIG wind turbines are able to adjust the voltage within narrow range.
The appearance of 340MW wind power plant will increase short-circuit current on local electrical
network but still falls within admissible limits.
The calculation of harmonic wave and voltage flicker show that total distortion of harmonic wave and
voltage flicker with 340MV wind power fall within admissible limits.
This research does not delve deeply into selecting the optimal Alternative but focuses on analysing
possible impacts on electrical system such as loading capacity of lines, voltage at joints, short circuit,
harmonic wave and voltage flicker. The selection of Alternatives should consider economic targets of
each Alternative.
85
4.2. RECOMMENDATIONS
As analyzed above, the selection of solutions to improve, upgrade electrical system to transmit all wind
power source to national electrical network depends much on economic and technical targets of each
wind power plant, more specific research into these targets is needed.
The wind potential in Binh Thuan – Ninh Thuan provinces is great; however, the load is small.
Therefore, demand for transmitting big capacity to other distant load areas arises. To select the best
transmission Alternative, it is necessary to study general solutions to electrical network with long-term
vision of 10-20 years to build a safe, consistent, sustainable, economical and effective electrical
network.
86
REFERENCES
[1] Institute of Energy, " National master plan for power development in the period of 2011-2020,
with a vision to 2030," Ministry of Industry and Trade, Hanoi, 2011.
[2] PECC3, "Wind power development master plan of Binh Thuan province in the period of 2009-
2015, with a vision to 2020," Nha Trang 2009.
[3] PECC3, "Wind power development master plan of Binh Thuan province in the period of 2011-
2015, with a vision to 2020," Nha Trang2011.
[4] NLDC, "Report on national electrical network operation in 2010," EVN, Hanoi, 2011.
[5] GIZ-IE, "Contract: Stydy on impacts of intergration of wind power in to the national grid," ed.
Vietnam, 2012.
[6] B. C. t. Institute of Energy, "Considering the connection of Binh Thuan wind power plants to
National electrical system," Hanoi, 2008.
[7] EVN-NLDC, "Annex to Summary of National electrical system operation 2011,"
National Load Despatch Center,", Hanoi 2012.
[8] REVN, "Wind power investment and construction project 1 - Binh Thuan," Hanoi, 2007.
[9] Circular on Transmission Power System, Ministry of Industry and Trade, 2010.
[10] Regulation on Distribution Power System, Ministry of Industry and Trade, 2010.
87
APPENDIXES
Appendix Error! No text of specified style in document..1 Active capacity of DZ 110kV network of Bình Thuận in năm 2011(without 30 MW Tuy Phong wind power plant)
No. Lines Voltage
(kV)
Diameter/Capacity MBA
(MVA)
Admissible operating
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, without Tuy Phong wind power
1 TBA 220/110kV TĐ Hàm Thuận
220/110 1x63 63 65+31 j 114 Overload
2 TBA 220/110kV Phan Thiết 2
220/110 2x250 500 143+67 j 32
3 TBA 220/110kV TĐ Đại Ninh
220/110 2x63 126 47+6 j 38
4 TBA 220/110kV TĐ Đại Ninh
220/110 1x63 63 -46-2 j 73
5 TBA 220/110kV TĐ Đa Nhim
220/110 2x63 126 -119-33 j 98
6 TĐ Đa My - TĐ Hàm Thuận
220 AC400 825 15 46+8 j 15
7 Đức Linh - Hàm Thuận
110 AC185 510 53 -53-3 j 55
8 Hàm Thuận - Phan Thiết 2
110 2xAC185 1020 56 10+14 j 9
9 Phan Thiết 2 - Mũi Né
110 AC185 510 25 28+9 j 30
10 Phan Thiết 2 - Phan Thiết
110 2xAC185 1020 1 124+62 j 71
11 Phan Thiết - Thuận Nam
110 AC185 510 27 39+21 j 46
12 Thuận Nam - Hàm Tân
110 AC185 510 34 -29-2 j 30
13 Hàm Tân - Xuyên Mộc
110 2xAC185 1020 48 -57-11 j 30
14 Phan Thiết - Rẽ Lương Sơn
110 AC185 510 33 -10+9 j 14
15 Rẽ Lương Sơn - Lương Sơn
110 2xAC185 1020 0,5 22+7 j 12
16 Rẽ Lương Sơn - Phan Rí
110 AC185 510 14 -32+3 j 33
17 Phan Rí - TĐ Đại Ninh
110 AC185 510 43 22+7 j 24
88
18 TĐ Bắc Bình - TĐ Đại Ninh
110 AC150 445 5 33+20 j 46
19 Phan Rí - Tuy Phong
110 AC185 510 2 8+5 j 10
20 Tuy Phong - Ninh Phước
110 AC185 510 42 8+5 j 10
21 Ninh Phước - Tháp Chàm
110 AC185 510 15 -9+2 j 9
22 Tháp Chàm - Ninh Sơn
110 AC185 510 42 -52-10 j 54
23 Ninh Sơn - TĐ Đa Nhim
110 ACSR336.4MCM
800 14 -70-17 j 47
89
Appendix Error! No text of specified style in document..2 Active capacity of DZ 110 kV network of Bình Thuận in 2011 (with 30 MW Tuy Phong wind power plant).
No. Lines Voltage
(kV)
Diameter/ Capacity MBA
(MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current
carrying
capacity (%)
Remark
Maximum load regimei, rainy season, with Tuy Phong wind power (30 MW)
1 TBA 220/110kV TĐ Hàm
Thuận 220/110 1x63 63
63+29 j 110 Overloa
d
2 TBA 220/110kV Phan Thiết 2 220/110 2x250 500
135+63 j 30
3 TBA 220/110kV TĐ Đại Ninh 220/110 2x63 126
38+3 j 30
6 TBA 220/110kV TĐ Đại Ninh 220/110 1x63 63
-38+0 j 60
7 TBA 220/110kV TĐ Đa Nhim 220/110 2x63 126
-110-29 j 90
8 TĐ Đa My - TĐ Hàm Thuận 220 AC400 825 15 44+3 j 14
15 Đức Linh - Hàm Thuận 110 AC185 510 53 -54-3 j 56
16 Hàm Thuận - Phan Thiết 2 110 2xAC185 1020 56 6+13 j 7
17 Phan Thiết 2 - Mũi Né 110 AC185 510 25 28+9 j 30
18 Phan Thiết 2 - Phan Thiết 110 AC185 1020 1 113+59 j 66
19 Phan Thiết - Thuận Nam 110 AC185 510 27 41+22 j 48
20 Thuận Nam - Hàm Tân 110 AC185 510 34 -27-2 j 28
21 Hàm Tân - Xuyên Mộc 110 2xAC185 1020 48 -55-11 j 29
24 Phan Thiết - Rẽ Lương Sơn 110 AC185 510 33 -23+6 j 24
25 Rẽ Lương Sơn - Lương Sơn 110 2xAC185 1020 0,5 22+7 j 12
26 Rẽ Lương Sơn - Phan Rí 110 AC185 510 14 -45-1 j 46
27 Phan Rí - TĐ Đại Ninh 110 AC185 510 43 22+7 j 24
28 TĐ Bắc Bình - TĐ Đại Ninh 110 AC150 445 5 33+16 j 43
29 Phan Rí - Tuy Phong WPP 110 AC185 510 2 -13-3 j 14
30 Tuy Phong WPP - Ninh Phước 110 AC185 510 42 16+8 j 18
31 Ninh Phước - Tháp Chàm 110 AC185 510 15 -1+4 j 4
32 Tháp Chàm - Ninh Sơn 110 AC185 510 42 -43-7 j 45
33 Ninh Sơn - TĐ Đa Nhim 110 ACSR336.4MCM 800 14 -61-13 j 41
Minimum load regime, dry season, with Tuy Phong power (30 MW)
1 TBA 220/110kV TĐ Hàm
Thuận 220/110 1x63 63
17+3 j 27
2 TBA 220/110kV Phan Thiết 2 220/110 2x250 500
35+16 j 8
3 TBA 220/110kV TĐ Đại Ninh 220/110 2x63 126
0+1 j 1
90
No. Lines Voltage
(kV)
Diameter/ Capacity MBA
(MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current
carrying
capacity (%)
Remark
6 TBA 220/110kV TĐ Đại Ninh 220/110 1x63 63
0-1 j 2
7 TBA 220/110kV TĐ Đa Nhim 220/110 2x63 126
-25-11 j 22
8 TĐ Đa My - TĐ Hàm Thuận 220 AC400 825 15 26-5 j 8
15 Đức Linh - Hàm Thuận 110 AC185 510 53 -15+3 j 16
16 Hàm Thuận - Phan Thiết 2 110 2xAC185 1020 56 2+7 j 4
17 Phan Thiết 2 - Mũi Né 110 AC185 510 25 10+2 j 10
18 Phan Thiết 2 - Phan Thiết 110 AC185 1020 1 27+24 j 19
19 Phan Thiết - Thuận Nam 110 AC185 510 27 1+13 j 13
20 Thuận Nam - Hàm Tân 110 AC185 510 34 -23+6 j 24
21 Hàm Tân - Xuyên Mộc 110 2xAC185 1020 48 -32+3 j 17
24 Phan Thiết - Rẽ Lương Sơn 110 AC185 510 33 -7+1 j 7
25 Rẽ Lương Sơn - Lương Sơn 110 2xAC185 1020 0,5 8+3 j 4
26 Rẽ Lương Sơn - Phan Rí 110 AC185 510 14 -15-0 j 15
27 Phan Rí - TĐ Đại Ninh 110 AC185 510 43 8+3 j 9
28 TĐ Bắc Bình - TĐ Đại Ninh 110 AC150 445 5 16+1 j 19
29 Phan Rí - Tuy Phong 110 AC185 510 2 -11-1 j 11
30 Tuy Phong - Ninh Phước 110 AC185 510 42 19-1 j 20
31 Ninh Phước - Tháp Chàm 110 AC185 510 15 13-2 j 14
32 Tháp Chàm - Ninh Sơn 110 AC185 510 42 -2-5 j 6
33 Ninh Sơn - TĐ Đa Nhim 110 ACSR336.4MCM 800 14 -8-6 j 7
91
Appendix 2.3 Voltage at connection points of 220 kV and 110 kV networks of Binh Thuan in 2011 with the different active power regimes
Node number
Node Voltage
(kV)
Without wind power
With wind power (total: 30MW)
Maxium load, rainy season
Maxium load, rainy season
Minimum load, dry season
Node voltage
(kV)
Difference (%)
Node voltage
(kV)
Difference (%)
Node voltage
(kV)
Difference (%)
53201 TĐ Đa Nhim 220 231 4.76% 231 4.76% 231 4.76%
54201 TĐ Hàm Thuận
220 231 4.76% 231 4.76% 231 4.76%
54202 Phan Thiết 2 220 221 0.45% 222 0.90% 229 3.93%
54205 TĐ Đại Ninh 220 231 4.76% 231 4.76% 231 4.76%
54206 TĐ Đa My 220 231 4.76% 231 4.76% 231 4.76%
59201 Long Bình 220 218 -0.92% 218 -0.92% 227 3.08%
53301 Ninh Phước 110 105 -4.76% 107 -2.80% 113 2.65%
53302 Tháp Chàm 110 105 -4.76% 107 -2.80% 113 2.65%
53303 Ninh Sơn 110 108 -1.85% 109 -0.92% 114 3.51%
53304 TĐ Đa Nhim 110 110 0.00% 111 0.90% 114 3.51%
54305 Hàm Tân 110 105 -4.76% 105 -4.76% 113 2.65%
54306 Thuận Nam 110 103 -6.80% 103 -6.80% 112 1.79%
54308 Phan Thiết 110 107 -2.80% 107 -2.80% 114 3.51%
54309 Mũi Né 110 105 -4.76% 106 -3.77% 113 2.65%
54311 Lương Sơn 110 106 -3.77% 108 -1.85% 114 3.51%
54312 Phan Rí 110 107 -2.80% 109 -0.92% 114 3.51%
54313 Tuy Phong 110 106 -3.77% 109 -0.92% 114 3.51%
54316 TĐ Bắc Bình 110 115 4.35% 116 5.17% 116 5.17%
54318 Rẽ Lương Sơn
110 106 -3.77% 108 -1.85% 114 3.51%
54321 Hàm Thuận 110 109 -0.92% 109 -0.92% 115 4.35%
54322 Phan Thiết 2 110 107 -2.80% 107 -2.80% 114 3.51%
54323 TĐ Đại Ninh 110 114 3.51% 115 4.35% 115 4.35%
92
Appendix 3.18 Active capacity of DZ 220 kV and 110 kW networks of Bình Thuận (without new WPPs)
No. Lines Voltage (kV)
Diameter/Capacity MBA (MVA)
Admissible operating flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity (%)
Remark
Maximum load regime, rainy season, with Tuy Phong wind power only
1 TBA 220/110kV Hàm Tân 2
220 1x250 250Typeequationhere. 117+55 j
52%
2 TBA 220/110kV Phan Thiết 2
220 125+250 375 232+85 j
66%
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63 48+21 j 83%
4 TBA220/110kV TĐ Đại Ninh
220 2x63 126 -68-5 j 54%
5 TĐ Hàm Thuận - TĐ Đa Mi
220 AC400 825 400 19-4 j 6%
6 Hàm Tân 2 - KCN Sơn Mỹ
110 AC240 605 2 117+47 j
109% Overload
7 KCN Sơn Mỹ - Hàm Tân
110 AC240 605 10 68+35 j 66%
8 KCN Sơn Mỹ - Phan Thiết
110 AC240 605 64 -18+2 j 16%
9 KCN Sơn Mỹ - Xuyên Mộc
110 AC240 605 36 46+1 j 40%
10 Hàm Tân - Tân Thành
110 AC240 605 30 1+5 j 4%
11 Hàm Tân - Thuận Nam
110 AC185 510 34 11+9 j 15%
12 Thuận Nam - Hàm Kiệm
110 AC185 510 14 -45-8 j 47%
13 Hàm Kiệm - Tân Thành
110 AC240 605 22 14-2 j 12%
14 Hàm Kiệm - Phan Thiết
110 AC185 510 15 -94-18 j
98%
15 Phan Thiết - Phan Thiết 2
110 3xAC185 1530 29 -178-53 j
64%
16 Phan Thiết - Rẽ Lương Sơn
110 AC185 510 33 7+15 j 17%
93
17 Phan Thiết 2 - Mũi Né
110 AC185 510 25 39+21 j 46%
18 Mũi Né - Hòa Thắng
110 AC240 605 13 -4+6 j 6%
19 Lương Sơn - Hòa Thắng
110 AC240 605 13 28+2 j 24%
20 TĐ Hàm Thuận - Phan Thiết 2
110 AC185 510 58 -1+6 j 6%
21 Ma Lâm - Phan Thiết 2
110 AC185 510 13 -14+3 j 15%
22 TĐ Hàm Thuận - Ma Lâm
110 AC185 510 45 8+9 j 12%
23 TĐ Hàm Thuận - Tánh Linh
110 AC185 510 33 41+1 j 42%
24 Đức Linh - Tánh Linh
110 AC185 510 20 -29+3 j 30%
25 Đức Linh - Xuân Lộc
110 AC185 510 41 -11+8 j 14%
26 Rẽ Lương Sơn - Lương Sơn
110 2xAC185 1020 0,5 77+18 j 41%
27 Rẽ Lương Sơn - Phan Rí
110 AC185 510 14 -70-2 j 72%
28 Phan Rí - TĐ Đại Ninh
110 2xAC185 1020 43 -98-20 j
51%
29 TĐ Bắc Bình - TĐ Đại Ninh
110 AC150 445 5 33+20 j 46%
30 Phan Rí - Tuy Phong
110 AC185 510 2 -22-1 j 23%
31 Tuy Phong - CN Vĩnh Hảo
110 AC185 510 13 7+7 j 10%
94
Appendix 3.2 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (PA 1)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with 340 MW wind power
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
104+59 j 48%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
177+90 j 53%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
41+23 j 75%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
37-6 j 30%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 27-5 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 104+52 j 101% Overload
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 59+38 j 61%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -27+5 j 24%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 50-0 j 43%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -4+7 j 7%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 6+11 j 13%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -49-6 j 51%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 19-3 j 17%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -103-15 j 107% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -144-64 j 54%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -45+31 j 56%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 6+28 j 29%
18 Mũi Né - Hòa Thắng 110 AC240 605 13 -36+14 j 34%
95
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 62-4 j 54%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -7+8 j 11%
21 Ma Lâm - Phan Thiết
2 110 AC185 510 13 -19+5 j 20%
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 2+11 j 12%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 46-1 j 47%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -33+6 j 35%
25 Đức Linh - Xuân Lộc 110 AC185 510 41 -16+11 j 20%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 110+12 j 57%
27 Hòa Thắng WPP -
Rẽ Lương Sơn 110 AC185 510 22 164+3 j 169% Overload
28 Phan Rí - Hòa Thắng WPP
110 AC185 510 20 47-3 j 48%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 4-28 j 15%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+20 j 46%
31 Phan Rí - Tuy Phong 110 AC185 510 2 -100+16
j 104% Overload
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 -17-1 j 18%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 66-1 j 68%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 42-10 j 44%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 31-14 j 35%
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 -79+13 j 82%
Minimum load regime, dry season, with 340 MW wind power
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
30+17 j 14%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
27+24 j 10%
96
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
4+4 j 9%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
90+1 j 71%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 18-4 j 6%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 30+17 j 30%
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 17+13 j 19%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -14+2 j 12%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 20-1 j 17%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -4+2 j 4%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 0+4 j 4%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -21-1 j 22%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 10-2 j 9%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -43-3 j 44%
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -24-22 j 11%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -54+15 j 58%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -22+11 j 25%
18 Mũi Né - Hòa Thắng 110 AC240 605 13 -38+6 j 33%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 47-2 j 41%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -10+3 j 11%
21 Ma Lâm - Phan Thiết
2 110 AC185 510 13 -15+3 j 16%
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 -7+4 j 8%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 21-4 j 22%
97
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -16+4 j 17%
25 Đức Linh - Xuân Lộc 110 AC185 510 41 -10+5 j 12%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 65+4 j 34%
27 Hòa Thắng WPP -
Rẽ Lương Sơn 110 AC185 510 22 125-0 j 129% Overload
28 Phan Rí - Hòa Thắng WPP
110 AC185 510 20 7-12 j 14%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 75+6 j 39%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 16-4 j 19%
31 Phan Rí - Tuy Phong 110 AC185 510 2 -100+1 j 103% Overload
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 -16+3 j 17%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 66-1 j 68%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 56-5 j 58%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 51-7 j 53%
36 Phước Hữu WPP -
Tháp Chàm 110 AC185 510 9 -99-1 j 102% Overload
98
Appendix 3.3 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (PA 2)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with 340 MW wind power
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
96+57 j 45%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
142+79 j 43%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
36+21 j 66%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
10-5 j 9%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 27-6 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 95+51 j 94%
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 53+38 j 57%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -31+5 j 27%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 52+0 j 45%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -6+7 j 8%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 3+12 j 13%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -52-6 j 54%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 22-3 j 19%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -109-15 j 113% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -125-69 j 49%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -47+20 j 53%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -18+15 j 24%
18 Mũi Né - Hòa Thắng 110 AC240 605 13 -87+15 j 77%
99
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -3-6 j 6%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -11+8 j 14%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -23+5 j 24%
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 -2+11 j 12%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 49-1 j 50%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -36+6 j 38%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -19+12 j 23%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 45+10 j 24%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 118+7 j 90%
28 Phan Rí - Rẽ Lương
Sơn 110 AC185 510 14 97-1 j 100%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 -22-24 j 17%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+18 j 44%
31 Phan Rí - Tuy
Phong 110 2xAC185 1020 16
-123+10 j
64%
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 6-3 j 7%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 43+2 j 44%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 18-6 j 20%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 8-8 j 12%
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 -57+7 j 59%
Minimum load regimei, dry season, with 340 MW wind power
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
23+17 j 11%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
-3+17 j 5%
100
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
0+3 j 5%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
68+1 j 54%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 18-4 j 6%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 23+17 j 25%
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 12+13 j 15%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -18+2 j 16%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 22-1 j 19%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -6+2 j 5%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 -3+4 j 5%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -23-1 j 24%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 12-2 j 11%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -48-3 j 49%
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 0-21 j 7%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -49+8 j 51%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -33+5 j 34%
18 Mũi Né - Hòa Thắng 110 AC240 605 13 -89+4 j 77%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -17-4 j 15%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -13+3 j 14%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -18+3 j 19%
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 -10+4 j 11%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 23-4 j 24%
101
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -19+5 j 20%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -12+6 j 14%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 1+2 j 1%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 118+10 j 90%
28 Phan Rí - Rẽ Lương
Sơn 110 AC185 510 14 51-4 j 53%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 53+8 j 28%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 16-8 j 21%
31 Phan Rí - Tuy
Phong 110 2xAC185 1020 16 -122-9 j 63%
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 5+4 j 7%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 44+0 j 45%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 35-3 j 36%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 31-4 j 32%
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 -79-6 j 82%
102
Appendix Error! No text of specified style in document..4 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (PA 3)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with 340 MW wind power
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
95+58 j 45%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
138+79 j
42%
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63
35+21 j 65%
4 TBA220/110kV
TĐ Đại Ninh 220 2x63 126
6-5 j 6%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 27-6 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 95+51 j 94%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 53+38 j 57%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -32+5 j 28%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 52-0 j 45%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -7+7 j 9%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 3+12 j 13%
12 Thuận Nam -
Hàm Kiệm 110 AC185 510 14 -52-6 j 54%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 22-3 j 19%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15
-110-15 j
114% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29
-123-69 j
48%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -47+20 j 53%
17 Phan Thiết 2 -
Mũi Né 110 AC185 510 25 -21+15 j 27%
18 Mũi Né - Hòa 110 AC240 605 13 -94+17 j 83%
103
Thắng
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -13-4 j 12%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -11+8 j 14%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -24+5 j 25%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 -3+11 j 12%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 49-1 j 50%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -37+7 j 39%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -19+12 j 23%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 36+12 j 20%
27 Hòa Thắng WPP
- Hòa Thắng 110 AC300 690 15 135+7 j 103% Overload
28 Hòa Thắng WPP
- Phan Rí 110 AC240 605 13 -17-1 j 15%
29 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 87-0 j 90%
30 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 -26-25 j 19%
31 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+18 j 44%
32 Phan Rí - Tuy
Phong 110 2xAC185 1020 16 -126+8 j 65%
33 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 9-3 j 10%
34 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 41+3 j 42%
35 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 16-6 j 18%
36 Ninh Phước - Phước Hữu
WPP 110 AC185 510 6 6-8 j 10%
37 Tháp Chàm - Phước Hữu
WPP 110 AC185 510 9 -55+7 j 57%
Minimum load regime, dry season, with 340 MW wind power
104
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
24+17 j 12%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
0+17 j 5%
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63
1+3 j 5%
4 TBA220/110kV
TĐ Đại Ninh 220 2x63 126
71+1 j 56%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 18-4 j 6%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 24+17 j 26%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 12+13 j 15%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -18+2 j 16%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 22-1 j 19%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -6+2 j 5%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 -3+4 j 5%
12 Thuận Nam -
Hàm Kiệm 110 AC185 510 14 -23-1 j 24%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 12-2 j 11%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -48-3 j 49%
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -1-21 j 7%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -49+9 j 51%
17 Phan Thiết 2 -
Mũi Né 110 AC185 510 25 -32+5 j 33%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13 -85+5 j 74%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -11-3 j 10%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -13+3 j 14%
21 Ma Lâm - Phan 110 AC185 510 13 -18+3 j 19%
105
Thiết 2
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 -10+4 j 11%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 23-4 j 24%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -18+5 j 19%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -12+6 j 14%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 7+3 j 4%
27 Hòa Thắng WPP
- Hòa Thắng 110 AC300 690 15 107+7 j 82%
28 Hòa Thắng WPP
- Phan Rí 110 AC240 605 13 11+6 j 11%
29 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 58-3 j 60%
30 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 55+10 j 29%
31 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 16-11 j 23%
32 Phan Rí - Tuy
Phong 110 2xAC185 1020 16 -121-7 j 62%
33 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 4+3 j 5%
34 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 46+1 j 47%
35 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 37-2 j 38%
36 Ninh Phước - Phước Hữu
WPP 110 AC185 510 6 32-3 j 33%
37 Tháp Chàm - Phước Hữu
WPP 110 AC185 510 9 -81-6 j 84%
106
Appendix Error! No text of specified style in document..5 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (1 failure mode of DZ 110 kV Phan Thiết – Phan Thiết 2)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with 340 MW wind power , 1 failure mode of Phan Thiết - Phan Thiết 2
1 TBA 220/110kV Hàm
Tân 2 220 1x250 250
105+57 j 48%
2 TBA 220/110kV Phan
Thiết 2 220 125+250 375
174+75 j 51%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
40+21 j 72%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
35-1 j 28%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 26-5 j 8%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 105+50 j 101% Overload
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 60+37 j 61%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -26+4 j 23%
9 KCN Sơn Mỹ - Xuyên
Mộc 110 AC240 605 36 50+0 j 43%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -3+7 j 7%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 6+11 j 13%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -49-7 j 51%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 19-3 j 17%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -103-16 j 107% Overload
15 Phan Thiết - Phan Thiết 2 (đứt 1 lộ)
110 2xAC185 1020 29 -139-53 j 77%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -48+18 j 53%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 6+21 j 22%
107
18 Mũi Né - Hòa Thắng 110 AC240 605 13 -36+7 j 32%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 61+3 j 53%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -8+7 j 11%
21 Ma Lâm - Phan Thiết
2 110 AC185 510 13 -20+4 j 21%
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 1+10 j 10%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 47+0 j 48%
24 Đức Linh - Tánh Linh 110 AC185 510 20 -34+5 j 35%
25 Đức Linh - Xuân Lộc 110 AC185 510 41 -17+10 j 20%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 110+19 j 57%
27 Hòa Thắng WPP -
Rẽ Lương Sơn 110 AC185 510 22 167+21 j 173% Overload
28 Phan Rí - Hòa Thắng WPP
110 AC185 510 20 50-12 j 53%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 2+5 j 3%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33-9 j 40%
31 Phan Rí - Tuy Phong 110 AC185 510 2 -101-9 j 104% Overload
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 -16+1 j 16%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 65+7 j 67%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 40-2 j 41%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 30-5 j 31%
36 Tháp Chàm - Phước
Hữu WPP 110 AC185 510 9 -78-11 j 81%
108
Appendix 3.6 Voltage variation at connection points and adjacent nodes in 2015 in failure mode
Node number Node Voltage
(kV)
Failure mode of Phan Thiết - Phan Thiết 2
Maximum load, rainy season
Node voltage (kV) Difference (%)
53201 TĐ Đa Nhim 220 231 4.76%
54201 TĐ Hàm Thuận 220 231 4.76%
54202 Phan Thiết 2 220 226 2.65%
54204 Hàm Tân 2 220 224 1.79%
54205 TĐ Đại Ninh 220 231 4.76%
54206 TĐ Đa My 220 231 4.76%
59201 Long Bình 220 225 2.22%
60201 Bà Rịa 220 225 2.22%
53302 Ninh Phước 110 116 5.17%
53303 Tháp Chàm 110 114 3.51%
53304 TC110kV TĐ Đa
Nhim 110 113 2.65%
53305 Ninh Sơn 110 113 2.65%
53306 TC110kV Tháp
Chàm 110 114 3.51%
53307 Phước Hữu WPP 110 116 5.17%
54301 KCN Sơn Mỹ 110 108 -1.85%
54302 Đức Linh 110 108 -1.85%
54303 Tánh Linh 110 109 -0.92%
54304 Ma Lâm 110 110 0.00%
54305 Hàm Tân 110 106 -3.77%
54306 Thuận Nam 110 104 -5.77%
54307 Hàm Kiệm 110 106 -3.77%
54308 Phan Thiết 110 109 -0.92%
54309 Mũi Né 110 108 -1.85%
54310 Hòa Thắng 110 108 -1.85%
54311 Lương Sơn 110 109 -0.92%
54312 Phan Rí 110 116 5.17%
109
Node number Node Voltage
(kV)
Failure mode of Phan Thiết - Phan Thiết 2
Maximum load, rainy season
Node voltage (kV) Difference (%)
54313 Tuy Phong WPP 110 119 7.56%
54314 CN Vĩnh Hảo 110 118 6.78%
54315 Tân Thành 110 106 -3.77%
54316 TĐ Bắc Bình 110 116 5.17%
54318 Rẽ Lương Sơn 110 109 -0.92%
54319 TC110kV Hàm Tân 2 110 109 -0.92%
54321 Hàm Thuận 110 111 0.90%
54322 Phan Thiết 2 110 110 0.00%
54323 TĐ Đại Ninh 110 115 4.35%
59301 Xuân Trường 110 109 -0.92%
60301 Xuyên Mộc 110 106 -3.77%
60302 Bà Rịa 110 107 -2.80%
54324 Hòa Thắng WPP 110 116 5.17%
54225 Phú Lạc WPP 110 118 6.78%
110
Appendix Error! No text of specified style in document..7 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV Lương Sơn – Hòa Thắng)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with 340 MW wind power, failure mode of Lương Sơn - Hòa thắng
1 TBA 220/110kV Hàm
Tân 2 220 1x250 250
106+60 j 49%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
190+97 j 57%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
43+24 j 78%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
49-7 j 39%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 26-6 j 8%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 106+52 j 102% Overload
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 61+39 j 63%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -25+6 j 22%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 49-0 j 43%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -3+7 j 7%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 7+12 j 14%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -48-6 j 50%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 18-4 j 16%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -102-15 j 106% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -97-72 j 41%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -88+40 j 99%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 68+26 j 75%
111
18 Mũi Né - Hòa Thắng 110 AC240 605 13 24+8 j 22%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 #N/A #N/A
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -5+9 j 11%
21 Ma Lâm - Phan Thiết
2 110 AC185 510 13 -18+6 j 20%
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 3+12 j 13%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 44-1 j 45%
24 Đức Linh - Tánh Linh 110 AC185 510 20 -32+6 j 34%
25 Đức Linh - Xuân Lộc 110 AC185 510 41 -15+11 j 19%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 49+16 j 27%
27 Hòa Thắng WPP -
Rẽ Lương Sơn 110 AC185 510 22 147+1 j 151% Overload
28 Phan Rí - Hòa Thắng WPP
110 AC185 510 20 29-2 j 30%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 16-29 j 17%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+20 j 46%
31 Phan Rí - Tuy Phong 110 AC185 510 2 -94+15 j 98%
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 -23-1 j 24%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 72-2 j 74%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 48-11 j 51%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 37-15 j 41%
36 Phước Hữu WPP -
Tháp Chàm 110 AC185 510 9 -85+15 j 89%
112
Appendix Error! No text of specified style in document..8 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node Voltage
(kV)
Failure mode of Lương Sơn - Hòa Thắng
Maximum load, rainy season
Node voltage
(kV) Difference (%)
53201 TĐ Đa Nhim 220 231 4.76%
54201 TĐ Hàm Thuận 220 231 4.76%
54202 Phan Thiết 2 220 225 2.22%
54204 Hàm Tân 2 220 224 1.79%
54205 TĐ Đại Ninh 220 231 4.76%
54206 TĐ Đa My 220 231 4.76%
59201 Long Bình 220 225 2.22%
60201 Bà Rịa 220 225 2.22%
53302 Ninh Phước 110 113 2.65%
53303 Tháp Chàm 110 112 1.79%
53304 TC110kV TĐ Đa
Nhim 110 112 1.79%
53305 Ninh Sơn 110 112 1.79%
53306 TC110kV Tháp
Chàm 110 112 1.79%
53307 Phước Hữu WPP 110 113 2.65%
54301 KCN Sơn Mỹ 110 108 -1.85%
54302 Đức Linh 110 108 -1.85%
54303 Tánh Linh 110 108 -1.85%
54304 Ma Lâm 110 109 -0.92%
54305 Hàm Tân 110 106 -3.77%
54306 Thuận Nam 110 104 -5.77%
54307 Hàm Kiệm 110 105 -4.76%
54308 Phan Thiết 110 108 -1.85%
54309 Mũi Né 110 104 -5.77%
54310 Hòa Thắng 110 103 -6.80%
113
Node number Node Voltage
(kV)
Failure mode of Lương Sơn - Hòa Thắng
Maximum load, rainy season
Node voltage
(kV) Difference (%)
54311 Lương Sơn 110 108 -1.85%
54312 Phan Rí 110 113 2.65%
54313 Tuy Phong WPP 110 114 3.51%
54314 CN Vĩnh Hảo 110 113 2.65%
54315 Tân Thành 110 105 -4.76%
54316 TĐ Bắc Bình 110 115 4.35%
54318 Rẽ Lương Sơn 110 108 -1.85%
54319 TC110kV Hàm
Tân 2 110 109 -0.92%
54321 Hàm Thuận 110 110 0.00%
54322 Phan Thiết 2 110 109 -0.92%
54323 TĐ Đại Ninh 110 115 4.35%
59301 Xuân Trường 110 109 -0.92%
60301 Xuyên Mộc 110 105 -4.76%
60302 Bà Rịa 110 107 -2.80%
54324 Hòa Thắng WPP 110 112 1.79%
54225 Phú Lạc WPP 110 114 3.51%
114
Appendix Error! No text of specified style in document..9 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV Điện gió Phước Hữu – Tháp Chàm)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Minimum load regime, dry season, with wind power, failure mode of Phước Hữu - Tháp Chàm
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
26+26 j 15%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
2+54 j 14%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
2+8 j 13%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
142-25 j 114% Overload
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 19-4 j 6%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 26+25 j 31%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 15+18 j 20%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -16+7 j 15%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 20-3 j 18%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -5+5 j 6%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 -1+7 j 7%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -22+1 j 23%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 11-5 j 10%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -46+2 j 47%
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -9-41 j 14%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -73+44 j 88%
17 Phan Thiết 2 - Mũi 110 AC185 510 25 -35+28 j 46%
115
Né
18 Mũi Né - Hòa
Thắng 110 AC240 605 13 -51+22 j 48%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 61-17 j 55%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -11+7 j 13%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -16+7 j 18%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 -8+8 j 12%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 21-7 j 23%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -16+7 j 18%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -10+8 j 13%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 79-11 j 41%
27 Hòa Thắng WPP -
Rẽ Lương Sơn 110 AC185 510 22 163-29 j 170% Overload
28 Phan Rí - Hòa Thắng WPP
110 AC185 510 20 46-25 j 54%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 131-35 j 70%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 16+20 j 30%
31 Phan Rí - Tuy
Phong 110 AC185 510 2
-195+53 j
208% Overload
32 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 85-21 j 90%
33 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 -36+15 j 40%
34 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 -45+12 j 48%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 -49+10 j 51%
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 #N/A #N/A
116
Appendix Error! No text of specified style in document..10 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node Voltage
(kV)
Failure mode of Phước Hữu - Tháp Chàm
Minimum load, dry season
Node voltage (kV)
Difference (%)
53201 TĐ Đa Nhim 220 231 4.76%
54201 TĐ Hàm Thuận 220 231 4.76%
54202 Phan Thiết 2 220 230 4.35%
54204 Hàm Tân 2 220 230 4.35%
54205 TĐ Đại Ninh 220 231 4.76%
54206 TĐ Đa My 220 231 4.76%
59201 Long Bình 220 232 5.17%
60201 Bà Rịa 220 229 3.93%
53302 Ninh Phước 110 116 5.17%
53303 Tháp Chàm 110 115 4.35%
53304 TC110kV TĐ Đa
Nhim 110 115 4.35%
53305 Ninh Sơn 110 115 4.35%
53306 TC110kV Tháp
Chàm 110 115 4.35%
53307 Phước Hữu
WPP 110 116 5.17%
54301 KCN Sơn Mỹ 110 113 2.65%
54302 Đức Linh 110 114 3.51%
54303 Tánh Linh 110 113 2.65%
54304 Ma Lâm 110 113 2.65%
54305 Hàm Tân 110 112 1.79%
54306 Thuận Nam 110 111 0.90%
54307 Hàm Kiệm 110 112 1.79%
54308 Phan Thiết 110 113 2.65%
54309 Mũi Né 110 112 1.79%
117
Node number Node Voltage
(kV)
Failure mode of Phước Hữu - Tháp Chàm
Minimum load, dry season
Node voltage (kV)
Difference (%)
54310 Hòa Thắng 110 111 0.90%
54311 Lương Sơn 110 111 0.90%
54312 Phan Rí 110 113 2.65%
54313 Tuy Phong WPP 110 115 4.35%
54314 CN Vĩnh Hảo 110 115 4.35%
54315 Tân Thành 110 112 1.79%
54316 TĐ Bắc Bình 110 112 1.79%
54318 Rẽ Lương Sơn 110 111 0.90%
54319 TC110kV Hàm
Tân 2 110 113 2.65%
54321 Hàm Thuận 110 114 3.51%
54322 Phan Thiết 2 110 113 2.65%
54323 TĐ Đại Ninh 110 112 1.79%
59301 Xuân Trường 110 114 3.51%
60301 Xuyên Mộc 110 112 1.79%
60302 Bà Rịa 110 113 2.65%
54324 Hòa Thắng WPP 110 113 2.65%
54225 Phú Lạc WPP 110 115 4.35%
118
Appendix Error! No text of specified style in document..191 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110kV Lương Sơn – Phan Thiết)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Minimum load regime, dry season, with 340 MW wind power, failure mode of Lương Sơn - Phan Thiết
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
35+19 j 16%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
41+33 j 14%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
6+5 j 12%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
104-11 j 83%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 18-4 j 6%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 35+18 j 34%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 20+14 j 21%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -12+3 j 11%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 19-1 j 17%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -2+3 j 3%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 1+4 j 4%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -19-1 j 20%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 8-3 j 7%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -40-3 j 41%
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -73-5 j 25%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 #N/A #N/A
119
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -53+38 j 67%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13 -70+30 j 66%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 81-22 j 73%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -8+4 j 9%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -13+4 j 14%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 -5+5 j 7%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 19-4 j 20%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -15+4 j 16%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -8+6 j 10%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 99-16 j 52%
27 Hòa Thắng WPP -
Rẽ Lương Sơn 110 AC185 510 22 102-9 j 105% Overload
28 Phan Rí - Hòa Thắng WPP
110 AC185 510 20 -16+4 j 17%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 91-28 j 49%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 16+20 j 30%
31 Phan Rí - Tuy
Phong 110 AC185 510 2 -93+19 j 98%
32 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 -24+4 j 25%
33 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 73-11 j 76%
34 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 64-15 j 68%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 59-19 j 64%
36 Phước Hữu WPP
- Tháp Chàm 110 AC185 510 9
-106+26 j
112% Overload
120
Appendix Error! No text of specified style in document..202 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node Voltage
(kV)
Failure mode of Lương Sơn - Phan Thiết
Minimum load, dry season
Node voltage
(kV) Difference (%)
53201 TĐ Đa Nhim 220 231 4.76%
54201 TĐ Hàm Thuận 220 231 4.76%
54202 Phan Thiết 2 220 231 4.76%
54204 Hàm Tân 2 220 230 4.35%
54205 TĐ Đại Ninh 220 231 4.76%
54206 TĐ Đa My 220 231 4.76%
59201 Long Bình 220 232 5.17%
60201 Bà Rịa 220 230 4.35%
53302 Ninh Phước 110 114 3.51%
53303 Tháp Chàm 110 113 2.65%
53304 TC110kV TĐ Đa
Nhim 110 113 2.65%
53305 Ninh Sơn 110 113 2.65%
53306 TC110kV Tháp
Chàm 110 113 2.65%
53307 Phước Hữu WPP 110 114 3.51%
54301 KCN Sơn Mỹ 110 114 3.51%
54302 Đức Linh 110 114 3.51%
54303 Tánh Linh 110 114 3.51%
54304 Ma Lâm 110 114 3.51%
54305 Hàm Tân 110 113 2.65%
54306 Thuận Nam 110 112 1.79%
54307 Hàm Kiệm 110 113 2.65%
54308 Phan Thiết 110 114 3.51%
54309 Mũi Né 110 113 2.65%
121
Node number Node Voltage
(kV)
Failure mode of Lương Sơn - Phan Thiết
Minimum load, dry season
Node voltage
(kV) Difference (%)
54310 Hòa Thắng 110 112 1.79%
54311 Lương Sơn 110 112 1.79%
54312 Phan Rí 110 114 3.51%
54313 Tuy Phong WPP 110 115 4.35%
54314 CN Vĩnh Hảo 110 115 4.35%
54315 Tân Thành 110 113 2.65%
54316 TĐ Bắc Bình 110 114 3.51%
54318 Rẽ Lương Sơn 110 112 1.79%
54319 TC110kV Hàm
Tân 2 110 114 3.51%
54321 Hàm Thuận 110 114 3.51%
54322 Phan Thiết 2 110 114 3.51%
54323 TĐ Đại Ninh 110 114 3.51%
59301 Xuân Trường 110 114 3.51%
60301 Xuyên Mộc 110 113 2.65%
60302 Bà Rịa 110 113 2.65%
54324 Hòa Thắng WPP 110 115 4.35%
54225 Phú Lạc WPP 110 115 4.35%
122
Appendix Error! No text of specified style in document..213 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV Tháp Chàm – ĐG Phước Hữu)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with 340 MW wind power, failure mode of Tháp Chàm - ĐG Phước Hữu
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
92+60 j 44%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
125+86 j
40%
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63
34+23 j 65%
4 TBA220/110kV
TĐ Đại Ninh 220 2x63 126
39-11 j 32%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 27-6 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 92+54 j 93%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 52+40 j 57%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -33+7 j 29%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 53-1 j 46%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -7+8 j 9%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 3+12 j 13%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -53-5 j 55%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 23-4 j 20%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15
-111-14 j
115% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29
-111-77 j
46%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33
-60+28 j
68%
123
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25
-23+17 j
29%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13
-98+20 j
87%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 8-12 j 13%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -12+9 j 15%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -25+6 j 26%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 -3+12 j 13%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 49-2 j 50%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -37+7 j 39%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41
-19+13 j
24%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 57+4 j 29%
27 Hòa Thắng WPP
- Hòa Thắng 110 AC300 690 15
118+10 j
90%
28 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 124-8 j 128% Overload
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 6-33 j 17%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+20 j 46%
31 Phan Rí - Tuy
Phong 110 2xAC185 1020 16
-179+25
j 93%
32 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 64-16 j 68%
33 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 -14+15
j 21%
34 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 -39+8 j 41%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 -49+4 j 51%
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 #N/A #N/A
124
Appendix Error! No text of specified style in document..224 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node Voltage (kV)
Failure mode of Phước Hữu - Tháp Chàm
Maximum load, rainy season
Node voltage (kV) Difference (%)
53201 TĐ Đa Nhim 220 231 4.76%
54201 TĐ Hàm Thuận 220 231 4.76%
54202 Phan Thiết 2 220 225 2.22%
54204 Hàm Tân 2 220 224 1.79%
54205 TĐ Đại Ninh 220 231 4.76%
54206 TĐ Đa My 220 231 4.76%
59201 Long Bình 220 225 2.22%
60201 Bà Rịa 220 225 2.22%
53302 Ninh Phước 110 114 3.51%
53303 Tháp Chàm 110 112 1.79%
53304 TC110kV TĐ Đa Nhim 110 113 2.65%
53305 Ninh Sơn 110 112 1.79%
53306 TC110kV Tháp Chàm 110 112 1.79%
53307 Phước Hữu WPP 110 114 3.51%
54301 KCN Sơn Mỹ 110 108 -1.85%
54302 Đức Linh 110 108 -1.85%
54303 Tánh Linh 110 108 -1.85%
54304 Ma Lâm 110 109 -0.92%
54305 Hàm Tân 110 106 -3.77%
54306 Thuận Nam 110 104 -5.77%
54307 Hàm Kiệm 110 105 -4.76%
54308 Phan Thiết 110 109 -0.92%
54309 Mũi Né 110 109 -0.92%
54310 Hòa Thắng 110 109 -0.92%
125
54311 Lương Sơn 110 109 -0.92%
54312 Phan Rí 110 112 1.79%
54313 Tuy Phong WPP 110 113 2.65%
54314 CN Vĩnh Hảo 110 113 2.65%
54315 Tân Thành 110 105 -4.76%
54316 TĐ Bắc Bình 110 115 4.35%
54318 Rẽ Lương Sơn 110 109 -0.92%
54319 TC110kV Hàm Tân 2 110 109 -0.92%
54321 Hàm Thuận 110 111 0.90%
54322 Phan Thiết 2 110 109 -0.92%
54323 TĐ Đại Ninh 110 114 3.51%
59301 Xuân Trường 110 109 -0.92%
60301 Xuyên Mộc 110 105 -4.76%
60302 Bà Rịa 110 107 -2.80%
54324 Hòa Thắng WPP 110 111 0.90%
54225 Phú Lạc WPP 110 114 3.51%
126
Appendix 3.15 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ double circuit of 110 kV Phan Rí – ĐG Tuy Phong)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with 340 MW wind power, failure mode of Phan Rí - ĐG Tuy Phong
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
96+57 j 45%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
145+79 j
44%
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63
36+21 j 66%
4 TBA220/110kV
TĐ Đại Ninh 220 2x63 126
6-6 j 7%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 27-6 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 96+51 j 94%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 54+38 j 57%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -31+5 j 27%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 52+0 j 45%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -6+7 j 8%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 4+12 j 13%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -52-6 j 54%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 21-3 j 18%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15
-109-15 j
113% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29
-127-69 j
50%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33
-45+21 j
51%
17 Phan Thiết 2 - Mũi 110 AC185 510 25 -17+15 23%
127
Né j
18 Mũi Né - Hòa
Thắng 110 AC240 605 13
-86+16 j
76%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -5-7 j 7%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -11+8 j 14%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -23+5 j 24%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 -2+11 j 12%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 49-1 j 50%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -36+6 j 38%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41
-18+12 j
22%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 44+9 j 23%
27 Hòa Thắng WPP
- Hòa Thắng 110 AC300 690 15 118+8 j 90%
28 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 93-3 j 96%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 -26-28 j 20%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+20 j 46%
31 Phan Rí - Tuy
Phong 110 AC185 510 16
-115+15
j 119% Overload
32 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 -1-3 j 3%
33 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 50+1 j 51%
34 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 25-7 j 27%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 15-10 j 19%
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 -64+9 j 67%
128
Appendix Error! No text of specified style in document..16 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node
Failure mode of Phan Rí - ĐG Tuy Phong
Maximum load, rainy season
Node voltage (kV) Difference (%)
53201 TĐ Đa Nhim 231 4.76%
54201 TĐ Hàm Thuận 231 4.76%
54202 Phan Thiết 2 226 2.65%
54204 Hàm Tân 2 224 1.79%
54205 TĐ Đại Ninh 231 4.76%
54206 TĐ Đa My 231 4.76%
59201 Long Bình 225 2.22%
60201 Bà Rịa 225 2.22%
53302 Ninh Phước 113 2.65%
53303 Tháp Chàm 112 1.79%
53304 TC110kV TĐ Đa Nhim 112 1.79%
53305 Ninh Sơn 112 1.79%
53306 TC110kV Tháp Chàm 112 1.79%
53307 Phước Hữu WPP 113 2.65%
54301 KCN Sơn Mỹ 108 -1.85%
54302 Đức Linh 108 -1.85%
54303 Tánh Linh 109 -0.92%
54304 Ma Lâm 109 -0.92%
54305 Hàm Tân 106 -3.77%
54306 Thuận Nam 104 -5.77%
54307 Hàm Kiệm 106 -3.77%
54308 Phan Thiết 109 -0.92%
54309 Mũi Né 109 -0.92%
54310 Hòa Thắng 110 0.00%
54311 Lương Sơn 109 -0.92%
129
Node number Node
Failure mode of Phan Rí - ĐG Tuy Phong
Maximum load, rainy season
Node voltage (kV) Difference (%)
54312 Phan Rí 112 1.79%
54313 Tuy Phong WPP 114 3.51%
54314 CN Vĩnh Hảo 113 2.65%
54315 Tân Thành 106 -3.77%
54316 TĐ Bắc Bình 115 4.35%
54318 Rẽ Lương Sơn 109 -0.92%
54319 TC110kV Hàm Tân 2 109 -0.92%
54321 Hàm Thuận 111 0.90%
54322 Phan Thiết 2 110 0.00%
54323 TĐ Đại Ninh 115 4.35%
59301 Xuân Trường 109 -0.92%
60301 Xuyên Mộc 105 -4.76%
60302 Bà Rịa 107 -2.80%
54324 Hòa Thắng WPP 112 1.79%
54225 Phú Lạc WPP 114 3.51%
130
Appendix Error! No text of specified style in document..17 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV Phan Rí – Rẽ Lương Sơn)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with 340 MW wind power, failure mode of Phan Rí - Rẽ Lương Sơn
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
109+54 j
49%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
204+76 j
58%
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63
44+21 j 77%
4 TBA220/110kV
TĐ Đại Ninh 220 2x63 126
72-6 j 57%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 27-5 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2
109+47 j
103% Overload
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 62+35 j 62%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -23+3 j 20%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 49+1 j 43%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -2+6 j 5%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 8+10 j 13%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -47-8 j 49%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 17-2 j 15%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15
-100-18 j
105% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29
-179-59 j
65%
16 Phan Thiết - Rẽ 110 AC185 510 33 3+11 j 12%
131
Lương Sơn
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 3+11 j 12%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13 -45+9 j 40%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -46-4 j 40%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -4+6 j 7%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -17+3 j 18%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 4+9 j 10%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 44+1 j 45%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -32+4 j 33%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -15+9 j 18%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 3+12 j 6%
27 Hòa Thắng WPP
- Hòa Thắng 110 AC300 690 15
118+11 j
90%
28 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 #N/A #N/A
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 40-28 j 25%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+20 j 46%
31 Phan Rí - Tuy
Phong 110 2xAC185 1020 16
-88+12 j
46%
32 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 -29+0 j 30%
33 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 79-3 j 81%
34 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 54-12 j 57%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 43-17 j 48%
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9
-91+17 j
95%
132
Appendix Error! No text of specified style in document..18 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node
Failure mode of Phan Rí - Rẽ Lương Sơn
Maximum load, rainy season
Node voltage
(kV) Difference (%)
53201 TĐ Đa Nhim 231 4.76%
54201 TĐ Hàm Thuận 231 4.76%
54202 Phan Thiết 2 225 2.22%
54204 Hàm Tân 2 224 1.79%
54205 TĐ Đại Ninh 231 4.76%
54206 TĐ Đa My 231 4.76%
59201 Long Bình 225 2.22%
60201 Bà Rịa 225 2.22%
53302 Ninh Phước 113 2.65%
53303 Tháp Chàm 112 1.79%
53304 TC110kV TĐ Đa
Nhim 112 1.79%
53305 Ninh Sơn 111 0.90%
53306 TC110kV Tháp
Chàm 112 1.79%
53307 Phước Hữu WPP 113 2.65%
54301 KCN Sơn Mỹ 109 -0.92%
54302 Đức Linh 108 -1.85%
54303 Tánh Linh 109 -0.92%
54304 Ma Lâm 110 0.00%
54305 Hàm Tân 106 -3.77%
54306 Thuận Nam 105 -4.76%
54307 Hàm Kiệm 106 -3.77%
54308 Phan Thiết 109 -0.92%
133
Node number Node
Failure mode of Phan Rí - Rẽ Lương Sơn
Maximum load, rainy season
Node voltage
(kV) Difference (%)
54309 Mũi Né 109 -0.92%
54310 Hòa Thắng 109 -0.92%
54311 Lương Sơn 108 -1.85%
54312 Phan Rí 114 3.51%
54313 Tuy Phong WPP 114 3.51%
54314 CN Vĩnh Hảo 113 2.65%
54315 Tân Thành 106 -3.77%
54316 TĐ Bắc Bình 115 4.35%
54318 Rẽ Lương Sơn 108 -1.85%
54319 TC110kV Hàm
Tân 2 109 -0.92%
54321 Hàm Thuận 111 0.90%
54322 Phan Thiết 2 110 0.00%
54323 TĐ Đại Ninh 115 4.35%
59301 Xuân Trường 109 -0.92%
60301 Xuyên Mộc 106 -3.77%
60302 Bà Rịa 107 -2.80%
54324 Hòa Thắng WPP 111 0.90%
54225 Phú Lạc WPP 114 3.51%
134
Appendix Error! No text of specified style in document..19 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV Lương Sơn – Phan Thiết)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with maximum wind power generation, failure mode of DZ 110kV Lương Sơn - Phan Thiết
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
26+17 j 12%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
9+18 j 5%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
2+3 j 6%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
79+1 j 63%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 18-4 j 6%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 26+16 j 26%
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 14+13 j 17%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -16+2 j 14%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 21-1 j 18%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -5+2 j 5%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 -2+4 j 5%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -22-2 j 23%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 11-2 j 10%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -46-4 j 48%
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -27-17 j 11%
135
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 #N/A #N/A
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -47+9 j 49%
18 Mũi Né - Hòa Thắng 110 AC240 605 13 -121+12
j 105% Overload
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 15-8 j 15%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -12+3 j 13%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -17+3 j 18%
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 -9+4 j 10%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 22-4 j 23%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -18+4 j 19%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -11+6 j 13%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 33-2 j 17%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 118+9 j 90%
28 Phan Rí - Rẽ Lương
Sơn 110 AC185 510 14 34-2 j 35%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 64+6 j 33%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 16-6 j 20%
31 Phan Rí - Tuy
Phong 110 2xAC185 1020 16 -116-10 j 60%
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 -2+5 j 6%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 51-1 j 52%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 42-4 j 43%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 37-6 j 39%
36 Tháp Chàm - 110 AC185 510 9 -86-4 j 89%
136
Phước Hữu WPP
Appendix Error! No text of specified style in document..230 Voltage variation at connection points and
adjacent nodes in failure mode.
Node number Node Voltage
(kV)
Failure mode of Lương Sơn- Phan Thiết
Maximum load, rainy season
Node voltage
(kV) Difference (%)
53201 TĐ Đa Nhim 220 231 4.76%
54201 TĐ Hàm Thuận 220 231 4.76%
54202 Phan Thiết 2 220 231 4.76%
54204 Hàm Tân 2 220 231 4.76%
54205 TĐ Đại Ninh 220 231 4.76%
54206 TĐ Đa My 220 231 4.76%
59201 Long Bình 220 232 5.17%
60201 Bà Rịa 220 230 4.35%
53302 Ninh Phước 110 118 6.78%
53303 Tháp Chàm 110 116 5.17%
53304 TC110kV TĐ Đa
Nhim 110 114 3.51%
53305 Ninh Sơn 110 115 4.35%
53306 TC110kV Tháp
Chàm 110 116 5.17%
53307 Phước Hữu WPP 110 117 5.98%
54301 KCN Sơn Mỹ 110 114 3.51%
54302 Đức Linh 110 114 3.51%
54303 Tánh Linh 110 114 3.51%
54304 Ma Lâm 110 115 4.35%
54305 Hàm Tân 110 114 3.51%
54306 Thuận Nam 110 113 2.65%
137
Node number Node Voltage
(kV)
Failure mode of Lương Sơn- Phan Thiết
Maximum load, rainy season
Node voltage
(kV) Difference (%)
54307 Hàm Kiệm 110 114 3.51%
54308 Phan Thiết 110 115 4.35%
54309 Mũi Né 110 116 5.17%
54310 Hòa Thắng 110 117 5.98%
54311 Lương Sơn 110 117 5.98%
54312 Phan Rí 110 118 6.78%
54313 Tuy Phong WPP 110 119 7.56%
54314 CN Vĩnh Hảo 110 119 7.56%
54315 Tân Thành 110 114 3.51%
54316 TĐ Bắc Bình 110 116 5.17%
54318 Rẽ Lương Sơn 110 117 5.98%
54319 TC110kV Hàm
Tân 2 110 114 3.51%
54321 Hàm Thuận 110 115 4.35%
54322 Phan Thiết 2 110 115 4.35%
54323 TĐ Đại Ninh 110 115 4.35%
59301 Xuân Trường 110 114 3.51%
60301 Xuyên Mộc 110 113 2.65%
60302 Bà Rịa 110 113 2.65%
54324 Hòa Thắng WPP 110 119 7.56%
54225 Phú Lạc WPP 110 119 7.56%
138
Appendix Error! No text of specified style in document..241 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV Tháp Chàm – Phước Hữu)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Minimum load regime, dry season, with maximum wind power generation, failure mode of DZ 110kV Tháp Chàm - Phước Hữu
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
18+20 j 11%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
-28+26 j 10%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
-2+5 j 9%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
105+1 j 83%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 19-4 j 6%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 18+20 j 23%
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 9+15 j 15%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -21+4 j 19%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 23-2 j 20%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -8+3 j 7%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 -4+5 j 7%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -25-0 j 26%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 14-3 j 12%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -52-1 j 54%
15 Phan Thiết - Phan 110 3xAC185 1530 29 21-29 j 12%
139
Thiết 2
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -68+17 j 72%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -41+8 j 43%
18 Mũi Né - Hòa Thắng 110 AC240 605 13 -106+10
j 92%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 0-10 j 9%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -15+5 j 16%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -20+4 j 21%
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 -12+6 j 14%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 24-6 j 25%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -20+6 j 21%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -13+7 j 15%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 18-4 j 9%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 118+12 j 90%
28 Phan Rí - Rẽ Lương
Sơn 110 AC185 510 14 90-12 j 93%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 91-2 j 47%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 16+5 j 20%
31 Phan Rí - Tuy
Phong 110 2xAC185 1020 16 -199+8 j 102% Overload
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 85-4 j 88%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 -36+4 j 37%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 -45+1 j 46%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 -49-1 j 50%
140
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 #N/A #N/A
Appendix Error! No text of specified style in document..252 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node
Failure mode of Tháp Chàm - Phước Hữu
Maximum load, rainy season
Node voltage (kV) Difference (%)
53201 TĐ Đa Nhim 231 4.76%
54201 TĐ Hàm Thuận 231 4.76%
54202 Phan Thiết 2 231 4.76%
54204 Hàm Tân 2 231 4.76%
54205 TĐ Đại Ninh 231 4.76%
54206 TĐ Đa My 231 4.76%
59201 Long Bình 232 5.17%
60201 Bà Rịa 230 4.35%
53302 Ninh Phước 122 9.84%
53303 Tháp Chàm 115 4.35%
53304 TC110kV TĐ Đa Nhim 115 4.35%
53305 Ninh Sơn 115 4.35%
53306 TC110kV Tháp Chàm 115 4.35%
53307 Phước Hữu WPP 123 10.57%
54301 KCN Sơn Mỹ 114 3.51%
54302 Đức Linh 114 3.51%
54303 Tánh Linh 114 3.51%
54304 Ma Lâm 114 3.51%
54305 Hàm Tân 113 2.65%
54306 Thuận Nam 113 2.65%
54307 Hàm Kiệm 113 2.65%
54308 Phan Thiết 114 3.51%
141
Node number Node
Failure mode of Tháp Chàm - Phước Hữu
Maximum load, rainy season
Node voltage (kV) Difference (%)
54309 Mũi Né 115 4.35%
54310 Hòa Thắng 116 5.17%
54311 Lương Sơn 116 5.17%
54312 Phan Rí 118 6.78%
54313 Tuy Phong WPP 120 8.33%
54314 CN Vĩnh Hảo 121 9.09%
54315 Tân Thành 113 2.65%
54316 TĐ Bắc Bình 116 5.17%
54318 Rẽ Lương Sơn 116 5.17%
54319 TC110kV Hàm Tân 2 114 3.51%
54321 Hàm Thuận 114 3.51%
54322 Phan Thiết 2 115 4.35%
54323 TĐ Đại Ninh 115 4.35%
59301 Xuân Trường 114 3.51%
60301 Xuyên Mộc 113 2.65%
60302 Bà Rịa 113 2.65%
54324 Hòa Thắng WPP 119 7.56%
54225 Phú Lạc WPP 120 8.33%
142
Appendix Error! No text of specified style in document..23 Capacity trend of DZ 220 kV and 110 kV
networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV Tháp Chàm – Phước Hữu WPP)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with wind power, failure mode of Tháp Chàm - Phước Hữu
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
91+60 j 44%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
118+87 j 39%
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63
33+23 j 64%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
28-10 j 24%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 27-6 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 91+54 j 92%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 51+40 j 56%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -34+7 j 30%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 53-1 j 46%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -8+8 j 10%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 2+13 j 14%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -53-5 j 55%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 23-4 j 20%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -112-13 j 116% Overload
143
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -108-77 j 46%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -59+27 j 67%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -29+19 j 36%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13
-110+24 j
98%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -12-5 j 11%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -13+9 j 16%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -25+6 j 26%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 -4+12 j 13%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 50-2 j 51%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -37+8 j 39%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -20+13 j 25%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 37+11 j 20%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 151+5 j 115% Overload
28 Hòa Thắng WPP -
Phan Rí 110 AC240 605 13 -33+4 j 29%
29 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 101-4 j 104% Overload
30 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 -5-32 j 17%
31 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+20 j 46%
32 Phan Rí - Tuy
Phong 110 2xAC185 1020 16
-179+24 j
93%
33 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 64-16 j 68%
34 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 -14+15 j 21%
35 CN Vĩnh Hảo - 110 AC185 510 28 -39+7 j 41%
144
Ninh Phước
36 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 -49+4 j 51%
37 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 #N/A #N/A
Appendix Error! No text of specified style in document..264 Voltage variation at connection points and adjacent nodes in failure mode.
Node number Node Voltage
(kV)
Failure mode of Phước Hữu - Tháp Chàm
Maximum load, rainy season
Node voltage
(kV) Difference (%)
53201 TĐ Đa Nhim 220 231 4.76%
54201 TĐ Hàm Thuận 220 231 4.76%
54202 Phan Thiết 2 220 225 2.22%
54204 Hàm Tân 2 220 224 1.79%
54205 TĐ Đại Ninh 220 231 4.76%
54206 TĐ Đa My 220 231 4.76%
59201 Long Bình 220 225 2.22%
60201 Bà Rịa 220 225 2.22%
53302 Ninh Phước 110 114 3.51%
53303 Tháp Chàm 110 112 1.79%
53304 TC110kV TĐ Đa
Nhim 110 113 2.65%
53305 Ninh Sơn 110 112 1.79%
53306 TC110kV Tháp
Chàm 110 112 1.79%
53307 Phước Hữu WPP 110 114 3.51%
54301 KCN Sơn Mỹ 110 108 -1.85%
54302 Đức Linh 110 108 -1.85%
54303 Tánh Linh 110 108 -1.85%
54304 Ma Lâm 110 109 -0.92%
54305 Hàm Tân 110 106 -3.77%
145
Node number Node Voltage
(kV)
Failure mode of Phước Hữu - Tháp Chàm
Maximum load, rainy season
Node voltage
(kV) Difference (%)
54306 Thuận Nam 110 104 -5.77%
54307 Hàm Kiệm 110 105 -4.76%
54308 Phan Thiết 110 109 -0.92%
54309 Mũi Né 110 109 -0.92%
54310 Hòa Thắng 110 109 -0.92%
54311 Lương Sơn 110 109 -0.92%
54312 Phan Rí 110 112 1.79%
54313 Tuy Phong WPP 110 113 2.65%
54314 CN Vĩnh Hảo 110 113 2.65%
54315 Tân Thành 110 105 -4.76%
54316 TĐ Bắc Bình 110 115 4.35%
54318 Rẽ Lương Sơn 110 109 -0.92%
54319 TC110kV Hàm
Tân 2 110 109 -0.92%
54321 Hàm Thuận 110 110 0.00%
54322 Phan Thiết 2 110 109 -0.92%
54323 TĐ Đại Ninh 110 114 3.51%
59301 Xuân Trường 110 109 -0.92%
60301 Xuyên Mộc 110 105 -4.76%
60302 Bà Rịa 110 107 -2.80%
54324 Hòa Thắng WPP 110 112 1.79%
54225 Phú Lạc WPP 110 113 2.65%
146
Appendix Error! No text of specified style in document..275 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ double circuit 110 kV Tuy Phong – Phan Rí)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with wind power, failure mode of Tuy Phong - Phan Rí
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
95+58 j 45%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
141+80 j 43%
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63
36+22 j 67%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
3-6 j 5%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 27-6 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 95+51 j 94%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 53+38 j 57%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -32+5 j 28%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 52-0 j 45%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -6+7 j 8%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 3+12 j 13%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -52-6 j 54%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 22-3 j 19%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -109-15 j 113% Overload
147
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -126-69 j 49%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -45+20 j 51%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -20+16 j 26%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13 -91+17 j 80%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -13-4 j 12%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -11+8 j 14%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -24+5 j 25%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 -2+11 j 12%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 49-1 j 50%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -36+7 j 38%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -19+12 j 23%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 36+12 j 20%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 132+6 j 101% Overload
28 Hòa Thắng WPP -
Phan Rí 110 AC240 605 13 -14+1 j 12%
29 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 84-2 j 86%
30 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 -30-27 j 21%
31 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+20 j 46%
32 Phan Rí - Tuy
Phong 110 AC185 510 16
-117+15 j
121% Overload
33 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 1-3 j 3%
34 Phú Lạc WPP - CN Vĩnh Hảo
110 AC185 510 8 48+2 j 49%
35 CN Vĩnh Hảo - 110 AC185 510 28 23-7 j 25%
148
Ninh Phước
36 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 13-9 j 16%
37 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 -62+8 j 64%
Appendix Error! No text of specified style in document..28 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node
Failure mode of Phan Rí - ĐG Tuy Phong
Maximum load, rainy season
Node voltage
(kV) Difference (%)
53201 TĐ Đa Nhim 231 4.76%
54201 TĐ Hàm Thuận 231 4.76%
54202 Phan Thiết 2 226 2.65%
54204 Hàm Tân 2 224 1.79%
54205 TĐ Đại Ninh 231 4.76%
54206 TĐ Đa My 231 4.76%
59201 Long Bình 225 2.22%
60201 Bà Rịa 225 2.22%
53302 Ninh Phước 113 2.65%
53303 Tháp Chàm 112 1.79%
53304 TC110kV TĐ Đa
Nhim 112 1.79%
53305 Ninh Sơn 112 1.79%
53306 TC110kV Tháp
Chàm 112 1.79%
53307 Phước Hữu WPP 113 2.65%
54301 KCN Sơn Mỹ 108 -1.85%
54302 Đức Linh 108 -1.85%
54303 Tánh Linh 109 -0.92%
54304 Ma Lâm 109 -0.92%
54305 Hàm Tân 106 -3.77%
149
Node number Node
Failure mode of Phan Rí - ĐG Tuy Phong
Maximum load, rainy season
Node voltage
(kV) Difference (%)
54306 Thuận Nam 104 -5.77%
54307 Hàm Kiệm 106 -3.77%
54308 Phan Thiết 109 -0.92%
54309 Mũi Né 109 -0.92%
54310 Hòa Thắng 110 0.00%
54311 Lương Sơn 109 -0.92%
54312 Phan Rí 112 1.79%
54313 Tuy Phong WPP 114 3.51%
54314 CN Vĩnh Hảo 113 2.65%
54315 Tân Thành 106 -3.77%
54316 TĐ Bắc Bình 115 4.35%
54318 Rẽ Lương Sơn 109 -0.92%
54319 TC110kV Hàm
Tân 2 109 -0.92%
54321 Hàm Thuận 111 0.90%
54322 Phan Thiết 2 110 0.00%
54323 TĐ Đại Ninh 115 4.35%
59301 Xuân Trường 109 -0.92%
60301 Xuyên Mộc 105 -4.76%
60302 Bà Rịa 107 -2.80%
54324 Hòa Thắng WPP 112 1.79%
54225 Phú Lạc WPP 114 3.51%
150
Appendix Error! No text of specified style in document..27 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV Phan Rí – Lương Sơn)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with wind power, failure mode of Phan Rí - Lương Sơn
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
100+58 j 46%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
159+84 j 48%
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63
38+22 j 70%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
26-5 j 21%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 27-6 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 100+51 j 97%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 56+38 j 59%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -29+5 j 26%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 51-0 j 44%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -5+7 j 7%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 5+11 j 12%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -50-6 j 52%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 20-3 j 18%
151
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -106-15 j 110% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -147-69 j 56%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -18+18 j 26%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -19+18 j 27%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13 -91+22 j 81%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -67+2 j 58%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -9+8 j 12%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -22+5 j 23%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 0+11 j 11%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 47-1 j 48%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -35+6 j 37%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -17+11 j 21%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 -18+18 j 13%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 190+7 j 145% Overload
28 Hòa Thắng WPP -
Phan Rí 110 AC240 605 13 -71+1 j 62%
29 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 #N/A #N/A
30 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 -6-27 j 14%
31 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+19 j 45%
32 Phan Rí - Tuy
Phong 110 2xAC185 1020 16 -114+9 j 59%
33 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 -3-2 j 4%
34 Phú Lạc WPP - 110 AC185 510 8 52+1 j 54%
152
CN Vĩnh Hảo
35 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 28-8 j 30%
36 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 17-11 j 21%
37 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 -66+10 j 69%
Appendix Error! No text of specified style in document..28 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node
Failure mode of Phan Rí - Rẽ Lương Sơn
Maximum load, rainy season
Node voltage (kV) Difference (%)
53201 TĐ Đa Nhim 231 4.76%
54201 TĐ Hàm Thuận 231 4.76%
54202 Phan Thiết 2 225 2.22%
54204 Hàm Tân 2 224 1.79%
54205 TĐ Đại Ninh 231 4.76%
54206 TĐ Đa My 231 4.76%
59201 Long Bình 225 2.22%
60201 Bà Rịa 225 2.22%
53302 Ninh Phước 113 2.65%
53303 Tháp Chàm 112 1.79%
53304 TC110kV TĐ Đa Nhim 112 1.79%
53305 Ninh Sơn 112 1.79%
53306 TC110kV Tháp Chàm 112 1.79%
53307 Phước Hữu WPP 113 2.65%
54301 KCN Sơn Mỹ 108 -1.85%
54302 Đức Linh 108 -1.85%
54303 Tánh Linh 109 -0.92%
54304 Ma Lâm 109 -0.92%
54305 Hàm Tân 106 -3.77%
54306 Thuận Nam 104 -5.77%
153
Node number Node
Failure mode of Phan Rí - Rẽ Lương Sơn
Maximum load, rainy season
Node voltage (kV) Difference (%)
54307 Hàm Kiệm 106 -3.77%
54308 Phan Thiết 109 -0.92%
54309 Mũi Né 109 -0.92%
54310 Hòa Thắng 109 -0.92%
54311 Lương Sơn 108 -1.85%
54312 Phan Rí 113 2.65%
54313 Tuy Phong WPP 114 3.51%
54314 CN Vĩnh Hảo 113 2.65%
54315 Tân Thành 105 -4.76%
54316 TĐ Bắc Bình 116 5.17%
54318 Rẽ Lương Sơn 108 -1.85%
54319 TC110kV Hàm Tân 2 109 -0.92%
54321 Hàm Thuận 111 0.90%
54322 Phan Thiết 2 109 -0.92%
54323 TĐ Đại Ninh 115 4.35%
59301 Xuân Trường 109 -0.92%
60301 Xuyên Mộc 105 -4.76%
60302 Bà Rịa 107 -2.80%
54324 Hòa Thắng WPP 112 1.79%
54225 Phú Lạc WPP 114 3.51%
154
Appendix Error! No text of specified style in document..29 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV Hòa Thắng WPP – Hòa Thắng)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with wind power, failure mode of Hòa Thắng WPP - Hòa Thắng
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
104+60 j 48%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
174+95 j 53%
3 TBA 220/110kV TĐ Hàm Thuận
220 63 63
40+23 j 73%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
38-9 j 31%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 27-6 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 104+53 j 101% Overload
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 59+39 j 61%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -27+6 j 24%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 50-0 j 43%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -4+8 j 8%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 6+12 j 14%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -49-6 j 51%
155
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 19-4 j 17%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -104-14 j 108% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -142-79 j 56%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -46+30 j 57%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 5+18 j 19%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13 -38+22 j 38%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 64-12 j 56%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -7+9 j 12%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -20+6 j 21%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 2+12 j 13%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 46-1 j 47%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -33+6 j 35%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -16+12 j 21%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 112+5 j 58%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 #N/A #N/A
28 Hòa Thắng WPP -
Phan Rí 110 AC240 605 13 118-6 j 103% Overload
29 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 170+1 j 175% Overload
30 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 6-31 j 16%
31 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+20 j 46%
32 Phan Rí - Tuy
Phong 110 2xAC185 1020 16 -108+3 j 56%
33 Phú Lạc WPP - 110 AC185 510 9 -10+2 j 10%
156
Tuy Phong
34 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 59-2 j 61%
35 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 34-11 j 37%
36 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 24-14 j 29%
37 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 -72+12 j 75%
Appendix Error! No text of specified style in document..30 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node
Failure mode of Hòa Thắng - Hòa Thắng WPP
Maximum load, rainy season
Node voltage (kV) Difference (%)
53201 TĐ Đa Nhim 231 4.76%
54201 TĐ Hàm Thuận 231 4.76%
54202 Phan Thiết 2 225 2.22%
54204 Hàm Tân 2 224 1.79%
54205 TĐ Đại Ninh 231 4.76%
54206 TĐ Đa My 231 4.76%
59201 Long Bình 225 2.22%
60201 Bà Rịa 225 2.22%
53302 Ninh Phước 113 2.65%
53303 Tháp Chàm 112 1.79%
53304 TC110kV TĐ Đa Nhim 112 1.79%
53305 Ninh Sơn 112 1.79%
53306 TC110kV Tháp Chàm 112 1.79%
53307 Phước Hữu WPP 113 2.65%
54301 KCN Sơn Mỹ 108 -1.85%
54302 Đức Linh 108 -1.85%
54303 Tánh Linh 108 -1.85%
54304 Ma Lâm 109 -0.92%
157
Node number Node
Failure mode of Hòa Thắng - Hòa Thắng WPP
Maximum load, rainy season
Node voltage (kV) Difference (%)
54305 Hàm Tân 106 -3.77%
54306 Thuận Nam 104 -5.77%
54307 Hàm Kiệm 105 -4.76%
54308 Phan Thiết 108 -1.85%
54309 Mũi Né 107 -2.80%
54310 Hòa Thắng 106 -3.77%
54311 Lương Sơn 107 -2.80%
54312 Phan Rí 112 1.79%
54313 Tuy Phong WPP 113 2.65%
54314 CN Vĩnh Hảo 113 2.65%
54315 Tân Thành 105 -4.76%
54316 TĐ Bắc Bình 115 4.35%
54318 Rẽ Lương Sơn 107 -2.80%
54319 TC110kV Hàm Tân 2 109 -0.92%
54321 Hàm Thuận 110 0.00%
54322 Phan Thiết 2 109 -0.92%
54323 TĐ Đại Ninh 115 4.35%
59301 Xuân Trường 109 -0.92%
60301 Xuyên Mộc 105 -4.76%
60302 Bà Rịa 107 -2.80%
54324 Hòa Thắng WPP 114 3.51%
54225 Phú Lạc WPP 113 2.65%
158
Appendix Error! No text of specified style in document..291 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV ĐG Hòa Thắng – Phan Rí)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Maximum load regime, rainy season, with wind power, failure mode of Hòa Thắng WPP - Phan Rí
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
96+57 j 45%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
142+79 j 43%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
36+21 j 66%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
10-5 j 9%
5 TĐ Hàm Thuận -
TĐ Đa Mi 220 AC400 825 400 27-6 j 9%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 95+51 j 94%
7 KCN Sơn Mỹ -
Hàm Tân 110 AC240 605 10 53+38 j 57%
8 KCN Sơn Mỹ -
Phan Thiết 110 AC240 605 64 -31+5 j 27%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 52+0 j 45%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -6+7 j 8%
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 3+12 j 13%
159
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -52-6 j 54%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 22-3 j 19%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -109-15 j 113% Overload
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -125-69 j 49%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -47+20 j 53%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -18+15 j 24%
18 Mũi Né - Hòa
Thắng 110 AC240 605 13 -87+15 j 77%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -3-6 j 6%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -11+8 j 14%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -23+5 j 24%
22 TĐ Hàm Thuận -
Ma Lâm 110 AC185 510 45 -2+11 j 12%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 49-1 j 50%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -36+6 j 38%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -19+12 j 23%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 45+10 j 24%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 118+7 j 90%
28 Hòa Thắng WPP -
Phan Rí 110 AC240 605 13 #N/A #N/A
29 Phan Rí - Rẽ Lương Sơn
110 AC185 510 14 97-1 j 100%
30 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 -22-24 j 17%
31 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 33+18 j 44%
32 Phan Rí - Tuy 110 2xAC185 1020 16 -123+10 64%
160
Phong j
33 Phú Lạc WPP -
Tuy Phong 110 AC185 510 9 6-3 j 7%
34 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 43+2 j 44%
35 CN Vĩnh Hảo - Ninh Phước
110 AC185 510 28 18-6 j 20%
36 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 8-8 j 12%
37 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 -57+7 j 59%
Appendix Error! No text of specified style in document..302 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node
Failure mode of Hòa Thắng WPP - Phan Rí
Maximum load, rainy season
Node voltage (kV) Difference (%)
53201 TĐ Đa Nhim 231 4.76%
54201 TĐ Hàm Thuận 231 4.76%
54202 Phan Thiết 2 226 2.65%
54204 Hàm Tân 2 225 2.22%
54205 TĐ Đại Ninh 231 4.76%
54206 TĐ Đa My 231 4.76%
59201 Long Bình 225 2.22%
60201 Bà Rịa 225 2.22%
53302 Ninh Phước 113 2.65%
53303 Tháp Chàm 112 1.79%
53304 TC110kV TĐ Đa Nhim 112 1.79%
53305 Ninh Sơn 112 1.79%
53306 TC110kV Tháp Chàm 112 1.79%
53307 Phước Hữu WPP 113 2.65%
54301 KCN Sơn Mỹ 108 -1.85%
54302 Đức Linh 108 -1.85%
54303 Tánh Linh 109 -0.92%
161
Node number Node
Failure mode of Hòa Thắng WPP - Phan Rí
Maximum load, rainy season
Node voltage (kV) Difference (%)
54304 Ma Lâm 109 -0.92%
54305 Hàm Tân 106 -3.77%
54306 Thuận Nam 104 -5.77%
54307 Hàm Kiệm 106 -3.77%
54308 Phan Thiết 109 -0.92%
54309 Mũi Né 109 -0.92%
54310 Hòa Thắng 110 0.00%
54311 Lương Sơn 109 -0.92%
54312 Phan Rí 113 2.65%
54313 Tuy Phong WPP 114 3.51%
54314 CN Vĩnh Hảo 113 2.65%
54315 Tân Thành 106 -3.77%
54316 TĐ Bắc Bình 116 5.17%
54318 Rẽ Lương Sơn 109 -0.92%
54319 TC110kV Hàm Tân 2 109 -0.92%
54321 Hàm Thuận 111 0.90%
54322 Phan Thiết 2 110 0.00%
54323 TĐ Đại Ninh 115 4.35%
59301 Xuân Trường 109 -0.92%
60301 Xuyên Mộc 105 -4.76%
60302 Bà Rịa 107 -2.80%
54324 Hòa Thắng WPP 112 1.79%
54225 Phú Lạc WPP 114 3.51%
162
Appendix Error! No text of specified style in document..313 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV Lương Sơn – Phan Thiết)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Minimum load regime, dry season, with maximum wind power generation, failure mode of DZ 110kV Lương Sơn - Phan Thiết
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
27+17 j 13%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
11+19 j 6%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
2+3 j 6%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
81+1 j 64%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 18-4 j 6%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 27+16 j 27%
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 14+13 j 17%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -16+2 j 14%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 21-1 j 18%
10 Hàm Tân - Tân
Thành 110 AC240 605 30 -5+2 j 5%
11 Hàm Tân - Thuận 110 AC185 510 34 -2+4 j 5%
163
Nam
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -22-2 j 23%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 11-2 j 10%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -46-4 j 48%
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 -29-18 j 12%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 #N/A #N/A
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -45+9 j 47%
18 Mũi Né - Hòa Thắng 110 AC240 605 13 -117+13
j 102% Overload
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 21-7 j 19%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -12+3 j 13%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -16+3 j 17%
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 -8+4 j 9%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 22-4 j 23%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -18+4 j 19%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -11+5 j 12%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 39-1 j 20%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 108+6 j 82%
28 Phan Rí - Rẽ Lương
Sơn 110 AC185 510 14 39-1 j 40%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 66+9 j 34%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 16-8 j 21%
31 Phan Rí - Tuy
Phong 110 2xAC185 1020 16 -114-7 j 59%
164
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 -3+4 j 5%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 52-0 j 54%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 43-4 j 44%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 39-5 j 40%
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 -87-4 j 90%
Appendix Error! No text of specified style in document..324 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node Voltage
(kV)
Failure mode of Lương Sơn- Phan Thiết
Phụ tải cực đại, mùa mưa
Điện áp nút (kV)
So lệch (%)
53201 TĐ Đa Nhim 220 231 4.76%
54201 TĐ Hàm Thuận 220 231 4.76%
54202 Phan Thiết 2 220 231 4.76%
54204 Hàm Tân 2 220 231 4.76%
54205 TĐ Đại Ninh 220 231 4.76%
54206 TĐ Đa My 220 231 4.76%
59201 Long Bình 220 232 5.17%
60201 Bà Rịa 220 230 4.35%
53302 Ninh Phước 110 118 6.78%
53303 Tháp Chàm 110 116 5.17%
53304 TC110kV TĐ Đa
Nhim 110 114 3.51%
53305 Ninh Sơn 110 115 4.35%
53306 TC110kV Tháp
Chàm 110 116 5.17%
53307 Phước Hữu WPP 110 118 6.78%
165
Node number Node Voltage
(kV)
Failure mode of Lương Sơn- Phan Thiết
Phụ tải cực đại, mùa mưa
Điện áp nút (kV)
So lệch (%)
54301 KCN Sơn Mỹ 110 114 3.51%
54302 Đức Linh 110 114 3.51%
54303 Tánh Linh 110 114 3.51%
54304 Ma Lâm 110 115 4.35%
54305 Hàm Tân 110 114 3.51%
54306 Thuận Nam 110 113 2.65%
54307 Hàm Kiệm 110 114 3.51%
54308 Phan Thiết 110 115 4.35%
54309 Mũi Né 110 116 5.17%
54310 Hòa Thắng 110 117 5.98%
54311 Lương Sơn 110 117 5.98%
54312 Phan Rí 110 118 6.78%
54313 Tuy Phong WPP 110 120 8.33%
54314 CN Vĩnh Hảo 110 119 7.56%
54315 Tân Thành 110 113 2.65%
54316 TĐ Bắc Bình 110 116 5.17%
54318 Rẽ Lương Sơn 110 117 5.98%
54319 TC110kV Hàm
Tân 2 110 114 3.51%
54321 Hàm Thuận 110 115 4.35%
54322 Phan Thiết 2 110 115 4.35%
54323 TĐ Đại Ninh 110 116 5.17%
59301 Xuân Trường 110 114 3.51%
60301 Xuyên Mộc 110 113 2.65%
60302 Bà Rịa 110 113 2.65%
54324 Hòa Thắng WPP 110 119 7.56%
54225 Phú Lạc WPP 110 120 8.33%
166
Appendix Error! No text of specified style in document..335 Capacity trend of DZ 220 kV and 110 kV networks of Binh Thuan province in 2015 (failure mode of DZ 110 kV Tháp Chàm – Phước Hữu)
No. Lines Voltage
(kV)
Diameter/ Capacity
MBA (MVA)
Admissible operation
flow (A)/MVA
Length (km)
Power Flow (P + Q j) (MVA)
Current carrying capacity
(%)
Remark
Minimum load regime, dry season, with maximum wind power generation, failure mode of DZ 110kV Tháp Chàm - Phước Hữu
1 TBA 220/110kV
Hàm Tân 2 220 1x250 250
17+21 j 11%
2 TBA 220/110kV
Phan Thiết 2 220 125+250 375
-31+28 j 11%
3 TBA 220/110kV TĐ
Hàm Thuận 220 63 63
-3+5 j 9%
4 TBA220/110kV TĐ
Đại Ninh 220 2x63 126
101+1 j 80%
5 TĐ Hàm Thuận - TĐ
Đa Mi 220 AC400 825 400 19-4 j 6%
6 Hàm Tân 2 - KCN
Sơn Mỹ 110 AC240 605 2 17+20 j 23%
7 KCN Sơn Mỹ - Hàm
Tân 110 AC240 605 10 8+16 j 16%
8 KCN Sơn Mỹ - Phan
Thiết 110 AC240 605 64 -21+4 j 19%
9 KCN Sơn Mỹ -
Xuyên Mộc 110 AC240 605 36 23-2 j 20%
10 Hàm Tân - Tân 110 AC240 605 30 -8+3 j 7%
167
Thành
11 Hàm Tân - Thuận
Nam 110 AC185 510 34 -5+6 j 8%
12 Thuận Nam - Hàm
Kiệm 110 AC185 510 14 -25-0 j 26%
13 Hàm Kiệm - Tân
Thành 110 AC240 605 22 14-3 j 12%
14 Hàm Kiệm - Phan
Thiết 110 AC185 510 15 -52-1 j 54%
15 Phan Thiết - Phan
Thiết 2 110 3xAC185 1530 29 23-30 j 13%
16 Phan Thiết - Rẽ
Lương Sơn 110 AC185 510 33 -67+16 j 71%
17 Phan Thiết 2 - Mũi
Né 110 AC185 510 25 -44+10 j 46%
18 Mũi Né - Hòa Thắng 110 AC240 605 13 -110+13
j 96%
19 Lương Sơn - Hòa
Thắng 110 AC240 605 13 -9-4 j 9%
20 TĐ Hàm Thuận -
Phan Thiết 2 110 AC185 510 58 -15+5 j 16%
21 Ma Lâm - Phan
Thiết 2 110 AC185 510 13 -20+4 j 21%
22 TĐ Hàm Thuận - Ma
Lâm 110 AC185 510 45 -12+6 j 14%
23 TĐ Hàm Thuận -
Tánh Linh 110 AC185 510 33 24-6 j 25%
24 Đức Linh - Tánh
Linh 110 AC185 510 20 -20+6 j 21%
25 Đức Linh - Xuân
Lộc 110 AC185 510 41 -13+8 j 16%
26 Rẽ Lương Sơn -
Lương Sơn 110 2xAC185 1020 0,5 9+2 j 5%
27 Hòa Thắng WPP -
Hòa Thắng 110 AC300 690 15 132+5 j 100%
28 Phan Rí - Rẽ Lương
Sơn 110 AC185 510 14 81-6 j 84%
29 Phan Rí - TĐ Đại
Ninh 110 2xAC185 1020 43 87+1 j 45%
30 TĐ Bắc Bình - TĐ
Đại Ninh 110 AC150 445 5 16+1 j 19%
168
31 Phan Rí - Tuy
Phong 110 2xAC185 1020 16
-199+10 j
103% Overload
32 Phú Lạc WPP - Tuy
Phong 110 AC185 510 9 85-4 j 88%
33 Phú Lạc WPP - CN
Vĩnh Hảo 110 AC185 510 8 -36+4 j 37%
34 CN Vĩnh Hảo - Ninh
Phước 110 AC185 510 28 -45+1 j 46%
35 Ninh Phước -
Phước Hữu WPP 110 AC185 510 6 -49-1 j 50%
36 Tháp Chàm -
Phước Hữu WPP 110 AC185 510 9 #N/A #N/A
Appendix Error! No text of specified style in document..36 Voltage variation at connection points and adjacent nodes in failure mode
Node number Node
Failure mode of Tháp Chàm - Phước Hữu
Maximum load, rainy season
Node voltage (kV) Difference (%)
53201 TĐ Đa Nhim 231 4.76%
54201 TĐ Hàm Thuận 231 4.76%
54202 Phan Thiết 2 231 4.76%
54204 Hàm Tân 2 231 4.76%
54205 TĐ Đại Ninh 231 4.76%
54206 TĐ Đa My 231 4.76%
59201 Long Bình 232 5.17%
60201 Bà Rịa 230 4.35%
53302 Ninh Phước 123 10.57%
53303 Tháp Chàm 115 4.35%
53304 TC110kV TĐ Đa Nhim 115 4.35%
53305 Ninh Sơn 115 4.35%
53306 TC110kV Tháp Chàm 115 4.35%
53307 Phước Hữu WPP 123 10.57%
169
Node number Node
Failure mode of Tháp Chàm - Phước Hữu
Maximum load, rainy season
Node voltage (kV) Difference (%)
54301 KCN Sơn Mỹ 114 3.51%
54302 Đức Linh 114 3.51%
54303 Tánh Linh 114 3.51%
54304 Ma Lâm 114 3.51%
54305 Hàm Tân 113 2.65%
54306 Thuận Nam 113 2.65%
54307 Hàm Kiệm 113 2.65%
54308 Phan Thiết 114 3.51%
54309 Mũi Né 115 4.35%
54310 Hòa Thắng 116 5.17%
54311 Lương Sơn 116 5.17%
54312 Phan Rí 118 6.78%
54313 Tuy Phong WPP 120 8.33%
54314 CN Vĩnh Hảo 121 9.09%
54315 Tân Thành 113 2.65%
54316 TĐ Bắc Bình 116 5.17%
54318 Rẽ Lương Sơn 116 5.17%
54319 TC110kV Hàm Tân 2 114 3.51%
54321 Hàm Thuận 114 3.51%
54322 Phan Thiết 2 114 3.51%
54323 TĐ Đại Ninh 115 4.35%
59301 Xuân Trường 114 3.51%
60301 Xuyên Mộc 113 2.65%
60302 Bà Rịa 113 2.65%
54324 Hòa Thắng WPP 118 6.78%
54225 Phú Lạc WPP 121 9.09%