Upload
godfrey-harmon
View
215
Download
0
Embed Size (px)
Citation preview
Georgia’s Off-shore Wind Opportunities
Presented by Bill Bulpitt and Rita Kilpatrickfor Tybee Island City Council
March 27, 2008
Georgia Wind Working Group
The Georgia Wind Working Group formed in 2005 through a partnership involving:- Southern Alliance for Clean Energy- Georgia Tech’s Strategic Energy Institute- Georgia Environmental Facilities Authority
The Group consists of people representing utility companies, wind developers, government agencies, universities, and non-profit organizations.
GEORGIA
WIND WORKING GROUP
Georgia Offshore Wind Maps
Class 3
Class 5
Class 4
Class 3
Class 4
50-M above Sea Level 90-M above Sea Level
Source: AWS Truewind, 2006
Off-Shore Wind Resourcein Georgia
Site specific data:
– 50 m high anemometer
– Online since June 1999 (nearly 7 years)
– 27 m deep water,` 60 km offshore– 6-minute data
averages
Source: Southern Winds Project
Southern Winds Off-shore Project
• By Southern Company and Georgia Tech
• Began July 1, 2005• To study viability of
wind power generation off the Georgia coast
Preliminary Findings:
• Wind resource warrants further review
• 20 year levelized cost: 50-160 MW scale:$.08-$.12/kwhr
• No “show stopper” environmental issues
• Coastal community acceptance important
Simulated View of a Wind Farm (10MW) 10.2 Miles South Southeast of
Tybee
Source: Southern Winds Project
US Projects Proposed
Prop
Atlantic Ocean
Gulf of Mexico
Cape Wind AssociatesWinergy
LIPA & FPL
W.E.S.T. LLC
Hull Municipal
Southern Company
Superior Renewable
New Jersey
Delaware
Project State MWCapewind MA 420LIPA NY 150Winergy (plum Island) NY 10Southern Company GA 10W.E.S.T. TX 150Superior Renewable TX 500Buzzards Bay MA 300New Jersey NJ 300Hull Municipal MA 15Delaware DE 600Total 2455
US Offshore Projects
Buzzards Bay
No projects installed in US yet
Benefits of Off-shore Wind
• Better wind resources• Reduced turbulence –
steadier wind• Higher wind = better
energy production• Higher capacity
factors –load matching• Minimize visual
impacts with greater distances
• Proximity to load centers
• Lower transmission constraints
• Serve high cost regions
• Uses indigenous energy
• Avoids size limits
GEORGIA
WIND WORKING GROUPCourtesy Walt Musial: NREL
Off-shore Wind Regulation Pending(beyond 3 nautical miles from shore)
• Minerals Management Service is establishing permitting rules
• Will require full environmental review for wind farms and cabling pathway
• Multiple federal and state governing authorities apply
• Environmental considerations include:
- Bird migratory pathways- Habitats – marine,
fisheries, avian- Natural reefs and other
aquatic life
GEORGIA
WIND WORKING GROUP
Next Steps for Utilities andWind Developers
• Track federal rulemaking process
• Install a meteorological tower for wind site specific resource assessment
• Plan wind farm projects where communities are supportive
• Participate in competitive process for lease site
Georgia
Wind Working Group
Photo Courtesy: NREL
The Georgia Wind Working GroupMission
Georgia
Wind Working Group
Promotes the responsible development and use of wind energy by facilitating stakeholder collaborations, assisting with resource assessments, and enhancing public understanding of the benefits and impacts of wind energy.
Georgia Wind Working Group
• Provides general public education
• Provides technical outreach and targeted stakeholder outreach
• Hosts wind workshops• Develops state
specific literature• Provides presentations
at key events
GEORGIA
WIND WORKING GROUP
The Georgia Wind Working Grouplooks forward to working with the
City of Tybee Island and others to explore wind energy opportunities.
Georgia
Wind Working Group
Photo Courtesy: Georgia Tech SEI
Additional Background on Existing Off-shore
Wind Farms
Courtesy: Georgia Tech SEI
Arklow
Project Statistics• Turbines 3.6MW x 7• Depth of piles 35-45m• Weight of piles 280tonne (5m diameter)• Weight of turbines 290tonne• Blades 50.5m, 15tonne each• Nacelle/Hub height 73.5M• Rotational speed 8.5 – 15 rpm• Distance offshore 10km• Onshore cable 5km• Voltage 38kV distribution connected• Rotor diameter 104m > soccer pitch area• 25MW serves 16,000 households (Irish)
• Sandbank 24 miles long & 2.5 wide, depths 3 -20 m• Largest commercially operating turbines installed to date• Largest consented offshore site to date
Source: McAdam
Courtesy: Georgia Tech SEI
Scroby Sands
Scroby SandsCountry: United KingdomLocation: East Anglian Coast, 3km east of Great YarmouthTotal Capacity: 60 MWNumber of Turbines: 30Distance to Shore: 2.5 kmDepth: 4-8 mCapital Costs: about 110 million EuroStatus: BuiltConstruction Date: 2003Manufacturer: VestasTotal Capacity: 2 MWTurbine-type: V80 - 80m diameter/ 60m hubheightMean Windspeed: 7.5 m/s Windfarm Developer: E.ON UK
Courtesy: Georgia Tech SEI
Horns Rev
Horns RevCountry: DenmarkLocation: West CoastTotal Capacity: 160 MWNumber of Turbines: 80Distance to Shore: 14-20 kmDepth: 6-12 mCapital Costs: 270 million EuroStatus: Operational Construction Date: 2002 Manufacturer: VestasTotal Capacity: 2 MWTurbine-type: V80 - 80m diameter / 70m hubheightMean Windspeed: 9.7 m/sAnnual Energy output: 600 GWhWindfarm Developer: Elsam http://www.hornsrev.dk/Engelsk/default_ie.htm