    Document #9C.1

    Library Board of Trustees

    November 16, 2011

    The District of Columbia Public Library

    Capital Construction Report

    November 16, 2011

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    2/14

    2

    Francis A. Gregory LibraryNew Library Contacts Progress

    Councilmember

    Steel work is complete

    Light weight concrete floor slabs complete

    Curtain wall installation 85% complete

    Interior Finishes to begin by the end of this month

    Ward 7 Yvette Alexander

    202.724.8068

    Architect Wiencek/Adjaye

    Scott Knudson

    301.948.6220

    Project

    ManagerLisa Deanes

    202.727.5181

    Contractor Hess Construction

    Jair Lynch

    Development

    PartnersDCPL PM

    Firm

    Mount PleasantInterior Restoration Contacts Progress

    Councilmember Jim Graham

    All zoning and legal issues have been resolved.

    Ward 1 202.724.8181

    Architect Core Architects

    Dale Stewart

    202.466.6116

    ProjectManager

    Chris Wright

    202.727.4913

    Contractor T.B.D

    DCPL Project

    Management

    Smoot

    Construction

    Design of the new Francis Gregory Library will include

    community input on planning and programming phase. Project

    is fully funded.

    Phase II of Mount Pleasant Renovation. Interior work will

    consist of total upgrade and modernization of all mechanical

    equipment as well as provide additional and functional library

    program space.

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    3/14

    3

    Northeast LibraryDesign-Build Renovations Contacts Progress

    Pre-design due diligence work includes a hazardousmaterials survey, a Phase 1 and Phase 2 Environmental

    Site Assessment and a Cost Benefit Analysis Study.

    Councilmember Tommy Wells

    Received 5 Proposals from Design-Build

    Contractors. Evaluations are underway.

    Final selections will take place with

    representatives from the community.

    Project is fully funded.

    Ward 6 202.724.8072

    Architect N/A

    ProjectManager

    Chris Wright

    202.727.4913

    Consultant

    Washington HighlandsNew Building Design Contacts Progress

    Councilmember

    Concrete Structure work complete

    Concrete work schedule to be complete in early

    April.

    3 pavilions are complete

    Curtain wall installation 95% Complete

    Interior finishes underway

    Ward 8 Marion Barry

    202.724.8045

    Architect Wiencek/Adjaye

    Scott Knudson

    301.948.6220

    Project

    Manager Lisa Deanes

    202.727.5181

    Contractor Coakley-Williams

    DCPL PM

    Firm

    Jair Lynch

    Development

    Partners

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    4/14

    4

    West End LibraryMixed Use Development Contacts Progress

    Councilmember Jack Evans

    New ground floor library will be part of mixed use

    development.

    Library designs are underway.

    Project is progressing through Planned Unit

    Development Process with DC Zoning Board.

    Ward 2 202.724.8058

    Architect Ten Arquitectos

    Erik Lang

    ProjectManager

    Kim Fuller

    202.442.6069

    Developer EastBanc

    Joe Sternlieb

    202.737.1000

    Woodridge LibraryDesign Contacts Progress

    Pre-design due diligence work includes a hazardous

    materials survey, a Phase 1 and Phase 2 Environmental

    Site Assessment, Existing Topographical Survey,

    Geotechnical Report and a Cost Benefit Analysis.

    Councilmember Harry Thomas Jr.

    Cost Benefit Analysis and Pre-Design Due

    Diligence Reports are Complete

    Design and Construction funding identified in

    Mayors Capital Budget. Design funding in FY 13.

    Ward 5 (202) 724-8028

    Architect N/A

    ProjectManager

    Chris Wright

    202.727.4913

    Consultant Hill and Argos

    Gilberto Cardenas

    202.379.4889

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    5/14

    5

    MLK Jr. LibraryBusiness and Technology Reconfiguration Contacts Progress

    Councilmember

    Space planning for Business, Science and

    Technology Complete

    Design is complete and has been approved by HPO

    MCN Build Selected as Construction Manager

    Funding for building out indentified in Mayors FY

    12 Capital Budget.

    Ward 2 Jack Evans

    202.724.8058

    Architect The Freelon Group

    Derek Jones

    919-941-9790

    Project

    ManagerKim Fuller

    202-442-6069

    Contractor MCN Build

    Joseph Kourney

    202.333.3424Improvements and upgrades to west reading room. Entire

    first floor is under the Historic Landmark Designation. The

    MLK Design Guidelines will be utilized.

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    6/14

    6

    Completed ProjectsAnacostia LibraryNew Building Construction Contacts Progress

    Councilmember

    Opened to the public April 26, 2010

    Ward 7 Yvette Alexander

    202.724.8068

    Architect Freelon Group

    Philip Freelon919.941.9790

    Project

    ManagerDedric Boyd

    202.727.1127

    ContractorForrester

    Construction

    Tom Willerton

    301.816.1700

    DCPL PM

    Firm Hill International

    Benning LibraryNew Building Design Contacts Progress

    Councilmember

    Opened to the public April 5, 2010

    Ward 7 Yvette Alexander

    202.724.8068

    ArchitectDavis, Brody,

    Bond & Aedas

    Peter Cook

    202.449.1190

    Project

    ManagerKim Fuller

    202.442.6069

    Contractor Forrester

    Jon McGee

    301.255.1750

    DCPL PM

    FirmA-1 Consulting

    New State of the Art Library on Good Hope Road SE is open.

    New State of the Art Library located at 3935 Benning Road NE

    is open.

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    7/14

    7

    Cleveland ParkNew Ceiling and Lighting Contacts Progress

    Councilmember

    Project Complete

    Ward 3 Mary Cheh

    202.724.8062

    Architect N/A

    Project

    ManagerEd Hampton

    202.442.6067

    ContractorEagle

    Construction

    DeanwoodNew Community Center and Library Contacts Progress

    Councilmember

    Opened to the public June 25, 2010

    Ward 7 Yvette Alexander

    202.724.8068

    Architect EEK

    Sean ODonnell

    Project

    Manager

    ContractorProject is a partnership with the Department of Parks and

    Recreation to co-locate a 10,000 square foot library within a

    54,000 square foot aquatic center and community center.

    Library and Community Center would share such space as

    computer lab, senior rooms, tutor rooms and community

    meeting rooms. Project location is 49th and Quarles St. NE

    Project consists of installing a new ceiling and lighting system.

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    8/14

    8

    The Library has received Federal Stimulus Money for energy

    enhancements. Projects will take place at the above locations,

    focusing on window replacements, energy efficient lighting,

    and automated building heating and cooling controls

    Energy Enhancement ProjectsVarious Locations Contacts Progress

    Capitol View, Cleveland Park,

    Shepherd Park, Lamond Riggs, Palisades, Southwest, West

    End and Woodridge

    Councilmember

    Energy Efficient Lighting Projects are

    COMPLETE

    Window and Door work is complete

    Various

    Architect T.B.D

    Project

    ManagerEd Hampton

    202.442.6067

    Contractor

    DCPL PM

    Firm

    Francis A. Gregory LibraryInterim Library Contacts Progress

    Councilmember

    Opened June 10, 2010

    Ward 7 Yvette Alexander

    202.724.8068

    Architect

    ProjectManager

    Lisa Deanes

    202.727.5181

    ContractorWilliam Scotsman

    Greg Bichell

    DCPL PM

    Firm

    Project consists of building a 4,200 square foot interim library

    to serve the community during construction; the interim will

    have 30 computers, books on CD as well as traditional

    collection material for all age sets

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    9/14

    9

    Georgetown LibraryBuilding Renovation Contacts Progress

    Councilmember

    Opened to the Public October 18, 2010

    Ward 2 Jack Evans

    202.724.8058

    Architect Martinez & Johnson

    Tom Johnson

    202.333.4480

    Project

    ManagerChris Wright

    202.272.4913

    Contractor N/A

    DCPL PM

    Firm

    Smoot

    Construction

    Mount PleasantInterim Library Contacts Progress

    Councilmember Jim Graham

    Opened to the public April 26, 2010Re-opened to the public May 15, 2010

    Ward 1 202.724.8181

    Architect Core Architects

    Dale Stewart

    202.466.6116

    ProjectManager

    Dedric Boyd

    202.727.1127

    Contractor MCN Build

    Bassem Boustany

    202.333.3424

    Renovation complete and Library open to the public.

    Project consists of building a 3,600 square foot interim library to

    serve the community during construction; the interim will have

    30 computers, books on CD as well as traditional collection

    material for all age sets

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    10/14

    10

    Northeast LibraryExterior Restoration Contacts Progress

    Councilmember Tommy Wells

    ConstructionSubstantial completion May 15, 2010

    Ward 6 202.724.8072

    Architect Bell Architects

    David Bell

    202.548.7570

    Project

    ManagerChris Wright

    202.727.4913

    ContractorMonarc

    Construction

    C. McDermott,

    703.201.1747

    Northwest OneNew Co-location Facility Contacts Progress

    Councilmember Tommy Wells

    Library Open December 7, 2009

    Open to the Public

    Ward 6

    Architect Hord Cort Plan

    Project

    ManagerReagan Assoc

    Contractor Forrester

    Project consists of Exterior Improvements to windows,

    doors, security lighting, masonry restoration, landscaping

    and signage.

    Project consists of 6,500 SQ FT Library facility as part of

    Elementary School and Recreation Center. This facility

    replaces the Sursum Corda kiosk.

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    11/14

    11

    Parklands-TurnerNew Storefront Library Contacts Progress

    Councilmember Marion Barry

    Ribbon Cutting October 5, 2009

    OPEN TO THE PUBLIC

    Ward 8 202.724.8045

    Architect Mood Nolan - DC

    Patrick Williams

    202.244.

    ProjectManager

    Dedric Boyd

    202.727.1129

    Contractor Lexx Group

    Ken Postell

    202.393.

    Petworth LibraryInterim Library Contacts Progress

    Councilmember

    Opened to public on January 11, 2010Closed February 5, 2011

    Ward 4 Muriel Bowser

    202.724.8052

    Architect N/A

    ProjectManager Lisa Deanes

    202.727.5181

    Contractor Sigal Construction

    Sarah Norman

    DCPL PM

    Firm

    Project to fit out approximately 5,000 Sq Ft of storefront space

    to replace the existing Parklands-Turner kiosk. The storefront

    library is similar in size, scope, computers, and collections to the

    Georgetown Interim and Tenley-Friendship Interim Libraries.

    Project consists of building a 4,200 square foot interim library

    to serve the community during construction; the interim will

    have 30 computers, books on CD as well as traditional

    collection material for all age sets

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    12/14

    12

    PetworthInterior Renovations Contacts Progress

    Councilmember

    Open February 28, 2011

    Councilmember Muriel Bowser

    Ward 4 202.724.8052

    Architect Frank and Loshen

    Fletcher FarrAnoyte

    Project

    ManagerChris Wright

    202.727.4913

    Contractor Sigal Construction

    Sarah Norman

    DCPL PM

    Firm

    McKissack and

    McKissack

    Tenley FriendshipNew Building Contacts Progress

    Councilmember

    Opened January 24, 2011

    Ward 3 Mary Cheh

    202.724.8062

    Architect Freelon Group

    Philip Freelon

    919.941.9790

    Project

    ManagerDedric Boyd

    202.727.1113

    Contractor Forrester.

    Joe Ockershausen

    301.255.1794

    DCPL PM

    FirmHill International

    Project updates the interior of the Petworth Library to be a

    fully functional state of the art 21st

    Century Library, while

    still being respectful of the buildings historic character.

    Design of the new Tenley Branch Library will include

    community input on planning and programming phase. Design

    and construction is fully funded.

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    13/14

    13

    Washington HighlandsInterim Library Contacts Progress

    Councilmember

    Open to the public December 21, 2009

    Ward 8 Marion Barry

    202.724.8045

    Architect Cooper Carry

    ProjectManager

    Lisa Deanes

    202.727.5181

    Contractor MCN Build

    DCPL PM

    Firm

    Jair Lynch

    Development

    Watha T. Daniel / ShawNew Building Design Contacts Progress

    Councilmember

    Opened to the public August 2, 2010

    Ward 2 Jack Evans

    202.724.8058

    ArchitectDavis, Brody

    Bond & Aedas

    Peter Cook

    202.449.1190

    Project

    Manager Kim Fuller

    202.442.6069

    Contractor Forrester.

    Joe Ockershausen

    301.255.1794

    DCPL PM

    FirmA-1 Construction

    Project complete and Library is open to the public.

    .

    Project consists of building a 5,000 square foot interim library

    for the Washington Highlands Community; the interim will

    have 20 computers, books on CD as well as traditional

    collection material for all age sets.

  • 8/3/2019 Document #9C.1 - Capital Construction Report

    14/14

    14

    Martin Luther King Jr. LibraryNew Teen Spot andCollege Information Center

    Contacts Progress

    Councilmember

    Project Complete

    Ward 2 Jack Evans

    202.724.8058

    Architect Sorg Associates

    Suman Sorg

    Project

    ManagerKim Fuller

    202.442.6070

    Contractor Bennett Group

    Kolar Bowen

    202. 625.3330

    New Teen Spot and College Information Center is a

    destination for teens. It provides stimulating learning

    opportunities that support their success in life. This destination

    provides opportunities to meet their need for homework help,

    exam preparation, and using computers and software

    applications. High quality program events are a key to the

    success of the library in assisting teens.