    Document #9C

    Board of Library Trustees MeetingMay 23, 2012

    The District of Columbia Public Library

    Capital Construction Report

    May 23, 2012

  • 7/31/2019 Document #9C - Capital Construction Report

    2/14

    2

    Bellevue LibraryNew Building Design Contacts Progress

    Councilmember

    Furniture installation began on May 15th

    Opening Date is June 13th

    .

    Ward 8 Marion Barry

    202.724.8045

    Architect Wiencek/Adjaye

    Scott Knudson

    301.948.6220

    Project

    ManagerLisa Deanes

    202.727.5181

    Contractor Coakley-Williams

    DCPL PM

    Firm

    Jair Lynch

    Development

    Partners

    Francis A. Gregory Library New Library Contacts Progress

    Councilmember

    Furniture Installation began on May 18th

    Opening Date is June 19th

    Ward 7 Yvette Alexander

    202.724.8068

    Architect Wiencek/Adjaye

    Scott Knudson

    301.948.6220

    ProjectManager

    Lisa Deanes

    202.727.5181

    Contractor Hess Construction

    Jair Lynch

    Development

    PartnersDCPL PM

    Firm

    Design of the new Francis Gregory Library will include

    community input on planning and programming phase. Project

    is fully funded.

  • 7/31/2019 Document #9C - Capital Construction Report

    3/14

    3

    Mount PleasantInterior Restoration Contacts Progress

    Councilmember Jim Graham

    All zoning and legal issues have been resolved.

    Work is 95% Complete

    Furniture Installation to begin on June 30th

    Opening date will be the last full week in July.

    Ward 1 202.724.8181

    Architect Core Architects

    Dale Stewart

    202.466.6116

    Project

    ManagerChris Wright

    202.727.4913

    Contractor T.B.D

    DCPL Project

    Management

    Smoot

    Construction

    Northeast LibraryDesign-Build Renovations Contacts Progress

    Councilmember Tommy Wells

    Design-Builder selected. Conceptual Design Phase

    underway.

    3rd

    Meeting with Northeast Friends May 21st

    Project is fully funded.

    Vertical transportation addition approved by

    HPRB.

    Ward 6 202.724.8072

    ArchitectBell/Vines

    Architects

    David Bell

    Victor Vines

    Project

    Manager

    Chris Wright

    202.727.4913

    Design-Builder Whiting-Turner

    Andrew Easter

    Phase II of Mount Pleasant Renovation. Interior work will

    consist of total upgrade and modernization of all mechanicalequipment as well as provide additional and functional library

    program space.

    This project is a major interior renovation of the 1930s era

    library. Renovations will create a 21st Century library while

    maintaining the historic integrity of the buildings interior.

  • 7/31/2019 Document #9C - Capital Construction Report

    4/14

    4

    West End LibraryMixed Use Development Contacts Progress

    Councilmember Jack Evans

    New ground floor library will be part of mixed use

    development.

    Library designs are underway.

    Project has received preliminary PUD approval

    from DC Zoning Commission on February 13,

    2012.

    Ward 2 202.724.8058

    Architect Ten Arquitectos

    Erik Lang

    Project

    ManagerKim Fuller

    202.442.6069

    Developer EastBanc

    Joe Sternlieb

    202.737.1000

    Woodridge LibraryDesign Contacts Progress

    Pre-design due diligence work includes a hazardous

    materials survey, a Phase 1 and Phase 2 Environmental

    Site Assessment, Existing Topographical Survey,

    Geotechnical Report and a Cost Benefit Analysis.

    Councilmember Harry Thomas Jr.

    Design contract to Weincek and Associates inpartnership with Bing Thom Architects was

    approved by Council.

    Program Analysis underway.

    Ward 5 (202) 724-8028

    Architect Wiencek + Assoc

    Bing Thom Arch

    Project

    ManagerKim Fuller

    202.442.6069

    Contractor

  • 7/31/2019 Document #9C - Capital Construction Report

    5/14

    5

    MLK Jr. LibraryBusiness and Technology Reconfiguration Contacts Progress

    Councilmember

    Space planning for Business, Science and

    Technology Complete

    Project scope has increased to handle shifting of

    library collections on the 2nd

    Floor. Currently

    reviewing building code issues.

    MCN Build Selected as Construction Manager

    eBic and Book Store Plus have been removed.

    Ward 2 Jack Evans

    202.724.8058

    Architect The Freelon Group

    Derek Jones

    919-941-9790

    Project

    ManagerKim Fuller

    202-442-6069

    Contractor MCN Build

    Joseph Kourney

    202.333.3424Improvements and upgrades to west reading room. Entire

    first floor is under the Historic Landmark Designation. The

    MLK Design Guidelines will be utilized.

  • 7/31/2019 Document #9C - Capital Construction Report

    6/14

    6

    Completed ProjectsAnacostia LibraryNew Building Construction Contacts Progress

    Councilmember

    Opened to the public April 26, 2010

    Ward 7 Yvette Alexander

    202.724.8068

    Architect Freelon Group

    Philip Freelon919.941.9790

    Project

    ManagerDedric Boyd

    202.727.1127

    ContractorForrester

    Construction

    Tom Willerton

    301.816.1700

    DCPL PM

    Firm Hill International

    Benning LibraryNew Building Design Contacts Progress

    Councilmember

    Opened to the public April 5, 2010

    Ward 7 Yvette Alexander

    202.724.8068

    ArchitectDavis, Brody,

    Bond & Aedas

    Peter Cook

    202.449.1190

    Project

    ManagerKim Fuller

    202.442.6069

    Contractor Forrester

    Jon McGee

    301.255.1750

    DCPL PM

    FirmA-1 Consulting

    New State of the Art Library on Good Hope Road SE is open.

    New State of the Art Library located at 3935 Benning Road NE

    is open.

  • 7/31/2019 Document #9C - Capital Construction Report

    7/14

    7

    Cleveland ParkNew Ceiling and Lighting Contacts Progress

    Councilmember

    Project Complete

    Ward 3 Mary Cheh

    202.724.8062

    Architect N/A

    Project

    ManagerEd Hampton

    202.442.6067

    ContractorEagle

    Construction

    DeanwoodNew Community Center and Library Contacts Progress

    Councilmember

    Opened to the public June 25, 2010

    Ward 7 Yvette Alexander

    202.724.8068

    Architect EEK

    Sean ODonnell

    Project

    Manager

    ContractorProject is a partnership with the Department of Parks and

    Recreation to co-locate a 10,000 square foot library within a

    54,000 square foot aquatic center and community center.

    Library and Community Center would share such space as

    computer lab, senior rooms, tutor rooms and community

    meeting rooms. Project location is 49th and Quarles St. NE

    Project consists of installing a new ceiling and lighting system.

  • 7/31/2019 Document #9C - Capital Construction Report

    8/14

    8

    The Library has received Federal Stimulus Money for energy

    enhancements. Projects will take place at the above locations,

    focusing on window replacements, energy efficient lighting,

    and automated building heating and cooling controls

    Energy Enhancement Projects Various Locations Contacts Progress

    Capitol View, Cleveland Park,

    Shepherd Park, Lamond Riggs, Palisades, Southwest, West

    End and Woodridge

    Councilmember

    Energy Efficient Lighting Projects are

    COMPLETE

    Window and Door work is complete

    Various

    Architect T.B.D

    Project

    ManagerEd Hampton

    202.442.6067

    Contractor

    DCPL PM

    Firm

    Francis A. Gregory Library Interim Library Contacts Progress

    Councilmember

    Opened June 10, 2010

    Ward 7 Yvette Alexander

    202.724.8068

    Architect

    ProjectManager

    Lisa Deanes

    202.727.5181

    ContractorWilliam Scotsman

    Greg Bichell

    DCPL PM

    Firm

    Project consists of building a 4,200 square foot interim library

    to serve the community during construction; the interim will

    have 30 computers, books on CD as well as traditional

    collection material for all age sets

  • 7/31/2019 Document #9C - Capital Construction Report

    9/14

    9

    Georgetown LibraryBuilding Renovation Contacts Progress

    Councilmember

    Opened to the Public October 18, 2010

    Ward 2 Jack Evans

    202.724.8058

    Architect Martinez & Johnson

    Tom Johnson

    202.333.4480

    Project

    ManagerChris Wright

    202.272.4913

    Contractor N/A

    DCPL PM

    Firm

    Smoot

    Construction

    Mount PleasantInterim Library Contacts Progress

    Councilmember Jim Graham

    Opened to the public April 26, 2010Re-opened to the public May 15, 2010

    Ward 1 202.724.8181

    Architect Core Architects

    Dale Stewart

    202.466.6116

    ProjectManager

    Dedric Boyd

    202.727.1127

    Contractor MCN Build

    Bassem Boustany

    202.333.3424

    Renovation complete and Library open to the public.

    Project consists of building a 3,600 square foot interim library to

    serve the community during construction; the interim will have

    30 computers, books on CD as well as traditional collection

    material for all age sets

  • 7/31/2019 Document #9C - Capital Construction Report

    10/14

    10

    Northeast LibraryExterior Restoration Contacts Progress

    Councilmember Tommy Wells

    ConstructionSubstantial completion May 15, 2010

    Ward 6 202.724.8072