53
DAIRY AIR WIND GENERATION PROJECT SYSTEM IMPACT STUDY 2200KW Crocket Engineering, LLC · August, 2016 Exhibit DAW-DPE-3 Page 1 of 53

DAIRY AIR WIND GENERATION PROJECT SYSTEM … · voltage at other Local EPSs to go outside the requirements of ANSI C84.1-2011 1995, Range A. It is recommended that the DR be allowed

Embed Size (px)

Citation preview

DAIRY AIR WIND

GENERATION PROJECT

SYSTEM IMPACT STUDY

2200KW

Crocket Engineering, LLC ·

August, 2016

Exhibit DAW-DPE-3 Page 1 of 53

Table of Contents

Page

1) Project Overview ................................................... 3

2) System Description ................................................ 4

3) Analysis Criteria ..................................................... 5

4) Interconnection Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

5) Summary ............................................................. 12

6) Appendix ............................................................ 13

A. System One-line Diagram

B. Project Site Plan

C. Generator and Equipment Specifications

D. Circuit Map

E. PSB Rule 5.500, Section 5.505

F. Substation Load Duration Curve

G.IEEE 1547 2014 Amendment

H. Fast Track Screening

I. Cost Estimate

2

Exhibit DAW-DPE-3 Page 2 of 53

1. Project Overview

Dairy Air Wind, LLC has proposed installing a 2200 kW1

wind turbine system, on School Road in Holland

2, Vermont. The proposed generation will be interconnected

at 12.5GrdY/7.2 kV with a Vermont Electric Cooperative (VEC) distribution system that originates at VEC's West Charleston Substation.

The West Charleston Substation is served via VEC's Newport-Island Pond 46 kV line, which is supplied by Vermont Electric Power Company's (VELCO) 115 kV system.

The proposed generation requires a Certificate of Public Good (CPG) under 30 V.S.A. §248. As required by §248(b) (3) of this statute, the applicant mustdemonstrate that the generation "will not adversely affect system stability andreliability". This System Impact Study will demonstrate that the generator will meetthese requirements for operation, provided that the additional analyses and upgradesspecified in Section 4 are performed and any recommended upgrades and settings areimplemented. This report assumes a maximum net output for the wind turbine of2200 kW. For outputs above this level, additional analysis will be required.

1 Net AC output 2

See Circuit Map, Appendix D

3

Exhibit DAW-DPE-3 Page 3 of 53

2. System Description

The project is presently served via VEC's West Charleston Substation. The substation consists of a 5/5.6/73 MV A, 46-13.2kV transformer, three 328 amp Cooper VR-32 regulators with Form CL-6A controls and four distribution circuits protected by Cooper VWE reclosers with Form 6 controls. The distribution circuits serve portions of Derby, Morgan, Holland, and Island Pond. The project is on the Holland Feeder, l A. In addition, Great Bay Hydro operates a 675 kW hydro plant served from the West Charleston Bus. A 500 kW solar project is proposed for Morgan and will be considered in the report. There are a set of regulators on Mead Hill Road with Form CL-7 A controls.

The distribution line that will be interconnected to the proposed Project is a multi­grounded wye circuit. The total length of distribution line between the Substation and the project location is approximately 8.7 miles, consisting of 7.7 miles of#2 ACSR three phase construction and .33 miles of 6A Copperweld, single phase construction. This study assumes that the 6A Copperweld has been replaced with three phase, 4/0 AAAC construction and that the 4/0 AAAC is extended 3000' to the site. The developer has planned a 500' 1/0 AAAC extension to the wind turbine.

The peak load on the circuit is 1235 kW based upon recent peak load readings at the Substation. There is a slight imbalance on the circuit, with A phase loaded to 59 amps and B phase loaded to 55 amps and C phase loaded to 61 amps.

There are 300 kV Ars of capacitors on this circuit as follows:

Location

Mead Hill Road

Phase kV Ar/Phase Total

ABC 100 300

All of the capacitors are fixed on. A review of the V Ar flows calculated by the loadflow analysis indicated that no changes are necessary at this time.

The substation regulators are positioned in a "bus regulation" configuration with co­generation settings on. It is assumed that the Mead Hill Road regulators will be set to co­generation mode also.

The new generator step-up transformer has been specified with a nameplate rating of 2750 kV A, 12.5GrdY/7.2 volt wye-690 Delta- 398 grounded wye configuration, and 7 % impedance. In addition, a 500 kV A grounding transformer will be installed at the interconnection.

3 5 MV A nameplate with additional cooling ratings

4

Exhibit DAW-DPE-3 Page 4 of 53

A lockable load-break gang switch, metering and recloser will be installed where the VEC distribution line enters the project property. The load-break switch & recloser are inside the property, as shown on Exhibit B.

5

Exhibit DAW-DPE-3 Page 5 of 53

3. Analysis Criteria and Study Results

The load flow studies were conducted using the MilSoft WindMil distribution circuit analysis program. WindMil was used to perform peak and minimum load level cases and the fault calculations. The peak load case is with the substation at 2540 kW and -100 kV Ar. The minimum load case is with the substation at 1000 kW and -300kV Ar. The circuit is loaded to approximately 1235 kW and 400 kW, respectively. A500 kW solar plant is planned for Morgan and is considered on for this analysis.

The study was conducted under the guidance of the following reports:

• IEEE Standard 154 7, IEEE Standard for Interconnecting DistributedResources with Electric Power Systems, July 28, 2003 and 2014Amendment.4

• PSB Rule 5.500 Interconnection Procedures for Proposed Electric GenerationResources

• Utility Interconnection Guidelines for Distributed Generation Equipment of 1MW or Less Connected to a Radial Distribution System, Philip Barker,January 23, 2006.

Fast Track Screening

PSB Rule 5.5055 provides a list of criteria that allows a project to be processed

without a Feasibility Study, System Impact Study or Facilities Report. To be considered, a project must meet all of the Fast Track Criteria. The Project does not meet criteria 5.505(B) 3, 4, 8 and 10, at a minimum, and is therefore not eligible as a Fast Track application.6

4 See Appendix G

5 See Appendix E

6 See Appendix H

6

Exhibit DAW-DPE-3 Page 6 of 53

Analysis:

i) Analyze the impact of the generation on the area voltage using loadflowanalysis.

IEEE 1547 now allows for system regulation by distributed generators. The proposed generator can provide up to 720 kV Ar to the system. The analysis therefore will include the generator regulating the voltage up to this level ofV Ar output. The voltage set point for the generator was assumed at .98 PU. The Mead Hill Capacitor has been assumed to be changed to a switched capacitor to reduce the voltage during generation periods.

The voltages, calculated by loadflow analysis, are as follows:

VOLTAGE CHANGE SUMMARY Before Dairy

Mead Hill Air Site At Substation Regulators

On peak, no generation 123.4 115.5 120.7

On peak, 2200 kW on at Dairy Air 122.3 120.5 122.1 On peak, 2200 kW on at Dairy Air and 500 kW

122.5 121.7 122.1 at Morgan Solar

Off peak, no generation 123.3 120.5 121.5

Off peak, 2200 kW unit on at Dairy Air 122.6 122.5 123.0

Off peak, 2200 kW on at Dairy Air and 500 kW 122.6 122.5 123.4

at Morgan Solar

As, shown, the voltage on and off peak are all below the 125.0 maximum allowed. In the case with the on-peak load and no generation on, the 300 kV Ar capacitor on Mead Hill switched on due to low voltage.

7

Exhibit DAW-DPE-3 Page 7 of 53

46 kV issue:

With the addition of the 2200 kW wind project onto the West Charleston Substation there exists a possibility of the project remaining energized when a line to ground fault occurs on the 46 kV system supplying the substation. The substation transformer is a 46 kV delta to 12.5 kV wye configuration. As a result, during a transmission line to ground fault, the phase to ground voltage on the unfaulted phases of the 46 kV system could shift to the full phase to phase voltage and the lightning arresters on the unfaulted phases of the 46 kV system could be experiencing 46 kV. The arresters at West Charleston are 54 kV duty cycle arresters, with a 43 kV MCOY (maximum continuous operating voltage) and would ultimately fail if the condition were to persist under these conditions. The "Suggested Guidelines for Anti-Island Screening" tool points to the condition where the DO is matching the load and V Ars and there is a rotating machine in the potential island that is greater than 25% of the total DO on the system. The total DO is 3375 kW and the hydro output is 675 kW, or 20 % of the total, at full output. Under conditions where the hydro output is at or near 100 % but the wind and or solar is not this condition could be met. To protect the 46 kV system from this possibility, a zero sequence over voltage detection system is required to be installed on the 46 kV bus at the VEC West Charleston Substation. The relay would then be set to trip the Holland Feeder (lA) to remove the source of the overvoltage.

Flicker:

Unlike conventional rotating machines, there is no significant inrush current as a result of energizing an inverter. The wind turbine will ramp up to its full output when it turns on. The voltage could sag as a result of the unit tripping. The maximum voltage drop expected under these circumstances is 1.5% for the 30 seconds that it will take the Mead Hill Regulators to adjust the voltage.

Substation Transformer and Regulator Loading:

The substation transformer is rated 7000 KV A while the substation regulators are rated for 7,500 kV A. The peak loading on the substation is 2500 kW and -100 kV Ar. During peak load periods the substation loading will be reducedby the project while the reverse power flow could be increased to -2375 kWduring light load periods. In either case, substation loading is not a problem.

ii) Analyze the impact of the generation on the circuit fault current:

As shown below, with the 2200 kW generator running, the single phase fault current increases to 674 amps at the Project transformer. No protective devices will be above

8

Exhibit DAW-DPE-3 Page 8 of 53

their interrupting rating and the increased fault current will not adversely affect the coordination of any devices. The additional fault current will provide better clearing times for lateral fuses on this section of line which will lower the chances of a minimum current fault remaining energized on the ground.

Fault Current Summary Without With

Generation 2200 kW

Generator

Project 3<J> 535 653

Project 1<j> 577 674

Substation 3<j> 2310 2351

Substation 1 <I> 2659 2697

i) Protection Coordination:

A review of the circuit protection scheme indicated that are no changes necessary as a result of the Project. Fuses may be added to the main line beyond the School Road tap to the project.

ii) Operating Changes:

As a result of the zero sequence detection scheme tripping the Holland Circuit Breaker, VEC personnel will need to be advised to verify that this breaker closes upon restoration of the transmission line.

In addition, IEEE 154 7 recommends items not otherwise discussed.

Section 4.1.17

requires that coordination with and approval of, the area EPS and DRoperators, shall be required for the DR to actively participate to regulate the voltage by changes of real and reactive power. The DR shall not cause the Area EPS service voltage at other Local EPSs to go outside the requirements of ANSI C84.1-2011 1995, Range A. It is recommended that the DR be allowed to actively regulate the voltage.

7 1547 2014 Amendment

9

Exhibit DAW-DPE-3 Page 9 of 53

Section 4.1.2 requires that the generators not disrupt the area grounding nor have an undue effect on ground fault protection of the circuit. Use of a grounded wye­grounded-wye transformer with an ungrounded wye source can lead to neutral shift on the primary system during a ground fault where the line or substation recloser opents. The PCC will include a grounding bank with a tripping function to the PCC recloser for ground faults.

Section 4.1.3 requires that synchronization not cause large voltage fluctuations or flicker issues. Because the generator will be inverter based, no large inrush currents will occur during synchronization, so voltage fluctuations and flicker will not be issues as with induction generators. The impact of the generator under various voltage conditions is described above.

Section 4.1.4 deals with issues associated with interconnection with a secondary spot network. The Project will not be connected to a spot network.

Section 4.1.5 requires that the generators not energize the distribution circuit when the circuit is de-energized. This requirement will be met with relaying at the recloser at the PCC and the use of an overvoltage detection scheme at the West Charleston Substation.

Section 4.1.6 requires that generators above 250 kV A have monitoring provisions to

provide connection status, and real and reactive power output and the voltage at the point of common coupling. The Project plans to install 2200 kW of generation, therefore monitoring provisions will be required. A telemetering package that includes status, real and reactive power output and voltage monitoring, at a minimum, will be required.

Section 4.1. 7 requires the installation of a readily accessible, lockable switch with a visible opening be installed between the Area EPS and the DG unit. Three disconnect switches will be installed in front of the recloser for visible protection. The recloser can be locked out.

Section 4.1.81 requires that the interconnection system shall be capable of withstanding electromagnetic interference in accordance with IEEE standard C37.90.2-1995 without miss operation. The equipment meets this standard.8

Section 4.1.8.2 requires that the system withstand voltage and current surges in accordance with IEEE C62.41.2-2002 or C37.90.l-2002, as applicable. The equipment meets these standards.9

Section 4.1.8.3 requires that the interconnection paralleling device be capable of 220% of the interconnection voltage. The equipment meets this standard. 10

8 Per the manufacturer's literature

9 Per the manufacturer's literature

10 Per the manufacturer's literature

10

Exhibit DAW-DPE-3 Page 10 of 53

Section 4.2.1 requires that the DR unit shall cease to energize the Area EPS for faults on the Area EPS circuit to which is connected. The relays will be set to trip the generator for faults on the distribution system.

Section 4.2.3 requires the generator to trip within specific times when the voltage is outside of preset limits. The generator over voltage and under voltage relays will be set to meet this Standard, as amended in 2014. See Table 1, Appendix G.

Section 4.2.4 requires that the DG shall sense high and low frequency conditions and trip within specified times. The generator under and over frequency relays will be set to meet this Standard, as amended in 2014. See Table 2 in Appendix G.

Section 4.2.6 requires that the DG not reconnect until the distribution system is within the limits specified by Range B of ANSI C84.1-1995 and a frequency range of 59.3-60.5 Hz. The applicable B Range values are 424 to 508 volts. In addition, a time delay for up to five minutes prior to re-energizing shall be included in the generator relaying. The under and over frequency relays and under and over voltage relays will assure that this standard is met. The inverter shall be set to implement the proposed time delay.

Section 4.3.1 requires that the system not inject DC current greater than .5% of the full rated output current at the point of interconnection. The inverter meets this standard. 11

Section 4.3.3 sets a standard for harmonics. The generator must satisfy IEEE 519-1992 for the harmonic content, as indicated by Table 3-3 below.

Table 3-3 IEEE 519-1992

Harmonic Order

2nd to 10th

11th to 16th

17th to 22nd

23rd to 34th

35th or hiQher

Total Harmonic Distortion

Level Allowed Relative to the

Fundamental for Odd

Harmonics*

4.0%

2.0%

1.5%

0.6%

0.3%

5.0%

*Even harmonics are limited to 25% of the odd harmonic values

11 Per the manufacturer's Literature

11

Exhibit DAW-DPE-3 Page 11 of 53

The specifications for this generator limit the total harmonics to less than the required 3%.

Section 4.4.1 requires that the generator not unintentionally island a portion of the distribution circuit and be de-energized within two seconds of a condition that would lead to islandizing. The inverter requires AC input to operate and will sense the loss of incoming power. In addition, the under and over frequency, voltage relays and ground fault detection relay will sense an islanding condition and trip the unit.

Section 4 lists the performance tests required to be conducted to demonstrate that the interconnection meets the requirements laid out in Section 3. The Project will be required to conduct and document the results of these tests prior to normal operation of the units in parallel with the Vermont Electric Cooperative System. The specific test requirements are listed in Appendix F.

12

Exhibit DAW-DPE-3 Page 12 of 53

4. Interconnection Requirements

The following items are required to assure proper operation of the new PV generators at the Project facility.

a. Installation of a grounding bank to provide a grounded generation source to theVEC distribution grid.

b. Installation of a high side voltage ground fault detection relay.

c. Installation of a SCADA controlled and motor operated three phase gang load

break switch at the Point of Interconnection (POI) to provide protection and avisual, lockable open point for line maintenance. SCADA requires a suitablecommunications path for SCADA back to the VEC Control Center.

d. Replacement of the lightning arresters at West Charleston, Island Pond andNewport substations if necessary.

e. Installation of a zero sequence over voltage detection scheme on the 46 kV bus atWest Charleston Substation, set to trip the Holland Feeder recloser.

f. The Project system to be inspected by a State Electrical Inspector to assurecompliance with the National Electrical Code.

g. Cost estimate for VEC's work is in Appendix Ih. The Project will complete the testing required by IEEE 1547.1 2005 and provide a

written copy to VEC.

13

Exhibit DAW-DPE-3 Page 13 of 53

APPENDIX A

System One-Line Diagram

14

Exhibit DAW-DPE-3 Page 14 of 53

ie G

� � g

;!: H 0: < i:: iii

I � !

LEGEND ---

� ®

SUNSET DRIVE DURGIN ROAD

7.5 MILES {EXISTING) VEC-WEST CHARLESTON SUB

MORGAN CHARLESTON ROAD

MEAD HILL ROAD

VALLEY ROAD

END OF 3 PHASE INTERSECTION OF VALLEY ROAD & SCHOOL ROAD

GORE ROAD

VEC : DAIRY AIR

1/0 AWG ACSR AERIAL TAP LINE 6500 FEET (NEW) SCHOOL ROAD

POI I

I

oisi����cT

II

10 KV(B.4KV MCOV) SURGE ARRESTOR

T

REVENUE METERING

(3)10KVA �

· 7200-240/120 VOLT

TRANSFORMERS (VOLTAGE SENSING

& PWR SUPPLY)

r.i _..,_

PAO MOUNT TMNSFORMER �'--- LOADIIIU!AKIWm:::H OENEMTOIII

CAIL! TERMINA TOil SEL411

% 1AMPFUSI!

111!1.AY lo CONTROUD:

---lf--111 IUIIICM!AfUlEST0R � >- 19ARABL£ CONNl!CTOIII

TRANll'OIIMER OVl!RHl!AD UNI!

560A; 12KA INTERRUPTING VWE RECLOSER W/ 351R CONTROLLER

500: 1 SR

�;' "' .,."'

-[ID-- IIIECLOSEII

T UNDflllQftOUNO CABLE

___,,/_ IWITCH

JUNCTION BOX

M0l.OEDCAILETOMINAT10NIIEL80Wl [fil Ulfflllft!MCBI

10KV (B.4KV MCOV) SURGE ARRESTORS

T

GT-1

GROUNDING TRANSFORMER

500KVA 12.47 /7.2KV

GRD Y - 4BOVCI 6%Z; X/R=7.5

10 11 12 13 14 15 16 17

GOLOWINO WIND TURBINE

RECTIFIER INVERTER >:c v' COLLECTOR CABLE

500 FEET 1/0 AWG ACSR AERIAL LINE

10KV (8.4KV MCOV) 1il.J INTERMEDIATE CLASS ,'

T1

2750KVA 12.47KV-0.69KV

t, - GRD Y 95KV BIL

2.2 MW

UPDATED GENERATOR DATA

M"t.A CONCEPTUAL DESIGN

10 11 12

06115116 SJS OPE

0&'06/16 BGH �,E '"" -·

GENERATOR

CONTROLLER

LS!G "" ·

F��;;-��t,;;;; +-®- -��- �-c CONDUIT I 2750kVA

Relay Legend

25 - Synchronization check 27 - under volloi;e 271 - nstontoneous under voltage J2R - reverse power 32F - forward power 46 - negative phase sequence 0/C 47 - reverse phase volta�e 49 - stator winding temperature 50/51 - instantaneous/timed ovcrcurrent 51 G - wound overcurrent 591 - t'iigh speed overvottoge 59T - time ovcrvoltoge 60 - >JO!toge balance relay 810 - over frequency 81U - undcrfrequency

130 AI.APS�NIT O 12.47KV

cR!-C

690V/12.47kV 7.0% ;X/R 8.0

PAO l.40UNTEO TRANSf'0Rl.4ER

DAIRY AIR WIND PROJECT

ENGINEERING

06/ll6/16 OAA-ff.

BGH DIOIN"D•�

217WtilltenRoad SCALE: NTS HOLLAND, VT

812E:ARCHO OPE

twfowd,IME 04347 ...,.a•

OPE Phone 207-121.1077 22070 Fax 207-821-1177 ONE LINE DIAGRAM OMWIHGtl:

OPE Al'IWI):

www.l'tc4ng.com E.JOO

13 14 15 16 17

A

C

G

Exhibit DAW-DPE-3 Page 15 of 53

APPENDIXB

Project Site Plan

15

Exhibit DAW-DPE-3 Page 16 of 53

0 0 N 1,-

0 0 N

en

;:o z en

DJ ;:o

;:o

/1�llli:1!

. ;l,,i21t,

1300

1300

. .

.

.

.

.�

� �

0 0 '<:I' ,..,

� �

Sources: Esri, HE-R'E-;-�·t..0�, lntefmap, incrementf/ Corp}, GEBCO, USGS, FAO, NPS, NRCAN, GeoBase, IGN, Kadaster NL, Ordnance Survey, E�ali'a,�ETI, Esri China (,1-j@l'l'g�Kong), swiss to po, Mapmylndi a, © OpenStreetMap contributors, and the GIS User Communi ty '-".

72°

0w

Dairy Air Wind, LLC Conceptual Site Plan

Topographic map of proposed project area including proposed study area, sit

design, property boundaries, and relate existing interconnection infrastructure.

CANADA

� 1,-.r�--"\.

--¼ r·- .' c:r- -onand

'-., '"-;.,

l

- ..{_

Legend

:Ii Wind Turbine Location

• Point of Interconnection

• • • • UG Collection System

�Upgraded VEC Single Phase Distributic

�New Three Phase Distribution

Crane Pad

Access Road

- VEC Three Phase Distribution

5 ft. Contours, NED DEM

C:=J Property Parcels

0 500 1,000

Feet

2,00(

Data sources: The underlying topographic map an, elevation and VEC electrical data are provided by VCGI at VCGl.vermont.gov. Project data provided VERA Renewables, Inc.

Prepared: 20160613rd

N

A Renewables

Exhibit DAW-DPE-3 Page 17 of 53

APPENDIXC

Generator Specifications

16

Exhibit DAW-DPE-3 Page 18 of 53

Rev.:B-LM DocumentNo.:GW-07FA.0096

GOLDWIND

Goldwind 2.2 MW Turbine General Technical Description

Goldwind Science & Technology Co., ltd.

www.goldwind.com.cn

[email protected]

Exhibit DAW-DPE-3 Page 19 of 53

�GOLDWIND Rev .:B-LM Document No .: GW -O?FA .0096

CONTENTS

1 Scope .. ..... ........... ................. .. ...... ........ .. . ... . . . . . . .. .. . ... . ... .. . 2

2 General Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

3 Rotor ....... .. . . ...... .. .. .. . ... .... .... .. .... .... .. ... ...................... ....... 4

4 P MDD Generator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

5 Nacelle. ........................... ......... .. . . . . . .. . . .......... .................. 9

6 Tower . ... . ....................... ................................ ................. ..... .. 11

7 Foundation ...... . .. . ... . .. . . ...... . . .. . . . . . ..... ................ ... .... ..... . . . . . . 11

8 Electrical Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

9 Turbine Controller. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

10 SCADA (Supervisory Control and Data Acquisition). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

11 Goldwind 121-2.2MW Wind Turbine Technical Data ................ .... ............... . . 14

Figures

Figure 1 Goldwind 2.2MW Turbine ........................................................................................................ 2

Figure 2 Pitch system and rotor ............................................................................................................. 4

Figure 3 Pitch Control Electrical Diagram ............................................................................................. 5

Figure 4 P MDD Generator ..................................................................................................................... 6

Figure 5 Heat Exchanger ............................................................................................................................ 8

Figure 6 Airflow though the generator ................................................................................................. 9

Figure 7 Yaw System ............................................................................................................................ 10

Figure 8 GW 2.2MW Electrical Diagram ............................................................................................. 12

Figure 9 GW 2.2MW Main Controller Diagram .................................................................................... 13

Tables

Table 1 Goldwind 121-2.2MW Wind Turbine Technical Data ............................................................... 14

Preserving Blue Skies and White Clouds for the Future Page 1 of 14

Exhibit DAW-DPE-3 Page 20 of 53

f;f:GOLOWINO Rev.:B-LM Document No.: GW-O?FA.0096

Goldwind 2.2 MW Turbine General Technical Description

1 Scope

This description specifies the general technical specifications. This description applies to Goldwind

GW121-2200 turbine series.

2 General Description

The basis of the GOLDWIND 2.2 MW wind turbine (GW 2.2 MW) is its Permanent Magnet (PM)

generator, which is gearless and Directly Driven (DD) by a 3-blade rotor. The combination of the PM

synchronous generator with its full power converter maximizes energy output, making the wind

turbine highly efficient and reliable. These technologies specify the turbine type.

Wind turbines frequently operate at partial load; a range wherein PM generators reach their highest

efficiency. The closed loop active air cooling system with its two air-to-air heat exchangers further

optimizes the generator's performance. Direct Drive (DD) is the ultimate concept for reducing turbine

components as well as increasing its reliability. Utilizing one double-row tapered roller bearing as the

rotor and generator bearing makes the design structure compact and light weight. The full load IGBT

converter allows an adapting rotor speed to achieve optimum aerodynamic efficiency at varied wind

speeds. This converter system c.ombined with the PM generator guarantees superior grid connection

capabilities. Tooth-belt driven pitch systems combined with ultra-capacitors ensure precision, safety

and low maintenance.

Figure 1 Goldwind 2.2MW Turbine

Preserving Blue Skies and White Clouds for the Future

1. Rotor Blade 2. Pitch Sys tern 3. casted Hub 4. PMDD Generator 5. Rotor/Generator Bearing 6. Base Frame 7. YawSystem 8. Heat Exchanger 9. Auxiliary Crane 10. Meteorological Equipment

Page 2 of 14

Exhibit DAW-DPE-3 Page 21 of 53

�GOLDWIND Rev.:B-LM Document No.: GW-07FA.0096

Special Features:

• Permanent Magnet "PM" generator

¢ No energy loss through magnetic field excitation

¢ High generator efficiency, especially at partial load

¢ No need for slip rings for excitation of generator-rotor

• Direct Drive "00" multi-pole generator• Direct flange connection between turbine-rotor and generator

¢ Gearless; no gearbox monitoring system

¢ No gearbox oil, no oil pumping, cooling or filtering• One Large Diameter, double-row tapered roller bearing to connect the turbine rotor and

generator rotor unit to generator stator• External generator-rotor concept• Air to air active cooling system

¢ Compact design

¢ Fewer components: high reliability, less maintenance, higher availability

• PMDD generator is combined with full power IGBT converter

¢ Wide range of speed control, optimum turbine-rotor efficiency

¢ Superior grid connection capabilities (ZVRT, LVRT, HVRT)

• Tooth belt driven blade pitch system

¢ No backlash; more precise pitch angle

¢ No grease lubrication needed for the tooth belt

¢ Easy to exchange (compared to a geared pitch bearing)

• Ultra-Capacitors used in series with each pitch actuator motor powersupply

¢ No use of lead-acid battery, no energy loss at low temperature

¢ Long lifetime • No change of operation mode of pitch system during voltage drop or grid loss• Permanent control of energy storage

¢ Safely pitch each blade to a safe position after power loss or for an emergency stop

Version Rated Nominal Rotor

Wind Class Power Diameter

GW121/2200 2.2MW 121m IEC 1118

Preserving Blue Skies and White Clouds for the Future Page 3 of 14

Exhibit DAW-DPE-3 Page 22 of 53

�GOLDWIND Rev.:8-LM Document No.: GW-07FA.0096

3 Rotor

3.1 Blades

The Goldwind 2.2 MW wind turbine rotor is equipped with 3 reinforced fiber glass blades (GRP) that

are produced by qualified international blade manufacturers. The high aerodynamic efficiency of the

rotor is based on the efficient design of the airfoils used in each blade. Different blade lengths are

used depending on the wind class of the site that the turbine will be placed. This optimizes energy

output and loads.

Blade Type Nominal Rotor Actual Rotor Swept Area

Diameter Diameter

LM 58.8 121m 120.lm 11329 m2

3.2 Hub

The hub supports the three rotor blades via the blade bearings and connects them to the generator.

The connections between the blades and hub, as well as the generator-hub connection are flange

bolt connections. The hub is optimized for size and weight and is made of casted iron (EN-GJS-400-

1 BU-LT I GGG 40.3). Additionally, the pitch system, including the pitch motor, gear box, control box,

and the nose cone support structure are integrated into the hub.

3.3 Pitch System

The pitch system is responsible for adjusting the pitch of the three blades. As the blades are pitched,

the angle of attack of each blade is changed, either increasing or decreasing the lift force over the

blades. All three blades are controlled collectively, with each blade acting independently.

The following components and connections are contained in each system.

1. Slew Bearing

2. Pitch Control Cabinet

3. Induction Motor

4. Gear Box

5. Casted Hub

6. Tooth Belt

Figure 2 Pitch system and rotor

Preserving Blue Skies and White Clouds for the Future Page4 of 14

Exhibit DAW-DPE-3 Page 23 of 53

�GOLDWINO Rev.:B-LM Document No.: GW-O?FA.0096

The blade is connected to the hub via a slew bearing. This is a double row ball bearing that allows the

blade to rotate around its longitudinal axis with minimal friction.

Motion is actuated by a 3-phase induction motor. The simple design of induction motors means the

system is reliable with minimal maintenance requirements. The motor is equipped with an

independent cooling fan and a motor brake on the second end.

The output of the motor is connected to a 3-stage planetary gear box.

A reinforced tooth belt transfers the output from the gear box pinion to the outer ring of the blade

bearing. This pre-stressed tooth belt adjusts the pitch angle with superior accuracy and no backlash.

High stiffness composite material ensures minimal elongation over time. The ease of interchanging

belts, and the lack of a need for lubrication, keeps costs at a minimum. The belt system used in the

Goldwind 2.2 MW turbine is a patented technology.

The pitch system receives power from the main power supply in the nacelle by means of a slip ring at

the center of the generator-hub connection. The power is rectified to DC to charge the ultra-capacitor

and power the control circuits. The DC source is thus converted to AC to power the induction motor.

Ll------,

L2---...,

L3

MAIN

CONTROL

�------<I AC

'

'

'-+--+---<I AC

24V 13A

PITCH - - - - - - - - - - - - - - - -, CONTROL - - -- - - -,

24V13A 29V 4.5kW

29V 4.5kW

POSITION SPEED

ENCODER

POSITION SPEED

ENCODER

POSITION SPEED

ENCODER

' I

' .

�-------------- ---------- ----- ---------- ---------------------J

L----------------------------------------------------------------�

Figure 3 Pitch Control Electrical Diagram

The three pitch controllers receive identical signals from the main turbine controller and each blade

subsystem responds independent of the other blades. The independent nature of the system means

that if a single blade fails the other two blades can respond to slow the turbine to a safe speed. This is

an inherent safety feature of the pitch system.

A position sensor on the second end of the motor reports the blade position and pitch speed to the

controller. A central pitch controller compares the position of each blade and synchronizes them. A

second position sensor is located on the blade bearing that checks the blade position and

Preserving Blue Skies and White Clouds for the Future Page 5 of 14

Exhibit DAW-DPE-3 Page 24 of 53

�GOLDWIND Rev.:B-LM Document No.: GW-07FA.0096 synchronization with the motor sensor for safety reasons. The desired pitch angle is basically calculated on the difference between the actual generator speed and the desired generator speed. The desired generator speed is derived from the utility power

demand and rotor output. In the event of power loss (i.e. grid failure) the pitch system needs stored energy to re-pitch the blades to a safe position. By placing the ultra-capacitors in series with the power supply, they will always carry a charge, giving immediate action when needed. No change in the operation mode of the pitch system occurs during a voltage drop and "low voltage ride through." In addition, there is no change in operating systems during grid loss. The continuous operation of the ultra-capacitors guarantees the permanent full control and functionality of this storage and safety system. Ultra-Capacitors also have the benefit of a long lifetime and are not largely affected by high and lowtemperatures.

4 PMDD Generator

The generator of the Goldwind 2.2 MW turbine is a multi-pole Permanent Magnet Direct Drive (PMDD) Synchronous type generator.

Integrated Rotor

Bearing

Slip Ring

_ Permanent Ma11nets

,;;;;;;:";;;;;;;;;;;;;;;;;;;;;.;;;;;;;;;==31 Stator· Rotor Alr Gap

Rotor Lock

Generator Rotor

Generator Stator

Figure 4 PMDD Generator

The Permanent Magnet (PM) design maximizes efficiency with no energy loss resulting from magnetic field excitation and no slip rings.

The direct drive (DD) aspect of the turbine means there is no gearbox. As a result, there are no couplings, gearbox oil, oil pumps, cooling, filtering, and gearbox monitoring systems, minimizing components and costs.

The variable speed nature of the generator-converter system means that the aerodynamic efficiency Preserving Blue Skies and White Clouds for the Future Page 6 of 14

Exhibit DAW-DPE-3 Page 25 of 53

�GOLDWIND Rev.:B-LM Document No.: GW-O?FA.0096 of the turbine rotor can be maximized by adapting the rotor speed to the wind speed. The combination of this type of synchronous generator and full load converter, allows the system

theoretically to be able to adapt to the full range of wind speeds from zero to rated output. As a safety measure and for maintenance operations, a hydraulically actuated rotor brake will slow the rotor to a complete stop following the use of the aerodynamic brake if needed. A hydraulic lock then locks the rotor in place. A special design feature of the GW 2.2 MW generator is the external rotor design.

Technical data Outside diameter Air gap between rotor and stator Winding type Slots and Coils Number of phases Rated voltage

4.1 Generator Rotor

4.935 m 7.5mm two layer fractional- slot winding 288 3 phases 690V

Permanent magnets are placed on the inside of the rotor cylinder in 21 blocks of 4 poles, resulting in 84 poles. The magnetic fields of the poles, rotating around the stator coils, produce the voltage in the stator. The rotor (entire rotating section of the generator, shown in red above) is manufactured using casted and welded components. The magnets are fixed to the inside of the rotor cylinder and sealed with high strength glue. Additionally, the magnets are covered by a fiber glass protective layering. The rotor is an external rotor, meaning the rotor rotates around the outside of the stator. Assuming the same diameter of the air gap between rotor and stator, the use of a PM rotor as an external rotor, reduces the total diameter of the generator. This is due to small thickness of the permanent magnets compared to an electrically excited rotor.

4.2 Generator Stator

The generator stator (shown in blue above) is a combination of casted and welded components that support the stator core and the three phase copper winding. The copper winding utilizes rectangular copper wiring, which ensures optimal insulation covering. The stator is fixed to the base frame of the turbine by a bolt flange connection.

4.3 Integrated Rotor Bearing

One large diameter double row taper bearing connects the turbine rotor and generator rotor unit directly to the generator stator. The rotor unit is connected to the inner ring of the bearing and the outer ring is connected to the stator. Using this type of bearing, the shaft is reduced to a ring, which provides stiffness to the bearing. This allows the generator to be compact and light weight. The large opening of the bearing allows for direct and easy access to the hub for service personnel.

4.4 Active Cooling System

The closed loop active cooling system cools the generator with two air to air heat exchangers located in the back of the nacelle.

Preserving Blue Skies and White Clouds for the Future Page 7 of 14

Exhibit DAW-DPE-3 Page 26 of 53

�GOLOWIND

Air From

Generator

Air .From

Generator

Rev.:8-LM

..

Document No.: GW-O?FA.0096

Heated Ambient

Air Exaust

_.. To Nacelle

Ambient Air

Figure 5 Heat Exchanger

Cooled air from the two heat exchangers is blown into the nacelle, which thus passes into the

generator through filtered vents. Heated air exits the generator via four air collection tubes and then

travels back to the two heat exchangers, thus closing the loop.

Within the flat plate heat exchanger, a separated cooling loop cools the heated air from the

generator. This isolates the air from the outside environment. Speed controlled fans regulate the

active cooling system according to the temperature of the generator. The nacelle is sealed from the

outside environment, keeping harmful moisture and dust out of the cooling system. This protects the

generator and systems located in the nacelle.

As cool air enters the generator it passes over the copper coils and travels into the stator-rotor air gap.

Air thus passes over the permanent magnets as it travels into the radial cooling channels. The novel

use of radial cooling channels within the stator laminations ensures that heat is removed efficiently

from all active components in thegenerator.

Preserving Blue Skies and Whtte Clouds for the Future Page 8 of 14

Exhibit DAW-DPE-3 Page 27 of 53

�GOLOWIND Rev.:B-LM Document No.: GW-O?FA.0096

Figure 6 Airflow though the generator

In addition to the active cooling system, the permanent magnets are cooled passively due to the

external rotor configuration. Ambient air flows over the outside of the rotor, cooling the magnets

inside.

This cooling system guarantees that the magnets cannot be demagnetized. The occurrence of

demagnetization depends on a combination of high temperatures and large magnetic fields. A

maximum magnetic field can be produced by a short circuit in the stator. The cooling system of the

turbine always keeps the temperature of the magnets so low, that a short circuit in the stator cannot

result in the rotor being demagnetized.

5 Nacelle

The nacelle is an enclosure that sits atop the tower. It is made of three parts; a base frame, a

walkable platform, and a fiberglass cover.

The base frame is connected to the axle (generator stator) by· a vertical flange and to the yaw system

by a horizontal flange. It is responsible for transferring all loads from rotor to the tower and is

manufactured using casted iron (EN-GJS-400-1 BU-LT I GGG 40.3).

The platform is fixed to the base frame; it provides an area for maintenance personnel and for the

systems that are housed in the nacelle.

The fiber glass cover protects the systems inside the nacelle. As a part of the generator cooling

system it seals the air inside against the outside environment.

The nacelle houses the yaw system, hydraulic system, heat exchangers, auxiliary crane and the so

called top boxes, which includes several electrical components, like the power supply and circuit

breakers for the subsystems in the nacelle and rotor hub.

The meteorological equipment, anemometer and wind vane, and hazard beacons (Upon Request)

are place on top of the cover.

Preserving Blue Skies and WMe Clouds for the Future Page 9 of 14

Exhibit DAW-DPE-3 Page 28 of 53

'1i=GOLDWIND Rev.:B-LM Document No.: GW-O?FA.0096

5.1 Yaw System

The yaw system turns the rotor / turbine head into the wind and adjusts its position as the wind

direction changes. The wind direction is monitored by a wind vane on the nacelle cover, which sends

a signal to the turbine controller to yaw the nacelle as the wind direction changes.

Induction Motor

Base Frame

-- Slew Bearing Outer Ring BrakeDlsk -

Hydraulic Brakes ---1-------

-

----

� Gear Pinion

Tower Top Flange

Figure 7 Yaw System

The system consists of a fixed system and a rotating system (blue). The fixed system includes the

tower top flange (tower), static brake disk, and outer slew bearing ring, which are all bolted to the

tower. The rotating system contains all components bolted to the base frame of the nacelle. This

includes four induction motors, a number of hydraulic brakes, and the inner ring of the slew bearing.

The induction motors are connected to a four stage planetary gear box. The output of the gear box

drives a pinion aligned with the toothed outer ring of the slew bearing. The motors apply the actuation

force to yaw the nacelle as the wind direction changes.

Hydraulically actuated brakes, located to the inside of the base frame and tower, apply pressure to

the brake disk to keep the turbine head from yawing. Additionally, motor brakes at the second end of

the induction motors add brake torque. During yawing, several brakes are released, while others

keep pressure to eliminate backlash between the gears, which could be induced by wind gusts.

After several full rotations, the turbine will return to its original position to untwist the power and data

cables that run from the nacelle to the base of the turbine.

Preserving Blue Skies and White Clouds for the Future Page 10 of 14

Exhibit DAW-DPE-3 Page 29 of 53

�GOLOWINO Rev.:B-LM Document No.: GW-O?FA.0096

6 Tower

The tower is manufactured using high strength steel in three to five sections, depending on the overall

tower height. Each section contains an inner flange on each end for connecting the segments. The

bottom tower section is bolted to the foundation and the subsequent sectionsare bolted on top.

Towers are equipped with a ladder and safety rail. Upon request an assisted climbing system or an

elevator can be included for maintenance access to the nacelle. Emergency lighting and platforms

are installed throughout the tower in regular intervals.

7 Foundation

The foundation is made of reinforced concrete with an embedded "foundation steel section". A flange

on the top of the foundation steel section connects the first tower section to the foundation.

Standard foundations are designed for each rotor diameter, tower height and wind class of the GW

2.2 MW turbine that meet different standards and a variety of environmental conditions. However,

local standards, soil conditions and other environmental conditions vary considerably from place to

place and it is necessary to design a site specific foundation. Goldwind works together with local civil

engineering firms with the specific local knowledge to design these foundations.

8 Electrical Systems

8.1 Converter

The GW 2.2 MW variable speed system is based on the combination of the PMDD synchronous

generator and the full power IGBT (Insulated Gate Bipolar Transistor) frequency converter. It allows

the generator to operate at the optimized rotor speed from cut in to cut out. Variable frequency AC

power from the generator (linear to the generator rotational speed} enters the converter, and is

converted to match the grid frequency, whether it is SOHz or 60Hz. The converter thus decouples the

generator frequency from the grid frequency. The converter system has its own controller unit (CPU),

separate from the turbine controller.

Preserving Blue Skies and White Clouds for the Future Page 11 of 14

Exhibit DAW-DPE-3 Page 30 of 53

�GOLOWIND Rev.:B-LM Document No.: GW-O?FA.0096

GENERATOR SIDE BREAKER

ACTIVE RECTIFIER (IGBT)

GRID SIDE UTILITY BREAKER MEASUREMENT

MAIN I DC LINK

GRID SIDE INVERTER

(IGBT) GRID SIDE FUSES I TRANSFORMER

LC-FILTER

AC�

_�DC DC�

-�AC

J

CHOPPER HIGH VOLTAGE PROTECTION

(LVRT)

POWER SUPPLY SUB SYSTEMS

I

I I LC-FILTER

� I �--------� �--------____, I �

NACELLE I

INSIDE TOWER I

OUTSIDE

TOWER

Figure 8 GW 2.2MW Electrical Diagram

The three phase power output from the generator enters an IGBT active rectifier that converts the AC

generator output to DC. An IGBT inverter then converts the DC back to AC at the required grid

frequency and supplies a sinusoidal current. The microprocessor controlled power electronics (IGBTs)

allow the system to be adapted to various grid requirements by software adjustments.

The DC-Link and capacitor are responsible for maintaining the balance between the generated and

output power. If the grid doesn't take the output of the rectifier (ex. grid fault), there will be a voltage

increase in the DC link. To protect the IGBT modules and to allow the turbine to stay connected to the

grid, for example during a "low voltage ride though" (LVRT), the high voltage protection circuit will limit

the excess voltage by dumping the load through a resistor.

Harmonic filters are located on the generator and the grid side of the converter. They support the

overall power quality of the system and ensure grid standards are met. Fuse boxes and circuit

breakers are able to disconnect the generator and converter from the grid.

To meet any present grid requirement and most future grid requirements the PMDD - full converter

system is a perfect base to be adapted, solely by software modifications.

The converter, located at the base of the tower, is a modular system that can be easily serviced.

The power supply to the subsystems in the turbine is taken directly from the grid. This includes the

power supply for the main controller, which is backed up by an uninterruptable power supply (UPS).

8.2 Main Turbine Transformer

The transformer is located downstream to the converter and transforms the low voltage output of the

turbine to medium voltage level. The standard is to place the transformer outside of the tower;

however, it can be placed inside as well.

Preserving Blue Skies and White Clouds for the Future Page 12 of 14

Exhibit DAW-DPE-3 Page 31 of 53

�GOLDWIND Rev.:B-LM Document No.: GW-O?FA.0096

9 Turbine Controller

The turbine controller manages all functions and sub controllers of the turbine; it optimizes the loads

and energy output, depending on utility and customer demand.

GENERATOR

PITCH 1

PITCH 2

PITCH 3

,. ,.

DC AC

J

L - - .!-_----------,,

HYDRAULIC

SYSTEM

,1

:: ,' ,,

::,,,,,, ,, ,, ,,,,,,,' ,' ,,

CONVERTER CONTROLLER

Power

v ar1d I p1d Speed Temp. Torque Power factor crs STS IV) (A) (rpm) ('C) (Nm) (kW) (d•II tdic••Q Ide I)

L - - - : :_-_-_-::��i{{��-�-�-{._:._:._{:.:.:.L - _ j...... ,,.

&_-__ -- ---- -- --,•,11•,1, ,., ... ,.,

,---...U..-"""""-----�

CTS(dJaiUQ � J, STStdJaiUQ �..J YAW SYSTEM

CTS: Control signal (digital signal). e.g. Reset parameters, open/dose valves, etc. STS: State signal {digital signal). e.g. Motors switched on/off, brokers open/dose, etc.

Figure 9 GW 2.2MW Main Controller Diagram

WATER

COOLING

COOLING

SYSTEM

Fan speed (rpm) Temp.("() CTS(d aij STS(d,gltaQ

METEREOLOGY

Spud(m/s}

Dlr•ctfon (d•1) CTS (dfllltaQ

Gen. Speed (rpm)

Powor(kW) CTS (d taQ STStd lll)

SCADA

It receives signals from the converter and pitch sub controllers, as well as data from all sensors within

the turbine, like the anemometer, wind vane, generator speed sensor, temperature sensors, yaw

position sensor, vibration sensors, etc ....

The turbine controller sends commands to the converter and pitch sub controllers, and activates the

yaw system, hydraulic system, etc ....

The main signals are transmitted by a DC-isolated profibus system.

The SCADA system is integrated into the turbine through the main controller. It can both send

commands to the turbine controller and receive data from the controller via the wind park control

system.

The turbine controller is placed at the base of the tower.

Preserving Blue Skies and White Clouds for the Future Page 13 of 14

Exhibit DAW-DPE-3 Page 32 of 53

�GOLDWINO Rev.:B-LM Document No.: GW-O?FA.0096

10 SCADA (Supervisory Control and Data Acquisition)

The turbine can be controlled and monitored externally through the wind farm control system at the

wind farm. The turbine can be monitored by the Goldwind SCADA system via any computer with

internet access.

Both current and historical turbine operating data can be viewed from a SCADA terminal. Various

levels of security exist within the systems, allowing the customer to choose specific access levels.

11 Goldwind121-2.2MW Wind Turbine Technical Data

Table 1 Goldwind121-2.2MW Wind Turbine Technical Data

Technical Data GW121/2200 Power Rated Power 2200 kW

Cut-in Wind Speed 3 m/s

Rated Wind Speed 8.9m/s

(Static)

Cut-out Wind Speed 22 mis (10-minute Average)

Operating Temp.* -30"C to 40"C

Standby Temp.* .4o·c to so·c

Rotor Diameter 121 m

Number of Blades 3

Swept Area 11329 m2

Blade Pitch Control Power Control

Hydraulic Disk Brake for Yaw system

Rotor Lock (for maintenance only)

Safety System Generator Permanent Magnet Direct Drive Synchronous Generator

Rated Voltage 690 V

Yaw System 4 Induction Motors

Tower Tubular Steel Tower

Hub Height 90m

Foundation Anchor Bolts Foundation

Converter Full Scale Converter (IGBT Modules)

Transformer Input Voltage 690V

Output Voltage 33kV (Others Possible)

Control System Microprocessor Controlled, DFO (SCADA)

Design Standard IEC 1118 or below

*According to IEC standard, the Operating Temp. Range is -1o·c to 40"C and Standby Temp. Range is -2o·c to so·c. However,

Goldwind product could extend these ranges larger as shown on the table thanks to good wind turbine performance.

Preserving Blue Skies and White Clouds for the Future Page 14 of 14

Exhibit DAW-DPE-3 Page 33 of 53

APPENDIXD

Circuit Map

17

Exhibit DAW-DPE-3 Page 34 of 53

-.

I

I I

I

I

I I

I

,,_.,., CKT 2 /

WEST &ljARLESTON

SUBSTATION 5.0/7.0 t.4VA 46/12.47KV "l

DAIRY AIR

HOLLAND

2 ACSR

DRAWN: ORC

Vermont Electic Cooperative Johnson, Vermont

DAIRY AIR HOLLAND

Appendix D DWG. No. I

LOCATION: HoHand. �ant

CHECKED: APPROVED:

SCALE: NONe °"TE: B/31/16 SHEET I of 1

Exhibit DAW-DPE-3 Page 35 of 53

APPENDIXE

PSB Rule 5.505

18

Exhibit DAW-DPE-3 Page 36 of 53

Effective: September 10, 2006 Vermont Rule 5.500

Public Service Board Page 6-8 of 21

5.505 Fast Track Screening Process

(A) Within 15 business days after the Interconnecting Utility notifies the Interconnection

Requester it has received a complete Application, the Interconnecting Utility shall

perform a review of the Application under the Fast Track Screening Criteria set forth

below, shall notify the Interconnection Requester of the results, and shall include with the

notification copies of the analysis and data underlying the Interconnecting Utility's

determinations under the Fast Track Screening Criteria.

(B) Fast Track Screening Criteria

(1) The Interconnection Requester's proposed Generation Resource meets the

applicable codes and standards of Section 5.510 or is a certified equipment

package under Section 5.511.

(2) The proposed interconnection point is not at transmission voltage (i.e., not over 23

kV line to line or 13.28 kV line to neutral).

(3) For interconnection to a Radial Feeder, the aggregated generation, including the

proposed Generation Resource, on the circuit will not exceed 15% of the line

section annual peak load as most recently measured at the substation. A line

section is that portion of a distribution system connected to a customer bounded

by Automatic Disconnect Devices or the end of the distribution line.

(4) The aggregated generation, including the proposed Generation Resource, on a

distribution circuit will not contribute more than 10% to the distribution circuit's

maximum fault current at the point on the high voltage (primary) level nearest the

proposed interconnection point.

(5) The aggregated generation, including the proposed Generation Resource, on a

distribution circuit will not cause any distribution protective devices and

equipment (including, but not limited to, substation breakers, fuse cutouts, and

line reclosers), or customer equipment on the system to exceed 85% of the shortcircuit

interrupting capability; nor is the Generation Resource proposed for a

circuit that already exceeds 85% of the short-circuit interrupting capability.

(6) For interconnection of a proposed single-phase or effectively-grounded threephase

Generation Resource where the primary distribution system is three-phase,

four-wire, the Generation Resource will be connected line-to-neutral. For

interconnection of a proposed single-phase or three-phase Generation Resource

where the primary distribution system is three-phase, three-wire, the Generation

Exhibit DAW-DPE-3 Page 37 of 53

Resource will be connected line-to-line.

{7) Voltage drop due to starting the proposed generator is within acceptable limits,

meaning that inrush current, due to starting the proposed Generation Resource up

to once per hour, is not greater than 3% of the available fault current. Voltage

drop due to starting the proposed Generation Resource more than once per hour

meets a tighter inrush-current tolerance, to be determined by the Interconnecting

Utility.

{8) For any single Generation Resource, the available utility short circuit current at

the Point of Interconnection divided by the rated output current of the Genera.tion

Resource is no less than:

{a) 50 for Generation Resources of less than 100 kW;

{b) 40 for Generation Resources from 100 kW to less than 500 kW; and

{c) 20 for Generation Resources equal to or greater than 500 kW.

(9) Aggregate generation, including the Generation Resource, on a circuit will not

exceed 2 MVA in an area where there are known or posted transient stability

limitations to generating units located in the general electrical vicinity {e.g., three

or four busses from the point of interconnection).

{10) No System Upgrades, in excess of limited preparations that do not necessitate a

Facilities Study, are required to facilitate the interconnection of the Generation

Resource.

{11) For interconnection of the proposed Generation Resource to the load side of spot

network protectors, the proposed Generation Resource utilizes inverter-based

equipment and aggregate generation, including proposed Generation Resource,

will not exceed the smaller of 5% of a spot network's maximum load or 50 kW.

Synchronous generators cannot be connected to a secondary network.

{12) If the Generation Resource is to be connected on a shared, single-phase secondary,

aggregate generation capacity on the shared secondary, including the proposed

generation, will not exceed 20 kV A.

{13) If the Generation Resource is single-phase and is to be interconnected on a center

tap neutral of a 240 volt service, its addition will not create an imbalance between

the two sides of the 240 volt service of more than 20% of the service transformer

nameplate.

Exhibit DAW-DPE-3 Page 38 of 53

APPENDIXF

Substation Load Duration Curve

19

Exhibit DAW-DPE-3 Page 39 of 53

MW

0 0 � � N N w .

0 u, 0 u, 0 u, 0

0 0 0 0 0 0 0

0 0 0 0 0 0 0

1

464 V,

927 C

1390 "' r+

1853 QJ

2316 r+ -·

2779 0 ::,

3242

3705 0

4168 QJ

4631 C.

5094 C

5557 C -,

6020 QJ r+

6483 -·

0 6946 ::,

7409 n 7872 C

8335

Exhibit DAW-DPE-3 Page 40 of 53

APPENDIXG

IEEE 154 7 2014 Amendment

20

Exhibit DAW-DPE-3 Page 41 of 53

IEEE Standard for Interconnecting Distributed Resources with Electric Power Systems

Amendment 1

IMPORTANT NOTICE: IEEE Standards documents are not intended to ensure safety, security, health, or environmental protection, or ensure against interference with or from other devices or networks. , Implementers of IEEE Standards documents are responsible for determining and complying with all appropriate safety, security, environmental, health, and interference protection practices and all applicable laws and regulations.

This IEEE document is made available for use subject to important notices and legal disclaimers. These notices and disclaimers appear in all publications containing this document and may be found under the heading "Important Notice" or "Important Notices and Disclaimers Concerning IEEE Documents." They can also be obtained on request from IEEE or viewed at http://standards.ieee.orgRPRldisclaimers.html.

NOTE-The editing instructions contained in th.is <amendment/corrigendum> define how to merge the material contained therein into the existing base standard and its amendments to form the comprehensive standard.

The editing instructions are shown in bold italic. Four editing instructions are used: change, delete, insert, and replace. Change is used to make corrections in existing text or tables. The editing instruction specifies the location of the change and describes what is being changed by using strilEelbe1:1gh (to remove old material) and underscore (to add new material). Delete removes existing material. Insert adds new material without disturbing the existing material. lnsertions may require renumbering. If so, renumbering instructions are given in the editing instruction. Replace is used to make changes in figures or equations by removing the existing fib'llre or equation and replacing it with a new one. Editing instructions, change markings, and this NOTE will not be carried over into future editions because the changes will be incorporated into the base standard.

Copyright© 2014 IEEE. All rights reserved.

! (1) -, .... Q) ..... ..... .... n en :, (/) (1) 0..

,+ 0

0 Q) :, .... ro ..... n -, g """(1) .+

..... .... n (1) :, (/) (1) (1)

C: (/) en

g .....

IC

n 0 "O IC -, .... "" :r ,+ (1) 0..

Q) :, C.

:i,

� :r 0 -, .... N (1) C.

C" IC

"!:? (/) ,+ -, .... n .+ .... 0

i;l :i, "O "O

:E

Exhibit DAW-DPE-3 Page 42 of 53

Change Clause 2 as follows:

2. Normative references

ANSI C84.l-2011+9%, Electric Power Systems and Equipment-Voltage Ratings (60 Hz).

4. Interconnection technical specifications and requirements

4.1 General requirements

4.1.1 Voltage regulation

Change 4.1.1 as follows:

The DR shall eat aetiYely Feg11late the Yelt&ge et the PCC. Coordination with and approval of. the area EPS and DR operators, shall be required for the DR to actively participate to regulate the voltage by changes of real and reactive power. The DR shall not cause the Area EPS service voltage at other Local EPSs to go outside the requirements of ANSI C84.l-20J l .J.-9%, Range A.

4.2 Response to Area EPS abnormal conditions

4.2.3 Voltage

Change 4.2.3 as follows:

The protection functions of the interconnection system shall detect the effective (rms) or fundamental frequency value of each phase-to-phase voltage, except where the transformer connecting the Local EPS to the Area EPS is a grounded wye-wye configuration, or single-phase installation, the phase-to-neutral voltage shall be detected.

When any voltage is in a range given in Table I, the DR shall cease to energize the Area EPS within the clearing time as indicated. Under mutual agreement between the EPS and DR operators. other static or dynamic voltage and clearing time trip settings shall be permitted. Clearing time is the time between the start of the abnormal condition and the DR ceasing to energize the Area EPS. For DR less than or equal to � 300 W in peak capacity, the voltage set points and clearing times shall be either fixed or fieldadjustable. For DR greater than � 300 W, the voltage set points and clearing times shall be fieldadjustable.

The voltages shall be detected at either the PCC or the point of DR connection when any of the following conditions exist:

a) The aggregate capacity of DR systems connected to a single PCC is less than or equal to 30 kW,

b) The interconnection equipment is certified to pass a non-islanding test for the system to which it isto be connected,

2

Copyright© 2014 IEEE. All rights reserved.

n 0 'C "' -, .... "" ::r ,+

� al � .... Ol ....

.... .... n

(/) ro a.

,+ 0

0 a, :, .... ro ....

n

g 1<'

g N 0 ...

"'

0 � �

.... .... n ro :, (/) ro ro

C: (/) ro

g ...."'

n 0 'C "' -, .... "" ::r ,+

ro a.

a, :, a.

:J> C: ,+

::r

Sl .... N ro a.

er "' H ,..,,..,,..,

ii? (/) ,+

-, .... n ,+

.... 0 :, (/)

:J> 'C 'C ...."'

Exhibit DAW-DPE-3 Page 43 of 53

c) The aggregate DR capacity is less than 50% of the total Local EPS minimum annual integrated

electrical demand for a 15 minute time period, and export of real or reactive power by the DR to

the Area EPS is not permitted.

Delete the current Table 1 as follows:

Table 1 IRtersoRRestioR system respoRse to abRormal voltages

Veltsge Nnge Cleent1g time(s)"

(% eJ hese .,.eltsge1

� �

S9 � ¥..::. 88 �

irnc:.¥..::.rw 4-,00

¥ � 1;!9 �

-Be:se veUages !l:fe the Aemiea! systeffl 1,·eltages states ifl ,"L"1SI C84. I 1995, Table l.

·�. 3Q lcW, m�ciRUIR� ele&riRg times; DR> 391cV,', Elefmilt ele&riRg times.

Insert a new Table 1 as follows:

Table 1-lnterconnection svstem default response to abnormal voltages

Default settings•

Voltage range(% of Clearing time Clearing time: adjustable up to and

base voltagei (s) including (s)

V<45 0.16 0.16

45<V <60 l 11

60<V <88 2 21

110 <V < 120 I 13

V> 120 0.16 0.16 8 Under mutual agreement between the EPS and DR operators, other static or dynamic voltage and clearing time trip settings shall be permitted b Base voltages are the nominal system voltages stated in ANSI C84.1-2011, Table I.

3

Copyright© 2014 IEEE. All rights reserved.

(") 0 "C IC -, .... OQ

;! �

ffl .+

� .... Q) ,-

,­..... n (1) :, "' (1) Cl.

,+ 0

ai' :, .... (1) ,-

n -, g ><" (1) ,+

0 :,

N 0 ...."'' 0

� 0 a,

,­.... n

� "' n, (1)

C: V) (1)

g,­IC

n 0

;g -, ..... 0Q. :,­,+ (1) Cl.

Q) :, C.

;p C: ,+

5 -, ..... N (1) C.

C­IC

H rr, rr, rr,

"' (1)

-, .... n ,+ .... 0

iii ;p

"C "C ,­IC

Exhibit DAW-DPE-3 Page 44 of 53

4.2.4 Frequency

Change 4.2.4 as follows:

When the system frequency is in a range given in Table 2, the DR shall cease to energize the Area EPS within #te a pre-set clearing time as indicated. Under mutual agreement between the EPS and DR operators. other static or dynamic frequency and clearing time trip settings shall be permitted. Clearing time is the time between the start of the abnormal condition and the DR ceasing to energize the Area EPS. FeF DR less thaA er l!EjUal te 30 kW ifl 13eak ea13aeit:y, the frequeAey set 13eiHts aHd elearieg times shall be either fi>Eed er field adjustable. Fer DR greater thae 30 kW, the frequeAey set 13eiAt:s shall be field adjustable.

The frequency and time set points in Table 2 shall be field adjustable. Adjustable under-frequency (UF) and over-frequency (OF) trip settings shall be coordinated with the Area EPS operatortieas. DR settings for frequency response shall be coordinated with load shedding schemes of the Area EPS.

As mutually agreed upon by the Area EPS and DR operators, DR shall be permitted to provide modulated power output as a function of frequency in coordination with functions UFL UF2. OF L and OF2. Operating parameters shall be specified when this function is provided.

Delete the current Table 2 as follows:

Table 2 IRteF68RR8Gti8R &y&teFR re&p8R68 te abR8FFRal frequeRGie&

D.R-5ii!e li'.Feq11et1�' Feege (Iii!) Gle11Fi:Rg time(st

� :53g lcW

� �

� �

> 3Q lc1,ll .:; (S9.8 S+.QJ Aeljustaele Q. le te 300

�11Elj11s1:eele set f!eifll)

� �

DR< 3Q kW, !llll!Hfllliffl el@BRRg linies; DR> 3Q kW, Eiefa11lt elear.ng limes.

Insert a new Table 2 as follows:

Table 2--lnterconnection system default response to abnormal frequencies

Default settings Ranges of adjustability

Function Frequency Clearing Frequency Clearing time (s) (Hz) time (Hz) adjustable up to and

(s) includine: UFI < 57 0.16 56-60 10

UF2 <59.5 2 56-60 300

OF1 > 60.5 2 60-64 300

OF2 > 62 0.16 60-64 10

4

Copyright© 2014 IEEE. All rights reserved.

n 0

"C

� .... "" ::T r+ (1) Cl.

� r+

!ll .... Ql .... ........ n (1) :, (I) (1) Cl.

r+ 0

0 Ql :, .... (1) .... n

g .,,.. ro r+

g "' 0 ...

"'' 0 "' '

0 CD

.... � ........ n (1) :, (I) (1) (1)

C: (I) ro

0 :, ....

IC

n 0 "C IC , ..... "" ::T r+ ro Cl.

Ql

5. :I> C: r+

� .... N (1) Cl.

CT IC

,., ro

!:i , ....n r+ .... 0 :, (I)

:I> "C "C .... IC

Exhibit DAW-DPE-3 Page 45 of 53

APPENDIXH

Fast Track Screening

21

Exhibit DAW-DPE-3 Page 46 of 53

Fast track screening review for the Dairy Air Wind project, Holland, Vermont.

Date of Interconnection Application Received: 6-18-16

P a g e 11

6-21-16 - by: Dean R. Denis, PE., Sr. Systems Engineer, Vermont Electric Cooperative, Johnson, Vermont.

Fast Track Screening:

PSB Rule 5.505 provides a list of criteria that allows a project to be processed without a Feasibility Study,

System Impact Study or Facilities Report. To be considered, a project must meet all of the Fast Track

Criteria. The proposed project does meet all 5.505(8) criterion except for criterion (3), (4), (8), and (10),

and is therefore not eligible as a Fast Track application. The Project, as proposed, may have an undue

adverse impact on system stability and reliability. Therefore a system impact study is required.

S.505 Fast Track Screening Process for the Dairy Air Wind project, Holland, Vermont.

Fast Track Screening Criteria

(1) The interconnection requester's proposed generation resource meets the applicable codes and

standards of Section 5.510 or is a certified equipment package under Section 5.511.

The proposed project can meet this standard with their proposed Goldwind, GW121-2.2 turbine.

(2) The proposed interconnection point is not at transmission voltage.

The proposed interconnection point will be at distribution, 12.47kV {GIS pt. 48-1A15, pole 109£1

15L}

(3) For interconnection to a radial feeder, the aggregated generation, including the proposed

generation resource, on the circuit will not exceed 15% of the line section annual peak load as

most recently measured at the substation. A line section is that portion of a distribution system

connected to a customer bounded by automatic disconnect devices or the end of a distribution

line.

The proposed generation is located, electrically, on the VEC West Charleston #48 substation and

the 1A circuit, which has a peak load of approximately 1,377kVA. The up-stream sectionalizing

point and line section where the generator is proposed to interconnect is the 48-1A15 single

phase line fuse located near the intersection of School Road and Valley Road. This single phase

line will be converted to three phases and continued up School Road for approximately one mile

to the site of the generator. The load in this area of point 1C (up-stream) has approximately

400kVA of single phase loads and down-stream of point of 1A15 on Valley Road is 676kVA of

Exhibit DAW-DPE-3 Page 47 of 53

Pa g e 12

three phase loads. Therefore, the 2,200kW generator exceeds 100% of the line section's annual

peak load and fails this criterion. Being located approximately 8. 7 miles from the West

Charleston Substation creates concerns of possible voltage rise at peak generation output and

low loading times. This will need to be analyzed further in a full system impact study.

(4) The aggregated generation, including the proposed generation, on a distribution circuit will not

contribute more than 10% to the distribution circuit's maximum fault current at the point on the

high voltage (primary) level nearest the proposed interconnection point.

The fault current near the point of interconnection on Valley Road is approximately 494 Amps.

Fault current tests per UL 1741 certification indicate that the fault tests to ground, output

current was measured to be 1.1 p.u. (peak) worst case except for a very short duration transient

current spike of 2.7 p.u. (peak) at the moment the fault was initiated during the all three phase

to ground test. During the phase to phase tests, output current measured to be 1.2 p.u. (peak)

worst case except for some very short duration transient current spikes with a maximum of 2.5

p.u (peak). Worst case output current during fault conditions was 1.2 p.u (rms). The very short

duration current spikes observed in both the phase to ground and phase to phase tests were all

less than 0.20 ms. These spikes resulted from discharge of filter capacitors in the phase to phase

AC output filter inside the inverter.1 10% of 494 is 49 Amps; Full load output of 2,200kW

inverters is 102 Amps; 1.2pu of 102 Amps is 122 Amps and represents 122/494 = 25% of the VEC

fault current near the point of interconnection. The proposed inverter based wind projects fail

this criterion.

(5) The aggregated generation, including the proposed generation, on a distribution circuit will not

cause any distribution protective devices and equipment (including, but not limited to,

substation breakers, fuse cut-outs, and line reclosers), or customer equipment on the system to

exceed 85% of the short circuit interrupting capability; nor is the generation proposed for a

circuit that already exceeds 85% of the short circuit interrupting capability.

Please refer to Answer (4) above for explanation of the limited fault current contributions from

inverter based generation. The project meets this criterion.

(6) For interconnection of a proposed single-phase or effectively grounded three phase generator

where the primary distribution system is three phase, four wire, the generator will be connected

line to neutral.

The generator will be connected to a grounded wye 12.47/7.2kV distribution system at three

phase secondary voltages.

1 Advanced Energy, April 23, 2014, implementation of protection to mitigate faults due

to phase faults for 1 OOONX Inverters.

Exhibit DAW-DPE-3 Page 48 of 53

Pa g e 13

(7) Voltage drop due to starting the proposed generator is within acceptable limits, meaning that

inrush current, due to starting the generation up to once per hour, is not greater than 3% of the

available fault current. Voltage drop due to starting the proposed generator more than once

per hour meets a tighter inrush-current tolerance, to be determined by the interconnecting

utility.

The inverters do not require nor produce inrush currents to start. The project meets this

criterion.

(8) For any single generation resource, the available utility short circuit current at the point of

interconnection divided by the rated output current of the generation resource is no less than:

SO for generators of less than lOOkW;

40 for generators from lOOkW to less than SOOkW; and

20 for generators equal to or greater than SOOkW.

The three phase fault current at the point of interconnection is approximately 494 Amps. The

rated output current of a 2,200kW generator is 102 Amps. 494 /102 = 4.8, which is less than the

minimum of 20. The project fails this criterion.

(9) Aggregate generation, including the proposed generator(s), on a circuit will not exceed 2MVA in

an area where there are known or posted transient stability limitations to generating units

located in the general electrical vicinity (e.g., three or four busses from the point of

interconnection).

There are no known transient stability limitations, however the generation resource does exceed

the 2MVA threshold and will be further analyzed in a system impact study.

(10) No system upgrades, in excess of limited preparations that do not necessitate a Facilities Study,

are required to facilitate the interconnection of the generator.

There is not existing three phase distribution conductor to the project location on School Road.

An approximately 1 mile long line extension will need to be built in order to interconnect the

project to the VEC system.

Exhibit DAW-DPE-3 Page 49 of 53

Pa g e 14

(11) For interconnection of the proposed generator to the load side of spot network protectors, the

proposed generator utilizes inverter-based equipment and aggregate generation, including

proposed generation, will not exceed the smaller of 5% of a spot network's maximum load or

SOkW. Synchronous generators cannot be connected to a secondary network.

The generation resource will not be connected to a spot network.

(12) If the generator is to be connected on a shared, single phase secondary, aggregate generation

capacity on the shared secondary, including the proposed generator, will not exceed 20kVA.

The generation resource will not be connected to a shared, single phase secondary.

(13) If the generator is single phase and is to be interconnected on a center tap neutral of a 240 Volt

service, its addition will not create an imbalance between the two sides of the 240 Volt service

of more than 20% of the service transformer nameplate (capacity).

The generation resource will not be single phase or connected on a center tap neutral of a 240V

service.

Exhibit DAW-DPE-3 Page 50 of 53

APPENDIX I

Cost Estimate

22

Exhibit DAW-DPE-3 Page 51 of 53

VERMONT ELECTRIC

Construction Worksheet -2016 C

Member: All 1:arth Kenewables

Project Manager / Engineer: Dean Denis

Below is the estimate for the following project: Morgan Solar - Valley Road

Project Description: Morgan Sdar generator, lhree phase interconnection facilitles, Valley Road, MOl'gan, vr. This cost estimate 11 non-binding. Project will incur adual VEC costs for materials and labor, including overheads. Prepayments req..iired, true up at comP,etion.

Total Labor Hours 776.00 Total Labor $ 79,090.10 Total Transportation Hours 373.00 Total Transportation $ 27,162.99

Material List: 167kVA overhead service transformer SCADA communication path (radio from substation to site

Aluma-Form large transformer duster mount Voltage Regulators - 114.3 kVA 7,620V, 150 A

Direct Charges Three phase load break switch with motor operator Regulator Bv Pass - 15 kV L.i'le meterials - 110 AAAC, misc - m, LAs, brackets, wd, terms, etc (See Materials

SCADA at site Sheet) Secondary CT metering

Station service

Total Materials $ 127,959.50

Total Estimate $ 234,212.59

This is just an ESTIMATE and will reQuire a True-up at time of completion.

SIGNATURES/AUTHORIZATIONS:

Worksheet Submitted By: Date: . .

-- -�-

Project Manager/Engineer : Dean Denis

Member Approved By: Date: ---- �

Member : All Earth Renewables

Work Order#: 0

Member Copy

Exhibit DAW-DPE-3 Page 52 of 53

Dairy Air Wind, LLC

94 Harvest Lane

Williston, VT 05495

Re: Addendum to the Dairy Air Wind Generation Project System Impact Study dated August, 2016

This addendum serves to clarify the details and ensure agreement between the "System Description" in

Section 2 and the "System One-Line Drawing" included as Appendix A of the Dairy Air Wind ("DAW")

System Impact Study ("SIS"). The SIS was prepared by Crocket Engineering on behalf of the Vermont

Electric Cooperative ("VEC"), for the proposed DAW project. The SIS contains discrepancies between the

System Description and the System One-Line Drawing.

The SIS currently includes the following description of the new generation step-up transformer:

"The new generation step-up transformer has been specified with a nameplate rating of 2750 kVA,

12.5GrdY /7 .2 volt wye -690 Delta- 398 grounded wye configuration, and 7% impedance."

In order for the new generation step-up transformer description within the System Description to match

the agreed upon System One-Line Drawing, the description of the new generation step-transformer

should be revised as:

"The new generation step-up transformer has been specified with a nameplate rating of 2750 kVA,

12.5kV Delta - 690/398 V Grounded Wye configuration, and 7% impedance."

This Addendum to the SIS will serve as a revision of the System Description which has been mutually

agreed upon by the DAW project and VEC.

Exhibit DAW-DPE-3 Page 53 of 53