Upload
others
View
6
Download
1
Embed Size (px)
Citation preview
Conservation Voltage Reduction (CVR)
Phillip Anderson P.E.
Engineering Project Leader
Research, Development & Deployment
Presentation Outline
• Background Information on CVR
– CVR Definition
– Voltage Control Theory
– CVR Theory
– Northwest Energy Efficiency Alliance Distribution Efficiency Initiative (DEI) Pilot Study
• Idaho Power CVR Implementation to Date
What is Conservation Voltage Reduction?
By reducing distribution feeder service voltage, Conservation Voltage Reduction (CVR) promises to reduce energy consumption.
What is Service Voltage?
• Voltage at point of delivery (at the meter)
• National Service Voltage Standard (ANSI C84.1) – “Range A” or Normal Conditions: 114 V-126 V
– Allows ± 5% service voltage bandwidth
• All electric devices operate properly
126 Volts
120 Volts
114 Volts
+5%
0%
-5%
National Standard
Typical Urban Feeder
• Typical Urban “Feeder” operates in upper half (120-126 V)
Typical Urban Feeder Voltage Profile
114
116
118
120
122
124
126
0 0.5 1 1.5 2 2.5 3 3.5 4
Serv
ice
Vo
lts
Miles from Substation
Typical Service Voltage
Pre CVR
124 Volts at Substation
120 Volts
Minimum
on Feeder
Voltage Drop Along a Feeder example
http://wiki.powerdistributionresearch.com/index.php?title=File:Voltage_profile_distribution.jpg
Feeder Reality
How do we control Voltage on a Feeder?
Substation Transformer Load Tap Changer (LTC) or Station Voltage Regulator settings
• LTC or Regulator Controller
– Voltage Band Center or Base Voltage
– Voltage Bandwidth (deadband)
– Line Drop Compensation (LDC)
End of Line (EOL) Voltage Control
• Not used by Idaho Power, requires EOL voltmeters, communications and a control system
Why CVR?
Lower voltage by 2-4%
Lower Voltage by 2-4%
1-3% Reduction in: Energy (kWh)
Peak Demand (kW)
Service Voltage
• National Service Voltage Standard (ANSI C84.1)
– “Range A” or Normal Conditions: 114 V-126 V
– Allows ± 5% service voltage bandwidth
• All electric devices operate properly
126 Volts
120 Volts
114 Volts
+5%
0%
-5%
National Standard
Typical Urban Feeder
Urban Feeder
with CVR • Typical Urban
“Feeder” operates in upper half (120-126 V)
• CVR Goal: Operate in lower half (114-120 V)
Typical Urban Feeder Voltage Profile with CVR
114
116
118
120
122
124
126
0 0.5 1 1.5 2 2.5 3 3.5 4
Serv
ice
Vo
lts
Miles from Substation
Typical Service Voltage
Pre CVR
CVR
124 Volts at Substation
120 Volts
Minimum
on Feeder
120 Volts at
Substation 116 Volts
Minimum
on Feeder
What are the challenges of implementing CVR?
• Voltage drop along a feeder may limit potential CVR feeder candidates
• Substation and feeder design/configuration may limit potential CVR candidates
• Ensure the “first customer” as well as the “last customer” are within voltage limits (114-126 volts)
• Complicated feeder layouts make determination of the EOL challenging
• Lots of modeling and load flow analysis and monitoring are necessary
2007 Pilot Study
• Northwest Energy Efficiency Alliance – Distribution Efficiency
Initiative (DEI)
• Lowered Voltage at one substation (Boise Sub) ~ 3%
• End of line feedback • 24 hrs on, 24 hrs off • Results: 1.5% - 2.5% Energy reduction
(kWh) 1.8% - 2.6% Demand reduction
(kW)
NORTHWEST ENERGY EFFICIENCY ALLIANCE DISTRIBUTION EFFICIENCY INITIATIVE PROJECT FINAL REPORT
CVR Data – DEI Pilot Study
NORTHWEST ENERGY EFFICIENCY ALLIANCE DISTRIBUTION EFFICIENCY INITIATIVE PROJECT FINAL REPORT
BOIS T134 Demand (kW) Reduction
NORTHWEST ENERGY EFFICIENCY ALLIANCE DISTRIBUTION EFFICIENCY INITIATIVE PROJECT FINAL REPORT
CVR Energy Reduction
Where does the 1.5 to 2.5 % CVR energy reduction come from (for voltage reduction only)?
• End User: 80% - 90%
• Power System Efficiency Gains: 10% - 20%
Direct benefit for customers:
For typical 1000 kWh/month residential customer:
• Reduce 90-180 kWh/year
2009 CVR at Idaho Power
• Reviewed over 600 feeder circuits for CVR potential – 264 feeder circuits in 81 substations were potential candidates – 30 feeder circuits selected based on extensive load flow analysis
• Implemented CVR at 6 Substations (30 feeder circuits) – 4 in Boise area – 1 in Nampa area – 1 in Pocatello
• ≈29,600 customers • ≈160 MW peak demand • Modified settings in substation transformer equipment • Expenses:
– Engineering studies – Technician time to change substation settings
Load Tap Changer (LTC) Line Drop Compensation settings changes
Typical Substation Transformer LTC Settings
• Base V = 122 volts
• Bandwidth = 3 volts
• R = 2 volts
New CVR Substation Transformer LTC Settings (9
transformers at 6 substations)
• Base V = 118.8 to 119.7 volts
• Bandwidth = 3 volts
• R = 3 to 6 volts
2010/11 CVR at Idaho Power
• Re-examined 69 feeder circuits of the 264 candidates using new load data
– 9 feeder circuits showed promise based on extensive load flow analysis for being potential CVR candidates
• Reviewed feeder circuits for potential candidates with minimal circuit upgrades
– 4 potential CVR candidates identified
• Not yet implemented
Review
• Distribution feeder voltage
• CVR
• DEI study
• Idaho Power CVR to date
Questions?