6/17/081
Undulator Travel and Girder Assembly
Undulator commissioning
Translation limitsInterferenceThe plan
David Schultz
D. Schultz
FAC Review [email protected]
6/17/082
Undulator Commissioning
We adopted the plan that initial Undulator beamline commissioning to the electron dump would be done without Undulator magnets on the girders.
1. Commission the line at 30 Hz with minimal risk to
the Undulator magnets.1. Commissioning includes the BLM MPS system.2. Commissioning includes BBA.3. Install 2 Undulator magnets per shift when
ready.
D. Schultz
FAC Review [email protected]
6/17/083
Undulator Translation Stops
In-position limits: (current plan)7.0 mm hard stop6.5 mm emergency shut-off6.0 mm reversing switch5.75 mm PV limit (software)(0.0 mm = nominal beam center)
±2.5mm good field region requires >3.75mm clearance
D. Schultz
FAC Review [email protected]
6/17/084
Undulator Vacuum Interference
Estimate ~2 mm clearance,2.0-1.25 mm usable range.
D. Schultz
FAC Review [email protected]
6/17/085
Girder Assembly
Girder assembly is under way.We need to set the stops on the girders now.Any Undulator is mountable on any girder.
Plan:Set all girders’ stops to the values on
slide 3Re-shim all undulators for full travel ~24 Undulators RFI by 3/1/0933 Undulators RFI by 6/1/09