Upload
charles-underwood
View
219
Download
4
Tags:
Embed Size (px)
Citation preview
CSIRO Astronomy and Space Science
Technologies for Radio Astronomy
Tasso TzioumisAssistant Director – EngineeringJune 2015
Mark BowenGroup Leader – Front End Technologies
(From last ATUC meeting)
• ASKAP & SKA: Core business of the Engineering Program.• Most of the program’s people and effort at present.
• Development projects for all ATNF facilities. Depends on budgets.
• Strategic developments – develop capabilities.• External contracts help to maintain capabilities.• Broad directions largely unchanged (June 2015)
Directions for ATNF Engineering
ATUC 2 June 2015
Available resources & allocations• After CSIRO restructure (refer last AUC report, Nov 2014)
• Lost: ~9 positions via attrition and redundancies.• ~ 42 FTE total remained in Technologies
• Since Nov 2014:• Lost: 1 senior digital engineer + 1 retirement
• Have permission to replace - underway• Gained: ~2 FTE short-term contracts – ASKAP production
• Some recruitments in progress.
• Overall largely unchanged! But will grow into next FY.
• ASKAP : ~ 22 FTE Ongoing commitment• SKA: ~ 11 FTE Re-structuring after SKA re-baseline
• More digital group effort? CSP-LOW? Active politicking!!
• Still only ~5 FTE (fragmented) for ALL other projects!!
ATUC 2 June 2015
Staffing – Conferences• SKA CSP meeting – Cape Town March 2015
• SKA Preliminary Design Reviews - Manchester• Document submission Nov – Dec 2014 (~30+ documents/consortium)• Australian Site Infrastructure – Feb 2015• Central Signal Processing (CSP) – Dec 2014 • Signal and Data Transport (SaDT) – Jan 2015• Dish – Feb 2015• Assembly Integration and Verification (AIV) – Feb 2015
• Special session on SKA in ICASSP conference (Brisbane April 2015)• ”Signal Processing Challenges for the Square Kilometer Array”• John Bunton presented invited paper on “SKA CORRELATORS AND BEAMFORMERS”• 4 Participants from Digital group Very valuable networking
• SKA-Dish related visits to Manchester
• AT-RASC (URSI regional meeting), May 2015.• ASKAP• SKA Survey
• SKA CSP workshop – Penticton Canada (June 2015)
ATUC 2 June 2015
CABB (unchanged since last ATUC)• Last ATUC: Formal CSIRO commitment ceased Sept 2014
• Now ALL tasks covered by post-retirement fellows!!
BUT
• Personal commitment by staff member to continue work on the 16 MHz mode.
• Possible delivery for 16 MHz end 2015?! still the target• No horizon for 4 MHz mode.
• NO CSIRO commitment possible. Facilitate as far as possible.• Some hope that 16 MHz may be completed.
ATUC 2 June 2015
ASKAP Update
ATUC 2 June 2015
• Aaron Chippendale to update in detail
• Still to do:• Phase closure under TOS control• Test zoom modes under TOS control• Tied-array processor for VLBI• Transient buffer for CRAFT
Ultra-wideband Receiver for Parkes• Observed band 700 - 4000 MHz; Tsys < 20K over most of band
• Science: pulsar timing, polarisation, interstellar scattering, dispersion, spectral lines, Galactic continuum, VLBI
• ARC Linkage Infrastructure, Equipment and Facilities grant• $370k awarded for 2015
• Investigators: Bailes, Gaensler, Wyithe, Bhat, Levin, van Straten, Wen, Melatos, Manchester, Hobbs, Kramer, Han
• Institutions: CSIRO, Curtin, MPIfR, Melbourne, Monash, NAO/CAS, Swinburne, Sydney, Western Australia
• Collaboration agreement in development – sign by July 2015
ATUC 2 June 2015
ATUC 2 June 2015
Parkes RFI Spectrum (Sept. 2014)
UWB Receiver Band
Phone (CDMA/3G)
Phone (GSM/3G)
Aircraft
SatellitePhone (3G)
Credit: Dick Manchester, Paul Roberts, Aidan Hotan, Ron Beresford, Brett Preisig
ATUC 2 June 2015
Parkes UWB Feed Design
Credit: Alex Dunning
• Quad-ridge horn with dielectric insert and outer rings
• Feed/OMT and dielectric cryogenically cooled - outer rings at ambient temperature
• Low cross-polarization (< -15 db)
• Beamwidth and focal position almost frequency-independent
ATUC 2 June 2015
Credit: Alex Dunning
Prototype UWB Feed Progress
• Prototype feed development at CSIRO
• New technology MUST test and “retire risk”
• Proof of concept feed testing in June 2015 – Room temperature
ATUC 2 June 2015
Teflon dielectric
Feed Horn Outer rings
ATUC 2 June 2015
UWB Feed Installed in Antenna Test RangeCredit: Alex Dunning
M. Bourne and A. Dunning Installing UWB FeedCredit: Alex Dunning
Technological Challenges• Cryogenic cooling - Materials• Vacuum window• Wideband LNA development• System integration
Cost of UWB system (ARC proposal)
• Total direct costs: ~$1M• Proposal for 50% from Partners & 50% ARC funds
• Shortfall: ~$100k from ARC
• But new partners committed funds at this level.
• Labour effort (from CASS) at ~$1.5M• ~ 6 FTE years effort. Timescale? (~2-3 years?)
• Need to manage limited CASS resources• Existing commitments – ASKAP, SKA, FAST
• FAST ramp-up will slow progress in the short-medium term
• SKA re-baseline limited scope for reallocation of effort?
• Scope to leverage digital developments from ASKAP/SKA work?
• Implications for single digital back-end for ALL Parkes systems!• Broadly on target to develop – subject to resources!
ATUC 2 June 2015
• Feasibility study accepted by NAOC.• Negotiationg with Chinese for full receiver
system design & construction• Challenging delivery deadline: September 2016 • Fully externally funded.• Detailed costing completed.• Contract negotiations under way.
• Strategic relationship with China!• MUST nurture & develop!?
• Resource requirements & conflicts• Recruit/Collaborate/secondment?
FAST – 19 beam 1.3 GHz receiver
ATUC 2 June 2015
ATUC 2 June 2015
ADE PAF and system for MPIfR• Contract for standard ASKAP PAF for Effelsberg telescope.
• Poor RFI environment at Effelsberg – need mods to PAF filtering
• Also for Parkes: Usable spectrum ~1100-1800 MHz (GSM bands below 1 GHz)
SPECIAL SYSTEM
• Single dish PAF system• PAF filter modifications• Modified beamformer outputs• Ethernet output Advanced
• Modifications externally Funded • Strategic use of PAF….
• Commissioning/Early science: Request from MPIfR for Bonn PAF at Parkes
• Advantages:• Attraction of early PAF science at Parkes (~ 1 year)• Showcasing single-dish PAF – more customers (e.g. Jodrell Bank)• Easier to commission/debug PAF• Resources at Parkes from Bonn & others• Demonstrate need for PAF @ Parkes – future funding?• More collaborations & outside resources
• Costs:• Effort to install at Parkes – 2-3 months FTE?• Disruption of Operations at Parkes• Need to maintain Parkes Pulsar effort Rx changes? (costs?)• Commissioning effort (BUT experience very valuable)
• Recommendation:• Benefits outweigh costs??
Bonn PAF at Parkes - Proposal
ATUC 2 June 2015
• Tentative timelines:• Install/Commission: OCT2015 semester?
• Bonn PAF modifications – by Nov 2015?• Parkes preparations: Early in semester – Complete by end 2015?
• Fibre wiring ~ 2 week shutdown?• Other wiring; Racks install; ….
• Install: Dec 2015 – Jan 2016. 2 weeks. Replace MB system for 1 year.• Engineering Commissioning: Jan-Mar 2016
• Science Commission & Scientific Observations: APR2016 semester?• 2-3 engineers/scientists external support
• Germany and Jodrell Bank• Joint CSIRO/MPIfR post-doc
• OCT2016 semester: PAF to Bonn• Re-install MB system at Parkes??• Develop new PAF system for Parkes??
Bonn PAF at Parkes – Proposed Timelines
ATUC 2 June 2015
• Commissioning expected to continue throughout 2015OCT Semester - It will not be possible for proposers to request observations using the PAF.
• Astronomical observing may be possible 2016APR and/or 2016OCT.
• PAF will not be a National Facility instrument: the control software, documentation and available support will not be to National Facility standard.
• Collaborative projects with MPIfR or CASS are encouraged – Only a limited number of observing modes will have been tested and a significant contribution of resources towards firmware or software development is likely to be required.
• Teams wishing to use the PAF for astronomical observing will be required to submit a proposal to the TAC at the regular proposal deadline for the use of National Facility time, explicitly addressing resourcing issues.
• MPIfR are planning to lead a proposal to use the PAF for FRB detection, and will welcome collaborators who can contribute resources to this project.
• To be discussed at this ATUC meeting
Bonn PAF at Parkes – science collaborations(from discussions with MPIfR)
ATUC 2 June 2015
• SKA re-baseline• No SKA1-survey re-focus CSIRO effort• SKA1-dish involvement reduction• PAF AIP to be setup – continue PAF development• some effort available in group? UWB, FAST,…
• SKAO decision in April 2015:• CSIRO to lead SKA1 CSP-LOW (signal processing) More digital effort?
• Correlator and Beamformer – Hardware and Firmware• Contentious decision within CSP consortium• Technical and political discussions on-going
• Closer collaboration with European partners??• CSP Board meeting – 9 June 2015 Final decision?
SKA re-baseline Implications for Technologies program
ATUC 2 June 2015
• ASKAP & SKA: Core business of the Engineering group.• Most of the group’s people and effort at present.• CSP-LOW lead?
• Development projects for all ATNF facilities. Depends on budgets.• UWB Receiver at Parkes• Single-dish PAF at Bonn/Parkes• FAST 19-beam system
• Strategic developments – develop capabilities.
• External contracts help to maintain capabilities.
Summary
ATUC 2 June 2015
Thank youAstronomy & Space ScienceTasso Tzioumis
t +61 2 9372 4350E [email protected] www.csiro.au/cass
Astronomy & Space ScienceMark Bowen
t +61 2 9372 4356E [email protected] www.csiro.au/cass