CoalPro Manual (Column Flotation Cell)

Embed Size (px)

Citation preview

  • CoalPro Column Flotation Cell

    Operating and Maintenance Manual

    Prepared By:

    Canadian Process Technologies Inc. 1636 West 75th Avenue

    Vancouver, B.C.

    Canada V6P 6G2

    Tel: +1 604 264 5610

    Fax: +1 604 264 5555

    Email: [email protected]

    URL: http://www.cpti.bc.ca

    October 2001

  • CPT Inc. CoalPro Operating & Maintenance Manual

    The purpose of this manual is to provide an overall guide to column flotation technology and operation,

    with emphasis on the CoalPro Coal Flotation Column and the SlamJet Gas Sparging System.

    This manual has been divided into seven sections, each dealing with a different aspect of the column

    flotation process, as follows;

    1. Introduction

    2. Column Commissioning

    3. Column Operation

    4. Instrumentation and Control

    5. Troubleshooting

    6. System Maintenance

    7. Collection Zone Theory

    8. Froth Zone Theory

    9. Production Column Testwork

    Companion Manual

    SlamJet Operating and Maintenance Manual

    1. Introduction 2. Components 3. Installation 4. Operation 5. Maintenance 6. Control System 7. Cracking Pressure Adjustment 8. Repair Procedures

  • CPT Inc. CoalPro Operating & Maintenance Manual

    TABLE OF CONTENTS

    1.0 INTRODUCTION ............................................................................................................1

    1.1 DESCRIPTION OF A FLOTATION COLUMN................................................................................1 1.2 SlamJet DESCRIPTION .....................................................................................................3 1.3 GLOSSARY OF COLUMN FLOTATION TERMINOLOGY .................................................................5

    1.3.1 Bias .........................................................................................................................5 1.3.2 Carrying Capacity......................................................................................................5 1.3.3 Difference Wash........................................................................................................6 1.3.4 Displacement Wash ..................................................................................................6 1.3.5 Entrainment ..............................................................................................................6 1.3.6 Flow Conventions ......................................................................................................6 1.3.7 Gas Holdup...............................................................................................................6 1.3.8 Air Sparger ...............................................................................................................7 1.3.9 Superficial Velocities .................................................................................................7

    1.4 TERMS.............................................................................................................................7 1.4 WASH WATER...................................................................................................................8

    2.0 COLUMN COMMISSIONING ........................................................................................9

    2.1 INTRODUCTION ..................................................................................................................9 2.2 COMMISSIONING................................................................................................................9 2.3 AIR SPARGING SYSTEM ......................................................................................................9

    2.3.1 Installation Check......................................................................................................9 2.3.2 Pressurization Check.................................................................................................9 2.3.3 Air System Purge.................................................................................................... 10 2.3.4 Sparger Hose Connections ....................................................................................... 10

    2.4 SPARGER WATER SYSTEM ................................................................................................ 11 2.4.1 Installation Check.................................................................................................... 11 2.4.2 Booster Pump Startup ............................................................................................. 11 2.4.3 Pressure Relief Valve Check..................................................................................... 11

    2.5 WASH WATER SYSTEM .................................................................................................... 12 2.5.1 Installation Check.................................................................................................... 12 2.5.2 Wash Water System Purge...................................................................................... 12 2.5.3 Wash Water System Start-up................................................................................... 12

    2.6 LEVEL CONTROL SYSTEM ................................................................................................. 13 2.7 COLUMN STARTUP........................................................................................................... 14 2.8 NORMAL COLUMN SHUTDOWN........................................................................................... 15

    2.8.1 Initial Procedure ...................................................................................................... 15 2.8.2 Final Procedure....................................................................................................... 15

    2.9 SHORT TERM SHUTDOWN HOURS ..................................................................................... 15 2.10 LONG TERM SHUTDOWN DAYS ..................................................................................... 16 2.11 EMERGENCY SHUTDOWN................................................................................................ 16

  • CPT Inc. CoalPro Operating & Maintenance Manual

    2.12 COLUMN RE-START ...................................................................................................... 16 2.12.1 Re-Pulping.............................................................................................................. 17 2.12.2 Re-Starting Underflow .............................................................................................. 17

    3.0 COLUMN OPERATION................................................................................................18

    3.1 SPARGER AIR.................................................................................................................. 18 3.2 INTERFACE LEVEL ............................................................................................................ 19 3.3 WASH WATER BIAS ......................................................................................................... 19 3.4 REAGENT DOSAGE ........................................................................................................... 20

    3.4.1 Frother ................................................................................................................... 20 3.4.2 Collector................................................................................................................. 21

    4.0 INSTRUMENTATION AND CONTROL ......................................................................22

    4.1 INTRODUCTION ................................................................................................................ 22 4.2 SPARGER PRESSURE......................................................................................................... 22 4.3 SPARGER AIR FLOW......................................................................................................... 22 4.4 COLUMN INTERFACE LEVEL ............................................................................................... 23 4.5 WASH WATER................................................................................................................. 23

    5.0 TROUBLESHOOTING.................................................................................................25

    5.1 PROBLEM HIGH ASH...................................................................................................... 25 5.1.1 Column Problems.................................................................................................... 25 5.1.2 Circuit Problems...................................................................................................... 25

    5.2 PROBLEM LOW YIELD .................................................................................................... 25 5.2.1 Column Problems.................................................................................................... 25 5.2.2 Circuit Problems...................................................................................................... 26

    6.0 SYSTEM MAINTENANCE............................................................................................27

    6.1 INTRODUCTION ................................................................................................................ 27 6.2 COLUMN MAINTENANCE.................................................................................................... 27 6.3 SPARGER MAINTENANCE................................................................................................... 28

    6.3.1 Orifice Wear............................................................................................................ 28 6.3.2 Tip Blockage........................................................................................................... 28 6.3.3 External Scaling...................................................................................................... 28 6.3.4 Sparger Removal for Inspection and Cleaning: ............................................................ 29 6.3.5 Poor Air Distribution................................................................................................. 30

    6.4 COMPRESSOR AND AIR LINES ............................................................................................. 30

    7.0 COLLECTION ZONE THEORY...................................................................................31

    7.1 INTRODUCTION ................................................................................................................ 31 7.2 RESIDENCE TIME.............................................................................................................. 31

    7.2.1 Column Volume....................................................................................................... 32 7.2.2 Gas Holdup............................................................................................................. 32

    7.3 AIR RATE ....................................................................................................................... 33

  • CPT Inc. CoalPro Operating & Maintenance Manual

    7.3.1 Maximum ............................................................................................................... 33 7.3.2 Optimum ................................................................................................................ 34

    7.4 PARTICLE AND BUBBLE SIZE ............................................................................................... 34 7.4.1 Gas Velocity........................................................................................................... 34 7.4.2 Probability of Collection............................................................................................ 34 7.4.3 Solids Carrying Capacity.......................................................................................... 35

    8.0 FROTH ZONE THEORY ..............................................................................................36

    8.1 INTRODUCTION ................................................................................................................ 36 8.2 FROTH CLEANING............................................................................................................. 37 8.3 GAS VELOCITY................................................................................................................ 37 8.4 FROTHER CONCENTRATION ................................................................................................ 39 8.5 SUPERFICIAL BIAS RATE................................................................................................... 39 8.6 SELECTIVITY................................................................................................................... 41 8.7 REFERENCES ................................................................................................................... 42

    9.0 PRODUCTION COLUMN TESTING ..........................................................................43

    9.1 INTRODUCTION ................................................................................................................ 43 9.2 AIR RATE ....................................................................................................................... 43 9.3 WASH WATER BIAS ......................................................................................................... 44 9.4 OPERATING LEVEL ........................................................................................................... 44 9.5 BUBBLE SIZE................................................................................................................... 45 9.6 RESIDENCE TIME.............................................................................................................. 45 9.7 WASH WATER DISTRIBUTOR HEIGHT ................................................................................... 46 9.8 SAMPLING...................................................................................................................... 46 9.9 COLLECTION ZONE DENSITY ESTIMATION ............................................................................. 46 9.10 FROTH ZONE DENSITY ESTIMATION.................................................................................. 47

  • CPT CoalPro Introduction Page 1

    Operating & Maintenance Manual

    1.0 INTRODUCTION

    1.1 DESCRIPTION OF A FLOTATION COLUMN

    The CPT CoalPro Flotation Column is a type of flotation machine that incorporates some unique design

    features to enhance metallurgical performance. Some of these features include:

    Reduced surface area to cell volume ratio to promote froth stability

    Froth washing system to stabilize the froth and to minimize the entrainment of impurities

    Quiescent flotation conditions to promote selectivity and enhance collection

    Adjustable air sparging system to allow control of bubble size

    Circular internal launders to enhance froth stability and minimize loaded bubble travel

    distances, thus increasing recovery, especially of coarse particles.

  • CPT CoalPro Introduction Page 2

    Operating & Maintenance Manual

    Flotation Columns derive their name

    from the geometric shape of the

    vessel. Unlike conventional

    mechanically agitated flotation

    machines which tend to use

    relatively shallow rectangular tanks,

    column cells are tall vessels with

    heights typically ranging from 25 ft

    to 50 ft. The tank cross-section may

    be either round, square or

    rectangular depending on the

    specific application. For an

    equivalent volumetric capacity, the

    surface area of the column cell is

    much smaller than a conventional

    cell. This reduced area is beneficial

    for promoting froth stability and

    allowing very deep froth beds to be

    formed.

    Figure 1 CoalPro Schematic

    Feed

    Air &Water

    CleanCoal

    Tailing

    CoalPro

    SlamJet SlamJet

    Wash Water

  • CPT CoalPro Introduction Page 3

    Operating & Maintenance Manual

    An important feature of flotation columns is the froth washing system. Froth washing provides an

    additional means for removing unwanted impurities from the flotation froth. Wash water, added at the top

    of the column, filters through the froth zone displacing process water and entrained particles trapped

    between the bubbles. In addition, froth wash water serves to stabilize the froth by separating bubbles

    into a packed bed of spherical, and therefore very strong, bubbles.

    Unlike conventional flotation machines, columns do not use mechanical agitation. The absence of

    intense agitation promotes selectivity and aids in the recovery of very coarse particles. The basic flow

    streams in a column are illustrated in Figure 1. Feed slurry enters the column at one or more feed

    points located in the upper third of the column body and descends against a rising swarm of fine

    bubbles generated by the air sparging system. Particles which collide with, and attach to the bubbles,

    rise to the top of the column, eventually reaching the interface between the pulp (collection zone) and

    the froth (cleaning zone). The location of the interface, which can be adjusted by the operator, is held

    constant by means of an automatic control loop which regulates a valve on the column tailings line.

    Varying the location of the interface will increase or decrease the height of the froth zone.

    Flotation air is introduced into an external manifold and is injected through a series of air lances

    (sparger tubes) located near the bottom of the column. The air rate used in the column is selected

    according to the feed rate and concentrate production requirements and will determine, in part, the point

    on the ash / yield curve at which the column operates.

    1.2 SlamJet DESCRIPTION

    CPTs patented SlamJet Model SLJ-75 Air Sparging System, shown schematically in Figure 2,

    comprises air and water manifolds that surround the column cell and supply a mixture of air with a small

    amount of water to a series of SlamJet spargers. The top of the manifold is fitted with connections for

    air as well as connections for a pressure gauge and a pressure transmitter. The side of the manifold is

    equipped with a series of couplings for connecting the water manifold to the air manifold. The bottom of

    the manifold is fitted with a series of recessed couplings for connecting to the sparger tubes and is also

    fitted with one or more drains.

    A small amount of water approximately 2 USgpm per SlamJet is supplied to the water manifold

    using a positive displacement pump. The water manifold is then connected in (typically) four places to

    the air manifold to provide even distribution of water within the air manifold.

  • CPT CoalPro Introduction Page 4

    Operating & Maintenance Manual

    Vessel

    SlamJet

    Check ValveGasManifold

    Optional

    Manifold Support Bracket

    Air Distribution Manifold

    Isolation Valve

    Sparger Water Manifold

    Flexible Hose

    QuickDisconnectCoupling

    Air-ActuatedSelf-AdjustingAuto Shut-off Assembly

    Liquid-Tight Seal

    Full Port Ball Valve

    Replaceable Ceramic WearProtected Injection Nozzle

    Figure 2 SlamJet Model SLJ-75 System

    Air enters the manifold through the connections located on the top of the manifold and exits through the

    series of couplings, (Figure 2) located on the bottom of the header. The manifold is sized to act as a

    buffer against turbulence and to provide sufficient reservoir capacity to ensure even distribution of the air

    / water mixture to all spargers. The volume of the header also provides some opportunity for foreign

    material to settle out.

  • CPT CoalPro Introduction Page 5

    Operating & Maintenance Manual

    The air / water mixture then flows through the connecting hose to the sparger tube and is injected into

    the column through the single ceramic lined orifices of the SlamJets. The number and length of

    SlamJets and the pattern of insertion is designed so as to ensure even distribution of fine bubbles.

    The exact number and size of SlamJets included for each column is specifically designed to provide for

    a maximum superficial gas velocity of 2.5 cm/s. Each SlamJet is attached to the header by a single

    flexible hose fitted with a quick-disconnect coupling to allow for easy removal for inspection or

    maintenance.

    The sparger elements have been designed to allow easy removal from the column. A full port ball valve

    and liquid-tight seal assembly comprises the sparger insertion port, and prevents process slurries from

    exiting the column when the sparger is removed. Each SlamJet is also fitted with a nozzle-mounted

    needle valve which provides air flow control and also provides automatic sealing of the SlamJet nozzle

    prior to removal.

    The quick-disconnect coupling is used to isolate the sparger air flow during removal.

    SlamJet nozzles initially should be checked monthly for fouling and wear. Worn nozzles can be quickly

    and easily replaced while the column is in full operation. The inspection schedule can later be modified

    on an experience basis.

    In some applications it can be advantageous to administer flotation reagents, especially frother, into the

    column along with the sparging air. This technique can result in tighter control of bubble size and can

    also result in a reduction in frother consumption. In such cases, the frother (or other reagent) is added

    with the sparger water, and is thus evenly distributed within the column.

    1.3 GLOSSARY OF COLUMN FLOTATION TERMINOLOGY

    The study of column flotation systems has resulted in new ways of examining flotation and some

    specific terminology has evolved to describe the process. Some of the common terms are:

    1.3.1 Bias

    The term Bias (Superficial bias - Jb) is used to describe the flow of water (magnitude and direction)

    through the froth zone into the collection zone. A positive bias is a net downward flow. It is often

    estimated as the difference between the volumetric flow of the column underflow slurry and the

    volumetric flow of the feed slurry rates divided by the cross-sectional area of the column.

    1.3.2 Carrying Capacity

    Three different carrying capacities have evolved;

  • CPT CoalPro Introduction Page 6

    Operating & Maintenance Manual

    Ca - The maximum overflow mass that a column can produce. This is commonly quoted in terms of

    tonnes of solids per hour per square meter of cross sectional column area ST/hft2 or t/hm2.

    A theoretical value can be estimated from Ca = 0.03 D80 rs.

    Cg - The maximum solids floated per unit of air, commonly expressed in units of kilograms of

    concentrate solids per cubic meter of air lb/ft3 or kg/m3.

    Cl - The maximum mass of pulp that can be transported over the lip of the column, normally

    expressed as tonnes per hour per meter of lip length ST/hft or t/hm. Note that lip length

    must include the length of all internal launders. This figure is critical in the design of large

    columns.

    1.3.3 Difference Wash

    The volume of water in the feed subtracted from the volume of water in the underflow is one difference

    wash. Any wash water added in excess of this amount is assumed to report to the overflow.

    1.3.4 Displacement Wash

    Displacement wash is the ratio of wash water to overflow water. A displacement wash of 1.0 means that

    all the wash water reports to the overflow, while a displacement wash of 2.0 indicates an equal amount

    of the water flow in the bias and overflow streams (assuming no feed water in the overflow).

    1.3.5 Entrainment

    Non-selective flotation caused by particles riding in a bubble's wake and thereby passing into the

    column overflow. Entrainment is common in mechanical cells, particularly with small particles, but is

    virtually eliminated in column flotation by the use of wash water.

    1.3.6 Flow Conventions

    Downward flow of slurry or liquid, and upward flow of air are defined as positive.

    1.3.7 Gas Holdup

    There are three types of holdup in a column reflecting it's three phase nature - solids (mineral), liquid

    (water) and gas (air).

    Gas Holdup (eg) is the fractional volume of gas. A typical value of gas holdup is 0.15 (or 15%) but this value may range between 0.05 and 0.25 (5% to 25%).

    Solids Holdup (es) is the solids fractional volume.

  • CPT CoalPro Introduction Page 7

    Operating & Maintenance Manual

    Liquid Holdup (e l) is the fractional volume of liquid.

    1.3.8 Air Sparger

    Any device used to create the bubbles in a flotation column. The common types are the CPT SparJet

    System, the CPT SlamJet System and various constructions of porous media.

    1.3.9 Superficial Velocities

    Superficial velocity is the volumetric flow rate of the material in question (slurry, water or air) divided by

    the cross sectional area of the column, normally expressed in cm/s. This normalized variable allows

    evaluation of column performance characteristics independent of column diameter.

    1.4 TERMS

    (Units may vary according to local use)

    Cx Carrying capacity where x = :

    a = theoretical bubble loading (ST/hft2 or t/hm2)

    g = loading per gas unit (lb/ft3 or kg/m3)

    l = removal capacity per unit lip length (ST/hft or t/hm)

    e x Holdup (all either fractional or %) where x = :

    g = gas

    l = liquid

    s = solids

    Jx Superficial Velocity where x = :

    b = bias

    o = overflow

    f = feed

    g = gas

    sl = slurry

    u = underflow

    w = wash water

  • CPT CoalPro Introduction Page 8

    Operating & Maintenance Manual

    spa = sparger air

    Qx Mass flow rate, with x values the same as for superficial velocities

    Vx Volumetric flow rate

    r x Density of x = :

    col = bulk, collection zone

    fro = bulk, froth zone

    s = average concentrate solids

    sl = column slurry estimated by using tails density

    u = underflow density

    (l) = liquids fraction

    (s) = solids fraction

    Hc = height of column (ft or m)

    Hf = height of interface (ft or m)

    Hspa = height of spargers (ft or m)

    P = pressure (psi or kPa)

    L = distance from column lip to pressure transducer (ft or m)

    1.4 WASH WATER

    Wash water (Jw) is the water added to clean the froth zone. In positive bias operation this Jw forms both

    the overflow liquid (Jo) and the bias (Jb).

  • CPT CoalPro Column Commissioning Page 9

    Operating & Maintenance Manual

    2.0 COLUMN COMMISSIONING

    2.1 INTRODUCTION

    This section covers column start-up and shut-down procedures and provides estimates of column

    parameters and guidelines for operation. It is intended to familiarize operators with column operation as

    a reference and as a start to determining the column's operational characteristics. The values it contains

    are estimates which must be confirmed in plant practice.

    2.2 COMMISSIONING

    All air and water lines should be carefully and completely purged of tramp material and construction

    trash BEFORE installing instrumentation or connecting to distribution manifolds.

    Perform a walk around to visually check that all piping for slurries, sparger air, sparger dilution water

    and column wash water are in place and properly connected.

    Ensure that all manual and automatic valves are closed.

    COMMISSIONING NOTE:

    Air and water supply lines should be flushed and verified clean PRIOR to the installation of flowmeters

    and control valves.

    2.3 AIR SPARGING SYSTEM

    2.3.1 Installation Check

    Perform a walk around to visually check that all SlamJet spargers are installed in the proper location

    as per Sparger General Arrangement drawings;

    All SlamJet tubes should be pushed fully into the insertion port assemblies.

    Note that the self-adjusting mechanism will ensure that all SlamJets are closed when not pressurized.

    2.3.2 Pressurization Check

    Turn all individual sparger air manifold and sparger water manifold isolation valves OFF (see Figure 2) to

    isolate the header from the spargers.

    Ensure that manual shut-off valves at battery limits of the air supply system are CLOSED.

  • CPT CoalPro Column Commissioning Page 10

    Operating & Maintenance Manual

    If automatic air flow control valves are supplied, stroke the valves in manual and check for full travel and

    correct opening, then return to fully CLOSED position.

    Ensure that air filter, if installed, is clear.

    SLOWLY OPEN the manual air supply shut-off valve. Check for leaks and repair if necessary.

    Ensure that and air supply pressure of 70 psi to 90 psi is available.

    CLOSE the manual air supply shut-off valve.

    2.3.3 Air System Purge

    OPEN the sparger manifold drain valve(s).

    SLOWLY OPEN the manual air supply shut-off valve to purge the air system through the manifold drain

    line(s). Gradually increase the air flow to 100% and purge for several minutes.

    While the system is purging, check the air flow meter to ensure that the flowmeter is operating

    correctly.

    Check emerging air flow for oil contamination.

    OPERATING NOTE:

    It is important that as little oil as possible is present in the air lines. Although small amounts of oil will

    not adversely affect operation of the SlamJets, the presence of oil may interfere with the metallurgical

    performance of the column by causing non-selective flotation. If this is determined to be the case, an oil

    filter will be required.

    When purging is complete, close the manifold drain valve(s) but leave the sparger manifold pressurized.

    2.3.4 Sparger Hose Connections

    With the sparger manifold pressurized to at least 70 psi, SLOWLY OPEN individual sparger manifold

    valves, one at a time. Check for air leaks and ensure that each SlamJet auto-close mechanism opens

    and allows air flow to begin.

    Correct any air leaks and tag any SlamJets that do not appear to be operating correctly.

    Note that commissioning of the column can continue with a few spargers not working.

    Leave all individual sparger manifold isolation valves OPEN, but CLOSE the manual air supply shut-off

    valve. Slowly open a manifold drain valve to de-pressurize the manifold.

    Sparger system commissioning is now complete.

  • CPT CoalPro Column Commissioning Page 11

    Operating & Maintenance Manual

    2.4 SPARGER WATER SYSTEM

    2.4.1 Installation Check

    Perform a walk around to visually check that the sparger water system is correctly installed and piped.

    2.4.2 Booster Pump Startup

    OPEN the sparger water supply shut-off valve and ensure that water is available to the booster pump.

    Note that the booster pump is a progressive cavity pump and the rubber stator will be very quickly

    damaged if the pump runs dry.

    Note that the sparger water system can ONLY be operated when the sparger air system is operating.

    OPEN the sparger air supply shut-off valve and set air flow to provide a manifold pressure of 70 to 80 psi

    using either the automatic flow control valve in manual mode (if supplied) or the manual valve.

    Verify that all spargers are operating and delivering air to the column.

    OPEN all sparger water manual flow control valves, one at a time. Check for system leaks and repair if

    necessary.

    Using the adjustable frequency controller, start the pump at very low speed, and immediately check for

    pump rotation and positive water discharge.

    Note The booster pump is protected by a pressure switch on the pump suction line that will not allow

    the pump to start unless the required minimum water supply pressure is available.

    SLOWLY INCREASE booster pump speed until the sparger water flowmeters indicate a flow equivalent

    to 2 USgpm per SlamJet, and visually confirm that water mist is being expelled from the spargers.

    Note individual SlamJet manifold connections are mounted vertically in the manifold using recessed

    couplings. Water will not reach the spargers until the bottom of the manifold has filled with water to the

    level of the recessed couplings (refer to Figure 2).

    2.4.3 Pressure Relief Valve Check

    The sparger water booster pump is a positive displacement pump, and the sparger system is therefore

    fitted with an emergency pressure relief valve to prevent over-pressure on the system. The relief valve

    should be set to about 10 psi higher than the maximum expected air supply pressure.

    Two people are required to safely perform the pressure relief check. One person should be stationed at

    the local start/stop switch for the booster pump, and the other person is required to close the sparger

    water manual flow control valves to initiate the test. One of these two people should be able to SEE the

    relief valve.

  • CPT CoalPro Column Commissioning Page 12

    Operating & Maintenance Manual

    Ensure that the sparger air system is running and the booster pump is running and delivering water to

    the spargers. With one person stationed at the booster pump local stop, the other person must close

    the flow control valves one at a time. As the last valve is SLOWLY CLOSED, the sparger water system

    should begin to go into an over-pressure condition, and the pressure relief valve SHOULD OPEN to let

    down the pressure.

    If the system pressure begins to exceed the relief valve setting, IMMEDIATELY STOP the booster pump

    or open the flow control valve, then shut down the sparger water system and correct the problem with

    the relief valve.

    2.5 WASH WATER SYSTEM

    2.5.1 Installation Check

    Perform a walk around to visually check that the wash water system is correctly installed and piped.

    2.5.2 Wash Water System Purge

    Purge the wash water supply piping so that no tramp material or construction trash reaches the

    perforated wash water distribution header(s).

    2.5.3 Wash Water System Start-up

    Verify that the wash water flow control valve, either automatic or manual, is CLOSED.

    SLOWLY OPEN the wash water system isolation valve. Check for leaks and repair if necessary.

    SLOWLY OPEN the wash water flow control valve(s) to verify water flow.

    Clear any blocked distributor holes.

    Check for even wash water distribution at low flow. If flow is not even, check that the wash water

    distributor is installed level, and check for partial blockages in the wash water distributor piping.

    CALIBRATION NOTE:

    Calibrate the wash water flow meter (if installed) by timing the filling of the column. If one or more

    pressure transducers are being used for level control, these can be calibrated at the same time.

  • CPT CoalPro Column Commissioning Page 13

    Operating & Maintenance Manual

    2.6 LEVEL CONTROL SYSTEM

    Level sensing is performed either by a mechanical ball float and ultrasonic detector system, or by single

    or dual pressure transducers. Level control is performed either by a local PID controller or a plant DCS.

    The controller receives a level sensor input (4 to 20 mA signal), compares this signal to a setpoint

    established by the flotation operator, and sends a control output (4 to 20 mA signal) to modulate the

    opening of the underflow pinch valve. If, for example, the sensed level rises above the operators

    setpoint, the underflow valve should open slightly to bring column level back down to the setpoint.

    For either the ultrasonic or pressure transducer system, check that the field sensor(s) is reporting a

    level signal, and also insure that the PID controller (or plant DCS) actuates the underflow valve in the

    appropriate manner opens when it should open, closes when it should close.

  • CPT CoalPro Column Commissioning Page 14

    Operating & Maintenance Manual

    CALIBRATION NOTE:

    From time to time, confirm the actual interface level with a hand held float probe. This simple check

    should be performed regularly, particularly if the slurry pulp density changes.

    Column gas holdup the air fraction in an aerated slurry can be checked with the column filled with

    water. With the air turned off, (eg = 0) the pressure transducer reading should be equal to rgh, where r = 1 (water), g = 9.81 m/s2 (gravity) and h = distance from transducer to water level (meters).

    If column sanding is a significant concern, the level controller should be programmed so that it will close

    the underflow pinch valve only to a preset minimum closure say 5% open. This will prevent the valve

    from closing fully and will help to alleviate sanding in the column.

    2.7 COLUMN STARTUP

    Perform a visual walk around to confirm that all process piping is correctly installed and that all manual

    and automatic valves are positioned to send slurry flow in the proper direction through the proper pumps

    and pipelines.

    Visually confirm that the column underflow isolation valve is OPEN and the flow control pinch valve is

    CLOSED.

    If launder sprays are installed, turn these ON and check for adequate flow and distribution of launder

    water. The launder spray system should be turned OFF until concentrate flow begins and the sprays

    become needed.

    If the column is empty, fill it with water using the wash water system, the feed pump or a simple water

    hose. In preparation for normal operation, enter a medium setpoint on the level controller. The level

    setpoint will be optimized for metallurgical performance during normal operation.

    Once the water level in the column rises about three feet (one meter) above the SlamJet spargers, the

    air sparging system (sparger air and sparger water) can be activated. Visually check that all spargers

    are discharging air.

    As the water level reaches the setpoint, visually confirm that the underflow pinch valve begins to open

    and that the level control system is functioning correctly.

  • CPT CoalPro Column Commissioning Page 15

    Operating & Maintenance Manual

    At this time, the level control system should be checked by inputting new setpoints above and below

    the initial setpoint, and visually confirming that the control system adequately maintains a stable level in

    the column.

    Once the column is operating in a stable manner, slurry flow can be started.

    2.8 NORMAL COLUMN SHUTDOWN

    2.8.1 Initial Procedure

    When the feed supply is discontinued, adjust the wash water flow so that the underflow pinch valve can

    maintain the interface level without sanding out lines. This may require an INCREASE in wash water

    flow.

    2.8.2 Final Procedure

    The column will continue to recovery and discharge to the overflow launder any contained floatable

    material as well as any floatable material entering the column from existing recycle flows. When this

    flotation ceases, assess the type of shutdown expected. A short term shutdown is a few hours. A long

    term shutdown is many hours or days.

    2.9 SHORT TERM SHUTDOWN HOURS

    When the column is to be taken off line for a short period of time, it should NOT be necessary to empty

    the column. The following procedures should be followed;

    The sparger air and water flows can be shut off and the SlamJets will automatically fail closed to

    prevent backflow of slurry. Wash water flow can be shut off and the underflow isolation valve can be

    closed.

    OPERATIONS NOTE:

    In a shutdown situation, the column underflow line between the isolation valve and the flow control pinch

    valve should be drained to prevent sanding.

    When feed is reintroduced, simply open the underflow isolation valve and reset the wash water and

    sparger air and water flow controls to their previous levels.

  • CPT CoalPro Column Commissioning Page 16

    Operating & Maintenance Manual

    2.10 LONG TERM SHUTDOWN DAYS

    If the column is to be taken off line for an extended period of time it should be drained. Confirm that the

    column has been floated out as described in Section 2.8.2. When all flotation ceases, stop all feed to

    the column, reduce wash water flow and allow the column to drain by opening the underflow pinch valve.

    This is done by placing the level controller in manual mode and setting the valve position to full open.

    When the level in the column drops below the spargers, sparger air and water flows and the wash water

    flow can all be shut off.

    The underflow pump, if installed, can now be shut down and the remaining material in the column can be

    drained to waste through the column drain valve.

    2.11 EMERGENCY SHUTDOWN

    In the event of a power failure or other emergency situation that results in a crash shutdown of the

    column, the following procedures should be followed;

    All streams entering or leaving the column should be IMMEDIATELY STOPPED, including sparger air

    and water, as well as any pump gland water flows.

    All SlamJets are designed to automatically fail closed. Visually check that this has occurred.

    The automatic air flow control valve, if installed, is designed to fail closed. If automatic air flow control is

    not installed, manually close the sparger air shut-off valve.

    If the sparger water booster pump is still running, it should be shut down.

    If the level controller has been programmed with a minimum closing for the underflow valve, then material

    will continue to drain from the column. In this case, the manual underflow isolation valve should also be

    closed, and care must be taken to drain the underflow line between the isolation valve and the pinch

    valve to prevent sanding. Note that the short term shut-down procedure does NOT apply here since, in

    an emergency situation, the column floatables will not have been removed.

    2.12 COLUMN RE-START

    If the column was shut down while under full operational load, it is possible that the column will be

    sanded out. For coal processing columns which typically operate at fairly low densities, the probability

    of sanding is low. If the column is operating at higher densities and there is a possibility of sanding, the

    following re-start procedure should be followed;

  • CPT CoalPro Column Commissioning Page 17

    Operating & Maintenance Manual

    2.12.1 Re-Pulping

    To repulp the column, connect water lines to the repulp lances and apply a water flow. After a short

    period of time (10 to 20 minutes), the air should be re-started. The combination of lance water and

    sparger air will serve to repulp the sanded contents at the bottom of the column.

    2.12.2 Re-Starting Underflow

    After the repulp lances and sparger air flows have been running for a period of time (20 to 30 minutes),

    the underflow isolation valve should be SLOWLY opened to initiate flow.

    WARNING:

    If, during the shutdown period, material settles to a level ABOVE the spargers, it is IMPERATIVE to

    thoroughly repulp the sanded contents and to open the underflow valve SLOWLY. Failure to observe this

    procedure can cause a large slug of sanded material to move suddenly downward, possibly resulting in

    SEVERE damage to the spargers by bending them down with the moving slug of material.

  • CPT CoalPro Column Operation Page 18

    Operating & Maintenance Manual

    3.0 COLUMN OPERATION

    This section suggests approximate initial settings for some of the more common variables. These

    variables should later be optimised during operation. Also given here are the general effects that

    changing one variable will have on a column at steady state. The control system can compensate for

    gradual variations, but quick swings in flow rates or pulses of high or low grade material may cause

    poorer performance than would otherwise be expected. Therefore the feed volumetric slurry rate and total

    flux of floatable material should be kept as constant as possible. Make sure that all control loops are

    tuned to prevent unwanted oscillations.

    3.1 SPARGER AIR

    The column air rate is the most commonly adjusted and most effective control variable. The response to

    changes in air rate will be very rapid (seconds to minutes). The normal operating levels for air addition

    rates for column cells range from 0.5 cm/s to about 2.0 cm/s depending on the application. The

    optimum rate will vary depending on bubble size, bubble loading and slurry velocities and must be

    determined during normal operation.

    Superficial gas velocities (cm/s) can be converted to free air flows as follows;

    Example for 2.0 cm/s air velocity in a 14 ft. diameter column

    Column Area = p 2 / 4 = 3.142 x 14 x 14 / 4 = 153.9 ft2.

    Gas Velocity = 2.0 cm/s x 1.969 = 3.937 ft / min

    Gas Flow (free gas) = 153.9 ft2 x 3.937 ft/min = 606 cfm (ft3/min)

    Increasing the air flow will generally have the following effects:

    grade of the froth product will be reduced (more ash entrainment)

    density (percent solids) in the overflow will be reduced (more water recovery)

    recovery of solids to the column overflow will increase

    These effects are only valid within a specific range of flow. Continued increase in the air rate will lead to

    the onset of bubble coalescence which will have a severely detrimental effect on performance. Some

    indications of excessive air rates are the loss of a well defined interface or excessive turbulence in the

    froth zone. Increases in air will lead to increases in overflow production and will require a corresponding

    increase in wash water rates to maintain a positive bias. Air volumetric flows below 0.5 cm/s may cause

    froth bed collapse. In this case the froth zone depth will have to be reduced. (i.e. pulp level raised).

  • CPT CoalPro Column Operation Page 19

    Operating & Maintenance Manual

    3.2 INTERFACE LEVEL

    The location of the interface level between the froth and pulp zones can influence both the concentrate

    quality (ash) and clean coal recovery to overflow (yield). A deeper froth will increase the purity of the

    froth by providing more time for the entrained impurities to drain from the froth. It will also, however,

    result in a decrease in the recovery of the clean coal due to an increase in "drop-back".

    The column level should normally be controlled in a range from 20 inches to 40 inches but can vary

    depending on the stability of the froth. Little benefit is expected at depths greater than 60 inches. Much

    shallower froths are possible and may be desirable if high yield is required and high ash can be

    tolerated. Tests should be performed to predict performance at various interface levels.

    3.3 WASH WATER BIAS

    The non-selective entrainment of hydrophilic minerals (ash) can be reduced by preventing feed water

    from entering the overflow. This is done by operating with a positive wash water bias. In general, this

    means that the volumetric flow rate of underflow should be at least slightly greater than the volumetric

    flow rate of feed to the column. The excess flow (tails minus feed) divided by column cross-sectional

    area is defined as the bias velocity, or Jb.

    The column should be operated with Jb in the range of 0.0 to 0.3 cm/s. A Jb of 0.05 cm/s is suggested at

    start-up.

    Increased bias flow will:

    increase the displacement wash and underflow/feed ratio

    increase the grade of the froth

    reduce the recovery of clean coal

    These effects do not continue indefinitely with increasing bias. Eventually channeling of the wash water

    and breaking of the froth occurs that negates all the benefits of extra wash water. To ensure a positive

    bias, maintain an underflow volumetric flow rate at least slightly greater than the feed volumetric flow rate

    by adjusting the wash water flow rate.

  • CPT CoalPro Column Operation Page 20

    Operating & Maintenance Manual

    3.4 REAGENT DOSAGE

    In order for a column to function properly, it is imperative that the chemical conditions of the feed are

    correct prior to feeding the column. If the process is sensitive to fluctuations in pH, measurements

    should be made at the column underflow to account for dilution effects caused by wash water addition.

    3.4.1 Frother

    Frother acts to stabilize the froth zone. Increased frother produces smaller bubbles which may or may

    not improve collection of particles.

    Frothers for coal flotation generally fall into two categories glycols and alcohols.

    Glycols are much more effective than alcohols, but also produce a more persistent froth that can cause

    material handling problems in other parts of the plant.

    Alcohols are less effective but alcohol froths break and de-aerate more quickly than glycol froths.

    In general, increasing the frother dosage will:

    reduce bubble size

    reduce the bias rate

    reduce the percent solids in the overflow.

    increase gas holdup in the collection zone

    reduce the maximum air rate

  • CPT CoalPro Column Operation Page 21

    Operating & Maintenance Manual

    3.4.2 Collector

    The most common coal collectors are fuel oil, kerosene or Diesel.

    The presence of collector enhances the attachment of coal particles to air bubbles and thus directly

    influences clean coal recovery.

    In general, increasing the collector dosage will:

    increase mass recovery

    increase the percent solids in the overflow

    increase ash content of froth

    reduce gas holdup in the collection zone

    increase the maximum air rate

    reduce bubble size

    Note that frother and collector often work against each other, and there is a tendency to overcome

    problems caused by too much of one reagent by adding more of the other. This will almost certainly

    lead to reagent overdosing, and must be avoided.

    For example, low recovery typically indicates a need for more collector. Increasing the collector dosage

    may cause the froth to dry out and collapse. This can be compensated for by increasing the frother

    dosage. More frother can lead to a runny froth and increased ash entrainment in the froth. This can be

    compensated for by adding more collector and so on.

    The flotation operators first move to solve a flotation problem should always be to check dosing levels

    and compare with normal levels. If reagent levels are already high, then selective reduction of reagents

    may solve the problem at hand without causing any other problems.

  • CPT CoalPro Instrumentation & Control Page 22

    Operating & Maintenance Manual

    4.0 INSTRUMENTATION AND CONTROL

    4.1 INTRODUCTION

    Columns can be instrumented with up to four automatic control loops: Column Interface Level,

    Sparger Air Flow, Sparger Water Flow and Wash Water Flow . For most CoalPro applications,

    sparger air, sparger water and wash water addition rates are manually controlled and only one automatic

    control loop is required for column level. The description of the operation of the control loop(s) should

    be read in conjunction with the Process and Instrumentation Diagram (P&ID). This drawing lists the

    normal, maximum and minimum flows for each process stream.

    4.2 SPARGER PRESSURE

    The pressure in the sparger manifold should be maintained between approximately 60 psi and 100 psi.

    Sparger manifold pressure is a function of

    SlamJet control setting (factory pre-set cracking pressure)

    Sparger air flow rate

    Sparger water flow rate

    Plant air supply pressure

    Hydrostatic head in the column

    An initial operating pressure of 80 psi is recommended. During commissioning, different operating

    pressures should be tested to determine the optimum value for each application. For systems requiring

    remote sensing of the header pressure, a pressure transmitter can be mounted on the air manifold.

    4.3 SPARGER AIR FLOW

    Air flow control is the most effective parameter available to the operator for maintaining proper column

    operation. The air flow rate is optionally measured with a vortex flow meter and is controlled manually

    with a simple valve, or automatically using a PID controller (or DCS or PLC) to adjust the position of a

    pneumatically actuated flow control valve.

    The recovery of solids to the column overflow (yield) and the quality of product (ash) are directly

    dependant on the air rate. Air flows corresponding to a superficial gas rate below 0.5 cm/s are not

    recommended but can be used with appropriate care.

    The estimated maximum air rate should correspond to a superficial gas rate of approximately 2.0 to 2.5

    cm/s. This rate may be lower or higher depending on column conditions. The air flow rate should be

  • CPT CoalPro Instrumentation & Control Page 23

    Operating & Maintenance Manual

    changed in a stepwise fashion using small incremental changes in order to minimize process upsets. A

    maximum change of 10% of total flow at a time is recommended.

    The maximum and minimum air flow rates given here are only estimates. The exact values should be

    determined under actual operating conditions. Below the minimum gas rate the froth becomes unstable.

    Above the maximum gas rate recovery of solids to the overflow will decrease with the onset of bubble

    coalescence. Both of these values will vary with changes in interface level, reagent dosages, feed

    tonnages and grades, particle size and slurry density.

    The amount of air needed to meet ash / yield requirements depends on the particle size and amount of

    material to be floated but should fall within the previously mentioned ranges.

    For systems with automatic air flow control, operators should check periodically to verify that the air flow

    has reached the flow required by the set-point when operating with high sparger pressures.

    4.4 COLUMN INTERFACE LEVEL

    The position of the froth / pulp interface is measured using either a ball float and ultrasonic detector or

    single or dual pressure transducers. Both systems deliver a 4 to 20 mA signal proportional to the

    position of the froth / pulp interface. The interface level is controlled by a PID Controller (or DCS or PLC)

    which adjusts the position of the automatic pinch valve on the column underflow line.

    Slight variations in column level are not critical to performance as long as the level remains within a

    certain range. Variations of 5 inches are generally acceptable over a time span of 10 minutes, as long

    as the variations are gentle. Column performance will improve with more stable control, especially when

    operating with a bias close to zero or with shallow froth depths.

    It is suggested that the level be operated at depths greater than 10 inches and less than 60 inches with

    normal operation at 20 to 40 inches.

    4.5 WASH WATER

    The wash water flow is optionally measured with a magnetic flow meter and is controlled by a local

    manually operated valve. The expected range of flow of the wash water will correspond to a superficial

    wash water flow of approximately 0.15 to 0.40 cm/s. Slow variations in flow are acceptable but better

    performance will be achieved with smooth control. The suggested wash water rates are estimates only

    and should be adjusted to produce the proper bias rate. Actual rates should be determined through

    column tests during operation as they will depend on the feed rate, feed grade and expected mass

    recovery to the column overflow.

    Minimum bias occurs when no wash water is added to the column. As bias is increased, the purity of

    the froth will increase due to the displacement of entrained particles. An initial bias of approximately 0.1

    cm/s is suggested.

  • CPT CoalPro Instrumentation & Control Page 24

    Operating & Maintenance Manual

    The volumetric flow rate required to achieve the desired bias (Jb in cm/s) can be calculated as follows;

    Example for 0.1 cm/s wash water bias in a 14 ft. diameter column

    Column Area = p 2 / 4 = 3.142 x 14 x 14 / 4 = 153.9 ft2.

    Bias Velocity = 0.1 cm/s x 1.969 = 0.197 ft / min

    Wash Water Flow = 153.9 ft2 x 0.197 ft/min = 30.3 ft3/min x 7.48 = 226 USgpm.

    In other words, the tails volumetric flow rate should exceed the feed volumetric flow rate by about 200

    USgpm.

  • CPT CoalPro Troubleshooting Page 25

    Operating & Maintenance Manual

    5.0 TROUBLESHOOTING

    This section gives possible causes of poor performance and suggests improvements. Two conditions

    are dealt with: poor grades (high ash) and poor recovery (low yield). Each is then subdivided into two

    categories: problems originating with the column and those that originate in the rest of the circuit.

    Possible solutions are given in order from most to least likely.

    5.1 PROBLEM HIGH ASH

    5.1.1 Column Problems

    High air rates may cause an increase in ash entrainment in the overflow by increasing the amount of

    feed water that is carried by the bubbles. To counteract this try, one at a time:

    Reduce the air rate.

    If the wash water bias rate Jb is less than 0.25 cm/s, increase the wash water flow QW

    The interface level may be too high which reduces the froth zone cleaning action. Increase the froth

    depth.

    5.1.2 Circuit Problems

    High reagent dosages could cause excessive amounts of feed water to report to the overflow causing

    increased entrainment and increased wash water rates. Check reagent addition rates.

    Grind size may be too large, resulting in a higher than normal concentration of middling particles in the

    froth. Check the size distribution of the feed, concentrate and tailings streams. Analyze the various size

    fractions to determine if there is a possible liberation problem.

    5.2 PROBLEM LOW YIELD

    5.2.1 Column Problems

    Low yield (recovery of clean coal) is quite often caused by low air rates. Increase the air rate, but watch

    for loss of interface, and approach air rates greater than 2.0 cm/s with caution. If the column is operating

    with a deep froth (greater than 1,000 mm) try reducing the froth depth.

    High air rates may cause a turbulent flow in the column which is not conducive to good flotation

    separation. The interface may also be lost. This may appear as volcanoes or geysers in the froth. (The

    volcanoes can also be caused by very high froth density). Reduce the air rate.

  • CPT CoalPro Troubleshooting Page 26

    Operating & Maintenance Manual

    Excessive wash water may cause froth breakage which reduces the production capacity. This will

    appear as an unstable froth. Reduce the wash water rate.

    Poor air distribution causes eddies within the collection and froth zones that decrease the effective

    column residence time. This may be seen as an unstable froth. Ensure that all spargers are clear and, if

    necessary, accelerate the sparger tube inspection and cleaning schedule.

    5.2.2 Circuit Problems

    Insufficient collector addition may contribute to poor flotation performance. Check reagent addition rates

    and adjust as required. If frothers are being used, low frother dosages may cause froth instability and

    can result in an increase in bubble size. Increase frother dosage or increase sparger air flow rate.

    Grind size may be too large creating middling particles that are difficult to float. This can be determined

    by microscopic examination for locked particles.

  • CPT CoalPro System Maintenance Page 27

    Operating & Maintenance Manual

    6.0 SYSTEM MAINTENANCE

    6.1 INTRODUCTION

    All maintenance should be done on a scheduled basis. Operators should regularly inspect all parts of

    the circuit. Operational and performance trends from the column should be noted for indications of

    instrument problems including faulty calibration and tuning.

    6.2 COLUMN MAINTENANCE

    The overflow launders, both external and internal, should be kept clear of scale and accumulated solids.

    This will ensure that the overflow of froth is not hindered. Scale and/or solids can have a tendency to

    build up on the lip of the launder and on the column walls at a point just below the lip. This material

    should be routinely scraped or washed off by the operators.

    The wash water system must be maintained so that the flow of water is evenly dispersed within the

    froth. Periodically inspect the distributor for build-up of solids or for blocked holes. The distributor holes

    must remain clear.

    MAINTENANCE NOTE:

    Pinch valve sleeves can wear out quickly if they are required to operate at low opening percentages.

    Careful attention must be paid to the wear of this valve as indicated by the valve percent opening Vs flow

    rate relationship and regular inspections.

    If pressure transducers are installed on the column, regular inspections should be made to ensure that

    they are functioning properly. The calibration should be checked from time to time by noting the

    readings when the column is full of water. Any scaling should be carefully removed according to

    manufacture's maintenance procedures.

    Level control systems that use a ball float should be cleaned regularly to prevent a build-up of solids on

    the float.

    The level calibration can be checked by using a manual float. At times the density of the froth is high

    enough to float the ball float but little resistance will be encountered when the ball float is pushed

    further down. This condition is commonly called a double interface: the true interface will be the lower

    one.

  • CPT CoalPro System Maintenance Page 28

    Operating & Maintenance Manual

    6.3 SPARGER MAINTENANCE

    The spargers have been designed for reliability and durability, but some maintenance is required.

    Regular inspections should be made both to maintain performance and to prevent a build-up of scale on

    the tube surfaces.

    6.3.1 Orifice Wear

    No rapid deterioration is expected at the tip orifice, but they are expected to enlarge slowly over a period

    of time. However, in the unlikely event that the sparger orifices become enlarged they must be replaced

    to avoid a reduction in metallurgical performance.

    Care should be taken to limit the SlamJets exposure to highly acid environments. Hydrochloric acid

    will corrode both the stainless steel tubes and the adhesive compound which holds the ceramic inserts

    in place.

    WARNING:

    Cleaning spargers with a strong acidic solution could result in corrosion to the stainless steel tubes as

    well as damage to the retaining compound used to adhere ceramic inserts in the sparger nozzles.

    6.3.2 Tip Blockage

    A maintenance program should be devised based on inspections for blocked nozzle orifices and poor air

    distribution. Each sparger tube should be removed and inspected on a regular basis. The interval of

    inspections depends on the scale forming tendency of the slurry and sparger water. Note that the

    SlamJet orifice diameter is 0.30 inches (7.62 mm), and blockage is not expected to be a problem.

    Initially CPT recommends that spargers be checked monthly. This interval can then be extended if no

    plugging or serious scale formation problems are encountered.

    In the case of blocked orifices the blockage should be removed. If tip blockage becomes a recurring

    problem, consideration should be given to the installation of additional filters for the air lines.

    6.3.3 External Scaling

    In the presence of highly scale-forming slurries, the external surfaces of sparger tubes will become

    scaled, making them difficult to remove for inspection. In severe cases, the external scale can cause

    damage to the rubber seal in the liquid-tight insertion port seal assembly.

  • CPT CoalPro System Maintenance Page 29

    Operating & Maintenance Manual

    If scale formation is a problem then different spargers should be pulled on a rotating basis, as often as

    required, and the external surfaces cleaned with an emery cloth. If scaling is a persistent problem,

    please contact CPT.

    6.3.4 Sparger Removal for Inspection and Cleaning:

    Close the isolation valve at the manifold. The SlamJet will then automatically fail closed.

    Remove the air hose by disconnecting the quick disconnect coupling.

    Slightly loosen the compression fitting so that the sparger can be slowly withdrawn from the column.

    WARNING:

    Slurry will leak from the compression fitting if it is loosened too much.

    Each sparger tube has been marked with a groove located approximately 12 in (300 mm) from the end,

    which provides a visual indication of when the end of the sparger tube has cleared the full port ball valve.

    When the groove appears, close the ball valve. If this is not done before fully removing the sparger, a

    stream of slurry will emerge from the column through the sparger nipple.

    Assess the condition of the sparger nozzle by direct visual observation, and clear any blockages. If the

    blockages are serious, it may be necessary to disassemble the SlamJet to clear it.

    Removal of exterior scaling of the sparger tube will ensure that the tubes are always easy to remove.

    To re-install the SlamJet, insert the tube until the end comes into contact with the closed ball valve in

    the insertion port. Tighten the compression fitting enough to stop leaks. Open the ball valve and push

    the sparger tube into the column, the tighten the compression fitting by hand and attach the air line.

    WARNING:

    If SlamJets are pressurized while outside the column, the resulting high velocity air jet is extremely

    hazardous. As a precautionary measure, always wear gloves when handling spargers that are operating

    outside the column and DO NOT direct the air jet at personnel.

  • CPT CoalPro System Maintenance Page 30

    Operating & Maintenance Manual

    6.3.5 Poor Air Distribution

    Uneven swelling of froth in the column may be a sign of poor air distribution caused by one or more

    partially or fully blocked SlamJets.

    This may be caused by insufficient air pressure in the system, blocked hoses which prevent air entry

    into the sparger or one or more spargers being turned off.

    In the unlikely event that the sparger holes become enlarged, the sparger nozzles must be replaced to

    avoid a loss in metallurgical performance.

    6.4 COMPRESSOR AND AIR LINES Oil from the compressor should not be allowed to enter the column. This oil may cause flotation

    problems, such as a excessive frothing and poor selectivity.

  • CPT CoalPro Collection Zone Theory Page 31

    Operating & Maintenance Manual

    7.0 COLLECTION ZONE THEORY

    7.1 INTRODUCTION

    The collection zone of the column is located between the froth interface (Hf) and the point of maximum

    descent of the bubbles below the spargers (Hspa). In this zone floatable material from the feed stream

    and material returned after rejection from the froth zone (drop-back) are collected by rising bubbles.

    Recovery of material within the collection zone is dependent on the zone's residence time and mixing

    characteristics.

    7.2 RESIDENCE TIME

    Collection zone residence time, as mentioned in the testwork section, is estimated for round columns

    by the following equation;

    slc2

    c spa f col sl

    tail( )=

    15 d ( H - H - H )(1 - / )V

    tp r r

    min

    Where

    tsl = collection zone residence time (min)

    dc = column diameter (m)

    Hc = total column height (m)

    Hspa = sparger level (m)

    Hf = interface level (m)

    rcol = collection zone density (t/m3)

    rsl = concentrate slurry density (t/m3)

    Vtail = tailing (underflow) volumetric flowrate (m3/hr)

    The equation has three parts: column volume, gas holdup and slurry velocity.

  • CPT CoalPro Collection Zone Theory Page 32

    Operating & Maintenance Manual

    Gas

    Hol

    dup

    - Eg (%

    )

    Superficial Gas Velocity - Jg (cm/s)

    Figure 3 - Gas Holdup Vs Gas Velocityfrom Dobby & Finch - 1988

    10

    30

    20

    Frother Concentration (ppm)15

    10

    5

    0

    1 2 3 4

    Figure 4 - Gas Holdup Vs Slurry Velocityfrom Dobby & Finch - 1988

    Gas

    Hol

    dup

    - Eg (%

    )

    Superficial Slurry Velocity - J sl (cm/s)0.5 1.0 1.5

    10

    30

    20

    Liquid Velocity JL ( cm/s)

    0.38

    1.00

    1.26

    7.2.1 Column Volume

    The volume of the collection zone is essentially fixed. Hf, the interface level, is the only variable which

    can be easily changed to increase collection zone volume but the impact on residence time will be

    small. The only significant way to influence residence time is to vary the column feed rate.

    7.2.2 Gas Holdup

    Gas holdup is the volume fraction of gas in the column. It is a parameter dependant on other variables

    such as volumetric air rate, size of the bubbles, slurry density, solids bubble loading, and slurry velocity.

    Increased gas holdup reduces collection zone residence time.

    Gas holdup may increase due to three factors:

    An increase in gas flow will increase the number of bubbles present in the column as more bubbles are

    being generated in any time period.

    A bubble size decrease caused by sparger operation or frother dosage will cause each bubble to rise

    more slowly in the slurry, again causing an increased amount of air in the column.

    An increase in downward slurry velocity will decrease bubble rise velocity relative to the column, also

    resulting in an increase in the quantity of air held up in the column.

  • CPT CoalPro Collection Zone Theory Page 33

    Operating & Maintenance Manual

    7.3 AIR RATE

    7.3.1 Maximum

    The maximum air rate which a column is capable of handling is determined by three limits: (i) the

    superficial feed rate must be less than the bubble rise velocity, (ii) the collection zone density must be

    greater than the froth zone density and (iii) bubble coalescence must not form air slugs.

    Sup

    erfic

    ial G

    as V

    eloc

    ity -

    J g (c

    m/s

    )

    Superficial Slurry Velocity - J sl (cm/s)

    Figure 5 - Column Floodingfrom Dobby & Finch - 1986

    1

    3

    2

    -2.0 -1.5 -1.0 -0.5 0.0 +0.5

    Countercurrent Cocurrent

    0.020.04

    0.07

    0.10

    db = 0.13 cm

    Particle Size (m)

    Figure 6 - Bubble & Particle Size Effectsfrom Dobby & Finch - 1988

    Ec *

    Ea (

    %)

    Bubble Diameter (mm)

    1.3

    0.5

    0.7

    1.0

    20 40 60

    0.5

    3.0

    1.0

    (i) Bubble rise velocity depends on bubble size, the difference between the apparent collection

    zone and bubble densities, and downward slurry velocity. A distribution of bubbles sizes is produced by

    any sparging system. Therefore, when the slurry feed rate exceeds the rise velocity of the smallest

    bubble, a percentage of the air is lost to the underflow.

    (ii) As the gas rate to the column increases the three phase density of the collection zone

    decreases. At the same time the density of the froth zone will increase until the two are equal. At this

    point the gas holdup will suddenly increase from about 15% to over 50%. When this occurs, the column

    is said to be frothed up. Recoveries drop significantly under these conditions.

    (iii) The increased turbulence and larger bubbles formed at higher gas rates cause an increase in

    bubble coalescence which results in a decrease in the incremental gas holdup. Eventually, severe

    coalescence will result in the formation of large slugs of air. This effect changes the column mixing

    characteristics and reduces both the surface area available for flotation and the collection of particles on

    the bubble surface. One of these factors will probably limit the maximum column gas velocity to

    between 1.8 and 3.5 cm/s.

  • CPT CoalPro Collection Zone Theory Page 34

    Operating & Maintenance Manual

    7.3.2 Optimum

    The optimum gas rate usually occurs at the point at which solids loading per gas volume is maximized

    (Cg) rather than at the maximum gas holdup. Maximum gas holdup usually occurs at a gas rate larger

    than optimum.

    7.4 PARTICLE AND BUBBLE SIZE

    Both the average size of bubbles and distribution of bubble sizes are important to column flotation. They

    affect maximum gas rate, probability of particle collection on the bubble, and solids gas carrying

    capacity (Cg). Bubbles used are typically between 0.8 and 1.6 mm in diameter with the actual size

    depending on reagent conditions, sparger design, and operating pressure.

    7.4.1 Gas Velocity

    Smaller bubbles have a reduced rise velocity, therefore, the maximum gas rate will be less than that

    possible with larger bubbles.

    7.4.2 Probability of Collection

    The flotation rate constant of a column has been related to the probability of particle - bubble collision

    and attachment by the following equation:

    cg a c

    bk =

    1.5 Jd

    e e

    Where

    kc is the flotation rate constant (min-1).

    ec is defined as the fraction of particles contained in the cylindrical volume traveled by the bubble which collide with that bubble.

    ea is defined by the fraction of particles which have collided with the bubble that attach to that bubble.

    db is defined as the bubble diameter in m.

    Bubble size should be adjusted for changing particle size to fully optimize a column. This can be

    achieved in two ways: (i) by adding a frother to the feed or (ii) by increasing the sparger pressure.

  • CPT CoalPro Collection Zone Theory Page 35

    Operating & Maintenance Manual

    7.4.3 Solids Carrying Capacity

    0.05 0.10 0.15

    Bub

    ble

    Dia

    met

    er (m

    m)

    Frother Consumption (mg/scm2)

    Figure 7 - Effect of Frother on Holdupfrom Dobby & Finch - 1988

    SlurryFrother

    SpargerFrother1.0

    2.5

    2.0

    1.5

    The amount of solids which can be carried by a bubble are influenced by the following factors: surface

    area to volume ratio, solids density, and particle size, hydrophobicity, and particle shape.

    Smaller bubbles have larger surface areas per volume and therefore can carry more solids per air

    volume. (The slower rise velocity of the smaller bubbles reduces the air volume which can be added to

    the column.) Very small bubbles (micro bubbles) may cause loss of collected solids to the underflow

    stream when bubble density (collected solids plus air) reduces bubble rise velocity to values smaller

    than the slurry velocity. More hydrophobic particles attach to the bubble faster therefore have a larger

    Ea. Particles which are highly angular tend to attach more quickly.

  • CPT CoalPro Froth Zone Theory Page 36

    Operating & Maintenance Manual

    8.0 FROTH ZONE THEORY

    8.1 INTRODUCTION

    The froth zone extends from the collection or pulp zone interface to the column lip. In this zone solids

    and water are carried between bubbles. The three phase density of this zone usually ranges from 0.2 to

    1.0 g/cm3, depending on the solids floated, location of measurement, froth depth, wash water, and

    frother dosage.

    Wash water stabilizes the bubbles and reduces coalescence. Figure 8 illustrates this effect by showing the change in holdup with level of the column (with wash water) and a mechanical cell (without wash water).

    20 40 60 80

    Gas Holdup - Eg (%)

    Fro

    th D

    epth

    (app

    rox.

    1.0

    m)

    Figure 8 - Conv. Vs Column Holdupfrom Dobby & Finch - 1988

    Overflow

    Interface

    ConventionalFroth

    CollectionZone

    Froth Zone

    Column Froth

    Wash Water Concentrate

    NegativeBias

    PositiveBias

    InterfaceLevel

    DrainingFroth BedEg > 0.80

    PackedBubble Bed

    Eg > 0.74

    ExpandedBubble Bed

    Eg < 0.74

    BubblingZone

    Eg < 0.20

    Figure 9 - Froth Zone Profilefrom Yianatos - 1985

    As the bubbles ascend the froth zone a certain amount of coalescence occurs. This reduces the bubble

    surface area available for solids and also decreases the volume of the voids between bubbles occupied

    by water. This property appears as an increase in gas holdup with height and is illustrated in Figure 9.

  • CPT CoalPro Froth Zone Theory Page 37

    Operating & Maintenance Manual

    8.2 FROTH CLEANING

    Since there is a net downward flow of water in the froth zone (assuming a positive bias) particles not

    attached to bubbles will be carried back into the collection zone. This includes particles that are carried

    with, but not attached, to bubbles (non-selective entrainment) and particles that become detached from

    the bubble due to coalescence. These particles, returned to the collection zone via the wash water, form

    a partial internal solids recycle. This is commonly termed "drop-back", and is the reason behind the

    increased grade and lower recovery at deeper interface levels (Figures 10 and 11).

    Cop

    per R

    ecov

    ery

    (%)

    Froth Depth (m)

    Figure 10 - Cu Recovery Vs Froth Depthfrom Huls - 1989

    50

    80

    70

    60

    0.8 1.0 1.2 1.4

    Con

    cent

    rate

    Gra

    de (%

    Ni)

    Froth Depth (m)

    Figure 11 - Ni Grade Vs Froth Depthfrom Huls - 1989

    0.8 1.0 1.2 1.4

    0.4

    1.0

    0.8

    0.6

    8.3 GAS VELOCITY

    An increase in gas velocity results in an increased collection zone holdup and a decreased froth zone

    holdup (Figure 12). Less coalescence occurs in the froth zone as gas rate is increased, therefore, froth

    grade deteriorates. Very high air rates may result in a loss of the interface.

    This is apparent when the holdup in the froth and collection zones are equal. This condition can

    contribute to the rapid drop in grade found at high recoveries on typical column grade / recovery curves

    (Figure 13).

  • CPT CoalPro Froth Zone Theory Page 38

    Operating & Maintenance Manual

    Overflow

    Interface

    CollectionZone

    Froth Zone

    Gas Holdup - Eg (%)

    Fro

    th D

    epth

    (app

    rox.

    1.0

    m)

    Figure 12 - Effect of Jg on Gas Holdupfrom Dobby & Finch - 1988

    20 40 60 80

    Jg

    Jg

    Gra

    de (%

    )

    Recovery (%)

    Figure 13 - Rghr Column Grade/Recovery

    48

    54

    52

    50

    92 94 96 98

    20 40 60 80Gas Holdup - Eg (%)

    Fro

    th D

    epth

    (app

    rox.

    1.0

    m)

    Overflow

    Interface

    CollectionZone

    Froth Zone

    Figure 14 - Effect of Frother on Gas Holdupfrom Dobby & Finch - 1988

    Frother

    Frother

    20 40 60 80Gas Holdup - Eg (%)

    Fro

    th D

    epth

    (app

    rox.

    1.0

    m)

    Overflow

    Interface

    CollectionZone

    FrothZone

    Figure 15 - Effect of Bias on Gas Holdupfrom Dobby & Finch - 1988

    Jb

  • CPT CoalPro Froth Zone Theory Page 39

    Operating & Maintenance Manual

    Increased gas velocity also results in a higher possibility of feed water reporting to the overflow (Figure 14) which lowers the purity of the froth product.

    8.4 FROTHER CONCENTRATION For applications where frothers are used, an increase in frother concentration has an effect similar to

    that of high air addition rates. The froth zone gas holdup (Figure 15) decreases causing lower froth

    percent solids and a decrease in froth grade. High frother dosages, especially when combined with high

    air rates, can be detrimental to column performance.

    20 40 60 80

    Feed Water in Froth (%)

    Frot

    h D

    epth

    (ap

    prox

    . 1.0

    m)

    Overflow

    Interface

    CollectionZone

    FrothZone

    Figure 16 - Effect of Jg on Entrainmentfrom Dobby & Finch - 1988

    Feed Water BiasWater

    Jg

    >2.5 cm/s

  • CPT CoalPro Froth Zone Theory Page 40

    Operating & Maintenance Manual

    water that reports to the flotation product. Three different sized particles are shown: 5, 10 and 20

    micrometers. Manual changes in the wash water rate will alter the superficial bias rate when using level,

    or displacement bias control method.

    20 40 60 80Feed Water in Froth (%)

    Fro

    th D

    epth

    (app

    rox.

    1.0

    m)

    Overflow

    Interface

    CollectionZone

    Froth Zone

    Figure 18 - Effect of Jb on Feed Water in Concfrom Dobby & Finch - 1988

    Jb ~0.5 cm/s

    Jb ~0.3 cm/s

    Jb ~0.1 cm/s

    Sol

    ids

    Rec

    over

    y (%

    )

    Water Recovery (%)

    Figure 19 - Recovery of Solids Vs Water

    40

    5 m

    10 m

    20 m

    20 40 60

    10

    30

    20

    Con

    cent

    rate

    Gra

    de (%

    )

    Distance Below Column Lip (cm)

    Figure 20 - Grade & Selectivity with Depthfrom Dobby & Finch - 1988

    20

    60

    30

    10

    70

    50 1000 150

    Column Size 45 x 45 x 1,200 cm

    Molybdenum

    Chalcopyrite

    Silica

    PyriteWas

    h W

    ater

    Inpu

    t

    Inte

    rfac

    e

  • CPT CoalPro Froth Zone Theory Page 41

    Operating & Maintenance Manual

    8.6 SELECTIVITY Selectivity occurs in the froth zone; the less floatable particles drop back into the collection zone as

    indicated in Fig 20. In this diagram Silica, Chalcopyrite and Pyrite grade reductions are traced.

    There is also a size class selection. Larger particles are usually the ones that remain locked and are

    therefore "middling" in nature and subject to washing. Larger particles project further from the bubble

    surface and are subject to more force from the passing wash water stream.

  • CPT CoalPro Froth Zone Theory Page 42

    Operating & Maintenance Manual

    8.7 REFERENCES

    Amelunxen, R.L., (1985). The Mechanics of Operation of Column Flotation Machines.

    Proceedings of the 17th Annual CMP Meeting, Ottawa, January 1985

    Egan, J.R., Fairweather, M.J., and Meekel, W.A., (1988). Applications of Column Flotation to Lead and Zinc Beneficiation at Cominco.

    1st International Symposium on Column Flotation, AIME, Phoenix

    del Villar, R., Gomez, C.O., Finch, J.A., and Espinosa -Gomez, R.,(1989). Flotation column amenability and scale-up parameter estimation tests. C.I.M. International Symposium on the Processing of Complex Ores, Halifax.

    Dobby, G.S., and Finch, J.A., (1988). Column Short Course, Cambourne School of Mines, Cornwall, England.

    Huls, B.J., Lachance, C.D., and Dobby, G.S., (1989). Gas rate and froth depth effects on performance of a Cu-Ni separation flotation column. C.I.M. International Symposium on the Processing of Complex Ores, Halifax.

    Wheeler, D.A., (1988). Historical View of Column Cell Development. Presented at 1st Int. Symp. on Column Flotation, A.I.M.E., Phoenix

    Wilson, S.W., (1987). The Study of Flotation Column Rate Constants as a Function of Particle Size. B.A.Sc. Thesis, Dept. of Geological Engineering, University of Toronto.

  • CPT CoalPro Production Column Testing Page 43

    Operating & Maintenance Manual

    9.0 PRODUCTION COLUMN TESTING

    9.1 INTRODUCTION

    The purpose of conducting testwork is to determine the optimum parameter settings to maximize

    column performance under varying plant operating conditions. Generally, a column operates best under

    steady-state conditions; the fewer disturbances in the system the better. Considering this, operation

    should be as smooth as possible, and any changes in interface level, wash water, air or reagent

    additions should be made slowly.

    When performing testwork, a minimum number of variables should be changed at one time -

    ideally only one - so that the fewest number of effects interact.

    It is important to remember that a column has a significant residence time and therefore an ability to

    accumulate floatable solids through internal recycle. If solids are building up due to insufficient air rate or

    other froth transport problems, excellent grades can be achieved without immediately sacrificing

    recovery. These solids, however, will eventually report to the underflow resulting in a significant

    deterioration of metallurgical performance. High solids loading may cause excessive coalescence in the

    froth zone and appear as "burping" or "volcanoes" in the froth. Therefore, whenever a grade / recovery

    curve is being constructed, values should not be recorded until a steady state is reached - which may

    take as long as three column residence times after the last change.

    9.2 AIR RATE

    The amount of material floated is very sensitive to the rate of air introduced through the spargers. In the

    first few days of operation with a new type of feed material, the reagent dosages and air flow rate should

    be adjusted to give optimal grade/recovery performance. Record the air loading (amount of solids carried

    per unit of air) as kg/m3. When the column feed rate changes, repeat the test. The purpose of these

    tests is to create a chart of air requirement Vs overflow tonnage production that can be used by

    operators. The amount of air needed to float a specific amount of solids