Upload
krzysztof-marcinkiewicz
View
171
Download
5
Embed Size (px)
Citation preview
C. H. Goodchild BSc, CEng, MCIOB, MIStructE
J. Glass BA, Dip Arch, DipBRS, PhD, ILTM
A guide to choosing and using combinations of precast and in-situ concrete for better value structural frames
Best Practice Guidance forHybrid Concrete Construction
1
1. Executive summary 2
2. Introduction 3
3. Why use Hybrid Concrete Construction? 5
4. Best Practice Guidance for Hybrid Concrete Construction 9
5. Achieving best practice 16
6. Case studies 28
Ipswich Town Football Club: North Stand 28
Toyota (GB) Headquarters 34
West Car Park, West Quay, Southampton 39
Whitefriars, Canterbury 47
7. Conclusions 51
8. References and further reading 52
Appendix: Background research 53
A.1 Context 53
A.2 Best Practice Guidance for Hybrid Concrete Construction research project 55
A.3 Structural design 61
Best Practice Guidance for Hybrid Concrete Construction
Contents
Published by The Concrete Centre on behalf of industry sponsorsRiverside House, 4 Meadows Business Park, Station Approach, Blackwater, Camberley, Surrey GU17 9ABTel: +44 (0)1276 606800 Fax: +44 (0)1276 606801
TCC/03/09 Published September 2004 ISBN 1-904818-09-9Price Group L © The Concrete Centre
All advice or information from The Concrete Centre is intended for those who will evaluate the significance and limitations of
its contents and take responsibility for its use and application. No liability (including that for negligence) for any loss resulting
from such advice or information is accepted by The Concrete Centre or their subcontractors, suppliers or advisors. Readers
should note that The Concrete Centre publications are subject to revision from time to time and should therefore ensure that
they are in possession of the latest version.
Front cover: Inland Revenue, Nottingham, interior of building.
Photo: Martine Hamilton-Knight/Built Vision. Architect: Michael Hopkins & Partners.
British Precast is the trade federation representing the UK precast and concrete masonry industry. The Structural Precast
Association is a member of British Precast and is supporting this publication. Website: www.britishprecast.org Tel: 0116 253 6161.
CONSTRUCT is an association of member companies dedicated to the task of improving the construction efficiency of in-situ
concrete frames and associated structures. For further details contact the Secretary on 01276 38444.
Acknowledgements
The Advisory GroupJohn Caine Curtins Consulting Engineers
Norman Brown ABC Structures
Clive Budge British Precast Concrete Federation
Mike Downing Downing Associates
Charles McBeath whitbybird
Rob Moura Ascon/Edmund Nuttall
Chris Packer HBG Construction
Mahesh Parmar Anthony Hunt Associates Ltd
Martin Southcott The Concrete Centre
Russ Wolstenholme W S Atkins for DTI
Interviewees and Participants at WorkshopsMatthew Allen Sir Robert McAlpine Design Group
Roger Bailey Tarmac Precast Concrete Ltd
Graham Beardwell Ove Arup & Partners (M&E)
Andy Butler Stanhope plc
Peter Carruthers Sir Robert McAlpine Ltd
Ian Cordingley Upton McGougan Consulting Engineers
Mike Crook HOK Sport
Ian Curry AMEC
John Cutlack Jan Bobrowski & Partners
Brian Cutler Independent Consultant
Phil Doyle Sheppard Robson Architects
Chris Edwards HBG Construction
Adrian Falconer Ove Arup & Partners
Jim Farley Sir Robert McAlpine Ltd
Ian Feast Hammerson plc
Andy Fereday Miller Construction
Jack Gabrielcyzk Taylor Whalley Spyra
Tony Giddings Argent Group
Kevin Gill Gill Associates
Ray Hull Byrne Brothers Ltd
Rob Jones Davis Langdon and Everest
Simon Lake Toyota GB
Suqlain Mahmood Sir Robert McAlpine Design Group
Bob Martin Bison Concrete Products
Gavin Murgatroyd Gardiner & Theobald
Dominic O’Neill Fitzroy Robinson
Robert Reed HBG Construction
Martyn Reeve Sir Robert McAlpine Ltd
Peter Rogers Stanhope plc
David Rose Ipswich Town FC
Peter Stackhouse Lyons Sleeman & Hoare
Thierry Suc Upton McGougan Consulting Engineers
George Tootell CV Buchan
Dennis Vittle The Marble Mosaic Company Ltd
David Walker Trent Concrete Ltd
Russell Woby Hoopers Architectural Services
Researchers on ‘Hybrid ConcreteConstruction for the UK Market’Ghassan Aouad University of Salford
Bousmaha Baiche Oxford Brookes University
Peter Barrett University of Salford
Pal Chana BCA (formerly of Imperial College)
Charles Fowler RPEG, University of Reading
Colin Gray RPEG, University of Reading
Rod Webster CiD
Dedicated to Gerry Shaw.
The Concrete Centre acknowledges and appreciates the support given by many individuals,companies and organisations. These include:
3
Introduction 2
Introduction
Hybrid Concrete Construction (HCC) combines all the benefits of precasting (e.g.
quality, form, finish, colour, speed, accuracy, prestressing) with all the benefits of in-situ
construction (e.g. economy, flexibility, mouldability, thermal mass, continuity, durability,
and robustness). HCC can answer client demands for lower costs and higher quality by
providing simple, buildable and competitive structures that offer consistent performance
and quality.
To date, the use of HCC has been confined mainly to bespoke structures. Some of these
structures achieved cost savings of up to 30% over more conventional structural frames.
Naturally, the concrete industry was eager to identify how this order of saving might
be achieved consistently and more widely. As well as responding to the challenges
laid down by the Latham 2 and Egan3 reports, wider use of hybrid structures would
significantly improve the productivity and therefore competitiveness of the whole UK
concrete frame industry.
With this in mind, the Reinforced Concrete Council was successful in gaining government
support, through the Department of Trade & Industry Partners in Innovation (PII)
scheme, to carry out a research project entitled ‘Best Practice Guidance for Hybrid
2
1 Executive summary
Executive summary
Hybrid Concrete Construction (HCC) is about providing best value in structural frames.
HCC provides simple, buildable and competitive structures that answer client demands
for better value. It meets industry requirements for increased prefabrication, increased
off-site activity, safer and faster construction and consistent performance.
Despite the challenges thrown down by the Latham2 and Egan3 reports and their
successors, the UK has been slow to realise the benefits of HCC. One of the barriers to
HCC’s more widespread use was found to be the lack of comprehensive guidance, a
situation which this publication aims to change.
Based upon work carried out under a PII research project, this publication demonstrates
how to achieve best practice. The guidance explains the benefits that result from:
■ early involvement of specialist contractors
■ using a lead frame contractor
■ using best value philosophy
■ holding planned workshops
■ measuring performance
■ trust
■ close co-operation – with an emphasis on partnering.
The guidance is supported by case studies and shows that although there are intense
periods of co-ordination during the design phase, there are tremendous rewards on site
and in use. Best value is achieved through communication and measured in terms of
buildability, construction speed, aesthetic, quality, environmental and whole-life cost
benefits.
HCC can achieve very significant cost savings and give rise to some very satisfied
clients. This publication is intended to show how this can be achieved.
Figure 1 Gatwick office project
Showing precast floor beams onto
in-situ beams and columns.Photo: J Doyle
5
Why use Hybrid Concrete Construction? 3
3. Why use Hybrid Concrete Construction?
Hybrid concrete technology is used primarily to achieve fast and cost effective construction
by removing labour-intensive operations on-site and replacing them with mechanised
production in precasting yards and factories. Potentially there are many other advantages;
these are discussed below.
Traditionally, cost is the most influential factor in the choice of frame material. Although
the structure of a building represents typically only 10% of construction cost, the
choice of structural frame material can have dramatic effects on the cost of other
elements of construction – such as external cladding, services and internal planning. It
also affects net-to-gross floor area ratios10. It can even determine whether air conditioning
or suspended ceilings are necessary. Selecting the correct structural framing material is
vital to a project’s feasibility and success.
Individually, each structural material has merits, yet there is greater benefit in combining
materials. The advantages of one material compensate for the drawbacks of another.
In-situ reinforced concrete is commonly viewed as the most economic framing option,
4
2 Introduction
Concrete Construction’. The research was completed under the auspices of the
Reinforced Concrete Council’s successor, The Concrete Centre.
This project built on previous research1 that had identified an enthusiasm for HCC.
Combinations of precast and in-situ concrete were found to be broadly cost neutral;
construction times were equal if not better than conventional construction methods
and HCC offered many other potential benefits such as reduced whole-life costs. Yet
its acceptance and more widespread use was hindered by a general lack of experience
or guidance.
This publication aims to change that situation. It is the main output from the best
practice research project, which itself was based on obtaining a fundamental
understanding of customer requirements, design concerns, construction business
processes and supply chain issues. This understanding has been achieved through the
help of many individuals and companies within the construction industry. It forms
the basis of this best practice guidance, which has been written, and therefore should
be viewed in the light of broader based initiatives in improving the construction
procurement process. These initiatives include:
■ Constructing the Team (Latham)2
■ Rethinking Construction (Egan)3
■ Movement for Innovation (M4i)4
■ Value management5
■ Construction Best Practice Programme6
■ Process Protocol7
■ Accelerating change8
■ Learning from the best9
�The belief is that if everybody involved in a project can work to an agreed
set of processes and procedures, then we will not only be more efficient,but
we will be in a much better position to meet the client�s business needs.�
Process Protocol7
Cost
Figure 2Italian floor construction
Hollowcore floor units have been
placed on in-situ beam formwork with
heavy duty falsework.Photo: Gruppo Centro Nord
7
Why use Hybrid Concrete Construction? 3
An increasingly frequent maxim is the ratio 1 : 5 : 20014. This represents the relationship
between capital cost, operating costs and business costs during the life of a building. It
recognises the importance of 'whole life cost' and changes the emphasis from first cost
to whole-life cost. Here, HCC can excel, not only in terms of energy demands, which
relate to the ‘5’, but also in terms of comfort and aesthetic leading to productivity
gains, which relate to the ‘200’.
Project cost is inextricably linked to speed as faster programmes mean earlier investment
income, lower interest charges, reduced construction preliminaries and, consequently,
optimal development cost.
Speed depends on designs that are easy to procure and construct. Encouraging speed of
construction through buildability should be a fundamental objective of design. It may
take more design effort and require contractual flexibility, but it results in more satisfied
clients, designers, contractors and end-users.
HCC essentially takes work away from site and into the factory, thus reducing the duration
of operations critical to the overall programme on site. Precasting is not constrained by
site progress or conditions and can continue independently of on-site operations.
Construction on-site should be quick provided there has been sufficient co-ordination
and attention to detail. Some HCC techniques can reduce or eliminate the need for
follow-on trades such as ceilings and finishes. This enables even faster programme
times, but requires greater co-ordination and care in detail and protection.
Buildability is the extent to which design simplifies construction and eradicates
unnecessary cost, subject to the requirements of the completed building. HCC’s key
strength is buildability. The nature of HCC forces pre-planning and the resolution of
construction issues, for instance, just-in-time deliveries reducing crane hook time
become a natural part of the process.
High quality finishes can be most easily produced in factory conditions in precast units.
In-situ elements and joints are important structurally but may not need to achieve
the same quality of finish and so can be hidden from view. Where finishes to in-situ
elements are required, the quantities can be minimised.
Traditional formwork typically accounts for up to 40% of in-situ frame costs and can be
a slow option. The trend is towards faster construction, better quality, more prefabrication
and reduced site activity. These demands can be met by HCC, where a high percentage
of the work is carried out in a factory and requires less skilled on-site labour than
traditional methods.
Speed
Buildability
Construction
6
3 Why use Hybrid Concrete Construction?
while precast concrete promotes speed and high quality. Combining the two by
adopting hybrid techniques gives even greater speed, quality and overall economy.
The resulting elemental cost of the frame may be higher, but total project costs are very
often lower than more conventional frames due to time and buildability savings on site.
For instance, use of a hybrid concrete frame instead of a composite steel frame on a
shell-and-core office project in central London led to savings of 29% and increased net
lettable floor area from 33,700 m2 to 38,200 m2 – (a 13% increase)11.
Whole-life costs are especially important for owner-occupiers and PFI operators. HCCs
can help reduce energy requirements – they give excellent facility for fabric energy
storage – using the thermal mass of concrete to moderate energy demands in cooling
and heating buildings.
Figure 3Toyota (GB) interior
Showing exposed precast concrete floor units.Photo: Barry Bulley/Trent
1 5 200
CAPITAL COST COST IN USE BUSINESS COSTS
To operate and maintain the building will cost five times the capital costs over the life of the building. However, thecost to the business, including salaries and staff productivity, of occupying the asset is 200 times the capital cost.
In some quarters this has been extended by attributing 0.1 to the cost of design and 1000 to the cost of theoutputs from the building.
Table 1 Long-term costs
of buildings14
HCC reduces the potential for accidents by providing successive working platforms on
a generally less cluttered site. Safety aspects of leading-edge work are similar to, and
should be guided by, recommendations for precast flooring12. Precast spandrel beams
can provide immediate edge protection.
A high proportion of the work is carried out in the precast factory by experienced
personnel. On site, the innovative use of HCC and the fact that buildability is a key
concern helps ensure that each safety plan is drafted on the individual project’s merits.
Concrete produces eminently lettable buildings which are stable, robust, fire resistant
and adaptable, as well as solid, quiet and essentially vibration free. Equally concrete's
thermal properties can be exploited in naturally ventilated low-energy buildings. The
finish and shape of exposed units can be used to help with even distribution of lighting
levels and to reduce noise levels..
Structurally, concrete is very versatile. Long spans can be achieved using large units, or
by pre-stressing or post-tensioning. Precast units can be 'welded' together using modern
very high strength concretes, which allow full tension laps between reinforcing bars to
be achieved in laps of only six diameters13.
HCC has much to offer. It can respond to the often competing needs for economy,
safety, speed, quality, flexibility, durability, service integration, appearance, function,
material availability and preferred construction methods.
HCC requires a high level of commitment from all parties at all stages of the design and
construction process and from all the contributors to that process. For full advantage
to be taken, HCC should be considered at the beginning of the design process because
it becomes progressively more difficult to influence design and reduce costs as design
development proceeds.
The remainder of this publication is devoted to best practice guidance so that the
commitment required might be better directed and the advantages of HCC are fully
exploited and delivered consistently.
9
Best Practice Guidance for Hybrid Concrete Construction 4
4. Best Practice Guidance
The ‘new’ processes necessary to achieve best practice in HCC are shown in Figure 4 as
the ‘Best Practice Guidance for Hybrid Concrete Construction process map’.
This process map has been derived from two larger process models developed during
the research project described in Appendix A.2. The larger models were developed,
refined and honed through a series of thirteen individual interviews with practitioners
and five workshops. One model illustrated the whole process and reflected what the
interviewees considered to be the ‘how it should be’ process within an Egan-compliant
procurement framework. This is presented as Figure 5. Another model (not featured)
described ‘how it is’. Figure 4 highlights the differences between the two larger models
and shows how to make ‘how it is’ into ‘how it should be’.
Figures 4 and 5 are aimed at achieving best value, as defined by the client, through
partnering and collaborative team work. They have been aligned with RIBA Stages of
Work 15; Process Protocol 7, a tool for looking at the procurement process in construction
projects; and with research by Gray16 and Barrett17 into in-situ and HCC processes.
Usefully, these new route maps can be applied to achieve best practice in all concrete
frame construction: they are considered to be equally applicable to in-situ, HCC or
precast concrete frame construction.
The ‘new’ processes shown in Figure 4 are explained in more detail below.
Early involvement of specialist contractorsDuring the early part of the procurement process the project manager should facilitate
the involvement of contractors and specialists much earlier than is traditionally the
case. Specialists should be appointed during conceptual design while structural options
are still being considered. This allows committed specialist knowledge to be brought to
bear at the time when options are being chosen. There may be contractual ramifications
arising from this change, but design becomes a much more participative affair.
For contractors, early appointment allows them to be committed to a project with the
confidence that their input will be rewarded. Design decisions are part-owned by the
eventual constructors, which benefits the whole project. Without early appointment (or
reward) contractors, in a commercial world, will not give more than courteous attention
to helping a project in the initial stages when their ideas and experience might
ultimately benefit another company. For example, one leading specialist company
usually sets a limit of one day of free advice per project.
Early appointment of specialist contractors goes against traditional tendering processes,
but this is the very nub of partnering. The client has the option of tendering or trusting,
8
3 Why use Hybrid Concrete Construction?
Safety
Other benefits
Summary
Best practice
New processes for best practice
11
Best Practice Guidance for Hybrid Concrete Construction 4
LFC should be approached and, ideally, appointed after initial conceptual design makes it
clear that an HCC solution may be suitable. Specialists’ knowledge can then be brought
to bear in working up concepts into viable schemes and is also available to help with
detailed design and buildability issues. The model moves away from the traditional
relationship where specialist contractors are detached from the design process.
Best valueThe model is devised around a more ‘Eganesque’ procurement regime, whereby best
value, partnering and project feedback play a much stronger part than is the case in
more traditional forms of procurement. Traditional procurement routes are based
on competitive practices, which often preclude the formulation of teams and the
achievement of a best value outcome. The emphasis in this new model is on achieving
10
4 Best Practice Guidance for Hybrid Concrete Construction
but tendering costs time and it also tends to create adversarial relationships from the
start. Trust encourages teamwork.
Lead frame contractorsIn the model, a lead frame contractor (LFC) is appointed to take overall responsibility
for the structure. This role could be undertaken by a multi-disciplinary firm, a precaster
or an in-situ contractor. The LFC could be large enough to undertake the whole frame
package themselves or act as the single point of responsibility, procuring various
work packages from other specialist suppliers, which might include precasters, in-situ
contractors or even steel fabricators.
LFC is a function recognised in construction management methods of procurement. An
Figure 4Best Practice
Guidance for
Hybrid Concrete
Construction
process map
Gateway (see ProcessProtocol)7
Appointment
Blue textRecommended‘new’ ways ofworking
Black textNormal practice
HPIHybrid ConcreteConstructionPerformanceIndicators (ourversion of KPIs)
Define ‘best value’.
Undertake value andrisk assessment.
Think HCC.
Think HCC.
.
Develop FES (Fabric Energy Storage)strategy.
Agree terms for earlyinvolvement.
Agree terms forearly involvement.Liaise withspecialist suppliers.Provide advice.
Provide advice asrequired.
Propose HPIs.Carry out ‘best value’workshop.Addresssustainability.
Evaluate qualityrequirements of frame.
Agree HCC option.
Agree FES strategy.
Agree HPIs. Participatein ‘best value’workshop.
Agree HPIs. Participatein ‘best value’ workshop.Provide technical andfinancial advice. Finalisestructural concept.
Agree HPIs. Participatein ‘best value’ workshop.Provide advice.
Participate in ‘best value’workshop if required.
Agree information flowsand approvals procedure.Facilitate contractor helpin design.
Visit specialists. Checkfor repetition. Integratestructure and services.
Agree HCC specification.Check for repetition.Integrate with services.
Integrate structure and services.
Liaise with designers toproduce final scheme.
Liaise with designers &specialist suppliers. Startproduction drawings.Provide advice.
Run an ‘open book’.Start productiondrawings.
Agree strategy for on-sitedecision making.
Liaise with LFC (andspecialist suppliers).
Liaise with specialistsuppliers to agree startdates, method statements,H&S plan and productiondrawings.
Generate productiondrawings. Produce methodstatement & H&S plan.
Measure performanceagainst HPIs
Agree programme.
Participate in virtualrun through.
Monitor performanceagainst HPIs.
Measure performanceagainst HPIs
Erect frame.
Erect frame.
Participate in workshop.
Arrange workshop.Feedback and makerecommendations for future projects.
Make recommendationsfor future projects.Participate in projectfeedback workshop.
z`
Participate in workshop.Give feedback.Make recommendations.
DESIGN (1)
Work up chosen option
DESIGN (2)
Production information
CONSTRUCTION(1)
Off-site manufacture
CONSTRUCTION(2)
On-site work
USE (1)
Post-handover
USE (2)
Occupancy
BRIEFING
Demonstrate the need
FEASIBILITY
Is it worth doing?
CONCEPTUALDESIGN (1)
Consider the options
CONCEPTUALDESIGN (2)
Choose the option
PARTY HBased on traditional procurement
WORK STAGE h
DESCRIPTION h
CLIENT
PROJECT MANAGER
ARCHITECT
ENGINEER
OTHER DESIGNERS(INCLUDING QS)
MAINCONTRACTOR/ CONSTRUCTIONMANAGER
LEAD FRAMECONTRACTOR
SPECIALISTSUPPLIERS
END USER
Facilitate earlyspecialist involvement.
Measure performance against HPIs.
£
£
£
£
v v v vv
vKEY
WORKSHOPS h(see Table 4)
0: REUNION 1: DESIGN ROUND TABLE 2: START UP 3: RISK 4: PRE-CONSTRUCTION 5: POST-COMPLETIONREVIEW
2: START UP
13
Best Practice Guidance for Hybrid Concrete Construction 4
Value Indicators and measuring performance Value-based methods require that value be measured (or at least estimated). First cost
should not be the only indicator of value and appropriate performance indicators need
to be selected and used.
Suitable indicators for HCC are presented in Table 2, with those towards the top being
the more important. The top six of these indicators might form the basis of HCC
Performance Indicators (HPIs) for a specific project.
Various forms of construction can be compared for ‘value’ by scoring each option
against indicators chosen and weighted by the client. Integrating score and weighting
gives a measure by which options can be compared, objectively.
Another indicator, safety, is an absolute necessity and must always be addressed.
Work stages The procurement process can be broken down into a series of work stages. There are
several ways of describing these work stages. Table 3 shows how the ‘work stages’
used in this publication align with the better known RIBA Stages of Work15 which
reflect traditional methods of procurement, and with Process Protocol Phases7, which
reflect more contemporary methods of procurement. These work stages were found
to best describe HCC. Indeed, they are particularly relevant to the procurement of
structure and are certainly relevant to the procurement of all forms of concrete frame
construction18.
12
4 Best Practice Guidance for Hybrid Concrete Construction
Table 2 Value Indicators:
Hybrid Concrete
Construction
Performance
Indicators (HPIs)18
Note* The RIBA stages G and H
have been placed in this boxfor a reason. In traditionalprocurement, tenders can
interfere with RIBA Plan Stage F– Production Information,
which precludes any benefit tothe design process from the
early involvement of specialists.
Table 3Work stages
DESIGN (1)
Work up chosen option
DESIGN (2)
Production information
CONSTRUCTION(1)
Off-site manufacture
CONSTRUCTION(2)
On-site work
USE (1)
Post-handover
USE (2)
Occupancy
BRIEFING
Demonstrate the need
FEASIBILITY
Is it worth doing?
CONCEPTUALDESIGN (1)
Consider the options
CONCEPTUALDESIGN (2)
Choose the option
WORK STAGE h
DESCRIPTION h
RIBA PLAN OFWORK STAGE(TRADITIONAL)
PROCESSPROTOCOL PHASES (NON-TRADITIONAL)
Phase 0:Demon-strating theneed.
Phase 1:Conceptionof need.
Phase 2:Outlinefeasibility.
Phase 3:Substantivefeasibilitystudy &outlinefinancialauthority.
AAppraisal.
B Strategic brief.
C Outline proposals.
Phase 4:Outline conceptual design.
Phase 5:Full conceptual design.
G Tenderdocuments*.
H Tenderaction*.
D Detailed proposals.
E Final proposals.
F Production information.
J Mobilisation.
K Constructionto practicalcompletion.
L After practical completion.
Phase 6:Co-ordinated design,procurement & fullfinancial authority.
Phase 7:Production information.
Phase 8:Construction.
Phase 9:Operation & maintenance.
best value for the client. One of the ramifications of this is that the project manager,
in particular, has more responsibility for ‘continuous improvement’ aspects such as
running Value Engineering workshops, monitoring on-going progress and organising
end-of-project feedback.
The question then becomes “What is best value?” This, of course, has to be decided by
an individual client for an individual project. Traditionally, value equated to cost, but
notions of whole-life costs, maintenance, comfort, aesthetics, worker efficiency, staff
retention, safety, certainty of delivery, the introduction of other Key Performance
Indicators 6 etc. make the modern concept of best value much more rational and
therefore valid. One of the roles of the design and project management teams is to
assess the relative importance of these indicators to particular clients on particular
projects. The problem then becomes one of measurement.
INDICATORS NOTES
Speed Productivity/efficiency on site; time; programme; lead-in time.
Cost First cost; running costs; whole-life costs; business costs; cost of package; value for money.
Spans/lettable area Floor depths/building height; preferred grid; vertical access routes; third-party aspects (spans).
Flexibility in use Low maintenance; good performance.
Fire Fire protection; robust fire protection; fire resistance.
Services integration Air conditioning options; control; sound/thermal insulation; fabric energy storage.
Buildability ‘Being tolerant’; tolerances; planning.
Environmental Sustainability indicators; operational energy; waste.
Finish Certainty of finish; architectural merit; visual surfaces.
Quality Certainty of quality of product.
Site conditions Access; site constraints; logistics.
Structure Dynamic requirements; load carrying ability; overall stability; temporary stability.
Market conditions Risk; capacity; resources; capacity available; certainty.
RolesSpecific feedback on the ‘how it should be’ model (Figure 5) included comments on
roles and responsibilities. Some useful ideas for improving ‘traditional’ communications
between the various professions involved are shown in Table 5.
Project workshopsProject workshops are designed to facilitate better communication, promote best value
and prevent, as far as possible, unforeseen problems from arising 18. The workshops lead
towards a clear feedback loop for continuous improvement, project and project-to-
project learning. The suggested programme of formalised workshops is shown in Table 4.
This recommended programme of workshops was perhaps the most insightful theme to
emerge from research. There was steady feedback on the importance of inclusive and
participative workshops throughout the course of a project. Regular design development
and progress meetings would continue as a matter of course.
15
Best Practice Guidance for Hybrid Concrete Construction 4
14
4 Best Practice Guidance for Hybrid Concrete Construction
r Produce separate ‘concrete profile’ CAD drawings, extracting and isolating the structural frame from itssurroundings and making it simpler for the engineer and lead frame contractor to consider.
r Hand over drawings and calculations to specialist suppliers to accelerate the ‘taking off’ process and prevent‘reinventing the wheel’.
r Develop a pre-briefing document (including M&E requirements) and with the design team, confirm the business plan, develop the design for it and organise the money for the design.
r Keep an ‘interface register’ between clusters to record anomalies and clashes for easy resolution during design development.
r Consider presenting a ‘concrete concept’ that responds to the client’s priorities rather than purely technicalperformance criteria.
r Signal their willingness to work in the consulting engineer’s office during design development to aid, forexample, the design of connections.
r Carry out an ‘as built’ survey at end of construction for the record.
r Look at costs more holistically with whole-life costing, providing a better service to the client.r Analyse growth in costs to see where lessons lie in patterns of spending for the next project.
r Optimise hook time for cranes on site.r Develop innovative connections.
Table 5 Roles ARCHITECT
CONSULTING ENGINEER
CLIENT / DEVELOPER
MAIN CONTRACTOR / CONSTRUCTION MANAGER
LEAD FRAME CONTRACTOR
QUANTITY SURVEYOR
PRECAST MANUFACTURER
Briefing
Feasibility
Conceptual Design (1) Conceptual Design (2)
Conceptual Design (2)Design (1)
Design (2)
Use (1)
�Reunion�
Design team �round table�
Start-up / best value
Risk workshop
Pre-construction
Post-completion
Usually takes place if the project partners areundertaking repeat business, but notexclusively. Aim is to check lessons fromprevious projects – the client, in particular,may have input here.
Aim is to clarify client aspirations; to establish‘what do we want’. This takes place after thebudget has been agreed.
This workshop takes place on appointment of all the specialists (sometimes ValueEngineering may be used here as the designconcept should be taking shape).
Now that the project is understood, the aimis to generate creative solutions for anyinterface problems that arise, rather thantrying to ‘fix’ them on site.
The purpose is to check that everyone iscontent with the programme on site and to run through the final details with ideallya virtual reality simulation to help thediscussion (this should be developed duringdetailed design).
The project review lessons are drawn outduring the workshop for the next project.(This is vital as it draws everyone backtogether after what may be a lengthy project process).
Client, project manager, design team,quantity surveyor (QS) if appointed. Maincontractor and perhaps a few selectedsuppliers may be invited. Project manager will take the lead.
Client, project manager, design team. Quantitysurveyor, if appointed, will take the lead. Maincontractor and/or specialists may be invited.
Main contractor/construction manager likelyto take the lead. All specialist contractors andsuppliers, project manager, design team andQS may be asked to attend.The client maybe represented by the project manager.
Main contractor/construction manager takesthe lead.All specialist contractors and suppliersshould attend. Project manager, design teamand QS may be invited.The client may berepresented by the project manager.
Main contractor/construction manager takes the lead. All specialist contractors andsuppliers should attend. Project manager,design team and QS will be invited.The client may be represented by the projectmanager.
Client and client advisors will take the lead.All project participants are invited and should attend.
Table 4Recommended
workshops and review
meetings
FUNCTION / DESCRIPTION WHO SHOULD ATTEND?WORK STAGE TITLE
17
Achieving best practice 5
When precast items are used, negotiations usually go through several stages and
everyone benefits if customers and clients have already considered and prepared some
answers to the questions highlighted in Table 6. Beware of imposing non-essential
constraints as these can restrict flexibility of design later on.
Price on value: resist pricing on initial cost only and resist ‘last job’ syndrome. Definitions
of value/value for money are different for different parties, (e.g. some may advocate
lowest initial cost, fastest, lowest whole-life cost, or most satisfactory to the user).
Do these really reflect the client’s requirements? Are design and construction teams
influenced by process issues rather than product?
The structural design of hybrid forms of construction can be seen as a barrier. However,
designers are comfortable with in-situ concrete design and, in general, are comfortable
with precast concrete design. They may be less familiar with composite concrete
design. However, composite concrete elements may be considered as being monolithic
and homogeneous. In the case of proprietary items, design is often covered by
manufacturers’ literature. For bespoke works, temporary load cases, the construction
stage loading and final load cases all need to be considered. Notes on the structural
design of HCC are given in Appendix A.3.
HCC needs a main contractor with commitment to the HCC method as well as
civil/structural expertise. Some of the best examples of HCCs have been alternatives
driven by trade contractors that have been accepted by enlightened construction
managers. In the future, as designs become more sophisticated, the use of HCCs will
become more common, increasing the need for specialist design input.
Contractors should at least be given the opportunity to comment on initial designs.
HCC is a very positive way to create large areas of floor very quickly, but advantages
can be lost if the in-situ reinforced concrete work is complex.
It is important to obtain specialist knowledge as soon as possible. The degree of
importance depends on the degree of innovation/newness and this influences the
choice of procurement route. Generally, generic forms of HCC such as using hollowcore
slabs on in-situ beams can be constructed using traditional forms of contract – but
even these relatively simple forms of HCC still benefit from specialist design input.
Bespoke types of HCC benefit from using non-traditional contractual arrangements
(e.g. construction management, design and build). Using inappropriate forms of contract
can result in adversarial relationships and lack of trust. But trust is the very basis of
teamwork. Bespoke HCC solutions are more likely to be successful on large projects
where investment in design and management time should pay back handsomely.
The Standard Method of Measurement (SMM) is ineffective in assessing overall
process benefits.
16
5 Achieving best practice
5. Achieving best practice
The ‘how it should be’ process model is presented in Figure 5. It is the key to best
practice for HCC.
To achieve best results, best practice needs to be applied throughout the procurement
process. Chapter 4 highlighted the new aspects and this chapter expands on these to
guide users through the whole procurement process, from feasibility to completion and
use. Guidance recommendations are supplemented by anecdotal points.
Communication and two-way understanding is central to achieving best practice. Good
performance requires contractors to understand what clients want but equally, clients
and designers should know what contractors need in order to perform. To help with this,
an outline of the process, from the specialist contractor’s point of view, is presented
throughout this chapter as Tables 6, 7, 9 and 10. An understanding of this process and
the issues involved will help ensure that agreements on timescales, quality, performance,
budgets, costs and rewards are realistic, practical and ultimately produce a highly
satisfactory result.
Think HCC! HCC has to be thought of as one of the options to be studied by the
architect and structural engineer at feasibility stage.
If HCC is not presented early on as an option to address the client’s requirements, then
it is much less likely to be used and the opportunity will have been lost. HCC solutions
can make a project feasible and in design-and-build tenders, it can make the difference
between winning and losing.
Think in terms of partnering – for instance, set up an open book approach for
procurement and remember weeks can be lost in a traditional tendering process.
An open book arrangement is one whereby:
■ actual costs are paid with agreed margins for overheads and profit
■ the difference between the actual cost and target cost is shared in a specified way
between the client and contractor – pain and gain are shared on an agreed basis
■ sharing the risk acts as an incentive mechanism to promote efficient working.
The decision to prefabricate should come early. Where HCC or indeed precast
construction is a possibility, seek advice from a precaster or talk to a LFC. Preferably
make visits to precasters. Precasters should be chosen not only on cost and value but
also on suitability, availability and quality.
Feasibility stage
Conceptual Design (1)
PRE-ENQUIRY ✔ Gain knowledge✔ Think precast at earliest concept stage✔ Evaluate quality requirements✔ Understand what can realistically be achieved✔ Seek specialist advice for initial project concept✔ Be able to discuss outline concepts of project at
initial contact e.g.r Type and user Site geometry and characteristicsr Grid requirementsr Unit sizesr Site accessr Environmental considerationsr Building performance/lifetime effectr Adequacy of supplyr Skill shortagesr Programme requirementsr Overall costr Weight restrictions on units.
✔ Don’t expect initial answers to be definitiveon price or programme, methods, etc.
r Arrange to meet precaster r Teamwork/trust – does it need to go
out to tender? Is partnering feasible?
ENQUIRY ✔ Define responsibilities✔ Who is responsible for what? – Define
responsibilities early and expect to maintain a cost-to-risk balance. Ensure other teammembers take responsibilities commensurate to their earnings and expertise
✔ Balance cost versus risk✔ Clarity✔ Who are the players and how do they relate?✔ Seek advice on specifications, both design and
architectural, e.g. tolerances and finishes✔ Don’t just print off the specification used on
the last job✔ Send specifications to precasters for comment
prior to issue✔ Commercial terms and conditions, standard /
non standard:r Parent company guarantees/performance
bondsr Retentionsr Warrantiesr Liquid and ascertained damagesr ‘Pass the risk down’ syndrome
✔ Financial✔ Payments – when? – on time?✔ Don’t ‘scatter gun’ the enquiry: effort will be
proportional to chance of getting the job – don’t expect too many free ideas
COMMITMENT ✔ Financial✔ Contractual✔ Ability to provide and deliver
Table 6Precast Checklist 1:
From initial enquiry to contract
19
Achieving best practice 5
18
5 Achieving best practice
PARTY HBased on traditional procurement
WORK STAGE h
DESCRIPTION h
Obtain userfeedback. Developpre-briefingdocument, discussfunding mechanisms.Brief project manager(if used); briefarchitect; brief QS.
CLIENT
Agree business plan.Agree M&E.Define ‘best value’.Liaise with PM oncontracts, etc.Agree costs;agree budgets.
Liaise with PM to facilitate early involvement.Agree terms for earlyinvolvement.Provide comment as required.
Provide comment as required.
Provide comment asrequired.Give final approvals.
Provide comment as required.Give approvals as required.
Provide comment as required. Provide comment as required.Check progress.
Participate in project feedbackworkshop.Agree recommendations for future projects.Receive building from MC/CM.
GATEAgreeneeds/aspirations.
SOFTGATE Decide ‘Is it worth it?’
GATEApprovescheme design.
GATEAgreefinaldesigndrawings.
Agree servicesrequired by client.Establish client needs.
ARCHITECT (latest)
Obtain outlineplanning permission.Think hybrid (HCC)!Refine client needs.Formulate designideas.
Develop scheme design.Develop specification.Generate floor plans etc.Seek advice from specialists;discuss plans with engineer.
Obtain full planningpermission.Evaluate qualityrequirements of frame.Agree scheme design.
Generate ‘concrete frameprofile’ drawings.Visit specialists, agreeHCC specification, checkdesign for optimumrepetition, integratestructure and services.Work up final drawings; refinespecification;liaise with engineer;liaise with other designers.
Liaise with LFC on production drawings.Invite LFC to work in engineer’s office.Obtain Building Regs approval.Check against specification.Produce some detail drawings.
Oversee manufacture.Approve moulds.Approve finishes.
Provide information as required.Oversee construction.Give final approvals?
Make recommendations for futureprojects.Participate in project feedbackworkshop.DELIVER-
ABLEDefineclientneeds/aspirations.
DELIVER-ABLEPresentdesignideas.
DELIVER-ABLEHand overfinaldrawings.
DELIVERABLEPresentscheme design.
GATESign offworks.
0: REUNION Only held if project participantshave worked together previously.
1: DESIGN ROUND TABLEClient and design team meet forthe first time, with others invitedif appropriate.
2: START UPHeld when all participants areappointed.Value engineering may be used.
3: RISK WORKSHOPNow the project is understood,effort is made to iron out anyproblems.
4: PRE-CONSTRUCTIONEveryone convenes prior to start on site to agree procedures etc.
5: POST-COMPLETION REVIEWEveryone participates in this ‘post-mortem’.
Make requirements known.Undertake survey of user needs.END USER Provide comment as required. Provide comment as required. Participate in ‘best value’ workshop
if required.Provide comment as required.
Provide comment as required. Participate in project feedbackworkshop (if required).
SPECIALISTSUPPLIERS(e.g. in-situ contractor,precaster or steel fabricator)
Optional entry point (with LFC).
Engage in a negotiation to obtainletter of intent.Provide advice as required (e.g. costs, programme, structure,environmental aspects andfinishes).
Liaise with LFC, establish an order of cost.Agree HPIs, participate in ‘best value’workshop, provide advice as required(e.g. costs, programme, structure,environmental aspects and finishes).
Run an ‘open book’.Start production drawings.
Develop inventiveconnections.Optimise hook time.Generate productiondrawings.Produce own methodstatement, produce own H&S plan.
Participate in VR frame erection run through.
Erect frame to agreed programme. Participate in project feedbackworkshop.
DELIVER-ABLEFinaliseproductiondrawings.
LEAD FRAMECONTRACTOR(i.e. Multi-disciplinary firm,in-situ contractor or precaster)
Optional entry point.
Agree terms for early involvement.Liaise with potential specialistsuppliers, provide advice asrequired (e.g. potential structuralsolutions, budget costings ofalternative HCC combinations).
Liaise with MC/CM.Agree frame responsibilities.Present the ‘concrete concept’.Agree HPIs, participate in ‘bestvalue’ workshop, provide technicaland financial advice as required,finalise desired structural concept.
Liaise with designers to produce final scheme.Liaise with specialist suppliers,start production drawings, providetechnical and financial advice asrequired.
Send team to work in engineer’s office.Participate in VR erection program.Liaise with specialistsuppliers to agree startdates during erection.Produce own methodstatement, produce ownH&S plan, liaise with MC/CM.
Agree programme to ensure sitedelivery times (e.g. mouldprocurement, precast unit production)with specialist suppliers.Carry out enabling works.
Carry out full ‘as-built’ survey.Erect frame to agreed programme.
Participate in project feedbackworkshop.Negotiate partnering on futureprojects.DELIVER-
ABLEAgreeproductiondrawings.
MAIN CONTRACTOR /CONSTRUCTIONMANAGER
Optional entry point.Provide advice as required.
Define packages / clusters.Advise on site logistics/buildability.Agree terms for early involvement.Provide advice as required.
Establish an ‘interface register’.Agree HCC frame responsibilitieswith LFC.Agree HPIs, participate in ‘bestvalue’ workshop.Provide advice as required.
Start using VR erection program.Liaise with designers to produce final scheme.Generate ‘main’ method statement.Produce H&S plan.Produce construction programme.Agree specialist sub-contracts.
Confirm HPIs.Continue to use VR erection program.Liaise with LFC (and specialist suppliers).Liaise with engineer.Agree method statements.Agree H&S plans.Agree deliveries.
Carry out final VR run-through.Measure performanceagainst HPIs.Carry out enabling works.
Measure performanceagainst HPIs.Measure specialists’performance.Manage construction.
Participate in project feedbackworkshop.Feedback on HPIs to PM/client.Feedback on specialists’ performance.Make recommendations for futureprojects.
SOFT GATEAgreeschedulebased on VR erectionrun-through.
GATEHand overto client.
CHECKINGAUTHORITIES
Advise on planning permission. Provide institutional checks. Advise on planning permission.Provide institutional checks.
Provide Building Regs approval. Provide Institutional checks.Provide Building Regs approval.
Oversee construction.
OTHER DESIGNPROFESSIONALSe.g. M&E Engineer Think HCC!
Agree basic M&E strategy.Advise PM as required.
Develop FES strategy.Develop services strategy.Provide advice as required.
Agree FES strategy.Agree scheme design.
Integrate structure and services.Work up layouts; liaise with engineer; liaise witharchitect.
Refine layouts (if required). Provide information as required. Provide information as required.Oversee construction.Give final approvals?
Make recommendations for futureprojects.Participate in project feedbackworkshop.DELIVER-
ABLEHand overlayouts.
GATESign offworks.
ENGINEER
Think hybrid (HCC)!Agree basic M&E strategy.Advise PM as required.
Assess HCC options.Develop structural concept.Discuss plans with architect;seek advice from specialists;discuss construction programme.
Agree HCC option.Agree scheme design.
Hand over designdrawings/calcs to LFC/specialists.Agree HCC specification,check design for optimumrepetition.Integrate structure and services.Work up GA drawings; carryout design calculations; liaisewith architect; liaise with otherdesigners;discuss ‘main’methodstatement with MC/CM.
Check method statements.Check specialists drawings.Refine GA drawings (if required).Generate RC drawings.
Oversee manufacture.Approve moulds.Approve finishes.
Provide information as required.Oversee construction.Give final approvals?
Make recommendations for futureprojects.Participate in project feedbackworkshop.DELIVERABLE
Produce schemedrawings.
DELIVER-ABLEHand overGAdrawings.
GATESign offworks.
Discuss funding mechanisms.Agree services required by client.
QUANTITYSURVEYOR
(latest)
Liaise with PM on cost plans. Expectto pay for LFC/specialist’s advice.Assess costs; assess budgets; advise PM as required.
Provide whole-life costinformation.Review forms of contract.Provide advice as required.
Help administer contracts.Provide advice as required.Agree scheme design.
Review costs.Review budgets.Report to PM as required.
Review costs.Review budgets.Review contracts.
Review costs.Review contracts.Agree payments with PM.
Analyse growth in contract costs.Participate in project feedbackworkshop.
Discuss funding mechanisms,define team roles, make contractconditions clear, make terms andconditions fair, instigate ‘no blame’culture.Agree services required by client.
PROJECT MANAGER
(latest)
Expect to pay for LFC/ specialist’s advice.Undertake value assessment.Undertake risk assessment.Agree form of contract.
Propose terms for earlyinvolvement.Identify appropriate specialists.Establish design parameters.Manage design development.
Propose HPIs.Carry out ‘best value’ workshop.Address sustainabilityAgree overall programme.Agree scheme design.
Agree design information flows, agreedesign approvals procedure, facilitatecontractor involvement in design,convene final approvals process.Manage design process.Agree ‘main’ contract; appoint MC orCM; liaise with MC/CM.
Agree communication strategy for on-site decision making.Manage design process.Liaise with designers.Liaise with MC/CM.
Manage construction process.Liaise with MC/CM.
Liaise with MC/CM on HPIs andperformance monitoring.Manage construction process.Liaise with MC/CM.Agree payments with QS.
Carry out project feedback workshop.Feedback on HPIs to client.Make recommendations for futureprojects.
BRIEFING
[A]
Demonstrate the need
FEASIBILITY
[B]
Is it worth doing?
CONCEPTUALDESIGN (1)
Consider the options
CONCEPTUALDESIGN (2)[D & G/ H:TENDERS]
Choose the option
DESIGN (1)
[E]
Work up chosen option
DESIGN (2)
[F]
Production information
CONSTRUCTION (1)
[K]
Off-site manufacture
CONSTRUCTION (2)
[K]
On-site work
USE (1)
[L]
Post-handover
USE (2)
Occupancy
£
£
£ £
£
£ £
£ £
£ £
£ £
£
£
v
★ ★
v
★ ★
★★
★
★
★
v v
v
v
v
vv
This is a generic model basedon what is considered to be
good practice within an Egan-compliant procurement
framework.The modeldescribes a scenario in which a
project manager facilitatesearly involvement of
contractor and specialists. Thewhole model is oriented
towards achieving best value(as defined by the client) via
‘partnering’ and collaborativeteam working.
Figure 5The ‘how it should be’
process map
WORKSHOPS hExact timing will depend on contract
type (partnering or prime contracting).
£
v
★
[A]Approximatecorrelation withRIBA Plan ofWork stages
Red textActivities thatshould takeplace to achievebest practice
Blue textEvidence frominterviews
Black textNormal practice
GATEAn activity that must becompleted forthe project tocontinue
Formal entrance/appointment ofa party
DELIVERABLEA key deliverablethat must beproduced for the project tocontinue
HPIHybrid ConcreteConstructionPerformanceIndicators (ourversion of KPIs)
KEY
21
Achieving best practice 5
Potentially, HCC can result in interface problems or clashes which are different from
traditional contracts (e.g. storage, phasing). If identified early on, these risks can be
managed and controlled. HCC is good for single point responsibility, hence the advocacy
of a LFC.
An interface register should be set up and maintained to highlight the possible
risks/interface difficulties that might occur, particularly between packages or clusters,
i.e. frame and cladding, frame and services.
While there is a need for good services integration, HCC timescales do not necessarily
tally with services design timescales. Usually, the M&E services design will need to be
well developed by the time an HCC scheme is finalised, and it should be finalised by the
time an HCC scheme is detailed. Although this is not a problem specific to HCCs, it can
have detrimental effects on HCCs if late changes are required. Managing information
about service voids, especially large ones, is important. For example, is the coring of
holes a strategy or defeat?
Tolerances must be realistic and the precaster and engineer should discuss, establish
and agree the scope and practicality of tolerances for a specific project. Equally, it
is important to address any differences between tolerances for precast and in-situ
elements. This is also a good time to discuss fixings – the precaster should give early
advice.
Teamwork with buy-in from all parties early on creates confidence. There needs to be
a high degree of co-ordination and this leads to ‘ownership’ of the project and team
bonding. All parties become motivated to work closely together.
There may be a need to assure the client that HCC is the right option. The architect, or
more often the engineer, needs to act as a ‘champion’, explaining and promoting the
benefits of HCC. When LFCs come on board, they can confirm budgets and establish
‘can do’ confidence.
20
5 Achieving best practice
Quality needs to be defined, planned and managed. It needs commitment and
accountability which are best achieved by a formal Quality Assurance scheme. Various
aspects must be considered including:
■ accuracy or quality of surface finish
■ quality of design or construction
■ performance
■ effect on other elements or processes
■ fitness for purpose.
Factory conditions for precast element production allow high standards of workmanship,
whereas in-situ elements may not achieve the same standards. If necessary these in-situ
elements can usually be hidden from view but if not, agree and issue guidelines on
consistency of finish including a strategy on protection and making good any damage.
Continue to make a case for HCC.
When considering forms of contract, it should be recognised that traditional forms of
contract can make HCC difficult because they preclude the vital early involvement of
specialist contractors. The traditional tender process involves a large amount of often
unproductive work – and usually there is a mass of information to assimilate at once.
Negotiating with the various sub-contractors in a short tender period can be difficult
when there are many issues to be resolved.
Alternative forms of agreement can minimize these difficulties. They can reduce delays
in getting prices and reduce the risk of these delays inhibiting progress. Where first cost
is a prime concern, trust can be enhanced using an open book policy. The lead frame
contractor (LFC) is usually the most likely party to promote this idea. It enables the LFC
to test the market’s capacity and readiness, to compare estimates and talk in detail to
potential suppliers without resorting to formal competitive tendering. The client and
project manager must trust the LFC to undertake this task, so the LFC will have to make
a good case and demonstrate that there will be full transparency during the use of an
open book.
Pre-assembly requires considerable off-site management of off-site activities. There is
increased management of design, integration of design, early service design decisions,
approvals and communications. Design co-ordination means understanding supply
chains, planning and producing design information and approvals on time, for example,
services designs will have a significant impact on structure. The project manager should
map out the processes involved and issue guidelines on, for example, issuing information,
approvals procedures, change control and the methods by which production and
assembly knowledge are fed into the total design process. Project managers should
choose people who can deal with such issues.
ConceptualDesign (2)
23
Achieving best practice 5
oral exchange of information and informal, as well as formal, co-ordination between
architect, structural engineer, precaster, LFC, etc. on such issues as finishes, positions for
services, lifting sockets, etc.
The precaster should give early advice to the design team, to prevent problems later
(e.g. on fixings etc). Precasters are at their most efficient when they are able to progress
whole packages, rather than hit-and-miss sections. Units with an architectural quality of
finish need special attention from all.
Details should be discussed and resolved amongst the whole team – designers
(architectural and structural), contractors, precasters and the LFC. For example, lengths
of bearing for hollowcore units on one project were specified from a structural
perspective as being 75 mm minimum, 150 mm was achieved, but 225 mm was
wanted on site to facilitate buildability. The message didn’t get across to the design
team that the constructors wanted wide bearings. Equally, counter-arguments from the
designers (and quantity surveyors) did not get through to the constructors. This issue
should have been aired and decided upon well before construction. Most of the issues
that will need to be resolved with the precaster are highlighted in Table 7.
That said, buildability of HCCs is usually good because almost all the issues will have
been discussed and agreed before the building goes to site. But it must be designed in.
Agree and issue guidelines on:
■ Tolerances.
■ Dimensional constraints.
■ Making things fit together (e.g. cast low, fill or pack).
■ Craneage and transportation.
■ Design of temporary works.
■ Propping (e.g. Is temporary propping a real problem costwise, timewise or just
perception? Props at 1/2 or 1/3 spans may be considered satisfactory as they may
not freeze-up an area. However, staging left in place may well do so).
■ Concreting on site:
r special measures
r non-shrink concretes
r ready-mixed supply or batch small volumes on site
r can in-situ concrete be poured into tight positions (e.g. under the
hollowcore unit?)
r self compacting concrete.
■ Preparing precast units for concrete pours.
■ Detailing rules – as traditional construction? Should loose splice bars lap with bars
within the precast units?
■ Protection of finishes, details and projections.
■ Differential floor cambers on adjacent floor units.
■ How to stop joints leaking and the cost of sealing joints.
■ Alternative details (e.g. would continuity reinforcement get over the need for a nib?).
22
5 Achieving best practice
Before the design work begins in earnest there should be a pause to reflect and,
importantly, get client feedback.
If an open-book approach has been agreed, its administration and success will depend
on close working and good communication between the designers, the precasters, QS
and/or LFC. For teams with less experience of such an approach, an experienced member
should lead and ensure complete transparency. Reassurance and regular checking will
be necessary.
Because of the amount of information in circulation, HCC may not necessarily be an
easy process to manage. People need to be clear about their inputs to the process and
team ethos, especially when thinking and working outside ‘traditional’ methods.
The use of 3D modelling techniques, Virtual Reality (VR) simulation programmes, or
animation based on CAD should all be considered. Such tools can be very powerful in
managing/optimising the construction programme for an HCC structure, especially
because the method often involves quite specific sequences of component installation
and in-situ stitching on site, which can benefit from detailed visualisation.
Correct decisions made promptly and without later changes are key to managing the
process. Regular meetings with a ‘one-stop client’ and all other parties involved are
essential because time constraints will put pressure on design. This demands good
Design (1)
Figure 6Inland Revenue Building interior
The competition brief required value for money and a
fast-track construction programme. The design fully
exploited the potential of precast concrete and
prefabrication of other major structural elements to
achieve real buildability. The superstructure was
manufactured almost entirely off site, at the same time as
the in-situ construction of the substructure took place.Photo: Martine Hamilton-Knight/Built Vision
DESIGN
✔ General arrangement drawings
✔ Mould drawings
✔ Unit details
✔ Repeatability
✔ Calculations
✔ Approval periods
✔ Interface with other disciplines notably services
✔ Freeze dates
✔ Approval procedures
MOULD PROCUREMENT
✔ Standard/non standard/ complexity
✔ Internal/external/resourcing
✔ Type – timber/steel
✔ Quality
PRODUCTION
✔ Reinforcement, plates, bars, inserts
✔ Capacity
✔ Finishing
✔ Stripping
✔ Handling
✔ Storage
DELIVERY & ERECTION
✔ Unit size restraints
✔ Site restraints
✔ Management
✔ Falsework and formwork
✔ Health & safety/CDM
IN-SITU WORK
✔ Responsibilities
✔ Finish
✔ Falsework and formwork
✔ Reinforcement
✔ Concrete
✔ Concreting
✔ Curing and protection
✔ Depropping
Table 7Precast Checklist 2:
From design to start on site
25
Achieving best practice 5
and reference should be made to the National Structural Concrete Specification (NSCS)20,
which covers tolerances under Construction Accuracy (Table 8).
“To arrive at the optimum cost and buildability, a common understanding on
tolerances for the structure, cladding and finishes should be shared by all parties.
Discussion is needed at the design stage on any tighter tolerances envisaged, since
they will result in higher costs and may not, in any event, be realistic.
Common sense must prevail should any item fail to meet the tolerance specified. It
is important to consider whether the work is still acceptable, having regard to the
operations that follow and the intended use of the structure. Checking must be carried
out as construction proceeds so that any remedial work which is required can be
sensibly planned and executed.”
National Structural Concrete Specification20
The clauses provided in NSCS are intended to simplify tolerances. It should be noted
that the fit-up of abutting elements with different permitted deviations requires careful
consideration.
The factory-based precast concrete industry works to improve upon the component
tolerances specified in BS 8110.
A strategy to overcome potential problems should be put in place. For instance,
guidance for landing precast elements onto in-situ elements, especially in-situ columns,
should be developed. In this case a preferred detail might be to either:
■ cast columns 100 mm low, place a collar around the column, place precast floor
elements and concrete the remaining column with the floor topping or
■ with beam soffits temporarily supported in place with help from the column
formwork, cast the whole column in-situ as one.
24
5 Achieving best practice
Connections need to be well designed. They should be simple and adaptable with
realistic tolerances and plenty of repetition. Repeated use of the same details allows
optimisation of construction method.
Establish early on the responsibilities for falsework, remembering that the supply of
relevant information is a duty under Health & Safety Act/CDM regulations.
The National Structural Concrete Specification (NSCS)20 is ideally suited to in-situ, precast
and HCC. Under the NSCS approach, the specialist concrete contractor (SCC) builds what
is shown on the drawings to a specified standard of workmanship. Prescriptive restraints
have been avoided to enable the SCC’s experience to be used to achieve efficient
construction. This specification helps innovation, efficiency and competition. All parties
involved in the construction process benefit – from the client to the subcontractor:
■ Clients receive better, less costly construction.
■ Designers no longer have to devise their own standard specifications, but may
concentrate their efforts on writing the individual project specification.
■ Contractors are able to identify more clearly the risks and requirements of the project
and have more freedom to innovate and develop their own solutions.
Make sure the processes of HCC are clear to all. Programming problems mostly arise from
lack of familiarity with techniques and uncertainty of procurement and are particularly
likely to affect smaller projects, which do not necessarily have the management resources
to understand and control unfamiliar processes.
This is a busy period for the designers in co-ordinating design and technical information.
A high level of communication is required, especially between architect, structural
engineer and services designers as well as with the contractors, because of the large
amount of design checking perceived to be necessary. Interchanges need commitment
underpinned by mutual trust. HCC requires team players prepared to work closely
together and to ensure that others are not let down. Paper based communication will
not be sufficient. Regular round-table meetings with oral exchanges resolve issues faster
than a more conventional approach.
Resolving all the design details at the design stage gets it right on site. 3D, VR or
physical models help enormously. The architect and others in the design team need to
be supportive of the structural engineer to resolve issues such as impact of ‘builders’
work’ on site. Late tweaking of details distracts effort and costs money, these should
have been resolved earlier.
Realistic tolerances must be allowed for; small numbers in specifications are no answer.
Precast units are generally quality assured; nonetheless, realistic tolerances are needed
Design (2)
Table 8Extract from the National Structural
Concrete Specification20
TOLERANCES FOR FORMED ELEMENTS
The linear dimension of formed elements shall be accurate to within the following distances (where L is length, height or width of element in the direction considered).
L Permitted deviation, D mm
Up to and including 600 mm 8 mm
Over 600 mm up to and including 1.5 m 10 mm
Over 1.5 m up to and including 8 m 15 mm
Over 8 m up to and including 15 m 20 mm
Over 15 m up to and including 30 m 30 mm
Over 30 m 30 mm + 1 mm per metre or part
27
Achieving best practice 5
At this stage delivery, erection and
construction issues should have been
agreed (see Table 9). Where feasible, a
final VR run through should be carried
out. Confidence can be strengthened
by having warranties for materials/units
stored off site and by inspecting
prototypes of any bespoke precast
units – this gives excellent evidence
on aesthetics and value.
To save crane time, mark each precast
item with a reference identifying
orientation and lifting point positions
(consider bar-coding/e-tagging).
It is vital to protect precast units on
site, particularly architectural units,
otherwise they will not retain their
ex-mould appearance. There needs to
be a strategy for protection so propping
and protection must be carefully
planned. For instance, damp marine
ply may mark architectural units.
The main contractor should be
instructed not to carry out any
‘unauthorised’ remedial works or builders’ works to the precast units. These are
specialist tasks. Procedures for remedial works should be included in the specification.
Construction on site tends to be very quick; this is the reward for the effort in working
up the co-ordinated design. Examples are given in the case studies in chapter 6.
The post-completion workshop allows
all parties to the project to give feedback
to others and to learn from the other
members of the design and construction
team and from users (see Table 10).
The outcome should be measured in
terms of Performance Indicators and,
in particular, the Hybrid Performance
Indicators used to make the value judgements during the conceptual design process.
26
5 Achieving best practice
The LFC must be given unambiguous information and instructions by the design team,
especially the architect. Avoid late decisions and design changes because the effects are
magnified further along the process and supply chain. Despite pressures on the design
team, especially the structural engineer, to release information quickly, it is important
to manage and co-ordinate information. Sufficient time should be made available to get
it right. In the interests of good communications, it is advantageous to invite the LFC’s
team to work in the engineer’s offices.
Problems need to be identified and notified early to mitigate additional costs. For
instance, lack of basic setting-out information could lead to delays or piecemeal
production, which is more expensive or could lead to acceleration charges.
Repeatability is key to economy in precast production. It should be appreciated that
minor changes, curves/radii etc. have major impacts on design time and mould re-use.
The aim should be to rationalise numbers of units and moulds. The cost and speed of
manufacture of precast concrete units, particularly the bespoke units, is dependent on
mould use and demouldability. The optimum use of timber moulds is about 30 units
(tolerances are difficult to maintain after about 30 uses); for steel moulds about 90
units is optimum 21. If the precaster can achieve a faster casting cycle time, then the
overall cost and time will decrease. Issues such as demoulding, optimising hook time
for cranes on site, protection strategy for precast units on site also need to be resolved.
Design of the units should be finalised under guidance from the precaster.
Avoid using units where projecting reinforcement is intended to lap with reinforcement
projecting from adjacent precast items – unless tolerances can be guaranteed to avoid
clashes. Use loose splice bars.
Figure 7Paternoster Square office development
The structural scheme consisted of precast vaulted ceiling
units onto in-situ beams and columns. It was chosen to
demonstrate speed and minimum construction depth in
comparison to rival materials.Photo: J. Doyle
DELIVERY
✔ More than just maximising payloads
✔ ‘Just in time’ delivery planning
✔ Correct sequence
✔ Nil damage deliveries
✔ Weight/size restriction
✔ Loading for minimal site handling
✔ Storage on trailers if necessary
ERECTION AND CONCRETING
✔ Competent and trained workforce
✔ Access/hardstanding
✔ Erection sequence – following trades
✔ Craneage – mobile/static
✔ Shared services – cranes/scaffolding etc
✔ Survey of previous works
✔ Erection procedures – H & S/CDM
✔ Falsework and formwork: checks and
responsibilities
✔ Reinforcement, post-tensioning
✔ Welding, bolting, grouting
✔ Concrete deliveries
✔ Curing and protection procedures
✔ Matching finishes
✔ Depropping and release to following trades
STABILITY
PROTECTION
✔ Avoidance of damage
✔ Repair strategy
FEEDBACK
✔ Performance
✔ Price
✔ Experiences for next time
Table 9Precast Checklist 3:
Delivery, erection and construction
Table 10Precast Checklist 4:
Feedback
Construction (1)
Construction (2)
At post-construction stage
29
Case studies 6
It became apparent early in the design process that quality of manufacture and
tolerance control was going to be critical to the achievement of the required erection
programme. The number and complexity of the interfaces between precast and
steelwork and the need for continuous co-ordination between suppliers and the
erection crew led to the conclusion that supply and erection of the entire structure
should form one subcontractor package. As a result an LFC was appointed whose entire
package was negotiated from its inception on an ‘open-book’ basis. This allowed the
earliest possible specialist input into the design process and gave continuity through to
the construction phase.
The structure itself has 14 massive precast concrete shear walls each 3 m wide and over
11 m high. As may be seen from Figures 9 and 10, they form the backbone to the stand,
taking the vertical and lateral loads from the upper tier and roof. Each wall consists of
an upper and lower unit. To maintain accuracy of fit and alignment, these wall units
were match-cast in pairs with steel shoe connectors at mid height. These shoes were
then welded together on site. Particular care had to be taken to place coupler fittings
correctly within the walls to receive steel beams. A high level of accuracy was achieved:
the general level of tolerance was 50% of the limits specified in BS 8110: Part 1:
1997 22. The interfaces between precast and steelwork and the co-ordination required
for successful construction is illustrated by Figures 12 to 16. These show details of the
wall unit W1, part of the cantilever shear wall system, and its fitments.
The upper tier of the stand is a balanced cantilever with the shear walls providing
stability against over-turning forces and wind loads. The lower tier consists of precast
28
6 Case studies
6. Case studies
These case studies show how HCC has been used with great success on a range of
building types and locations.
The studies come from a series of 'knowledge capture' workshops that were convened
in order to identify key events and evaluate what went right and what could have been
improved on particular projects. In addition to producing evidence of the successful use
of HCC, they provided a way of testing the process maps being developed at the time.
They were, in essence, facilitated post-completion workshops, which the participants
found to be enormously valuable.
From the outset, the design and construction of the new 7,500-seater North Stand at
Ipswich Football Club (Figure 8) was dominated by a tight schedule. Work on site could
not start until the end of the 2000/2001 football season but had to be completed as
soon as possible during the next. It was clear to the design team that to achieve this
goal, the following aspects had to be considered:
■ The use of off-site prefabrication.
■ Minimal use of applied finishes.
■ Inherent structural fire resistance of the structure.
■ Ease of erection.
■ Reduced erection time by minimising the number of components.
All these factors indicated that precast concrete would be the most appropriate material
for the project, and this was reflected in the structural design which was essentially
precast augmented by in-situ stitches and toppings and steel beams and a steel roof.
Figure 8North Stand – Ipswich Town Football Club
Photo: C. Goodchild
Above: Figure 9From the North
Photo: Hufton+Crow/View Pictures
Right: Figure 10Typical cross-section of the stand – North
Ipswich Town Football Club: North Stand
Figure 11Shear walls and staircases during construction
Photo: Jan Bobrowski and Partners
3130
6 Case studies Case studies 6
Figure 12General arrangement – Elevation on a lower
wall unit, type W1
Inset right: Figure 13Detail B
Below: Figure 14Wall type W1 – RCC details
33
Case studies 6
North Stand began in May 2001. Superstructure erection began on 16 July and was
completed in 23 weeks by Christmas 2001. The lower tier was used for the first time
on 16 November.
Amongst the best aspects of this project were thought to be:
■ regular meetings with all involved and with a ‘one stop client’
■ early and firm decisions being made; prompt decisions made everything else work
■ unambiguous instructions helped progress the timescale
■ having a LFC on board went hand-in-hand with the hybrid form of construction
■ having an ‘open book’ policy reduced delays on getting prices, and reduced risk of
these delays inhibiting progress – which relied on trust.
Project Team:
Client Ipswich Town FC
Architect HOK Sport
Engineers Jan Bobrowski & Partners
M&E Engineers Hannan Associates
Supervising Architect Hoopers Architectural Services
Quantity Surveyor Gill Associates
Main Contractor Jackson Building Ltd
Lead Frame Contractor ABC Structures
Precast Suppliers Trent Concrete Ltd, Tarmac Topfloor
Steel Suppliers H Young Structures & Westbury Tubular Steel Ltd
References:
Concrete April 2002
Concrete Quarterly Winter 2003
32
6 Case studies
concrete staircase-like units, which span, unconventionally, front to back. They provide
the propping forces necessary to stabilise the shear walls in the transverse direction.
There are 499 units in the upper tier, as opposed to only 289 on the lower tier which
occupies almost the same plan area. Fewer units in the lower tier resulted in a
substantial saving in erection time. On the lower tier, around 800 m of grouting was
undertaken, whereas the more traditional form of construction on the upper tier
required nearly 2300 m. To differentiate their appearance from the upper tier units, the
lower tier units were made from different concrete mixes.
Stitching together the primary and secondary elements into a single entity resulted in
considerably fewer elements and a structure that could be erected as a self-finished
article. The precast units required no additional fire protection or applied finishes.
Longitudinal stability is provided by a combination of moment connections and
diaphragm action from the floors and tiers. The roof structure is essentially a separate
structure spanning 92 m onto Vierendeel towers. Secondary trusses cantilever to the
front and rear of the main truss.
The initial structural design brief was given in January 2001 and demolition of the old
Above left: Figure 15Detail of mild steel shoe for wall type W1
Above right: Figure 16Section 7-7
Right: Figure 17Steel beam connection onto wall type W1 and
its designer. Note: also angle support for
stair landing above
Photo: C. Goodchild
Far right: Figure 18Stair core showing shear wall W1
Photo: C. Goodchild
Right: Figure 19Detail through end of terrace unit
Above: Figure 20Section 4-4
35
Case studies 6
A hybrid of exposed precast and hidden in-situ reinforced concrete was chosen for the
building frame after an intense design period with collaboration between all members
of the design team. It was selected because of its visually striking appearance, ceiling
height, energy efficiency, flexibility and speed. It was also integral with the concept of
using a low energy displacement ventilation system for comfort conditioning within the
offices. The exposed structural soffits of the floors act as reservoirs for storing ‘coolth’, a
feature which contributes to the lowering of heat loads across the daily cycle of occupation.
HCC allowed a high proportion of the frame to be manufactured in quality controlled
factory conditions off-site and led to high speed construction on site. During the design
development process, the design was continually modified to accommodate lighting,
extract ducts, buildability and architectural developments, and yet maintain repetition.
Detailed models were made of the office floor showing the relationship of the precast
units to other key components and interfaces, such as the glass façade, the suspended
lighting units and the central services distribution zone.
Each floor of the wing is constructed from precast concrete coffered floor panels
supported by an in-situ concrete perimeter beam and by an internal ‘shoulder’ beam
system. The shoulder beam system consists of two in-situ concrete downstands hung
from an upstand column head (named ‘drup’ – a ‘drop’ that goes up). The floor panels
were fully integrated with the services with pre-formed slots and holes for ducts and
conduits.
34
6 Case studies
Located in Epsom, Surrey, this exciting and glamorous building entirely meets the
client’s brief for the most advanced and innovative workplace possible. The modern and
flexible office environment has been fully realised by using an exposed hybrid concrete
structure to get best value – in the client’s terms.
The project started as an architectural design competition, which resulted in the
concept of a two storey building orientated around a dramatic entrance rotunda. Four
15 m wide office wings radiate from a glazed ‘street’ where circulation and informal
meeting facilities are concentrated. The building is designed for up to 500 people and
has a gross floor area of 14,200 m2. Daylight potential is maximised in the offices by
the use of large areas of clear glazing offering largely uninterrupted views of a pleasant
landscape.
Toyota (GB)Headquarters
Figure 22Interior of one of the offices at the
Toyota (GB) headquarters
Photo: C. Goodchild
Figure 21A model of Toyota (GB) headquarters
Photo: C. Goodchild
Figure 23Section through office wing
Photo: whitbybird
37
Case studies 6
appearance. Great care was taken in the specification of mould type, tolerance and
finish to control imperfections.
All the units were cast in fibreglass lined moulds. This produced the specified high quality
ex-mould finish required to eliminate the need for decoration, which in turn saved on
the need to bring in further finishing trades and aimed to reduce maintenance costs
during the life of the building. At the first inspection of the precast unit at the works,
the unit was hoisted up to its correct height for a clearer and more accurate inspection.
The ten tonne floor units were delivered to site with three units per lorry. Adopting a
‘just in time’ policy, all units and components were lifted directly into place, to avoid
storage and double handling.
The shape of the overarching structural steel roof is derived from a large diameter torus.
This form maximised repetition of curvature and standardisation within the 150 tonnes
of structural steel components in the 80 m x 45 m partially glazed roof.
Structural design began in December 1997 and the site started in January 1999 with
three months of demolition. Practical completion was achieved in April 2001.
36
6 Case studies
An in-situ concrete structural topping locks all the floor members together in composite
action. Each floor plate uses 34 panels of approximately 6 x 3 m plan dimension within
a 9.0 x 7.5 m column grid. By careful detailing it was possible to limit the number of
panels in each floor plate to seven. The repetition reduced costs, increased efficiency of
production and helped avoid site errors. The maximum weight of panel was restricted to
10.5 tonnes for handling purposes.
Because of the complex shape and presence of service voids within the panels, the
design of floor plates included finite element analysis. The reinforcement also had to
be planned and modelled in three dimensions prior to production.
The building’s columns are generally 8.5 m high structural steel encased in 500 mm
diameter pre-cast concrete with a similar finish to the floor panels. Advantage was
taken of the stiffness of the columns to act as vertical cantilevers for the frame stability
against horizontal loading. This also helped to preserve the clear open space within the
building, as no internal bracing was needed. The column encasement was held back at
floor levels, which enabled perimeter beam reinforcement to pass through the web of
the steel column and thus help ensure a moment connection necessary for the frame
action assumed.
Air is supplied through the floor plenum and extracted through the ceiling soffit, while
the thermal mass of the exposed concrete ceiling helps reduce heat load.
Benchmarking visits were made to various sites to establish the required quality and
fit of the coffers. These visits involved the main contractor, the specialist concrete
contractor and the design team. The project specification was taken from a previous
project and agreed.
The concrete mix for both the pre-cast floor panels and columns was Derbyshire
Limestone aggregate with Antique White cement to create a light, off-white
Below left: Figure 25Structure/services integration
Photo: whitbybird
Below right: Figure 26Steel billets were used to ensure transfer of loads
between precast floor units and in-situ beamsPhoto: whitbybird
Below left: Figure 28PC floor unit being lifted into position.
Note: falsework and formwork, ducts
in units, columnsPhoto: Barry Bulley/Trent
Below right: Figure 29During construction
Photo: whitbybird
Figure 27Perimeter beam construction sequence
The in-situ beam picks up the precast floor panels.
Beam reinforcement passes through the web of
the encased structural steel column to help guarantee
a moment connection.
Figure 24Falsework
Photo: whitbybird
39
Case studies 6
The West Quay shopping centre in Southampton is home to over 150 shops, restaurants,
bars and cafes. It is served by two car parks, the largest of which is the main West Car
Park – now one of the largest multi-storey car parks in the UK. By cost it was just 7%
of the whole West Quay development. However, because of a deferred start, the
multi-storey car park’s completion became critical to the centre’s opening in time for
Christmas 2000.
The structure is 95 m long, 95 m wide and 20 m high – eight-storeys with 15 split
levels. In plan it is divided into four equal quadrants by movement joints. Each quadrant
has varying architectural treatment and layout requirements (Figure 31). There are a
total of seven stair cores plus two double lift cores. Headroom is 2.2 m clear.
Various structural frame options were considered at scheme design stage: structural
steelwork, wholly precast concrete, in-situ concrete and post-tensioned. The selected
scheme was based on composite precast double tee floor units spanning 15.8 m onto
in-situ concrete beam-and-column frames.
The decision to use HCC followed a value engineering exercise. By combining the cost
advantages of in-situ and the speed advantages of precast, the design and build
contractor concluded that the structure could be completed on time and within budget.
Another consideration was the piled foundations: piling had been installed with the
main development. Unfortunately, this piling was to a preliminary scheme and design
changes increasing the thickness of cladding (from 100 mm thick to 165 mm) and
service loads, meant that additional piling was needed. The choice of a relatively
lightweight double tee slab structure helped control overall loads and thereby reduced
the need for further piling to just 14 continuous flight auger piles.
38
6 Case studies
The Toyota (GB) Corporate Headquarters won the Building category in the 2001/2002
Concrete Society Awards. Among the best aspects which helped win the award were:
■ Early decision to prefabricate and have a sustainability/low energy concept.
■ Close teamwork with overall buy-in early on and confidence that project could be
delivered. There was a high degree of co-ordination and ‘ownership’. The team
bonded, established a proximity and were motivated to work closely together.
■ Arrangements for manufacture were very satisfactory. Warranty for materials/units
stored off site was included which established confidence.
■ The quality of the precast units was assured. The frame went well as all details on
paper had been resolved beforehand. The structural engineer’s use of 3D drawings
was vital – it reduced costs and helped to resolve details.
■ Construction efficiency was enhanced by prefabrication.
■ Use of a prototype factory unit to help secure the client’s confidence in precast.
■ The speed of construction of precast and subsequent progress built confidence within
the client organisation.
Two years after moving in the client remains very pleased with the building:
■ “It looks good”. “Wouldn’t change a thing.”
■ Compared to the previous offices they now have a building three times larger, with
double the staff, but the energy costs are 40% less than before.
■ “Very comfortable – even in the heat wave of 2003.”
■ Moving from rented space to being an owner-occupier will pay back in 10-15 years with
far better energy consumption, a more manageable and positive environment. Internal
planning works well with minimum turnover of staff and reduced absenteeism.
HCC was the obvious and logical solution, combining the quality finish and repetition of
precast with the flexibility of in-situ.
Project Team:
Client Toyota GB plc
Project Manager Insignia – Richard Ellis
Architect Sheppard Robson
Structural Engineer whitbybird
M&E Engineers Arup
Quantity Surveyor Davis Langdon & Everest
Main Contractor Takenaka (UK)
Precast Concrete Trent Concrete Ltd
Concrete Frame Duffy Construction Ltd
References:
Sheppard Robson Toyota brochure
whitbybird PowerPoint presentation 16 September 2003
Concrete Quarterly Summer 2001 – 199
IStructE www.istructe.org.uk. David Alsop Commendation 2002
Concrete Society www.concrete.org.uk
Figure 30The first floor balcony in the ‘drum’ overlooks the
reception area and gives access to meeting roomsPhoto: C. Goodchild
West Car Park,West Quay, Southampton
Figure 31East elevation showing
the curved pedestrian entrancePhoto: C. Goodchild
41
Case studies 6
east/west direction. The units have scarf ends for seating onto nibs. The scarfs were
extended to provide 300 mm wide channels for services such as electrical, CCTV and
lighting. This feature also provides the flexibility to the client to increase the service
provision at a future date without compromising headroom (see Figures 34 and 36).
The ramps presented some challenges. The in-situ framing initially considered for each
end of the ramps would have caused significant difficulties with the load paths down to
the foundations. However, by using cranked double tees in the normal bay no additional
framing was required (Figure 39). This arrangement provided the additional benefit of a
more consistent soffit line.
Lateral loads were taken by shear walls and cores. Tie bars cast in the in-situ beams
were bent down over the precast units and cast into the structural screed to ensure
diaphragm action and robustness.
The construction method required that two bays were left open for mobile crane access
so that units could be lifted directly off lorries and straight into position in the other
bays. Once the top level was complete, the infill bays were constructed with the cranes
backing out slowly towards Harbour Parade.
40
6 Case studies
The span of the slabs is almost 16 m.This meant that precast slabs could be either 600 mm
deep double tees or 400 mm deep hollowcore units. Double tees were used as they
were lighter: the dead load is 5.0 kN/m2, including screed, against 6.7 kN/m2 for the
hollowcore. To allow greater headroom some hollowcore units were used in lobby areas.
The double tee beams are 2.4 m wide with 600 mm deep ribs. The beams’ width is the
same as the width of the car parking bays and fits neatly into the 7.2 m grid in the
Figure 32General layout
Below left: Figure 33Double tee slabs
Photo: C. Goodchild
Below right: Figure 34Scarf joints onto in-situ beam
allow for cables and conduitsPhoto: C. Goodchild
Right: Figure 37Prefabricated edge beam cage
Photo: Sir Robert McAlpine Ltd
Far right: Figure 38Edge detail
Above left: Figure 35Section through edge beam
Above right: Figure 36Section through internal beam
43
Case studies 6
42
6 Case studies
Stability during the construction phase was ensured by welding the double tee units
together at 2.4 m centres and to the in-situ beams at 1.2 m centres. Each welded
connection had a tensile capacity of 105 kN and together in effect formed a diaphragm
in the temporary condition.
The shear walls between the half levels proved slow to construct as they could only be
concreted in shallow lifts.
The car park is an integral part of the West Quay development and, therefore, has
special perimeter architectural treatment. This includes precast concrete cladding
systems using reconstituted stone and knapped flint and curved in-situ concrete
features at the entrances and other prominent areas. The interfaces with cladding called
Right: Figure 40The shear wall between two half-levels
Photo: C. Goodchild
Far right: Figure 41Spandrel cladding on east elevation
Photo: C. Goodchild
Figure 39Section through ramp – showing cranked
double tees
Figure 42Fixing detail 59
Above : Figure 43Section through spandrel cladding
Above right: Figure 44Fixing detail 60
Right: Figure 45Co-ordination works! Fixing detail 59 in place
Photo: C. Goodchild
45
Case studies 6
44
6 Case studies
for a significant degree of co-ordination, especially for the curved pedestrianised
entrance (Figure 31).
Best aspects of this project were:
■ The hybrid concrete frame worked well as a system, in terms of the overall result
and lack of interface problems.
■ The potential advantages of using double tees were fully realised and proved to be
a very positive way to create large areas of floor very quickly.
Figure 46East Elevation with buttress cladding
Photo: C. Goodchild
Below left: Figure 47Buttress cladding – detail 54
Below right: Figure 48Buttress cladding – detail 58
Left: Figure 49Buttress cladding section – East elevation
Below: Figure 50Buttress cladding – detail 62
47
Case studies 6
The switch from a purely in-situ to a hybrid concrete structure of precast hollowcore
floor slabs and in-situ beams and columns helped win this major retail scheme for the
design-and-build contractor. Its adoption helped to shave some 15 weeks from the
original construction programme.
The site owner, Land Securities, is working in partnership with Canterbury City Council
to deliver an exciting new £100m retail scheme that will transform 12 acres in the
heart of the city centre. Upon completion in 2006, Whitefriars will be fully pedestrianised
and comprise 38 retail units, one department store, two further major stores and a 520
space multi-storey car park.
Following an architectural competition, public consultation and detailed discussions
carried on through 1996 and 1997, before formal planning permission was granted in
January 1999. Detailed design was undertaken while demolition, enabling works and
extensive archaeological digs were carried out on site. Tenders went out in January
2002. The contract was awarded in April 2002 and work started on 1 July 2002.
The structure was originally designed as a fully in-situ concrete frame with two-way
solid slabs and downstand beams. Over the relatively short tender period the contractor
concentrated efforts on finding alternative solutions to those indicated on the tender
drawings. He was looking for advantages that would deliver a quicker and more
buildable project at a price to win the job. Considerable effort was therefore put into
rationalising the substructure and the shopping and car parking areas (Zone C).
The advantages of a hybrid construction, using precast concrete hollowcore floors units,
quickly became apparent. The number of in-situ concrete beams was almost halved due
to the greater spans achieved by the hollowcore units. Less formwork and propping
was required and the frame construction programme was reduced by one month. Cost,
weight and deeper beams mitigated against a fully precast scheme.
Using hollowcore slabs in the HCC scheme reduced the overall weight of the floor slabs
and the amount of in-situ concrete placement required. This, in turn, reduced the overall
numbers of lorry movements to the site, a sensitive issue in this historic city, especially
during rush hour.
46
6 Case studies
■ Delivery and construction went smoothly. Because there were relatively few types of
floor unit there was flexibility to stop deliveries or bring them forward. The quality of
the double tees was good.
■ There were good relationships, good exchange of information and regular meetings
to resolve issues. Early specialist advice, for example on fixings etc., prevented
problems later.
■ Precast cladding panels were produced under pressure of time. Ideally, the cladding
contractor should have had a whole package of architectural designs with
‘engineering’ input at an early stage, without late tweaking of details. Regular
meetings meant that issues were resolved around the table, and this proved to be
faster than a conventional approach.
The client is very happy with the car park. It is user-friendly and feedback is very good.
A comparable project, built by another method, has not stood the test of time. The
split-level works well for car circulation and number of spaces.
Team member’s comment: “Quite proud of it!”
Project Team:
Client Hammerson plc
Client’s Concept Architect BDP
Design Consultants Chapman Taylor Architects
Engineers Pell Frischmann
Client’s Q S Cyril Sweett & Partners
D&B Contractor Sir Robert McAlpine Ltd
Engineers Sir Robert McAlpine Design Group
Contractor’s Foundation Engineers Ove Arup & Partners
Precast floors Tarmac Precast Concrete Ltd
Precast cladding The Marble Mosaic Company Ltd
References:
Allen, M. Paper to Southern Branch Concrete Society
Precast Concrete in Construction BPCF supplement, Construction News, 2000
Façade Winter 2000/01
Parking Review May 2001
Figure 51Artist’s impression of Whitefriars Street
Photo: Land Securities
Figure 52Gravel Walk elevation – Zone C
Whitefriars,Canterbury
49
Case studies 6
48
6 Case studies
The use of hollow core units had two other major benefits:
■ Construction of the extensive basement was critical to the programme and a form of
top-down construction was necessary to achieve overall time savings. The solution lay
in using the hollowcore floor to prop the secant piled retaining wall at ground floor level
while excavation and construction took place over the whole basement area below.
■ Use of hollowcore also minimised the amount of propping required between ground
floor and basement 4 to 5 m below. Additionally, it reduced the amount of concrete
required as no structural topping was needed to create the necessary diaphragm.
Units were delivered, lifted and landed onto partly-cast supporting in-situ beams. The
ends of all units were delivered with open ends, 500 - 600 mm long. Reinforcement
was introduced through the top of the supporting beam and extended into the open
ends of the slab units. When concreted, this detail provided robustness and integrity
to the diaphragm.
Figure 53Site plan: the basement access and delivery
area extends over the whole site
Overall, this method saved weeks on the construction programme and contributed
significantly to the success of the tender.
In Zone C, the relatively lightweight hollowcore units allowed bays of 8 m x 9.6 m at
retail unit level to be converted to bays of 16 m x 9.6 m to suit car park layouts above
– admittedly this required some fairly substantial in-situ beams to span 16 m, but
nonetheless it saved on column construction and time on unnecessary beams.
In the car park areas, the hollowcore slabs are designed to act compositely with a 75 mm
thick reinforced concrete structural topping. These floors are designed for a very severe
exposure condition in accordance with BS 8110, whilst all internal areas, such as those
for shopping, are left as the bare plank, ready to receive a cementitious finishing screed.
The use of prefabricated stair components reduced the requirements for scaffolding.
Their use also enabled the contractor and subcontractors to access all areas of the
constructed floors immediately after the stair units had been placed.
Car park loading
Shop unitloading
Figure 58Zone C, 1st Floor – the hybrid solution significantly
reduced the number of beams required
Right: Figure 56One bay of hollowcore was temporarily left out of
Whitefriars Square, the ground floor slab between
zones B and D. This gave access for constructing the
basement while working on the critical upper
storeys along Gravel Walk beyond
Photo: C. Goodchild
Far right: Figure 57Completed ground floor soffit
Photo: C. Goodchild
Right: Figure 54The Gravel Walk entrance during construction
Photo: C. Goodchild
Far right: Figure 55Falsework for in-situ beams remains in place while
hollow core units are placedPhoto: C. Goodchild
51
Conclusions 7
7. ConclusionsHybrid Concrete Construction is about providing best value for clients.
It is not necessarily about first cost. But it is about savings from improved buildability
on site and these savings soon overtake any material cost differences. It is also about
inherent benefits – such as thermal mass. Thermal mass leads to energy savings; it also
leads to occupier comfort which, in turn, leads to user efficiency. By using the 'whole-life’
cost approach and recognising the 1 : 5 : 200 relationship between initial cost, maintenance
and lifetime business costs, the advantage of HCC can be seen more clearly.
Value has to be measured in the client’s terms and best value will only be achieved by
changing from ‘traditional’ procurement methods. The processes advocated by this
document align very closely with the ideals of Rethinking Construction 2. Best Practice
for HCC is set out in Chapter 5 where the whole ‘how it should be’ process is mapped
out and described. Many leading companies already use methods similar to this model
– and the model is just as applicable to getting best value out of purely in-situ and
precast construction as it is for combinations of the two. Chapter 4 highlights the ‘new’
processes necessary to achieve the desired results. These include:
■ The early involvement of specialist contractors.
■ The use of a lead frame contractor.
■ Adopting a programme of project workshops.
■ Adopting the principles of best value.
Adopting the principle of best value means that there has to be some way of measuring it.
Value indicators must weigh up the relative importance of cost, speed, quality, robustness and
lettability etc. Issues such as whole-life costs, energy usage and the effects of the structure
and design on overall business costs need to be considered and factored in. As the case
studies demonstrate, the purpose is to provide best value in the client’s terms. For example:
■ The North Stand at Ipswich Town FC was delivered fast, in only 23 weeks.
■ The Toyota (GB) Headquarters delivered award-winning quality.
■ The West Car Park at Southampton’s West Quay is inviting and user-friendly.
■ Adopting the hybrid frame at Whitefriars helped save 15 weeks on the programme.
Positive comments such as “quite proud of it” and “wouldn’t change a thing” come
from satisfied clients and are the result of commitment and team effort. The successful
outcomes on these projects were achieved with enlightened attitudes between parties
and a willingness to adopt innovation and best practice guidance. This is all within an
environment of trust promulgated by clarity of roles and purpose, promoted by an open
book approach to contract procurement. The high levels of buildability called for higher
than usual levels of pre-planning and team players, but as has been proven, HCC delivers.
HCC will be driven further by the need to manufacture off-site and construct safely on
site. HCC brings quality, value and speed but more significantly, consideration of overall
business costs will become the compelling argument for using HCC.
50
6 Case studies
The remaining retail units have steel frames, which were designed as fully composite,
except at perimeter locations where the plain beams support the loads while allowing
for holes through adjacent slabs.
At the time of writing, this project was still on site but amongst the best aspects of this
project are:
■ The in-situ /precast, hybrid solution helped win the job by saving time and money. It
provided a solution that achieved the contractor and client’s cost and programme
requirements.
■ The decision to go ‘top down’ with the basement construction was made feasible by
using hollowcore units and proved to be a turning point in winning the contract.
Again, the HCC solution saved time and money.
■ Together with reducing the number of beams/columns and the decision to go top
down, the HCC scheme saved 15 weeks on the initial programme estimates.
■ There were good working relationships amongst all parties. The precaster was
involved at a reasonably early stage.
Contractor’s comment: “This is a high standard concrete frame – it looks good.”
Project team:
Client Land Securities in partnership with Canterbury City Council
Concept Architect Chapman Taylor
Client’s Engineers Upton McGougan Consulting Engineers
Project Managers MACE
D&B Contractor HBG Construction
Engineers HBG Construction
Contractor’s Architect Lyons + Sleaman + Hoare
Frame Contractor Whelan & Grant
Precast floors Bison Concrete Products
Above left: Figure 5916 m spanning beams at upper car park level
Photo: C. Goodchild
Above right: Figure 60Typical section through beam
53
Appendix
Appendix Background researchThe best practice guidance given in this publication follows on from earlier pieces of
research carried out for the concrete industry within the context of many initiatives and
drivers for change in the wider construction industry.
The Reading Production Engineering Group (RPEG) at the University of Reading investigated
the Barriers to Hybrid Concrete Construction23 by using force field techniques. These are
used to identify and remove impeding forces (or barriers). Impelling forces will then,
naturally, take the adoption of a technique or practice forward into more widespread
adoption and practice.
Hybrid Concrete Construction for the UK market1 aimed to identify the most advantageous
systems, quantify potential benefits and discover how these benefits might be achieved
more widely in practice. The research by Oxford Brookes University School of Architecture,
The University of Salford and Imperial College, London, investigated client and customer
requirements, business processes, perceived barriers to use and structural design.
Following the completion of the research above, the construction industry witnessed
several major advances in the process of construction procurement. Most notably, the
Rethinking Construction2 task force report, led by Sir John Egan and published in 1998,
contained the clear message that the industry would not significantly improve unless
it embarked upon radical change. This would involve a totally new approach to the
delivery of the construction product.
From these ideals the ‘Movement for Innovation’ (M4i) was born. This is now part of
Constructing Excellence. M4i continues to lead radical improvement in construction
in terms of value for money, profitability, reliability and respect for people, through
demonstration and dissemination of best practice and innovation.
Other initiatives were being taken forward at the same time:
■ Value management and principles of value engineering were being applied to
construction projects.
■ Government had sponsored the ‘Construction Best Practice programme’ 6 to
provide support to individuals, companies, organisations and supply chains in the
construction industry seeking to improve the way they do business.
■ Several bodies undertook process research. Under the EPSRC ‘Innovative Manufacturing
Initiative’ (IMI), research into Process Protocol was undertaken during 1995-98
(Figure 61). Researchers used manufacturing principles as a reference point for a
framework of common definitions, documents and procedures that were developed
to help construction project participants work together seamlessly.
Previous concrete industry research
A.1 Context
52
8 References and Further Reading
Government and other initiatives
8. References and further readingReferences
1 GOODCHILD, C H et al. Hybrid Concrete Construction for the UK market: final report on research into using combinations of in-situ and precast concrete in structural frames to achieve better value for UK customers. Crowthorne, BCA, on behalf of theindustry sponsors of the RCC, 2001. 422 pp. Ref. 97.369. ISBN 0 720 1528 X.
2 SIR MICHAEL LATHAM. Constructing the Team: final report of the government/industry review of procurement and contractualarrangements in the UK construction industry. London, DOE, 1994. ix, 130 pp.
3 EGAN. Rethinking Construction, Rethinking the construction client, the national debate. London, DTI, 1998. 40 pp.
4 Movement for Innovation (M4i) now see www.constructingexcellence.org.uk/
5 CONNAUGHTON, J N & GREEN, S D Value management in construction: A client’s guide. London. CIRIA Special Publication129, 1996. 73 pp. ISBN 0 86017 452 2.
6 Construction Best Practice Programme (CBPP) now see www.constructingexcellence.org.uk/
7 KAGIOGLOU, M et al. A generic guide to the design and construction Process Protocol. University of Salford, 1998.ISBN 090 289 617 2.
8 THE STRATEGIC FORUM FOR CONSTRUCTION. Accelerating change. 2002 London, Rethinking Construction (c/o TheConstruction Industry Council). 42 pp. ISBN 1 898671 28 1. See www.strategicforum.org.uk.
9 STEEL CONSTRUCTION INSTITUTE AND BRITISH CEMENT ASSOCIATION, Learning from the best. Ascot, SCI, 2003. Ref.RT952. www.steel-sci.org/Publications.
10 GOODCHILD, C H Cost model study: a report on the comparative costs of concrete and steel framed office buildings.Crowthorne: BCA on behalf of the industry sponsors of the RCC, 1993. 48 pp. Ref. 97.333. ISBN 0 7210 1469 0.
11 GOODCHILD, C H Hybrid Concrete Construction: combining structural materials for speed, quality and economy in buildings.Crowthorne, BCA on behalf of the industry sponsors of the RCC, 1995. Ref. 97.337. 64 pp. ISBN 0 7210 1479 8.
12 PRECAST FLOORING FEDERATION. Code of practice for safe erection of precast concrete flooring and associated components.Leicester, PFF, 2001. 88 pp.
13 Innovation and Research Focus No 51 November 2002, Institution of Civil Engineers, London, ISSN 0960 5185 (see also www.crc-tech.com).
14 EVANS, R, HARYOTT, R, HASTE, N & JONES, A The long-term cost of owning and using buildings, 1998. London, RoyalAcademy of Engineering. See www.raeng.org.uk/news/publications/reports.
15 RIBA. The RIBA Plan of Work Stages 1999. See www.architecture.com/go/Architecture/Using/Contracts_306.html.
16 GRAY, C In situ concrete frames: a strategy for improving the performance and productivity of the in situ concrete frame industrywhich will lower the cost of construction for the industry and its clients. (Improving concrete performance series). Reading,Reading Production Engineering Group, University of Reading, 1995. 24 pp. ISBN 0 7049 0505 1.
17 BARRETT, P Current business processes and desirable process improvements (workpackage 3): a report by the University ofSalford, in Goodchild et al. (2001), Hybrid Concrete Construction for the UK market (Ref. 1 above).
18 GLASS, J A best practice process model for Hybrid Concrete Construction. Article submitted to Construction Management andEconomics Journal.
19 BROWN, N The procurement of structural precast concrete. Paper given at Concrete Society seminar, Cirencester 1997.High Wycombe, ABC Structures, 01494 441144.
20 CONSTRUCT, the Concrete Structures Group. National Structural Concrete Specification for Building Construction. 2nd edition.Crowthorne, BCA, 2000. 72 pp. Ref. 97.378. ISBN 0 7210 1571 9.
21 DAWSON, S. Cast in Concrete. Leicester, Architectural Cladding Association, 2nd Edition, 2003. 96 pp. ISBN 0 9536773 3 8.
22 BRITISH STANDARDS INSTITUTION. Structural use of concrete: Part 1. Code of practice for design and construction.(BS 8110 Part 1). London, BSI, 1997.
23 READING PRODUCTION ENGINEERING GROUP. Barriers to Hybrid Concrete Construction: an unpublished report by RPEG,University of Reading, 1997 in Goodchild et al, Hybrid Concrete Construction for the UK market (Ref 1).
24 GLASS, J Best Practice Guidance on Hybrid Concrete Construction: Work stage 2: Practitioner interviews (confidential researchreport). Oxford Brookes University, 2002.
25 GLASS, J Best practice guidance on Hybrid Concrete Construction: Work stage 3: Knowledge capture workshops (confidentialresearch report). Loughborough University, 2003.
26 ELLIOTT, K S Multi-storey precast concrete framed structures: a design guide, Oxford, Blackwell Science, 1996. 601 pp.ISBN 0 632 03415 7.
27 CEN. pr EN1992-1-1. Eurocode 2: Design of concrete structures – Part 1.1: general rules and rules for buildings, April 2003version. Brussels, CEN.
28 GHALI, A, FAVRE R, & ELBADRY, M Concrete structures, stresses and deformations, 3rd edition, London, E & F N Spon Ltd,2002. 584 pp. ISBN 0 415 24721 7.
29 CEB-FIP Model Code 1990, Thomas Telford Ltd, November 1993, 480 pp. ISBN 0 727 71696 4.
Further reading■ BRUGGELING, A S G, & HUYGHE, G, F Prefabrication with concrete. Rotterdam, A A Balkema. 1991, 380 pp.
ISBN 90 6191 183 4.
■ CIRIA. Snapshot – Standardisation and pre-assembly based on research project RPS32, London, CIRA, 1998. 7 pp.
■ FIP COMMISSION ON PREFABRICATION. Composite floor structures. London, SETO Ltd, 1998. 58 pp. ISBN 1 874266 38 7.
■ FIB, COMMISSION 6 ON PREFABRICATION. Planning and design handbook on precast building structures. 2nd Edition BFTBetonwerk + Fertigteil-Technik, Gutersloh, Germany, 2004. 139 pp.
■ GRAY, C Value for money – helping the UK afford the building it likes. University of Reading. 1996. 60 pp.
■ HARLAND, C M, Supply chain management: Relationships, chains and networks, British Journal of Management, Vol. 7,Special Issue, S63-S80. 1996.
■ HUNTON, D A T Precast concrete in buildings – Past, present and future. Betonwerk + Fertigteil-Technik, 10/90. pp. 70–77.
■ MALE, S et al. The value management benchmark: framework document. London, Thomas Telford. 1998. 64 pp.ISBN 0 7277 2729 X.
The Partners in Innovation project Best Practice Guidance on Hybrid Concrete Construction
was a 15-month study to identify and disseminate best practice on hybrid concrete
structures. This publication forms the main output from that project.
Essentially, the research undertaken by Dr Glass consisted of a series of interviews24 with
a range of industry professionals to produce procurement process maps and discuss
relevant issues. The process maps were created and examined in each successive
interview and iteratively amended so they became increasingly robust. Finally, in a series
of Knowledge Capture Project Workshops25, held on site, they were tested against
events that occurred on actual HCC projects. The ‘how it should be’ process map (Figure
5) is the basis of the best practice given. However, along the way, the many examples
and anecdotes given have been collected, analysed and used to provide further pointers
to achieving best practice in HCC18.
The Accelerating Change8 report published in September 2002 by The Strategic Forum for
Construction set out rigorous targets intended to produce a more modern and dynamic
industry. The report challenged the construction industry to provide maximum value for
clients and end users and to provide a consistently world-class product. It committed
the Forum to produce an integration aid to help the industry to achieve this target.
Learning from the Best9 extracted lessons from Rethinking Construction2 demonstration
projects. It found that considerable improvements have been made by companies that
have adopted new methods of working.
Within this changing business environment, the Reinforced Concrete Council (RCC) set out
to produce Best Practice Guidance for Hybrid Concrete Construction. It was researched
during 2002 and 2003 by Dr Jacqueline Glass of Oxford Brookes University’s School of
Architecture and more recently of the Department of Civil and Building Engineering at
Loughborough University. The research was managed by the RCC (and its successor, The
Concrete Centre) and guided by an industry advisory group made up of representatives
of leading exponents of new approaches to concrete frame procurement.
Figure 61Process Protocol mapCourtesy of University of Salford
AppendixAppendix
5554
A.2 Best Practice Guidance for Hybrid
Concrete Construction research project
Liaison withProcess
Manager
Liaison withother Activity
Zones
Establishthe need
for aproject
Establishthe need
for aproject
DEVELOPMENTMANAGEMENT
RESOURCEMANAGEMENT
PROJECTMANAGEMENT
DESIGNMANAGEMENT
FACILITIESMANAGEMENT
PRODUCTIONMANAGEMENT
HEALTH &SAFETY,
STATUTORY ANDLEGAL
MANAGEMENT
PROCESSMANAGEMENT
Prepareoutline
BusinessCase
ConsiderRisk
Issues
Prepareoutline
Businesscase
DevelopinitialStake-holder
List
DevelopinitialStake-holder
List
Establishinitial
Comm-unicationStrategy
Compileinitial Risk
Register
Establishinitial
Comm-unicationstrategy
PrepareProject
ExecutionPlan
PrepareProcess
ExecutionPlan
Finalisethe
Statementof Need
for aproject
Finalisethe
Statementof Need
for aproject
PrepareProjectBrief
PrepareProjectBrief
Updateoutline
BusinessCase
ConsiderRisk
Issues
Updateoutline
BusinessCase
Assessstake-holder
impact &require-ments
Assessstake-holder
impact &require-ments
ConsiderSite andEnviron-mentalissues
ConsiderSite andEnviron-mentalissues
UpdateComm-
unicationStrategy
Updateinitial Risk
Register
UpdateComm-
unicationStrategy
UpdateProject
ExecutionPlan
UpdateProcess
ExecutionPlan
Under-take
outlineFeasibilitystudiesfor eachoption
Under-take
outlineFeasibilitystudiesfor eachoption
UpdateProjectBrief
UpdateProjectBrief
Updateoutline
BusinessCase
ConsiderRisk
Issues
Updateoutline
BusinessCase
UpdateSite andEnviron-mentalissuesReport
UpdateSite andEnviron-mentalissuesReport
UpdateComm-
unicationStrategy
Updateinitial Risk
Register
UpdateComm-
unicationStrategy
UpdateProject
ExecutionPlan
UpdateProcess
ExecutionPlan
SOFT
GA
TEPH
ASE
rev
iew
SOFT
GA
TEPH
ASE
rev
iew
SOFT
GA
TEPH
ASE
rev
iew
UndertakesubstantiveFeasibilitystudies onthe most‘feasible’options
UndertakesubstantiveFeasibilitystudies onthe most‘feasible’options
UpdateProjectBrief
UpdateProjectBrief
UpdateBusiness
Case
ConsiderRisk
Issues
UpdateBusiness
Case
UpdateSite andEnviron-mentalissuesReport
PrepareinitialCDM
assess-ment
UpdateSite andEnviron-mentalissuesReport
UpdateComm-
unicationStrategy
Updateinitial Risk
Register
UpdateComm-
unicationStrategy
UpdateProject
ExecutionPlan
UpdateProcess
ExecutionPlan
HA
RDG
ATE
PHA
SE r
evie
w
ReviseProjectBrief
ReviseProjectBrief
Revisefull
BusinessCase
ConsiderRisk
Issues
Revisefull
BusinessCase
UpdateSite andEnviron-mentalissuesReport
ReviseCDM
assess-ment
UpdateSite andEnviron-mentalissuesReport
UpdateComm-
unicationStrategy
Prepareinitial
Cost Plan
Revise Risk
Register
UpdateComm-
unicationStrategy
ReviseProject
ExecutionPlan
ReviseProcess
ExecutionPlan
SOFT
GA
TEPH
ASE
rev
iew
UpdateProjectBrief
PrepareOperationPolicy andMainten-ance Plan
UpdateProjectBrief
UpdateBusiness
Case
ConsiderRisk
Issues
UpdateBusiness
Case
UpdateSite andEnviron-mentalissuesReport
UpdateCDM
assess-ment
UpdateSite andEnviron-mentalissuesReport
UpdateComm-
unicationStrategy
UpdateCost Plan
Update Risk
Register
UpdateComm-
unicationStrategy
UpdateProject
ExecutionPlan
HA
RDG
ATE
PHA
SE r
evie
w
ReviseProcess
ExecutionPlan
ReviseProcess
ExecutionPlan
FinaliseBusiness
Case
ConsiderRisk
Issues
UpdateOperation
Policyand
Mainten-ance Plan
FinaliseBusiness
Case
UpdateSite andEnviron-mentalissuesReport
UpdateCDM
assess-ment
UpdateSite andEnviron-mentalissuesReport
UpdateComm-
unicationStrategy
Revise Risk
Register
UpdateComm-
unicationStrategy
ReviseProject
ExecutionPlan
ReviseProcess
ExecutionPlan
HA
RDG
ATE
PHA
SE r
evie
w
FinaliseProjectBrief
UpdateOperation
Policyand
Mainten-ance Plan
FinaliseProjectBrief
FinaliseSite andEnviron-mentalissuesReport
ConsiderRisk
Issues
FinaliseHealth &
SafetyPlan
FinaliseSite andEnviron-mentalissuesReport
FinaliseComm-
unicationStrategy
FinaliseCost Plan
UpdateRisk
Register
PrepareProduc-
tionInform-ation
FinaliseComm-
unicationStrategy
PrepareHand-over Plan
Startenablingworks
PrepareHand-over Plan
UpdateProject
ExecutionPlan
UpdateProcess
ExecutionPlan
SOFT
GA
TEPH
ASE
rev
iew
Updateand
imple-mentHand-
over Plan
FinaliseRisk
Register
Developas-builtinform-ation
Revise &implementOperationPolicy &Mainten-ance plan
Manage& under-
takeconstruc-
tionactivities
ManageHealth &
Safety
Updateand
imple-mentHand-
over Plan
ConsiderRisk
Issues
UpdateProject
ExecutionPlan
UpdateProcess
ExecutionPlan
HA
RDG
ATE
PHA
SE r
evie
w
Under-take PostProjectReview
ConsiderRisk
Issues
Ongoingupdate ofOperationPolicy &
Mainten-ance plan
Under-take PostProjectReview
FinaliseProject
ExecutionPlan
FinaliseProcess
ExecutionPlan
Performongoingreview ofFacilitiesLifecycle
PHASE ZERO PHASE ONE PHASE TWO PHASE THREE PHASE FOUR PHASE FIVE PHASE SIX PHASE SEVEN PHASE EIGHT PHASE NINE
OPERATION & MAINTENANCECONSTRUCTIONPRODUCTION INFORMATIONDETAILED DESIGN, PROCUREMENT
& FULL FINANCIAL AUTHORITYFULL CONCEPTUAL DESIGNOUTLINE CONCEPTUAL DESIGN
SUBSTANTIVE FEASIBILITY STUDY& OUTLINE FINANCIAL AUTHORITY
OUTLINE FEASIBILITYCONCEPTION OF NEEDDEMONSTRATING THE NEED
OUTLINEPLANNINGAPPROVAL
DETAILEDPLANNINGAPPROVAL
PRE-PROJECT PHASES PRE-CONSTRUCTION PHASES CONSTRUCTION POST-CONSTRUCTIONPHASE
FinaliseProcurement
Plan
FinaliseProcurement
Plan
Prepare FeasibilityDesign Brief
Prepare FeasibilityDesign Brief
Prepare initialProcurement Plan
Prepare initialProcurement Plan
UpdateProcurement
Plan
UpdateProcurement
Plan
UpdateProcurement
Plan
UpdateProcurement
Plan
UpdateProcurement
Plan
UpdateProcurement
Plan
Prepare conceptDesign Brief
Prepare conceptDesign Brief
Prepare outlineConcept Design
Prepare outlineConcept Design
Prepare fullConcept Design
Prepare fullConcept Design
Produce Detailed Design
Produce Detailed Design
USE & CREATION OF LEGACY ARCHIVE
FEEDBA
CK TO
OTH
ER PROJEC
TS VIA
LEGA
CY A
RCH
IVE
PROCESSMANAGEMENT/
CHANGEMANAGEMENT
FEED
BAC
K F
ROM
CU
RR
ENT
& P
AST
PRO
JEC
TS
57
Appendix
56
Appendix
Thirteen interviews were conducted with senior practitioners within the field of
concrete frame construction. They were used to develop, test and confirm process
models for HCC, to agree HCC performance indicators (HPIs) and to discuss any other
relevant issues.
The process models described and documented the activities, roles and responsibilities
of various players in the procurement, design and construction of a hybrid concrete
structure. The aim was to ensure that both traditional procurement and partnering type
regimes were reflected and analysed in two models; the first ‘how it is’ and the second
‘how it should be’.
The framework used was based on Process Protocol7.(Figure 61). This framework was
aligned with RIBA Stages of Work15, but above all it was developed to reflect the
specifics of concrete frame construction. The models’ horizontal axes included stages
of work from briefing, feasibility and design through to construction, hand-over and
occupancy. The vertical axes listed the full range of occupations/professions that one
might expect to be involved (i.e. client, architect, quantity surveyor, main contractor,
precaster etc.). Thus, the matrices were populated with tasks, deliverables and ‘gateways’
(i.e. ‘what should be done, by whom and at what stage’) as appropriate.
The second model, the ‘how it should be’ model, is reproduced as Figure 5 and details
activities under a partnering style procurement route. It may be thought of as being
more akin to the Rethinking Construction model with strategic alliances formed early
on in the programme.
The models were validated by the project advisory group before circulation to
interviewees for detailed feedback. After the interviews, the models were amended to
take account of feedback from the various practitioners. There was genuine consensus
that the models, subject to those amendments, were a good representation of practice,
both current and ideal.
r Pleased with it.
r Looks good.
r Environment feelsmuch morepositive.
r The positives faroutweigh thenegatives.
r There were somevery positiveaspects to thisproject.
r Quite proud of it.
r We couldn’t havedelivered thisproject viacontractor designportions /packages.
r Duringconstruction, thesite operatedwithout needing amain contractor.
r Ambience
r Tactile finishes
r Needed leadframe contractorand open booktendering
r Prefabrication led to a qualityexposed finish.
r Quality products.
r Known and provenmaterials.
r Achieved excellentlight grey finish;important forlighting.
r Fully integratedapproach conceptensures full earlyintegration.
r Units made incontrolledenvironment withhigh qualitystandards achieved.
r Integration between packagesub-contractors.
r Enabled services to be integratedefficiently andwith confidence.
r Final account forstructural packagewas within + or – 10% oforiginal budgetincludingconstraints causedby outside forcesunknown attender stage.
r Value for money.
r Open bookapproach.
r Maximum planning time for constructionsequence.
r Early decisions byclient/contractorgave materialssupply to site abetter chance of keeping toprogramme.
r Allowed fasterection ofstructure.
POSITIVE COMMENTS ABOUT THE HCC BUILDINGS FROM WORKSHOPS
Knowledge captureworkshops
Table 12Positive comments about the
HCC buildings from workshops
The objective of the workshops was to reconvene project teams (including client,
architect, project manager, engineer, main and specialist contractors, precast
manufacturer and/or others as appropriate) who were involved with completed HCC
buildings or structures. The aim was to capture the key ‘events’ that characterised the
use of HCC. ‘What went right’ and ‘what could have been improved’ were evaluated
such that generic best practice lessons on process and product were extracted. How is
the building performing? Do maps of the process look right? Have drivers and barriers
been identified?
A series of five workshops was held in
various locations around the country
during early 2003. The workshops were
designed and facilitated to maximise the
extraction of both explicit and implicit
knowledge.
The workshops generally followed the
following format:
■ Walk around site.
■ Introductions and briefing.
■ An ‘event line’, detailing the critical events that affected the HCC was constructed. The
aim was to find out how the team came to the decision to use HCC, how they got the
go ahead and how it progressed on site. The exercise revealed what was the ‘process’,
who was involved and when.
As the workshop timetable was very tight, participants were asked to bring relevant
information – by way of drawings (floor plans, sections, and frame details), elemental
costs, frame/element specifications, diaries, form of contract information or other
documents on procurement etc. relating to the project – to help create the event line.
Process mapping
THE KNOWLEDGE CAPTURE WORKSHOPS
Ipswich Town Football Club North Stand
Toyota GB Headquarters Epsom
West Quay Car Park Southampton
Whitefriars Shopping Centre Canterbury
In addition, a ‘not hybrid’ workshop was held withmembers of the Advisory Group in London.
Table 11The Knowledge capture workshops
The event line was evaluated and its content was examined. The aim was to find out
‘what went right?’ ‘what went wrong?’, and ‘what would the team do differently next
time or advise others to do?’ Each participant highlighted at least one good and one
bad aspect of the project and was asked to explain why he or she had chosen that
aspect and how, in the case of it being a negative, it could be resolved next time. The
exercise revealed where the key learning points were and some best practice lessons.
Following a summing up, the project was reviewed as a whole. Members of the group
commented from their perspectives on the HCC aspects in particular. The aim was to
establish whether HCC satisfied the project objective(s) overall.
Each workshop was written up, checked by participants and analysed. Generic lessons
were incorporated into the process model and best practice guidance. The content of
the workshop reports are confidential to the participants; some anecdotes are featured
in Chapter 5.
During the research and interviews several themes came to light. The following (Table
13) summarises the findings:
59
Appendix
58
Appendix
Emergent themes
Table 13Emergent themes18
Note* The term ‘two-stage
contract’ was used here in thecontext that a job is let in two
stages, with the initial inputfrom contractors/specialists
paid for in its own right duringthe first stage (usually
extending only into conceptualdesign).The second stage may
extend up to construction(which is then let out
separately) or may extendthrough design, productiondrawings and construction.
EMERGENT THEMES
Problem solving
Trust
Communications
Get better value
Early involvement
Lead Frame Contractor (LFC)
Workshops
‘How it should be’
r There is an emphasis on problem solving at the design stage, rather than tendering and squeezing of budgets.The ultimategoal should be that on-site operations should go smoothly because any anomalies will be worked out ‘on paper’.
r There is an inherent degree of trust involved, whereby the specialists come forward early on, giving advice in goodfaith, but this goodwill must be honoured in some way to maintain good working relationships.
r Management of communications is key to success and so the role of project manager becomes closely associated withthe business process and personnel aspects of the project. On the other hand, the role of a lead frame contractor (LFC)is to undertake and deliver the practical matters. In general, roles are very clear cut, provided sufficient early agreementsare reached between all the parties.
r Several interviewees suggested that the Best Practice for Hybrid Concrete Construction (HCC) model should apply toany project, not solely HCC because it offers a much better opportunity to get a better value building. Many peoplehad direct experience of this – some even called the model ‘how it is for us – every day’.
r It was thought vital that the architect, engineer, quantity surveyor and M&E engineer were on board at thefeasibility stage. The interviewees felt this better represented true partnering and it was crucial for theseprofessions not to work in isolation.
r Main contractors and specialists could join earlier than conceptual design stage, depending on the client and/or thecontract. In some cases a two-stage contract* was thought to be a good option as too early an involvement may notalways be ideal.
r Providing this would not lead to too many layers of management, the concept of a LFC was favoured.The LFC must bewell versed in all materials.When working with construction managers, the LFC must expect to work within an integraldelivery team or cluster to deliver a frame & envelope package.
r Perhaps the most insightful theme to arise during the interview process was the steady feedback on the importance of workshops throughout the course of a project, leading towards a clear feedback loop for continuous improvementand project-to-project learning.The suggested programme of workshops is shown in Table 4 and is clearly designed tofacilitate better communication, promote best value and prevent unforeseen problems arising as far as possible.
r Regular design development and progress meetings would continue as a matter of course.
r The ‘How it should be’ model, was seen as a good basis for a less adversarial way of working.This way of working ismore favourable to all types of construction, not only HCC.
The Construction Best Practice Programme (CBPP)6 oversaw the development of Key
Performance Indicators (KPIs). This series of simple indicators provides industry with a
method of measuring performance against benchmarks. The M4i Demonstration
Projects programme brought the indicators to life and many of the 180 projects were
measured publicly against the KPIs. M4i thus developed as a springboard organisation
for companies involved with the demonstration projects to share their progress with
other like-minded organisations throughout the UK. The effect of these developments is
that the industry is now more accustomed to indicators and a culture of measurement.
On this basis, it was agreed that while the original HCC list17 of aesthetics, function,
speed, responsiveness, safety, integration, buildability and confidence, was representative
in an academic sense, it needed to be tested against current market conditions. A list
of likely performance indicators was compiled. Interviewees were invited to view this
list as a stimulus for proposing Hybrid Concrete Construction Performance Indicators
(HPIs) from their own viewpoints.
Interviewees were asked to state the most important HPIs (Table 14) from their own
viewpoints and experience and to rank them. The small sample of interviewees
precluded any valid statistical analysis, so the results are presented below simply on
the basis of frequency of citations by interviewees. Three levels of relative importance
emerged and these are shown in Table 15.
The fact that speed and cost issues appear at the head of this list comes as no surprise,
but what was interesting was the frequency of use of terms such as value, value for
Performance indicators
Notes1. First espoused by Rethinking
Construction 2, now firmlyestablished within the
‘Construction Best PracticeProgramme’6 as a
measurement method forcompanies, sector and the
industry as a whole.
2. Proposed in summer 2002as a means of adding more
qualitative issues to theoriginal KPIs.
3. Movement for Innovation(M4i) 4 Sustainability Working
Group Report, these areenvironmental performance
indicators for sustainableconstruction.
M4i,Watford, Herts.
4. Established during a previousresearch project on HCC,
principally by Peter Barrett,University of Salford17.
r Client satisfaction – product
r Client satisfaction – servicedefects
r Predictability – cost of design
r Predictability – cost of construction
r Predictability – time for design
r Predictability – time forconstruction
r Profitability
r Productivity
r Safety
r Construction cost
r Construction time
r Overall cost
r Overall time
r Build quality: performance,engineering systems,construction
r Functionality: use, access,space
r Impact: form and materials,internal environment, urbanand social integration,character and innovation
r Operational energy (CO2)
r Embodied energy (CO2)
r Operational waterconsumption
r Waste (in construction)
r Construction transport
r Biodiversity
r Aesthetics
r Function
r Speed
r Responsiveness
r Safety
r Integration
r Buildability
r Confidence
r Cost
Table 14Potential HPIs list KEY PERFORMANCE
INDICATORS (KPIs)1
DESIGN QUALITYINDICATORS (DQIs) 2
ENVIRONMENTALPERFORMANCEINDICATORS (EPIs) 3
HCC PERFORMANCE CRITERIA 4
61
Appendix
money and best value in describing the commercial criteria for success. The main caveat
to the exercise is that most interviewees stated that: “the final choice will vary from
project to project”.
The predominance of speed/cost is clear, but the second order of HPIs is perhaps the
more critical for this study. Spans, flexibility in use, fire protection and services
integration are proving to be the real battleground for structural frames. This would
indeed be the case on the basis of feedback from the client/developer sector. This group
of interviewees was keenly aware that, with M&E constituting on average one-third of
their capital expenditure on a project, their choice of structural frame will often be
determined by the frame’s facility to optimise the installation and operation costs for
the M&E. HCC may be at an advantage here by being able to offer, for example, thinner
floor slabs, clear span spaces and thermal mass.
Some sectors such as client/developer groups are driven to choose framing materials on
the basis of criteria such as flexibility and M&E provision. This indicates that the offering
from specialist concrete contractors and others should perhaps be targeted more
appropriately to meet these needs.
60
Appendix
Table 15Prioritised Hybrid
Concrete Construction
Performance
Indicators (HPIs)
INDICATORS NOTES
As part of its work on Hybrid Concrete Construction for the UK market 1. Imperial College
was asked to give guidance on the structural design of HCCs. In the main, the principles
of in-situ and precast concrete hold true. In the case of proprietary items, design is
often covered by manufacturers’ literature. Designers may be less familiar with the
design of bespoke composite concrete and so the notes below were prepared.
In general, composite concrete elements may be considered as being monolithic and
homogeneous. Usually, the precast concrete will be stronger than the in-situ concrete; it
will definitely be older and drier. It will be generally conservative to design the elements
on the basis of the lower strength but the different concrete properties of the concretes
should be acknowledged and reference should be made to BS 8110: Part 1, Clause 5.422.
It may be appreciated that not all the information required for design will be available
to designers at the beginning of the design process. Methods of construction,
timescales, materials etc. should be discussed and agreed with the contractors and
other members of the design team as appropriate as the design develops.
Composite reinforced concrete elements and structure should be checked for the
following stages:
Stage 1: Construction stage (dead load + construction loading) The precast units are checked using traditional calculation methods. The loading
includes self weight, weight of wet concrete and construction loading. For proprietary
items, tables for span and load limits are usually provided in manufacturers’ literature
and these construction load checks or temporary propping requirements are generally
implicit. Otherwise, full design checks will be required at both ULS and SLS. Handling
requirements are also often given in manufacturers’ literature.
Intermediate propping of precast units has the advantage of reducing construction
stage span moments, deflections and shears, but has the disadvantage of introducing
possible time and cost penalties on site and of inducing hogging moments over props
which have to be catered for.
Stage 2: Depropping (dead load + construction loading) Checks are generally not required unless removal of intermediate props is proposed
prior to the in-situ concrete reaching its full design strength. Nevertheless, removal of
props causes redistribution of loads and the capacity of members to carry the revised
loads should be considered. In the unlikely event of this being a worse case than the
final design load case, design checks should be made for the revised loads using a
concrete design strength appropriate to the time of removal of props.
Where depropping is needed before the concrete has achieved full design strength,
checks will be required at both ULS and SLS.
A.3 Structural Design
General
The design process
‘Higher’ importance
Speed
Cost
‘Medium’ importance
Spans / lettable area
Flexibility in use
Fire
Services integration
‘Lesser’ importance
Buildability
Environmental
Finish
Quality
Site conditions
Structure
Market conditions
Safety: An absolute necessity and must always be addressed
r Productivity/efficiency on site; time; programme; lead-in time.
r Cost of package; value for money (NB: eight of the 13 interviewees had speed/cost in their top three choices).
r Floor depths/building height; preferred grid; vertical access routes; third-party aspects (NB: clients prioritised maximising lettable area spans of up to 15 metres).
r Low maintenance; good performance.
r Fire protection; robust fire protection.
r Air conditioning options; control; sound/thermal insulation; fabric energy storage.
r ‘Being tolerant’; tolerances.
r Embodied energy/operational energy; waste; M4i sustainability indicators.
r Certainty of finish; architectural merit; visual surfaces.
r Certainty of quality of product.
r Access; site constraints; logistics.
r Dynamic requirements; load carrying ability; overall stability; temporary stability.
r Risk; capacity; resources; capacity available; certainty.
63
Appendix
Stage 3: Full composite action (dead + live loads)Flexure
Reinforcement is calculated for the total ultimate moment using the full composite
section. For prestressed precast units, an alternative method is to calculate the area
of steel required for Stage1 (with precast section only) and add the area required for
Stage 3 (using increased lever arm for composite action). The difference in using either
method is not great if the superimposed moment for Stage 3 is more than twice the
self weight moment for Stage 1. The flexural capacity of composite beams can be
enhanced because the breadth of the compression flange can be increased up to the
maximum permitted value for monolithic construction (BS 8110: Part 1, Clause 3.4.1.2).
Detailed guidance on this is given by Elliot26.
Shear
Shear checks on beams and slabs are made using traditional methods assuming full
composite action. It is conservative to use the lower concrete compression strength
for the shear calculation. For precast hollowcore floor slabs, shear strength can be
calculated or taken from trade literature. The ultimate limit state of shear is not usually
critical and hence any in-situ topping is usually ignored in the calculations. If required,
additional shear strength provided by the topping may be calculated using background
research information.
Interface shear transfer
Full composite action assumes that the shear transfer across the interface between
in-situ and precast is adequate. Interface shear transfer depends on the surface type
of the precast unit and can be calculated using the principles given in BS 8110: Part 1,
Clause 5.4.7.2.1. It may be necessary to provide links to connect the in-situ concrete to
the precast element and to ensure interface shear transfer.
Anchorage and bearing
See BS 8110. Tolerances will need to be considered.
Differential shrinkage
BS 8110: Part 1, Clause 5.4.6.4.1 recommends that differential shrinkage should be
considered where there is an appreciable difference between the age and quality
(strength) of concrete in the precast and in-situ components. Tensile stresses due to
differential shrinkage may require consideration in design and the engineer should refer
to specialist literature in deciding where these stresses may be significant. Further
guidance on this is given by Elliott26.
62
Appendix
Deflections
The main serviceability issue to be considered for composite construction is the control
of deflections. Deflection checks should be carried out on the composite structure as for
a monolithic structure. This will normally be based on a simple span: depth limit given
in current codes. This assumes that the precast and in-situ units act fully compositely
for longer term loading. Deflections can be carried out using the methods given in
BS 8110: Pts 1 or 2. Where rigorous calculations are required for deflections, the method
given in the CEB-FIP Model Code 199029 can be used. This method is similar in principle
to the current Eurocode 2; Design of concrete structures27. The method can be suitably
adapted to take account of varying concrete strengths within the section or the lower
concrete strength can be assumed throughout the section as illustrated by Ghali and
Favre28. Tests have shown that the floor units effectively contribute to the stiffness of
composite beams. However, design models are not yet available to take this advantage
into account.
Striking the formwork is assumed to be carried out in such a way that composite action
is maintained. It will normally be conservative to assess the age for striking as for
normal in-situ construction by specifying a minimum concrete strength for the in-situ
concrete.
Deflection calculations should take into account the different compressive strengths of
the precast and in-situ parts: however, it will generally be conservative to use the in-situ
concrete strength for the whole section. The designer should also consider the practical
implications of deflection at each stage. For example, if a false ceiling is to be provided,
then Stage 1 and 2 deflections may not be considered as being significant and only
Stage 3 deflections might be subject to limitations. In other cases, deflections developed
in the structure before composite action has been established must be added to the
longer term deflections of the composite action. Deflections can be calculated on the
basis of a simple analysis taking into account loading due to the placing of concrete or
other construction loading acting on the precast elements.
Cracking
It will be conservative to check cracking limits for SLS assuming a concrete strength for
the in-situ concrete. Deemed-to-satisfy detailing rules are generally sufficient to check
for cracking at the SLS. If detailed analysis is required, this should be based on the
actual strain distribution due to Stage 1 and Stage 3 loading. Detailed design guidance
is given in Clause 3.4.7 of BS 8110.
Toppings
Structural toppings are not normally necessary to achieve adequate interaction between
the floor units. However, where used, they do increase ultimate moment capacity.
Toppings should be at least 40 mm thick and lightly reinforced. They should be laid on
clean, damp (not wet) surfaces and to avoid shrinkage, the mix should not be too rich
or too wet.
Supports
Some of the practical points to be considered are:
■ minimum support length allowing for tolerances and spalling. Table 16 gives initial
values, which might be decreased (e.g. if temporary supports are provided)
■ evenness of the contact zone along the support
■ rotation capacity – prevention of spalling
■ tie arrangements
■ degree of restraint of the floor units (e.g. unintentional continuity).
Openings
Hollowcore units can be manufactured with openings up to approximately 400 mm
wide internally and up to about 300 mm on an edge. Holes up to about 150 mm
diameter can be core-drilled on site. Larger holes usually involve trimmer angles or
in-situ trimmer beams.
In composite floor-planks, voids and cut-outs can easily be added, even after placing the
floor planks, due to the small thickness of the plates. If required, additional reinforcement
may be placed in the in-situ part of the slab.
64
Appendix
Reinforced concrete orsteel girders
Brick masonry
100 –150 mm
70–130 mm
75 –150 mm
–
70 mm
100 mm
125 mm
125 mm
SUPPORTINGSTRUCTURE
HOLLOWCORE UNITS120 mm - 400 mm thick
RIBBED SOFFIT UNITSLow – heavy loading
FLOOR PLATES
BEAM-BLOCKFLOORS
Table 16Nominal values for support length to
be used at the initial stage of projects
Best Practice Guidance for Hybrid Concrete Construction
This publication emanates from the DTi PII Research Project‘Best Practice Guidance for Hybrid Concrete Construction’.The research was intended to provide introductoryexperience-based guidance on the use of Hybrid ConcreteConstruction for key players as identified in previous research.
This publication aims to provide such guidance and demonstrateshow to achieve best practice. It is a guide to choosing and usingcombinations of precast and in-situ concrete for better value frames.
Charles Goodchild, main author of this publication, is thePrincipal Structural Engineer within The Concrete Centre.
Dr Jacqueline Glass, principal researcher on this project, isLecturer in Architectural Engineering at Loughborough University.
CI/Sfb
UDC
624.05.016-033.3 (083.132)
TCC/03/09 Published September 2004 ISBN 1-904818-09-9Price Group L © The Concrete Centre
Riverside House, 4 Meadows Business Park,Station Approach, Blackwater, Camberley, Surrey GU17 9AB Tel: +44 (0)1276 606800 Fax: +44 (0)1276 606801www.concretecentre.com