[CCH] BST22316 2012_2013 Sem B RW Assignment

Embed Size (px)

Citation preview

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    1/24

    1

    Semester B, 2012/2013

    BST 22316

    Construction Technology

    Lecturer:

    Mr. WONG Wai Man Raymond

    Individual Assignment

    Student Name: Cheung Chun Hin

    Student I.D.: 52999911

    Hand-in date: April 2, 2013

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    2/24

    2

    Table of Content

    1. Introductions / Assumptions / Overall View2. Stage 1 - Ground Stabilization Provisions3. Stage 2 - Cut-off Walling Provisions/Lateral Soil4. Support Provisions5. Stage 3 - Excavation Arrangement6. Stage 4 - Dewatering Arrangement7. Stage 5 - Spoil Removal Arrangement8. Stage 6 - Basement Construction Arrangement9. Conclusion10.References

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    3/24

    3

    1.Introductions / Assumptions / Overall View1.1 Abstract

    In building a deep and large-size basement, there are various elements and

    considerations such as labor, space, material, machineries, basement design

    requirement, etc. As for a successful project, a proper arrangement and control

    is important, therefore we will focus on situation analysis, make appropriate

    approach and problem solving methods in the each of the following parts.

    In this report, there will be mainly focus on the basement construction with the

    6-7 principle steps. By illustration of diagram and photos taken by me, it would

    be explained in detail about the actual steps of construction sites and material

    types. More than learning in text book through theories, it is learning in a more

    realistic method and manner.

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    4/24

    4

    Nature & Purposes

    Project Aims: This project is to build up a building with a deep and large basement

    1.2 Master Flow Chat

    1.3 Common managerial problems identified in the construction of deep basement:1. Very expensive and time consuming in nature, often involved

    huge amount of work resources.

    2. Inconsistent and sensitive to the quality of planning and

    management of individual projects.

    3. Works are highly hazardous, both to human operatives

    working within and the life and properties of third parties that

    within the vicinity.

    4. Works involved a lot of managerial challenges. Such as, in

    the preparation of a highly efficient working programme,

    monitoring and rectifying the progress of works in case

    problems arising, or in resources planning where materials,

    labours & plant equipment are involved.

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    5/24

    5

    2.Stage 1 - Ground Stabilization Provisions2.1 Purpose

    There are mainly 3 functions for ground stabilization, including strengthens

    improvement (increase load-bearing capacity of soil), dust control (alleviate

    dust generated by machinery operations), and soil waterproofing (to increase

    waterproofing ability of soil from surface)

    2.2 Situation AnalysisGiven that the site is large in size and the soil in weaker in nature, the main

    function for ground stabilization is to strengthen soil load bearing capacity so

    that the soil have sufficient stability to support the loading from the building(dead-load) and users (live load).

    2.3 Possible Methods & ChoiceThe method of soil stabilization is broadly divided into 2 approaches, chemical

    soil stabilization and mechanical soil stabilization. In Hong Kong, there is

    mainly using grouting which is under chemical soil stabilization approach

    1. Add quicklime / hydrated limeMechanism: absorb the water / moisture in soil

    Advantages: easy transportation, cheap

    Considerations: cannot reach deep underground, time-consuming

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    6/24

    6

    2. Fly ashMechanism: reduce the air voids

    Advantages: easy transportation, cheap

    Considerations: cannot reach deep underground, time-consuming

    3. GroutingMechanism: reduce the air voids, control water fillings, prevent sand

    deification, reduce vibration, and reduce settlement.

    Advantages: numerous varieties of functions, stable, effective

    Considerations: comparatively expensive

    Recommendation

    Among the above options, it is recommended to take grouting as the way to

    stabilize the ground, because it is relatively efficient, reliably stable.

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    7/24

    7

    2.4 SequenceCement grout is formed by mixing water, cement, sand in a proper ratio (typical

    proportion by weight is 1:0.5:3). It is intended that cement mortar is

    constructed by placing, packing, or pressure pouring. Owing to the relatively

    high water content, the mixing of cement with water produces a fluid

    suspension which can be poured under base plates or into holes. Then to wait

    some days for setting and hardening, this process is to create a good

    performance. After the grouting is finished, a substantial proportion of load is

    designed to be transferred by the bedding to other members.

    2.5 Considerations of this Method2.5.1 Rainy weather may lengthen the time-requirement for setting, weaken or

    even damage the grouting.2.5.2 Strong sunlight may damage the grouting quality2.5.3 It is necessary to control the voids in the soil, because excessive voids may

    affect the strength, stiffness and permeability of grout

    2.6 Solutions2.6.1 Ensure the soil quality by civil engineer2.6.2 Prepare the project time properly in avoid construction within rainy seasons.Calculate the mixture ratio of grouting carefully based on the soil data, and add other

    chemicals whenever necessary.

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    8/24

    8

    3.Stage 2 - Cut-off Walling Provisions/Lateral SoilSupport Provisions

    3.1 PurposeTo withstand the lateral loading of the site, so that the site can be safe when

    constructing basement or other works.

    3.2 Situation AnalysisWe assumed that the soil is bad graded and soil content is wet in nature. There

    are adjacent buildings nearby. We should consider the spacing and the sufficient

    support to the side force.

    3.3 Possible Methods & ChoiceThere are many ways to construct a cut-off wall. Despite of the methods are so

    many, there are commonly 6 types of practices in Hong Kong which are as

    follow:

    1. Steel pile

    [Photo taken ME @ 1/4/2013 Wu Hu Street]

    Advantages: resist tension

    Considerations: rusting may occur

    STEEL PILE

    Lateral Support

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    9/24

    9

    2. Soldier pile

    [Drawn by Me]

    Advantages: reusable, reliable, relatively cheaper than steel pile

    Considerations: rusting may occur, require accuracy jointing

    3. Hand-dug caisson

    Advantages: cheaper cost

    Considerations: very dangerous to workers life

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    10/24

    10

    4. Bore pile

    Advantages: very stable

    Considerations: expensive, permanent

    5. Mini-pile or pipe pile

    Advantages: suitable for small or medium construction site

    Considerations: rusting may occur, limited to 12m depth

    6. Diaphragm wall

    Advantages: fully supported

    Considerations: require more complex procedure and more support system

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    11/24

    11

    Recommendation

    After the choosing the above choices, it is better to use diaphragm wall with

    steel struts and diagonal bracing in this situation (but not using anchor),

    because it support deep excavation without using other underground

    spacing.

    Elevation:

    [Photo taken by ME@1/4/2013 Intercontinental Hong Kong expansion work]

    Illustration Drawings [Drawn by Me]:

    Section:

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    12/24

    12

    NOT USING ANCHOR (because buildings nearby)

    [Photo taken ME @ 1/4/2013 Chatham Road North]

    3.4 Case Example

    Just like the basement work in Intercontinental Hong Kong expansion work

    Anchors

    Increase the slope stability

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    13/24

    13

    () which owned by the New World Development

    Company Limited. The basement used the diaphragm wall with lateral

    supported by the steel struts and diagonal bracing. It is a common and

    economic method which broadly adopted in large site construction.

    3.5 Considerations of this Method1. Require more complex procedure2. Need more spacing3. Preparations require more time

    3.6 Solutions1. Recruit more skilled labor2. Carefully planning the site spacing and use more

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    14/24

    14

    4.Stage 3 - Excavation Arrangement4.1 Purpose

    Before building a new structure at a specific site, excavation of the original spoil

    above or below the ground is needed so that the building works are process

    properly. There are several considering factors which are as follow:

    1. Nature of subsoil affect type of machine used and the necessity of soilprotection.

    2. Size of excavation affect type of machine used and method to excavate.3. Scale of work large volume of excavation may involve complicated phasing

    arrangement and work planning

    4. Ground water condition affect degree of protection (watertight sheetpiling or dewatering may require)

    5. Surrounding condition impose certain restrictions and precautions (e.g.diversion of a government drain, or underpinning work to the nearby

    building foundation)

    6. Depth of excavation affect use of spacing and working platform4.2 Situation Analysis

    In this site, the subsoil is loosely compacted, not much rock and there isnecessary to strengthen the soil. Since the site is large enough, large machines

    with higher efficiency are available in use. In building a deep basement,

    excavation machines are needed to work at the bottom of the designated site

    with different level at each of the time. So, when the basement is not deep,

    there would only need to use simple excavation machines; but when it is deep

    enough, it would necessary to use machines support long distance carrying.

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    15/24

    15

    4.3 RecommendationIt is recommended to take excavation in a way ofbencharrangement for open

    site. Firstly, it excavate the central part of soil and make it similar to open-cut

    method. Then it forms slopes at the surroundings and excavate the soil at the

    side after the central part is clear. This is a pattern that the site would be

    excavating into a shape like bench when we looking at the top of the site. This

    has an advantage that the remaining soil can act as a support at the corners

    while there is sufficient spacing provided for operation of work. About the edge

    of the remaining soil, it would be good enough to have cut edge with step or

    edge of cut, because these 2 shapes are safety enough. Even there is a heavy

    rain, it would not easily collapse or slide down.

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    16/24

    16

    5.Stage 4 - Dewatering Arrangement5.1 Purpose

    It is a process to remove the over-saturated water in ground and keep the

    subsoil within a non-saturated condition.

    5.2 Situation AnalysisWe assume that there is no underground river crossing the expected working

    space, high water table and there is a need of dewatering. In this case, we are

    going to build a deep and large size basement, therefore we should dewatering

    as a way to lower pore pressure in soil and avoid causing any damages by base

    heave.

    5.3 Possible Methods & ChoiceIn total there are 3 methods in dewatering, including:

    [Active drainage method]

    Dewateringby deep wells

    Dewatering by wellpoints &

    [Passive drainage method]

    Dewatering by horizontal drainage.

    1. Dewatering by deep wells

    Advantages: drain large amount of water at a time

    Disadvantages: uneven drainage over the whole construction site

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    17/24

    17

    2. Dewatering by wellpoints

    Advantages: very flexible arrangement, occupied less area

    Disadvantages: not as efficient as the above method

    3. Dewatering by horizontal drainage (e.g. sump pit)

    Advantages: no need to exclusively excavate

    Disadvantages: working condition is poorer, passive

    Recommendation

    After analysis the above methods, we will choose to take dewatering method

    by well points. Because the site condition is assumed to have no underground

    river which no need to drain large amount of water, but needed to drain evenly

    over the whole site. Whenever necessary, we should also use dewatering by

    horizontal drainage.

    5.4 Precautions5.4.1 It has to be ensure the depth, number, distribution of wellpoints are

    appropriate

    5.4.2 The use of horizontal drainage should be ready when site level reached theoriginal water table level

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    18/24

    18

    6.Stage 5 - Spoil Removal Arrangement6.1 Purpose

    There are always spoils created by excavation, ground displacement work,

    in-suit materials, etc. In order to protect the adjacent environment and to cope

    with the regulations, it is necessary to remove the spoils in a proper method. In

    addition, there are some special materials requires special treatment before

    discharge (e.g. Asbestos). Therefore, it is undoubtedly that even removal

    requires a plan.

    6.2 Situation AnalysisIn the construction of a basement, there would probably have the followingspoils:

    1. Soil2. Concrete materials3. Sewage4. Temporary non-reusable structures5. DustBut in the above, we will focus on soil removal arrangement. Because soil takes

    the largest portion of spoil in nearly every site. When in considering soil removalmethod, we would make decision on using what types of excavator and why to

    use them.

    6.3 Possible Methods & ChoiceThere are many types of excavator, including:

    1. Compact excavator [Photos taken by ME @1/4/2013 Chatham Road North]

    Advantages: higher mobility

    Disadvantages: lower weight can be carried (0.7-0.8 tones)

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    19/24

    19

    2. Dragline excavator [Photo taken by ME@1/4/2013 Intercontinental Hong Kong expansion work]

    Advantages: Able to transport 168 meters and 450 tones material

    Disadvantages: extremely high capital cost

    3. Long reach excavator

    Advantages: support distance away carriage

    Disadvantages: (same with Compact excavator)

    4. Steam shovel

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    20/24

    20

    Advantages: allow to install on the train

    Disadvantages: Uncommon to be use

    5. Power shovel

    Advantages: very powerful in harrying weight

    Disadvantages: not applicable in all types of construction

    Recommendation

    From the analysis of the above excavators, we decided that Compact excavator

    and Dragline excavator will be used in the construction work. There will be

    around 10 compact excavator working at the basement site and cooperativelywork with dragline excavator at the upper level of the site.

    6.4 Considerations of this Method6.4.1 Accidents maybe happen during lifting the soil upwards6.4.2 Spacing is important for accessing6.4.3 Air pollution is serious in the site6.4.4 Air pollution and noise pollution may affects the surroundings6.5 Solutions6.5.1 All workers should equipped with safety protective equipment and supervise

    by experienced manager

    6.5.2 Keep area tidy6.5.3 Improve air ventilation of te site6.5.4 Cover the working site area with plastic curtain

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    21/24

    21

    7.Stage 6 - Basement Construction Arrangement7.1 Purpose

    Illustrate basement construction method within the common choice of

    Open-cut arrangement, Bottom-up arrangement, Top-up arrangement

    with considerations of efficiency and economy.

    7.2 Situation AnalysisAs information given, the proposed basement site is large in size and deep.

    Therefore 4 points can be deduced as follows:

    1. Numerous large machineries are supported to work at the same time2. The lateral support is heavy3. Basement works working time requirement proportionally larger than

    normal site, as in accounting the whole project time requirement

    4. The basement can support complex construction environment5. System formwork may be used if the spacing can appropriately handled

    7.3 Possible Methods & ChoiceConsidering using which of the methods in basement construction, factors like

    construction environment, machineries, spacing and spoiling removal methodsare important and the following table shows the major comparison with each of

    the methods.

    Open- Cut

    Top-down Bottom-up

    Size of site Very large Large Medium to small

    Site environment Unobstructed Adaptable to most

    environment

    Adaptable to most

    complex environment

    Lateral Protection Minimum Limited shoring

    support

    Complex lateral

    support

    Machineries

    Support

    All size

    machinery

    Only small size

    machinery

    All size machinery

    Space provision Not much Not much Temporary vertical

    support is needed

    Spoil removal

    method

    Most Limited Limited, but more

    choice

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    22/24

    22

    Recommendation

    After comparing 3 common practices in Hong Kong, it is affirmative that

    Top-down method is the most appropriate one among the choices. The

    reasons are as follow:

    1. Support above ground construction carried out simultaneously2. Save the cost of formwork3. Settlement can be reduced4. Less time requirement

    [Drawn by ME]

    7.4

    Considerations of this Method1. Accurate cost analysis or work study is difficult to carry out for there is

    limited commonality to make comparisons.

    2. A great number of random and uncontrollable variances are likely to ariseduring the courses of work. This makes planning and scheduling almost

    cannot be exact.

    3. The actual effectiveness of works is highly depended on the as-constructedsite environments.

    4. Quality of the management and the executing parties, as well as theproblems solving ability of the frontline personnel, also seriously affects the

    performance and effectiveness of works.

    7.5 Problem Solutions1. Collecting the material data from the market and make use of bulk purchase

    when prices are low, properly manage use of material and avoid wastage.

    2. Make thoughtful building plan before the start of work3. Keep area tidy by place unnecessary equipment away the working area4. Recruit skilled managers and workers

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    23/24

    23

    8.Conclusion

    After the above 6-7 involvement principle, we can conclude that theconsiderations are broadly classified as cost, materials, working method, time, design,

    structural properties and management. It is the utmost consideration of construction

    in Hong Kong that, time and conveniences are more an essential factors in the whole

    working process because the income on sales or rental of the building is a large

    amount of pays, compared to the cost of constructing it.

    Another point is that, compared to the past years, safety concerns are arising its

    importance to any of the constructions in Hong Kong. In the past, building basement

    is a difficult and dangerous job as accidents may frequently appeared, particularly

    the cut-off method called Hand-dug Caisson1. This kind of method is extremely

    dangerous as anything dropped into the hole almost killed the man as there are no

    where he can escape. Therefore, I have check online and discovered that, it has been

    strictly discourage and even prohibited to be applied in Hong Kong, unless it is

    proved that no other way to construct without using this method and have a

    convincing evidence about the safety in applying this method.

    1Refer to Reference No. 6

  • 7/28/2019 [CCH] BST22316 2012_2013 Sem B RW Assignment

    24/24

    24

    9.ReferencesWEB SITE

    1. Basement Construction in Bottom-Up Methodhttp://deltacorp.vn/index.php?option=com_content&view=article&id=191&Itemi

    d=340&lang=en

    2. Construction of basement in Top-Down methodhttp://deltacorp.vn/index.php?option=com_content&view=article&id=192%3Ata

    ng-ham-theo-phuong-phap-top-down&catid=72%3Acong-ngh-mi-ang-ap-dng&Ite

    mid=339&lang=en

    3. Essential Health and Safe Tips in Basement Constructionhttp://www.hse.gov.uk/pubns/cis66.pdf

    4. Goodwood Residence Basement Construction Sequence by Steve R. Nebreshttp://www.authorstream.com/Presentation/stevenebres-598273-basement-con

    struction-sequence/

    5. Deep Underground Basements for Major Urban Building Constructionhttp://www.nicholsonconstruction.com/techresources/techPapers/PDF/Deep%2

    0Underground%20Basements%20Final%20with%20edits%20-%2010-14-03.pdf

    6. Hand-dug Caissonhttp://www.safetypartnering.com/smd/inside_c4_c.htm

    7. Introduction to Soil Stabilizationhttp://china.cat.com/cda/files/408341/7/Soil%2520Stabilization%2520QEDQ122

    9.pdf

    BOOK

    1. Puller, M., (1996), Deep Excavations: A Practical Manual, London: Thomas TelfordLtd.

    http://deltacorp.vn/index.php?option=com_content&view=article&id=191&Itemid=340&lang=enhttp://deltacorp.vn/index.php?option=com_content&view=article&id=191&Itemid=340&lang=enhttp://deltacorp.vn/index.php?option=com_content&view=article&id=191&Itemid=340&lang=enhttp://deltacorp.vn/index.php?option=com_content&view=article&id=192%3Atang-ham-theo-phuong-phap-top-down&catid=72%3Acong-ngh-mi-ang-ap-dng&Itemid=339&lang=enhttp://deltacorp.vn/index.php?option=com_content&view=article&id=192%3Atang-ham-theo-phuong-phap-top-down&catid=72%3Acong-ngh-mi-ang-ap-dng&Itemid=339&lang=enhttp://deltacorp.vn/index.php?option=com_content&view=article&id=192%3Atang-ham-theo-phuong-phap-top-down&catid=72%3Acong-ngh-mi-ang-ap-dng&Itemid=339&lang=enhttp://deltacorp.vn/index.php?option=com_content&view=article&id=192%3Atang-ham-theo-phuong-phap-top-down&catid=72%3Acong-ngh-mi-ang-ap-dng&Itemid=339&lang=enhttp://www.hse.gov.uk/pubns/cis66.pdfhttp://www.hse.gov.uk/pubns/cis66.pdfhttp://www.authorstream.com/Presentation/stevenebres-598273-basement-construction-sequence/http://www.authorstream.com/Presentation/stevenebres-598273-basement-construction-sequence/http://www.authorstream.com/Presentation/stevenebres-598273-basement-construction-sequence/http://www.nicholsonconstruction.com/techresources/techPapers/PDF/Deep%20Underground%20Basements%20Final%20with%20edits%20-%2010-14-03.pdfhttp://www.nicholsonconstruction.com/techresources/techPapers/PDF/Deep%20Underground%20Basements%20Final%20with%20edits%20-%2010-14-03.pdfhttp://www.nicholsonconstruction.com/techresources/techPapers/PDF/Deep%20Underground%20Basements%20Final%20with%20edits%20-%2010-14-03.pdfhttp://www.safetypartnering.com/smd/inside_c4_c.htmhttp://www.safetypartnering.com/smd/inside_c4_c.htmhttp://china.cat.com/cda/files/408341/7/Soil%2520Stabilization%2520QEDQ1229.pdfhttp://china.cat.com/cda/files/408341/7/Soil%2520Stabilization%2520QEDQ1229.pdfhttp://china.cat.com/cda/files/408341/7/Soil%2520Stabilization%2520QEDQ1229.pdfhttp://china.cat.com/cda/files/408341/7/Soil%2520Stabilization%2520QEDQ1229.pdfhttp://china.cat.com/cda/files/408341/7/Soil%2520Stabilization%2520QEDQ1229.pdfhttp://www.safetypartnering.com/smd/inside_c4_c.htmhttp://www.nicholsonconstruction.com/techresources/techPapers/PDF/Deep%20Underground%20Basements%20Final%20with%20edits%20-%2010-14-03.pdfhttp://www.nicholsonconstruction.com/techresources/techPapers/PDF/Deep%20Underground%20Basements%20Final%20with%20edits%20-%2010-14-03.pdfhttp://www.authorstream.com/Presentation/stevenebres-598273-basement-construction-sequence/http://www.authorstream.com/Presentation/stevenebres-598273-basement-construction-sequence/http://www.hse.gov.uk/pubns/cis66.pdfhttp://deltacorp.vn/index.php?option=com_content&view=article&id=192%3Atang-ham-theo-phuong-phap-top-down&catid=72%3Acong-ngh-mi-ang-ap-dng&Itemid=339&lang=enhttp://deltacorp.vn/index.php?option=com_content&view=article&id=192%3Atang-ham-theo-phuong-phap-top-down&catid=72%3Acong-ngh-mi-ang-ap-dng&Itemid=339&lang=enhttp://deltacorp.vn/index.php?option=com_content&view=article&id=192%3Atang-ham-theo-phuong-phap-top-down&catid=72%3Acong-ngh-mi-ang-ap-dng&Itemid=339&lang=enhttp://deltacorp.vn/index.php?option=com_content&view=article&id=191&Itemid=340&lang=enhttp://deltacorp.vn/index.php?option=com_content&view=article&id=191&Itemid=340&lang=en