Upload
margery-jefferson
View
215
Download
0
Tags:
Embed Size (px)
Citation preview
Biomethane Review of UK activity
Alan MidwinterSGN Project Manager
29th September 2011Wardell Armstong LLP
2
Who are SGN?
• Scotia Gas Networks –Formed in June 2005 following the acquisition of two gas distribution networks from National Grid (Scotland and South of England)
• Owns and operates the second largest gas distribution network in the UK.
• Serving over 5.8 million customers
Why gas networks here?
DECC 2050 Pathways Study Demonstrated that substantial electrification of heat and transport is required in order to meet 2050 Targets (80% GHG emission reduction)
What is the future for the gas networks ?ENA Gas Futures Group commissioned Redpoint to develop future gas scenarios to 2050 and beyond :-
• Retaining gas infrastructure could be up to £700bn cheaper to UK plc than a complete electrification solution
• Require low carbon renewable gas (BIOGAS) for Bio-methane • Potential for Bio-methane injection - 50% of UK domestic heating load
DECC output targets for bio-methane are 7TWh p.a. by 2020 and could extend to 150-210 TWh per annum of renewable gas by 2050
3
Gas Futures Redpoint
Pathways involving
significant
Biomethane to Grid Injection
•Green Gas
•Gas Versatility
Low Carbon Energy - Biogas• UK produces 16 million tonnes of food waste (8 million tonnes from households) and
90 million tonnes of animal waste annually with the majority going to landfill.
• Organic material degrades producing methane gas, 23 times more damaging to the environment as a greenhouse gas than carbon dioxide.
• EU landfill directive obliges local authorities to send less biodegradable waste to landfill, generating requirement to recycle or reprocess.
• Anaerobic Digestion (AD) is a waste treatment process for organic waste, recovering energy from waste in the form of biogas (50% to 65% methane)
• Biogas traditionally has been used for Electricity generation but can be cleaned for Biomethane injection or used as CNG for vehicle fuel.
6
Government Incentives
• UK Government is committed to meet Greenhouse Gas Emission targets• 15% reduction by 2020• 80% reduction by 2050
• Landfill taxes – increasing to £80 per tonne.
• Energy recovery potential for AD could support 2,100 AD plants (50,000 t) will be required.
• The Government has incentive schemes for the use of Biogas as a low carbon energy
• Existing incentives FIT’s & ROC’s for electricity generation• RTFO’s for vehicle fuels
• Government has now incentivised a scheme that will for the first time provide long-term guaranteed financial support for renewable heat installations
• Renewable Heat Incentive (RHI)
8
RHI & Bio-methane Injection
• Introduction of the RHI (July 2011) provides a sound economic pathway for gas injection into the grid, financially attractive above 500 m3/h bio-gas (300 m3/h biomethane).
• Bio-methane RHI tariff is currently 6.8p / kWh
• 20 year tariff to include capital cost for all plant
• Degression of RHI tariff will feature once target volume is reached
• Bio-methane injection is 50% more efficient than electricity only applications
• Important contribution to a stable and reliable energy supply
11
Project time-line
• SGN commissioned Feasibility study in April 2009
• Project Approval April 2010• 3 October 2010 SGN, working with
our partners, Thames Water and Centrica, delivered the first Bio-methane gas to Grid in the UK
12
Key Objectives
• SGN used Innovation Funding to deliver a number of important objectives:
• Understand Legislative and Regulatory issues• Improve understanding in relation into gas quality (Oxygen and
siloxanes in particular)• Understand the impacts of bio-methane on the operation and
configuration of the local gas network• Prove biogas clean-up and upgrading technology in the UK• Provide a ‘base-line’ for gas quality monitoring and associated
equipment from which lower cost options could be developed• Share Project learning and improve efficiency to the benefit of future
schemes
13
Regulatory Requirements
• Safety (HSE)• Transporters may only Transport gas that complies with
provisions of Gas Safety Management Regulations (GS(M)R)• Gas Transporters are obliged (by the Regulations) to take
sufficient measures to confirm that gas is compliant or must not allow gas to flow
• Commercial (Ofgem and the Uniform Network Code)• The bio-methane must have its energy measured in
compliance with Gas Thermal Energy Regulations• The processes must comply with appropriate UNC
arrangements
Gas Quality Baseline
• Establish Biogas composition and available flow-rate• Ensure the local SGN Network could accept the
volume of gas that will be produced on a 24/7 basis• Establish biomethane gas quality requirement,
specifically around :• Oxygen• Siloxanes• Calorific value
• Identify appropriate biogas clean-up and upgrading technology for Didcot
14
Key Objective Outputs
• Oxygen content could potentially be up to 2%• HSE derogation would be required for >0.2%
• Siloxanes were likely to be present in the biogas• Additional filtration equipment would be required
• The calorific value from the bio-methane would be lower than the existing network values
• Enrichment with propane would be required
• Costs were likely to be high – SGN IFI Funding used• The project could be implemented in 2010 and would
therefore provide valuable learning ahead of RHI introduction in 2011
15
How can AD Biogas become Bio-methane
• Bio-gas from an anaerobic digester contains typically
• Natural gas contains around 90% methane, with ethane, propane, butane, CO2 and nitrogen making up the rest.
• To inject Biogas into the gas grid it is necessary to clean it and upgrade it to biomethane
• Bio- methane is around 98% methane content
16
Methane = 55 – 65% CO2 = 35 – 40% O2 = 0.1 – 0.5%
N2 = 0.5 – 2% H2S = 200 – 2,000 ppm Siloxanes (sewage only)
Why Didcot ?
• Existing Sewage Treatment Works with 2 Digesters producing sufficient waste biogas
• Thames Water interested in the SGN proposition to clean up the biogas, upgrade and inject into
the local SGN grid
• Practical details:• Resilient local Network within 400m of site• Available space• Unlikely to have issues with planning authorities
19
21
Site Location
Location of New Plant
Connection to Gas Network
Residential Area that will use new
gas supply
22
Biomethane – The Process
ADGas
Storage
Flare
Bio-gas Clean Up Plant
(Water Wash)
Bio-methane to Grid Entry Equipment
(Network Entry Assets)
Existing Gas Network
Out of Spec Bio-methane
Gas Engines
Network Entry
Valve (ESD)
Network Connection
Bio-methane
97-98% BioCH4
0.3% O2
Typical Bio-gas
60-65% CH4 34-36% CO2
1% O2
Propane Upgrade
CO2 Filters
AD
Electricity Output
Site Layout
23
Water Wash Process
Plant
Water Wash Process
Plant
Propane Storage and Blending PlantPropane Storage and Blending Plant
Biomethane to Grid PlantBiomethane to Grid Plant
Gas Analysis equipmentGas Analysis equipment
Filters for Siloxanes and H2S
Filters for Siloxanes and H2S
24
Didcot Project (Apr – Oct 2010) First Biomethane to grid plant in UK
DIGESTERS
GAS STORAGE
CLEAN UP PLANT
CUSTODY TRANSFER STN
UPGRADE PLANT -
PROPANE
TELEMETRY
25
Biogas Clean-up and Upgrading Equipment• Established Water scrubbing
technology• Removes CO2
• Removes H2S• Removes most siloxanes• Dries the biogas
• Additional filtration to ensure no siloxanes enter network
• H2S captured when it is removed from the water and not vented to atmosphere
26
Propane Enrichment
Propane Storage Tanks
Mixing Vessel
Propane Tanks refilled by Tanker every 3 to 4 weeks
Industry Review Group (GDNs, shippers, REA, Ofgem)
Sept-Oct 2010 agreed that adding propane to meet FWACV was necessary to ensure customers were not being disadvantaged by bio-methane injection
Biomethane Injection – Equipment and Regulations
Gas Transporter must ensure :- Regulation Requirement
Gas Quality Measurement GS(M)R Reg 8 Schedule 3 pt 1
Pressure Control of gas delivery into network GS(M)R & PSSR
Stenching Agent injection GS(M)R Reg 8 Schedule 3 pt 1
Volume Flow Measurement GS(M)R & Gas (Calculation of Thermal to enable calculation of gas quality Energy ) Regs
Gas Flow weighted average CV to OFGEM Direction under the 1996 Gas measure/record the energy of the gas (Calculation of Thermal Energy ) Regs
27
COMPLIANCE -Telemetry to monitor & record to Gas Control Centre
SHUTDOWN - Emergency Shutdown System (ESD)
• Key considerations that the project had to recognise -
• Charge to Consumers CV • Consumer Safety H2S & Wobbe Number • Network Integrity Water dewpoint & Oxygen
(internal corrosion)
• Existing Constraints
• Currently only one OFGEM approved device (Danalyser)• Siemens Microbox (FWACV hardware – supervisory software)• Total sulphur & H2S measurement (MAXUM)• Hydrocarbon dewpoint measurement • High Pressure Metering Information System (HPMIS)
Gas Network Considerations
29
HSE - GAS SAFETY – GS(M)R Fast Acting and Shut Off ( ESD)
Emergency Shut Down System Fast acting gas qualitysampling equipment
(H2O, H2S, S, CV, H2, O2 , etc)
3131
GAS SAFETY - Pressure Control & Metering
Accurate flow measurement
Pressure control – entry into 2 bar MP
32
OFGEM - Thermal Energy
SGN as the gas transporter were Directed by OFGEM to use an approved type Danalyser ( Gas chromatograph) that enables highly accurate sampling.
Accurate to around 0.14 MJ/M3 (less than 0.4% error)
Accepted that this is an expensive solution but there was no alternative for Didcot 2010
700 Series Danalyser
33Biogas clean-up and upgrading plant
Propane Storage
Digesters
Gas bag
Energy and quality Measurement, odorant addition, telemetry to Gas Control Centre
Propane mixing and injection Thames
Water control room
H2S and Siloxane filters
Completed Project (1)
38
Successes – All in it together!!
• Bio-methane quality of clean up plant established
• Propane requirement less than anticipated
Co-operation of Regulatory Bodies
HSE - Positive support for 2% Oxygen exemption
OFGEM - Timely Letter of Direction - Expedited verification of Danalyser and other directed equipment
Single Party Delivery of Project
Modular Construction • Excellent H&S record on congested site• Significantly reduced construction period
Output of the Technology
• SGN lead project delivery as principle contractor supported by our technical partner CNG Services Ltd
Learning
• Location of Anaerobic Digestion - near gas grid• Capacity of the gas grid must be able to support facility• Operating pressure (IP or MP best)• Clean up technology and AD must be designed together to meet
gas and energy quality requirements – retrofit process performance difficulties
• Income balance between CHP (Fit’s) and grid injection (RHI) is attractive
• Network Entry Agreements – Must be appropriate• Measurement• Telemetry• Nominations – link to gas sales• Communication
• Design and Build Agreements – need industry standard• Maintenance • Ownership and Responsibility for Plant• Plant Redundancy / Availability
39
Technical Challenges for Biomethane Injection
Technical barriers to Biomethane growth in UK
• Oxygen content / specification - GS(M)R – is it appropriate at 0.2%?
• CV enrichment with propane – not seen as green
• Cost - Gas Quality / Thermal Energy equipment• Regulations and systems are designed for large volumes of gas.• GSMR data duplication - clean-up and network entry plant.• Increase diversity of suppliers for network entry systems
• Network Entry Agreement • Historically designed for large facilities, need to be reflective of smaller biomethane
sources.
• Network Capacity Constraints• Capacity re-engineering and suitable models to facilitate biomethane entry
• Gas Transporters Licence exemption• Class Exemption from section 6A of Gas Act for Biomethane
41
Future Challenges for Biomethane Injection
Socio-economic barriers to Biomethane growth in UK
Clarity on ownership and funding for network entry equipment.
Incentives for GDN’s within next Price Control Period?
RHI degression from 2012 ?
Feedstock suitability – varied feedstock contaminants / landfill gas 2012 ?
Project Funding – (Energy from Waste AD facilities)
42
43
Conclusions
Bio-methane could supply up to 50 % of domestic gas load here in the UK.
Bio-methane into the Gas Grid is far more efficient than into the electricity grid providing a sustainable gas supply
2020 UK Government target - generate 15% of national energy requirement from renewable sources
The Gas networks currently have the infrastructure to deliver this energy supply to the majority of our consumers .
Bio-methane injection is the best way to supply this low Carbon energy into millions of homes and businesses