64

Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March
Page 2: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Baart sarkar

kond`Iya ivaVut p`aiQakrNa

piScama xao~Iya ivaVut saimait

mauMba[-

Government of India

Central Electricity Authority

Western Regional Power Committee Mumbai

p xao iva sa kI

idnaaMk 13.11.2019 kao p xao iva sa Mumbai maoM

Aayaaoijat 82vaI baOzk kI kaya-saucaI

Agenda items of 82nd Meeting of CCM to be held on 13.11.2019

at WRPC Mumbai

Page 3: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Agenda item of 82nd CCM meeting

(13.11.2019) at WRPC Mumbai

A Confirmation

Confirmation of the Minutes of 81st Meeting of CCM

Minutes of the 81st meeting of Commercial sub Committee held on

14.05.2019 at Mumbai were circulated vide WRPC letter no.:

WRPC/Comml.-I/CCM/Minutes/2019/6467 dated 06.06.2019,

The following comments were received from utilities:

Comment:

MSEDCL vide letter no. CE/PP/80th CCM MoM/17066 dated

19.06.2019 (copy enclosed at Annex-1) informed the following:

In the MoM of 81st CCM Meeting in Comment-III under Para (G)

following statement is mentioned:

“…. MSEDCL representative informed that no such violation done by

WRLDC, however RLDC should inform…..”

MSEDCL requested to add following corrigendum in above para of

MOM

“…. MSEDCL representative informed that presently no such violation

of RSD procedure being done. However, RLDC should inform …. ”.

Committee may like to discuss the above comment and approve the same.

The Committee may like to confirm the Minutes of 81st CCM

B CCM agenda items

Item Issuance of provisional REA data issued by WRPC every month- correction

Page 4: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

No.1 thereof

CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of

January to March -17 held on 27th of April 2017, the URS data in respect of CSEB showing in implemented schedule in WRLDC website

was not matching with REA data provided by WRPC for the month of Dec-2016 to Mar-2017.

(ii) Further in the 74th CCM (item 14 in MoM) pertaining to CSEB Schedule in Kahalgaon super thermal power stations (ER) (K-II) for the period of Aug-2016 to Oct-2016 and issues in past REAs of Aug & Oct-

15, Jan-16, May-16 and Sept-17 were discussed and WRLDC agreed to send the revised data to WRPC.

CSPTCL requested to resolve this long pending issue in REA.

Committee may like to discuss.

Item No.2

Issuance of provisional REA data pertaining to transaction between

Kishanganga Hydel Plant to CSEB_Beneficiary

CSPTCL vide letter dated 12.07.19 informed that-

Scheduling of Kishanganga Hydel Plant was started from 10/06/2018. Difference in data of transaction between Kishanganga Hydel Plant and

CSEB Beneficiary was observed in REA issued by WRPC for the month of June-18, July-18, Sept-18 and Nov-18 for which letters were sent to WRLDC.

For the above issue, CSPTCL engineer visited WRLDC, Mumbai on 26th Dec. 2018. As per discussion there, WRLDC required the day wise mismatch in the schedule of KISHANGANGA Hydel Plant to CSEB

Beneficiary for the month of June, July, September and November 2018, to accurately find monthly mismatch which was sent to WRLDC

vide letter dt.28/12/2018. The issue of mismatch has not been resolved till date. Further the schedule of Kishanganga Hydel Plant to CSEB Beneficiary

may also be included in the REA issued by WRPC.

Committee may like to discuss.

Item No.3

Issuance of provisional REA data pertaining to transaction between Mouda,

Solapur and NSPCL to CSEB_Beneficiary

CSPTCL vide letter dated 12.07.19 informed that- Difference in data of transaction between Mouda, Solapur and NSPCL to

CSEB_ Beneficiary was observed in REA issued by WRPC for the month

Page 5: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

of May-2019 and transaction between Mouda and NSPCL to CSEB_ Beneficiary for month of June-2019 also it was observed that the URS

data showing in REA of month MAY & JUNE-19 is not matching with the URS showing in WRLDC Website for which letters were sent to WRLDC & WRPC.

CSPTCL requested to revise the REAs.

Committee may like to discuss.

Item no 4.1

Change in RSD procedure for ISGS to get schedule for state having less

share

CSPTCL vide letter dated 23.10.19 informed that:

The share of CG state in ISGS station of WR is in the range of 6 to 12% only. In case of RSD of any of the NTPC generating station, the

state with smaller percentage of share are always on losing side because of the surrender/Re-allocation of share by states having larger share.

During the month of July-19 August-19 and September-19, CG state could not get it share from Mouda-II Solapur & Gadarwara station despite requirement due to surrender by states having larger share and

has to arrange power from other sources at a short notice and high cost.

To safeguard the interest of all small states, there should be an addition to RSD condition that is “if a state is helping any thermal station to be

on bar by scheduling over and above its share in that station for meeting technical minimum requirement, then it should continue to get the additional quantum of schedule at least for next 72 hours of

scheduling and the original beneficiary shall have right for re-allocation to the balance quantum only.

This will help in not only keeping the ISGS on bar but will also help states with smaller share in meeting their requirement through ISGS

stations.

Committee may like to discuss.

Item

No.4.2 Working Arrangement for commercial settlement of transfer of URS from

one constituent to another constituent to meet the technical minimum

requirement of ISGS

Page 6: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

SLDC Gujrat vide letter dated 24.10.20 (copy enclosed at Annex 4.1) informed that:

SLDC Gujarat has already raised the concerns in the matter. In many forums/meetings, it is decided to ensure injection schedule of the

generating stations at least up to the technical minimum level. Hence, ideally every constituent has to ensure its minimum requisition

according to its share in the generating station X technical minimum of the generating station (of „on bar‟ machines). However, in case of requirement of other beneficiaries in the same generating station for

more than its technical minimum share, remaining beneficiary(ies) can requisite lower than its technical minimum share accordingly.

Further, due to any of the reasons, if it is not possible for any constituent to requisite up to the technical minimum and other

beneficiary (ies) is able to take/accommodate that portion in their drawl schedule to support the grid and to ensure technical minimum requirement of the generator then such quantum of URS is to be

considered in a different way than the regular/normal (on need basis) transfer of URS.

As per the existing agreed mechanism, constitutes availing URS should pay fixed and variable cost of that quantum of URS. However, in case of

transfer of URS to support the technical minimum requirement of the particular generator, it is proposed that constitutes (availing URS to support the technical minimum) should only pay variable charges

for the support quantum. The liability of fixed charges will remain with original beneficiary (ies). Transfer of URS with

variable cost only will help to accommodate ISGS in the State merit order dispatch mechanism. This is a WIN-WIN situation for all the entities.

The similar kind of mechanism can also be introduced for transfer of

URS above the technical minimum of the ISGS.

The abstract of record notes of the 34th WRPC meeting in ITEM No 35 is reproduced hereunder:

Quote

After the discussion, TCC agreed on the following: · All members agreed to the proposal of MP wherein the URS availing beneficiary shall pay 50% capacity charges and

remaining 50% shall be borne by MP themselves. · The proposed above mechanism is valid up to 31.03.2018.

· WRPC shall provide the URS quantum availed in its REA, whereas the adjustments made for the capacity charges shall be done by NTPC.

Page 7: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

WRPC discussion:

General Manager, GUVNL stated that GUVNL through letter has conveyed to WRPC that URS share of GUVNL can be availed by any

other state utility without paying capacity charges while GUVNL reserves right to recall the power after 4th time block. In case, the other

state beneficiary desires GUVNL‟s URS on committed basis for a day, the beneficiary shall pay 50% of capacity charges to GUVNL. The energy charges and other cost will be settled with NTPC as is being presently

done

Unquote It will help in better utilization of cheaper resources (it is observed that

some States are facing problem of coal shortage and still don‟t be able to schedule URS from other cheaper ISGS due to liability of both variable and fixed cost), higher PLF of ISGS and most of the time ISGS will get

the schedule more than technical minimum. Frequent start-stop of the ISGS can also be avoided

Committee may like to discuss.

Item

No 4.3 Scheduling of beneficiaries who do not get power due to technical difficulties

DD vide letter dated 06.11.19 (copy enclosed at Annex 4.3) informed the following –

U.T. of Daman & Diu has been allocated power from various generating stations of NTPC and NPC both during peak and off peak hours. UT of

DD do not have their own generating stations and as such our entire load requirement by and large are mostly met from the allocations of power made from central sector generating stations.

NTPC are regularly submit 15 min time block Declared Capacity of their stations to WRLDC and based on the DC declared and scheduled power

sought by various beneficiaries of these stations commensurate to their entitlements, WRLDC issues final schedules to these NTPC Stations.

U.T. of Daman & Diu, based on the DC declared and the entitlement of allocated power, submit requirement for scheduling of power from

Gadarwara, Solapur and Mouda Stations of NT PC. However, nil generation schedule is issued to the generating units of these station as

other beneficiaries of WR has not asked to schedule power from these unit and the total schedule is below technical minimum.

Page 8: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

In the above process U.T. of DD is in need of power and right to schedule as per allocation, but is deprived. So on one hand no power is

schedule despite DC declared by NTPC and on the other hand DD end up in paying capacity charges.

DD requested to look into the matter and examine the possibility of scheduling the power from other running units of NTPC in the above

prevailing situations.

Item No.5

Payment of outstanding charges for wheeling of power through OPTCL

system via Budhipadar and other applicable charges.

MSEDCL vide letter no. MSEDCL/CE/PP/82nd CCM/agenda points/020663 dated 24.07.19 informed the following:

MSEDCL vide email dated 24/10/2018 has informed WRPC that MSEDCL has to recover provisional amount of Rs. 1,25,19,751/- for the

wheeling charges as paid to OPTCL for the period July 2011 to March 2012. Though, M/s OPTCL has claimed the same through PoC mechanism, it used to raise invoices @17.5 Ps per unit to MSEDCL.

MSEDCL has paid the subjected bills as per the prevailing rate of @10 Ps per unit for April 2011 to March 2012.

Further, ERPC has to prepare STOA credit receivable to Maharashtra pertaining to period FY 2004 to FY 2011 and inform the same. Gujarat and MP have also raised the issue of outstanding charges as

receivable to them from M/s OPTCL in CCM forum. Accordingly, this issue was discussed in 78th and 79th Commercial committee meetings. During 79th CCM, Committee had decided to convene the meeting

between beneficiaries WRPC, SRPC, OPTCL and ERPC at the earliest. But no such meeting has been held so far. The representative of M/s

OPTCL/ ERPC may be requested to attend the meeting to resolve the issue else separate meeting between beneficiaries WRPC, SRPC, OPTCL and ERPC

may be arranged as decided in 79th CCM meeting.

Committee may like to discuss.

Item No.6

NTPC (WR-I) AGENDA ITEM

NTPC vide email dated 22.10.2019 informed the following agenda. Background:

Agenda items a, b and c were discussed the 523rd and 524th OCC and MS, WRPC informed that scheduling of generators is governed by CERC regulations and Merit order dispatch by DISCOMS. He opined that

Page 9: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

these issue could be discussed with DISCOMS in CCM meeting of WRPC.

a. Ensuring Technical minimum schedule for all the coal-based stations of the WR region.

b. Frequent start stops of Gas turbine along with steam turbine for Jhanor and Kawas stations.

c. Ensuring liquid fuel schedule (minimum 30MW) for minimum 2 blocks once in 1 month for availability of gas turbine on secondary fuel

(Naphtha fuel)for Kawas Station.

d. Migration of secondary fuel from Naphtha to HSD for Kawas gas power

project. As HSD is safer fuel to handle.

e. RRAS payment is not being done for open cycle generation for Kawas and Jhanor stations.

f. Ensuring 55% loading (Scheduling) on Steam turbine for combined cycle power plant, presentation already made in 518th OCCM in the

month of April 2019

Committee may like to discuss.

Item

No.7

ASSETS COMMISSIONED BUT COULD NOT BE DECLARED UNDER

COMMERCIAL OPERATION(PGCIL )

PGCIL vide email dated 29.07.2019 informed that: POWERGRID Works Associated with System Strengthening Scheme For IPP’s in Chhattisgarh and other Generation projects in Western Region.

As per the Investment Schedule 2 No 765kV GIS Line bays at 765/400kV Pune(GIS)(POWERGRID) (For LILO of one circuit of

Aurangabad(POWERGRID)-Padghe(POWERGRID) 765kV D/C Line) were to be commissioned by March‟19. The elements were commissioned and successfully charged by Jan‟19. DOCO for the said

asset will be declared after the approval of CERC by pleading under Regulation 4(3)(ii) of Tariff Regulations.

Western Region Strengthening Scheme-XVII

As per Investment approval 1 No 240MVAR Switchable Line Reactor

along with 850ohm NGR and associated bays were to be commissioned at Pune(GIS). This asset was proposed in the 39th SCM meeting of

Western Region for providing the reactive compensation for LILO of one circuit of Aurangabad (POWERGRID)-Padghe(POWERGRID) 765kV D/C Line being implemented through TBCB route. The asset was charged

successfully as a Bus Reactor in Jan‟19. DOCO for the said asset will be declared after the approval of CERC by pleading under Regulation

Page 10: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

4(3)(ii) of Tariff Regulations.

Committee may like to note.

Item No.7.1

The list of assets to be notified by PGCIL

Sl. No.

Asset Project DOCO(dd.mm.yy

yy)

1

URTDSM System (Control Centre

Equipment (PDC), PMUs & associated

Equipment integrated & Commissioned at

SLDC Gujarat).

Phase-I Unified Real Time Dynamic State

Measurement (URTDSM) 31.05.2019

URTDSM System (Control Centre

Equipment (PDC), PMUs & associated

Equipment integrated & Commissioned at

SLDC Madhya Pradesh).

URTDSM System (PMUs & associated

Equipment integrated & Commissioned for

WRLDC, Mumbai)

2

A.) Central Sector Establishment of Fibre Optic Communication

System in Western Region under Master

Communication Plan

21.06.2019 220 kV Kawas - Vav

220 kV Kawas - Navsari

3

A.) Central Sector Establishment of Fibre Optic Communication

System in Western Region under Master

Communication (Additional Requirement)

21.06.2019

765 kV Bina - Jabalpur

4

A.) Central Sector

Establishment of Fibre Optic Communication

System Plan in Western Region under Master

Communication (Additional Requirement)

29.06.2019

220 kV Vapi-Kharadpada

66 kV Kharadpada - Amli

B.) State Sector

220kV Indore – Indore (SZ)

220kV Gwalior - Malanpur

220kV Neemuch - Gandhisagar

220kV Bina - Shivpuri

132kV Waidhan - Singrauli

5

2 No. 765kV line bays along with 2 No.

240MVAR 765kV Switchable Line Reactors

at Bilaspur Pooling Station for Bilaspur

Pooling Station (POWERGRID)-

Rajnandgaon(TBCB) 765kV D/C Line”.

POWERGRID Works Associated with Additional System Strengthening for SIPAT STPS(DPR-5)

23.03.2019

Page 11: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

6

2 No. 765kV line bays along with

2x240MVAR switchable Line Reactors at

765/400kV Raipur Pooling Station of

POWERGRID (for 765kV D/C

Jharsuguda(Sundargarh)-Raipur Pool {line

under TBCB})

POWERGRID Works Associated with TBCB Lines under Common Transmission System for Phase-II Generation Projects in Odisha(DPR-2)

07.04.2019

7

1) URTDSM System [Control Centre

Equipment (PDC), PMU’s & associated

Equipment integrated & Commissioned at

SLDC Maharashtra] 2)

URTDSM System[Control Centre Equipment

(PDC) , PMU’s & associated Equipment

integrated & Commissioned at SLDC

Chhattisgarh]

3) URTDSM System[Control Centre

Equipment (PDC), PMU’s & associated

Equipment integrated & Commissioned at

WRLDC, Mumbai)

Phase-I- Unified Real Time Dynamic State

Measurement (URTDSM) 31.05.2019

8

Vapi Kudus(upto LILO portion of Kala from

Vapi)

Establishment of Fiber Optic Communication

System in Western Region under Master

Communication Plan

26.05.2019

Committee may like to note.

Item No.8

Computation and Payment of Capacity charges for Thermal generating stations in FY 2020-21

CERC (Terms and Conditions of Tariff) Regulations,2019 contains

the following provisions pertaining to computation and payment of Capacity Charge for Thermal Generating Stations (copy of the relevant pages are enclosed at Annex 8):

" The capacity charge shall be recovered under two segments of

the year, i.e. High Demand Season (period of three months) and Low Demand Season (period of remaining nine months), and within each season in two parts viz., Capacity Charge for Peak

Hours of the month and Capacity Charge for Off Peak Hours of the month….”

"The number of hours of "Peak" and "Off-Peak "periods during a day shall be four and twenty respectively. The hours of Peak and Off-

Peak periods during a day shall be declared by the concerned RLDC at least a week in advance. The High Demand Season (period of three months, consecutive or otherwise) and Low Demand Season

(period of remaining nine months, consecutive or otherwise) in a region shall be declared by the concerned RLDC, at least six

Page 12: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

months In advance. Provided that RLDC, after duly considering the comments of the

concerned stakeholders, shall declare peak Hours and High Demand Season in such a way as to coincide with the majority of the Peak Hours and High Demand Season of the region to the

maximum extent possible…"

The capacity charge payable to a generating station for a calendar month shall be calculated in accordance with the formula as per above regulation.

Committee may like to note.

Item No.9

Installation of new Interface Energy meters, AMR system and meter data processing system

Background:

As per the minutes of 36th WRPC, POWERGRID has to replace existing meters by New Interface Energy Meters, AMR system and meter data processing system having specifications as approved in 34th WRPC

meeting and recover the cost from the entities on one time basis. POWERGRID had invited bids for the work of “Implementation of 5-

minute metering with New Interface Energy Meter (IEM), Automated Meter Reading (AMR) System and Meter Data Processing (MDP) System

in POWERGRID Western Region” vide NIT dtd. 27.11.2018. Some vendors had sought clarifications in the pre-bid meeting.

37th WRPC Meeting (18th December, 2018), A group, with members from WRLDC, GETCO, MPPTCL, MSETCL,

POWERGRID, Chhattisgarh and Adani Power was formed to address the pre-bid queries raised by the vendors. The group met on 24.12.18 and deliberated the points raised by the vendor. The minutes of the meeting,

after approval of TCC Chairman forwarded to POWERGRID by WRPC. Further POWERGRID wrote to WRPC about vendors seeking some

modification in the payment terms/penalty clause. The same was forwarded by WRPC to all subcommittee members. The consolidated

response was emailed by WRPC to POWERGRID. Thereafter POWERGRID further sought the opinion of WRPC regarding

opening of bids in the event of poor participation. Opinion of WRPC members was forwarded to POWERGID by MS, WRPC on 12.04.2019.

38th WRPC Meeting (27/28th June, 2019):

Page 13: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

PGCIL informed the following

Only one supplier quoted and bid was opened on 24.06.2019.

Supplier quoted three times the estimated cost.

Evaluation committee will evaluate the bid and it will take 21 days to evaluate the price bid.

The report of the evaluation committee will be sent to WRPC members.

Within 21 days or before, PGCIL would give the update. Further follow-up.

PGCIL vide letter dated 16.08.2019 informed the following: Price Bid of single bidder M/s Secure opened on 24.06.2019. The price

quoted is abnormally higher side than our estimate. On detailed Analysis we have found following reasons- 1)Being first of its kind, there was no bench marking/historical data for

cost estimate 2)Implicit BOQ i.e. requirement of various hardware and software for control center and FO cables for system integration at SS level

After internal deliberations and consultation with other utilities, the

BOQ is being finalized. With the finalization of Bill of quantities and market survey, cost estimate is being worked out based on TS issued along-with various amendment by WRPC. After approval of revised Cost

estimate retendering process shall be done on top priority. WRLDC vide letter no. WRLDC/MO/1551/2019 dated 30.10.19

informed the following – a. WRLDC had forwarded the estimated future SEM requirement

to WR-1 and WR-2 vide email dtd. 26.11.18 and 24.09.19. b. It is understood that MSETCL has placed award for new interface

meters, AMR and MDP system. The technical specifications were

based on the approved WRPC specifications. It is understood that several vendors participated. POWERGRID may like to benefit

from the MSETCL experience.

POWERGRID may update the present status.

Committee may like to discuss.

Item No 10

Non-availability of Delay Payment Charges towards Payment of DSM Bill for 31.12.2018

MSLDC vide letter dated 27.08.2019 informed that: MSLDC had received DSM bill wherein bill period mentioned was

31.12.2018 to 06.01.2019. It was evident from the covering letter that the payment mentioned was for the week 31.12.2018 to 06.01.2019

amounting to Rs 277491/- & it was duly signed. This Office has paid Rs 277491/- vide Cheque No. 097/42 dtd 07.02.2019 within the timelines

Page 14: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

of DSM. Further, MSLDC was in receipt of revised bill with period mentioned

01.01.2019 to 20.01.2019 amounting to Rs 30606903/- . However, considering the weekly pattern of bills issued by WRPC, this office had inadvertently deducted the charges i.e. Rs 277491/-. For 31.12.2018

from the said bill. The payment was done by this office for Rs 30329412/- vide Cheque No. 097755 dtd 27.02.2019, i.e. with

deduction of charges for 31.12.2018. After scrutinizing, it was found that the amount Rs 277491/- was only for 31.12.2018. Thus, the said amount was immediately paid through

Cheque No. 109829 dtd 15.07.2019. MSLDC has never defaulted payment against the timelines of DSM bills

and therefore, DPC may not be charged for the respective period ,i.e. 31.12.2018 as it is inadvertent error on both sides. In view of the above, DPC should not be levied on the amount Rs 277491/-.

Committee may like to discuss.

Item No 11

Submission of statement of Regulatory account before RPC Commercial Committee

As per Para 15 complementary commercial mechanism (Annexure-I) of IEGC (Amendment-1) which is reproduced here:

Quote “The RLDC shall place the complete statement of regional UI account,

the Regional Reactive energy pool account and Congestion Charge account before the RPC‟s commercial committee meeting on a quarterly basis for audit.”

Unquote

WRLDC to submit all related data of above regulatory accounts (DSM, REC, RRAS etc.) to CCM on quarterly basis.

Committee may like to discuss.

Item No 12

Transmission Charges payable by RGPPL to MSETCL

Ministry of Power has allocated 540MW to Indian Railways (out of Maharashtra Share) in Ratnagiri Gas and Power Private Limited for five

years since 01.04.2017. Scheduling of this 540 MW allocation (210 MW-Central Railways, 90 MW -Western Railways, 85 MW-West Central Railways, 70 MW South Eastern Railways, 50 MW North Central

Railways and 35 MW South Western Railways) is being done by WRLDC

Page 15: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

in line with WRPC Orders issued in this regard. Indian Railways, 'based on the PPA signed with RGPPL against

allocation as above, entered into LTOA with MSETCL for use of their intervening transmission system to connect to nearest CTU system to wheel their share to destination states. The power from RGPPL is

evacuated using 400kV STU lines in Maharashtra namely Dabhol- Nagothane and Dabhol- Koyna lines which were constructed more than

20 years back. Nearest CTU connectivity is at Padghe. RGPPL share to DD & DNH is also wheeled using these lines as per study conducted by WRPC in FY 2010-11. Transmission charges applicable to DD & DNH

were approved in 15th meeting of WRPC/TCC using contract path method.

As per PPA transmission charges paid by Railways are recovered from RGPPL bills as the PPA provides for composite rate of 5.50/Kwh upto Railway Traction Sub-Station. It is seen that transmission charges billed

by MSETCL to Indian Railways are of the order of Rs 7.20 Crore per month for 330 MW flowing into CTU system. which is about Rs 2.20 Lakh/MW/month.

The charges levied to DD & DNH for using the above corridor are about 0.73 Lakh/MM/Month. Applicable transmission charges for DD &DNH

were worked using contract path method in consultation with MSETCL in FY 2010-11 under Item No. 3.3 of minutes of 56th CCM and Item 3.3 & 3.4 under 15th TCC/WRPC Meeting.

RGPPL requested that transmission charges applicable to 330 MW share of Indian Railways from RGPPL for using transmission corridor of

Dabhol-Nagothane-Padhge to connect to CTU network be reviewed by MSETCL based on contract path method as done in case of DD & DNH.

Committee may like to discuss.

Item No 13

Performance Guarantee test of NTPC Generators

Background: In 523 OCC NTPC informed that Performance Guarantee Tests(PG) are planned to be conducted in NTPC Solapur and Mouda and requested

beneficiaries to provide schedule so as the PG test can be carried out successfully. MS WRPC opined that PG test is a once in a lifetime activity of generator

and hence suggested that States provide the requested schedule to NTPC for successful completion of PG test of its units.

Committee may like to discuss.

Page 16: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Item No 14

Allocation of open cycle share of Kawas to all beneficiaries

SLDC Gujarat vide letter dated 05.11.19 (copy enclosed at Annex 14) informed the following:

In recent past, on pursuance of Gujarat requirement, NTPC - Kawas has arranged APM gas fuel for economical operation.

During initial open cycle operation of about six hours (must to bring unit in combined cycle), Gujarat is only requisite the requirement of

around 90 MW which is well above the allocation at 4.27 Rs variable cost.

All beneficiaries are punching their requisition when machine comes in combined cycle leading to loss of share (Gujarat share is 47 MW in one

machine in combine cycle) to Gujarat who has extended support of open cycle operation (90 MW of about six hours at high variable cost) for bringing gas turbine on bar.

Gujarat requested to all beneficiaries to contribute its share in open cycle operation mode if they desire to avail their share in combined

cycle.

Committee may like to discuss.

WRLDC Agenda Items

WRLDC vide letter no. WRLDC/MO/1551/2019 dated 30.10.19 (copy

enclosed at Annex-15) submitted the following Agenda Items -

Item No 15

Availability of sufficient no. of spare SEM/DCD

WRLDC informed the following –

A. It is being observed that on many occasions meter

replacement/installation is getting delayed due to non-availability

of meter spares and auxiliaries (DCD, cable). Few cases are listed

below:

Page 17: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

S No.

Location Element Issue Remarks

1 Raigarh

(CSPTCL)

220kV Raigarh

(CSPTCL)-Raigarh

(PG) line 1& 2

Meter not installed.

Pending since

24.09.18 (letter

issuing date)

2 Raigarh (PG)

220kV Raigarh

(CSPTCL)-Raigarh

(PG) line 1& 2

Meter not installed.

Pending since

24.09.18 (letter

issuing date)

3 Dhariwal 400 kV Dhariwal-

Parli line-4

Check

Meter was

showing blank

data

Meter was replaced

on

24.10.19, 1 month

after the date of

intimation

(24.09.19).

4 Raipur

Energen

(erstwhile

GMR

Chhattisga

rh)

400KV Raipur

Energen- Durg

line-2

Main

Meter was

showing blank

data

Meter was replaced on

05.10.19, 17 days

after the date of

intimation

(18.09.19).

5 Dhule 400 kV Khandwa line-1

& 2

Delayed data

submission.

Data not

downloaded

due to DCD

failure in one

week

(24.06.19 to

30.06.19)

Spare DCD

not available at

Dhule/

Aurangabad(PG).

B. The procurement and installation of new IEM, AMR and MDP in

WR has been delayed. In the 81st CCM (agenda item no. 6) held on 14.05.19 it was agreed that adequate spares shall be

maintained. POWERGRID to furnish the details of the spare SEM/DCD available in WR-1 and WR-2 along with their make.

PGCIL may update.

Committee may like to discuss.

Item No

Metering issues at Kawas NTPC

Page 18: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

16

WRLDC vide letter no. WRLDC/MO/1551/2019 dated 30.10.19 informed the following –

A. Long pending CVT replacement in 220 kV Kawas-Icchapur line-1 at Kawas end

In the CT and CVT testing carried out by NTPC, it was found that

measured ratio of R and B phase CVT is lower (3-

5%) than expected level. Therefore, the main meter of 220 kV Kawas-

Icchapur line-1 at Kawas end is given Bus PT input while check

meter was given faulty line CVT input. The main meter is being used

for computing NTPC Kawas injection.

In the 80th CCM, it was discussed that line CVT at Icchapur end in

220 kV Kawas-Icchapur line-1 shall be replaced as it was confirmed

by the tests that R & B phase CVT‟s are showing irregular results.

Further, after replacement of faulty CVT with a healthy CVT, the main

meter shall be provided the line CVT input and its readings shall be

validated by WRLDC with standby meter readings.

In the 81st CCM, GETCO informed that the work will be done in the

month of May 2019, however the work is yet to be finished.

GETCO may apprise the committee the cause of the delay and

tentative date by which the work shall be completed. B. Replacement of one check and two standby meters at NTPC

Kawas

The following meters installed at NTPC Kawas have a time drift of about 1 hour as seen in data validation at WRLDC.

• HV side of GT-1A (NP-5529-A, Elster make)

• HV side of GT-1B (NP-5445-A, Elster make)

• 220 kV Kawas-Icchapur line-2 (check meter, NP-5457-A, Elster make)

The time drift has been confirmed from the unit outages timings in the outage report.

However, time display in the meter does not reflect the time drift. Thus it may be inferred that the meter is faulty.

An email was sent to NTPC Kawas and PGCIL Navsari s/s on

01.10.2019 regarding checking and correction of time drift. Further,

NTPC informed vide email dtd. 18.10.19 that they have done time

drift correction on 14.10.19, however the issue was not resolved.

WRLDC informed the same to NTPC Kawas and POWERGRID vide

email dtd. 25.10.19.

Page 19: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Thus, these three meters (NP-5529-A, NP-5445-A and NP-5457-A)

need to be replaced with meters of different make.

Committee may like to discuss.

Item No 17

Relocation of Check meters for ISGS evacuated through dedicated lines

Vide letter ref. no. WRLDC/SO/Metering/774-90 dtd. 03.07.2018,

S.

N

o

Name of Generating Statio

n

Evacuation Path

Interface

point

Remote end Recommendatio

n

Main Standby Check

1

KWPCL

400kV

KWPCL-

Kotra(PS)

line-1

Kotra (PS)

KWPCL

KWPCL

Check meter

to be shifted

from KWPCL

to Kotra (PS)

2

KWPCL

400kV

KWPCL-

Kotra(PS)

line-2

Kotra (PS)

KWPCL

KWPCL

Check meter

to be shifted

from KWPCL

to Kotra (PS)

3

Raipur

Energen

(GMR

Chhattis

garh)

400kV Raipur

Energen-

Durg(PS) line-1

Durg(PS)

Raipur

Energen

Raipur

Energen

Check

meter

removed

from Raipur

Energen,

however not

installed at

Durg (PS)

4

Raipur

Energen

(GMR

Chhattis

garh)

400kV Raipur

Energen-

Durg(PS) line-1

Durg(PS)

Raipur

Energen

Raipur

Energen

WRLDC/SO-1/Metering/2018/ dtd. 11.01.2019 and WRLDC/SO-

1/Metering/2019/981 dtd. 06.08.2019 POWERGRID was advised to

coordinate relocation of check meters for generating stations (IPPs)

and installation of 4 new check meter for JPL Tamnar. The matter

was discussed in 80th CCM held on 21st February 2019 wherein it

was agreed to complete the work within fifteen days. The matter was

further discussed in 81st CCM on 14.05.19.

Present status :

Relocation of check meters: Out of 24 check meters, 20 check meters have been relocated.

Work related with 4 check meters for KWPCL and

Page 20: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Raigarh Energen (erstwhile GMR Chattisgarh) is still pending. Details are are as above

KWPCL, Raipur Energen & POWERGRID may

apprise the committee about the progress.

Committee may like to discuss.

Item No. 18

Installation of New meters at Raigarh

Vide WRLDC letter dtd. 24.09.2018 POWERGRID was advised to

install SEMs on 220kV Raigarh (CSPTCL)- Raigarh (PG) line 1& 2 on

both ends. The matter was again followed up in letter WRLDC dtd.

11.01.19 and 06.08.2019 and also in supplementary information for

regional energy accounting from week-18 (29.07.19-04.08.19) onwards.

http://wrldc.org/content/207_1_SEMDiscrepancies.aspx

In the absence of meters in these lines, Chhattisgarh drawl is being

computed by using meters installed in the HV side of the ICT and

220 kV Raigarh (PG)-Budhupadar line.

After, installation of meters in 220kV Raigarh (CSPTCL)-Raigarh

(PG) line 1& 2, the ISTS drawal interface point of Chhattisgarh at Raigarh (PG) shall be shifted to 220 kV Bus.

PGCIL / CSPTCL may provide the status of installation.

Committee may like to discuss.

Item

Page 21: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

No. 19

Frequent failure/issues observed in Elster make SEMs in WR

Frequent failure of Elster meters and unsatisfactory support services

from Elster were reported by WR utilities as well as WRLDC vide letter

dated 09.11.2018. Reminders were issued vide letter dated

11.01.2019,

29.03.2019 and 06.08.2019. Matter was also discussed in 80th CCM & 81st CCM.

80th CCM:. POWERGRID agreed to take appropriate action with

ELSTER as per terms and conditions of the contract for supply of

meter and support/service by ELSTER.

81st CCM: PGCIL representative informed that they have decided

not to consider M/s. Elster in future bidding, at present they are

having 26 spare meters out of warranty. WRLDC representative

suggested that the redundant meter (list annexed in the minutes) shall

be used in place of faulty meter on case to case basis. Vide letter dtd. 11.01.19, WRLDC requested POWERGRID for

replacement of defective SEMs of Elster make. Out of 10 requested replacements, 7 are completed while 3 are pending. The pending status is as below:

S

r

.

N

o

.

SEM Sr.

No.

LOCATION Issue Remarks

1

NP-8690-

A

400kV side of ICT-1

at

Tamnar (PS)

Blank data in

NPC file since

28.06.18

Stan

dby

mete

rs

To be

replaced

with new

meters of

different

make

2

NP-5554-A

400kV side of ICT-II

at

Rewa (PG)

Blank data in NPC file

3

NP-8686-

A

400kV side of ICT-1 at

Durg(Raipur_PS)

Blank data in

NPC file

Similar problems have been reported in the following cases also

Sr.n

o

SEM Sr.no Location Issue faced Remarks

1

NP8723ANP8730A

NP8

732ANP8731A

NSPCL Failure of time

drift correction

NSPCL email

dtd.

29.10.19 2

NP8739A

400KV Raigarh(PS)

line-2 at

Durg(Raipur-PS)

Blank data in

NPC

file

No

redundancy

if standby

3 NP8685A 765KV side of ICT-1 AT

Durg 4 NP8686A 400KV side of ICT-1 AT

Durg

Page 22: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

5

NP8737A

765KV Dharamjaygarh

line 2 at

Durg

fails

6

NP8773A

765kV Wardha

line-2 at

Aurangabad 7

NP5478A

400kV side of

765/400kv ICT-2 at

Banaskhanta 8

NP8745A

765KV Dhule (BDTCL)

line at

Aurangabad(PG) 9

NP8697A

400KV Side of

ICT-3 at

TAMNAR(PS)

10 NP8822A 400kv side ICT-2 at

Pune(GIS) 11

NP5529A

NP5445A

NP5457A

NTPC KAWAS

HUGE TIME

DRIFT

Check

and

Standby Meter

WRLDC requested POWERGRID to replace all the above faulty meters

with meters of different make.

Committee may like to discuss.

Item

No. 20 Correction of Time drift in energy meters

Previous CCM discussions:

79th CCM: The list of meters where time drift has been reported /

observed was shown by WRLDC. Committee decided that the concerned

utility in whose premises the SEM is installed shall follow the

procedure for time drift correction through DCD in L&T, Secure and

Elster Meters as available at the WRLDC website. Concerned utilities

were requested to check/correct the time drift every week.

80th CCM: It was agreed that the weekly time drift

checking/correction is the responsibility of the station where SEM is

installed. It was also decided that all stations shall submit time drift

report along with the SEM data every week. It was also decided that

POWERGRID would include time drift correction in the scope of the

meter testing contract in future.

81st CCM: It was agreed to replace the meters having time drift of

Page 23: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

more than 10 minutes and to correct the time drift through DCD in

meters where drift is less than 10 min. The list of meters having time

drift more than 10 minutes was shared by WRLDC. The status is as

under:

Meter

ID

Meter

Number

Time

drift

Reported in

81st CCM

Tim

e

drift

as

on

date

Description

Remarks

POWERGRID

MM-24

NP2659

A

5

0

400kV Line-1 to HVDC

at

Bhadravati(west bus)

Issue

resolved

PG-80 NP2639A

5 0 400KV Bhilai line at Bhadrawati

GG-73 NP2779

A

2

6

.

4

3 400KV Vadodara line-1

at Asoj

To be

corrected

GG-72

NP2778

A

23.22

1

1

400KV Vadodara(PG)

line-2 at

ASOJ

GETCO

GU-51

NP4167

A

25.29

0

220kV Gandhar line-1

at

Haldarwa

Issue

resolved

GU-61 NP4171A

16.31 0 220kV Nasik line-1 at Navsari

GU-59

NP4173

A

16.24

0

220kV Navasari(PG)

Line at

Navsari (GETCO)

GU-25 NP2607

A

15.16 0 400kV Dhule (SSP) at

Kasor

GU-62 NP4172

A

15.04 0 220kV Nasik line-2 at

Navsari

GU-53 NP4160

A

10.25 0 220kV KAPS-1 at

Haldarwa

GU-55 NP4163

A

8.16 0 220kV Kawas-1 at

Haldarwa

PC-45 NP2300

A

13.39 0 220KV Vapi(PG) line-2

at Bhilad

NTPC

LA-17

NP9143A

18.48

Mete

r

Repl

aced

400KV CHAMPA Line-1

at

LARA(NTPC)

Issue resolved

Page 24: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

LA-05

NP9130

A

5.2 0

400KV Side of ST-1 at

LARA(NTPC)

CHATTISGARH

CS-52

NP2155

A

19.2 Mete

r

Repl

ace d

220kV Amarkantak line-

II at

Kotmikala

Issue

resolved

Meter

ID

Meter

Numbe

r

Time

drift

Reported

in

81st CCM

Tim

e

drift

as

on

date

Description

Remarks

CS-51

NP2413

A

5.4

0

220kV Amarkantak line-

I at

Kotmikala

CS-24

NP2146

A

9

0

400kV KSTPS line-I at

Korba(W)

CS-54

NP2122

A

12.56

-

1

220kV Budhipadar line-

II at

Korba(E)

To be

corrected

Ba

se

d

on

th

e

pa

ir

ch

ec

ki

ng

/v

ali

da

tion it is suspected that time drift has developed in few additional

meters. Letters were issued to the utilities for checking the time drift

at site and for taking corrective measures. List is as below: The summary is as below

S.no

Utility

Total

no of

mete

rs

Main

meters

with drift

>10 min

Standby

Meter

with

drift >10

min

Locations

Total

1

POWERGRID

784

11 (WR-

I: 0,

WR-II

:11)

39 (WR-

I:6,

WR-

II:33)

Durg, Wardha,

Boisar, Damoh,

Indore, Navsari,

Gwalior, Jabalpur,

Rajgarh,

Shujalpur,

Vadodara, Bina,

Khandwa,

Vindhyanchal

50

Page 25: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

2 NTPC 252 1 4 Gadarwada, Kawas,

Mouda

5

3 NPCIL 62 1 4 TAPS -1&2, KAPS-3&4

5

4

IPP

329

0

1

2

DB Power, Raigarh

Energen, RKM,

NSPCL, CGPL

12

5 Gujarat 111 3 0 Veloda, Asoj 3

6 Chhattisg

arh

25 1 0 Dongargarh 1

7

Maharash

tra

46

7

1

Akola, Alkud,

Dhule,

Kalmeshwar,

Koradi, Nasik,

Tillari

8

8

Madhya

Pradesh

66

1

2

1

Annupur,Kirnapur,B

hopal,Bin a,Indore,

Malanpur, Nagda,

Pandurna

13

9 DNH 15 1 2 Sayali,

Kharadpada

3

Total

1724

37 out of

565

63 out of

996

100

out

of

1724

Committee may like to discuss.

Item

No.21

Delayed submission of SEM data by Raigarh Energy Generation

Limited erstwhile KWPCL:

IEGC mandates that all utilities shall download and furnish SEM

meter data to WRLDC every week by Tuesday noon . The meter data

is essential for preparation of weekly DSM account. There has been

an inordinate delay in SEM data submission by Raigarh Energen for

the last 5 to 6 months. The details are as below

Page 26: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Week Week

duration

Delay in

hours

Week Week

duration

Delay

in

hours

WEEK

NO-27

300919-

061019

NOT

RECEIVED

WEEK

NO-13

240619-

300619 33

WEEK

NO-26

230919-

290919 48

WEEK

NO-12

170619-

230619 26

WEEK

NO-25

160919-

220919 24

WEEK

NO-11

100619-

160619 25

WEEK

NO-24

090919-

150919 69

WEEK

NO-10

030619-

090619 6

WEEK NO-23

020919-080919

58

WEEK

NO-9

270519-

020619 13

WEEK

NO-22

260819-

010919 58

WEEK

NO-8

200519-

260519 4

WEEK

NO-21

190819-

250819 78

WEEK

NO-7

130519-

190519 4

WEEK

NO-20

120819-

180819 23

WEEK

NO-6

060519-

120519 8

WEEK NO-19

050819-110819

78

WEEK

NO-5

290419-

050519 1

WEEK

NO-17

220719-

280719 24

WEEK

NO-4

220419-

280419 7

WEEK

NO-16

150719-

210719 27

WEEK

NO-15

080719-

140719 98

WEEK NO-14

010719-070719

24

The injection of Raigarh Energen is computed from the main meters at Kotra end. Check meter is not available at Kotra. In the absence of

Standby meter data the validation of the main cannot be done

Raigarh Energy Generation Ltd. to adhere to IEGC regulations and send weekly SEM data on time.

Committee may like to discuss.

Item

No.22 Installation of Check/Standby SEMs to ensure redundancy

The following main meters which are being used in accounting are

having no check or standby meters for their validation. In the event of failure of the SEM, there is no alternative data for substitution.

Sr.no Meter

sr.no Type Location Used for

Page 27: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

1 NP-9212-A Main 33 kV Tertiary side of

400/220/33KV ICT-1 at Durg

CS drawal

Main

33 kV Tertiary side of

400/220/33KV ICT-2 at

2 NP-9213-A Dharamjaygarh (PG)

4 NR-3680-

A Main

33 kV STATCOM Auxiliary

Transformer at Gwalior MP drawal

Main

38.5 kV side of STATCOM

Auxiliary transformer at

MH drawal

5 NP-9897-A Aurangabad

6 NP-8976-A Main 33 kV side of 765/400 kV

ICT-2 at Warora (PG)

7 NP-2904-A Main

33 kV side of ICT

(400/220/33KV) at

Bhadrawati(PG)

8 NP-8628-A Main 33 kV BARC Line-4 at TAPS

Zone-III BARC

9 NP-8629-A Main 33 kV BARC Line-6 at TAPS

Zone-III drawal

10 NP-2001-B Main 6.6 kV Vindhyachal HVDC-

ckt 1 at Vindhyachal STPS

PG drawal

11 NP-2017-B Main 6.6 kV Vindhyachal HVDC -

ckt 2 at Vindhyachal STPS

12 NP-2002-B Main 6.6 kV Vindhyachal HVDC -

ckt 3 at Vindhyachal STPS

13 NP-2004-B Main 6.6 kV Vindhyachal HVDC -

ckt 4 at Vindhyachal STPS

14 NP-2319-A Main 11 kV supply from MSEDCL

at Bhadravathi

15 NP-4216-A Main 11 kV supply from MSEDCL

at Bhadravathi

16 NP-9148-A Main 33 kV side of ICT-1 at

CHAMPA HVDC

17 NP-9112-A Main 33 kV side of ICT-4 at

CHAMPA HVDC

18 NP-2812-A Main 132 kV MSETCL line-1 at

Mouda(NTPC) Mouda inj

19 NP-2811-A Main 132 kV MSETCL line-2 at

Mouda(NTPC)

20 NP-2239-A Main 33 kV TAPS 3&4 line at

TAPS 1&2 TAPS inj

21 NP-2889-A Main 33 kV feeder at TAPS 1&2

22 NP-2890-A Main 33 kV feeder at TAPS 1&2

23 NP-2687-A Main 400 kV Side of ST-1 AT

SASAN Sasan Inj

24 NP-2688-A Main 400 kV Side of ST-2 AT

SASAN

Feasibility of installation of standby meters at the opposite end or in

series with the main meters at the same location to be confirmed by

respective utilities. POWERGRID to coordinate installation of the

Page 28: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

standby meters.

Utilities may update the status

Committee may like to discuss.

Item

No.23 Interface Energy Meter Data Discrepancies

The discrepancy report of SEMs is being forwarded to WRPC

secretariat every week along with the processed energy meter

readings. These details are also posted on the WRLDC website. All

the discrepancies were suitably addressed.

Committee may like to note.

Item

No.24 24X7 availability of Tejas Engineers at WRLDC

• Discussion summary of 518th OCC (26th April 2019):

The Committee decided to discuss the issue in telemetry meeting scheduled on 26 Apr 2019.

• Discussion summary of 520th OCC (13th June 2019):

SE(Opn), WRPC requested all constituents to give their opinion on matter of making arrangement of resident engineer support

from OEM at WRLDC for 24X7. In response, Gujarat and MP agreed but Maharashtra stated that they would discuss the issue with their management and confirm later on.

• Discussion summary of 38th WRPC Meeting (27th/28th June 2019):

ED LD &C, PGCIL stated that in principle it could be agreed but full agenda was required. But methodology could be discussed in SCADA meeting.

• Discussion summary of 521th OCC (16th July 2019):

PGCIL informed tentative cost towards Tejas 24X7 deployment shall be around 1.6 crore for a period of 5 years and requested

WRPC to decide mode of recovery of these charges to

POWERGRID through common corpus.

• SLDC, Gujarat shall inform GUVNL regarding the details of proposed arrangement of 24X7 Tejas Engineer at WRLDC.

• Maharashtra shall take up the issue with their management and

participate in CCM with their clear stand

• The issue shall be further discussed in next CCM.

Page 29: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Committee may like to discuss methodology of cost sharing and may take final decision.

Committee may like to discuss.

Item No.25

Status of Revised Letter of credit (LC) opening against Deviation charges liability for 2019-20.

The Hon‟ble CERC has issued regulations on “Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) Regulations, 2014” dtd 6th January 2014 implemented from 17th Feb‟14. Regulation 10 (4) of the principal Regulations is as below:

Quote

“All regional entities which had at any time during the previous financial year failed to make payment charges of Deviation including Additional charges for Deviation within the time specified in this regulations shall be required to open a Letter of Credit (LC) equal to 110% of its average payable weekly liability for Deviations in the previous financial year, in favour of the concerned RLDC within a fortnight from the date these Regulations come into force…………

………Provided further that LC amount shall be increased to 110% of the payable weekly liability in any week during the year, if it exceeds the previous LC amount by more than 50%.” Unquote

Sl No.

WR Entity who have to open LC

LC Amount

(Rs in

lakhs)

Remark / Status

1 CSPDCL 186 LC yet to be opened

2 MP Power Management Co. Ltd. 216 LC yet to be opened

3 D&D 142 LC Received

4 JINDAL POWER LIMITED 33 LC Received

5 HVDC Vin. 2 LC yet to be opened

6 HVDC Bha. 4 LC yet to be opened

7 Lanco Amarkantak Power Ltd 38 LC yet to be opened

8 ACBIL 36 LC yet to be opened

Page 30: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

9 RGPPL 37 LC yet to be opened

10 BALCO 49 LC yet to be opened

11 CGPL UMPP MUNDRA 77 LC yet to be opened

12 DCPP JSPL 21 LC yet to be opened

13 Essar Power MP ltd 38 LC yet to be opened

14 KSK Mahanadi 18 LC yet to be opened

15 GMR Warora Energy ltd 30 LC Received

16 KORBA WEST POWER Corp. LTD 4 LC yet to be opened

17 D. B.Power 64 LC yet to be opened

18 JAYPEE NIGRI TPP 39 LC yet to be opened

19 Essar Steel Ltd 118 LC yet to be opened

20 DGEN (Torrent Energy Limited) 18 LC yet to be opened

21 GMR Chhattisgarh Energy ltd 37 LC yet to be opened

22 RKM POWERGEN 17 LC yet to be opened

23 MB POWER 28 LC yet to be opened

24 JHABUA POWER 34 LC Received

25 SKS POWER 36 LC yet to be opened

26 TRN Energy ltd 21 LC yet to be opened

27 BARC 63 LC yet to be opened

28 HVDC CHAMPA 5 LC yet to be opened

29 Mahindra Renewable Pvt. Ltd (part of RUMS)

2 LC yet to be opened

30 ARINSUN CLEAN ENERGY (part of RUMS)(INFIRM)

3 LC Received

31 Ostro-Kutch Wind Pvt. Ltd.(INFIRM) 28 LC Received

Page 31: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

32 ACME Jaipur Solar (part of RUMS)(INFIRM)

5 LC yet to be opened

Committee may like to note.

Item No.26

Status of Reconciliation of Deviation, RRAS and REC pool account for the period upto Q2 FY 19-20

WRLDC vide letter dated 14.10.2019, have intimated that WRLDC has sent the signed reconciliation statement for the period upto Q2 FY

2019-20 to all Deviation/REC pool members. All the details of payments/receipts of Deviation charges and REC upto Q2 FY 19-20

are also uploaded on WRLDC website (https://wrldc.in/content/78_1_MarketOperations.aspx \ under the head “Pool Reconciliation\) As WRLDC has not received the signed

reconciled statements from the following entities the same has been considered as deemed reconciled by WRLDC.

DSM Pool Members : 1 CSPDCL

2 MPPTCL

3 GETCO LTD.

4 MSLDC UI Settlement account

5 Goa

6 D&D

7 JINDAL POWER LIMITED

8 HVDC Vin.

9 HVDC Bha.

10 Lanco Amarkantak Power Ltd

11 NSPCL

12 ACBIL

13 RGPPL

14 BALCO

15 CGPL UMPP MUNDRA

16 DCPP JSPL

17 Essar Power MP Ltd

18 SASAN Power Limited

19 KSK Mahanadi

20 Vandana Vidyut Ltd

21 KORBA WEST POWER Co. LTD

22 D. B.Power

23 Essar Steel India Ltd

Page 32: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

24 DGEN (Torrent Energy Limited)

25 GMR Chhattisgarh Energy Ltd

26 Dhariwal Infrastructure Ltd.

27 RKM Powergen Pvt Ltd.

28 MB Power (Madhya Pradesh) Ltd.

29 Jhabua Power Ltd

30 SKS POWER GENERATION (CHHATTISGARH) LTD

31 TRN Energy Ltd.

32 BARC (PAO, PREFRE, Tarapur)

33 HVDC CHAMPA

34 Mahindra Renewable Pvt. Ltd (part of RUMS)

35 ARINSUN CLEAN ENERGY (part of RUMS)(INFIRM)

36 Ostro-Kutch Wind Pvt. Ltd.

37 ACME Jaipur Solar (part of RUMS)

38 RENEW POWER

39 GIWEL SECI 2

40 GIWEL SECI 3

41 INOX WIND

REC Pool members

1 GETCO

2 MPMPCL

3 CSPDCL

4 MSEDCL

5 DD

6 GOA

RRAS

1 RGPPL

2 CGPL

3 SASAN

4 NSPCL

Committee may like to note.

Item No.27

Status of Payable/Receivable by WR entities

A. Status of Deviation charges : Payable/Receivable by WR entities to WR Deviation pool account

fund maintained by WRLDC as on 25 October 2019.

Page 33: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Major Default by Entities towards Deviation charges –Payable

1. Vandana Vidyut Ltd- Rs 10.00 Crs - Default from 14th week (30.06- 06.07.14). Already disconnected. 2. Mahindra Renewable Pvt. Ltd.:- Rs. 395.21 Lakh - Default from 14th week (01-07.07-19) up to 19th week (05-

11.08.19). 3. SKS Power – Rs. 174.15 Lakh - Default of previous FY 2018-19 and Rs.23.37 Lakh from 24th week (09-15.09.19) to

26th week (23-29.09.19). 4. Korba west –Rs. 92.90 Lakh - Default from previous quarter of FY

2018-19 and from 23rd week (02-08.09.19) to 26th week (23-29.09.19). .

5. HVDC Vindhyachal – Rs. 41.03 Lakh - Default from 01st Jan 2019. 6. Essar Steel – Rs.71.35 Lakh - Default of previous FY revisions.

B. Status of Reactive Energy Charges Payable to REC Pool Account Last updated on 25/10/19

No outstanding of Reactive payment

C. Status of Congestion Charge Account Payable to REC Pool Account Last updated on 25/10 /19 No outstanding of Reactive payment

Committee may like to note.

Item No.28

Interest calculation statement

A. Interest calculation statement of Deviation Pool Account for

FY 2018-19 due from following entities:

Vandana Vidyut Ltd – Rs. 647.07 Lakh

KORBA WEST POWER Co. LTD – Rs. 11.17 Lakh

B. Interest calculation statement of REC account for FY 2018-

19.

The summary of interest payable/receivable for Deviation pool

account along with payment status as on 25.10.19 is as given below:

Net interest

payable(+)/ receivable(-)

(in Rs.) Constituent

GETCO LTD. -1,49,329.00

-2,20,111.00

Page 34: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

*************

MP Power Management

Co. Ltd.

-8,907.00

Goa

-23,877.00

D&NH

-4,02,224.00

Total Rs.

C. Interest calculation statement of Congestion charge Account

for FY 2018-19. No outstanding interest on account of delay in Congestion payment till March‟2019.

Committee may like to note.

Item No.29

Venue and date of next CCM of WRPC

The date & venue of next (83rd CCM) shall be intimated in due course of

time.

Page 35: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-1 (1/2)

Page 36: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-1 (2/2)

Page 37: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-4.1 (1/2)

Page 38: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-4.1 (2/2)

Page 39: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-4.3 (1/1)

Page 40: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-5 (1/2)

Page 41: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-5 (2/2)

Page 42: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

82

CHAPTER – 11

COMPUTATION OF CAPACITY CHARGES AND ENERGY CHARGES

42. Computation and Payment of Capacity Charge for Thermal Generating

Stations:

(1) The fixed cost of a thermal generating station shall be computed on annual basis

based on the norms specified under these regulations and recovered on monthly basis

under capacity charge. The total capacity charge payable for a generating station shall

be shared by its beneficiaries as per their respective percentage share or allocation in

the capacity of the generating station. The capacity charge shall be recovered under two

segments of the year, i.e. High Demand Season (period of three months) and Low

Demand Season (period of remaining nine months), and within each season in two

parts viz., Capacity Charge for Peak Hours of the month and Capacity Charge for Off-

Peak Hours of the month as follows:

Capacity Charge for the Year (CCy) =

Sum of Capacity Charge for three months of High Demand Season +

Sum of Capacity Charge for nine months of Low Demand Season

(2) The Capacity Charge payable to a thermal generating station for a calendar

month shall be calculated in accordance with the following formulae:

Capacity Charge for the Month (CCm) =

Capacity Charge for Peak Hours of the Month (CCp) +

Capacity Charge for Off-Peak Hours of the Month (CCop)

Annexure-8 (1/5)

Page 43: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

83

Where,

High Demand Season:

CCp1= (0.20 𝑥 AFC) 𝑥 𝑥 subject to ceiling of (0.20 𝑥 AFC) 𝑥

CCp2 = {(0.20 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.20 𝑥AFC)𝑥 } −

𝐶𝐶𝑝1

CCp3= {(0.20 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.20 𝑥AFC)𝑥 } −

(𝐶𝐶𝑝1 + 𝐶𝐶𝑝2)]}

CCop1= {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 }

CCop2 = {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 } −

𝐶𝐶𝑜𝑝1

CCop3 = {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 } −

(𝐶𝐶𝑜𝑝1 + 𝐶𝐶𝑜𝑝2)

Low Demand Season:

CCp1 = {(0.20 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.20 𝑥AFC)𝑥 }

CCp2= {(0.20 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.20 𝑥AFC)𝑥 } −

𝐶𝐶𝑝1

CCp3= {(0.20 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.20 𝑥AFC)𝑥 } −

(𝐶𝐶𝑝1 + 𝐶𝐶𝑝2)

CCp4= {(0.20 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.20 𝑥AFC)𝑥 } −

(𝐶𝐶𝑝1 + 𝐶𝐶𝑝2 + 𝐶𝐶𝑝3)

Annexure-8 (2/5)

Page 44: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

84

CCp5= {(0.20 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.20 𝑥AFC)𝑥 } −

(𝐶𝐶𝑝1 + 𝐶𝐶𝑝2 + 𝐶𝐶𝑝3 + 𝐶𝐶𝑝4)

CCp6 = {(0.20 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.20 𝑥AFC)𝑥 } −

(𝐶𝐶𝑝1 + 𝐶𝐶𝑝2 + 𝐶𝐶𝑝3 + 𝐶𝐶𝑝4 + 𝐶𝐶𝑝5)

CCp7 = {(0.20 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.20 𝑥AFC)𝑥 } −

(𝐶𝐶𝑝1 + 𝐶𝐶𝑝2 + 𝐶𝐶𝑝3 + 𝐶𝐶𝑝4 + 𝐶𝐶𝑝5 + 𝐶𝐶𝑝6)

CCp8= {(0.20 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.20 𝑥AFC)𝑥 } −

(𝐶𝐶𝑝1 + 𝐶𝐶𝑝2 + 𝐶𝐶𝑝3 + 𝐶𝐶𝑝4 + 𝐶𝐶𝑝5 + 𝐶𝐶𝑝6 + 𝐶𝐶𝑝7)

CCp9 = {(0.20 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.20 𝑥AFC)𝑥 } −

(𝐶𝐶𝑝1 + 𝐶𝐶𝑝2 + 𝐶𝐶𝑝3 + 𝐶𝐶𝑝4 + 𝐶𝐶𝑝5 + 𝐶𝐶𝑝6 + 𝐶𝐶𝑝7 + 𝐶𝐶𝑝8)

CCop1 = {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 }

CCop2 = {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 } −

𝐶𝐶𝑜𝑝1

CCop3 = {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 } −

(𝐶𝐶𝑜𝑝1 + 𝐶𝐶𝑜𝑝2)

CCop4 = {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 } −

(𝐶𝐶𝑜𝑝1 + 𝐶𝐶𝑜𝑝2 + 𝐶𝐶𝑜𝑝3)

CCop5= {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 } −

(𝐶𝐶𝑜𝑝1 + 𝐶𝐶𝑜𝑝2 + 𝐶𝐶𝑜𝑝3 + 𝐶𝐶𝑜𝑝4)

Annexure-8 (3/5)

Page 45: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

85

CCop6 = {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 } −

(𝐶𝐶𝑜𝑝1 + 𝐶𝐶𝑜𝑝2 + 𝐶𝐶𝑜𝑝3 + 𝐶𝐶𝑜𝑝4 + 𝐶𝐶𝑜𝑝5)

CCop7= {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 } −

(𝐶𝐶𝑜𝑝1 + 𝐶𝐶𝑜𝑝2 + 𝐶𝐶𝑜𝑝3 + 𝐶𝐶𝑜𝑝4 + 𝐶𝐶𝑜𝑝5 + 𝐶𝐶𝑜𝑝6)

CCop8 = {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 } −

(𝐶𝐶𝑜𝑝1 + 𝐶𝐶𝑜𝑝2 + 𝐶𝐶𝑜𝑝3 + 𝐶𝐶𝑜𝑝4 + 𝐶𝐶𝑜𝑝5 + 𝐶𝐶𝑜𝑝6 + 𝐶𝐶𝑜𝑝7)

CCop9 = {(0.80 𝑥AFC)𝑥 𝑥 subject to ceiling of (0.80 𝑥AFC)𝑥 } −

(𝐶𝐶𝑜𝑝1 + 𝐶𝐶𝑜𝑝2 + 𝐶𝐶𝑜𝑝3 + 𝐶𝐶𝑜𝑝4 + 𝐶𝐶𝑜𝑝5 + 𝐶𝐶𝑜𝑝6 + 𝐶𝐶𝑜𝑝7 +

𝐶𝐶𝑜𝑝8)

Provided that in case of generating station or unit thereof under

shutdown due to Renovation and Modernisation, the generating company shall

be allowed to recover O&M expenses and interest on loan only.

Where,

CCm= Capacity Charge for the Month;

CCp= Capacity Charge for the Peak Hours of the Month;

CCop= Capacity Charge for the Off-Peak Hours of the Month;

CCpn= Capacity Charge for the Peak Hours of nth Month in a specific

Season;

CCopn= Capacity Charge for the Off-Peak of nth Month in a specific

Season;

AFC = Annual Fixed Cost;

Annexure-8 (4/5)

Page 46: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

86

PAFMpn = Plant Availability Factor achieved during Peak Hours upto the end

of nth Month in a Season;

PAFMopn = Plant Availability Factor achieved during Off-Peak Hours upto the

end of nth Month in a Season;

NAPAF= Normative Annual Plant Availability Factor.

(3) Normative Plant Availability Factor for “Peak” and “Off-Peak” Hours in a

month shall be equivalent to the NAPAF specified in Clause (A) of Regulation 49 of

these regulations. The number of hours of “Peak” and “Off-Peak” periods during a

day shall be four and twenty respectively. The hours of Peak and Off-Peak periods

during a day shall be declared by the concerned RLDC at least a week in advance. The

High Demand Season (period of three months, consecutive or otherwise) and Low

Demand Season (period of remaining nine months, consecutive or otherwise) in a

region shall be declared by the concerned RLDC, at least six months in advance:

Provided that RLDC, after duly considering the comments of the concerned

stakeholders, shall declare Peak Hours and High Demand Season in such a way as to

coincide with the majority of the Peak Hours and High Demand Season of the region to

the maximum extent possible:

Provided further that in respect of a generating station having beneficiaries

across different regions, the High Demand Season and the Peak Hours shall correspond

to the High Demand Season and Peak Hours of the region in which majority of its

beneficiaries, in terms of percentage of allocation of share, are located.

(4) Any under-recovery or over-recovery of Capacity Charge as a result of under-

achievement or over-achievement, vis-à-vis the NAPAF in Peak and Off-Peak Hours of

Annexure-8 (5/5)

Page 47: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

ffitW\}lrliitA:'{Si:.i

Phone - (022) (O) 2760 1931 (P) 2760 1762 Fax- (022) 2760 1769t2760 2936E mail - [email protected] NO. U40 109MH2005SGC153646

U RL-www. mahatra nsco. in/www. mah asldc. in

i

il!ll

Hl4t;

2200oxe:2tl Au0

Office of

, The Chief EngineerMaharashtra State Load Dispatch Centre

Thane-Belapur Road, AiroliNaviMumbai-4O0 708 ( INDIA )

(lSO 9001-2000 ceftified unit of Mahatransco)

Ref.No. : CElMSLDC / KLw I E A /

To,The Superintending Engineer (Commercial),Western Regional Power Committee,F-3, MIDC Area, Marol,Opp. SEEPZ, Central Road,Andheri (East), Mumbai - 4OO 093.

Sub:- Non-applicability of Delay Pa5rment Charges towards Fa5rment of, DSM BiIl for3r-12.2A1a.

Ref.:- 1) L,etter no.WRPC/Comml.-Il4/ABTDSM /2OLB/12.51575 dtd.31.O1.2019.2) I*tter no.WRPC/Comm1.-Il4/ABTDSM /ZOLB/12.5A-1.2A/2O3O dtd. L8.O2.2O79.

Sir,

This office had received DSM bill vide u/r (1) wherein bill period mentioned was3L.L2.2OLB to O6.01.2019. It was evident from the covering letter that tJ:e pa5rment mentionedwas for the week from 31.L2.2078 to 06.01.2O19 amounting to Rs.2,77,49L/- & it was dulysigned- This offrce has paid Rs.2,'l"l ,491/- vtde Cheque No.U9'/'/4'2 dtd. tJ'|.O2.2O19 within thetimelines of DSM bill due date.

Further, this office was in receipt of revised bill with period mentioned as O1.01.2019 to2O.O1.2O1,9 vide u/r (2) amounting to Rs.3,O6,O6,9O3/-.However, considering the weeklvpattern of bills issued by IVRPC, this oflice had inadvertently deducted the charges i.e.Rs.2,77,49L/- far 31.12-2018 from the said trill. The payrnent was done by this oflice forRs.3,03,29,412/- vide Cheque No.O97755 dtd.27-O2.2O19 i.e. with deduction of charges for31.12.20L8.

After scrutinizing, it was found that the amount of Rs. 2,77,491/- was only for31.L2.2O18. Thus, the said amount was immediately paid by this office through cheque No.

LO9829 dtd. 15.07 .2079.

It is pertinent to note that Maharashtra State L,oad Dispatch Centre has never defaultedpayment against the timelines of DSM bills and therefore, DPC may not be charged for therespective period i.e. 31.72.2OL8 as it is inadvertent error on both sides. In view of above, DPCshould not be levied on the amount Rs.2,77,491/-.

Your's faithfuliy,Thanking you.

Annexure-10 (1/1)

Page 48: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-12 (1/2)

Page 49: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-12 (2/2)

Page 50: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-14 (1/1)

Page 51: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (1/13)

Page 52: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (2/13)

Page 53: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (3/13)

Page 54: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (4/13)

Page 55: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (5/13)

Page 56: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (6/13)

Page 57: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (7/13)

Page 58: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (8/13)

Page 59: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (9/13)

Page 60: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (10/13)

Page 61: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (11/13)

Page 62: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (12/13)

Page 63: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-15 (13/13)

Page 64: Baart sarkar - wrpc.gov.in · No.1 thereof CSPTCL vide letter dated 12.07.19 informed that- (i) As discussed in the meeting for freezing of REA data for the month of January to March

Annexure-27 (1/1)