Upload
lamlien
View
243
Download
5
Embed Size (px)
Citation preview
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 1
AGENDA OF 128th PROTECTION COMMITTEE MEETING OF WRPC
TO BE HELD ON 06.12.2016 & 07.12.2016
ITEM NO.1: CONFIRMATION OF MINUTES OF 127th PROTECTION COMMITTEE
MEETING
The minutes of 127th PCM, held on 27.07.16 and 28.07.16 at WRPC, Mumbai were
circulated vide WRPC letter No. WRPC/Protection/127PCM/2016/ 10893 dated 05.10.2016.
No comments were received.
Committee may like to confirm the minutes of 127th PCM.
ITEM 2: OCCURANCES/GRID DISTURBANCES:
A. OCCURANCES IN GUJARAT SYSTEM
2.1. Grid Incidence at 400/220 kV Asoj Sub-station on 14th May 2016
On 14th May 2016, at 02:04 hrs, R phase CT (Make: HBB, Date of commissioning:
12.03.1987) of 400 kV Asoj- Kosamba line flashed and caught fire at Asoj substation. Due to
this bus fault occurred on 400 kV Bus 1 on which the circuit was connected at Asoj Substation.
Due to failure and blasting of this CT, other damages are as under.
Y phase CT of Kosamba line.
B phase CT of Chorania 1 line.
B phase LA of Chorania 1 line.
Rotating PI of TBC isolator of Chorania line.
This led to bus fault and Alstom make bus bar protection scheme operated correctly by
tripping 400 kV Bus 1 and all connected lines and ICTs connected to 400 kV Bus 1 and 400 kV
bus coupler tripped. There was no load or generation loss during the event.
Most of the elements were restored by 03:35 hrs; expect 400 KV Kosamba which was
restored at 4:45 of 15.05.16 and 400 KV Chorania 1 was switched off due to damage of CT and
LA from 5:25hrs of 14.05.16 to 20.00hrs of 16.05.16.
The report received from WRLDC is enclosed in annexure 2.1.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 2
2.2. Grid Incidence at 400/220 kV Choronia substation on 17th June 2016
On 17th June 2016, at Chorania s/s, 400KV Asoj line no.1 was under outage for line
maintenance work. After completion of work line was charged at 17:22 hours. At 17:55hrs, B-
phase pole (Towards line side) of 400 kV breaker (Make: CGL, Date of commissioning: 29-03-
1994) of 400kV Choronia- Asoj 1 circuit failed at 400/220 kV Chorania substation. With the
bursting of breaker pole, its support column, both side pipe bus connectors and line side isolator
also got damaged which further damaged the Insulator of the Y-phase breaker pole. Damaged
pipe bus connector on the bus side of B-phase pole of the breaker got earthed causing Bus fault
on 400 kV Bus 1 at 400/220 kV Choronia substation. With this, the bus bar protection has
operated for 400 kV Bus 1 resulting in tripping of 400/220KV 500MVA ICT No.1, 400/220 kV
500 MVA ICT 3, 400 kV Choronia-Asoj 1, 400 kV Choronia-Asoj 1, 400 kV Choronia-
Kosamba 1, 400 kV Choronia-Vadavi 1, 400 kV Choronia-CGPL 1, 400 kV Bus coupler to
isolate the fault.
There was no load/generation loss during the event. Most of the elements are restored by
19:19 hrs.
DCRM test was carried out on 04-04-2015 and the Results found normal. On 04-02-2016
breaker timing test was carried out. Routine maintenance like cleaning of porcelain parts etc.
carried out.
The report received from WRLDC is enclosed as annexure 2.2.
Committee may like to discuss.
2.3. Grid Incidence at 400/220 kV Kansari Sub-station on 12th July 2016
On 12th July 2016, at 01:24 hrs, 220 kV Kansari-Palanpur 2 tripped on distance
protection in zone 2 from Palanpur end only on B phase to Earth fault. Due to VT fuse failure for
both 220 kV Buses, the distance protections relays for 220 kV lines got disabled at Kansari end.
Simultaneously, 220 kV Kansari-Palanpur 1 tripped on distance protection zone 2 from Palanpur
end. At Kansari end, master trip relay operated due to the operation of E/F relay, but breaker
tripped with delay. So, the LBB relay for same line at Kansari end has also operated. As 220 kV
Kansari-Palanpur 1 was connected with 220 KV Bus A, all bays connected with 220 kV Bus A
and 220 kV Bus coupler tripped on operation of bus bar trip relay. During the event, fault has
persistently been seen by remote end and tripping the lines in zone 2. However, there was no
load/generation loss during the event.
During the event heavy DC earth leakage was observed in DC-1 as well as DC-2 source.
Work of locating DC earth leakage was taken up by substation staff by removing fuses of DC
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 3
circuit one by one and also checking DC circuit of each control and relay panel for 220 kV Bay.
At 13.21 hrs. due to prevailing DC earth leakage, trip bus of bus bar scheme (pilot wire for Bus 2
tripping) was energized inadvertently and so all feeders and transformers connected with 220 kV
Bus B tripped. 220 kV Bus coupler also tripped. During this event there was no interruption of
power supply.
The report received from WRLDC is enclosed in annexure 2.3.
Committee may like to discuss.
2.4. Grid Incidence at 400/220 kV Kansari Sub-station on 29th June 2016
On 29th June 2016, at 05:40 Hrs, LBB relay for 400 kV Kansari-Kankroli circuit mal
operated at Kansari end causing tripping of 400 kV Bus Bar 2 at Kansari and tripping of 400 kV
Kansari-Kankroli, 400 kV Kansari-Ranchorpura 2, 400 kV Soja-Kansari, 400 kV Varsana-
Kansari, 400/220 kV ICT 1, 400/220 kV ICT 3 along with bus coupler, connected to Bus 2.
After this event, the 400/220 kV ICT 1 & 3 which were on Bus 1 were out causing load
to shift on ICT 2. This ICT also tripped within 2 minutes on overload. However there was no
interruption at 220 kV level as load was managed through 220 kV system.
Also at 400 kV Kansri-Ranchorpura 2 and 400 kV Kansari-Soja SOE has not generated
from Kansari end. Further Ranchorpura end and Varsana end SOE has also not generated.
Gujarat SLDC and GETCO need to work on these issues with WRLDC SCADA team. Tripping
report along with DR/EL has not been submitted by GETCO to WRLDC/WRPC.
The report received from WRLDC is enclosed in annexure 2.4.
Committee may like to discuss.
2.5. Grid Incidence at 400/220 kV Kansari (Zerda) Sub-station on 30th June 2016
On 30th June 2016, at 01:35 Hrs. R Phase L.A of 66 kV Kansari-Samsherpura line and 66
kV Kansari-Voda line flashed over during the rainy weather with lightning at Kansari Sub-
station. Simultaneously, Y Phase HV bushing of 220/66 kV, 100 MVA Transformer 3 (CGL
make) also flashed resulting in fire and got damaged. Subsequently fire also took place in OLTC
box, marshaling box and RTCC panel in control room. Due to fire in OLTC drive box, breaker
M.K box, all connected control cables got damaged and D.C leakage has occurred.
Due to the loss of D.C supply to breaker trip coil, 220/66 kV 100 MVA Transformer 3
(CGL make) did not tripped. However, differential trip signal is picked up in the relay. The
transformer differential relay (Alstom makes -MicomP632) is completely damaged due to fire.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 4
The Y-B phase in the system which was not being cleared due to DC leakages causing delayed
fault in the system.
With this 220 kV Lines from Kansari sub-station picked up in zone 2 and tripped. While
the 400/220 kV ICT 1, 2 and 3 at Kansari sub-station tripped on Group A protection from LV
side. Further, 400 kV APL-Kansari, 400 kV Bhinmal-Kansari, 400 kV Kansari-Varsana, 400 kV
Kansari-Ranchodpura 1 and Line reactor of 400 kV Kansari- APL 1 and 2 future lines also got
tripped. There was no major load/generation loss during the event. All the elements are restored
by 20:45 hrs.
The tripping sequence and relay indications from GETCO and report received from
WRLDC are enclosed in annexure 2.5.
Committee may like to discuss.
2.6. Grid Incidence at Kutch Lignite Thermal power plant, Panandharo on 14th June 2016
On 14th June 2016, at 18:14 Hrs, R phase conductor of 220 kV KLTPS-Kukma 1 circuit
fell on 220 kV Bus 1 at KLTPS in the switchyard causing bus fault on Bus 1. With this 220 kV
lines connected with 220 kV Bus 1 along with Unit 1 & 2 and 220/66 kV ICT got tripped. Total
generation loss during the event was 140 MW and load loss of 20 MW.
The above incident due to lack of details from SLDC Gujarat and KLTPS generating plant,
has been analyzed on the basis of preliminary information at WRLDC and no conclusive
analysis has been made.
Further, it seems that lines have tripped from Bus bar protection operation from 220 kV Bus
1 at KLTPS end. The details are not available from SLDC regarding its operation. The tripping
of 400 kV AKLTPS-KLTPS 2 from AKLTPS (Akrimota) end was not desirable. Further,
tripping of both units was also not desirable in view of bus fault on only one of the bus.
Most of the elements are restored by 20:04 hrs. The Unit 1 at KLTPS is taken into service at
21:31 hrs, and Unit 2 at KLTPS is taken into service at 22:36 hrs.
Gujarat SLDC/KLTPS are requested to submit report on the event along with relevant
disturbance recorder and event logger.
The report received from WRLDC is enclosed in annexure 2.6.
Committee may like to discuss.
2.7. Grid Incidence at 400/220 kV Pirana PG on 25th June 2016 and its Impact on the Grid
It was reported by PGCIL that rains, lightning and thunderstorm were prevailing at
Pirana (PG) station. On 25th June 2016, at 19:45:10:735 Hrs, Initially Y phase fault appeared in
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 5
the 400 kV Vadodara-Pirana (PG) Circuit 2 which was detected by Pirana (PG) relay in Zone 4
i.e. reverse zone. The fault current observed was 19 kA from Pirana (PG) end. After 250 ms of
the fault in Y phase, the fault also appeared in R phase with fault current of 19 kA from Pirana
(PG) end. Fault was still observed by Pirana (PG) end in Zone 4. After 500 ms, the Zone 4 from
Pirana end and Zone 2 from Vadodara end operated and cleared the fault. (DR attached in
Annexure 2.7).
At same time (19:45:10:735 Hrs); Due to the lightning strike on 400 kV Vadodara-
Pirana (PG) 1 circuit, it tripped in stage 2 overvoltage operation at Pirana (PG) station. Direct
trip was sent to Vadodara end and it tripped the line. However the Voltage was still observable
in the line which became zero only after clearance of the fault on parallel circuit. The voltage in
B phase reached to 231 kV to 417 kV during the lightning. The line tripped after 182 ms from
Pirana (PG) end while the voltage has come to zero in the line after 500 ms only. (DR attached
in Annexure 2.7)
As the fault on 400 kV Vadodara-Pirana (PG) 2 circuit was in the zone 1 of the line
however relay of this circuit observed it in zone 4, this resulted in fault being seen by other line
connected from Pirana in their Zone 4 and their remote end in Zone 2. 400/220 kV ICTs of
Pirana (PG) will also be observing this fault in their backup protection from 220 kV side.
This resulted in 400 kV Pirana-Dehgam 1 & 2 tripping in Zone 4 from Pirana end. These circuits
also tripped from their remote end in zone 2. (DR attached in Annexure 2.7)
However, the 400 kV Pirana (Torrent)-Pirana (PG) 1 & 2 circuit did not trip from
Pirana (PG) end in Zone 4. Further, 400 kV Pirana (Torrent)-Pirana (PG) 2 which initially did
not observe the fault in zone 2 from Pirana (Torrent) when fault was in Y phase has seen it as
Zone 3 only. As soon as the fault appeared in R phase in 400 kV Vadodara-Pirana (PG) 2 circuit
after the Y phase, Pirana (Torrent) end relay observed the fault in Zone 2 with increased fault
current and immediately gave the trip command only to the R phase Pole and zone 2 got reset.
The fault at Remote end sub-station of Pirana (PG) got cleared in 500ms and zone 3 got reset.
The other Y and B phase pole of this got tripped after 1.2 second of the fault initiation. (DR
attached in Annexure 2.7) There was no tripping of 400 kV Pirana (Torrent)-Pirana (PG) 1 from
Pirana (Torrent) end in zone 2.
Thus the only 400 kV Incoming feeder to Pirana(PG) was 400 kV Pirana (Torrent)-
Pirana (PG) 1 which through 400/220 kV ICTs at Pirana (PG) kept feeding the 220 kV loads
connected at Pirana(PG).
However, due to this delayed fault clearance and severity of the fault in the system, df/dt
based load shedding relay operated in Gujarat and Maharashtra system causing load shedding. In
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 6
Gujarat around 559 MW load has shed while in Maharashtra 411 MW of load was lost on this
account. The net Load loss amount expected is around 970 MW and Energy unserved was in
the quantum of 407 MWHr. The frequency rose from 49.814 Hz to 50.017 Hz ie., a rise of
0.203 Hz.
The report received from WRLDC is enclosed in annexure 2.7.
Committee may like to discuss.
2.8. Grid Incidence at 400/220 kV Wanakbori Sub-station:
On 18th May 2016, Due to multiple CTs failure at 400 kV level in 400/220 kV
Wanakbori Sub-station between 22:07 to 22:57 Hrs, 400 kV Wanakbori Unit 4, 6 & 7, 400/220
kV Wanakbori ICT, 400 kV Wanakbori-Soja and 400 kV Wanakbori-Dehgam circuit have
tripped along with 400 kV Bus 2.
Prior to the incidence, all 400 kV lines and units were in service at Wanakbori.
At 22:07:54.800 Hrs, R phase CT of Tie Bay of 400 kV Wanakbori-Dehgam circuit and
Unit 6 failed with which bus bar protection operated resulting in tripping of the circuit breakers
in the dia and thus isolating the fault. However, with this all Main breaker of 400 kV Bus 2 has
also tripped on the bus bar differential protection which was not desirable.
At 22:07:56.560 Hrs, B phase to earth fault occurred on 400 kV Wanakbori-Soja circuit
with which distance protection operated thus line got tripped. As Unit 7 was connected via the
tie CB and Main CB of the line through 400 kV Bus 1, it also tripped with the tripping of line.
With these two events, 400 kV Bus 2, Unit 6 and 7 has tripped along with 400 kV Wanakbori-
Soja and Wanakbori-Dehgam circuit at 400/220 kV Wanakbori sub-station.
At 22:57:35.200 Hrs, B phase CT of 400 kV Main Bay of 400/220 kV ICT (which is
between Main Breaker and ICT) at Wanakbori also failed resulting in operation of ICT
differential protection and tripping of Main and Tie CB. As Unit 4 was connected via the tie CB
and Main CB of the ICT through 400 kV Bus 1, it also tripped.
The loss of units has resulted in 581 MW of generation loss.
The report received from WRLDC is enclosed in annexure 2.8.
Committee may like to discuss.
2.9. Grid Incidence at 220 KV AKLTPS AND KLTPS Sub-Stations on 19th May 2015
During removal of Vibration Damper work on Location No.364(S) of the 220 kV
KLTPS-Kukma circuit 2, an accident occurred at 16:45 Hrs, due to which 220 kV KLTPS-
Kukma circuit 2 got tripped. At the same time, 220 KV AKLTPS-Nakhatrana circuit 1 tripped
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 7
only from Akrimota end on SOTF. Afterwards, at 16:56 Hrs, 220 kV KLTPS-Nakhatrana circuit
1 got tripped from both ends due to breaking of conductor at Location No. 58(T).
Simultaneously, 220 kV KLTPS-Nakhatrana circuit 2 tripped only from KLTPS end only.
After that at 16:58 Hrs, 220 kV AKLTPS-Nakhatrana circuit 2 tripped at Akrimota end
only(R-Ph Breaker Pole problem at Akrimota). Simultaneously 220 kV KLTPS-AKLTPS D/C
also tripped at Akrimota end only on Under-Voltage and Under-Frequency.
Due to tripping of above lines and non-availability of Power Evacuation for KLTPS and
Akrimota Generation, all units of Panandharo and Akrimota tripped and hence Blackout
occurred at Panandharo and Akrimota TPS. Due to above incident Panandharo remained in zero
power from 16:58 Hrs. to 17:08 Hrs. i.e. 10 minutes and Akrimota remained in zero power from
16:58 Hrs. to 17:23 Hrs. i.e. 25 minutes. Along with the above, six 66 kV Sub-Stations remained
in zero power from 16:58 Hrs. to 17:18 Hrs. i.e. 20 minutes. Most of the elements were restored
by 23:20 hrs.
The report received from WRLDC is enclosed in annexure 2.9.
Committee may like to discuss.
2.10. Grid Incidence at 220 kV AKLTPS Sub-station in Gujarat on 24th May 2016
Prior to the incident, only one unit i.e. unit 2 at Akrimota TPS (AKLTPS) was on bar. All
the 220 kV lines were in service from the sub-station. On 24th May 2016, at 05:20 Hrs, B phase
to earth fault occurred on 220 kV Akrimota-Nakhatrana 1 circuit and cleared within 160 ms. The
fault location was 1.5 km from Akrimota end. However with this Bus bar protection for Zone 2
and Zone 3 also operated on C phase resulting in tripping of both the buses and causing
complete blackout at Akrimota sub-station.
The loss of Unit 2 due to blackout cause loss of 95 MW of the generation.
It seems that fault for close in fault on the line, the bus bar protection has mal-operated resulting
in complete loss of the sub-station.
The report received from WRLDC is enclosed in annexure 2.10.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 8
B. OCCURANCES IN MADHYA PRADESH SYSTEM
2.11. Grid Incidence at 220/132 kV Bina Sub-station, Madhya Pradesh on 5th April 2016
220 /132 kV Bina sub-station in Madhya Pradesh is having a SMT bus scheme. Prior to
the event, all the elements were in service at the station. On 05th April 2016, at 05:41 Hrs, B
phase CT of 220 kV Bina-Bina Interconnector 1 circuit failed at 220/132 kV Bina sub-station
resulting in Bus fault. After this bus bar protection operated at Bina sub-station and all 220 kV
elements tripped. However, the fault was observed by the 220 kV Bina-Bina Interconnector 1
from 400/220 kV Bina end in zone 2 resulting in its clearance after 400 ms.
Further, it can be seen that due to fire and fume Y phase fault has also developed in the
system. The Zone 2 operation at remote end is due to the location of CT after the breaker in the
SMT arrangement. As during the morning hour load is less and 132 kV systems were
interconnected so none of the area observed any blackouts and system was intact. It is observed
that remote end has not received direct trip command after us bar protection operation which
may kindly be included in the scheme. This will reduce the fault duration timing as observed in
the above case. MPPTCL may kindly appraise on the above issue in details.
220/132 KV, 160MVA x”mer –I, was restored by 06:17hrs, 132 KV Bina- Bori Ckt I &
II was restored by 06:20hrs, 220/132 KV, 3*40MVA x”mer –III was restored by 11:28hrs,
220KV Bina interconnector was restored by 21:42hrs. 220KV Bina- Vidisha Ckt and Bina-
Ganjbasoda Ckt were restored on 07.04.2016 at 20:12hrs and 20:16hrs respectively.
The report received from WRLDC is enclosed in annexure 2.11.
Committee may like to discuss.
2.12. Grid Incidence at 400/220/132 kV Cheggaon Sub-station on 4th May 2016 & 18th May
2016
On 4th May 2016, at 11:43 Hrs, due to bursting of B Phase CT of 220/132 kV, 160 MVA
ICT 1 at 400/220/132 kV Cheggaon Sub-station Bus fault occurred on 220 kV bus 1. With this
it’s Bus Bar protection operated resulting in tripping of feeders connected to 220 kV Bus 1.
During the event 50 MW load loss occurred at Cheggaon with energy unserved quantum of 22.5
MWHr. Most of elements are restored by 12:50hrs. 220/132 KV transformer is still out.
On 18th May 2016, prior to the incidence the system was normal and at 400KV S/s
Cheggaon, all 220KV and 132 KV feeders were in charged condition and normally loaded. At
400 KV S/s Cheggaon double main transfer bus scheme exists for 220KV system.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 9
At around 17:20 hrs, Y-phase CT (Make: SCT, date of commissioning: 24th January
2011) of 220 KV Chhegaon – Nepanagar Ckt burst at 400KV S/s Cheggaon resulting 220KV
bus fault consequently bus bar protection of 220 KV main Bus-I operated at 400KV S/s
Cheggaon resulting all connected feeders and transformers tripped.
220KV Main Bus I at 400 KV S/s Chhegaon was energized by charging 400/220KV,
315MVA ICT at 18:09hrs. Later, most of the elements are restored by 18:50hrs.after
replacement of failed Y phase CT of 220KV Chhegaon –Nepanagar Ckt, the feeder was charged
on 19th May 2016, at 21:55hrs.
The report received from WRLDC is enclosed in annexure 2.12.
Committee may like to discuss.
2.13. Grid Incidence at 220/132 kV Damoh Substation, Madhya Pradesh on 25th May 2016
On 25th May 2016, at 10:00 Hrs, due to mal operation of 220 kV bus bar protection
system at 220/132 kV Damoh (MP) Substation, all 220 kV connected feeders tripped. However,
the 132 kV System remained intact with the system so there was no load/generation loss.
MPPTCL and MP SLDC may kindly submit the data on the event. MPPTCL may give the
reasons for mal operation of bus bar protection relay.
The report received from WRLDC is enclosed in annexure 2.13.
Committee may like to discuss.
2.14. Grid Incidence at 220/132 kV Mahalgaon (MP) Substation on 20th May 2016
On 20th May 2016, at 08:15 Hrs due to bursting of Y phase 220 kV CT of 220 kV Bina
(MP)-Mahalgaon circuit (which was ideally charged from 220KV Mahalgaon end) at Mahalgaon
end, resulting bus fault occurred on 220 kV bus causing bus bar protection operation and
tripping all connected 220 kV feeders.
However, 132 kV system at Mahalgaon substation remain connected through lines from
132 kV Dabra and 132 kV Karera. Hence, there was no generation/load loss during the event.
Most of the elements are restored by 08:42hrs. The damaged CT has been replaced and 220KV
Bina- Mahalgaon Ckt was ideally charged from 220KV Mahalgaon end on 24th May 2016, at
15:45hrs.
The report received from WRLDC is enclosed in annexure 2.8.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 10
2.15. Grid Occurrence at 220/132 kV Maihar substation on 25th May 2016
On 25th May 2015, at 12:23 Hrs, 220 kV Katni-Maihar circuit got tripped from Katni
End, R phase distance protection operated in zone 1 because of earth fault which has led to the
shifting of entire load of 220/132 kV Keymore and radially connected stations on 132 kV
Keymore-Maihar circuit. At 12:25 Hrs, 132 kV Maihar-Keymore circuit also tripped on R phase
to earth fault due to the disc insulator failure. With this supply to 220/132 kV Maihar substation
was lost and the substation got blackout.
Further at 12:32 Hrs, due to tripping of 132 kV Keymore-Katni Ckt I got tripped from
Katni End, R phase distance protection operated in zone III because of R phase to earth fault has
led to blackout of 132 kV Keymore sub-station. The event caused a load loss of 56.8 MW along
with energy unserved of 13.41 MWhr to the consumers. Most of the elements are restored by
13:13 hrs.
The report received from WRLDC is enclosed in annexure 2.15.
Committee may like to discuss.
2.16. Grid Incidence at 220/132 kV Malanpur on 20th May 2016
220 kV Malanpur Bus is having a single main and auxiliary bus scheme. Prior to the
event all 220 kV lines and ICTs were in service from Malanpur end. On 20th May 2016, at 23:38
Hrs, B phase CT of 220 kV Gwalior(PG)-Malanpur 1 got burst causing bus fault and tripping of
all the 220 kV connected elements from Malanpur sub-station on Bus bar protection. The 132
kV systems have survived at Malanpur and there was no load/generation loss during the event.
Most of the elements are restored on 21st May 2016 by 01:25hrs.
The report received from WRLDC is enclosed in annexure 2.16.
Committee may like to discuss.
2.17. Grid Incidence at 400/220 kV Satpura Thermal Power station on 6th April 2016
On 06th April 2016, at 19.50 Hrs. Satpura Unit 9 got tripped on Generator CB Air
Pressure Very Low alarm. After rectification of the same, the unit was being synchronized by
circuit breaker closing at 21:00 Hrs, during the synchronization of Unit 9 of Satpura with 400 kV
Bus 1 at 400/220 kV Satpura Sub-station, its generating transformer REF protection operated
and trip command got initiated to the circuit breaker. However, the circuit breaker failed to trip
and its LBB protection got initiated which gave command to Bus Bar Zone-1 protection
operation to isolate Bus 1 along with the Bus coupler. This led to tripping of all connected 400
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 11
kV elements from the bus including Unit 10. As the station transformer for Unit 11 was on Bus 1
which got tripped causing tripping of Unit 11 which was actually on Main bus 2. This leads to
467 MW of generation loss occurred due to the tripping of the Unit 10 and 11 in this event.
Further, with Operation of Bus bar protection due to LBB trip command, the generator
circuit breaker (the same does not operate when REF protection operated and trip command
initiated) has tripped.
All the elements expect unit 9 unit 10 & unit 11 were restored by 22:31 hrs. Unit 10 and
Unit 11 are restored on 07th April 2016 at 00:32hrs and 05:39 hrs respectively. Unit 9 was
restored on 09th April 2016 at 09:05hrs.
The report received from WRLDC is enclosed in annexure 2.17.
Committee may like to discuss.
2.18. Grid Incidence at 765/400 kV Vindhyachal pooling station on 13th August 2016
On 13th August 2016, at 12:18 Hrs, due to snapping of snapping of 400 kV
Sasan Vindhyachal R phase conductor (Top) and its contact with Y phase (Middle) conductor
has caused R-Y phase to phase fault on the line. With this, distance protection operated at Both
ends thus isolating the fault.
This phase to phase fault was sensed by 400 kV Vindhyachal PS-Sasan D/C and 400 kV
Vindhyachal PS- Vindhyachal IV D/C in zone 3 from the Vindhyachal PS end. The Phase to
Phase pickup for all the above four lines at Vindhyachal PS were assigned in group. This logic
was later modified and corrected as intimated by PGCIL WR-2.
During the event, there was no load/generation loss. All the lines were restored by
13:29hrs expect 400 kV Vindhyachal-Sasan which was restored on 14th August 2016, at
12:05hrs.
The report received from WRLDC is enclosed in annexure 2.18.
Committee may like to discuss.
2.19. Grid Incidence at Vindhyachal Generating station on 27th May 2016
On 27th May 2016, at 11:50 hrs the Bus Sectionalizer between 400 kV Bus-4 and 400 kV
Bus-6 at Vindhyachal Substation tripped along with bus section 4. It was observed that along
with this tripping, 400 kV Vindhyachal-Jabalpur 2, Vindhyachal -Satna 2, Vindhyachal-Korba,
400/132 kV ICT 1 and Unit 8 have tripped.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 12
The generation loss during the event was 487 MW due to tripping of Unit 8. Most of the
elements are restored by 13:53 hrs.
The report received from WRLDC is enclosed in annexure 2.19.
Committee may like to discuss.
2.20. Grid Incidence at 220/132 kV Badod on 19th May 2016
Prior to the event all the 220 and 132 kV elements were in service at 220/132 kV Badod
Sub-station. On 19th May 2016, at 23:12 Hrs, R phase line side CVT of 220 kV Badod-Nipaniya
circuit burst at Badod end. This led to tripping of all 220 kV elements like 220 kV Badod
Nipaniya, 160 MVA 220/132 kV ICT 1, 160 MVA 220/132 kV ICT 2, 220 kV Badod Sakatpur,
220 kV Badod Ujjain 1, 220 kV Badod Ujjain 2 on Bus bar protection from Badod sub-station.
This led to loss of 132 kV radial network in the Badod causing loss of 20 MW load.
Restoration started by taking Badod-Ujjain ckt 1 and 2 in service by 00:08 and 00:10 Hrs
respectively on 20 May 2016. After this other elements were restored.
WRLDC has noted that, this is the second event after 27th November 2015 where
bursting of line CVT resulted in Bus bar protection operation at Badod sub-station. It is
observed that the fault was on line CVT which should have been cleared by the line protection
however bus bar protection also operated. CT wiring for Bus bar protection at 220 kV Badod
needs to be checked in order to verify the correct operation of protection during the event. Also,
whether the line protection got blocked due to loss of CVT voltage (due to its damage) should
also be checked. Also, in such cases it is beneficial to have backup overcurrent protection logic
for line tripping which discussed in 126th PCM.
The report received from WRLDC is enclosed in annexure 2.20.
Committee may like to discuss.
2.21. Grid Incidence at 220/132 kV Birsinghpur (MPPTCL) Sub-station on 18th May 2016
At 220/132 kV Birsinghpur S/s, Double Main and Transfer Bus Scheme exists for 220
kV Bus. Bus Bar Protection for 220 kV sub-station was out of service. Further, the due to theft
of protection cable of 220 kV Birsinghpur-Jabalpur 2, its protection was out of service at 220 kV
Birsinghpur S/s (Report of MP SLDC).
220 kV Birsinghpur –Birsinghpur TPS Interconnector 1 was kept open from 220 kV
Birsinghpur S/s end since 11:31 Hrs. of 11.05.2016 due to High voltage. 220 kV Birsinghpur -
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 13
Birsinghpur Hydel circuit was also kept open from Birsinghpur HPS end. Remaining all 220 kV
and 132 kV feeders at Birsinghpur S/s were in charged condition and normally loaded.
220 kV Bus Coupler Breaker and 220 kV Bus Tie Breaker at 220 kV Birsinghpur S/s were out,
hence 200 kV Main Bus 1 and 220 kV Main Bus 2 have been made as Rigid Bus by closing the
Main Bus 1 and Main Bus 2 isolator of 220 KV Birsinghpur-Jabalpur 1 at 220 kV Birsinghpur
S/s. (Report of MP SLDC).
At 14:56 Hrs, due to R phase to earth fault on 220 KV Birsinghpur – Jabalpur 2 and its
line protection being out of service at Birsinghpur end has resulted in tripping of all the feeders
from Birsinghpur end on distance protection from remote ends. This has led to blackout of
220/132 kV Birsinghpur Sub-station along with radially fed 132 kV Umariya sub-station. Total
load loss during the event was 37 MW with energy unserved quantum of 21.58 MWHr.
First the 220 kV 220 kV Jabalpur – Birsinghpur 2 was charged to extend supply to 220
kV Birsinghpur followed by charging of 220/132 kV ICT. After this traction supply was
extended.
The report received from WRLDC is enclosed in annexure 2.21.
Committee may like to discuss.
2.22. Grid Incidence at 400 kV Indirasagar (ISP) power Plant on 4th June 2016
On 04th June 2016, at 12:15 Hrs, while transferring the 400 kV ISP-Nagda from 400 kV
Bus 2 to 400 kV Bus 1 at 400 kV ISP substation, the bus bar protection operated causing 400 kV
Bus 2 tripping and loss of all elements at 400 kV Indirasagar substation. This has led to complete
blackout of the substation.The exact details of the cause of Bus bar protection operation could
not be found in absence of DR/EL from the Indirasagar Substation.
Due to tripping of ISP Unit 6, generation loss of 100 MW occurred as observed from WRLDC
SCADA.
Supply at ISP was resumed by charging 400KV STPS – ISP Ckt at 13:42hrs.
Subsequently 400KV ISP- Indore Ckt II and 400KV ISP- Nagada Ckt were charged at 14:06 and
14:38 respectively, later units were synchronized.
The report received from WRLDC is enclosed in annexure 2.22.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 14
2.23. Grid Incidence at 400 kV Indirasagar (ISP) on 18th May 2016
Prior to the event as intimated by the event, All 400 kV Lines along with Unit 1 and 8
were in service from ISP. 400 kV ISP is having a Double Main Transfer Scheme Bus bar
arrangement. So, In order to create a balance 2 feeders and 4 units are kept on one bus at a time.
However, due to pantograph isolators issue the same could not be followed on various occasions.
As per the details given by SLDC it was observed that 400 kV ISP-Indore 1, 400 kV
ISP-Nagda and Unit 1 were on 400 kV Bus 1 while 400 kV ISP-Indore 2, 400 kV ISP-Satpura
and Unit 8 on 400 kV Bus 2. 400 kV Bus Coupler was in service. However the single diagram as
available in the WRLDC indicating that all the lines and units were on both the buses and the
bus coupler was out of service as it’s one of the isolator was in open condition. The single
diagram of the sub-station on 18 May 2015 at 02:15 Hrs. from WRLDC SCADA is shown in
figure 2 of Annexure 2.23, based on which WRLDC have made their analysis.
At 02:19 Hrs, 400 kV R phase CVT of 400 kV Bus 2 has burst resulting in the bus fault on
400 kV Bus 2. With this Bus bar protection has operated however with this all elements from
both the buses have been tripped which was not expected. The Fault as observed from the
Synchrophasor data at Dehgam which indicate the R phase fault which is cleared within the
time. Due to Static Bus bar at Indirasagar, DR is not available for bus bar operation. However
from the available DR of all the four lines it is observed that fault has cleared within 120 ms (All
DRs are attached as annexure however they are not time synchronized). Based on the available
details from DR, 400 kV ISP-Satpura & ISP-Nagda has Bus Bar operation along with DT send
to remote end while the 400 kV ISP-Indore 1 and 2 were having DT send command only at the
time of trip during the R phase fault.
This caused complete blackout of the sub-station along with generation loss of 215 MW.
After isolation of 400 kV Bus 2, 400 kV Bus 1 was charged by taking 400 kV ISP-Indore 2 at
03:30 Hrs. After this, other lines were taken in service followed by Unit 2 at 03:45 and Unit 7
04:15 Hrs.
The report received from WRLDC is enclosed in annexure 2.23.
Committee may like to discuss.
2.24. Grid Incidence at 400 kV JP Nigrie Sub-station on 14th April 2016
Prior to the incident, Both 400 kV JP Nigrie-Satna 1 & 2 along with JP Nigrie Unit 1 &
2 were in service. On 14th April 2016, At 13:29:37.409 Hrs: R Phase to E/F occurred on the 400
kV JP Nigrie-Satna 1 circuit which was in Zone 1 from Satna and Zone 2 from JP Nigrie. Both
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 15
ends issued the single phase tripping with carrier exchange. This fault was detected as Zone 4
(reverse zone fault) by the Satna end relay for circuit 2. (DR from both ends are attached as
annexure) Within 350 ms, direct trip for both circuit was received at Satna end from JP Nigrie.
Based on the DR it was observed that Tie CB of the 400 kV JP Nigrie-Satna 1 & 2 (these circuits
are in the same dia at JP Nigrie end) LBB has operated which was undesirable as there was no
breaker issue at JP Nigrie end. On further, analysis of disturbance it was observed that the LBB
timer for R phase of the Tie CB of these circuits at JP Nigrie end has initiated with the trip
command given from Main 1 protection and got reset as the breaker has successfully opened.
However, even after the reset , the LBB three phase trip has initiated which issued the
LBB protection operation and tripping command to both all breakers in the Dia (Main Breaker
of 400 kV JP Nigrie-Satna 1 & 2 circuits) at JP Nigrie end. Also, as per the LBB scheme, it has
sent the direct command to the remote end of the lines causing their tripping from the Satna end
along with JP Nigrie end. With these, the evacuation path of JP Nigrie units 1 & 2 each of
capacity 660 MW was lost resulting in their tripping. With these, Unit 1 and 2 at JP Nigrie also
tripped causing generation loss of 1089 MW.
After the event, restoration was started by charging of JP Nigrie Circuit 2 at 14:23 and
circuit 1 at 17:32Hrs. After this Unit 2 was synchronized at 18:03 Hrs and Unit 1 at 19:03 Hrs.
The report received from WRLDC is enclosed in annexure 2.24.
Committee may like to discuss.
2.25. Grid Incidence at 400 kV JP Nigrie Sub-station on 1st May 2016
Prior to the incident, Both 400 kV JP Nigrie-Satna 1 & 2 along with JP Nigrie Unit 1 &
2 were in service. On 01st May 2016, at 12:24Hrs. R Phase to E/F occurred on the 400 kV JP
Nigrie-Satna 1 circuit which was in Zone 1 from Satna and Zone 2 from JP Nigrie. Both ends
issued the single phase trip with carrier code exchange (DR from both ends are attached as
annexure 2.24). The fault current from Satna was 12.9 kA while from JP Nigrie it was 3.17 kA.
Within the next 350 ms, direct trip for both circuit was received at Satna end from JP Nigrie.
At the same time, LBB protection of the Tie Circuit breaker of JP-Nigrie-Satna 1 & 2 at
JP Nigrie end has operated resulting in tripping of Main Breakers and sent the direct trip code to
remote end Satna sub-station. This led to tripping of both lines from Satna end. With the tripping
of these lines, the JP Nigrie has suffered complete blackout of substation as it is connected to
Indian grid via these two lines. With these, Unit 1 and 2 at JP Nigrie also tripped causing
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 16
generation loss of 1092 MW. Due to Loss of generation frequency dropped from 50.032 Hz to
49.900 Hz (drop by 0.132 Hz)
After the event, restoration process was started by charging of JP Nigrie Circuit 2 at
12:55 and circuit 1 at 19:46 Hrs. Further, Unit 1 was synchronized at 16:17 Hrs and Unit 2 at
20:01 Hrs. Further, Based on the submitted DR it was observed that this incident is the repetition
of the GD-1 event at this station which occurred on 14th April 2016.
The report received from WRLDC is enclosed in annexure 2.25.
Committee may like to discuss.
2.26. Grid Incidence at 400 kV JP Nigrie Sub-station on 02nd September 2016
Prior to the event, all the elements from JP Nigrie were in service. On 02nd September
2016, at 16:04 Hrs, Y phase to Earth fault occurred on 400 kV J P Nigrie-Satna 1 & 2 in zone 1
from both ends. Line After tripping Y phase went for A/R cycle and taken attempt after one
second. During this, fault persisted on circuit 1 which tripped immediately while circuit 2 got
successfully reclosed. However, during A/R instant of Y phase on circuits, both units got tripped
on under voltage trip alarm.With the tripping of both units of JP Nigrie, there was a generation
loss of 1051 MW. As 400 kV JP Nigrie-Satna 2 circuit was in service so immediate restoration
activity of system has started. It can be seen that by 18:57 complete system has been restored
along with the both units.
In this event, simultaneous transient fault was observed on both the lines out of which
one has reclosed and other tripped due to persisting fault respectively. The reason for the
simultaneous fault on the line has not been provided by the utility. Such kind of events are rare
and need a detailed analysis to find the root cause so that remedial action can be taken in
advance. Also it was observed that during the A/R occurring on both lines, JP Nigrie both units
have tripped on under voltage protection. Further, It was observed that 128 ms drift has been
observed in JP Nigrie end DR for transmission lines. While the generating Units DR and event
logger are way out of time synchronization by more than 2-3 minutes.
JP Nigrie should time synchronize their DR and event logger. The cause of under
voltage, Unit protection setting etc. should be checked by JP Nigrie.
The report received from WRLDC is enclosed in annexure 2.26.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 17
2.27. Grid Incidence at 400 kV JP Nigrie Sub-station on 03rd May 2016
Prior to the incident, Both 400 kV JP Nigrie-Satna 1 & 2 along with JP Nigrie Unit 1 &
2 were in service. On 03rd May 2016, at 21:07hrs. R phase to earth fault occurred 400 kV JP
Nigrie –Satna 2 circuit. Both ends have issued the single phase trip for A/R. With this the flow in
other circuit increased and from Satna end the Zone 3 picked up. After 1 second the circuit 1 got
tripped from Satna end on Zone 3 protection. While A/R operated successfully at JP Nigrie end
after 1.2 second while no reclosure occurred at Satna end. With this generator at JP Nigrie was
connected with only two phases with the grid and after 300 ms fault reappeared and circuit
tripped. With tripping of both lines, JP Nigrie generator isolated from the system and tripped
causing loss of 1211 MW of generation.
JP Nigrie has charged the circuit 1 immediately as it was in charged condition from
Satna end. After this Unit 1 and 2 were synchronized at 002:48 and 00:08 Hrs respectively. Line
2 was taken in service at 09:02 Hrs.
This is the third time in recent months when complete blackout of the JP Nigrie sub-
station has occurred and in three cases loss of generation is more than 1000 MW. The frequency
of the grid has dropped by more than 0.13 Hz in the three occasions. These events need to be
reviewed immediately from the system reliability and security point of view.
JP Nigrie is advised to check all the three incidents in detail and perform the root cause
analysis and present the same in PCM.
The report received from WRLDC is enclosed in annexure 2.27.
Committee may like to discuss.
2.28. Grid Incidence at 400 kV JP Nigrie Sub-station on 22nd June 2016
Prior to the incident, Both 400 kV JP Nigrie-Satna 1 & 2 along with JP Nigrie Unit 1 &
2 were in service. On 22nd June 2016, at 13:18hrs, R phase to earth fault occurred on the 400 kV
JP Nigrie-Satna 2 circuit at around 56 km from Satna end. Both ends relays have tripped the line
in carrier aided zone 1 protection with which its R phase pole got opened. Zone 3 started in 400
kV JP Nigrie Satna 1 circuit at JP Nigrie end due to increased loading on this circuit. After
around 332 ms (13:18:14.025) Zone 2 also pickup in this circuit and within next 105 ms
(13:18:14.130) the circuit has tripped from JP Nigrie end. The reason for this tripping could not
be ascertained from the submitted DR from JP Nigrie end. This led to the shifting of complete
1246 MW on the Y & B healthy phases of 400 kV JP Nigrie-Satna 2 circuit with which power
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 18
swing started in the circuit with current reaching to 3.5 kA in phases. At 13:18:27.154: DT was
received at Satna end on 400 kV JP-Nigrie-Satna 1 circuit causing its tripping.
This led to islanding of JP Nigrie from the grid however, AVR of Units responded and
the voltage was held constant and line reclosed from JP Nigrie end. However, both units got
tripped on over speed/over frequency due to system islanding from the grid. Generation loss due
to JP Nigrie Unit 1 and 2 tripping was 1246 MW.
Restoration was immediately started by taking 400 kV JP-Nigrie-Satna 1 is service
which was in charged condition from Satna at 13:21. While the circuit 2 was taken in service at
15:51 Hrs. This was followed by taking Unit 1 and Unit 2 synchronization at 16:06 and 16:18
Hrs respectively.
The report received from WRLDC is enclosed in annexure 2.28.
Committee may like to discuss.
2.29. Grid Incidence at 220/132 kV Malanpur Sub-station on 7th April 2016
220 kV Malanpur Bus is having a single main transfer bus scheme. Prior to the event,
All 220 kV and 132 kV elements from Malanpur were in charged condition and loaded within
permissible limit. 220 kV Malanpur-Gwalior (PG) 2 circuit was charged through 220 kV Bus
coupler breaker 2 since 14:51 Hrs of 04-04-15 due to over howling of its main breaker at
Malanpur end.
On 7th April 2016, at 20:30 Hrs, R phase CT (SCT make) of 220 kV Malanpur-Gwalior(PG)
1 at Malanpur end which was charged through the bus coupler breaker 2 burst causing bus fault
in the system resulting in Bua bar protection for Zone 1 and Zone 4 operation and tripping of all
220 lines and 220/132 kV ICTs. With these blackout occurred in the 220/132 kV Malanpur and
radial connected 132 kV Ambha, Bhanmore, Morena, Morara, Badgaon sub-stations.
Supply at 132 KV S/s Banmore was resumed by charging 132 KV Banmore – Motijheel Ckt
– II at 22:39 Hrs, 132 KV Supply at 220KV S/s Malanpur was resumed by charging 132 KV
Malanpur – Mehgaon Ckt at 22:40 Hrs. subsequently supply was extended to interrupted ares by
charging respective transformers and feeders.
The report received from WRLDC is enclosed in annexure 2.29.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 19
2.30. Grid Incidence at 400 kV MB Power on 25th May 2016
Prior to the event, Unit 2 of MB power was out due to flame failure since 16 May 2016.
There were heavy rain and thunderstorm reported in the Anupur.
At 09:14 Hrs, R phase to E/F occurred on 400 kV MB Power-Jabalpur PS 2 circuit and it
tripped on Distance protection. (DR attached as annexure 2.30). After this at 14:28 Hrs, Due to
lightening on the bus reactor at MB Power, its R and Y phase lightning arrester and isolator got
damaged and with this bus reactor differential protection operated. However, the Main 2
protection of Line 1 at MB power end also operated for Zone 4 fault in zone 1 resulting in
tripping of this circuit resulting in islanding of MB power station from the grid. With this, Unit 1
of MB power tripped with TURBINE tripping of over speed protection and with this sub-station
got blackout.
Net generation loss due to tripping of the Unit 1 was 477 MW. Most of the elements are
restored by 17:03hrs, the unit 1 was taken into service on 26th May 2016 at 17:24hrs.
The report received from WRLDC is enclosed in annexure 2.30.
Committee may like to discuss.
2.31. Grid Incidence at 400 kV MB Power on 30th April 2016
Prior to the event, Bad weather with high wind were prevailing at the MB Power Sub-
station. 125 MVAR bus reactor was out of service at the MB power sub-station resulting in
opening of 407 and 408 CB. This has resulted in MB power Unit 2 connection to the Main Bus 1
through only one CB i.e. 407 CB as it is in same diameter of the bus reactor.
On 30th April 2016, at 15:01:43.841 Hrs, B Phase Bus side isolator of GT 2 got opened
due to wind resulting in Bus fault due to arcing as it came in induction zone of the Y phase. With
this, Bus bar protection Zone 1 operated which resulted in tripping of Main Bus 1 and all
connected Main bus breaker ( Breaker 403,406 and 409). This resulted in isolation of the fault
within 60 ms. (DR is attached as annexure 2.31). Due to this MB power Unit 2 has tripped.
While the Unit 1, ST, 400 kV Jabalpur PS-MB Power 1 & 2 circuit remain in service with
Healthy 400 kV Bus 2 at MB power.
At 15:01:43.853 Hrs, The Fault was also seen by the 400 kV Jabalpur PS-MB Power 1
& 2 circuit from Jabalpur PS end in zone 2. However both circuit has issued three phase trip to
the circuit. This has resulted in Islanding of the MB Power Unit 1 from the grid. There is no
house load operation scheme in operation at The MB Power station at present otherwise unit
could have gone to House load of 83 MW (Aux consumption) and survived. The loss of
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 20
connectivity to the grid was seen as load throw off by the islanded system of Unit 1 with aux
consumption load and 400 kV charged lines losses which resulted in increase in the island
frequency (MB Power station) causing over speeding of Generating unit 1.
At 15:01:45.743 Hrs, Unit 1 tripped on over frequency at 56.2 Hz. With this complete
blackout occurred at MB power. At 15:39 Hrs, 400 kV Jabalpur PS- MB Power 1 circuit was
taken in service. However, due to isolator opening of B phase isolator of the line reactor of 400
kV Jabalpur PS- MB Power 1 circuit at MB Power end, Y-B phase fault occurred causing line
tripping. With this again blackout occurred at station. Total loss of generation with tripping of
both Units of MB power was 1025 MW.
Restoration started by checking of all the isolators in the yard at MB Power as two
isolators have got opened during the event. First at 18:28 Hrs, 400 kV Jabalpur PS-MB Power 2
was charged follwed by 400 kV bus 2 at MB power. 400 kV MB power Bus 1 was charged at
20:15 Hrs followed by charging of ckt 1 at 22:08 Hrs. Units 1 & 2 were then taken subsequently
into service on 01st May 2016 at 15:26 hrs and 01:05 hrs respectively.
The report received from WRLDC is enclosed in annexure 2.31.
Committee may like to discuss.
2.32. Grid Incidence at 400 kV MB Power on 30th August 2016
Prior to the event, System was in normal state with 400 kV MB Power-Jabalpur PS both
lines in service along with MB power Unit 1. Unit 1 was generating 455 MW prior to the event.
On 30th August 2016, at 08:08:18.347 hrs, 400 kV MB Power-Jabalpur PS circuit 2 tripped
from Jabalpur PS end on direct trip receipt command. At 08:08:18.801hrs, 400 kV MB Power-
Jabalpur PS circuit 1 tripped from Jabalpur PS end on Direct trip receipt command. This caused
islanding of MB power system and MB power Unit 1 responded with forced AVR response.
However due to hanging lines, the voltage started picking up with no load condition for units. At
08:18:19:421hrs, 400 kV MB Power-Jabalpur PS circuit 1 tripped from MP Power end on Direct
trip receipt command. Over Voltage stage 2 operated at Jabalpur PS. At 08:18:19:446hrs, 400
kV MB Power-Jabalpur PS circuit 1 tripped from MP Power end on Direct trip receipt
command. Over Voltage stage 2 operated at Jabalpur PS as well as MB power PS. MB Power
Unit 1 thereafter tripped on over frequency. Generation loss quantum during the event MB
Power Unit 1 was 455 MW.
The restoration in the MB power case was quite delayed as Jabalpur PS end was getting
continuous carrier signal at their end. Finally, after clarification from PGCIL Jabalpur and MB
power on 1st September 2016, 400 MB Power-Jabalpur PS 1 was charged at 10:45 Hrs and
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 21
circuit 2 at 10:49 Hrs. MB power Unit 1 was synchronized at 18:01 hrs however it tripped on
turbine tripping at 18:14 Hrs. Further, it was synchronized at 18:45 Hrs.
Further, it was observed that on 8th Sept 2016 at 15:53 Hrs, 400 kV MB Power-Jabalpur PS 2
circuit tripped from MB power end on receipt of direct trip from PGCIL end. PGCIL has
informed that they are looking into the issue with this event however so far no details have been
received
The report received from WRLDC is enclosed in annexure 2.32.
Committee may like to discuss.
2.33. Grid Incidence at 220/132 kV Mehgaon Sub-station on 4th April 2016
220/132 kV Mehgaon is having a single main and auxiliary bus scheme at 220 & 132 kV
level. At 01:05 Hrs, Y Phase CT of 220 kV Malanpur-Mehgaon line at Mehgaon end burst
resulting in Bus fault at Mehagon S/s. This led to Bus bar protection operation and tripping of
220kV Mehgaon-Auraiya line and the 220/132 kV ICTs. With this blackout at Mehgaon
occurred resulting in load loss of 70 MW and energy unserved quantum of 23.33 MWHr.
The restoration of load was taken up immediately by taking 132 kV Malanpur-Mehgaon
circuit at 01:25 Hrs which is in general kept out. After this at 02:26 Hrs, Mehgaon-Auraiya was
taken in service thus 220/132 kV ICT 1 & 2 came into load.
The report received from WRLDC is enclosed in annexure 2.33.
Committee may like to discuss.
2.34. Grid Incidence at 220/132 kV Mehgaon Sub-station on 29th August 2016
Prior to the incident, the 220 kV Mehgaon-Malanpur S/C was out since 28th August 2016
from 21:19 Hrs on R phase to earth fault. Line could not be restored due to persisting nature of
the fault. Now the Mehgaon system was being fed from 220/132 kV Mehgaon substation and its
radial system was being fed from 220 kV Mehgaon-Auraiya and 132 kV Mehgaon-Malanpur
circuit.
On 29th August 2016 at 01:27 hrs, the 220 kV Mehgaon-Auraiya circuit tripped from bus
fault at Auraiya end causing the shifting for complete load of 220/132 kV Mehgaon and its redial
connected sub-station on 132 kV Mehgaon-Malanpur circuit which also tripped on overcurrent
protection. With this, in absence of any source feeder at Mehgaon, Substation along with radial
connected 132 kV Stations got dark out.
Load loss in tune of 122 MW has occurred during the event. The Energy unserved
quantum during the event calculated based on the loss was around 708.67 MWhr.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 22
Restoration was initiated by charging 132 kV Mehgaon-Malanpur and taking around 87
MW of the load. In the morning the 220 kV Mehgaon-Malanpur was restored and rest of the
loads was taken in service.
The report received from WRLDC is enclosed in annexure 2.34.
Committee may like to discuss.
2.35. Grid Incidence at 220/132 kV Pandhurna substation on 6th June 2016
Prior to the event there was rainfall and wind at 220/132 kV Pandhurna sub-station. At
15:57 Hrs, its 220 kV Bus main bus B phase flyover jumper post insulator broke down causing
the jumper to swing. This led to the bus fault however, all the 220 and 132 kV tripped from the
remote end protection. This caused blackout at 220/132 KV Pandhurna Substation and loss of
around 50 MW. The energy unserved quantum during the event was 25 MWHr. Most of the
elements are restored by 16:55hrs.
The report received from WRLDC is enclosed in annexure 2.35.
Committee may like to discuss.
2.36. Grid Incidence at 220 kV Rewa, Siddhi and nearby Area on 4th August 2016
On 04th August 2016, at 12:04 Hrs, 220 kV Birsinghpur (SGTPS)- Rewa Circuit tripped
on transient fault from both ends. Simultaneously 132 kV Amarpatan-Maihar circuit also tripped
due to overloading. Consequently the complete load of 220 kV Rewa & 220 kV Sidhi substation
got shifted on 220 kV Amarkantak-Sidhi Circuit, resulting in its over loading and tripping at
12:16 Hrs.
Due to the above tripping interruption occurred in following areas due to non-
availability of any other supply source: 220 kV Rewa, 220 kV Sidhi, 132 kV Rewa,132 kV
Sidhi, 132 kV Deosar, 132 kV Mauganj,132 kV Katra,132 kV Mangawan,132 kV Rewa II
(Sagra/Paharia), 132 kV Rampur Naikin, 132 kV Beohari,132 kV Amarpatan, Jhinna HPS,
Silpara HPS, Devlond HPS,220 KV Hindalco (Industry) substations.
This led to 240 MW load and energy unserved quantum of 97.91 MWHr. Most of the
elements were restored by 13:08hrs. 220 kV Satna – Satna (PGCIL) Interconnector – II was
charged at 13:31 Hrs after attending the hot point. Thereafter 220 kV Rewa – Tons Ckt – I was
charged at 13:58 Hrs.
The report received from WRLDC is enclosed in annexure 2.36.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 23
2.37. Grid Incidence at Tons HPS on 23rd May 2016
On 23rd May 2016, at 14:50 Hrs, due to falling of lighting cable of switchyard lighting
on 220 kV Main Bus 2 and its earthing through the structure at 220 kV Tons has led to Bus fault
at Tons. The event occurred due to heavy rainfall and wind. The bus fault caused tripping of all
elements from tons and blackout at the Tons hydel power station. During the event, Unit 1of
Tons tripped causing 105 MW loss of generation.
Supply at Tons HPS was resumed by charging 220KV Tons-Rewa Ckt I at 17:38hrs.
Subsequently rests of the elements were restored thereafter.
The report received from WRLDC is enclosed in annexure 2.37.
Committee may like to discuss.
2.38. Grid Incidence at HPS-Rewa and Siddhi on 25th May 2016
Prior to the event, multiple 220 kV lines were out in the area due to tower collapse during
the heavy rainfall and wind. During these time 220/132 kV Rewa and Siddhi substations were
radially fed from 220 kV Tons substations through 220 kV Tons-Rewa D/C.220 kV Bus 2 of
Tons having a double main transfer bus scheme was under outage. Therefore at Tons all
elements were connected to 220 kV Bus 1.
On 25th May 2016, At 11:59 Hrs, B Phase to E/F occurred on 220 kV Satna-Kotar circuit
during heavy rainfall and wind. With this 220 kV Satna-Kotar along with 220 kV Tons-Kotar
circuit tripped. However, with the opening of 220 kV Tons-Kotar circuit at Tons substation, its
LBB has operated resulting in tripping of 220 kV Bus 1 (Bus 2 under outage) along with all
connected element outage at Tons. During this time, 220/132 kV Rewa and Siddhi substations
were being radially fed from 220 kV Tones-Rewa D/C, their tripping from tons has caused the
blackout of 220/132 kV Rewa and Siddhi substations and associated 132 kV substations at lower
voltage level. With this, 128 MW load was lost in the area with energy unserved quantum of
85.33 MWHr.
Supply at Tons HPS was resumed by charging 220KV Tons-Satna Ckt at 12:24hrs.
Thereafter supply was extended to 220KV S/s Rewa by charging 220KV Tons-Rewa Ckt at
12:29hrs. Subsequently rests of the elements were restored thereafter.
The report received from WRLDC is enclosed in annexure 2.38.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 24
C. OCCURANCES IN MAHARASHTRA SYSTEM
2.39. Grid Incidence at 400 kV & HVDC Bhadrawati Sub-station on 4th May 2016
On 04th May 2016, at 19:16 Hrs : B Phase to Earth fault occurred in 400 kV Bhadrawati-
Ramagundam 1 and it auto reclosed at Bhadrawati end but did not auto-reclose at Ramagundam
end. Within 10 seconds the line tripped from Bhadrawati end also due to direct trip received
from Ramagundam end. The direct trip may be due to open end of line causing overvoltage
protection at Ramagundam end. Now, HVDC Bhadrawati Pole-1 & 2 were carrying 700 MW in
west to south direction with 400 kV Bhadrawati - Ramagundam 2 line in service.
At 19:26 Hrs. 400 kV Bhadrawati-Ramagundam 2 also tripped on B phase to earth fault.
As per the auto-reclosure scheme it did not operate and subsequently, due to AC under voltage
on South Bus, both the Poles tripped on "GROUND FAULT" & "DC>AC" alarms. This resulted
in sudden change in power flow of A/C interconnection to southern grid i.e. 765 kV Solapur-
Raichur 1 & 2 and 400 kV Kolhapur-Narendra D/C.
Restoration was carried out at 20:21 Hrs, 400 kV Bhadrawati-Ramagundam 1 line was
charged thereby energizing South Bus bar of HVDC Bhadrawati S/s. After this an attempt was
made to deblock HVDC Pole-2 but the pole failed to deblock due to “RPC request to standby
“signal from Reactive power Control(RPC).
Meanwhile, on 05.05.2016 at 01:59 Hrs, Ramagundam-1 line tripped on over voltage
protection operation at Bhadrawati end. Line was taken back into service at 02:59 Hrs. The filter
availability was made available to RPC by resetting the power supply units and processor cards
in RPC and both the Poles were normalized on 05/05/2016 at 04:40Hrs & 03:40Hrs respectively.
400 kV Bhadrawati-Ramagundam 2 could be taken in service immediately as when the charging
attempt was made from Ramagundam end on 05.05.2016 at 05:30 Hrs the line has tripped on
operation of SOTF protection. After rectification work completion, it was taken on 5th May
2016 at 21:33 Hrs.
The report received from WRLDC is enclosed in annexure 2.39.
Committee may like to discuss.
2.40. Grid Incidence at 400/220 kV Dhule Sub-station on 28th May and 14 July 2016
There were two incidents of RADSS Bus Bar scheme Mal-operation for 400 kV Bus at
400/220 kV Dhule Sub-station of MSETCL. The First incident occurred on 28th May 2016 at
08:46 Hrs where the 400KV Bus Bar protection operated in zone – A. At that time there was no
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 25
actual bus fault or any external fault too. Also at that time no yard operation is going on. The bus
bar scheme is RADSS. Only U flag indication is available i.e. tripping flag, also there was no
phase indication this implies the bus bar mal operation. The bus bar operation causes tripping of
all 400 KV Bus 1 connected elements. The mal operation is due to carbonization of R-ph & Y-
ph of RQDA module. This is cleaned up and all the elements are taken into service by 11:44hrs
and normalcy restored in the system.
The second incident is on 14th July 2016 at 21:08 Hrs, where the 400KV Bus Bar
protection operated in zone – B. At that time there was no actual bus fault or any external fault
too. Also at that time no yard operation is going on. The bus bar scheme is RADSS. Only U flag
indication is available i.e. tripping flag, also there was no phase indication this implies the bus
bar mal operation. The bus bar operation causes tripping of all 400 KV Bus 1 connected
elements. The mal operation is due to carbonization of R-ph, Y-ph & B-ph at SR/DR card of
RQDA module. This is cleaned up and all the elements are taken into service by 23:44hrs and
normalcy restored in the system.
The report received from WRLDC is enclosed in annexure 2.40.
Committee may like to discuss.
2.41. Grid Incidence at 400/220 kV Karad Substation on 12th April 2016
Prior to the event the voltage of 400 kV Karad bus was 424 kV and Kolhapur 416 kV. In
order to control the voltage during evening and night off peak hour, the 400 kV Karad-Kolhapur
1 circuit was being opened at 16:38 Hrs. Line got opened successfully however, after 274 ms the
external flashover on the R phase breaker pole was observed at Karad end. The arcing persisted
for around 15 seconds and after this pole got burst creating a bus fault in the system. (DR from
Karad end is attached as annexure 2.41) With this 400 kV Bus bar protection for Zone 1 has
operated resulting in tripping of all 400 kV elements from Karad end along with the bus coupler.
During the event, there was no load/generation loss as the 400 kV Bus 2 and remaining lines
from Karad were in service.
This case is similar to the event which occurred on 28th August 2015 when the 400 kV
Karad-Kolhapur 1 circuit was opened with Karad voltage above 424 kV causing bursting of R
phase pole of the circuit breaker and Bus fault on the 400 kV Bus 1 at Karad.
The report received from WRLDC is enclosed in annexure 2.41.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 26
2.42. Grid Incidence at 400/220 kV Kolhapur on 13th May 2016
Prior to the event there were heavy rain, storm and lightening at the Kolhapur Sub-
station. On 12th April 2016, at 15:59 Hrs, the B phase CT of 400 kV Kolhapur-Kolhapur GIS
circuit 2 at Kolhapur end observed flashover on its surface. This led to Bus fault on the line as
well as its Line fault observed from both end of the line. The circuit was connected on 400 kV
Bus 2 at Kolhapur end so accordingly Bus bar protection operated and tripped all 400 kV
connected elements.
However, there was no load/generation loss as other circuit and ICTs has managed the
load along with the 220 kV networks. After analysis it was found that flashover has occurred
over the CT and with the cleaning of the CT, its C, Tanδ, IR were found within the limit. After
that, it was charged from Kolhapur GIS end however due to hissing sound, corona ring for the
CT was changed. With this line was successfully charged on 14th May 2016, at 22:29hrs.
The report received from WRLDC is enclosed in annexure 2.42.
Committee may like to discuss.
2.43. Grid Incidence at 400/220 kV Nagothane Substation on 30th September 2016
On 30th September 2016, at 18: 05 hrs, R Phase IPS tube between ‘C’ bus isolator to
line isolator for 400 kV Nagothane-RGPPL 1 circuit got disconnected from Clamp at Nagothane
end disconnected from creating bus fault on 400 kV Bus 2 at Nagothane. With this 400 kV Bus 2
bus bar protection operated resulting in tripping of 400 kV Bus 2 along with all connected
lines/ICT and Bus coupler.
The 400KV main bus –II is charged by taking 400KV bus coupler into service at
18:40hrs and thereafter ICT – III and 400KV Padghe-II were taken into service at 18:42hrs &
20:11hrs respectively.
The report received from WRLDC is enclosed in annexure 2.43.
Committee may like to discuss.
2.44. Grid Occurrence at 400/220/100 kV Padghe and HVDC Padghe S/s on 28th April 2016
On 28th April 2016, aat 15:55 Hrs, 50 MVA 220/22 kV BHEL make transformer 220 kV
side Y-phase stub bus (jack bus) suspension string insulator got decapped and fell on gantry
which created the 220 kV main bus 2 (Bus Zone 2) fault at 400/220 kV Padghe s/s. The 50
MVA, 220/22 kV BHEL TF is connected to 220 kV main bus 2 from 220 kV side and all lines,
ICTs, Transformers connected to 220 kV main bus 2 tripped on bus bar protection.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 27
With this 220 kV Padghe –Nalasopara feeder along with 400/220/33 kV ICT 2 & 3
which were on 220 kV main bus 2 also tripped. Due to this the radial load of about 135 MW of
220 kV Nalasopara s/s got completely disconnected.
The 33 kV Auxiliary of HVDC Padghe was being fed through 33 kV Supply of
400/220/33 kV ICT 3 and 220/22 kV transformer and during the event both got tripped. Due to
loss of auxiliary supply and non-sustaining of load on the UPS-battery bank system and issues
with Diesel generators, both poles of HVDC Chandrapur-Padghe at Padghe got tripped. The
total bipole load prior to tripping was about 1400 MW. This led to increase in the loading of
parallel AC corridors.
As the 400/220/33 kV ICT 2 & 3 also tripped during bus fault, the ICT 1 and 4 got overloaded
resulting in load trimming scheme stage-1 operation causing load loss of 328 MW.
After isolating fault, 220KV bus coupler was charged at 16:26 hrs and the rest of the
elements are charged one after other by 17:53hrs expect 50MVA 220/22KV BHEL transformer,
which was restored at 19:58hrs after replacing the suspension insulator string.
The report received from WRLDC is enclosed in annexure 2.44.
Committee may like to discuss.
2.45. Grid Incidence at 765/400 kV Pune GIS sub-station on 11th may 2016
Prior to the event all lines and ICTs were in service at 765/400 kV Pune GIS Sub-station
and Bad weather condition (Wind and Rain) was prevailing near to Pune. On 11th May 2016, at
18:42 Hrs, 400 kV Pune-Pune GIS 2 circuit got tripped on Y phase to Earth fault, which was on
400 kV Bus 1 at Pune GIS.
After this, at 18:52 Hrs 400 kV Pune-Pune GIS 1 circuit tripped on Y phase to earth
fault which was on 400 kV Bus 2 at Pune GIS S/s. However, simultaneously 400 kV elements
from 400 kV Pune GIS also tripped on 400 kV Bus Bar protection for Bus 1. There was no
load/generation loss during the event.
Immediately restoration procedure was started by WRLDC with coordination of PGCIL
WR-1. And situation was made normal by 22:07 Hrs. The delay in restoration was due to
unknown reason for the tripping of Bus 1 at 765/400 kV Pune GIS S/s.
PGCIL may give the reasons for tripping of Bus 1 at 765/400KV Pune GIS S/s.
The report received from WRLDC is enclosed in annexure 2.45.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 28
2.46. Grid Incidence due to tripping of 765 kV Sholapur-Raichur 1 & 2 on 18th May 2016
On 18th May 2016, during heavy rain, the 765 kV Sholpaur-Raichur 2 tripped at 16:56
Hrs. and 765 kV Sholpaur-Raihcur 1 at 16:57 Hrs. This resulted in interconnection of Southern
Grid via only 400 kV Kolhapur-Kudgi D/C circuit with NEW grid which is a longer path for
interconnection. Immediate steps were taken to restore these lines however, in view of WRLDC
for that the standing phase angle between 765 kV Sholapur and 765 kV Raichur has to be less
than 5 degrees. As the operator were taking action in this regard by increasing the generation in
southern region by HVDC power flow increment, there was sudden load throw off in Northern
region at 17:32 Hrs. due to Phase to phase fault near load center.
This has led to sudden increase in change of power flow and angle across Raichur-
Sholapur which crossed 72 degree and due to which synchronization of lines through auto
synchronization facility got delayed. However, the load restored quickly within 6 minutes and
angular separation of 765 kV Sholapur and Raichur reduced below 5 degree resulting in
restoration of circuits. During the event no SPS has operated in the grid.
The report received from WRLDC is enclosed in annexure 2.46.
Committee may like to discuss.
2.47. Grid Incidence due to tripping of 765kV Wardha-Aurangabad 1, 2, 4 on 6th May 2016
On 6th May 2016, at 18:01 hrs, 765 kV Wardha-Aurangabad 1 tripped on Y-B phase to
earth fault. After this at 18:18 hrs, 765 kV Wardha-Aurangabad 2 also tripped on B Phase to
earth fault. During this period the 765 kV Wardha-Aurangabad 3 was out for controlling high
voltage. At 18:32 Hrs, while attempting the trial charging of 765 kV Wardha-Aurangabad 1, 765
kV Wardha-Aurangabad 4 circuit also got tripped from Aurangabad end. With this all four lines
between 765 kV Wardha and 765 kV Aurangabad were not in service resulting in rush of power
on the parallel 400 kV circuits.
At 18:37 Hrs, the circuit breaker at Aurangabad end was closed by the operator and the
circuit came into service. After this circuit 3 was taken back in service at 19:29 Hrs. However,
765 kV Aurangabad-Wardha 1 & 2 could not hold and patrolling instruction was given. During
the event, there was no load/generation loss.
The report received from WRLDC is enclosed in annexure 2.47.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 29
2.48. Grid Incidence at 220/132 kV Miraj Sub-station, Maharashtra on 18th May 2016
On 18th May 2016, at 03:31 Hrs, B phase (SCT Make) PT of 220 kV Bus of 220/132 kV
Miraj sub-station got burst resulting in bus fault and tripping of all the elements from the Miraj
sub-station. This resulted in the blackout of Miraj and nearby area. Total load loss during the
event was 196 MW and quantum of energy unserved 529.2 MWHrs.
After isolating the 220 KV PT, normalcy was restored. The failed PT is replaced with
spare Mehru make PT on 19th May 2016.
MSETCL may kindly be seen that in November 2015, R phase PT has burst at the Miraj
Sub-station. Prior to that CT failure also occurred in Miraj in one of the line in October 2015.
MSETCL may analyze this and submit the details to WRLDC/WRPC.
The report received from WRLDC is enclosed in annexure 2.48.
Committee may like to discuss.
2.49. Grid Incidence at 400 kV Mouda Sub-station on 5th May 2016
On 5th May 2016, at 18:53 hrs, 400 kV Mouda-Wardha 2 tripped on B phase to earth
fault at a location of 11.5 km from Wardha end. At 19:00 Hrs, 400 kV Mouda-Wardha 2 line
also tripped on R-B Phase to Phase fault at location of 18.5 km from Wardha end. Tripping of
both the lines resulted in isolation of Mouda from the grid and its blackout. With this Mouda 1 &
2 unit tripped and resulted in 555 MW of generation loss.
400 kV Mouda-Wardha 2 & 400 kV Mouda-Wardha 1 were restored on 5th May 2016, at
19:26hrs & 19:49hrs respectively. Mouda Unit 2 was restored on 06th May 2016 at 04:15 hrs.
Mouda Unit 1 was restored on 07th May 2016 at 07:35 hrs.
The report received from WRLDC is enclosed in annexure 2.49.
Committee may like to discuss.
2.50. Grid Incidence at 400 kV Kalwa Sub-station on 12th August 2016
Prior to the event, outage was approved for PMU works on the 400 kV Kalwa-Padghe 2
circuit. On 12th August 2016, at 09:28 Hrs, while the hand trip command was given to this line
from Kalwa, its Y phase pole got stuck and remaining poles tripped from Kalwa end. The line
has also tripped from Padghe end on receipt of direct trip due to hand trip command.
Now as per the procedure, the operator should have isolated the faulty section of the
breaker by taking Bus 1 outage and opening of the isolators associated with the lines. However,
the operator has initiated the Bus isolator opening for the feeder while the Y phase remained in
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 30
service. Due to this as the Y Phase Isolator was opened at 09:40 Hrs, heavy arcing observed on
Y phase PG isolator & arc remained continued.
Further, due to heavy winds the arc got shifted towards adjacent R phase creating R-Y
phase to phase bus fault at Kalwa s/s. Due to the heavy arcing due to line charging current of 400
kV Kalwa – Padghe line (line length is about 54 km) bus fault has occurred at Kalwa s/s. This
has resulted into operation of bus bar protection relay for 400 kV Bus 1 and tripping of
associated elements.
During the event, there was no load or generation loss. Bus Coupler and 400 kV Bus 1 at
Kalwa were restored at 10:19hrs. 400 kV Kalwa-Pune was restored at 10:38hrs. 400/220 kV ICT
was restored at 2 10:50hrs. 400 kV Kalwa-Khargar was restored at 13:38hrs.
The report received from WRLDC is enclosed in annexure 2.50.
Committee may like to discuss.
2.51. Grid Incidence at 400/220 kV Kolhapur S/S causing blackout of 400 kV Kolhapur
GIS, 400/220 kV Mapusa, 220 kV Mumewadi, Halkarni substations along with 220/132 kV
Goa System connected with Western Regional Grid
On 17th September 2016, High voltage scenario was prevailing in Southern Maharashtra
and Goa system during the off peak hours. In view of this, various 400 and 765 kV lines were
kept open prior to the event in the area to control the over voltage. Even then the voltages were
not in the limits and voltages of all 400 kV Nodes and 765 kV nodes in Southern Maharashtra
remain outside the IEGC Band. The voltage of 400 kV Kolhapur, 400 kV Karad and 400 kV
Mapusa even touched 436 kV, 434 and 437 kV respectively at 03:43 Hrs. As soon as the voltage
of Kolhapur touched 440 kV, the overvoltage relay of 400 kV Karad-Kolhapur 1 and 400 kV
Kolhapur-Sholapur 1 has picked up at Kolhapur end.
At 03:43:03 Hrs, 400 kV Kolhapur-Sholapur 1 tripped on overvoltage protection from
Kolhapur end and the direct trip was sent to Karad end. Even after tripping of this line, the Karad
voltage remained very high and over voltage relay of 400 kV Karad-Kolhapur 1 did not reset.
At 03:43:07 Hrs, 400 kV Karad-Sholapur 1 also tripped from Kolhapur end and DT was
sent to remote end. However, at Kolhapur end its B phase pole re-strike happened causing its
failure. This led to fault in the B phase in the system. However, there was no direct ground
involved during the fault as intimated by the substation. But the attached DR of this line in the
annexure indicate the presence of ground in the fault with neutral current flowing through earth
being equal to the fault current i.e. 3.63 kA. It is also observed that the fault was of resistive
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 31
nature leading to the high current with the low voltage drop during the event. As the pole burst,
the fault was persisting and it was to be cleared by the bus bar protection at 400 kV Kolhapur.
Although, this fault due to breaker failure should have been detected by the Bus bar
protection as observed from the current in the faulty circuit, Bus bar protection failed to operate
at 400 kV Kolhapur. Report from MSETCL is indicating that the bus bar failed to operate due to
the absence of differential current in the system. This persisting earth fault was being observed
by the backup protection system from remote end substation. This led to tripping of 400/220 kV
Kolhapur ICTs on backup protection followed by tripping of 400 kV Kolhapur GIS-Kudgi D/C
and 400 kV Kolhapur GIS-Mapusa 1 on directional earth fault from Kudgi and Mapusa
respectively.
Along with this, 220 kV Kolhapur-Mudshingi 1 tripped on Non -directional overcurrent
protection from Kolhapur and 220 kV 220 kV Kolhapur-Mudshingi 2 tripped on directional
Overcurrent and E/F protection from Mudshingi end.
After the above, 220 kV Kolhapur-Hamidwada tripped from Hamidwada end on Non-
directional overcurrent protection. With this Complete load of Goa along with 220 kV
Substation of Mumewadi, Halkarni, Mahalaxmi and Tillari got shifted on 220 kV Mudshingi-
Belewadi-Mumewadi circuit.
After this, 220 kV Belewadi-Mumedwadi circuit tripped from Belewadi end on
overcurrent protection causing islanding of the 220 kV Mumewadi, Halkarni substations along
with 220/132 kV Goa System from the rest of grid and their blackout due to low generation-high
load island formation.
With this around 200 MW load of Goa, 18 MW load and 16.8 MW Generation in
Maharashtra got affected. The generation affected are Mahalaxmi generation (8. 8 MW) and
Hemrus Sugar generation (8 MW) in Maharashtra.
Immediately after the blackout, the allocation of Goa from SR was increased from 95
MW to 145 MW with the consent of SRLDC/Karnataka to meet essential VVIP, Domestic,
Water Supply and Hospitals. Loads were dirstributed equally to North/Central Goa stations viz
50 MW to Xeldem, 15 MW to Verna, 50 MW to Ponda, 15 MW to Kadamba, 15 MW to Tivim
and 5 MW to Amona.
Initially when 400 kV Kolhapur Bus was charged by taking 400/220 kV ICT 3 at Kolhapur
(220 kV Kolhapur system was in service), It led to charging of 400 kV Kolhapur-Kolhapur GIS
2, 400 kV Kolhapur GID-Kudgi D/C (up to Kudgi) and 400 kv Kolahpur GIS-Mapusa 1(up to
Mapusa end) resulting in high voltage at open end and tripping of all these feeders on
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 32
overvolatge. 400 kV Kolhapur GIS-Kolhapur 1 did not trip. Subsequently 400 kV Bus was again
discharged at 04:21 Hrs. It was again charged at 04:39 Hrs.
After this restoration to restore Southern Maharshtra was also undertaken and 220 kV
Downstream network from Kolhapur and Mudshingi to Mumewadi and then to Halkarni were
restored one by one. Further, 220 kV Tillari-Amona and 220 kV Mahalaxmi-Amona were
charged, however these lines could not be restored due to prevailing high voltages.
Subsequently, after controlling the high voltage at these substations, lines were synchronised
followed by taking the loads. By 06:32 Hrs, the complete supply was normalised for the Goa
system.
The report received from WRLDC along with DR received from various utilities was
enclosed in annexure 2.51.
Committee may like to discuss.
D. OCCURANCES IN CHATTISGARH SYSTEM
2.52. Grid Incidence at Korba, Korba West, Korba East and nearby on 17th May 2016
On 17th May 2016, Due to Bad weather (Heavy rain and thunderstorm) In the Korba
district of Chhattisgarh, many of the lines tripped on single phase fault.
At 05:23Hrs, R phase to earth fault followed by Y phase to E/F occurred on the 400 kV
Korba-Bhilai 1 circuit. At 17:24Hrs, B phase to Earth Fault on the 400 kV Korba-Raipur 4
circuit and lines got successfully reclosed from both ends. However after 3.394 sec, the fault
reappeared in B phase and line got tripped.
At 17:33hrs, R phase to E/F occurred on the 400 kV Korba-Korba West circuit and line
tripped. A/R could not be confirmed but lines successfully reclosed at both end as intimated by
the sites. Fault location was 3.81 km from Korba end. At 17:41hrs, B phase to earth fault
occurred on the circuit and line successfully reclosed at Korba end however tripped from Korba
west end.
At 17:38hrs Y phase to E/F occurred on the 400 kV Korba-Balco circuit. However, Fault
was also in the B phase as observed from DR. The Fault current in Y phase was double of the
fault current in B phase so relay at Korba as well as Balco has sensed only as Y phase to E/F. No
A/R has occurred from either of the ends. Balco end DR is attached in annexure 2.50, however it
is not time synchronized. From Balco end it initiated the A/R cycle however did not take reclose
attempt and tripped after 7 seconds on DTT command.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 33
At 17:41Hrs, R Phase to earth fault occurred on the 400 kV Korba-Sipat circuit. The line
tripped without attempting A/R. 400 kV Korba West Ext-Bhilai 1 lines has tripped at 17:33 Hrs
on R phase fault at the same time as of first fault observed on 400 Korba-Korba West circuit in
its R phase. 400 kV Korba West-Marwa 1 lines tripped on B phase to earth fault. A/R is not
observed from one or both ends.
Along with several 400 kV lines from Korba and Korba West tripped along with few
220 kV lines following which one unit each of Korba east & Korba east extension tripped.
Further with overloading of lines from Korba sub-station, Generation was in its units. Total
generation loss due to unit tripping at Korba east and Korba east Extension 300 MW.
Expect 220 kV Korba East – Korba West I/C 1, which is faulty. Most of the elements are
restored by 21:22 hrs.
The report received from WRLDC is enclosed in annexure 2.52.
Committee may like to discuss.
2.53. Grid Incidence at 400/220 kV NSPCL Bhilai on 21st April 2016
On 21st April 2016, At 19:52 Hrs, R phase to earth fault occurred in 132 kV Bus of the
captive Power plant of BSP due to failure of 132 kV R phase CT of Bus coupler, situated in 132
kV Switchyard of BSP-2 Plant. As the fault was not cleared from the 132 kV side, it went on to
feed from the 220/132 kV ICT and further from 220 kV bus from BSP to NSPCL Bhilai though
interconnecting circuits. As the 220 kV ICTs and Interconnecting circuits were not tripping, it
resulted in protection operation of 220 kV NSPCL-BSP 3 and NSPCL-BSP 1 circuit which were
on the 220 kV Bus 1 at NSPCL Bhilai.
However, during the opening of 220 kV NSPCL-BSP 3 circuit from NSPCL end which
was on 220 kV Bus 1 at NSPCL, its breaker LBB protection operated which gave trip command
through bus bar protection resulting in tripping of 220 kV Bus 1 and connected elements. With
these, the Interconnecting NSPCL-BSP 1, NSPCL-BSP 3, Station Transformer 1 and 400/220
kV NSPCL ICT 2 tripped. This led to overloading of 400/220 kV ICT 1 at NSPCL which
tripped after one hour on overcurrent protection. There was no load/generation loss during event.
The report received from WRLDC is enclosed in annexure 2.53.
Committee may like to discuss.
2.54. Grid Incidence at 220/132 kV Urla, 220/132 kV Bhilai on 3rd June 2016
On 3rd June 2016, at 02:08 Hrs, due to tripping of 132 kV Urla A-Birgaon circuit on R
phase -B phase fault, load at Urla got shifted to 220/132 kV Bhilai sub-station causing tripping
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 34
of 220/132 kV, 160 MVA ICT on overload and loss of the load from 132 kV Birgaon,
Gudhiyara, Sarona and Urla sub-stations. The load loss during this event was around 207 MW as
per WRLDC SCADA.
The remaining loads were being fed from other 220/132 kV, 125 MVA ICTs and
220/132 kV ICTs at Urla. At 02:20 Hrs, 132 kV Bhilai-Urla C circuit tripped from Bhilai end on
overcurrent protection operation followed by overload tripping of 220/132 kV, 125 MVA Bhilai
MVA ICT- 2 at 02:50 Hrs. This has caused load loss of around 141 MW as per WRLDC
SCADA.
At 03:05 Hrs, when the 132 kV Urla A-Birgaon faulty feeder was trail charged, it again
tripped on persisting fault. However at the same time, all the three 220/132 kV ICTs at Urla also
tripped. This caused further load loss of 130 MW in the area.
The total load loss due to interruption of load in the in Urla and nearby areas was 323
MW. The total energy unserved during the whole event is 554 MWHr. Normalcy in the system
is restored by 03:50hrs.
The report received from WRLDC is enclosed in annexure 2.54.
Committee may like to discuss.
2.55. Grid Incidence at 220/132 kV Raigarh Sub-station on 21st April 2016
Prior to the event all the elements from 220/132 kV Raigarh Sub-station were in service.
220 kV Raigarh is having a double Main and transfer Bus scheme. There was no 220 kV Bus
protection scheme at Raigarh sub-station so any fault on the bus will be cleared by the remote
end/backup protection of the connected elements.
On 21st April 2016, At 20:58 Hrs, High Bus Jumper between 220 kV Main Bus-1 and
220 kV Main Bus-2 isolator of 220 KV Raigarh-Raigarh (PG) 2 circuit snapped with heavy flash
over. Due to this 220 kV bus fault (whether fault was on both or only one bus was not explained
by CSPTCL) occurred at 220/132 kV Raigarh Sub-station.
With this, total interruption of supply at 220/132 kV Raigarh S/s along with 220 KV
Saraipali, 220 KV Gerwani and 132 KV substations of Raigarh-Sarangarh, Baramkela,
Gharghoda, Patthalgaon, Jashpur, Chaple and Adbar occurred.
This has led to total load loss of about 289 MW. Most of the elements are restored by
22:55hrs.
The report received from WRLDC is enclosed in annexure 2.54.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 35
E. Miscellaneous Items
2.56. Demand Crash in Madhya Pradesh and Chhattisgarh
In the afternoon hours of 21th May 2016 heavy rains prevailed in eastern part of Madhya
Pradesh and Chhattisgarh demand crashed by around 1200MW and 1000 MW.
Western Regional demand gradually reduced from about 41300 MW to 38900 MW due to rains
and further reduced during evening hours (17:00 HRS-18:00 HRS) to 36000 MW as normal
trend.
No Generating units tripped, No power interruption took place. Several lines tripped on
faults which are enclosed in annexure 2.56.
Committee may like to discuss.
ITEM NO. 3: Tripping of lines / ICTs :
The minor incidences of tripping of lines and ICTs during the period 01-04-2016 to
30-09-2016 are enclosed at Annexure–3.
All utilities shall furnish the single line trippings & minor trippings to WRPC and
indicate whether A/R is provided at both ends of the line or not. Also it shall be reported as to
whether the A/R operation was successful for transient faults or not and whether A/R is locked
out for permanent faults on the lines or not. Constituents shall provide A/R availability/status for
each line at both ends.
Committee may like to discuss/note.
ITEM No. 4 : Multiple tripping of evacuation lines at CGPL(Leading to tripping 4x830
MW generators) and 400 kV lines at 400 kV Bachhau S/S.
A complete blackout at CGPL took place on 13.07.2016. A group comprising of CGPL,
GETCO, Powergrid WR-II, WRLDC and WRPC representatives met at Vadodara on 18.07.2016
to discuss the blackout. Later in the 127th PCM, Committee suggested that CGPL, GETCO,
WRLDC will form a group to study the power swing phenomenon observed in the CGPL
system. CGPL, GETCO and WRLDC were requested to send the details of the incidental system
before the occurrence and relevant tripping data (DRs, PMU recordings etc.) to WRPC. Based
on the discussions and details received, a report is prepared by WRPC and it is available in
WRPC website under PCM Minutes.
The following were the conclusions and recommendations based on report prepared by
group, which is put up to PCM for vetting.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 36
1. RTV Silicone Coating of Insulators:
The bus fault at Varsana has occurred due to the insulator tracking and flashover
during foggy weather conditions with rains. PGCIL informed that flashover event could
be minimized if the hot-line washing and RTV silicone coating of insulators be
completed prior to the rainy season. Therefore sub-station falling under pollution
zone/saline zone should explore adopting best practices of hot line washing prior to rainy
season along with the application of RTV silicone coating to avoid such events in future.
Varsana is an important GETCO station connected to two large generation complexes.
GETCO may look into the possibility of RTV Silicone coating in such areas.
2. Charging of Dead Bus:
Dead Bus should generally be charged through a long line or through ICTs, so
that the fault currents are less. A Dead Bus, after bus fault, should not preferably be
charged through short line and lines having generator connected at remote ends of lines.
Also dead bus should not be charged through line having strong source at the other end.
Action: All utilities to please note for future.
3. Power Swing phenomenon
Prior to the event, the CGPL generation was around 2875 MW. During the event
CGPL Units had fed the three phase fault at Varsana for a duration of 350 ms. Along
with this event, three 400 kV lines also got tripped which was followed by a continuous
decline of voltage for 290ms. The voltage started rising, this was detected as a power
swing entering in zone-1 by the line DPS at CGPL end and the lines tripped.
The reasons for excitation of the oscillations need to be found out since these
oscillations were not damped out resulting in a severe power swing. A transient study by
modeling the proper network is required to done.
PCM may decide the modalities of carrying out these studies. The scope of these
studies shall be to examine the cause of power swing, various factors that
contributed to CGPL machines going Out of Step and suggest remedial measures.
4. Protection Coordination Issue in Zone 2
The Zone 2 settings adopted by CGPL for all the lines, at CGPL end is 300msec
and the remote end settings are 350msec. The adoption of 300msec for Zone 2 at CGPL
end is in view of stability of generating units and critical clearing time of faults. It was
noted that the 400kV Bacchau-Versana-1 & 2 lines are very short lines (8.5kM).
Therefore group recommended interimly that PGCIL may adopt 250msec for 400kV
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 37
Bacchau-Versana-1 & 2 and CGPL may adopt 350msec for time being, and afterwards
based on the studies for critical clearing time/stability of the generators for faults to be
carried out, it would be decided to raise the zone 2 time settings for these lines.
PGCIL/GETCO/CGPL in mutual coordination may set the relay settings as above. PCM
may vet these interim settings.
5. Permissive Trip Carrier being received as direct trip for 400 kV Bhachau-CGPL 1
at Bhachau end.
It was observed that the permissive carrier sent by CGPL for the 400 kV CGPL-
Bhachau 1 was received as direct trip by the Bhachau end. In view of this, end to end
testing of the Carrier signal has to be checked by the both utilities (CGPL and PGCIL) in
coordination with each other.
6. Bus configuration at 400 kV Varsana.
The elements should be distributed evenly on the buses (Bus A & Bus B) such
that these elements can be served optimally in the event of Bus faults to enhance the
reliability. The elements on Bus-1 & Bus-2 were not evenly loaded at 400kV Varsana
S/S. Therefore it is recommended that GETCO may explore how Bus configuration can
be changed such that, balanced loading on buses is achieved on both the 400 kV buses at
Varsana S/S.
7. SPS at CGPL :
As none of the criteria for CGPL operation was satisfied due to low generation at
CGPL, the SPS has not operated as per the design.
8. Loss of PMU data from CGPL:
After tripping of units & auxiliaries the PMU data was not available. It should be
ensured that the data from PMU should always be available.
Further in the report on similar blackout at CGPL in 2014 it was recommended
that the PMU installed on unit 40 does not serve any purpose in analysing such events
and therefore it was suggested that the same should be shifted on 400KV CGPL-
Bhachau line.
It is again recommended that the above should be done immediately.
WRLDC has also prepared a report on the incidence and the same is available on their website.
The report prepared by WRPC is enclosed at Annexure-4.
Committee may like to discuss.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 38
ITEM NO. 5: Hon’ble CERCs orders on the Grid disturbance of 30.07.2012 &
31.07.2012
5.1: Compliance Status observations made in Protection Audit (Petition No.
220/MP/2012) Back Ground :
Back ground : CERC vide its order dated 21.02.2014 in respect to petition No. 220/MP/2012
filed by POWERGRID have directed that CTU and SLDCs shall submit quarterly Protection
Audit Report to the respective RPC latest by 15thday of the first month of next quarter and
RPCs shall submit the report to the Commission latest by 15thday of the second month of next
quarter. The Member Secretary of Regional Power Committees shall monitor the
protection related issues and bring to the notice of the Commission any instance of non-
compliance of the Regulation 1.5 of the Grid Code in respect of the protection related issues
considered in the instant petition.
It was decided that all observations of protection audit would be classified as protection system
related i.e. Category A, Category B & system improvement related observations, would be
furnished separately and shall not be included in the list of category A or B deficiencies.
The updated status filed to Hon’ble CERC as on 31st July 2016 is enclosed at
Annexure-5.
All the constituents/Utilities are requested to submit the updated status regularly
Committee may like to discuss.
5.2: Grid Disturbance on 30.07.2012 & 31.07.2012 (Petition No. 167/Suo-Motu/2012)
Back ground : Hon‟ble CERC‟s vide order dated 22.02.2014 in the matter of grid
disturbance occurred on 30.07.2012 & 31.07.2012 in petition No. 167/Suo-Motu/2012,
have made certain observations and issued directions.
According to this order, all the RPCs have to maintain the relay settings data of all the
ISTS lines and lines emanating from interface S/Ss of Utilities to ISTS (400 kV& above and
220 kV interfacing lines). Therefore all utilities were requested to submit relay setting data
to WRPC/WRLDC.
In 123rd PCM, committee requested all utilities to compile & maintain the data of their
system for voltage level of 132 kV & above. The relay setting data in respect of all 400 kV
lines and important 220 kV lines (interface lines with ISTS & lines connected to generating
stations) shall be submitted to WRPC/WRLDC. Committee requested WRLDC/SLDC to
collect and compile the data of all utilities under their control area and submit the same to
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 39
RPC. The data has been received from MP, GETCO and Maharashtra.
In 127th PCM, Committee requested all the utilities (PGCIL, CSPTCL, ISGS, Goa, and
DD & DNH) to submit the updated relay settings data to their respective SLDCs, WRLDC, and
WRPC at the earliest.
WRLDC/SLDCs may give status on the data.
Committee may like to discuss.
5.3: CERC Order dated 05.08.2015 on draft protocol for checking protection settings and
its healthiness (Petition No. 009/SM/2015)
Back ground :
5.3.1) Background:
Hon‟ble CERC vide order dated 05.08.2015 in the matter of “following up actions on the
recommendations of CAC Sub-Committee on Congestion in Transmission” have
considered and accepted the Sub-Committees report and recommendations on measures to
reduce congestion in transmission for which actions need to be taken by CEA, NRCE, CTU,
POSOCO, POWERGRID, RPCs as well as CERC.
CERC, in its above order have directed Member Secretary (RPCs) as follows;
“Protection sub-Committee of RPC should bring out protocol for checking the settings,
ensuring healthiness of existing protection system and periodicity of carrying out this
exercise”.
The protocol formulated in the special meeting held on 16.10.2015 and 126th PCM was discussed
in detail in the 31st WRPC meeting and the committee approved the following:
5.3.2) 126th PCM & 31st WRPC meeting discussions : With regard to a new element
getting connected to CTU, CTU informed that they are already providing the settings. However,
for lines of CTU network not constructed by POWERGRID, this role will have to be played by
the line constructing entity. The revised network configuration which includes the next busses
along with the line length where a change in network has taken place should be given, so that
testing circles can set their distance relay reaches.
5.3.3) Protocol approved in the 31st WRPC meeting :
a) Protocol 1: (For overall settings) The proposer can either be Local/Field testing Engineers or
HQ and the approver for these settings can be HQ and Local/Field testing Engineers respectively.
These two should be different/independent groups.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 40
b) Protocol 2: Review at site: Checking and validating of the settings be done once in a year
by testing/site engineer. OR Whenever a Grid Disturbance occurs, the relay settings of the
affected station and nearby station (where protection has mal operated) be checked thoroughly.
c) Protocol 3 : Database: Soft copies of the settings be available at the CTU/STU HQ and the
same be forwarded to SLDCs/WRLDC for voltage levels of 400kV & above and ISTS lines (of
all kV levels). A database of all the above elements be maintained at WRLDC/SLDC/WRPC (in
addition to being maintained by respective utilities for their systems).
d) Protocol 4: New Elements Integration: In case of new element to be synchronized first time,
the new element entity should get the settings certified/vetted (particularly the distance relay
reaches) by STU/CTU as the case maybe and forward the same to WRLDC/SLDC. The
parameters/fault levels regarding the incidental system to the new elements be provided by
CTU/STU as the case may be to the Utility proposing to connect the new element and the
settings arrived by the Utility be got verified from CTU/STU. For this the Utility proposing to
connect the new element shall approach CTU/STU as the case may be. The verified settings shall
be adopted by the Utility and same shall be communicated to WRLDC/SLDC as the case may be
and thereafter WRLDC/SLDC shall give permission for synchronization for such elements after
completion of all other formalities required as per regulations in vogue.
e) In case of any network changes, the revised network configuration (which includes the list of
adjacent busses lines and along with the line lengths of the network where a change in network
has taken place) should be given to the concerned testing circles/utilities/IPPs who can then set
their distance relay reaches as per the Ramakrishna Committee guidelines. For any
difficulty/ratification, the matter can be discussed in PCM forum of WRPC.
5.3.4) 127th PCM Discussions: In the 127th PCM constituents felt that since there would be
difficulty in following protocol 4 at d) and e) above, in the field, and therefore there is a
need to modify it slightly as follows,;
d) Protocol 4: New Transmission line Element Integration - In case of new transmission
line to be synchronized first time, the new element entity should approach respective
CTU/STU/concerned utility where it is getting connected, for getting the information of
Transmission Line(s) connected at that particular utility S/s(i.e remote s/s) , and the distance
relay’s settings and zone timings. The new utility shall then arrive at the settings for
distance relays zone reach and timings and for that it shall adopt the overall settings of
distance relay as per the Ramakrishna committee Guidelines. The zone timings shall have to
be suitably co-ordinated with the existing settings adopted in the next station.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 41
The Bus fault levels regarding the incidental system to the new elements shall be provided
by CTU/STU as the case may be to the utility proposing to connect the new element.
These settings shall be forwarded to WRLDC/SLDC and with copies to
CTU/STU/concerned utility and WRPC. For doubts or disagreement, if any, the matter can
be referred to WRPC PCM, after adopting interim settings as above.
e) In case of any network changes such as due to (d) above or otherwise, the existing
utilities need to review the reaches and timings for the distance relay. For this the utility
whose substation configuration is getting changed due to the network change/ addition,
shall indicate to all remote ends and next to remote ends s/s the new configuration of
network along line lengths and their existing zone reaches and timings. It is then the
responsibility of all the utilities, to apply the reaches (as per Ramakrishna Committee
recommendations) and revised time co-ordinations for lines from their s/s for the changed
configuration. They shall follow the proposer/approver model as per Protocol (1).
5.3.5) The above changes suggested by PGCIL in the 127th PCM were put up in the 32nd
WRPC meeting:
In the 32nd WRPC meeting, PGCIL representative informed that CTU did not
want to own the responsibility of validating or vetting the settings. The settings have to be
implemented as per Ramakrishna Committee recommendations and it is the responsibility of
the entity to set its relay settings. Hence they had requested the modification. CTU did not
have any issues in giving relevant data. Vetting should be done by PCM.
It was clarified that perhaps the protocol 4 is slightly misunderstood by CTU. The scope is
not as wide as CTU is envisaging. Consider a new entity getting integrated or a new line
getting LILOed at a station. This will call for a change in distance relay settings especially
for Zone 2 and Zone 3. Hence Protocol 4, now envisages in a detailed manner what data
shall be provided by whom. It is clear that the responsibility of adopting a setting in line
with Ramakrishna guidelines rests with the utility, for which he should be provided
with the data. The utility shall accordingly set the relays, and the CTU or STU will
play an advisory role on the settings adopted by the incoming utility for only for the
interim period(from the time the utility comes till the next PCM), which is usually a
maximum period of 3 to 4 months. Further if it is not a new utility, then existing
STU/CTU/utilities are responsible for their jurisdictions. By such discussions on the
settings, many incidents could have been minimized/avoided as seen in the PCM minutes.
Once the PCM vets, the interim advisory role of CTU/STU is over. If it is required very
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 42
urgently for complicated settings changes, then a small group of PCM members can
specially meet and decide the interim settings and put up in the next PCM. The whole idea is
to guide a new utility to adopt the Ramakrishna guidelines properly and allow flow of
information.
The above was agreed in the 32nd WRPC meeting.
Protection sub-Committee may note.
ITEM NO. 6 : Proposal for revision in relay settings.
6.1) Proposal for revision in relay settings for lines emanating from 400kV CGPL UMPP.
A proposal for revision of relay settings for lines eminating from CGPL UMPP was
forwarded by CGPL vide email dated 13.10.2016, after incorporating the observations made
by GETCO. The proposal was sent for vetting to CTU, PGCIL and GETCO, in line with the
decision in 32nd WRPC meeting vide email dated 25.10.2016, with a reminder on
11.11.2016. GETCO have confirmed that the observations made by them were incorporated
by CGPL. However no communication was received from CTU & PGCIL.
The CGPL proposal is enclosed at Annexure-6. Letter received from CGPL is
enclosed at Annexure- 6.
Committee may like to discuss and approve the settings.
6.2) Updating the status on relay co-ordination in Akola area of MSETCL:
A report on disturbance on 29.03.2015 at Akola S/s was circulated vide letter dated
02.11.2015 and discussed in the 126th PCM.
The recommendation pertaining to relay co-ordination in Akola area of MSETCL is as
follows;
The system near about Akola (Akola, Wardha, Koradi, Chandrapur, Khaparkheda&
Aurangabad) is complex and have many complexities as regards to Main/Backup
protection settings. A coordinated setting of Main/backup relays at the complex of Akola is
required to be arrived at, considering the In-feed/Out-feed effect by simulating faults at
various locations. Hence the traditional/Ramkrishna Committee recommendations would be
required to deviate. PGCIL, Maharashtra STU, M/s MEGPTCL and Indiabulls
representatives in co ordination with WRLDC & WRPC may sit together and decide proper
settings.
PGCIL, MSETCL may update the status.
Committee may decide the members for the group.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 43
ITEM NO. 7: Status of implementation of recommendations of Report on Grid disturbance
on 30th and 31st July 2012 in WR.
Back ground:
An enquiry committee was set up under the chairmanship of Chairman, CEA to
enquire into the grid disturbance on 30th& 31st July, 2012 in NEW grid. As per the
recommendations of this committee, all utilities/SLDCs/RLDC were required to submit updated
status on implementation of recommendations made by the committee to RPC on
1st& 15th of every month and the same has to be sent to CEA by RPC by 3rd& 17th of every
month.
The nodal officers responsible for submission of data to RPC were already identified and were
requested to forward the data regularly for onward submission of the same to CEA/MoP. In a
special meeting held on 18.12.2014, it was decided that the status shall be submitted year wise
separately for FY 2012-13 & 2013-14 and the data may be furnished on quarterly basis
for April – 2014 onwards. In the 123rd PCM, Committee observed that there were
discrepancies or mismatch in respect to protection audit data furnished by utilities for
submission to CEA in format and to CERC in format. It was opined that to have a clear picture
of implemented status on above recommendations in respect of protection audit, utilities may
submit the consolidated and detailed status of all 132 kV, 220 kV, 400 kV and 765 kV S/s. It
was also felt that SLDCs and WRLDC would coordinate to get the details.
A special meeting was held on 16.02.2016 to discuss the above issue.
The updated position is enclosed at Annexure-7.
Item No. 8: Task Force report
8.1 : Report of the Task Force on Power System Analysis Under Contingencies:
Ministry of Power, GoI constituted a “Task Force on Power System Analysis under
Contingencies”, in December 2012 under the chairmanship of Shri V. Ramakrishna as per
the recommendation made by Enquiry Committee headed by Chairman, CEA on grid
disturbances that took place in NEW grid on 30thand 31stJuly 2012. The terms of reference
of Task Force broadly cover analysis of the network behavior under normal conditions and
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 44
contingencies, review of operational philosophy of protection relays, review of islanding
schemes and technological options to improve the performance of the grid. The report of the
Task Force was discussed briefly in 122nd
PCM and subsequently discussed in detail in a special
meeting held on 18.12.2014. Thereafter the recommendations were discussed in the previous
PCMs. A brief on suggestions given by Ramakrishna Committee, discussions/observations of
the group and PCM are as follows.
1) Review & correction of relay settings:
Zone-1 PSB: The task force recommended to trip the line, if power swing enters Zone – I
Characteristics and block tripping for other zones during power swing.
Decision in PCMs : All existing relays may not have feature of delayed tripping for one zone &
blocking for other zones i.e. delayed tripping for Z-I and blocking for Z-II & Z-III, hence all
utilities shall instantaneously trip for Zone – I power swing and block the tripping for power
swing in other zones(Z-II & Z-III). Specific stations where this is not possible may be identified
and put up in the next PCM.
In the 125th PCM & 126th PCM, PGCIL, MPPTCL, CSPTCL, GETCO and MSETCL
representatives intimated that there settings(PSB) are in line with above recommendation.
NTPC representatives intimated that power swing is blocked for 2 secs for all 3 zones i.e. Z-1,
Z-2 & Z-3 and if power swing still persist the relay will trip for all 3 zones.
NTPC may update the status on the above.
2) Formulation of Special groups for studies and protection coordination:
The Task Force recommended forming a group for studies, protection coordination and relay
settings. It also recommended that each utility should establish a protection application
department with adequate man power & skills. The members of protection team shall
undergo regular training to enhance their skills.
Contingency and Stability Studies: The Task Force recommended to form a special
group to analyze the grid conditions and factors affecting its operation and simulation of critical
system conditions expected for forthcoming season on regular basis and suitable operational
strategy worked out.
Tuning of power electronic devices & PSS: The Task Force recommended carrying out studies
& reviewing the network at regular intervals (3-4 years) with introduction of newer power
electronic devices. The results may be implemented within next 3-4 years. It also suggested that
as this requires specialized dynamic modeling, the task may be entrusted to reputed independent
agency and implementation of tuning be entrusted to respective manufacturer.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 45
Decision in 127th PCM: It was decided that MSETCL, GETCO, CSPTCL, MPPTCL, WRLDC,
POWERGRID and NTPC would nominate one member from studies side and one member from
protection side and send the name of the members to WRPC for carrying out studies mentioned
above. It was also decided that SLDC would give PSS details format for state generators,
WRLDC for IPPS and NTPC for their generators.
SE (protection), WRPC intimated that in view of the above decision, a group was formed and a
meeting of the group was held at WRPC on 22.04.2015. Following was decided in the meeting;
(i) Operational & Off line Studies: It was decided to update the PoC Q4 case of 2014-
15 with the actual network and set this as a starting point. All utilities would furnish the bi-
monthly data of planned network, planned generation and anticipated load generation for
the period upto March 2016. The study group after updating the network and receipt of the
forecast data would take up the operational planning studies.
(ii) Transient Stability & Short circuit Studies: Utilities would furnish the machines transient
data of their system, wherever data is not available the same shall be assumed as per CEA/CBIP
manuals. Training on the same could be arranged with IIT-B.
It was decided that two subgroups could be formed to look into the above
recommendations. One subgroup would be headed by Shri R H Satpute, SE (Testing
Division – Vashi). This sub group would review the protection system in WR and coordinate the
relay settings as per the Ramakrishna recommendations. The other subgroup would be headed by
Shri Satyanarayan. S, SE (P&S), WRPC. This subgroup would carry out studies required for
coordination of relay settings.
iii) In house training:
Task force strongly recommended that a dedicated group is required to be trained in all utilities
to carry out computer aided studies for relay settings. It was felt that knowledge sharing sessions
/ discussions, in house training on the fundamentals of load flow studies, contingency studies,
stability studies etc.., may be shared with the system study engineers of utilities of WR.
iv) Training by IIT: In order to build a strong team of WR in specialized areas of studies,
training sessions may be arranged to team members at IIT Bombay on relevant specialized areas
subjects like transient stability, PSS tuning, tuning of FACTs devices, SSR etc..,
vi) On line studies & State Estimation: An update on the online studies (Online state
estimation and contingency rankings etc) being carried out by utilities was updated as regards to
packages available with them and online studies conducting at their end.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 46
WRLDC representative informed that in compliance to recommendation 10.1.2 of Rama
Krishna committee on Task Force on Power System Analysis under Contingencies, WRLDC is
operating Real Time Security Desk in Control Room since June‟14 with an officer
c o n v e r s a n t with s y s t e m s t u d i e s through PSS/E software and knowledge of
SCADA/EMS.
Presently WRLDC and SLDCs are upgrading the SCADA/EMS system. In this new
SCADA / EMS system complete network model of Western Region would be incorporated
which would result in effective utilization of State Estimation in real time. In the upgraded
SCADA/EMS, the plan is to run state estimation along with contingency analysis in real time
and integrate PMU data with new SCADA/EMS system which would improve observability of
network.
MSETCL representative intimated that earlier MSETCL was carrying out online studies on
Seimens State Estimator software but due to increase in network complexities and
constraint with existing S/W package, these studies were discontinued. It was intimated that
very soon MSETCL would be shifting to new S/W package, through which online studies could
be carried out.
GETCO, CSPTCL & MPPTCL representatives intimated that they are not performing online
studies.
Committee may like to discuss/note.
8.2 : Meeting for appointment of consultant-A to conduct the study/analysis to
ensure secure and reliable operation of national grid:
In compliance to MoP order dated 16.07.2014, the process of appointment of
consultants to conduct the study/analysis to ensure secure and reliable operation of national
Grid, has been under taken by CEA. A meeting to decide the data/inputs for the consultants was
held at CEA on 22.05.2015 under the Chairmanship of Member (GO &D), CEA.
Following issues pertaining to protection and system studies and actions required by RPCs and
constituents were discussed in the meeting:
(i) The Grid Study Committee will be chaired by Member (GO&D), CEA.
GM,NLDC, POSOCO will be the convener. MS RPCs will be the members. One STU from
each region would be nominated as member for the committee on rotational basis.
(ii) Identification of 25 nos of critical S/Ss in WR (already audited) for review of
protection audit and setting of protection relays thereof. The consultant would carry out
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 47
Protection Audit and review the protection philosophy adopted.
(iii) Substation wise protection audit reports in respect of all the substations audited in the
FY 2012-13.
(iv) Nomination of nodal officers from all power sector entities. A CE level officer from
each STU shall be appointed by each State/UTs to co-ordinate with SLDCs. Monthly meeting
will be held on VC.
From WR, CE, STU, MSETCL was nominated for the grid study committee. WRLDC
identified 25 critical S/s (already Audited) of WR and the same were forward to Grid Study
committee, CEA.
Accordingly M/s Tractable was appointed as consultant. A meeting of WR
constituents was held on 12.08.2015 at WRPC, to collect the data required by the consultant.
The consultant M/s Tractable commenced the work under Task-I in August 2015. 256 S/S
protection audit reports were forwarded to M/s Tractable and they have completed the scrutiny
the protection audits reports for these S/Ss.
The Task-II for review of protection audit and protection relays thereof for 25
critical S/Ss commenced in December 15 and they have almost completed the Task-II and
have recommended revisions in setting of the stations where protection audit has been
carried out by them. WRLDC may update the status.
NLDC has organized training on power systems for 5 days by the international
consultant (M/s Tractebel), at WRPC Mumbai. The training program is scheduled from
09th January 2017 to 13th January 2017.
WRPC vide letter dated 14th October 2016 has requested to nominate protection
engineers for the above training. However, as on date, nomination has not been received
from any of the constituents. Utilities may give nomination of their representatives for this
training program so that the same can be conveyed to NLDC.
Committee may like to discuss.
ITEM NO. 9: LINE DIFFERENTIAL PROTECTION FOR SHORT LINES:
CEA vide letter dated 27.10.2016 (copy enclosed at Annexure-12.2) have requested that
the recommendation of the sub-Committee on Relay/Protection under task force for Power
System Analysis under contingencies on transmission lines having OPGW or separate OF laid
for communication shall have line differential protection as Main-I protection with distance
protection as backup (Built in Main relay or standalone) and Main-II shall continue to be used as
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 48
DPS. Auto reclosure shall be blocked for faults in the cables. Further CEA has requested to
deliberate the matter in PCMs of RPCs.
WRLDC vide letter dated 12.10.2016 have intimated that several Grid incidences
occurred in the recent past due to problems in the distance relay setting coordination of long
lines followed by short lines, i.e. tripping of longer lines in zone 2 prior to tripping of short lines.
A list of short 765 and 400 KV lines with the line length less than 50 Km in WR has been
prepared by POSOCO and the same is enclosed at annexure-8.
Utilities concern may bring the Main-I & Main-II protection employed for the lines
at both ends and plan for replacement of Main-I relays as above for the lines in Annexure-
8. Also the feasibility of providing Main-I as differential protection on lines having FO for
other lines be furnished in the PCM.
Committee may like to discuss.
ITEM NO 10: COMMISSIONING OF NEW SYSTEM PROTECTION SCHEMES IN
CONNECTION WITH SYNCHRONIZATION OF SR AND NEW GRID
1)Revision in SPS : With commissioning of 765kV Kolhapur-Kudgi (PG) D/C (initially charged at
400kV), revision of SPS and the present status of implementation of the SPS by various agencies
involved was communicated by NLDC vide letter dated 23.12.2015. NLDC vide letter dated 16th
March 2016, superseding all the previous communications in relation to the NEW-SR SPS have
intimated revision in the SPS on NEW-SR corridor for implementation.
2) 31st WRPC meeting deliberations:
WRLDC representative stated that all the revised NLDC SPS has been implemented except
generation back down & load shedding of 200-300MW in Maharashtra envisaged at SPS-5 and load
shedding of 200-300MW in Maharashtra at SPS-6. As regards to SPS-8, the tripping of bus reactor
at Pune (PG) and Parli (PG) has not been implemented as directed by NLDC/WRLDC, since these
reactors are in the same dia of other important elements.
CE, SLDC, MSETCL, informed that they do not agree for generation backing down at Koradi-
70MW, Chandrapur-250MW and Khaparkheda-150MW for SPS-5 (Tripping of one ckt of 400kV
Wardha-Parli D/C and flow on other circuit>750MW). He further informed that backing of
generation at these places in Maha Genco, has not be shown to be effective. Hence he requested
that these should be dropped. However as per the SPS-5 backing down at APL Tirora-200MW;
Mauda-100MW, IB-30MW may be retained. Hence he requested that SPS-5 and SPS-6 requires to
be revisited. As regards to addl 200-300MW LS in Western Maharashtra, they would instead pick
up generation at Koyna.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 49
MS, WRPC informed that SPS has to be followed by all. These SPS are designed to save the grid in
case of critical contingencies. GM, WRLDC informed that the chances of SPS-5 getting operated is
less due to expansion of network and commissioning of Aurangabad-Solapur D/c. CE, SLDC,
MSETCL informed that the SPS for tripping of Aurangabad-Solapur D/c is already there and
therefore SPS-5 becomes redundant. Hence there is a strong need revisit the SPS-5.
MSETCL was suggested to give their concerns to WRPC and the same would be taken up with
NLDC, since the SPS has been proposed by NLDC.
3) 127th PCM Discussions :
The matter taken up by MSETCL with NLDC and reply of NLDC was discussed in the PCM and
MSETCL representative stated that NLDC have proposed a meeting to resolve the issue.
4) 32nd WRPC meeting discussions:
It was informed that MSETCL had raised several concerns about SPS-5 and had written to
NLDC. The reply of NLDC was also discussed in the PCM and NLDC had proposed a
meeting to resolve the issue. CE,SLDC, MSETCL informed that various concerns of
MSETCL on SPS-5 and a meeting with NLDC and other stakeholders was already proposed
and the same shall be discussed at that time.
WRLDC/MSETCL may like to update the status
ITEM NO 11: IMPLEMENTATION STATUS OF SPS
11.1) SPS for 765 kV Bina – Gwalior – Agra: An SPS has been implemented for Bina–
Gwalior– Agra D/C, wherein when sudden reduction in import by NR on Agra-Gwalior I & II
ckts by more than or equal to 1500MWs, 500MWs generation back down in WR (KSTPSNTPC–
120MWs,VSTPSNTPC–200MWs&CGPL –180MWs)and load shedding in NR would take
place.
11.2)Revision of SPS: NLDC vide letter dated 07th Sept.2015 intimated that with
commissioning of 765kVGwalior-Phagi D/C & 765kV Phagi-Bhiwani, the SPS margin of
1500MW on 765kV Gwalior-Agra D/C was increased to 3000MW. Generation backing down
quantum in WR increased from 500MW to1000MW and load shedding in NR was also
increased. In addition to NTPCKSTPS, NTPC-VSTPS&CGPL stations, SASAN UMPP has also
been included in the SPS for a total backing down quantum of 1000MW.
Subsequently, the SPS signal was wired up to SASAN through PLCC channel and the backing
down at NTPC-KSTPS, NTPC-VSTPS, CGPL and SASAN was revised to250MW.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 50
The mock testing of the SPS was carried out on 12.05.2016 and during mock testing, a signal
for loss of 1500MW was generated at Agra end and receipt of the same at VSTPS,CGPL and
KSTPS was confirmed by WRLDC vide their letter dated 18.05.2016. Further it was informed
that the SPS signal did not get extended to SASAN, since it was generated from Agra end
which has FO connectivity.
11.3) WRPC vide letter dated 23.05.2016 (enclosed at annexure 20 ) took up the matter with
NLDC/WRLDC as the setting for loss of import on 765kV Agra-Gwalior D/C lines, is still
kept at 1500MW.
Further it was requested to confirm implementation of SPS as per NLDC letter dated
07.09.2015 and it was suggested that in case the revision in SPS is not carried out as per letter
dated 07.09.2015 at Agra end, the WR generating stations, VSTPS, KSTPS, CGPL and
SASAN may please be advised to set their backing down quantum to 125MW from 250 MW
each(the present backing down quantum implemented for this SPS is 250MW each) and
PGCIL be advised to retain the original setting of 1500MW(which at present is set at
3000MW) at Gwalior end for 765kV Agra-Gwalior D/C lines SPS.
11.4) In the 127th PCM it was informed that the above has not been implemented. PCM
suggested to implement the above modifications in SPS till the SPS is implemented in NR and
at Agra end..
In the 32nd WRPC meeting PGCIL informed that PGCIL has revised the settings at Gwalior
end (to 1500 MW) and tested locally. Fiber optic cable laying to Sasan is in process and
expected to be completed by September 2016. CGPL has implemented 125 MW backing
down. Other generators shall also implement 125 MW each (Total 500 MW till NR
implements their portion after which it will come back to total 1000 MW)
WRLDC may like to update on the above.
Committee may like to note.
ITEM NO 12: ISLANDING SCHEMES:
12.1) Islanding scheme for Sugen:
In the 124th
PCM, WRLDC representative intimated that a meeting was held at
WRLDC, Mumbai on 16.04.2015 to finalize the islanding schemes of Sugen and the proposal
was discussed in the 126th & 127th PCM. However due to unavailability of Sugen representative
the Islanding scheme could not be finalized.
In the 127th PCM, GETCO representative stated that they have completed the necessary work at
their end and requested that TPL may inform the status on the same at their end. Accordingly
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 51
WRPC took the matter with TPL and subsequently a meeting was held at Sugen Surat on
07.11.2016 and the Islanding scheme was discussed in detail.
10.2) The brief on the proposed Islanding scheme was as follows;
SUGEN switchyard consists of the following:
400 KV switchyard – 2 Main Bus and 1 Transfer Bus
3 x 382.5 MW Generators
400kV Sugen-Vapi Line (PGCIL)
400kV Sugen Jhanor Line (PGCIL)
400kV Sugen-Unosugen line (TPGL)
400kV Sugen-Pirana Line (TPGL)
220 KV switchyard – 2 Main Bus
220kV TPL Surat Bhatar Feeders – 2nos.
220kV TPL Surat Ved Feeders – 2nos.
220kV TPL Surat Puna Feeders – 2nos.
220kV TPL Surat Bhatar Feeders – 2nos.
220kV Gensu Feeders- 2 nos.
400/220 KV Interconnecting Transformers (ICTs):
315 MVA ICT – 3 nos.
Surat Load of around 630 MW consists of load on Surat-Ved,Surat-Bhatar and Surat-
Puna Lines (220 KV D/C lines).
Islanding of SUGEN with Surat load is designed as follows:
1. 48.5 HZ: 220 KV Sugen-Kim line and Gensu line D/C will be tripped
2. 48.4 HZ: Load-Generation balance to be monitored with respect to 220 KV feeders for
Surat City and Generation at Sugen. If generation is more than Surat Demand, the
adaption Logic will Trip the Unit/ST or various combinations of Units/ST to reduce the
load-Generation difference.
If Surat Load is more than Generation, Load shedding PLC Logic will Trip the
Substation Breakers at 66 KV level as per Priority Logic.
3. 48.2 Hz: 400 KV Sugen-Pirana and 400 KV Sugen-Vapi (PG) to be opened in first phase
one by one. Fine frequency tuning would be intimated by Sugen at the time of
implementation.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 52
4. 48.0 Hz: 400 KV Sugen-Unosugen and Sugen-Gandhar (Jhanor) line have to be opened
in next phase resulting in islanding of Sugen with Surat load. Fine tuning of frequency
would be intimated by Sugen at the time of implementation.
10.3) Observations made during meeting held on 07.11.2016 :
1) It was suggested to open the 400 KV Lines in sequence before opening the 220kV
Sugen-Kim line and 220kV Gensu Line, since for Islanding scheme to be successful it is
anticipated that the fault is in the Grid and the disturbance is spreading. If the 400 KV
lines remain connected till frequency falls to 48.0 Hz, the Power from Sugen will be
flowing towards the Faulty section of the Grid and Load-generation balance could never
be achieved as long as these 400 KV lines remain connected to Sugen 400 KV
Switchyard. Further, if Sugen-Kim lines and Gensu lines remain connected, it is possible
to form the Island with large portion of Gujarat and Sugen with Surat load initially and if
still the frequency is falls, Sugen can further be Islanded from GETCO system by
disconnecting the 220kV Sugen-Kim line and 220kV Gensu Line .
2) MS WRPC observed that as Surat load is only 630 MW and after forming Islanding,
Power Number of Surat will be reduced to 20 MW, which itself is very small number.
Therefore, Load-Generation balance should be done with very fine tuning of load which
can be achieved at lower voltage level i.e. 33/11 kV. It will be difficult to control the
variation of frequency in the Island without fine load control and the Island will not
sustain if such control is not there. Similarly, it is necessary to take prior permission from
PGCIL to trip the Sugen-Vapi line under emergency/Grid failure condition.
3) SLDC Gujarat/WRLDC emphasized opening of 220kV Sugen-Kim and Gensu feeders
ahead of opening 400kV lines. MS WRPC suggested that opening of 400kV lines before
220kV lines may cause severe disturbance and it would be difficult to prepare for the
Island with proper load generation balance. Therefore Sugen may remain connected with
the 400kV lines and the 400kV lines could be opened with the following changes in the
proposal at 10.2.
At 48.1 Hz OR (Freq<48.2 Hz .AND. time delay=0.15): 400kV Sugen-Unosugen and
400kV Sugen-Gandhar (Jhanor) lines will be tripped.
TPL/GETCO may update the progress.
Committee may like to note.
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 53
ITEM NO. 11: FOLLOW UP ITEMS:
11.1: Status of Bus Coupler and Bus Bar protections at S/s.
Back Ground: In the 118th PCM, Chairman TCC stated that the Bus Bar protection schemes
should be implemented by the respective utility, without expecting the funding under R&U
from MoP, GoI.In 121st PCM,WRLDC informed that BB protection at 7 Nos of 220kV S/Ss
(Single Bus S/Ss) in GETCO system, 3 Nos of 220kV S/Ss in MSPGCL system, 7 Nos of
220kV S/Ss in MPPTCL system & 5 Nos of 220kV S/Ss in CSPTCL system was pending.
In 123rd PCM, GETCO representative intimated that out of 7 substations, BB
protection was commissioned at 5 substations. In the 127th PCM, GETCO representative stated
that the BB protection at 220 KV Limdi substation would be commissioned by September 2016.
The BB protection at, 220 KV Navsari substation would be commissioned by March 2017.
MPPTCL representative intimated that BB protection relays were procured and commissioning
is under progress.
The updated status given by constituents in the 127th PCM is as follows;
1) Non Availability of Bus Bar protection at 220/132 kV Bhatapara S/s:CSPTCL
intimated that busbar protection is under tendering stage.
2) Bus Bar protection at 400/220 kV Korba West S/s: Regarding LBB/Bus Bar protection at
400/220 kV Korba West, 200/132 kV Korba East and 220 kV Korba East Extension, CSPTCL
intimated that busbar protection has been installed at 400/220 kV Korba West S/s & it is
under testing. He also intimated that busbar protection relay procured for Korba east
extension.
Constituents may update the position.
Committee may like to note.
ITEM NO. 12: Distance Protection Scheme settings at APL end on 400kVMundra- Sami
lines 1 & 2 :
In the 126th PCM, PGCIL representative stated that FSC is installed on 400kV Mundra-
Sami 1 & 2. However the DPS provided on the lines have not been set by factoring the FSC,
this may result in over reaching of the DPS schemes and therefore APL may factor in FSC, in
the settings of the distance protection schemes. APL representative stated that they are studying
the mutual coupling effect on zero sequence components during the faults and after detailed
Agenda for 128th PCM, to be held on 06.12.2016 & 07.12.2016 Page 54
study they would come up in the next PCM.
In the 126th PCM, the Committee suggested that the practice used by PGCIL, in setting the relay
of lines having FSC, be adopted by APL for time being and as & when the study by APL is
completed the same shall be shared by APL in the PCM for further discussions.
In the 127th PCM, APL representative stated that they still have observations on
adopting the settings as being adopted by PGCIL. He further requested that the matter be
discussed in a separate meeting. Committee suggested that a separate meeting be held in
Vadodara on the above issue.
The above meeting could not be held; therefore APL may give their observations
before the PCM.
Committee may like to discuss.
ITEM NO. 13: ANY OTHER ITEM.
ITEM NO. 14: DATE AND VENUE OF THE NEXT MEETING
Committee may like to decide the date and venue for next PCM (129th PCM).
POWERGRID WRTS-I
SN NAME OF LINE/ICTTRIPPING
DATETRIPPING
TIMERESTORATI
ON DATERESTORATI
ON TIMEREASON
1 400kV DHARIWAL TPP-PARLI II 2-Apr-16 17:29 3-Apr-16 11:44LINE TRIPPED DUE TO BROKEN OPGW & FALLING Y=PH CAUSING Y PH-EARTHFAULT AT 239KM FROMPARLI.
2 400kV KORBA-BHILAI I 3-Apr-16 13:28 3-Apr-16 14:50LINE A/R SUCCESSFUL AT BHILAI END ON Y PH TO E FAULT AT F. L. OF 71.99 KM FROM KORBA.F.C. -2.5 KA, LINE TRIPPED DUE M/s CSEB 11KV RAIL POLE, WHICH IS CREATING LOW CLEARANCEPROBLEM AT LOC.NO 277 (90KM FROM KORBA END).
3 400kV BHADRAVATI-PARLI I 5-Apr-16 18:18 5-Apr-16 18:18LINE A/R SUCCESSFUL AT BOTH END ON R-PH TO EARTH FAULT AT 51.78KM FROM BHADRAWATIHAVING FC OF 6.284KA AND 166.5KM FROM PARLI
4 400kV BHADRAVATI-PARLI I 5-Apr-16 19:23 5-Apr-16 19:23LINE A/R SUCCESSFUL AT BOTH END ON R-PH EARTH FAULT. F.C=6.2KA , F.L.=52KM FROM BVT END,378KM FROM PARLI END. F/C=1.17KA,
5 400kV KORBA-BHILAI I 5-Apr-16 18:40 5-Apr-16 20:36
LINE TRIPPED ON Y PH TO EARTH FAULT AT 91.73KM FROM BHILAI FC OF 3.674KA AND 93.19KMFROM KORBA. LINE TRIPPED DUE M/s CSEB 11KV RAIL POLE, WHICH IS CREATING LOW CLEARANCEPROBLEM AT LOC.NO 277 (90KM FROM KORBA END). THE POLE HAS BEEN REMOVED INCOORDINATION WITH CSEB.
6 400Kv PARLI-PUNE(GIS)_1 5-Apr-16 16:00 5-Apr-16 16:51LINE TRIPPED ON Y PH EARTHFAULT AT 174KM FROM PUNE GIS FAULT CURRENT 1.8KA AND 84.11KMFROM PARLI END.
7 400kV SATPURA-SEONI 6-Apr-16 21:00 6-Apr-16 21:42 LINE TRIPPED DUE TO RELAY MAL OPERATION AT SATPURA MPPTCL END.
8 400kV BHILAI-SEONI 9-Apr-16 16:39 9-Apr-16 17:24 LINE TRIPPED ON B PH TO E FAULT AT F.L. OF 13.7 KM FROM SEONI.
9 400kV KORBA-BHILAI II 9-Apr-16 9:59 9-Apr-16 12:59 LINE TRIPPED DUE TO HEAVY SPARKING IN MAIN BAY AT BHILAI CSPTCL END.
10 400kV SATPURA-SEONI 9-Apr-16 16:39 9-Apr-16 17:19 LINE TRIPPED ON B PH TO E FAULT AT F.L. OF 13.7 KM FROM SEONI.
11 400kV SATPURA-SEONI 10-Apr-16 12:56 10-Apr-16 16:36 LINE TRIPPED ON B PH TO E FAULT AT F.L. OF 14.5 KM FROM SEONI.
12 400kV BHILAI-SEONI 13-Apr-16 13:36 13-Apr-16 14:17LINE TRIPPED AT 13:36HRS ON Y PH-EARTH FAULT FL 40.3KM FC 7.32 KA FROM SEONI, & FL 497.8KMFC 1.692 KA FROM BHILLAI
13 400kV RAIGARH-STERLITE IV 13-Apr-16 13:55 13-Apr-16 14:44 LINE TRIPPED AT STARLITE END ONLY DUE TO TRIPPING OF TIE BAY CB DURING A/R OF STARLITE -ROURKELA END. AT STARLITE LINE IS ON BUS-1 THROUGH TIE BAY ONLY. SUSPECTED PROBLEM MAYBE RELAY SCHEME AT STARLITE END.INCLUDED. NO DT SIGNAL RECEIVED AT RAIGARH
14 400kV SATPURA-SEONI 16-Apr-16 4:01 16-Apr-16 4:27LINE TRIPPED ON B PHASE TO E/F LINE. A/R SUCCESSFULLY AT SEONI END WHILE LINE TRIPPED FROMSATPURA END. A/R UNSUCESSFUL AT SATPURA MPPTCL END. LINE BELONGS TO M/S MPPTCL.
15 400kV KSK-RKKML III 17-Apr-16 21:13 17-Apr-16 22:24LINE TRIPPED AT RKMPPL END ONLY. A/R SUCCESSFUL AT KSK END DUE TO B PH EARTHFAULT AT3.58KM FROM KSK AND FC- 985A. A/R WAS DISABLED AT RKMPPL END.
SN NAME OF LINE/ICTTRIPPING
DATETRIPPING
TIMERESTORATI
ON DATERESTORATI
ON TIMEREASON
16 765KV DURG PS - D'JAIGARH 17-Apr-16 21:20 17-Apr-16 22:48LINE TRIPPED DUE TO Y PH EARTH FAULT AT 132KM FROM D'GARH. FC - 10.9KA AT D'GARH END AND7.2KA AT DURG END.
17 400kV RAIGARH-IBEUL I 22-Apr-16 15:30 22-Apr-16 17:47LINE TRIPPED DUE TO R PH EARTHFAULT AT 93.1KM FROM RAIGARH END F/C OF 2.69KA & 10.52 KMFROM IND BARATH. FAULT LOCATION IS IN THE LILO PORTION OF IND BARATH.
18 400kV RAIGARH-IBEUL I 23-Apr-16 13:57 23-Apr-16 14:12 LINE TRIPPED DUE TO R PH EARTHFAULT AT 94.2KM FROM RAIGARH END F/C OF 3.06KA.
19 400kV RAIPUR-KWPCL II 25-Apr-16 16:41 25-Apr-16 17:57LINE TRIPPED ON LINE REACTOR BUCKHOLZ PROTECTION OPERATED DUE TO DC EARTH FAULT ATRAIPUR END
20 400kV RKKML-RAIGARH III 26-Apr-16 20:26 26-Apr-16 20:41 LINE TRIPPED ON YPH-EARTH FAULT. F/L=1.3KM & F/C=12.8KA FROM RKKML
21 400kV BHADRAVATI-PARLI I 27-Apr-16 21:14 27-Apr-16 21:14LINE A/R SUCESSFULLY FROM BOTH END ON R-PH AT A DISTANCE OF 308KM (M1) & 316KM(M2)FROM PARLI END.
22 400Kv PARLI-PUNE(GIS)_2 27-Apr-16 19:44 27-Apr-16 20:00LINE TRIPPED ON R PH EARTH FAULT AT F/L=269KM & F/C= 1.2KA FROM PUNE GIS AND F/L=7.7 KM& F/C= 13.5KA FROM PARLI.
23 400kV RKKML-RAIGARH III 27-Apr-16 20:50 27-Apr-16 21:05LINE TRIPPED ON Y PH EARTHFAULT AT 1.72KM FROM RKM AND 21.8KM FROM RAIGARH HAVING FCOF 13.1KA.
24 400kV VINDHYACHAL-KORBA II 27-Apr-16 13:30 27-Apr-16 19:40LINE TRIPPED DUE TO HEAVY RAIN & THUNDER NEAR TO V'CHAL AREA ON M1- R PH E FAULT & M2 -Y PH E FAULT AT 287.7KM FROM KORBA AND Y PH E FAULT AT 14.36KM FROM V'ÇHAL HAVING FC OF17.44KA.
25 765kV SEONI-WARDHA I 29-Apr-16 1:25 29-Apr-16 1:58LINE TRIPPED ON BPH-E FAULT AT 141.6KM FC-4.48 FROM WARDHA AND 98KM FROM SEONI END FCOF 5.49KA.
26 400kV RAIPUR-BHADRAVATI II 4-May-16 19:08 4-May-16 19:22LINE AUTO RECLOSED AT BHADRAWATI END DUE TO TRIPPING ON B PHASE FAULT. MAIN-1 (REL670)RELAY OPERATED ON ZONE-2 WITH CARRIAR RECEIVE FROM RAIPUR END WITH FAULT CURRENT 1.8KA
27 400kV RKKML-RAIGARH III 4-May-16 20:03 4-May-16 20:13LINE AUTO RE CLOSED SUCCESSFUL FROM BOTH END, BUT FAULT PERSISTED AND TRIPPED DUE TO RPH TO EARTH FAULT. FC-18.6 KA, FD-8.4 KMS FROM RAIGARH END.. LINE TRIPPED DUE TO LESSCLEARANCE BETWEEN OPGW PILOT WIRE & Y-PHASE
28 400kV BHADRAVATI-CHANDRAPUR IV 5-May-16 19:53 5-May-16 21:23LINE AUTO RECLOSED ON B PHASE TO EARTH FAULT BUT TRIPPED ON FAULT AGAIN IN RECLAIMETIME. DURING TRIIPING HEAVY LIGHTNING AND RAINS IN BHADRAWATI AREA. MAIN-1= FL=7.28KMIB=13.83KA,
29 400kV BHADRAVATI-PARLI I 5-May-16 18:04 5-May-16 18:04LINE A/R SUCESSFULLY ON B-PH TO EARTH FAULT AT BOTH ENDS FAULT DISTANCE 187.8KM FROMPARLI.
30 400kV BHADRAVATI-PARLI I 5-May-16 18:10 5-May-16 19:10LINE TRIPPED ON Y-PH TO EARTH FAULT AT DISTANCE OF 207KM FROM PARLI & FROM BHADRAWATIEND MAIN-1= FL=137KM IY=2.8KA,
31 400kV BHADRAVATI-PARLI I 5-May-16 19:43 6-May-16 11:45LINE TRIPPED DUE TO LINE ISOLATOR R PH JUMPER DAMAGED AT BHADRAWATI END . RELAYINDICATION AT BHADRAWATI : MAIN-1= FL=-1.1KM IR=30.27KA,
SN NAME OF LINE/ICTTRIPPING
DATETRIPPING
TIMERESTORATI
ON DATERESTORATI
ON TIMEREASON
32 400kV DHARIWAL TPP-PARLI II 5-May-16 18:10 6-May-16 16:09LINE TRIPPED ON BPH E FAULT DUE TO OPGW PILOT ROPE BROKEN . F.L 206KM FROM PARLI END. &TRIPPED ON R-Y PHASE FAUL FROM PARLI END.
33 400KV VANDANA-BIRSINGHPUR 5-May-16 18:09 5-May-16 19:13 LINE TRIPPED ON B PH E FAULT . F.L - 145KM FROM BIRSINGPUR . F.C -2.18KA .
34 400KV VANDANA-BIRSINGHPUR 5-May-16 20:23 5-May-16 20:43LINE TRIPPED ON B PH E FAULT F.C -2KA FROM BIRSINGPUR . FAULT OCCURRED DUE TO ONE OPENYPH- SUBCONDUCTOR JUMPER AT LOC. 06 IN M/S VANDANA LILO PORTION INFORMED BY M/SVANDANA ON 13.05.16.
35 400kV WARDHA-MAUDA I 5-May-16 19:00 5-May-16 19:26LINE COULD NOT A/R ON RPH TO EARTH FAULT AS AUTO RECLOSED KEPT IN OFF POSITION FORCARRYING OUT ONLINE OPEGW WORK. RELAY INDICATION AT WARDHA S/S. MAIN-1:- ZONE-1 , RPH-GRN, 18.15KM , 16KA. MAIN-2 :- Z-1 OPTD., RPH-GRND, 18.15 KM , 16KA
36 400kV WARDHA-MAUDA II 5-May-16 18:53 5-May-16 19:49LINE AUTORECLOSED SUCESSFULLY FROM BOTH ENDS BUT TRIPPED FROM BOTH ENDS DUE TOFAULT IN RECLAIM TIME. RELAY INDICATION AT WARDHA S/S. MAIN-1:- ZONE-1 OPTD, BPH-GRND, 19KA, 11.5 KM.
37 765kV WARDHA - AURANGABAD(PG) I 6-May-16 18:01 7-May-16 10:38LINE TRIPPED DUE TO Y-B PH FAULT AT 23.7KM FROM WARDHA F/C= 22.2KA DUE TO FALLING OFSNAPPED EARTH WIRE ON PHASE CONDUCTORS AT LOC. NO. 70-71.
38 765kV WARDHA - AURANGABAD(PG) II 6-May-16 18:14 6-May-16 18:14LINE A/R SUCESSFULLY FROM BOTH ENDS ON BPH EARTH FAULT AT 22.2KM FROM WARDHA HAVINGFC OF 12.6KA.
39 765kV WARDHA - AURANGABAD(PG) II 6-May-16 18:15 6-May-16 18:15LINE A/R SUCESSFULLY FROM BOTH ENDS ON BPH EARTH FAULT AT 22.2KM FROM WARDHA HAVINGFC OF 12.6KA.
40 765kV WARDHA - AURANGABAD(PG) II 6-May-16 18:18 7-May-16 16:34LINE TRIPPED AFTER SUCESSFULLY A/R ON PERSISTANT BPH EARTH FAULT AT 22.2KM FROMWARDHA F/C= 12.6KA DUE TO FALLING OF SNAPPED EARTH WIRE AT LOC. 70-71 AND 296.3KM FROMA'BAD HAVING FC OF 1.9KA .
41 765kV WARDHA - AURANGABAD(PG) IV 6-May-16 18:32 6-May-16 18:37LINE TRIPPED AT WARDHA END DUE TO RELAY MAL-OPERATION DURING CHARGING OF 765KVWARDHA - AURANGABAD(PG) II LINE.
42 400Kv PARLI-PUNE(GIS)_1 11-May-16 18:51 11-May-16 23:15 LINE TRIPPED ON BUS BAR PROTECTION OPERATION
43 400Kv PARLI-PUNE(GIS)_2 11-May-16 18:51 11-May-16 21:16LINE TRIPPED ON BUS BAR PROTECTION OPERATION DURING HEAVY WIND , THUNDER & LIGHTINGAT PUNE(GIS).
44 400Kv PUNE(GIS)-PUNE(TALEGOAN)_1 11-May-16 18:45 11-May-16 18:45LINE A/R SUCCESSFUL AT PUNE END DUE TO Y PH EARTH FAULT AT 66.8KM FROM PUNE HAVING F/COF 2.85KA.
45 400Kv PUNE(GIS)-PUNE(TALEGOAN)_1 11-May-16 18:51 11-May-16 21:08 LINE TRIPPED ON BUS BAR PROTECTION OPERATION
46 400Kv PUNE(GIS)-PUNE(TALEGOAN)_2 11-May-16 18:42 12-May-16 9:47LINE TRIPPED ON Y PH- EARTH FAULT AT 36.9KM FROM PUNE F/C= 8.46KA. F/C - 7.9KA AT PUNE GIS.LINE TRIPPED DUE TO OPGW PILOT ROPE TOUCHING TO PHASE WIRE NEAR LOC. NO. 721 .
SN NAME OF LINE/ICTTRIPPING
DATETRIPPING
TIMERESTORATI
ON DATERESTORATI
ON TIMEREASON
47 400KV VANDANA-BIRSINGHPUR 11-May-16 15:42 11-May-16 17:24LINE TRIPPED BY DISTANCE PROTECTION Z 1, FC - ZERO & FL - 0.8 KM FROM VANDANA AND 144KMFROM BIRSINGHPUR. FAULT OCCURRED DUE TO ONE OPEN YPH- SUBCONDUCTOR JUMPER AT LOC.06 IN M/S VANDANA LILO PORTION.
48 400kV KOLHAPUR (MSETCL)- KOLHAPUR (GIS) II 13-May-16 15:59 13-May-16 16:14LINE TRIPPED DUE TO FAILURE OF B PHASE LINE CT AND OPERATION OF BUSBAR PROTECTION ATKOLHAPUR MSETCL END
49 400Kv PARLI-PUNE(GIS)_2 13-May-16 13:25 13-May-16 14:16LINE TRIPPED AT PUNE GIS ON R PH REACTOR DIFFERENTIAL PROTECTION OPERATION DURINGTIGHITNG OF LOOSE CT CONNECTION TERMINAL.
50 400kV RAIGARH-IBEUL I 13-May-16 1:08 13-May-16 2:37LINE TRIPPED FROM RAIGARH END ONLY ON BPH- EARTH FAULT UNDER ZONE-2 F/L= 86KM FROMRAIGARH.
51 400kV RAIPUR-KSK III 13-May-16 17:41 13-May-16 17:41LINE A/R SUCESSFULLY FROM BOTH ENDS ON BPH TO EARTH FAULT. F/L= 20KM FROM KSK & 152KMFROM RAIPUR. F/C=3.51KA.
52 400KV VANDANA-BIRSINGHPUR 13-May-16 15:48 13-May-16 17:54LINE TRIPPED ON B-PHASE TO E FAULT FD-0.8 KMS FROM VANDANA FC-2.1 KA .FAULT OCCURREDDUE TO ONE OPEN YPH- SUBCONDUCTOR JUMPER AT LOC. 06
53 765kV CHAMPA- KOTRA PS 13-May-16 19:19 13-May-16 20:17LINE TRIPPED DUE TO R PHASE TO Y PHASE FAULT. FC R PH=8.87KA, FC Y PH=8.87KA, FD=65KM FROMKOTRA END. FD=31.5KM FROM CHAMPA END.
54 400kV BHADRAVATI-CHANDRAPUR I 14-May-16 11:25 14-May-16 15:15LINE TRIPPED ON BPH TO EARTH FAULT F/L=8.74KM FROM BHADRAWATI DUE TO FIRE CAUSED BYBURNING OF GRASS BY VILLAGER/ FARMERS IN UNDERNEATH OF LINE AT LOC. NO. 885.
55 400kV RAIGARH-ROURKELA II 16-May-16 22:44 16-May-16 22:44LINE AUTO RE-CLOSD SUCCESSFULLY FROM BOTH END ON R=PH TO E FAULT F/C-1.9 KA,& F/L= 201.2KM FROM RAIGARH.
56 400kV KORBA-BALCO 17-May-16 17:39 17-May-16 18:35LINE TRIPPED ON B-PH EARTH FAULT AT BALCO F/C =5KA. F/L= 7.8KM FROM KORBA . FAULT IS INLILO PORTION OF M//S BALCO.
57 400kV KORBA-BHILAI I 17-May-16 17:23 17-May-16 18:28 LINE TRIPPED ON Y PH EARTH FAULT AT Z2 & 200KM FROM BHILAI F/C = 1.951KA
58 400kV KORBA-KORBA(WEST) 17-May-16 17:46 17-May-16 18:12 LINE TRIPPED ONLY AT KORBA CSEB END & HANGING FROM KORBA NTPC END.
59 400kV KORBA-RAIPUR IV 17-May-16 17:24 17-May-16 18:03 LINE TRIPPED ON B PH EARTH FAULT AT 215KM FROM RAIPUR F/C = 1.99KA. FL - 13KM
60 400kV KORBA-SIPAT 17-May-16 17:41 17-May-16 18:11LINE TRIPPED ONLY AT KORBA NTPC END & HANGING FROM SIPAT NTPC END.. FAULT OCCURREDDUE TO HEAVY WIND, THUNDERSTORM AND RAIN.
61 400kV RAIGARH-IBEUL I 17-May-16 1:05 17-May-16 1:41LINE TRIPPED ON B-E FAULT. F/C=6.2KA, F/L=56.7KM. LINE A/R SUCESSFULLY FROM BOTH ENDS BUTAFTER 1 SEC DT RECEIVED FROM REMOTE END AND TRIPPED DUE TO PROBLEM IN RELAY SCHEME ATIBEUL END.
62 765kV CHAMPA- KOTRA PS 17-May-16 18:44 17-May-16 22:07LINE TRIPPED ON TO Y PH - B PH FAULT AT 60.98KM FROM KOTRA PS F/C 8.7KA & 8.3KARESPECTIVELY. F/L =36.4KM FROM CHAMPA PS.
63 765kV D'JAIGARH-RANCHI II 17-May-16 18:10 17-May-16 19:16 LINE TRIPPED ON R-PH EARTH FAULT AT Z1 & 4KM FROM D'GARH F/C=14.6KA
SN NAME OF LINE/ICTTRIPPING
DATETRIPPING
TIMERESTORATI
ON DATERESTORATI
ON TIMEREASON
64 400kV DHARIWAL TPP-PARLI II 19-May-16 15:47 19-May-16 16:49 LINE TRIPPED ON Y-E, 83.8KM FROM PARLI F/C= 3.5KA.
65 765kV DURG PS -WARDHA_2 20-May-16 17:14 20-May-16 18:41LINE TRIPPED ON B PHASE TO E FAULT AFTER SUCESSFUL A/R, ,FC-11.7KA,FL-16 KM FROM DURG ANDFC-2.8KA,FL-370 KM FROM WARDHA END
66 400kV KORBA-BHILAI I 21-May-16 16:05 21-May-16 17:14 LINE TRIPPED ON R PHASE TO E FAULT FD-53.22 KMS FROM D'-JAYGARH END FC-5.607 KA
67 400kV RAIGARH-IBEUL I 21-May-16 18:02 21-May-16 20:15 LINE TRIPPED DUE TO BUS BAR PROTECTION OPERATED AT IBEUL END
68 400kV RAIPUR-DURG I 21-May-16 16:32 21-May-16 18:01 LINE TRIPPED ON Y PHASE TO B PHASE FAULT FD-22.5 KMS FROM DURG END FC-7.0KA
69 400kV RAIPUR-DURG II 21-May-16 16:41 22-May-16 10:39LINE TRIPPED DUE TO HEAVY WIND AND THUNDER STORM ON Y PHASE TO B PHASE FAULT FC-2.0KA , FD-1.0 FROM DURG END
70 400KV RAIPUR-WARDHA I 21-May-16 15:48 21-May-16 16:35 LINE TRIPPED ON B PHASE TO E FAULT FD-160 KMS FROM RAIPUR END FC-2.8 KA
71 400kV RKKML-RAIGARH III 21-May-16 16:58 21-May-16 18:44 LINE TRIPPEDON RPH-E FAULT . F.L -17KM FROM RKM END . F.C-2.4 KA.
72 765kV D'JAIGARH-RANCHI I 21-May-16 16:14 21-May-16 18:03 LINE TRIPPED ON R PHASE TO E FAULT FD-83.1 KMS FROM D'-JAYGARH END FC-3.0 KA
73 765kV D'JAIGARH-RANCHI II 21-May-16 16:04 21-May-16 23:08 LINE TRIPPED ON Y PHASE TO E FAULT FD-344 KMS FROM D'-JAYGARH END FC-2.2 KA
74 765KV DURG PS - D'JAIGARH 21-May-16 16:13 21-May-16 17:15 LINE TRIPPED ON B PHASE TO E FAULT FD-205 KMS FROM D'-JAYGARH END FC-3.4 KA
75 400kV DHARIWAL TPP-PARLI II 23-May-16 22:37 23-May-16 23:37LINE TRIPPED ON PERSISTANT FAULT AFTER SUCESSFUL A/R, DUE TO HEAVY WIND, THUNDERSTROM, LIGHTNING ON Y PH EARTH FAULT AT 86.8 KM FROM PARLI F/C= 3.7 KA..
76 400kV KORBA-BALCO 23-May-16 13:59 23-May-16 15:08 LINE TRIPPED DUE TO Y PH EARTH FAULT AT 12.2KM FROM BALCO F/C =5.35KA. JUMPER OPEN
77 400kV KORBA-VANDANA 23-May-16 13:59 23-May-16 15:17 LINE TRIPPED DUE TO Y PH EARTH FAULT AT 11.8KM FROM VANDANA F/C= 1.649KA.
78 765kV D'JAIGARH-RANCHI II 23-May-16 14:55 23-May-16 16:18LINE TRIPPED DUE TO B PH EARTH FAULT AT F/L=260KM FROM D'GARH F/C=2.4KA AND 133KM FROMRANCHI HAVING FC OF 2.6KA.
79 765kV PUNE(GIS)-SOLAPUR 24-May-16 18:25 24-May-16 19:00LINE A/R FROM BOTH ENDS BUT TRIPPED ON PERSISTANT FAULT DUE TO ON Y PH - E FAULT.FD=98.6KM, FC= 6.57KA AT SOLAPUR END AND FD=145 KM, FC= 2.43KA AT PUNE GIS END.
80 400kV RAIPUR-DURG I 25-May-16 14:23 25-May-16 14:23 A/R SUCCESSFULLY OPERATED AT BOTH ENDS ON B PH - E FAULT. FD=12KM FROM RAIPUR END
81 400kV VINDHYACHAL-KORBA II 27-May-16 11:50 27-May-16 13:25 LINE TRIPPED ONLY AT VINDHYACHAL END DUE TO BUS FAULT AT VINDHYACHAL..
82 400KV RAIPUR-KSK IV 28-May-16 12:26 28-May-16 13:39 LINE TRIPPED AT KSK END ONLY. DT RECEIVED AT RAIPUR.
83 765kV KOTRA PS-DURG PS I 28-May-16 19:23 29-May-16 20:37LINE TRIPPED DUE TO HEAVY WIND, THUNDERSTROM & LIGHTNING NEAR KOTRA PS CAUSING R-PHASE CVT JUMPER STUD OPENED LATER COLLIDED WITH TOP STACK DUE TO WHICH TOP STACK OFCVT GOT DAMAGED AND OIL SPLASHED ALL-AROUND AT KOTRA END
SN NAME OF LINE/ICTTRIPPING
DATETRIPPING
TIMERESTORATI
ON DATERESTORATI
ON TIMEREASON
84 400kV BHADRAVATI-CHANDRAPUR III 3-Jun-16 15:13 3-Jun-16 17:50 LINE TRIPPED ON BPH-EARTH FAULT, 2.7 KM FROM BHADRAWATI END, FC 22 KA
85 400kV BHADRAVATI-CHANDRAPUR IV 3-Jun-16 15:13 3-Jun-16 18:16 LINE TRIPPED ON B-E, 5.4 KM FROM BHADRAWATI END
86 400kV RAIGARH-ROURKELA II 3-Jun-16 16:45 4-Jun-16 11:15LINE TRIPPED OPGW WIRE FALL ON Y PHASE (TOP ) AT DISTANCE OF 10 KM (APPRX) FROMRAIGARH & F/C 19.76KA.
87 765kV AURANGABAD(PG)-SOLAPUR I 3-Jun-16 17:20 3-Jun-16 17:20A/R SUCCESSFULLY FROM BOTH ENDS ON R-PH TO EARTH FAULT, F/L=116KM F/C=4.3KA FROMSOLAPUR.
88 400kV DHARIWAL TPP-PARLI II 4-Jun-16 20:31 4-Jun-16 21:31 LINE TRIPPED ON Y-PH TO E FAULT. F/L -86KM & F/C-3.79KA FROM PARLI END .
89 400Kv AURANGABAD(MSETCL)-PUNE(GIS) II 5-Jun-16 18:51 5-Jun-16 18:51 A/R SUCESSFULLY ON YPH-E FAULT F.L-49.9KM FROM PUNE GIS. F.C-5.6KA.
90 400kV BHILAI-SEONI 5-Jun-16 18:05 5-Jun-16 18:05 A/R SUCESSFULLY ON RPH-E FAULT F.C-3.03KA. F.L-158.5KM FROM SEONI.
91 765kV SEONI-WARDHA I 5-Jun-16 07:27 5-Jun-16 11:30 LINE TRIPPED DUE TO L/R B PH BUCHHOLZ RELAY OPERATED AT WARDHA S/S.
92 400kV AURANGABAD (PG) -AKOLA I 6-Jun-16 05:47 6-Jun-16 6:28LINE A/R SUCCESSFUL AT AURANGABAD END,BUT TRIPPED AT MSETCL AKOLA END ON B PHASE TO EFAULT,FC-31.07KA,FL-8.8 KM FROM AKOLA END. PROBLEM IS SUSPECTED IN A/RCONFIGURATION OF TIE BCU AT AKOLA MSETCL.
93 400kV KORBA-MAHAN 6-Jun-16 19:33 6-Jun-16 20:20LINE TRIPPED ON Y PHASE TO E FAULTFC-1.9KA,FL-28 KM FROM MAHAN AND FL-208KM FROMKORBA END.
94 400kV LARA(NTPC)-KOTRA PS I 6-Jun-16 15:57 6-Jun-16 16:50 LINE TRIPPED ONLY AT KOTRA END DUE TO DT RECEIVED FROM LARA END.
95 765kV SEONI-WARDHA I 6-Jun-16 15:30 6-Jun-16 15:30LINE A/R SUCCESSFUL FROM BOTH ENDS ON B-PH TO EARTH FAULT. F/L=140.73KM AND FAULTCUREENT:4.6KA FROM WARDHA END. & F/L=M1:100.5 KM AND F/C=:4.9KA FROM SEONI.
96 765kV SEONI-WARDHA I 6-Jun-16 15:30 6-Jun-16 15:58LINE A/R SUCCESSFUL & THEN TRIPPED DUE TO HEAVY WIND, THUNDERSTROM & LIGHTNING ON BPHASE TO E FAULT,FC-4.6KA,FL-140.7 KM FROM WARDHA AND FC-4.9KA,FL-100.5 KM FROM SEONIEND .
97 400kV BHADRAVATI-PARLI I 7-Jun-16 12:53 7-Jun-16 20:17LINE TRIPPED ON R PH EARTH FAULT AFTER SUCCESSFUL A/R AT BOTH END. FD - 8.6KM FROM BVTAND 254.7KM FROM PARLI. FC - 20KA AT BVT. LINE TRIPPED DUE TO HANGING OF OPGW PILOTROPE.
98 765kV TAMNAR PS-KOTRA PS I 7-Jun-16 18:10 7-Jun-16 18:10LINE SUCCESSFUL AUTO RECLOSE FROM BOTH ENDS ON R-E PH FAULT . FAULT DISTANCE =27.4 KM& F/C=5.05KA FROM TAMNAR .
99 400kV DHARIWAL TPP-PARLI II 8-Jun-16 05:11 8-Jun-16 7:29LINE A/R SUCCESSFUL AND THEN TRIPPED DUE TO HEAVY WIND, THUNDERSTROM & LIGHTNING ONB-E, FC-1.8KA,FL-194.9KM FORM PARLI & FC-2.58KA,FL-149 KM FROM DHARIWAL END.
100 400kV RAIPUR-WARDHA I 9-Jun-16 3:04 9-Jun-16 3:04LINE A/R SUCCESSFULLY ON Y PH TO FAULT,FD-265 KM FROM WARDHA AND 127 KM FROM RAIPUREND,
101 400kV DHARIWAL TPP-PARLI II 11-Jun-16 17:21 11-Jun-16 17:40LINE TRIPPED ON R PH - B PH FAULT, FL-216.39 KM FROM PARLI END, FC R PH 2.83 KA, Y PH 2.48KA.LINE CHARGING
SN NAME OF LINE/ICTTRIPPING
DATETRIPPING
TIMERESTORATI
ON DATERESTORATI
ON TIMEREASON
102 400kV DHARIWAL TPP-PARLI II 12-Jun-16 13:37 13-Jun-16 0:43 LINE TRIPPED ON R PH - B PH FAULT, FL-216.39 KM FROM PARLI END, FC R PH 2.83 KA, Y PH 2.48KA.
103 400kV RAIGARH-ROURKELA II 16-Jun-16 13:09 16-Jun-16 13:51LINE TRIPPED BY R-Y PH TO PH FAULT AT 70KM FROM RAIGARH F/C =3.8KA AND 127KM FROMROURKELA. 02 NOS TOWER COLLAPSE WAS FOUND IN THE STERLITE LILO PORTION (LINE OWNED BYSTERLITE).
104 400kV WARDHA-MAUDA I 17-Jun-16 15:22 17-Jun-16 16:45LINE TRIPPED ON Y PH-E FAULT DUE TO HANGING OF OPGW PILOT ROPE, FL- 64.2 KM FROMWARDHA END. F.C=6.6 KA. A/R WAS IN NON-AUTO MODE FOR OPGW WORKS.
105 400Kv PUNE(GIS)-PUNE(TALEGOAN)_4 20-Jun-16 1:38 20-Jun-16 2:35LINE TRIPPED DUE TO HEAVY WIND, THUNDERSTROM & LIGHTNING ON Y PH-E FAULT,FC-6.9KA AT TALEGAON, F/L=40KM FROM PUNE TALEGOAN
106 400kV DHARIWAL TPP-PARLI II 21-Jun-16 17:42 21-Jun-16 18:48 LINE TRIPPED ON Y PHASE TO E FAULT,FC-3.9KA,FL-82.8KM FROM PARLI END.
107 765kV BILASPUR-SIPAT II 21-Jun-16 16:57 21-Jun-16 18:53 LINE TRIPPED FROM SIPAT NTPC END. DT RECEIVED AT BILASPUR END.
108 400kV KORBA-RAIPUR III 22-Jun-16 19:05 22-Jun-16 21:09LINE TRIPPED AT KORBA END ONLY DUE TO RELAY MAL-OPERATION AT KORBA END.LINE WAS INCHARGED CONDITION FROM RAIPUR END.
109 400kV LARA(NTPC)-KOTRA PS II 23-Jun-16 19:57 23-Jun-16 20:15 LINE TRIPPED DUE TO B PH EARTHFAULT AT 19.8KM FROM KOTRA PS HAVING FC OF 16.1KA.
110 400kV RAIGARH-KOTRA PS II 23-Jun-16 20:30 23-Jun-16 21:18 LINE TRIPPED AT RAIGARH END ONLY DUE TO B PH EARTHFAULT HAVING FC OF 9.6KA.
111 765kV TAMNAR PS-KOTRA PS II 23-Jun-16 19:57 23-Jun-16 20:13 LINE TRIPPED AT KOTRA PS END ONLY .A/R SUCCESSFULLY OPTD. AT TAMNAR
112 400kV KORADI-SATPURA 25-Jun-16 14:58 25-Jun-16 21:42LINE TRIPPED DUE TO HANGING OF OPGW PILOT ROPE AT LOC NO 710 ON R PHASE TO E FAULT, F.D185.7 MTR, F.C 22.5 KA AT KORADI END.
113 400kV BHILAI-BHATAPARA 26-Jun-16 18:44 26-Jun-16 19:36 LINE TRIPPED ON Y PHASE TO E FAULT F.D 11.8KM FROM BHATAPARA END, F.C 5KA AT BHILAI END
114 400kV RAIPUR-WARDHA II 26-Jun-16 17:28 26-Jun-16 17:28A/R SUCCESSFULLY OPERATED AT BOTH ENDS ON B PHASE TO E FAULT. F.C 5.5KA, F.D 88.5 KM FROMWARDHA END
115 765kV DURG PS- CHAMPA_1 1-Jul-16 19:44 1-Jul-16 23:40LINE TRIPPED ON Y-B PH FAULT AT ZONE -2 FROM DURG PS HAVING FC OF Y PH 6.196KA & B PH6.184KA AT RAIPUR(DURG).
116 400kV RAIPUR-RAIGARH II 6-Jul-16 7:48 6-Jul-16 11:14 LINE TRIPPED ON RPH-E FAULT DUE TO TCSC VALVE SYSTEM FAILURE / FIRE CAUGHT AT RAIPUR END
117 765kV DURG PS- CHAMPA_1 9-Jul-16 12:33 9-Jul-16 12:33 LINE A/R SUCESSFULLY F/L=117KM FROM DURG PS.
118 400kV AURANGABAD (PG) -AKOLA II 12-Jul-16 13:03 12-Jul-16 21:14LINE TRIPPED DUE DC SUPPLY EXTENDING TO RELAY WHILE RECTIFICATION OF CONTROL CABLES ATAURANGABAD END
119 765kV WARDHA - AURANGABAD(PG) I 13-Jul-16 17:13 13-Jul-16 17:36LINE TRIPPED ONLY AT WARDHA END DUE TO DT SENT FROM AURANGABAD. DT SEND CONTACT INAUXILARY SWITCH OF TIE BREAKER (SIEMENS MAKE) GOT FAULTY DUE TO THE CORROSION PROBLEMAT A'BAD.
SN NAME OF LINE/ICTTRIPPING
DATETRIPPING
TIMERESTORATI
ON DATERESTORATI
ON TIMEREASON
120 765kV WARDHA - AURANGABAD(PG) II 15-Jul-16 13:58 15-Jul-16 14:48LINE TRIPPED ON REF PROTECTION DUE TO DC EARTH LEAKAGE DURING RECTIFICATION OF CABLEWORKS AT AURANGABAD END.
121 400kV RAIPUR-RAIGARH II 21-Jul-16 23:33 21-Jul-16 23:33LINE AUTO RECLOSED SUCCESSFULLY ON BPH- EARTH FAULT, 2.9 KA, 129.3 KM FROM RAIGARH END.REMOTE END: MAIN-1 --B- PHASE, 80.5 KM, 04.31 KA. MAIN-2 – 78.82 KM. END
122 400kV KORBA-KORBA(WEST) 22-Jul-16 1:14 22-Jul-16 3:24 LINE TRIPPED AT KORBA NTPC END ONLY.
123 400kV WARDHA-PARLI II 23-Jul-16 17:32 23-Jul-16 17:32 LINE AUTO-RECLOSURE SUCCESSFUL ON R-E FAULT AT F/L24.66KM, F/C=12.4KA.
124 400kV WARDHA-PARLI I 30-Jul-16 22:09 30-Jul-16 22:51LINE TRIPPED ON . Y-E FAULT , 141KM FROM WARDHA, 3.6KA. A/R SUCESSFUL AT PARLI END BUTUNSUCESSFUL AT WARDHA END,
125 765kV D'JAIGARH-BILASPUR 30-Jul-16 12:32 30-Jul-16 13:29LINE TRIPPED AT BILASPUR END ONLY . DT RECEIVED AT BILASPUR. MAIN BAY SHUTDOWN WASAVAILED AT DHARAMJAYGARH.
126 400kV BHADRAVATI-PARLI I 31-Jul-16 15:49 31-Jul-16 23:52LINE TRIPPED DUE TO FALLING OPGW WIRE ON CONDUCTOR , FD -4.27 KMS,(FROM BVT END) FC-24.8 KA , Y PHASE TO E/F, PARLI END DETAILS:- FD- 378.2 KMS, FC-1.0 KA ,Y PH TO E/F.
127 400kV RAIGARH-STERLITE IV 2-Aug-16 4:30 2-Aug-16 4:30 LINE A/R SUCESSFULLY FROM BOTH ENDS ON -R- PHASE, 3.74 KA, 104.5 KM FROM RAIGARH END.
128 765kV D'JAIGARH-BILASPUR 3-Aug-16 12:54 3-Aug-16 13:22 LINE TRIPPED AT BILASPUR END ONLY BY DT RECEIVED FROM D'GARH DUE TO PLCC MAL OPERATION
129 400kV AURANGABAD (PG) -AKOLA II 5-Aug-16 18:33 5-Aug-16 20:20 LINE TRIPPED DUE TO MALOPERATION OF BPL MAKE PLCC CHANNEL-1 AT AURANGABAD END.
130 400kV KOLHAPUR (MSETCL)- KOLHAPUR (GIS) I 9-Aug-16 11:45 9-Aug-16 12:53 LINE TRIPPED AT KOLHAPUR MSETCL END ONLY DUE TO PLCC PANEL MALOPERATION.
131 400kV RAIGARH-JHARSUGUDA III 10-Aug-16 5:22 10-Aug-16 15:37 LINE TRIPPED ON . R-Y , R -8.9 KA, Y - 12.43 KA, 31.5 KM FROM RAIGARH END
132 400kV RAIGARH-STERLITE IV 10-Aug-16 5:22 10-Aug-16 5:22LINE A/R SUCESSFULLY FROM BOTH ENDS ON -R- PHASE, R- PHASE, 7.3 KA, 25.11 KM FROM RAIGARHEND.
133 765kV TAMNAR PS-KOTRA PS II 15-Aug-16 15:25 15-Aug-16 15:25LINE A/R SUCESSFULLY FROM BOTH ENDS ON B PH. F/C=5.56 KA AND FAULT DISTANCE IS 15.29 KMFROM TAMNAR PS.
134 400kV KORBA-BIRSINGHPUR 16-Aug-16 23:12 16-Aug-16 23:30 LINE TRIPPED AT ONLY BIRSINGPUR END, DUE TO CB PROBLEM AT BIRSINGPUR MPPTCL END.
135 765kV CHAMPA- KOTRA PS 17-Aug-16 10:48 17-Aug-16 10:48
LINE A/R SUCESSFULLY FROM BOTH ENDS ON Y PH - B PH, FAULT CURRENT = 8.8 KA & FAULTLOCATION = 60.98 KM FROM KOTRA PS END.
136 400kV BHATAPARA-KORBA 22-Aug-16 6:44 22-Aug-16 8:06LINE SUCESSFULLY A/R FROM BHATAPARA END BUT A/R RELAY FAILED TO OPERATE AT KORBA NTPCEND, HENECE LINE TRIPPED ON TRANSIENT B PHASE TO E FAULT ONLY AT KORBA END. F/C=2.4KA &F/D=96KM FROM BHATAPARA END.
SN NAME OF LINE/ICTTRIPPING
DATETRIPPING
TIMERESTORATI
ON DATERESTORATI
ON TIMEREASON
137 400kV AURANGABAD (PG) -AKOLA I 25-Aug-16 18:42 25-Aug-16 19:20LINE CBS OPEND AT AKOLA END ONLY ON RECEIPT OF DT, LINE IS IN CHARGED CONDITION FROMAURANGABAD END.
138 400kV RAIGARH-IBEUL I 25-Aug-16 18:53 25-Aug-16 18:53LINE A/R SUCESSFULLY FROM BOTH ENDS ON YPH-EARTH FAULT AT F/L=30.9 KM & 9.5KA FROMRAIGARH END.
139 400kV RAIGARH-KOTRA PS II 25-Aug-16 8:55 25-Aug-16 8:55LINE A/R SUCESSFULLY FROM BOTH ENDS ON YPH-EARTH FAULT AT F/L=2 KM & 19.2KA FROMRAIGARH END.
140 400kV RAIPUR-RAIGARH I 25-Aug-16 14:53 25-Aug-16 14:53LINE A/R SUCESSFULLY FROM BOTH ENDS ON RPH-EARTH FAULT AT F/L=185 KM & 2.1KA FROMRAIGARH END.
141 400kV RAIPUR-RAIGARH II 25-Aug-16 9:26 25-Aug-16 9:26LINE A/R SUCESSFULLY FROM BOTH ENDS ON YPH-EARTH FAULT AT F/L=5.4 KM & 22.9KA FROMRAIGARH END.
142 400kV RAIPUR-SIPAT III 25-Aug-16 13:39 25-Aug-16 15:41LINE A/R SUCCESSFUL AT RAIPUR END , BUT TRIPPED AT ONLY SIPAT END ON Y PH - E FAULT,FC-3.66KA,FL-90 KM FROM RAIPUR END.
143 400kV KORBA-BIRSINGHPUR 30-Aug-16 00:57 30-Aug-16 5:41 LINE TRIPPED DUE TO R-PH TO GROUND FAULT, F.L. - 47.9 KMS FROM KORBA, F.C.- 6.365 KA,
144 400kV KORBA-BIRSINGHPUR 30-Aug-16 20:57 30-Aug-16 22:30LINE TRIPPED DUE TO R PH EARTH FAULT AT 51KM FROM KORBA HAVING FAULT CURRENT OF 6.64KAAND 166.5KM FROM BIRSINGHPUR HAVING FAULT CURRENT OF 1.956KA
145 400kV RAIGARH-STERLITE IV 30-Aug-16 15:56 30-Aug-16 16:27LINE TRIPPED DUE TO HEAVY WIND, LIGHTNING, THUNDERSTORM AND HEAVY RAIN , BPH TO E/F, FC-13.7 KA, FL- 124.4 KMS FROM RAIGARH
146 400kV RAIPUR-BHADRAVATI II 30-Aug-16 14:25 30-Aug-16 14:25A/R SUCCESSFULLY OPERATED FROM BOTH ENDS ON Y PH TO E/F. F/C-1.83 KA, F/L- 215 KMS FROMRAIPUR
147 400kV VANDANA-BIRSINGHPUR 30-Aug-16 02:35 30-Aug-16 5:18 LINE TRIPPED DUE TO R-PH TO GROUND FAULT, F.L. - 128.5 KMS FROM BIRSINGHPUR, F.C.- 0.59KA,
148 400kV WARDHA-MAUDA II 30-Aug-16 11:46 30-Aug-16 16:38LINE TRIPPED DUE SCRAP/ GRASS BURNT BY THE FARMER AT LOCATION NO. 222, BELOW THETOWER. HEAVY SMOKE WAS APPEARED CLOSED TO CONDUCTOR & HAS GOT SPARK, Y PH - E FAULT,F.C = 9.0 KA, F.D = 42 KM FROM WARDHA END
149 400kV KORBA-MAHAN 31-Aug-16 14:16 31-Aug-16 17:27LINE TRIPPED ON RPH TO E FAULT. FD-9.230 KMS FC-21.8 KA FROM NTPC KORBA DUE TO HEAVYWIND AND LIGHTNING.
150 400kV WARDHA-MAUDA I 31-Aug-16 16:26 31-Aug-16 19:31LINE TRIPPED ON Y-B PHASE FAULT DURING INSTALLATION OF OPGW IN PLACE OF E/W.FD-4.27 KMSFC-37.5 KA FROM WARDHA END.
151 400kV LARA(NTPC)-KOTRA PS I 3-Sep-16 21:24 3-Sep-16 23:36 LINE TRIPPEDON R-E FAULT , Z1 ,FC-3.0KA,F/L=5.1Km FROM KOTRA PS.
152 400kV LARA(NTPC)-KOTRA PS II 3-Sep-16 21:24 3-Sep-16 23:36 LINE TRIPPED ON R-E FAULT , Z1 ,FC-29.1KA,F/L=5.1Km FROM KOTRA PS.
153 400kV KORADI-SATPURA 6-Sep-16 16:59 6-Sep-16 19:35 BUS BAR PROTECTION OPERATED AT SATPURA END. DT RECEIVED AT KORADI
154 400kV DHARIWAL TPP-PARLI II 7-Sep-16 21:54 8-Sep-16 00:29 REACTOR DIFFERENTIAL PROTECTION, R PH OPERATED AT PARLI END
155 765kV KOTRA PS-DURG PS I 12-Sep-16 2:32 12-Sep-16 3:34LINE TRIPPED ON Y-E, 0KM FROM DURG,13.2KA FROM DURG END. LINE WAS TRIPPED DUE TOFAILURE OF Y-PH-LA AT DURG PS.
SN NAME OF LINE/ICTTRIPPING
DATETRIPPING
TIMERESTORATI
ON DATERESTORATI
ON TIMEREASON
156 400kV BHADRAVATI-DHARIWAL TPP II 13-Sep-16 15:31 13-Sep-16 15:55 LINE TRIPPED ONLY AT DHARIWAL END DUE TO PLCC CARD FAILURE AT DHARIWAL END
157 400kV RAIPUR-WARDHA II 13-Sep-16 14:41 13-Sep-16 14:41 LINE AUTO RECLOSED SUCESSFULLY ON B PH-E FAULT . F.L- 34KM FROM WARDHA . F.C- 8.9KA.
158 400kV RAIPUR-WARDHA II 14-Sep-16 18:06 15-Sep-16 10:58LINE TRIPPED ON 3 PH EARTH FAULT AT 146KM FROM WARDHA HAVING F/C OF 6 KA AND 252KMFROM RAIPUR HAVING FC OF 3.704 KA. 3-PH FAULT WAS DUE TO SNAPPING OF EARTH WIRE ATLOCATION NO:652-653 (AT RIVER CROSSING).
159 400kV AURANGABAD (PG) -AKOLA I 15-Sep-16 19:45 15-Sep-16 20:36LINE TRIPPED AT AKOLA END ONLY. A/R SUCCESSFULLY OPERATED AT A'BAD BUT FAILED AT AKOLAEND. R PH E-FAULT AT 24.75KM FROM A'BAD HAVING FC OF 12.3KA. 226KM FROM AKOLA HAVING FCOF 1.99KA
160 400kV KOLHAPUR (GIS)-MAPUSA I 17-Sep-16 3:43 17-Sep-16 06:30LINE TRIPPED DUE TO BLASTING OF CB POLE AND BUS BAR TRIPPED AT 400KV MSETCL KOLHAPURS/S.
161 400kV KOLHAPUR (MSETCL)- KOLHAPUR (GIS) I 17-Sep-16 3:43 17-Sep-16 05:11LINE TRIPPED DUE TO BLASTING OF CB POLE AND BUS BAR TRIPPED AT 400KV MSETCL KOLHAPURS/S.
162 400kV KOLHAPUR (MSETCL)- KOLHAPUR (GIS) II 17-Sep-16 3:43 17-Sep-16 07:47LINE TRIPPED DUE TO BLASTING OF CB POLE AND BUS BAR TRIPPED AT 400KV MSETCL KOLHAPURS/S.
163 400kV VANDANA-BIRSINGHPUR 18-Sep-16 16:27 18-Sep-16 18:09LINE TRIPPED ONLY AT VANDANA END ONLY ON Y PH-E FAULT.A/R OPERATED AT BIRSINGHPUREND,FC-1.75KA,FL-92.9 KM FROM VANDANA END.
164 400kV BHADRAVATI-PARLI I 21-Sep-16 21:32 22-Sep-16 23:05LINE TRIPPED ON Y PH TO E FAULT,FC-7.3KA,FL-34.3 KM FROM PARLI & FC-1.235KA,FL-338.95 KMFROM BVT END INSULATOR DECAPPED AT LOC 912
165 400kV LARA(NTPC)-KOTRA PS I 21-Sep-16 17:56 21-Sep-16 20:04LINE TRIPPED DUE TO R PH TO EARTH FAULT AT LARA (NTPC) END.F/L=19.98KM,F/C=12KAMP FROMKOTRA.
166 400kV LARA(NTPC)-KOTRA PS II 21-Sep-16 17:56 21-Sep-16 19:22LINE TRIPPED DUE TO R PH TO EARTH FAULT AT LARA (NTPC) END.F/L=19.98KM,F/C=8.4KAMP FROMKOTRA.
167 765kV WARDHA - AURANGABAD(PG) II 23-Sep-16 14:48 23-Sep-16 17:06LINE TRIPPED AT A'BAD ON RELAY MALOPERATION DUE TO DC SOURCE 1 SWITCHED OFF FORMEGGERING. DT RECD BY WARDHA
168 400kV BHILAI-KORADI 24-Sep-16 16:55 24-Sep-16 16:55A/R successful at both end on 400kV Koradi - Bhilai line at 16:55hrs due to R Ph G Fault at 9.8kMfrom Koradi having FC of 11.12kA
169 400kV RAIPUR-BHADRAVATI II 24-Sep-16 19:57 24-Sep-16 19:57A/R successful at both end on 400kV Raipur - BVT ckt-2 at 19:57hrs due to Y Ph G Fault at 218.36kMfrom Raipur having FC of 1.85kA
170 400kV RAIPUR-WARDHA I 24-Sep-16 21:37 24-Sep-16 21:37A/R successful at both end on 400kV Raipur - Wardha ckt-1 at 21:37hrs due to B Ph G Fault at 153kMfrom Wardha having FC of 3.1kA
171 400kV RAIPUR-WARDHA I 24-Sep-16 22:06 25-Sep-16 0:02LINE TRIPPED DUE TO B PHASE TO EARTH FAULT, FC- 5.164KA,FD-84.19KM FROM RAIPUR END &F/L=254.1kM, F.C-2kA FROM WARDHA UNDER ZONE-2.
172 400kV RAIGARH-IBEUL I 27-Sep-16 15:45 28-Sep-16 17:05LINE TRIPPED ON B PHASE TO E FAULT,FC-5.05KA,FL-78.9KM FROM RAIGARH & 6.6 KM FROM IBEULEND.
173 765kV D'JAIGARH-RANCHI I 28-Sep-16 11:50 28-Sep-16 13:29LINE TRIPPED ON DC SUPPLY EARTH FAULT AND DC SUPPLY FLACTUATION RESULT TO GROUP RELAYOPERATED AT DHARAMJAYGARH S/S
SN NAME OF LINE/ICTTRIPPING
DATETRIPPING
TIMERESTORATI
ON DATERESTORATI
ON TIMEREASON
174 765kV DURG PS -WARDHA_2 29-Sep-16 13:16 30-Sep-16 18:34LINE TRIPPED ON B-E, FC-3.0KA,F/D 238KM & F/C=3KA FROM WARDHA . CONDUCTOR SNAPPED ATLOC. 339
ANNEXURE - 3
DATE TIME DATE TIME
1400 KV SINGAJI - CHHEGAON FDR
27.04.2016 16.49 Hrs. 27.04.2016 17.23 Hrs. In service DT received.
2400 KV SINGAJI - JULWANIA FDR
28.04.2016 07.21 Hrs. 28.04.2016 08.44 Hrs. In service Line Tripped due to 'B & C' phase fault, Z-1 optd.
3 400 KV SARNI- ISP FDR 02.04.2016 15.53 Hrs. 02.04.2016 16.47 Hrs. In service Line Tripped due to 'Y' phase fault, Z-1 optd.
4 210 MW unit no. 9 of STPS 06.04.2016 21.00 Hrs. 08.04.2016 09.05 Hrs. NA
Due to stuckup of Generator breaker didn't tripped therefore LBB initiatedand cleared fault through bus bar Zone-1 protection . Following element onBus-I were tripped & cleared the fault :400 KV Sarni-ISP fdr, 400 KV Sarni-Seoni fdr, 400KV Sarni-Ashta fdr-1,400KV Bus Reactor-1, 400KV Bus Coupler, Station transformer-11 andunt#10. The details are as below:
( a ) 400 KV BUS COUPLER 06.04.2016 21.00 Hrs. 06.04.2016 21.14 Hrs. NA Line tripped on Bus bar Zone-1 operated due to Unit 9 Local breaker backup protection operated.
( b ) 400 KV SARNI- SEONI FDR 06.04.2016 21.00 Hrs. 06.04.2016 21.42 Hrs. In service do
( c ) 400 KV SARNI- ISP FDR 06.04.2016 21.00 Hrs. 06.04.2016 21.55 Hrs. In service do
( d ) 400 KV BUS REACTOR-1 (63 MVAR) 06.04.2016 21.00 Hrs. 06.04.2016 22.05 Hrs. NA do
( e ) 400 KV SARNI- ASHTA FDR-I 06.04.2016 21.00 Hrs. 06.04.2016 22.31 Hrs. In service do
5 400 KV SARNI- SEONI FDR 09.04.2016 16.39 Hrs. 09.04.2016 17.15 Hrs. In service Line Tripped due to 'B' phase fault, Main-1 & Main-2 protection optd.
6 400 KV SARNI- SEONI FDR 10.04.2016 12.55 Hrs. 10.04.2016 16.25 Hrs. In service Line Tripped due to 'B' phase fault, Main-1 & Main-2 protection optd.
7 400 KV SARNI- SEONI FDR 16.04.2016 04.00 Hrs. 16.04.2016 04.27 Hrs. In service Line Tripped due to 'B' phase fault, Main-1 & Main-2 protection optd.
8 220 KV AMK-JABALPUR FDR-II 05.04.2016 14.31 Hrs. 05.04.2016 14.42 Hrs. In service Line Tripped due to 'C' phase fault, Z-1 optd.
9 220 KV AMK-JABALPUR FDR-II 08.04.2016 19.23 Hrs. 08.04.2016 19.32 Hrs. In service Line Tripped due to 'A-N' phase fault, Z-1 optd.
10 220 KV AMK-JABALPUR FDR-II 14.04.2016 11.32 Hrs. 14.04.2016 11.45 Hrs. In service Line Tripped due to 'C' phase fault, Z-1 optd.
11 220 KV AMK-BIRSINGHPUR FDR-III 19.04.2016 11.52 Hrs. 19.04.2016 12.41 Hrs. In service Line Tripped due to 'A-B' phase fault, Z-2 optd.
12 220 KV AMK-JABALPUR FDR-I 20.04.2016 15.22 Hrs. 20.04.2016 16.08 Hrs. In service Line Tripped due to 'AB' phase fault, Z-1 optd.
13 220 KV AMK-JABALPUR FDR-II 20.04.2016 15.24 Hrs. 20.04.2016 15.40 Hrs. In service Line Tripped due to 'BC' phase fault, Z-1 optd.
14 220 KV AMK-PANAGAR FDR 29.04.2016 12.45 Hrs. 29.04.2016 13.09 Hrs. In service Line Tripped due to 'A' phase fault, Z-2 optd.
15 220 KV AMK-BIRSINGHPUR FDR-II 29.04.2016 15.14 Hrs. In service Line Tripped due to 'C' phase fault, Z-1 optd.
S.NO. ELEMENTTRIP RESTORED
A/R STATUS
Faulty Declare
TRIPPING DETAILS OF 400/220 KV SUBSTATIONS during 01.04.2016 TO 30.09.2016
REASONS
16 220 KV AMK-PANAGAR FDR 29.04.2016 15.14 Hrs. In service Line Tripped due to 'A' phase fault, Z-1 optd.
17 220 KV AMK-BIRSINGHPUR FDR-III 29.04.2016 16.04 Hrs. 29.04.2016 20.56 Hrs. In service Line Tripped due to 'A' phase fault, Z-1 optd.
18 220 KV AMK-JABALPUR FDR-I 29.04.2016 21.04 Hrs. 29.04.2016 21.24 Hrs. In service Line Tripped due to 'A' phase fault, Z-1 optd.
19 220 KV BIRSINGHPUR- REWA FDR 15.04.2016 08.46 Hrs. 15.04.2016 09.05 Hrs. Line Tripped due to 'BC' phase fault, Z-1 optd.
20 220 KV BIRSINGHPUR- REWA FDR 15.04.2016 09.40 Hrs. 15.04.2016 10.08 Hrs. Line Tripped due to 'C' phase fault, DPR optd.
21 220 KV BIRSINGHPUR- REWA FDR 19.04.2016 11.56 Hrs. 19.04.2016 12.05 Hrs. Line Tripped due to 'AB' phase fault, Z-4 optd.
22 220 KV BIRSINGHPUR- PALI, I/C-III 19.04.2016 11.56 Hrs. 21.04.2016 12.08 Hrs. Line Tripped due to 'AB' phase fault, Z-1 optd.
23 220 KV BIRSINGHPUR- PALI, I/C-I 19.04.2016 12.12 Hrs. 19.04.2016 13.06 Hrs. Line Tripped due to 'BC' phase fault, Z-2 optd.
24 220 KV BIRSINGHPUR- PALI, I/C-II 19.04.2016 12.12 Hrs. 19.04.2016 13.09 Hrs. Line Tripped due to 'BC' phase fault, Z-2 optd.
25 220 KV BIRSINGHPUR- REWA FDR 19.04.2016 12.12 Hrs. 19.04.2016 12.37 Hrs. Line Tripped due to 'BC' phase fault, Z-4 optd.
26 220 KV BIRSINGHPUR- PALI, I/C-IV 19.04.2016 12.12 Hrs. 19.04.2016 18.46 Hrs. Line Tripped due to 'BC' phase fault, Z-1 optd.
27220 KV BIRSINGHPUR- PALI, I/C-I 21.04.2016 12.23 Hrs. 21.04.2016 16.25 Hrs. Line Tripped due to 'BC' phase fault, Z-2 optd.
28220 KV BIRSINGHPUR- PANAGAR FDR 24.04.2016 12.41 Hrs. 24.04.2016 13.19 Hrs. Line Tripped due to 'R,Y,B' phase fault, Z-1 optd.
29220 KV BIRSINGHPUR- PALI, I/C-I 30.04.2016 10.21 Hrs. 30.04.2016 10.53 Hrs. Line Tripped due to 'A' phase fault, Z-1 optd.
30220 KV SARNI - ITARSI FDR No. 2 22.04.2016 18.39 Hrs. 22.04.2016 19.16 Hrs. Line Tripped due Zone-I, PAT, PE,PD optd.
31220 KV SARNI - Substation I/C No. 2 28.04.2016 12.00 Hrs. 28.04.2016 12.40 Hrs. Line Tripped due PAR, PAS, PE optd.
32 220 KV TONS- KOTAR FDR 22.04.2016 14.35 Hrs. 22.04.2016 15.40 Hrs. Line Tripped due to 'A-N' phase fault, Z1 optd.
33 220 KV TONS- REWA II FDR 20.04.2016 08.00 Hrs. 20.04.2016 08.10 Hrs. Line Tripped due to ' phase to ground fault', DPR optd.
34 400 KV BIRSINGHPUR - KATNI FDR-I 03.05.2016 18.11 Hrs. 03.05.2016 19.53 Hrs. In service DT received.
35 400 KV BIRSINGHPUR - KATNI FDR-II 03.05.2016 18.11 Hrs. 03.05.2016 20.10 Hrs. In service DT received.
36 400 KV BIRSINGHPUR - KATNI FDR-I 04.05.2016 16.19 Hrs. 05.05.2016 13.12 Hrs. In service DT received.
37 400 KV BIRSINGHPUR - KATNI FDR-II 04.05.2016 16.19 Hrs. 04.05.2016 17.47 Hrs. In service DT received.
38 400 KV BIRSINGHPUR - KATNI FDR-I 05.05.2016 17.44 Hrs. 05.05.2016 22.53 Hrs. In service DT received.
39 400 KV BIRSINGHPUR - KATNI FDR-II 05.05.2016 21.17 Hrs. 07.05.2016 15.36 Hrs. In service DT received.
40 400 KV BIRSINGHPUR - KATNI FDR-II 08.05.2016 18.02 Hrs. 17.05.2016 06.15 Hrs. In service DT received.
41 400 KV BIRSINGHPUR - KATNI FDR-I 21.05.2016 17.23 Hrs. 25.05.2016 20.38 Hrs. In service Line tripped due to overvoltage.
42 400 KV BIRSINGHPUR - KATNI FDR-II 21.05.2016 17.59 Hrs. 21.05.2016 19.34 Hrs. In service DT received.
43 400 KV BIRSINGHPUR - KATNI FDR-I 28.05.2016 17.16 Hrs. 28.05.2016 17.44 Hrs. In service DT received.
44 400 KV BIRSINGHPUR - KATNI FDR-II 28.05.2016 17.16 Hrs. In service DT received.Not charged till date
Faulty Declare
45 400 KV SARNI- ISP FDR 09.05.2016 17.14 Hrs. 09.05.2016 18.18 Hrs. In service Line Tripped due to 'R' phase fault, Z-1 optd.Main-1 & Main-2 protection optd.
46 400 KV SARNI- ISP FDR 18.05.2016 02.20 Hrs. 18.05.2016 03.34 Hrs. In service DT received.
47 220 KV AMK-SIDHI FDR 05.05.2016 18.19 Hrs. 05.05.2016 18.33 Hrs. In service Line Tripped due to 'A-N' phase fault, Z-1 optd.
48 220 KV AMK-JABALPUR FDR-I 06.05.2016 21.04 Hrs. 06.05.2016 21.30 Hrs. In service Line Tripped due to 'C' phase fault, Z-1 optd.
49 220 KV AMK-JABALPUR FDR-I 09.05.2016 06.02 Hrs. 09.05.2016 06.17 Hrs. In service Line Tripped due to 'C-N' phase fault, Z-2 optd.
50 220 KV AMK-JABALPUR FDR-I 09.05.2016 18.25 Hrs. 09.05.2016 18.38 Hrs. In service Line Tripped due to 'A' phase fault, Z-1 optd.
51 220 KV AMK-PANAGAR FDR 09.05.2016 18.58 Hrs. 09.05.2016 19.20 Hrs. In service Line Tripped due to 'C-N' phase fault, Z-1 optd.
52 220 KV AMK-SIDHI FDR 22.05.2016 19.02 Hrs 22.05.2016 19.24 Hrs In service Line Tripped due to 'A' phase fault, Z-1 optd.
53 220 KV AMK-JABALPUR FDR-II 24.05.2016 17.07 Hrs. 24.05.2016 17.19 Hrs In service Line Tripped due to 'C-N' phase fault, Z-1 optd.
54 220 KV AMK-JABALPUR FDR-II 25.05.2016 13.53 Hrs. 25.05.2016 14.32 Hrs In service Line Tripped due to 'C-N' phase fault, Z-1 optd.
55 220 KV BIRSINGHPUR- REWA FDR 02.05.2016 12.20 Hrs. 02.05.2016 12.55 Hrs. Line Tripped due to 'C' phase fault, Z-2 optd.
56 220 KV BIRSINGHPUR- PANAGAR FDR 02.05.2016 12.56 Hrs. 02.05.2016 13.50 Hrs. Line Tripped due to 'R-N' phase fault, Z-1 optd.
57 220 KV BIRSINGHPUR- PANAGAR FDR 02.05.2016 19.15 Hrs. 02.05.2016 19.48 Hrs. Line Tripped due to 'R-N' phase fault, Z-2 optd.
58 220 KV BIRSINGHPUR- AMK-III FDR 03.05.2016 14.20 Hrs. 03.05.2016 14.30 Hrs. Line Tripped due to 'A' phase fault, Z-1 optd.
59 220 KV BIRSINGHPUR- PANAGAR FDR 03.05.2016 18.54 Hrs. 03.05.2016 19.24 Hrs. Line Tripped due to 'R-N' phase fault, Z-2 optd.
60 220 KV BIRSINGHPUR- PANAGAR FDR 09.05.2016 18.58 Hrs. 09.05.2016 19.30 Hrs. Line Tripped due to 'C' phase fault, Z-1 optd.
61 220 KV BIRSINGHPUR- PANAGAR FDR 15.05.2016 17.09 Hrs. 15.05.2016 17.40 Hrs. Line Tripped due to 'C' phase fault, Z-2 optd.
62 220 KV BIRSINGHPUR- PALI, I/C-II 18.05.2016 14.57 Hrs. 18.05.2016 15.52 Hrs. Line Tripped due to directional E/F relay 67 NX optd.
63 220 KV BIRSINGHPUR- PALI, I/C-III 18.05.2016 14.57 Hrs. 18.05.2016 15.53 Hrs. Line Tripped due to directional E/F relay 67 NX optd.
64 220 KV BIRSINGHPUR- PALI, I/C-IV 18.05.2016 14.57 Hrs. 18.05.2016 15.54 Hrs. Line Tripped due to directional E/F relay 67 NX optd.
65 220 KV BIRSINGHPUR- AMK-III FDR 22.05.2016 19.02 Hrs. 30.05.2016 23.54 Hrs. Line Tripped due to 'A' phase fault, Z-1 optd.
66 220 KV BIRSINGHPUR- REWA FDR 24.05.2016 17.31 Hrs. 30.05.2016 23.58 Hrs. Line Tripped due to 'C' phase fault, Z-1 optd.
67 220 KV SARNI - SUB STATION I/C No. 2 04.05.2016 19.09 Hrs. 04.05.2016 19.57 Hrs. Line Tripped due PAR, PAT, Inst.O/C ' R & B' phase optd .
68220 KV SINGAJI - CHHEGAON FDR-I
04.05.2016 11.43 Hrs. 04.05.2016 12.50 Hrs. In service DT received.
69220 KV SINGAJI - CHHEGAON FDR-I
18.05.2016 17.20 Hrs. 18.05.2016 18.35 Hrs. In service DT received.
70220 KV SINGAJI - CHHEGAON FDR-I
20.05.2016 18.29 Hrs. 20.05.2016 20.10 Hrs. In service Bus bar protection operated.
71220 KV SINGAJI - CHHEGAON FDR-II
20.05.2016 18.29 Hrs. 23.05.2016 18.50 Hrs. In service DT received,
72 220 KV TONS- REWA FDR- II 04.05.2016 21.44 Hrs. 06.05.2016 22.29 Hrs. Line Tripped due to 'C-N' phase fault.
73 220 KV TONS- REWA FDR- II 04.05.2016 22.35 Hrs. 06.05.2016 19.10 Hrs. Line Tripped due to ' phase to ground fault', Z-1 optd,
74 105 MW TONS HPS GENERATOR UNIT # 3 08.05.2016 19.50 Hrs. At the time of Hand Tripping of unit#3, Pole descripiency trip occurred, consequentlyBus bar protection optd.
75 220 KV TONS- KOTAR FDR 23.05.2016 14.22 Hrs. 24.05.2016 13.36 Hrs. Line Tripped due to 'A-N' phase fault, Z-1 optd.
76 220 KV TONS- REWA FDR- II 23.05.2016 14.50 Hrs. 23.05.2016 17.40Hrs.
i 220 KV TONS- REWA FDR- I 23.05.2016 14.50 Hrs. 23.05.2016 17.38 Hrs.
ii 220 KV TONS- SATNA FDR 23.05.2016 14.50 Hrs. 23.05.2016 17.46 Hrs.
77 400 KV SARNI- ISP FDR 04.06.2016 12.18 Hrs. 04.06.2016 13.49 Hrs. In service DT received.
78 400 KV SARNI- ICT 22.06.2016 13.10 Hrs. 22.06.2016 15.02 Hrs. In serviceAt 13.10 Hrs. in 220 KV SST interconnector-1 tripped on fault and simultaneously
400KV/220KV I.C.T. both side C.B. tripped on 220KV side 'B- phase' instantaneousBack up over current protection operated.
79 400 KV SARNI- KORADI FDR 25.06.2016 14.58 Hrs. 25.06.2016 21.42 Hrs. In service Line Tripped due to 'R' phase fault, , Main-1/2 protection, Z-2 optd.
80 400 KV SARNI- ASHTA FDR-2 28.06.2016 19.47 Hrs. 28.06.2016 20.51 Hrs. In service Line Tripped due to 'B-N' phase fault, , Z-1 optd.
81 400 KV BIRSINGHPUR - KATNI FDR-I 12.06.2016 17.07 Hrs. 12.06.2016 19.34 Hrs. In service DT received.
82 400 KV BIRSINGHPUR - KATNI FDR-I 19.06.2016 02.08 Hrs. 19.06.2016 02.43 Hrs. In service O/V trip, Master trip, DT send.
83 400 KV BIRSINGHPUR - KATNI FDR-I 20.06.2016 02.29 Hrs. 26.06.2016 22.26 Hrs. In service O/V trip, Master trip, DT send.
84 400 KV BIRSINGHPUR - KATNI FDR-I 28.06.2016 00.37 Hrs. 28.06.2016 22.37 Hrs. In service DT received.
85 400 KV BIRSINGHPUR - KATNI FDR-II 30.06.2016 01.59 Hrs. In service DT received.
86 220 KV SARNI - SUB STATION I/C No. 1 22.06.2016 13.10 Hrs. 22.06.2016 14.10 Hrs.Line Tripped due to Electromagnetic relay & DPR PD, PAT, PTaW, PSW, optd.
87 220 KV TONS- REWA FDR- II 18.06.2016 12.37 Hrs. 18.06.2016 12.58 Hrs. Line Tripped due to 'B-N' phase fault.
88 220 KV BIRSINGHPUR- PANAGAR FDR 02.06.2016 13.20 Hrs. 02.06.2016 13.44 Hrs. Line Tripped due to 'R-N' phase fault, Z-1 optd.
89 220 KV BIRSINGHPUR- REWA FDR 20.06.2016 18.58 Hrs. 21.06.2016 01.12 Hrs. Line Tripped due to 'C' phase fault, Z-1 optd.
90 220 KV BIRSINGHPUR- REWA FDR 24.06.2016 15.05 Hrs. 24.06.2016 17.18 Hrs. Line Tripped due to 'A' phase fault, Z-1 optd.
91 220 KV BIRSINGHPUR- PANAGAR FDR 30.06.2016 09.25 Hrs. 30.06.2016 16.45 Hrs. Line Tripped due to 'R-N' phase fault, Z-1 optd.
92 400 KV SARNI- ITARSI FDR 08.07.2016 19.00 Hrs. 08.07.2016 19.38 Hrs. In service Line Tripped due to 'R' phase fault, , Main-1 protection, Z-1 optd.
93 400 KV SARNI- ICT 22.07.2016 03.15 Hrs. 22.07.2016 11.27 Hrs. In service
At 03.15 Hrs. 400KV/220KV I.C.T. got tripped from 400 KV side on pole descripiancy.After getting permission from L/D, ICT synchronised from 400 KV side at 03.25 Hrs butagain tripped at 03.56 Hrs. on pole descripancy at 400 KV side at that incident 220 KVside CB hand tripped at 04.04 Hrs. for thorough checking. On checking it was foundthat one number cable core became earthed in pole descripiancy circuit. Problemattended by using spare core of the cable. After clearance from L/D, ICT charged from220 KV side and synchronised from 400 KV side at 11.27 Hrs. Dt.22.07.2016.
94 400 KV SARNI- ASHTA FDR-2 08.07.2016 18.59 Hrs. 21.07.2016 12.46 Hrs. In service Line Tripped due to 'Reactor Backup Impedance protection' optd.
95 400 KV BIRSINGHPUR - KATNI FDR-I 01.07.2016 12.59 Hrs. In service DT received.
96 400 KV BIRSINGHPUR - KATNI FDR-II 05.07.2016 17.59 Hrs. 19.07.2016 19.58 Hrs. In service DT received.
97 220 KV SARNI - SUB STATION I/C No. 2 11.07.2016 22.41 Hrs. 12.07.2016 15.37 Hrs. Line Tripped due to Circuit breaker control circuit fault.
Line Tripped due to 'A-N' phase fault. Fault occurred due to lighting cable ofTower lighting of switch yard fallen on 220 KV Bus-2 ( Bus-1 under permit),
Fdr is not charged till now
Fdr is not charged till now
98 220 KV SARNI - SUB STATION I/C No. 1 13.07.2016 12.56 Hrs. 13.07.2016 13.54 Hrs. Line Tripped due to Electromagnetic relay & DPR PD, PAT, Z-1 optd.
99 220 KV SARNI - SUB STATION I/C No. 2 20.07.2016 03.45 Hrs. 20.07.2016 18.04 Hrs. Line Tripped due to Circuit breaker control circuit fault.
100 220 KV BIRSINGHPUR- REWA FDR 01.07.2016 12.52 Hrs. 01.07.2016 13.27 Hrs. Line Tripped due to 'A' phase fault, Z-2 optd.
101 220 KV BIRSINGHPUR- AMK-III FDR 16.07.2016 12.26 Hrs. 16.07.2016 16.15 Hrs. Line Tripped due to '186A & 186B Lock out' optd.
102 220 KV BIRSINGHPUR- PALI, I/C-II 20.07.2016 12.54 Hrs. 20.07.2016 13.33 Hrs. Line Tripped due to 'BC' phase fault, Z-1 optd.
103 220 KV BIRSINGHPUR- PANAGAR FDR 23.07.2016 10.13 Hrs. 23.07.2016 10.53 Hrs. Line Tripped due to 'R' phase fault, Z-4 optd.
104 220 KV BIRSINGHPUR- AMK-II FDR 23.07.2016 10.13 Hrs. 23.07.2016 17.17 Hrs. Line Tripped due to 'B' phase fault, Z-1 optd.
105 220 KV BIRSINGHPUR- REWA FDR 29.07.2016 14.36 Hrs. 29.07.2016 15.10 Hrs. Line Tripped due to 'C' phase fault, Z-1 optd.
106 220 KV AMK-SIDHI FDR 08.07.2016 21.41 Hrs. 08.07.2016 21.56 Hrs. In service Line Tripped due to 'AN' phase fault, Z-1 optd.
107 220 KV AMK-JABALPUR FDR-II 10.07.2016 04.26 Hrs. 10.07.2016 04.35 Hrs. In service Line Tripped due to 'A' phase fault, Z-1 optd.
108 220 KV AMK-JABALPUR FDR-I 18.07.2016 02.27 Hrs. 18.07.2016 02.40 Hrs. In service Line Tripped due to 'C' phase fault, Z-1 optd.
109 220 KV AMK-BIRSINGHPUR FDR-III 20.07.2016 12.55 Hrs. 20.07.2016 13.44 Hrs. In service Line Tripped due to 'B-C' phase fault, Z-2 optd.
110 220 KV TONS- SATNA FDR 10.07.2016 12.45 Hrs. 10.07.2016 13.15 Hrs. Line Tripped due to 'C-N' phase fault, BB Protn. Z-4 optd.
111 220 KV TONS- REWA FDR-I 10.07.2016 12.45 Hrs. 10.07.2016 13.25 Hrs. Line Tripped due to 'C' phase fault, BB Protn. optd.
112 220 KV TONS- KOTAR FDR 10.07.2016 12.45 Hrs. 10.07.2016 13.17 Hrs. Line Tripped due to 'C-N' phase fault, BB, Dist. Protn, Z-1 optd.
113 105 MW TONS HPS GENERATOR UNIT # 2 19.07.2016 16.15 Hrs.
'Y phase pole' of GT#2 main breaker damaged at the time of stopping of unit #2 hencebus bar protection operated, consequently 220 KV Tons-Kotar fdr, Tons- Rewa fdr IItripped as these are on same bus and 220 KV Bus coupler also tripped .Bus barprotection optd. The details are as follows:
i 220 KV TONS- KOTAR FDR 19.07.2016 16.15 Hrs. 19.07.2016 17.00 Hrs. Line Tripped due to 'E/F relay' , Dist. Protn. optd.
ii 220 KV TONS- REWA FDR-II 19.07.2016 16.15 Hrs. 19.07.2016 16.55 Hrs. Line Tripped due to 'E/F relay' , Dist. Protn. optd.
114 220 KV TONS- SATNA FDR 23.07.2016 17.50 Hrs. 23.07.2016 18.08 Hrs. Line Tripped due to 'A-N' phase fault, Z-1 optd.
115 220 KV TONS- KOTAR FDR 30.07.2016 13.45 Hrs. 30.07.2016 14.36 Hrs. Line Tripped due to 'C' phase fault, Z-1 optd.
116 400 KV SARNI- ISP FDR 17.08.2016 16.46 Hrs. 18.08.2016 10.01 Hrs. In service
Line Tripped due to 'Y' phase fault, , Main-1 & II protection, Z-1 optd.Line charged from ISP end, Line immediately tripped on same fault. Onchecking by Transmission division, Disc Insulator found burst at location no.125 in 'Y' phase and same has been replaced.
117 400 KV SARNI- ISP FDR 24.08.2016 12.58 Hrs. 24.08.2016 14.05 Hrs. In service Line Tripped due to 'Y' phase fault, , Main-1 & II protection, Z-1 optd.
118 400 KV BIRSINGHPUR - KATNI FDR-II 07.08.2016 04.10 Hrs. 28.08.2016 12.50 Hrs. In service DT received.
119 220 KV SARNI - SUB STATION I/C No. 1 02.08.2016 11.44 Hrs. 02.08.2016 20.22 Hrs. Line Tripped due to DPR, Z-1 optd.
120 220 KV SARNI - HANDIA FDR 02.08.2016 11.44 Hrs. 03.08.2016 20.20 Hrs. Line Tripped due to O/C 'A' Phase, Zone-1 optd.
121 220 KV SARNI - ITARSI FDR-II 30.08.2016 21.47 Hrs. 30.08.2016 22.41 Hrs. Line Tripped due to O/C 'A' Phase, Zone-2 optd.
122 220 KV BIRSINGHPUR- AMK-II FDR 12.08.2016 11.06 Hrs. 12.08.2016 11.30 Hrs. Line Tripped due to 'A-N' phase fault, Z-1 optd.
123 220 KV BIRSINGHPUR- REWA FDR 04.08.2016 12.03 Hrs. 04.08.2016 12.43 Hrs. Line Tripped due to 'B-C' phase fault, Z-2 optd.
124 220 KV BIRSINGHPUR- REWA FDR 09.08.2016 11.55 Hrs. 09.08.2016 12.05 Hrs. Line Tripped due to 'C' phase fault, Z-2 optd.
125 220 KV BIRSINGHPUR- REWA FDR 24.08.2016 09.35 Hrs. 24.08.2016 09.45 Hrs. Line Tripped due to 'C' phase fault, Z-1 optd.
126 220 KV BIRSINGHPUR- REWA FDR 24.08.2016 11.36 Hrs. 24.08.2016 11.48 Hrs. Line Tripped due to 'C' phase fault, Z-1 optd.
127 220 KV BIRSINGHPUR- REWA FDR 26.08.2016 17.10 Hrs. 26.08.2016 17.26 Hrs. Line Tripped due to 'C' phase fault, Z-1 optd.
128 220 KV AMK-SIDHI FDR 04.08.2016 12.16 Hrs. 04.08.2016 12.37 Hrs. In service Line Tripped due to 'C' phase fault, Z-1 optd.
129 220 KV AMK-JABALPUR FDR-I 05.08.2016 00.09 Hrs. 05.08.2016 00.18 Hrs. In service Line Tripped due to 'C' phase fault, Z-1 optd.
130 220 KV AMK-SIDHI FDR 11.08.2016 15.19 Hrs. 11.08.2016 15.33 Hrs. In service Line Tripped due to 'A-N' phase fault, Z-1 optd.
131 220 KV AMK-SIDHI FDR 17.08.2016 19.27 Hrs. 17.08.2016 20.27 Hrs. In service Breaker tripped due to Air pressure low, 86 X optd.
132 220 KV AMK-PANAGAR FDR 17.08.2016 23.18 Hrs. 17.08.2016 23.27 Hrs. In service Line Tripped due to 'C' phase fault, Z-1 optd.
133 220 KV AMK-JABALPUR FDR-I 24.08.2016 11.06 Hrs. 24.08.2016 11.26 Hrs. In service Line Tripped due to 'A' phase fault, Z-1 optd.
134 220 KV AMK-TRACTION FDR-II 24.08.2016 11.06 Hrs. 24.08.2016 11.35 Hrs. In service Line Tripped due to 'C' phase fault, Z-1 optd.
135 220 KV AMK-SIDHI FDR 25.08.2016 15.31 Hrs. 25.08.2016 15.46 Hrs. In service Line Tripped due to 'A-N' phase fault, Z-2 optd.
136 220 KV AMK-SIDHI FDR 26.08.2016 17.02 Hrs. 26.08.2016 17.20 Hrs. In service Line Tripped due to 'A-N' phase fault, Z-1 optd.
137 220 KV AMK-PANAGAR FDR 27.08.2016 05.28 Hrs. 27.08.2016 05.50 Hrs. In service Line Tripped due to 'C' phase fault, Z-1 optd.
138 220 KV AMK-PANAGAR FDR 29.08.2016 15.18 Hrs. 29.08.2016 15.33 Hrs. In service Line Tripped due to 'A-N' phase fault, Z-1 optd.
139 220 KV TONS- REWA FDR-II 27.08.2016 04.29 Hrs. 27.08.2016 04.48 Hrs. Line Tripped due to 'C-N' phase fault, Z-1 optd.
140 400 KV SARNI- ASHTA FDR-II 17.09.2016 01.09 Hrs. 17.09.2016 02.53 Hrs. In service
On dated 17/09/16 at 1:09:08 Hrs 400 kV Ashta-II circuit was tripped onZone-1 protection (B-phase tripped ) at 78.3 kms from Ashta End ,Autoreclose occurred at Ashta end however at Sarni end Due to problem inSCADA Autoreclose didnot occured and feeder was tripped on Line Breaker-pole discrepancy operated. After clearance from LD feeder wassynchronisedffrom Sarni end at 02:53 Hrs on dated 17.09.16.
141 400 KV SARNI- ITARSI FDR 06.09.2016 16.59 Hrs. 06.09.2016 19.15 Hrs. In service
142 400 KV SARNI- KORADI FDR 06.09.2016 16.59 Hrs. 06.09.2016 19.31 Hrs. In service
143 400 KV SARNI- ISP FDR 27.09.2016 10.38 Hrs. 27.09.2016 10.58 Hrs. In service Line Tripped due to 'B' phase fault, Main-1 & II protection, Z-1 optd.
144 400 KV SARNI- ISP FDR 28.09.2016 10.04 Hrs. 28.09.2016 10.20 Hrs. In service Line Tripped due to 'B' phase fault, , Main-1 & II protection, Z-1 optd.
145 400 KV SARNI- ISP FDR 29.09.2016 13.15 Hrs. 29.09.2016 13.25 Hrs. In service Line Tripped due to 'B' phase fault, , Main-1 & II protection, Z-1 optd.
146 220 KV Singaji- Chhegaon 17.09.2016 03.29 Hrs. 17.09.2016 04.32 Hrs. In service DT received.
147 220 KV SARNI - HANDIA FDR 17.09.2016 01.45 Hrs. 18.09.2016 11.56 Hrs. Line Tripped due to O/C 'B' Phase, Zone-1 optd.
148 220 KV BIRSINGHPUR- AMK-III FDR 05.09.2016 20.39 Hrs. 05.09.2016 20.53 Hrs. Line Tripped due to 'A' phase fault, Z-1 optd.
149 220 KV BIRSINGHPUR- AMK-III FDR 07.09.2016 23.00 Hrs. 08.09.2016 00.30 Hrs. Line Tripped due to Bus Bar Z-2 optd.
On dated 06/09/16 at 16:59 Hrs 400 kV 400 KV Bus reactor No.-2(63 MVAR) Back up impedance Y & B phase operated. The C.B. of Bus reactor-2 didn't open timaly causing LBB to operate, which is turn causes Bus Bar
150 220 KV BIRSINGHPUR- REWA FDR 07.09.2016 23.00 Hrs. 08.09.2016 01.25 Hrs. Line Tripped due to Bus Bar Z-2 optd.
151 220 KV BIRSINGHPUR- PALI Interconnector-I 13.09.2016 13.10 Hrs. 13.09.2016 13.35 Hrs. Line Tripped due to 'A' phase fault, Z-1 optd.
152 220 KV BIRSINGHPUR- PALI Interconnector-II 13.09.2016 13.10 Hrs. 13.09.2016 17.21 Hrs. Line Tripped due to 'A' phase fault, Directional E/F 67 NX Relay optd.Z-1optd.
153 220 KV BIRSINGHPUR- REWA FDR 18.09.2016 18.45 Hrs. 18.09.2016 19.07 Hrs. Line Tripped due to 'A' phase fault, Z-1 optd.
154 220 KV BIRSINGHPUR- REWA FDR 19.09.2016 12.38 Hrs. 19.09.2016 12.59 Hrs. Line Tripped due to 'C' phase fault, Z-2 optd.
155 220 KV BIRSINGHPUR- REWA FDR 19.09.2016 17.31 Hrs. 19.09.2016 17.45 Hrs. Line Tripped due to 'B' phase fault, Z-2 optd.
156 220 KV BIRSINGHPUR- AMK-II FDR 20.09.2016 13.35 Hrs. 20.09.2016 14.35 Hrs. Line Tripped due to 'A&C' phase fault, Z-1 optd.
157 220 KV BIRSINGHPUR- REWA FDR 25.09.2016 11.47 Hrs. 25.09.2016 11.56 Hrs. Line Tripped due to 'C' phase fault, Z-2 optd.
158 220 KV BIRSINGHPUR- PANAGAR FDR 29.09.2016 23.42 Hrs. 30.09.2016 00.20 Hrs. DPR optd.
159 220 KV BIRSINGHPUR- PALI Interconnector-III 29.09.2016 23.42 Hrs. 30.09.2016 00.30 Hrs. Line Tripped due to 'C' phase fault, Z-1 optd.
160 220 KV BIRSINGHPUR- PALI Interconnector-IV 29.09.2016 23.42 Hrs. 30.09.2016 00.45 Hrs. Line Tripped due to 'B' phase fault, Z-1 optd.
161 220 KV AMK-JABALPUR FDR-II 08.09.2016 20.32 Hrs. 08.09.2016 20.43 Hrs. In service Line Tripped due to 'A' phase fault, Z-1 optd.
162 220 KV AMK-PANAGAR FDR 09.09.2016 14.52 Hrs. 09.09.2016 15.14 Hrs. In service Line Tripped due to 'A-N' phase fault, Z-2 optd.
163 220 KV AMK-SIDHI FDR 14.09.2016 14.02 Hrs. 14.09.2016 14.13 Hrs. In service Line Tripped due to 'A-N' phase fault, Z-1 optd.
164 220 KV AMK-SIDHI FDR 19.09.2016 18.16 Hrs. 19.09.2016 18.33 Hrs. In service Line Tripped due to 'B-N' phase fault, Z-2 optd.
165 220 KV AMK-JABALPUR FDR-I 20.09.2016 16.15 Hrs. 20.09.2016 16.25 Hrs. In service Line Tripped due to 'C' phase fault, Z-1 optd.
166 220 KV AMK-JABALPUR FDR-II 20.09.2016 16.31 Hrs. 20.09.2016 16.45 Hrs. In service Line Tripped due to 'A' phase fault, Z-1 optd.
167 220 KV AMK-BIRSINGHPUR FDR-III 29.09.2016 23.46 Hrs. 30.09.2016 00.01 Hrs. In service Line Tripped due to 'BC-N' phase fault, Z-1 optd.
168 220 KV AMK-JABALPUR FDR-II 30.09.2016 11.26 Hrs. 30.09.2016 11.55 Hrs. In service Line Tripped due to 'C-N' phase fault, Z-1 optd.
169 220 KV TONS- KOTAR FDR 15.09.2016 16.32 Hrs. 15.09.2016 17.00 Hrs. Line Tripped due to 'A C-N' phase fault, Z-1 optd.
170 220 KV TONS- SIRMOUR FDR 15.09.2016 16.32 Hrs. 15.09.2016 17.49 Hrs. Line Tripped due to 'A C-N' phase fault, Check Zone Bus Bar Protection optd.
171 220 KV TONS- SATNA FDR 15.09.2016 16.32 Hrs. 15.09.2016 17.55 Hrs. Line Tripped due to 'A C-N' phase fault, Z-1 optd.
172 220 KV TONS- SATNA FDR 18.09.2016 15.57 Hrs. 18.09.2016 16.10 Hrs. Line Tripped due to 'A-N' phase fault, Z-1 optd.
173 220 KV TONS- SIRMOUR FDR 20.09.2016 14.58 Hrs. 20.09.2016 15.13 Hrs. Line Tripped due to 'A-N' phase fault, Z-1 optd.
174 220 KV TONS- SATNA FDR 23.09.2016 14.31 Hrs. 18.09.2016 14.52 Hrs. Line Tripped due to 'A-N' phase fault, Z-1 optd.
175 220 KV TONS- REWA FDR-II 27.09.2016 00.46 Hrs. 27.09.2016 01.01 Hrs. Line Tripped due to 'C-N' phase fault, Z-1 optd.
Report of Black out at CGPL on 13.07.2016
Introduction:
A complete blackout at CGPL took place on 13.07.2016. A group comprising of
CGPL, GETCO, Powergrid WR-II, WRLDC and WRPC officers met at Vadodara on
18.07.2016 to discuss the blackout.
List of participants in the meeting is enclosed at Annexure-1.
The description of the blackout is described next. Finally, conclusions &
recommendations of the group are presented.
The outcome of the report shall be put up to PCM forum of WRPC.
1. Brief summary on occurrence:
The occurrence of complete blackout of CGPL can be analysed by separating it into
three events which occurred one after the other. The first event started at Varsana Sub-station
at 20:29 Hrs on 12th July 2016 which led to Bus 1 tripping along with associated element due
to bus fault. The primary reason was insulator tracking in the switchyard of Varsana Sub-
station. This was followed by second event at 21:49Hrs, where again due to insulator tracking
at another location at Varsana Sub-station, the fault occurred on 400 kV Bus 2 resulting in
loss of all 400 kV elements from 400/220 kV Varsana sub-station. After getting clearance
from Gujarat SLDC/GETCO and PGCIL, 400 kV Varsana-Bhachau 1 circuit was being
charged from Bhachau end to energize the 400 kV Bus of Varsana at 02:37 Hrs on 13th July
2016. However, after charging of line from Bhachau end and before synchronizing it from
Varsana end, fault appeared at Varsana end near the gantry of this circuit. The fault first
appeared in Y phase followed by conversion into three phase fault. This fault was sensed in
Zone 2 from Bhachau end relay. 400 kV CGPL-Bhachau 1 from CGPL end and 400 kV
Bhachau-Ranchodpura 1 & 2 from Ranchodpura end also tripped in Zone 2 before tripping of
400 kV Varsana-Bhachau 1 line from Bhachau end, at about same time. Power swing
observed on remaining lines from CGPL and 220 kV Bhachau-Morbi circuit and the lines
eventually tripped on Zone-1 power swing trip, causing complete blackout at CGPL. CGPL
units also tripped in Out of Step condition. The loss of generation at CGPL was of the order
of 2875 MW. The loss of CGPL generation resulted in frequency fall causing df/dt based load
shedding operation in Gujarat system. Preliminary assessment of the amount of df/dt based
load shedding as intimated by GETCO was 119 MW.
Report of Black out at CGPL on 13.07.2016
Since there was a complete generation loss of around 2875 MW at CGPL an UMPP
station it required a detailed analysis using all the available data from sub-
station/SLDC/RLDC. A meeting was held at PGCIL Vadodara on 18.07.2016 to look into the
matter, based on the available input received from various utilities. The occurrence has been
subdivided into three events viz;
1. Event 1 : Outage of 400 kV Bus 1 at 400/220 kV Varsana Substation
2. Event 2 : Outage of 400 kV Bus 2 at 400/220 kV Varsana Substation
3. Event 3 : CGPL Blackout while charging of 400 kV Bhachau-Varsana 1.
2. System condition prior to Incident:
The single line diagram showing important lines connecting two major generating stations
(CGPL & APL) is given below
The generation of CGPL was around 2878 MW (Unit-10: 760 MW, Unit-30: 742 MW,
Unit 40: 757 MW & Unit 50: 619 MW).
Report of Black out at CGPL on 13.07.2016
The evacuation from CGPL was through the following lines.
(1) 400 KV CGPL-Jepur 1 & 2 : 799 MW
(2) 400 KV CGPL-Chorania : 466 MW
(3) 400 KV CGPL-Mansar : 510 MW
(4) 400 KV CGPL-Bhachau 1 & 2 : 1092 MW
The load flow pattern at 2.37.08 Hrs. i.e. after event 1 and before event 2 took place is as
shown below.
Report of Black out at CGPL on 13.07.2016
3. Event 1: Tripping of 400 kV Bus 1 at 400/220 kV Varsana Substation
3.1. Antecedent condition at 20:24 Hrs on 12th July 2016
Prior to the event the weather was a foggy and it was raining around 400/220 kV Varsana
substation. Arcing, corona & tracking were continuously observed in the substation. In
Gujarat system, 400 kV Chorania-Asoj 1 and 400 kV Kasor-Rajgarh 1 were out on breaker
problem at Choronia end and high voltage control respectively. The Bus arrangement at
400kV Varsana, at 20:24 Hrs on 12th July 2016 is as tabulated below. The Bus bar
arrangement at 400 and 220 kV Varsana prior to event is shown in figure 1(a) & (b).
Bus bar arrangement at 400 kV Varsana:
400 kV Bus 1 400 kV Bus 2
400 kV Varsana-Kansari400 KV Varsana-
Bhachau-2
50 MVAR Bus Reactor 1125 MVAR Bus
Reactor 2
400/220 kV 315 MVA ICT 1400/220 kV 315
MVA ICT 2
400 kV Varsana-Hadala
400 kV Varsana-APL 1
400 kV Varsana-APL 2
400 kV Varsana-Bhachau 1
400/220 kV 315 MVA
ICT 3
Report of Black out at CGPL on 13.07.2016
Figure 1(a): 400 kV Bus of 400/220 kV Varsana Substation at 20:29 Hrs
Figure 1(b): 220 kV Bus of 400/220 kV Varsana Substation at 20:29 Hrs. (400/220 kV
ICT 3 not modelled in 220 kV Varsana SLD)
3.2. 400 kV Bus 1 fault at Varsana at 20:29 Hrs
Due to the insulator tracking, bus fault occurred on 400 kV Bus 1 causing tripping of all
connected elements on 400 kV Bus 1 and Bus coupler. The fault was in Y phase.
Report of Black out at CGPL on 13.07.2016
400 kV Bus 1 bus bar protection operated leading to tripping of all 400 kV Lines/ICTs along
with the bus coupler at Varsana. The details of elements tripped are as following:
1. 400 kV APL-Varsana 1
2. 400 kV Varsana-Kansari (Zerda)
3. 400 kV Varsana-Hadala
4. 400 kV Varsana-Bhachau 1
5. 400 kV Varsana-Bhachau 1
6. 400/220 kV 315 MVA ICT 1
7. 400/220 kV 315 MVA ICT 3
8. 50 MVAR Bus Reactor 1
Further, due to tripping of 400/220 kV Varsana ICT 3 (where 300 MW OPGS Unit 1 is
connected radially to 220 kV Bus of ICT through 220kV OPGS-Varsana circuits), OPGS
Unit 1 generating 87 MW also got tripped.
3.3. Post Event Scenario after Event 1 at 20: 35 Hrs.
The status of elements after the tripping of 400kV Bus 1 is as shown in Fig 2(a) & (b).
Figure 2 (a): 400 kV Bus of 400/220 kV Varsana Substation after 400 kV Bus 1 Outage.
Report of Black out at CGPL on 13.07.2016
Figure 2(b): 220 kV Bus of 400/220 kV Varsana Substation after 400 kV Bus 1 Outage.
3.4. Restoration of the system
As the fault was due to the tracking of bus post insulator so, 400 kV Bus 1 remained out
at Varsana. GETCO/Gujarat SLDC after ensuring the healthiness of 400 kV Varsana-Hadala
ckt., took it on 400 kV Bus 2 at 21:41 Hrs. Remaining 400 kV lines, bus coupler, 400/220
kV ICTs and 400 kV Bus 1 remained out of service.
4. Event 2: Tripping of 400 kV Bus 2 at 400/220 kV Varsana Substation
4.1. Antecedent Condition prior to 21:49 Hrs
400 kV Bus 1 of Varsana was out of service due to the fault and persistent tracking at
Varsana sub-station.
4.2. 400 kV Bus 2 Fault at Varsana at 21:49 Hrs
At 400 kV Bus of Varsana sub-station, Bus 2 also tripped at 21:50 Hrs on Bus bar protection
operation with Y phase to earth fault due to persistent tracking on insulators. The Y phase
fault was observed. The following elements connected to Bus-2, tripped at 400/220 kV
Varsana sub-station.
1. 400 kV Varsana-Hadala
2. 400 kV Varsana-Bhachau 2
Report of Black out at CGPL on 13.07.2016
3. 400/220 kV 315 MVA ICT 2
4. 125 MVAR Bus Reactor 2
4.3. Post Event Scenario after Event 2 at 21:55 Hrs
Both the 400 kV Buses at 400/220 kV Varsana substation became dead. The status of 220kV
Bus at 400/220kV Varsana S/S was as shown in fig 3.
Figure 3: 220 kV Bus of 400/220 kV Varsana Substation after both 400 kV bus
becoming dead.
4.4. Restoration of the system
It was intimated by Gujarat SLDC that after cleaning of the post insulator at the 400 kV
Varsana substation, 400 kV Bhachau-Varsana 1 was ready for charging.
5. Event 3: CGPL Blackout while charging of 400 kV Bhachau-Varsana 1
5.1. Antecedent Condition at 02:30 Hrs on 13th July 2016
Prior to the charging of 400 kV Bhachau-Varsana 1 circuit system condition at 02:30 Hrs on
13 July was as shown in figures 4 -7. Prior to this event following circuits were out in Gujarat
System:
1. 400 kV Chorania-Asoj 1: Out since 30th June 2016 due to breaker problem at
Chorania end (At Choronia end TBC has been used for charging of Bus reactor 2)
2. 400 kV Kansari-Ranchropura 2:
3. 400 kV Rajgarh-Kasor 1: On High Voltage control since 9th July 2016 at 17:42 Hrs.
Report of Black out at CGPL on 13.07.2016
4. 765 kV Vadodara-Dhule S/C: On High Voltage control since 12th July 2016 at 22:15
Hrs.
5. 400 kV Chorania-Ranchodpura 1: On High Voltage control since 12th July 2016 at
23:51 Hrs.
6. 400 kV Amreli-Jetpur 2: On High Voltage control since 12th July 2016 at 23:55 Hrs.
7. 400 kV Kosamba-Chorania 2: On High Voltage control since 13th July 2016 at 00:06
Hrs.
Figure 4: Gujarat system at 02:30 Hrs i.e. prior to blackout of CGPL.
Report of Black out at CGPL on 13.07.2016
Figure 5: CGPL Bus at 02:30 Hrs
Figure 6: Bhachau 400 kV Bus at 02:30 Hrs
Report of Black out at CGPL on 13.07.2016
Figure 7: Bhachau 220 kV Bus at 02:30 Hrs
5.2. Blackout at CGPL at 02:37 Hrs
At 02:37 Hrs, 400 kV Bhachau-Varsana 1 was charged from Bhachau end. However after 7
seconds of the charging of the line, initially fault developed in Y phase followed by its
conversion to three phase fault at the gantry end of this line at Varsana end. The PMU plot of
Dehgam is as shown in figure 8.
Report of Black out at CGPL on 13.07.2016
Figure 8: 400 kV Dehgam Bus voltage observed from the PMU indicating initially Y
phase followed by three phase fault.
It was found that all the remaining lines from CGPL tripped along with 400 kV Bhachau-
Ranchodpura D/C, 220 kV Bhachau-Morbi. This caused blackout of CGPL and tripping of all
its running units.
List of Tripped elements during the event are as following:
1. Bhachau – Varsana 1 on Zone 2 protection seen from Bhachau end.
2. 400 kV CGPL-Bhachau 1 on Zone 2 protection seen from CGPL end
3. 400 kV CGPL-Mansar
4. 400 kV CGPL-Chorania
5. 400 kV CGPL-Jetpur 1 & 2
6. 400 kV Bhachau-Ranchodpura 1 & 2 on Zone 2 protection seen from Ranchodpura
end.
7. 400 kV Bhachau-Essar Vadinar 1 & 2 (Idle changed from Bhachau)
8. 220 kV Bhachau-Morbi
9. CGPL Unit 10, 30, 40 and 50 on Out of Step protection.
Generation Loss: Due to this event, generation loss of 2875 MW of CGPL occurred with
tripping of Unit 10, 30, 40 and 50.
Load Loss: Due to the event of loss of large generation, frequency drop was fast which has
resulted in the df/dt based load shedding relays operation in Gujarat system. Frequency and
Rate of change of frequency observed in various states of WR from PMUs is shown in figure
9 and 10 respectively. It can be observed that in Gujarat, the df/dt observed is more than 0.2
Hz/sec for considerable amount of time due to nearness of the event causing operation of
ROCOF based load shedding scheme.
Report of Black out at CGPL on 13.07.2016
Figure 9: Rate of Change Frequency observed in Gujarat and Maharashtra during the
event of CGPL Blackout from PMUs.
Figure 10: Rate of Change Frequency observed in Madhya Pradesh and Chhattisgarh
of WR during the event of CGPL Blackout from PMUs.
Frequency drop during the event: Due to loss of generation followed by df/dt based load
shedding frequency dropped from 49.9685 Hz to 49.7385 Hz i.e. a drop by 0.23 Hz. This can
be observed from the frequency plot from various PMU in figure 11. It can also be observed
that frequency has restored within 10 minutes of the incident to its initial value.
Report of Black out at CGPL on 13.07.2016
Figure 11: Frequency drop during the event of blackout of CGPL from various PMUs.
5.3. Analysis of the Event
5.3.1. Event Analysis from Gujarat SLDC for Bus fault at Varsana (Event 1 & 2)
There was a foggy and rainy atmosphere at 400/220 kV Varsana substation and arcing,
corona & tracking were continuously observed in the substation. The bus bar operation of
Alstom make Micom P741-743 at 20.29 hrs. for 400 kV Bus 1 and at 21.50 for 400 kV Bus 2
was due to arcing and chattering observed in bus coupler bay P.I and adjacent bays. 30 kA of
differential current in Y-phase was recorded in the Central Unit of the bus bar scheme during
bus fault of 400 kV Bus 1 at 20:29 Hrs. 15 kA of differential current in Y-phase was recorded
in the Central unit of the bus bar scheme at 21.50 hrs during bus fault on 400 kV Bus 2. DR
files of Bus bar protection are placed at Annexure 3.
5.3.2. Inferences from the Disturbance Recorder Files and PMU data for Event 3:
The disturbance recorder files for event 3 are placed at Annexure 3 were analysed in details
and with the help of this DR, time line of event 3 has been prepared.
The whole event can be described as follows:
Event started with a Y phase fault followed by three phase fault on the 400 kV Bhachau-
Varsana 1 circuit. The fault was located outside the gantry of 400 kV Varsana sub-station.
Report of Black out at CGPL on 13.07.2016
Flash over were found in wave trap R & B phase and BPI between CVT & LA of Y-
Phase of the circuit at Varsana Sub-station. The fault has occurred at around 7 seconds of
the charging of line from Bhachau end.
The fault on the 400 kV Bhachau-Varsana 1 was seen in zone 2 by Bhachau end. The
time delay at this end for zone 2 is kept as 350 ms as per Ramakrishna committee
recommendation.
The Fault was sensed in Zone 2 by 400 kV CGPL-Bhachau D/C at CGPL end; 400 kV
Bhachau-Ranchodpura D/C at Ranchodpura end.
The time delay for Zone 2 at CGPL end for 400 kV CGPL-Bhachau and at Ranchropura
end for 400 kV Bhachau-Ranchodpura D/C were kept at 300 ms.
As per the Ramakrishna committee report the time delay for these lines should be more
than 350 ms in view that these lines are long lines followed by short lines to avoid
undesirable tripping in case of fault on short line.
After 371 ms of the fault, 400 kV CGPL-Bhachau 1 tripped in Zone 2 from CGPL end (
300 ms zone 2 and 71 ms for Breaker opening).immediately 400 kV Bhachau-
Ranchodpura D/C also tripped in zone 2 from Ranchodpura end ( 300 ms for Zone 2 and
75 ms for breaker opening)
The CGPL generators which were already under forced AVR response due to the three
phase fault, also experienced the power swing with the tripping of 400 kV Bhachau-
CGPL 1 and 400 kV Bhachau-Ranchropura D/C .
The fault in 400 kV Bhachau-Varsana 1 got cleared from the system at 409 ms ( 350 ms
zone 2 and 59 ms for breaker operation time)
The CGPL voltage during the event of fault and after the fault is shown in figure 12 as
taken from DR of 400 kV CGPL-Bhachau 2 circuit. During the fault the CGPL single
phase to neutral voltage has reduced from 237 kV to 95 kV. It was further observed that
with the tripping of 400 kV CGPL-Bhachau 1 and 400 kV Bhachau-Ranchodpura D/C the
voltage has uplifted to 108 kV. However, with the clearance of fault from the system, the
CGPL voltage instead of recovering, declined gradually.
Report of Black out at CGPL on 13.07.2016
Figure 12: Voltage and current of R phase of 400 kV CGPL-Bhachau 2 which
tripped at the last.
This gradual decline in voltage without any appreciable change in the current was
observed from all the remaining five feeders emanating from CGPL.
Further, on analyzing the Active and reactive power Flow on the lines it was found that
during the fault generators have injected VAR to feed to fault. Figure 13 Shows the P/Q
plot on 400 kV CGPL-Bhachau 2 circuit observed from CGPL end. Prior to the fault
generators were in MVAR absorption mode as per the capability curve. With the Y phase
fault, Generators started injecting VAR to feed the fault which increased further with the
fault conversion the three phase fault which is anticipated in case of a generator feeding
the fault..
After the clearance of fault, Generators went to MVAR absorption mode with normal
active power flow. However, the Active power started reducing gradually on all the lines
with suppression of voltage as observed and it eventually became zero.
Trigger13-07-16
2:37:10 AM.226
t/s0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
iL1/kA
0
1
2
3
t/s0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
uL1/kV
0
50
100
150
200
Y phase fault on 400kV Bhachau-Varsana1 at Varsana Fault converted
to three phasefault
400 kV Bhachau-CGPL 1 trip in Zone2
Three phase fault cleared on400 kV Bhachau-Varsana 2
Voltage reduction started from 151 kVand reached to 8 kV within 290ms
As voltage started going up. Relay detected unstable powerswing for all 5 remaining lines from CGPL at CGPL end.
Report of Black out at CGPL on 13.07.2016
Figure 13: (A) No Fault in the system. All generators in absorbing VAR so Line MVARvalue is on -ve side (B) Y Phase Fault in the system. VAR went on Positive side due tofault feeding from CGPL generators. (C)Three Phase Fault in the system. VARcontribution from CGPL has further increased due the three phase fault. (D) Just priorto three Phase Fault clearance from the system. Generator in injection mode. (E) Afterthree Phase Fault clearance from the system. Generator in absorption mode. MVAR onthe line changed from +990 MVAR to -190 MVAR. (F) With decrease in voltage, Activepower flow on the line getting reduced. This is observed for all line emanating fromCGPL.
A B
C D
E F
Report of Black out at CGPL on 13.07.2016
The gradual decrease in the voltage of CGPL bus, after the fault clearance is indicative of
the fact that a power swing was set up. This gradual decrease in voltage of CGPL from
151 kV (after fault clearance) to 8 kV occurred within 290 ms., whereas the current on the
feeders has not changed significantly during this period of voltage decay as can be
observed in figure 14. The CGPL line Distance Protection Relays sensed the apparent
impedance entering in zone 3 followed by zone 2 and eventually zone 1. As soon the
impedance locus entered zone 1, the voltage started going up. All the five line relays
issued the trip command from CGPL end in zone 1 power swing. The power swing digital
status was not available in DRs from CGPL however, same is available in the event
logger of these lines at CGPL end and is placed at Annexure 4. Out of Step protection
also acted at CGPL and tripped units at about same time.
Figure 14: Impedance locus movement during the event at CGPL where it can be seen
how during voltage suppression the impedance has entered zone 1 causing tripping.
As it can be observed that Real power to the network through the five remaining lines
from the CGPL after the fault had started reducing. This resulted in the reduction in
electrical power on these lines causing difference in mechanical power to the generator
1. Apparent Impedance seenby relay when no fault insystem
2. Apparent Impedance of Y Phaseseen by relay in zone 2 when Yphase fault in the system.
3. Apparent Impedance of allthree Phases by the relay in zone2 when three phase fault in thesystem.
4. Apparent Impedance seenby relay when three phasefault got cleared.
5. Apparent Impedance seen by relay when voltage suppressionstarted. After this movement of impedance local all the threephase can be seen. The impedance locus has entered zone 1.
6. As voltage rise started to occur, it was detected asunstable power swing and again the impedanceentered zone 1. With this trip command issued.
Report of Black out at CGPL on 13.07.2016
and electrical power output from the generator, resulting into over speeding of units and
high frequency at CGPL. Due to this the unit went out of step /pole slipping.
Along with these five lines 220 kV Morbi-Bhachau circuit, also sensed the power swing
at Morbi end resulting in tripping of this line along with other lines.
Further during 400 kV CGPL-Bhachau and 400 kV Bhachau-Ranchropura D/C tripping,
power swing was sensed by 400 kV CGPL-Jetpur D/C line DPS.
Low voltage at CGPL has resulted in tripping of drives and auxiliary supply failure and
the SCADA and PMU data got interrupted due to communication equipment were being
supplied power from station supply, after isolation of rest of the system from CGPL.
One PMU is installed at CGPL sub-station with Bus Voltage and Line current of CGPL-
Jetpur 2 and Unit 40. During this event, the Communication supply of CGPL at CGPL
which was sending Data to WRLDC also got affected resulting in lack of PMU data. The
data is available till 02:37:11.560 ms.
Figure 15 shows the PMU frequency plot which shows that event after the fault clearance
the frequency of CGPL bus has reached 50.24 Hz. Increase in frequency at CGPL
indicate the over speeding of generators due to load thrown-off..
Figure 16 Shows the Angular Separation of Various nodes along with CGPL w.r.t
Vindhyachal Bus.
Figure15: Frequency of CGPL with the rest of the grid.
Report of Black out at CGPL on 13.07.2016
Figure 16: Angular Separation of Various nodes along with CGPL w.r.t Vindhyachal Bus.
5.4. Post event Scenario at 02:40 Hrs
After the blackout of CGPL and tripping of Lines from Bhachau, the Gujarat system became
power deficient and power flow increased on the inter-state lines from Madhya Pradesh,
Maharashtra and on Inter-Regional AC lines from Rajasthan towards Gujarat. This can be
observed in Figure 17 which provides the scenario of the Gujarat system after the event.
Figure 17: Gujarat system at 02:40 Hrs i.e. after the blackout of CGPL. CGPL end data
got stuck due to issue at CGPL end. Import on Inter-State lines of Gujarat and Inter-
Regional lines from Rajasthan has increased.Report of Black out at CGPL on 13.07.2016
Figure 16: Angular Separation of Various nodes along with CGPL w.r.t Vindhyachal Bus.
5.4. Post event Scenario at 02:40 Hrs
After the blackout of CGPL and tripping of Lines from Bhachau, the Gujarat system became
power deficient and power flow increased on the inter-state lines from Madhya Pradesh,
Maharashtra and on Inter-Regional AC lines from Rajasthan towards Gujarat. This can be
observed in Figure 17 which provides the scenario of the Gujarat system after the event.
Figure 17: Gujarat system at 02:40 Hrs i.e. after the blackout of CGPL. CGPL end data
got stuck due to issue at CGPL end. Import on Inter-State lines of Gujarat and Inter-
Regional lines from Rajasthan has increased.Report of Black out at CGPL on 13.07.2016
Figure 16: Angular Separation of Various nodes along with CGPL w.r.t Vindhyachal Bus.
5.4. Post event Scenario at 02:40 Hrs
After the blackout of CGPL and tripping of Lines from Bhachau, the Gujarat system became
power deficient and power flow increased on the inter-state lines from Madhya Pradesh,
Maharashtra and on Inter-Regional AC lines from Rajasthan towards Gujarat. This can be
observed in Figure 17 which provides the scenario of the Gujarat system after the event.
Figure 17: Gujarat system at 02:40 Hrs i.e. after the blackout of CGPL. CGPL end data
got stuck due to issue at CGPL end. Import on Inter-State lines of Gujarat and Inter-
Regional lines from Rajasthan has increased.
Report of Black out at CGPL on 13.07.2016
5.5. Restoration of the system
Immediately after the event, the restoration activities were started by WRLDC control room
in coordination with CGPL/Gujarat SLDC and PGCIL. Start-up supply was extended to
CGPL from 400 kV CGPL-Chorania circuit at 03:40 Hrs. After this one by one other
transmission elements were taken in service as provided in table 1 which have tripped during
event 1, event 2 and event 3. Generators were also restored subsequently as provided in table
2.
Table 1 : Transmission Elements Restoration
Element Date of
Restoration
Time of Restoration
400 kV Varsana-Hadala* 12-07-16 21:41 (It again tripped
on bus 2 fault at 21:50
Hrs)
400 kV Bhachau-Ranchodpura 2 13-07-16 03:11
220 kV Bhachau-Morbi 13-07-16 03:24
400 kV CGPL-Chorania 13-07-16 03:40
400 kV CGPL Bus 1 13-07-16 03:40
400 kV CGPL Bus 1 13-07-16 03:40
400 kV CGPL-Bhachau 2 13-07-16 04:47
400 kV Varsana-Hadala* 13-07-16 09:10
400 kV Varsana Bus 2 13-07-16 09:10
400/220 kV 315 MVA Varsana
ICT 213-07-16 11:26
125 MVAR Varsana Bus Reactor
213-07-16 11:39
400 kV APL-Varsana 1 13-07-16 11:51
400 kV APL-Varsana 2 13-07-16 11:57
400 kV Varsana-Kansari 13-07-16 18:35
400 kV Varsana Bus 1 13-07-16 18:35
50 MVAR Varsana Bus Reactor 1 13-07-16 18:46
400/220 kV 315 MVA Varsana
ICT 113-07-16 18:57
Report of Black out at CGPL on 13.07.2016
400 kV CGPL-Jetpur 1 13-07-16 19:50
400/220 kV 315 MVA Varsana
ICT 313-07-16 22:26
400 kV Varsana-Bhachau 2 14-07-16 16:26
400 kV CGPL-Bhachau 1 14-07-16 08:58
400 kV CGPL-Mansar 14-07-16 09:36
400 kV Bhachau-Ranchodpura 1 14-07-16 08:39
400 kV CGPL-Jetpur 2 14-07-16 10:20
400 kV Varsana-Bhachau 1 15-07-16 13:25
400 kV Bhachau-Essar Vadinar 1
(Idle changed from Bhachau)16-07-16 07:48
400 kV Bhachau-Essar Vadinar 2
(Idle changed from Bhachau)16-07-16 07:48
Table 2 : Generation Restoration
Unit Name Date of
Restoration
Time of Restoration
CGPL Unit
40
13-07-16 18:36
CGPL Unit
40
14-07-16 00:45
OPGS Unit 1 15-07-16 02:39
CGPL Unit
30
16-07-16 19:07
CGPL Unit
10
21-07-16 19:10
Report of Black out at CGPL on 13.07.2016
6. Performance of defence mechanisms
1. Frequency Response Characteristic
Frequency Response Characteristics of WR and its constituents during CGPL Blackout is
enclosed at Annexure-5
2. ROCOF (df/dt) Based load Shedding
The quantum of df/dt based load shedding is enclosed at Annexure-6
3. SPS Scheme at CGPL
The SPS in service at CGPL is enclosed at Annexure-7
7. Conclusions & Recommendations:
1. RTV Silicone Coating of Insulators:
The bus fault at Varsana has occurred due to the insulator tracking and
flashover during foggy weather conditions with rains. PGCIL informed that flashover
event could be minimised if the hot-line washing and RTV silicone coating of
insulators be completed prior to the rainy season. Therefore sub-station falling under
pollution zone/saline zone should explore adopting best practices of hot line washing
prior to rainy season along with the application of RTV silicone coating to avoid such
events in future. Varsana is an important GETCO station connected to two large
generation complexes. GETCO may look into the possibility of RTV Silicone coating
in such areas.
2. Charging of Dead Bus:
Dead Bus should generally be charged through a long line or through ICTs, so
that the fault currents are less. A Dead Bus after bus fault should not preferably be
charged through short line and lines having generator connected at remote ends of
lines. Also dead bus should not be charged through line having strong source at the
other end.
Action: All utilities to please note for future.
Report of Black out at CGPL on 13.07.2016
3. Power Swing phenomenon
Prior to the event, the CGPL generation was around 2875 MW. During the event
CGPL Units had fed the three phase fault at Varsana for a duration of 350 ms. Along
with this event, three 400 kV lines also got tripped which was followed by a
continuous decline of voltage for 290 ms. The voltage started rising, this was detected
as a power swing entering in zone-1 by the line DPS at CGPL end and the lines
tripped.
The reasons for excitation of the oscillations need to be found out since these
oscillations were not damped out resulting in a severe power swing. A transient study
by modelling the proper network is required to done.
PCM may decide the modalities of carrying out these studies. The scope of these
studies shall be to examine the cause of power swing, various factors that contributed
to CGPL machines going Out of Step and suggest remedial measures.
4. Protection Coordination Issue in Zone 2
The Zone 2 settings adopted by CGPL for all the lines, at CGPL end is
300msec and the remote end settings are 350msec. The adoption of 300msec for Zone
2 at CGPL end is in view of stability of generating units and critical clearing time of
faults. It was noted that the 400kV Bacchau-Versana-1 & 2 lines are very short lines
(8.5kM). Therefore group recommended interimly that PGCIL may adopt 250msec
for 400kV Bacchau-Versana-1 & 2 and CGPL may adopt 350msec for time being,
and afterwards based on the studies for critical clearing time/stability of the generators
for faults to be carried out, it would be decided to raise the zone 2 time settings for
these lines. PGCIL/GETCO/CGPL in mutual coordination may set the relay settings
as above. PCM may vet these interim settings.
5. Permissive Trip Carrier being received as direct trip for 400 kV Bhachau-CGPL
1 at Bhachau end.
It was observed that the permissive carrier sent by CGPL for the 400 kV
CGPL-Bhachau 1 was received as direct trip by the Bhachau end. In view of this, end
to end testing of the Carrier signal has to be checked by the both utilities (CGPL and
PGCIL) in coordination with each other.
Report of Black out at CGPL on 13.07.2016
6. Bus configuration at 400 kV Varsana.
The elements should be distributed evenly on the buses (Bus A & Bus B) such
that these elements can be served optimally in the event of Bus faults to enhance the
reliability. The elements on Bus-1 & Bus-2 were not evenly loaded at 400kV Varsana
S/S. Therefore it is recommended that GETCO may explore how Bus configuration
can be changed such that, balanced loading on buses is achieved on both the 400 kV
buses at Varsana S/S.
7. SPS at CGPL :
As none of the criteria for CGPL operation was satisfied due to low generation
at CGPL, the SPS has not operated as per the design.
8. Loss of PMU data from CGPL:
After tripping of units & auxiliaries the PMU data was not available. It should
be ensured that the data from PMU should always be available.
Further in the report on similar blackout at CGPL in 2014 it was
recommended that the PMU installed on unit 40 does not serve any purpose in
analysing such events and therefore it was suggested that the same should be shifted
on 400KV CGPL- Bhachau line.
It is again recommended that the above should be done immediately.
*********************************************************************
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
1) Zone 1 seeting of 400kV & 220kV lnes areset to 90% instead of 80% which needs to berevised to 80%.
Yes Yes … … … … ……
Directional E/F setting to be adopted inBhusawal & Nandgaon Peth Bay.
… … … Yes No …
STUB Protection to be enabled in NandgaonPeth & Bhusawal Relay.
… … … Yes No …
Zone-4 setting was 1000 ms. Yes Yes … … … … Zone-4 setting adopted400 ms according ESGgroup.
Harmonic restrain feature not adopted inboth H.V. & L.V. Back-Up Relay
… … … Yes No … Services of SiemensEngineer required.Requirement sent to TheExe.Engg 400KV RSDivision, Akola.
Only internal OPEN delta used in NDVRRelay for tripping. External Open delta foralarm is not available.
Yes Yes … … … …
Importang digital signals are not included inDR of Nandgaon peth, Bhusawal & ICT bay.
… … … Yes No … Required changes insetting file of relay iscarried out offline.However for configurationoutage , services ofsiemens engineer isrequired.Requirementalready sent to TheExe.Engg 400KV RSDivision, Akola.
Wide variation in LBB current detectorsetting.
… … … … … … Matter is taken up withM/S PGCIL.
400 KV
Required changes insetting file of relay iscarried out offline.However for configuration
Name of Zone: Amravati
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Akola1
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Name of Zone: Amravati
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
2 Paras 220 KV The s/stn is audited in previous 2 years andthe descripancies are attended andcomplied. No descripancy observed duringthe PA - 2014-15
… … … … … … The s/stn is audited inprevious 2 years and thedescripancies are attendedand complied. Nodescripancy observedduring the PA - 2014-15
3 Akola 220 KV The setting of LBB relays was 0.2 Amp forEHV Lines
Yes Yes … … … … The setting revised andkept 0.8 amp as per ESGrecommendation.
1. Carrier protection & AR scheme for 220KV feeders not commissioned
No -- -- Yes Yes -- SEL 321 relays replacedunder retrofitting schemeand AR Scheme commd.
2. Load trimming scheme for ICTs is needed. Yes Yes -- No -- -- Load trimming schemecommissioned.
1. Zone 3 setting of all 220 KV & 132 KVlines was 100% of protected + 100% oflongest line at remote s/stn
Yes Yes … … … … Settings corrected as perESG recommendation as :120% (Protected line +Longest line at RemoteS/stn)
2. Zone -2 time setting of 220 kV Ambazari& 132 kV Ambazari lines needs to be revisedas these lines are followed by short line atremote S/stn.
Yes Yes … … … … Existing 350 msec settingsevised to 450 msec.
1. Zone 3 setting of all 220 KV was 100% ofprotected + 100% of longest line at remotes/stn
Yes Yes … … … … Settings corrected as perESG recommendation as :120% (Protected line +Longest line at RemoteS/stn)
2. LBB setting of T/F 1&2 was 80% of CTRconnected instead of 80% of T/F operatingcurrent
Yes Yes … … … … The settings corrected.
Badnera 220 KV6
220 KVChikhali4
220 KVAmravati5
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Name of Zone: Amravati
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
7 Malkapur 132KV … … … … … … …
8 Dhamangaon 220 KV 1. Zone 3 setting of all 220 KV was 100% ofprotected + 100% of longest line at remotes/stn
Yes Yes … … … … Settings corrected as perESG recommendation as :120% (100% Protected line+ 100% Longest line atRemote S/stn)
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,re
ason
Yes/No
WhetherattendedYes/No
If no,expecteddate to attend
1. Zone-4 (reverse zone)timing setting ofDisatce relay is 900 mSec
Yes Yes -- -- -- completed Zone -4 (reverse Zone) timesetting revised to 350 msec
2.DG set not available -- -- -- Yes No On receipt ofmaterial
3.Only one DC source available -- -- -- Yes No On receipt ofmaterial
1.Zone-4 (reverse)timing setting of Disatancerelay is 900 mSec.
Yes Yes -- -- completed Zone -4 (reverse Zone) timesetting revised to 350 msecas per Protection auditguidelines.
2.DG set not available -- -- -- Yes No On receipt ofmaterial
3.Only one DC source available -- -- -- Yes No On receipt ofmaterial
4. 220KV & 132KV Bus section isolationcircuit Breaker not available. The saidbreaker are proposed in the 220 kV & 132kV Main Buses.
-- -- -- Yes No On Availabilityof Breaker
1.For 400kV Solapur line zone 4 & brokenconductor detection functions are OFF in M-1 & M-2. A/R function is OFF in M-2
NO NO Yes NAWork inProgress
ABB representative isawaited. communicationsoftware is not available
For 220kV Murud line zone 3 setting is morethan calculated setting
Yes Yes NA NA NA completedThe same is rectified andadopted as per calculation
For PGCIL ckt- 1 & 2 Zone 4 time setting issame as zone 3 time and Broken conductorfunction is OFF in main-2 relay of both lines.
Yes Yes NA NA NA NA
1)Zone 4 time changedfrom 1 sec to 1.1 sec 2)Broken conductor functionis enabled in main-2 relayof both lines.
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 30/07/2016
Name of Zone: Aurangabad
Sr.No.
Name Of S/sIdentified for
protection Audit S/svoltage
(kV)
Observations of Protection Audit Deficiencies that can becorrected without
procurement(Category-A)
Deficiencies involvingprocurement(Category-B)
Present status as on30/07/2016
1 220KVPADEGAON
220 KV
2 220KV JALNA 220 KV
3 400kV Girwali400/
220kV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,re
ason
Yes/No
WhetherattendedYes/No
If no,expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 30/07/2016
Name of Zone: Aurangabad
Sr.No.
Name Of S/sIdentified for
protection Audit S/svoltage
(kV)
Observations of Protection Audit Deficiencies that can becorrected without
procurement(Category-A)
Deficiencies involvingprocurement(Category-B)
Present status as on30/07/2016
BRC feature disabled. YES YES NA NO NA completed
SOTF feature is selected for all zones YES YES NA NO NA completed
PSB blocking zones selected for all zones YES YES NA NO NA completed
A/R feature is disabled NO NO YES NOon receipt ofbinary IO cards
single ph LBB initiation isnot available
Timing of Zone II for 220 KV Harangul I & II& nanded is 350 mSec.
YES YES NA NO NA completed
Some contacts of PT selection relay are notoperating.
NO NO NA YES NOAfter receipt ofrelays
Requirement submitted
Existing PT selection scheme is as per old PT.In old PT only 1 core is used for ProtectionAs well as metering purpose.
NO NO NA YES NOAfter receipt ofPT
Requirement submitted
5220 KV New TPSParli
220 KV SOTF feature is selected for all zones YES YES NA NO NA completed
1. Protected Line Lengths. YES YES NA NO NA completed
2. Brocken conductor function disabled. YES YES NA NO NA completed
3. SOTF selected for all zones. YES YES NA NO NA completed4. PSB blocking zones selected asZ1,Z2,Z3,Z4.
YES YES NA NO NA completed
5. 132KV bus-bar protection fail alarm &block settings were different.
YES YES NA NO NA completed
8. DC supervision scheme is not available onany panel.
NO NO NA YES NOOn PanelReplacement
Requirement submitted
9. Separate DC circuits for Main prot., B/Uprot., isolator circuits, trip ckt-1 & 2,annunciation & indication ckts, etc are notavailable in any panel.
NO NO NA YES NOOn PanelReplacement
Requirement submitted
11. The present annunciators on 132KVRenapur, 132KV Latur Line and 132/33KV TF-4 panels are faulty.
NO NO NA YES NOWork inProgress
Requirement submitted
4220 KV OLD GCR
Parli220 KV
6 220 KV GIRWALI220/132/3
3 KV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,re
ason
Yes/No
WhetherattendedYes/No
If no,expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 30/07/2016
Name of Zone: Aurangabad
Sr.No.
Name Of S/sIdentified for
protection Audit S/svoltage
(kV)
Observations of Protection Audit Deficiencies that can becorrected without
procurement(Category-A)
Deficiencies involvingprocurement(Category-B)
Present status as on30/07/2016
2) 132KV Jangamwadi-II Bay: Announciatorfaulty.
NO NA NA YES NOWork inProgress
Requirement
14) 220KV PT:- i) Single core has beenutilized for protection & metering as per oldscheme ii) Open delta voltage derived fromauxiliary PT
YES NA
After cablelaying & onavailabilityof outage
duringretroffiting
NO NA NA Outage awaited
16) 132KV Umri-1, 132KV Umri-II, 132KVNarsi, 132/11KV 25MVA Emco TF, 132/11KV25MVA BB TF, 50MVA 132/33KV Vijay TF,50MVA 132/33KV BBL TF: 132/33KVTripcircuit Supervision Relay
NO NA NA YES NOOn RelayReceipt
Requirement submitted
17) 132KV Umri-1, 132KV Umri-II, 132KVNarsi, 132/11KV 25MVA Emco TF, 132/11KV25MVA BB TF, 50MVA 132/33KV Vijay TF,50MVA 132/33KV BBL, 132KV Jangamwadi-1, 200MVA 220/132KV BBL ICT-1, 200MVA220/132KV BBL ICT-II, 220KV TBC TF:- C.BSupervision relays
NO NA NA YES NOOn RelayReceipt
Requirement submitted
20) cable from TF LV bay CT M.B to Panel formetering is of 4 core Aluminium cable.Hence eeds to be replaced by 4 core Coppercables.
NO NA NA Yes NO work in Progress Requirement submitted
7 220KV Waghala 220KV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,re
ason
Yes/No
WhetherattendedYes/No
If no,expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 30/07/2016
Name of Zone: Aurangabad
Sr.No.
Name Of S/sIdentified for
protection Audit S/svoltage
(kV)
Observations of Protection Audit Deficiencies that can becorrected without
procurement(Category-A)
Deficiencies involvingprocurement(Category-B)
Present status as on30/07/2016
7. NT switches for 132KV Jintoor & Parbhanibays are not working
NO NA NA YES NO Attended completed
8. Cables utilized in CT circuitery for 132 &220KV from CT M.B to Panels are Aluminiumtype. Needs to b replaced by copper
NO NA NA YES NO work in Progress Requirement submitted
9. Bus sectionaliers for 132 & 220KV notavailable.
NO NA NA YES NO work in Progress Requirement submitted
10. 05 nos of Battery cells detected -Ve.Replacement required
NO NA NA YES NOAfter
Procurement.Requirement submitted
13. 07 nos of D.C supervision relays foundfaulty
NO NA NA YES NOAfter
Procurement.Requirement is to besubmitted
220 KV Parbhani 220KV8
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
DGA testing of ICT YES Yes - - -DGA tender is in processby O & M circle office
GPS synchonisation of Relays YES No
Issue to betaken withmanufactu
rer
- - -
Zone 1 seeting of 400kV &220kV lnes are set to 90%instead of 80% whichneeds to be revised to80%.
400KV Karad-Lonikand Line Autorecloser notin service.
YES Yes - - -Work is done. AR taken inService in July -15
Nitrojen injectoin system for ICT -I is onManual mode due to only one relay panel(CTR Make)
- - - Yes No
within 10 daysafter receipt of
relays, subject tooutage
Requirement of 400/220KV, 315MVA ICT-I relay panelalready submitted to C.OMumbai
GPS synchonisation of Relays - - - YES No -GPS synchonisation isdone for Main-I & Main-II
DG set shall be made available foremergencies
- - - YES No -Requirment is submitted toC.O.
3 220 kV Vita 220 - - - - - -OTI meter found faulty for EMCO make,220/132 kV, 100 MVA T/F
- - - Yes No Needs Procurement
R Phase element of TMD unit is faulty for220 kV Busbar Protection relay
- - - Yes No
5 220 kV Peth 220 Nil - - - - - - -
6 220 kV Ogalewadi 220 Nil - - - - - - -
Distance relay of 110 kV Vishrambag 1 line isfound removed due to its faulty power card
- - - Yes No -Relay is repaired &retrofitted on 02.02.2015
New 110 kV Busbar protection scheme isrequired in view of replacement of old faultyscheme.
- - - Yes No - Order is placed by C.O.
Present Status as on31/07/2016
1
2
4
7 220 kV Miraj 220
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Karad
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
400kV Karad 400 kV
400 KV New Koyna 400 KV
220 kV SataraMIDC
220
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Karad
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
WTI & OTI of 220/33 KV T/F No.1 & 2 arefaulty.
- - - Yes No - Needs Procurement
Relays for generation feeders should be ofDirectional feature i.e. for 33 KV vankusavde1,2,3,4, 33 KV RS India 1,2 feeders foravoiding unwanted trippings along withoutgoing feeders at Malharpeth S/stn
- - - Yes No -
R and Y phase 220 KV PTs are of 2 cores(mixed metering and protection core) . Itshould be of 3 cores for correct protectionoperation and proper energy accounting.
- - - Yes No -
33 KV PT not available for 220/33 KV, T/FNo.2; and it is required for proper energyaccounting and UFR & Feeders (directionalrelay ) tripping.
- - - Yes No -
UFR should be having PT selection for 33 KVPT 1&2
- - - Yes No -
9 220 kV Lonand 220
22 kV Bus PT is having Single Cores whichshould have of 3 cores so as to separate outprotection and metering classes forcorrosponding applications.
- - - - - - -
10 220 kV Jath 220 Nil - - - - - - -
11132 kV Satara
Road132 Nil - - - - - - -
8 220 kV Malharpeth 220
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Karad
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
MOG of 110/11 KV,EMCO T/F not working - - Yes No - Needs Procurement
No trip relays are available to O/C-E/F relays'of following feeders- 33KV Shirgaon LIS,33KV Shahu LIS, 11 KV Kay pulp
- - Yes No -
O/C-E/F relays of generation feeders shouldbe having directional feature i.e. for 33 KVVankusavade 1,33 KV Vankusavade 2 feeders
- - Yes No -
UFR should be having PT selection for 33 KVPTs and 11 KV PT
- - Yes No -
13 110 kV Ashta 110 Nil - - - - - - -
14 Mudshingi 220 KV
110 kV PT is having 2-cores which shouldhave of 3-cores so as to separate outProtection and metering classes forcorresponding applications
- - - Yes No needs Procurement
15110 kV Gokul
Shirgaon110 KV Nil
Directional Relay should be provided forTransformer-I & Transformer-II.
Yes NoNR Scope make Panels arereceived & replacementwork is in process
REF relays for 50 MVA Transformer-I & IIshould be replaced. Existing relays are notsuitable for REF Protection.
Yes No
220 kV PT should be of 3 Cores. Presentlythere is of 2 Cores PT.
Yes No needs Procurement
17 kale 110 KV nil
18 Halakarni 220 KV nil
19 Pawas 220 KV Busbar protection relay required Yes NoOrder given to M/S NR forbusbar relay
12
16 220 kV Mumewadi 220/33 KV
110 kV Atit 110
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Karad
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
1) For 110 /33 KV Voltamp make TF Fan no-3 not working.
YesNot working fan wasreplaced on dated24.01.2015
2) Fan switch for 110/33 KV Voltamp makeTf needs to be in auto mode.
Fan switch kept on automode
3) B/U relay time setting of 110 KVRadhanagari fedder needs to be modified ifrequired.
Settings are revised as perfault level
21 Bapat Camp 110 KV nil
22 Wathar 220 KV220 KV Bus bar protection is out of servicesince 16 Mar 2014 due to relay's displayproblem.
Yes NoAfter repaired, tested andtaken into service
23 Kanakavali 132 KV nil
24 Kharepatan 220 KV Busbar relay found faulty Yes NoAwaited for M/S ABBrepresentative for repairthe same
25 Lote 220 KV nil
20 Kotholi 110KV Yes
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
1) Zone 1 seeting of 400kV & 220kV lnes areset to 90% instead of 80% which needs to berevised to 80%.
Yes Yes Attended
2)Earth leakage to be attended Yes Yes Attended
3) For 400KV Bhusawal & Koradi-II ckt, REL521 ABB make distance schemes (Main-I &Main-II) are provided. In REL 521 (ABB make)distance scheme, Zone-4 i.e. Back-up to busbar feature is not available.
Yes No Pending
2400KV
Khaperkheda S/Stn400KV
1)220V Set :- Cell no. 5 specific gravity to beconfirmed
Yes YesSpecific Gravity of Cell no.5 is 1220
3400KV Koradi-II
S/Stn400KV 1) Earth leakage to be attended Yes No
Notattendedby Project
agency
Pending
1)Earth leakage to be attended Yes Yes Attended 2)Battery 220V Set 1 Cell no.36 is in poorcondition & need to be replaced.
Yes Yes Attended
5400KV Chandrapur-
II S/Stn400KV
1)Charger Earth leakage problem in boostmode to be attended
Yes No
To attend the problemsome costly spares are
required and as it is stillunder guarentee periodhence matter is taken
upwith M/s.BHEL1)DC mixing problems to be attended Yes Yes Attended
2)Earth leakage (2-3 mA) to be attended Yes Yes Attended
3)MB Cable pulling problem to be attended Yes NoMatter taken up with M/sL&T dt.26.08.2015
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
4400KV GCR
Chandrapur S/Stn400KV
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
6400 KV Warora
S/Stn400KV
1400KV Koradi
S/Stn400KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
1)Earth leakage to be attended Yes YesEarth leakage attendedand presently earthleakage is NIL
2)132/11KV, 25MVA T/F: Oil leakage fromdrain valve to be attended.
Yes Yes Attended
3)Vermin proofing needs to be improved. Yes Yes Attended
4) Metal spreading is inadequate. Yes Yes Attended
5)Grass cutting is required. Yes Yes Attended
6)220KV & 132KV Isolator structure problem Yes NoPertaining to civil Dncorrespondace done withcivil Dn.
7)ICT-3 (Bharat Bijlee):- Online H2 & H2Omeasurement (model calisto make MORGONSCHFFER Canada) not working
Yes No Offer not received fromagency
8)220V 500AH Exide battery set havingEfficiency 60% Needs to be replaced/reconditioned
Yes No Requirement submitted
9)48V 200AH exide battery set efficiency70% Needs to be replaced/ reconditioned
Yes Yes Replaced can 12.03.2015
10)25 MVA, 132KV/11KV T/F-I Bph Ir is 227micro Amp. It=1219.7 micro amp. IR valuesof LA stack needs to be confirmed.
Yes Yes Ir-37 It-618 on dt. 13.01.2016
11)Hingna-I 132KV Bph Ir = 239 microA It =410 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-35 It-585 on dt. 13.01.2016
7220KV Ambazari
S/Stn220KV
7220KV Ambazari
S/Stn220KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
12)220KV Koradi-II 220KV RphIr = 277 microA It = 252 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-25 It-570 on dt. 13.01.2016
13)Koradi-I 220KV RphIr = 175 microA It = 271 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-33 It-589 on dt. 13.01.2016
14) 200MVA, 220/132KV-ICT-III 132KV YphIr = 232 microA It = 1228 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-31 It-760 on dt. 13.01.2016
15) 200MVA, 220/132KV-ICT-II220KV BphIr = 238 microA It = 771 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-81 It-430 on dt. 13.01.2016
16)200MVA, 220/132KV-ICT-III132KV BphIr = 297 microA It = 1986 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-71 It-600 on dt. 13.01.2016
17)200MVA, 220/132KV-ICT-II132KV YphIr = 222 microA It = 1765 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-41 It-561 on dt. 13.01.2016
220KV220KV Ambazari
S/Stn7
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
18) 150MVA, 220/132KV ICT-I132KV Y-PHIr = 247 microA It = 3642 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-32 It-760 on dt. 13.01.2016
19) 25MVA, 132/11KV T/F-I132KV Y-PHIr = 208 microA It = 1144 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-24 It-571 on dt. 13.01.2016
20)25MVA, 132/11KV T/F-I132KV B-PHIr = 267 microA It = 759 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-37 It-618 on dt. 13.01.2016
21) 132KV Amrawati132KV Y-PHIr = 201 microA It = 2153 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-31 It-536 on dt. 13.01.2016
22) 132KV Hingna-I132KV B-PHIr = 374 microA It = 589 microALA needs to be replaced.
Yes Yes Ir-35 It-585 on dt. 13.01.2016
23)CTs having higher Tan delta values needsto be replaced
Yes YesPD carried out and CTsfound ok
24) In 7SA511 Zone-4 is not in operation Yes No Pending
220KV AmbazariS/Stn
220KV7
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
1)220KV K' Wada-II ckt: 3nos IVT's to bereplaced by CVT's
Yes No Requirement submitted
2)48V battery bank: 15th number cell isbypassed needs restoration
Yes Yes Cell Commissioned
3) K'Wada-I -2 nos,Suryalaxmi-1 no,Butibori-III - 1 No4 Nos oil leaked CVT's to be attended
Yes Yes Attended
4)Cable trench broken slippers to bereplaced.
Yes NoPertaining to civil Dn Dn.correspondace done
5) Earth leakage to be attended. Yes Yes Attended6) Grass cutting & metal spreading in yard isrequired.
Yes Yes Attended
7)Vermin proofing needs to be improved. Yes Yes Attended
1)Bus coupler: Y-Ph & R-ph CT oil leakageto be attended.
Yes Yes Attended
2)100MVA, 220/132KV ICT, T/F-3 & T/F-1:-Oil leakage to be attended.
Yes Yes Attended
3)Grass cutting in yard is required. Yes Yes Attended
4) Vermin proofing needs to be improved. Yes Yes Attended
5) 50MVA 220/33KV T/F-I EMCO 220KV R-PHIr = 153 microA It = 823 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-29 It-715 on dt. 28.01.2016
6)50MVA 220/33KV T/F-I EMCO 220KV B-PHIr = 223 microA It = 813 microAIR values of LA stack needs to be confirmed.
Yes Yes Ir-77 It-655 on dt. 28.01.2016
7)132KV Khapri-II 132KV B-PH Ir = 184microA It =408 microA IR values of LA stackneeds to be confirmed.
Yes Yes Ir-32 It-486 on dt. 28.01.2016
8220KV
Khaperkheda S/Stn220KV
9220 KV Butibori
S/Stn220KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
1)Earth leakage to be attended. Yes Yes Attended2) 48V Battery set: Battery Bank efficiency :-50%Needs replacement/ recondition
Yes YesReplaced on Feb 15(27.02.2015 ) Battery 100%
3) Hingna –II feeder ABT meter problemneeds to attend
Yes Yes Meter replaced
4) 132/11KV, 25 MVA T/F-I132/11KV, 16 MVA T/F-II132/11KV, 50 MVA T/F-IICooling fans not working in auto mode.
Yes Yes Attended
5)For 220KV Amabazari & 220KV Pandhurnafeeder, PLCC coupling is Ph-E. Needs to beconverted to Ph-Ph to reduce the chances ofA/R failure during Ph-E fault.
Yes No CCs recivied WTs required.
6)Vermin proofing needs to be improved. Yes Yes Attended
7)Metal spreading is inadequate. Yes NoPertaining to civil Dn Dn.correspondace done
8) 220KV Ispat, R-Ph -118, Y-Ph – 199, B-ph -143 Repeat the CRM
Yes YesValues within permissiblrlimit R-ph - 38 Y ph - 22 Bph - 28
1)220V Battery bank :75 no. Cell is bypassed Yes Yes Attended
2)220V Battery bank:- Efficiency 65%. Batterybank needs to be replaced.
Yes Yes Attended
3)220V Battery bank:- Cell no.7,9,20,21,66,95,96 specific gravity to beconfirmed.
Yes Yes Attended
4) Oil leakage in Y ph bus PT-I needs to beattended
Yes Yes Attended
5)Oil leakage in 200 MVAICT R& Y ph HV &neutral bushing to be attended.
Yes No Pending
11220KV Bhandara
S/Stn220KV
10220KV Kalmeshwar
S/Stn220KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
6) Vermin proofing needs to be improved Yes Yes Attended
7)Diagnostic testing progress needs to beaccelerated.
Yes Yes Attended
8)Earth resistance value to be confirmed. Yes No Pending
9) After transferring Kanhan-I feeder on TBC,it is observed that, distance protection nottransferring on TBC. Same to be confirmed/rectified with Testing Engineers
Yes Yes Attended
10)Following feeders are not closingremotely1) 132KV madgi-I & II2) 16MVA T/F HV side3) 132KV Ambhora-I4) 132KV Kardha5) 100MVA ICT HV/LV
Yes No Pending
11) 132KV Ambhora-II & 132KV Kanhanfeeder CB spring charging problem
Yes Yes Attended
1)220V Battery bank: Cell no. 26 specificgravity to be confirmed
Yes Yes Sp. Gravity is ok
2) 220V Battery bank :72 no. Cell is bypassed Yes No Requirement is forwarded
3) 220V Battery Bank efficiency :- 60%48V Battery Bank efficiency :- 70%Needs replacement/ recondition
Yes No Requirement is forwarded
4) Earth resistance value to be confirmed. Yes YesEarth Resistance valuesconfirmed and satisfactory
5) CTR is bypassed for 200MVA ICT Yes Yes CTR taken in Service 6)33KV Tiroda breaker remote closingproblem
Yes Yes Problem resolved
12220KV Kaulewada
S/Stn220KV
220KV220KV Bhandara
S/Stn11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
7) Oil leakage of following equipments to beattended1)200MVA ICT-I & 100MVA ICT-I2)220/33KV 25MVA TF-1 & 2
Yes
Yes(Except
220/33KV25MVA TF-
1 & 2)
Requirement is forwarded
8)132KV Kachewani-I132KV Y-PHIr = 160 µA It = 1394 µAIR values of LA stack needs to be confirmed
Yes Yes Trend is under Monitoring
9) CC’s are bypassed for following feeders:-1) 132KV Madgi-1 B Ph2) 132KV Gondia-13) 132KV Gondia-2 B Ph4) 220KV Khaperkheda-2
Yes No Requirement is forwarded
1)220V DC Earth leakage problem to beattended
Yes NoWill be
attendedsoon
The work is to be carriedout by testing/by externalagency
2) Earth leakage ammeter on charger to beprovided
Yes No At an earliest Pending
3)110V DC earth leakage problem to beattended
Yes NoWill be
attendedsoon
Pending
4) 110V Charger Annunciator is not inworking condition
Yes No At an earliest Pending
5)Cracks found in REC structure of isolator Yes No At an earliest Pending
6)Oil leakage of following equipments to beattended1)66/11KV 10MVA TF2)220/66KV 50MVA TF-23)66/11KV 10MVA TF 3
Yes1) No 2)
Yes 3) No
1) Work till notattended 2)
Work attendedby agency 3)Work till not
attended
Pending
13220KV Wardha
S/Stn220KV
12220KV Kaulewada
S/Stn220KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
7)Vermin proofing needs to be improved YesYES (Partiallycompleted)
Requirement submitted
8)Diagnostic testing progress needs to beaccelerated.
Yes Yes Attended
9) Earth resistance value to be confirmed. Yes Yes Attended
10)Metal spreading required Yes No Requirement submitted 11)HEL make CB of TF is not remotelyclosing.
Yes No Requirement submitted
1)Last C/D cycle carried out in Yr. 2012 Yes No Pending 2)Oil leakage of following equipment to beattended1)25MVA, 132/33KV TF-1 & 22) 80MVA 220/132KV ICT3)33KV Bus PT
Yes Yes Attended
3)Earth resistance value to be confirmed. Yes Yes Attended
4)Vermin proofing needs to be improved Yes Yes Attended
5) Metal spreading required Yes Yes Attended
6)Grass cutting is required. Yes Yes Attended
7)CRM not carried out in 2014-15 Yes Yes Attended
8)DGA not carried out in 2014-15 Yes Yes Attended9)ABT meter not present for followingequipments / feeder:1)220/132KV 100MVA ICT-2 HV/LV2)132/33KV 25MVA TF-1 LV3)80MVA 220/132KV ICT-I LV
Yes NoABT meters arenot available
Pending
10)220/132KV 80MVA ICT-1 (HV breaker)TC1:- RPh- 108, Y Ph:- 111, B Ph:- 109TC2:- RPh- 108, Y Ph:- 110, B Ph:- 108Repeat the timing
Yes Yes Attended
13 220KV220KV Wardha
S/Stn
14220KV Hinganghat
S/Stn220KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
1)220V Battery bank:- Cell no. 4,43,45,48,68cell voltage to be confirmed
Yes YesBattery cell replaced ondtd 11.01.2016
2)Grass cutting is required. Yes Yes Attended 3)Lloyd CB PDR relay problem needs to beattended.
Yes Yesproblem attended on dtd.10.12.2015
4)Oil leakage of following equipment to beattended1)Lloyd feeder Y ph Metering PT2)TBC Y ph CT3)220/33KV 25MVA TF 1 & 24) 220/132KV 100MVA ICT5) 220/132KV 100MVA ICT LV Y Ph CT6)132KV Deoli R,Y,B ph CT7)132KV Seloo R ph CT8)33KV Sewagram Y ph CT9) 33KV Bus Y ph PT
Yes
Yes(except132KV
Deoli Y phCT &
33KV BusY ph PT
minor leakagefrom connectionbox.hence\ need
replacement
Requirement submitted
5)Vermin proofing needs to be improved Yes Yes Attended
6) Diagnostic testing progress needs to beaccelerated.
Yes Yes Attended
7)Earth resistance value to be confirmed. Yes Yes Attended
8)Metal spreading required Yes No Requirement submitted 9)220/132KV 100MVA ICTAERC3 :- 3 nos. Multiplier relay faulty needsto be replaced.
Yes No Requirement submitted
15220KV Bhugaon
S/tn220KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
1)220V Set :- Cellno.1,3,5,14,16,35,36,60,61,74, 104 specificgravity to be confirmed
Yes Yes Values are within limit
2)Last C/D Cycle carried out on 12.04.2012 Yes YesCD cycle carried out on dt.14/04/2015.
3)48V Set :- Cell no.1, 16 specific gravity tobe confirmed
Yes Yes Values are within limit
4)Earth leakage ammeter on charger isfaulty
Yes NoAdministrative approvalproposal for batery chargerrepairs is submitted
5)Post Monsoon LCM not carried out. Yes YesCarried out ondt.23/02/2015
6)Earth resistance value to be confirmed. Yes YesConfirmed values arewithin limit
7)Grass cutting is required. Yes YesDone by agency ondt.10.12.2015
8)Earth leakage to be attended. Yes YesAttended but (-) ve leakageis present.
9)Oil leakage of following equipments to beattended : 1)220/33 KV 25 MVA TF 1 & 2,2)220/132 KV 50 MVA ICT 1, 3) 220/132 KV100 MVA ICT 2, 4) R ph & B Ph CT of220/132 KV 100 MVA ICT 2, 5) 220KV Virur YPh CT, 6) 220KV R Ph CT & 33KV R Ph CT of220/33 KV 25 MVA TF 2
Yes Yes Oil leakage attended
10)TBC Breaker Compressor problem Yes Yes Problem attended
11)100MVA ICT-2Cooling fans not working in auto mode.
Yes YesE-tender for repairs of T/Fcooling fan is underprocess.
12)ABT Meter not present for 33KV Kotgal-MIDC & 33KV Vyahad feeder
Yes NoAvailable meters are of 110V DC so required voltageconversion card
16220KV Gadchiroli
S/Stn220KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
1)220/66KV ICT (Make :- NGEF): Coolingcontrol cabinet of this T/F is very old anddue to percolation of leakage oil from ICTtank, most of the contactors are not working,also part of the above terminal connectorsswitches are damaged.Out of 14 nos of cooling fans, 11 nos are inworking condition.
Yes NoE-tender for repairs of T/Fcooling fan is underprocess.
2)220/66KV ICT (Make :- NGEF):Tap changerposition :- Tap changer mechanism rod issealed by Mseal for arresting oil leakage,hence tap cannot be changed. Current tapposition is tap no 8 and normal tap positionis at tap no 9.
Yes No
Total O/H of Tap changerunit is required as during
the inspection ondt.06.02.2016 it is observedthat the tap changer unit is
completely wet withleakage of oil from the top.
Requires replacement.
3) 220/66KV ICT (Make :- NGEF): There are02 nos of oil pump in working condition butAC supply arrangement is not proper
Yes No
Oil pump Sr.No. 15875-DN255/4 is kept
disconneced from ACsupply which needs to beinvestigated thorougly.
4) 220/66KV ICT (Make :- NGEF): Oil levelgauge is not working presently.
Yes No
As per inspection ondt.06.02.2016, the oil levelshows'0' reading is seems
to be faulty, requiresreplacement.
220KV GadchandurS/Stn
220KV17
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
5)220/66KV ICT(Make:- EMCO)Cooling control fan:- Out of 24 nos of fansonly 09 nos are in working condition. Forremaining 15 fans either contactor or fansare to be checked.
Yes NoE-tender for repairs of T/Fcooling fan is underprocess.
6)220/66KV ICT(Make:- EMCO): Oil levelgauge:- Not working.
Yes No
The oil gauge just showingfaulty deviation of the
pointer which is incorrect.The gauge is to be
replaced.
7)220/33KV, 25MVA T/F(Make:- EMCO)AC supply MCB's and its connectors aredamaged, hence supply cannot be extend.
Yes NoTransformer is dismantledon dt. 15.01.2016 againstaugmentation scheme.
8) Detailed and latest earth results should besubmitted along with the confirmation ofICT / Transformer neutral earthingconnecting with S/stn earth grid
Yes YesEarth results taken on dtd13.06.2015
9)Vermin proofing needs to be improved. Yes YesOnly CP/RP cleaned byULTB method
10) Earth leakage to be attended.+ve to E = 152.9 ; -ve to E = 83.6
Yes NoEarth leakage meter is
required with concerneddevice.
1) 220V Battery Bank efficiency :- 50%48V Battery Bank efficiency :- <50%Needs replacement/ recondition(Date of C/D Cycle:- 04.04.2012)
Yes Yes
As per the CD cycle carriedout on dated 08.02.2015 1)220V Battery Bankefficiency :- 80% 2)48VBattery Bank efficiency :-75% .
2)TSS-1 & TSS-2 remote closing problem Yes YesReplaced by new one ondated 04.11.15 & 07.11.15.
220KV220KV Gadchandur
S/Stn17
18220KV Warora
S/Stn220KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
3) Grass cutting is required. Yes YesDone by Agency on dt.25.12.2015.
4)Oil leakage of following equipments to beattended1)220/66KV, 50MVA PTR-1,2,3,42)33KV Shegaon feeder B Ph CT
Yes YES
Till minor oil leakages fromPTR-1 & 2 33kV ShegoanCT has been replaced on22.05.15.
5)Earth resistance value to be confirmed. Yes Yes Confirmed.Value in order.
6)220/66KV PTR-1, 2,3 &4Cooling fans not working in auto mode.
Yes YesPTR-3 & 4 cooling fans areworking in AUTO Mode.
7)Post Monsoon LCM not carried out. Yes YesPost Monsoon LCM taken23.01.2016.
8) 220/66KV, 50MVA PTR-2 LV ABT meterproblem
Yes YESReplaced on dated05.04.2015.
1) Oil leakage of following equipments to beattended1)220KV TSS-2 R & Y Ph CT2)220/132KV, 100MVA ICT-I & II3) 132/33KV, 25 MVA TF- I & II
Yes
Yes (except132/33KV,
25 MVA TF-I)
Pending
2)Last C/D Cycle carried out on 12.04.2012 Yes YesCD cycle carried out ondt.14.03.2015
3) Grass cutting is required. Yes Yes Under process.4) Earth leakage ammeter on charger isfaulty
Yes Yes Attended
5) Vermin proofing needs to be improved Yes YesDone by agency on dt.02.12.2015
6) 220/33KV, 100MVA ICT-1 & 2132/33KV 25 MVA T/F-1 & 2Cooling fans not working in auto mode.
Yes No Contactor Faulty.E-tender for repairs of T/Fcooling fan is underprocess.
7) Earth resistance value to be confirmed. Yes Yes Attended
18
220KV220KV Virur S/Stn19
220KV220KV Warora
S/Stn
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
8) Metal spreading required. Yes NoRequirement sent to CivilDivision vide ltr. no. 1866Dt. 07.08.2013.
9)Post Monsoon LCM not carried out. Yes Yes Attended
10)Earth leakage to be attended. Yes NoEarth leakage Kit is notavailable. Requirementsent
1) 48V Battery bank:Cell no 18 specificgravity to be confirmed
Yes YesDone & results are withinlimit.
2)110V Battery bank Cell no 42 specificgravity to be confirmed
Yes YesDone & results are withinlimit.
3)132/33KV, 50MVA, T/F-2: Oil leakageobserved in turret CT
Yes NoTender under process atcircle level
4)132/33KV, 50MVA, T/F-3: OTI meter faulty Yes Yes Attended
5)Vermin proofing needs to be improved Yes Yes Attended
6)Earth resistance value to be confirmed. Yes YesAttended & results arewithin limit.
7) 132KV UppalwadiR-Ph -191µΩY-Ph – 131 µΩB-ph -120 µΩ CRM value to be confirmed
Yes YesCRM result taken on dt.27.01.2016.R=212,Y=135,B=235
8) 25MVA, 132/11KV T/F-3 (EMCO)132KV B-PHIr = 233 microA It = 1112 microAIR values of LA stack needs to be confirmed
Yes Yes Ir=117,It=522
9)132KV Uppalwadi132KV B-PHIr = 261 microA It = 80 microAIR values of LA stack needs to be confirmed
Yes Yes Ir=118,It=467
19 220KV Virur S/Stn 220KV
20 132 KV Pardi S/Stn 132 KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
1)48V battery bank Efficiency 67%. Needs tobe replaced
Yes Yes
Efficiency wronglymentioned by M/SDevshree, Nagpur. 02 nos.of negative cells replacedby new cells. Now Efficencyincrease from 20% to 50%.
2)Vermin proofing needs to be improved Yes YesDone as ULTB workscarried out.
3)Oil leakage 25 MVA, 132/11KV T/F-I to beattended.
Yes NoTender under process atcircle level
4)Earth resistance value to be confirmed. Yes Yes Within Limit
5) 132/33KV 50MVA T/F-I (CGL)R-Ph -195Y-Ph – 195B-ph -96 Repeat the CRM
Yes Yes
5) 132/33KV 50MVA T/F-I(CGL)R-Ph -76.1Y-Ph – 73.4B-ph -64.2
6) 33KV VinkarR-Ph - 115Y-Ph – 111B-ph -110.3 Repeat the CRM
Yes Yes
6) 33KV VinkarR-Ph - 85Y-Ph – 79B-ph -55
7) 33KV KSL-I (CGL)R-Ph -191.8Y-Ph – 139.3B-ph -164.7 Repeat the CRM
Yes Yes
7) 33KV KSL-I (CGL)R-Ph -83Y-Ph – 94B-ph -89
8) 33KV VinkarR-Ph -62Y-Ph – 61B-ph -62 Repeat the timing
Yes Yes
8) 33KV VinkarR-Ph -67Y-Ph – 65B-ph -68 Megawin breakerhas the tripping time morethan 60 ms.
132 KVBesa S/Stn21 132 KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
9)33KV AanandanR-Ph -64Y-Ph – 64B-ph -64 Repeat the timing
Yes Yes
9)33KV AanandanR-Ph -36Y-Ph – 36B-ph -36
10) 33KV KSL-II (ALSTOM)R-Ph -58Y-Ph – 58B-ph -60 Repeat the timing
Yes Yes 78
1) 48V battery bank: Efficiency notconfirmed.
Yes Yes 2%
2)25MVA 132/11KV T/F-I & II Oil leakage tobe attended
Yes Yes Attended
3) Vermin proofing needs to be improved Yes Yes Attended
4)Metal spreading in yard is required. Yes Yes Attended
5)Earth leakage to be confirmed. Yes Yes
Test done but not detectedas earth leakeage isnegligable, hence cannotshow in earth meter.
6)Earth resistance value to be confirmed. Yes Yes Within range
7)132/33KV 50MVA T/F-II (CGL)R-Ph -111.2Y-Ph – 126.2B-ph -126.8 Repeat the CRM
Yes Yes
R-Ph -126.5Y-Ph – 136.7B-ph -145.6 As it is oldbreaker hence guidancerequired.
8) 33KV NaraR-Ph -47Y-Ph – 196.8B-ph -199 Repeat the CRM
Yes YesR-Ph -52.8Y-Ph – 171.9B-ph -172.9
21 132 KV Besa S/Stn
132 KV22132KV Mankapur
S/Stn
132 KV
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone : Nagpur
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
9) 33KV MRS UGR-Ph -58Y-Ph – 57B-ph -57 Repeat the timing
Yes YesR-Ph -57Y-Ph – 57B-ph -58
10) 33KV Amravati road gorewadaR-Ph -62Y-Ph – 60B-ph -60 Repeat the timing
Yes YesR-Ph - 61Y-Ph – 65B-ph - 69
11)132KV Ambazari-I132KV R-PHIr = 264 microA It = 1095 microAY-Ph Ir = 280 microA It = 1067 microAB Ph Ir = 221 microA It = 1078 microAIr values of LA stack needs to be confirmed.
Yes Yes
Ir = 123 microA It = 544microAY-Ph Ir = 127 microA It =505 microAB Ph Ir = 120 microA It =543 microA
12) 132KV Hingna-I132KVY-Ph Ir = 183 microA It = 1025 microAB Ph Ir = 323 microA It = 1107 microAIr values of LA stack needs to be confirmed
Yes Yes
Y-Ph Ir =156 microA It =1017 microAB Ph Ir = 104 microA It =651 microA
13) 132KV Uppalwadi-IY-Ph Ir = 225 microA It = 1103 microAB Ph Ir = 155 microA It = 963 microAIr values of LA stack needs to be confirmed
Yes Yes
Y-Ph Ir = 196 microA It =1103 microAB Ph Ir = 137 microA It =948 microA
132KV MankapurS/Stn
132 KV22
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
1 BABHALESHWAR 400Zone 1 seeting of 400kV & 220kV lnes areset to 90% instead of 80% which needs to berevised to 80%.
NA NA NA NA NA NATo be carried out byexternal agency
2 DHULE 400 Found in order NA 26.12.2014
3 KHADAKA 400 Found in order NA NA NA NA NA NA 26.12.2014
4 DEEPNAGAR 400 Found in order NA NA NA NA NA NA 26.12.2014
5 MALEGAON 220 Found in order NA NA NA NA NA NA 22.09.2014
6 NASHIK GCR 220 Found in order NA NA NA NA NA NA 30.07.2014
7 NASHIK OCR 220 Found in order NA NA NA NA NA NA 30.07.2014
8 BABHALESHWAR 220 Found in order NA NA NA NA NA NA 20.12.2014
9 DHULE 220 Found in order NA NA NA NA NA NA 26.12.2014
10 CHALISGAON 220 Found in order NA NA NA NA NA NA 26.12.2014
11 DEEPNAGAR GCR 132 Found in order NA NA NA NA NA NA 22.11.2014
12 DEEPNAGAR ECR 132 Found in order NA NA NA NA NA NA 22.11.2014
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone:Nasik
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
1 400kV Lonikand II 400kVForcebly ON/OFF command bypassinginterlocks of isolator through Areva MakeSCADA
Yes Yes.For isolators forceblyON/OFF commands
disable through SCADA
2 220kV Talegaon 220kV1) Zone 1 seeting of 400kV & 220kV lnesare set to 90% instead of 80% which needsto be revised to 80%.
YES Yes.
Siemens make distanceprotection relay suaitablefor short distance line is
provided.
3 220kV Bhosari I 220kV
For selective tripping of TBC CTs to beprovided for TBC bay. After commissioningof 220KV Bussectionalizer (ABB make PASS)modification of configuration and wiring inbusbar is required,
Yes No Jun-16For Bus Barconfiguration,matter istaken with M/S NR.
4 132kV Kharadi 132kV132kv Markal Line Backup relay is Statictype needs to be replaced. TC1 & TC2 relayare faulty, Trip Coil 2 is fault
YES Mar-16 Work is in progress
5132kV
Ganeshkhind132kV
Display of 132KV Chinchwad bay Distancerelay Make-GE is faulty.
Yes No Mar-16Matter is taken with M/SGE by O&M authority.
1) 132kV Ujani line Distance relay foundfaulty and replaced.
Yes Yes
2) 132kV Akkalkot Line problem in N/Tswitch wiring.
Yes Yes
7220kV South
solapur220kV
1) BCU and BU were clubbed and thereforeAREVA make MICOM C264 firmwareupgradation required.
Yes Yes
6 220kV Bale 220kV
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone:Pune
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
1) Zone 1 seeting of 400kV & 220kV lnes areset to 90% instead of 80% which needs to berevised to 80%.
Yes YesCarried out on 27.05.15 &completed.
2) Zone 3 setting of 400kV Kalwa line is tobe revised as per guidelines.
Yes YesCarried out on 27.05.15 &completed.
3) Reverse Zone (Zone 4) time delay settingfor 400kV & 220kV lines are to be revised tozone 3 time delay (700 msec)
Yes YesCarried out on 27.05.15 &completed.
4) PSB blocking for all zones (Z1, Z2 & Z3) &unblock time delay for 400kV lines are to berevised to 2 sec.
Yes YesCarried out on 27.05.15 &completed.
5) 315MVA, 400/220kV ICT - 1 & 2 HV & LVBack up relay setting are to be revised as perguidelines.
Yes YesCarried out on 27.05.15 &completed.
6) For 315MVA, 400/220kV ICT-2, thetransformer trip protections are not groupedas per guidelines 9i.e. Group-A & Group-B),which needs to be modified.
Yes NoWill be completed by30.04.2016
7) For 80MVR, Reactor, the protections arenot grouped as per guidelines, which needsto be modified.
Yes NoWill be completed by30.04.2016
8) DRs of 315MVA 400/220kV ICT -1 & 2 areto be reconfigured as per guidelines.
Yes NoWork in progress & Will becompleted by 30.04.2016
9) Zone 2 & 3 setting of all 220kV lines is tobe revised as per guidelines.
Yes YesCarried out on 27.05.2015& Completed.
10) 400kV & 220kV lines parameters settingare to be verified with remote end s/s.
Yes YesCarried out on 27.05.2015& Completed.
400/220kVKharghar
1 400KV
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
11) On line direction of B/U EF relays for all220kV lines are to be confirmed.
Yes YesConfirmed on 20.10.2015& completed.
12) 50MVA, 220/33kV TF-1 TF auxiliarlyprotection relay (30GHI) is found to befaulty, which needs replacement.
Yes No
Relay received afterrepairing, same will befixed during outage___ by30.04.2016
13) For 220kV lines & 50MVA TFs, CB status& TF auxiliary BI are not taken for DR, whichneeds to be wired up.
Yes NoWork in progress & Will becompleted by 30.04.2016
1) Zone3 setting of 400kV lines are to berevised as per guidelines.
Yes Yes
2) Reverse Zone (Zone 4) feature is notavailable in 400kV Padghe-1 &2 andKharghar for both Main1 & 2 (7SA513)
Yes No
3) As per guidelines, DR signals could not beconfigured as the relays are of old version,needs to be replacement.
Yes No
1) VT fuse failure time delay for 220kV linesis set 3 sec which needs to be revised to 5sec.
Yes Yes
2) On line direction of B/U EF relays for all220kV lines are to be confirmed.
Yes Yes
3) Zone 2 setting of 220kV Taloja line is tobe revised as per guidelines.
Yes Yes
4) Zone 2 setting & time coordination for220kV Apta -Kalwa line is to revised incoordination with EE testing, panvel.
Yes Yes
The scheme for replacmentof all CP & RP by BCPPpanel is sent to CO forapproval on Jan 16
3 220/100KV Kalwa 220KV
2 400/220kV Kalwa 400KV
1400/220kVKharghar
400KV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
1) Zone 1 setting of 220kV Kalwa/Tambati/Bombay dying lines are set to 90%instead of 80% which needs to be revised to80%.
Yes Yes
2) Zone 2 & 3 setting of 220kV Kalwa line isto be revised considering the new 220kVAKP & Bapgaon line length.
Yes Yes
3) Zone 2 setting of 220kV ACCIL line is tobe revised.
Yes Yes
4) Reverse Zone (Zone 4) time delay settingfor all 220kV lines are to be revised to zone3 time delay (700 msec)
Yes Yes
5) PSB blocking for all zones (Z1, Z2 & Z3) &unblock time delay for all 220kV lines are tobe revised to 2 sec.
Yes Yes
6) Back up relay setting for all 220kV linesare to be revised considering ROT of500msec.
Yes Yes
7) On line direction of B/U EF relays for all220kV lines are to be confirmed.
Yes YES
8) The 220kV HOC line Pilot wire protection,HORM4 is not in service, which needsreplacement.
Yes No
Tender for Supply, Errection &commissioning of Numericalline differential protectionrelay & ADSS cable requiredfor communuication ispublished by Zone office butdue to poor response, againtender is being floatedseparately by zone office.
9) Zone 1 setting of 100kV Patalganga line isto be revised to 80%.
Yes Yes
4 220kV Apta 220kV
4 220kV Apta 220kV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
10) Zone 2 & 3 setting of all 100kV lines areto be revised as per guidelines.
Yes Yes
11) Reverse Zone (Zone 4) time delay settingfor all 100kV lines are to be revised to zone3 time delay (700 msec)
Yes Yes
12) PSB feature of all 100kV lines are to bedisable.
Yes Yes
13) On line direction of B/U EF relays for all100kV lines are to be confirmed.
Yes Yes
14) Back up relay setting for all 100kV linesare to be revised considering ROT of500msec.
Yes Yes
15) Zone 2 setting & time coordination for220kV Apta -Kalwa line is to revised incoordination with EE testing, Kalwa.
Yes YesRevised consideringMulund as a shortest line
1) Zone 2 setting of 220kV Tarapur lines areto be revised by considering 120% ofprotected line.
Yes Yes
2) Zone -2 time of 220kV Kalwa line is to becordinated with 220kV Kalwa - AKP line.
Yes Yes
3) Reverse Zone (Zone 4) time delay settingfor all 220kV lines are to be revised to zone3 time delay (700 msec)
Yes Yes
4) 200MVA, 220/100MVA ICT-1 HV & LVBackup relay settings are to be revised asper guidelines.
Yes Yes
2) Zone 2 setting of 220kV HOC, Apta- 2, 3&4 lines are to be revised as per guidelines.
Yes Yes
4 220kV Apta 220kV
5 220kV Borivali 220KV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
3) Zone 3 setting of 220kV HOC is to berevised as per guidelines.
Yes Yes
4) Zone 4 setting for 220kV HOC, Apta 2, 3& 4 lines are to be revised as per guidelines(2 kM)
Yes Yes
5) Reverse Zone time delay setting for all220kV lines are to be revised to zone 3 timedelay (700 msec)
Yes Yes
6) VT fuse fail setting for 220kV Apta 3, 4 &Kharghar 1, 2 and JNPT are to be revised asper guidelnes (80mA & 40mA respectively)
Yes Yes
7) 220kV lines parameters setting are to beverified with remote end s/s and respectiveline s/Dn. For 220kV Apta 2, 3 & 4.
Yes Yes
8) For 220kV Uran - HOC line PUR scheme isnot in service, which needs to be taken intoservice.
Yes Yes
9) PSB blocking for all zones (Z1, Z2 & Z3) &unblock time delay for all 220kV lines are tobe revised to 2 sec.
Yes Yes
10) The B/U relay OC setting for 220kV Apta3, Kharghar 2 lines are to be revised as perguidelines.
Yes Yes
11) The B/U relay for all 220kV lines are tobe revised considering ROT 500msec.
Yes Yes
12) On line direction of B/U EF relays for all220kV lines are to be confirmed.
Yes Yes
13) DR of all 220kV Lines & TFs are to be setto trigger for any start/trip signals.
Yes Yes
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
14) For DR triggering the BI for TF are to beconfigured for transformer aux. protection.
Yes Yes
1) Zone 2 & 3 setting for 220kV Mulund,Kharghar & Sonkhar lines are to be revisedas per guidelines.
Yes Yes
2) Resitive reach for ground fault is not setfor all 220kV lines, which needs to be set asper guidelines.
Yes Yes
3) Reverse Zone time delay setting for all220kV lines are to be revised to zone 3 timedelay (700 msec)
Yes Yes
4) The Auto reclose for all 220kV lines arenot in service, it is suggested to take A/R inservice.
Yes No
The DPR SEL421 relayconfiguration issue for ARscheme. ER support for thesame not available Followupwith ER is on to take the ARscheme in service. __ by June-2016
5) PSB unblock time delay for all 220kV linesare to be revised to 2 sec.
Yes Yes
6) TF Protections are to be grouped Group-A& B as per guidelines.
Yes Yes
7) HV B/U of 200MVA 220/100kV ICT 1 & 2are non directional, which needs to be madedirectional.
Yes Yes
8) DR of all 220kV Lines & ICTs are to be setto trigger for any start/trip signals.
Yes Yes
1) Zone 2 setting for 220kV Pirngute, Bhira,Koyana, Sonaallid & ONGC lines are to berevised as per guidelines.
Yes Yes
7 220kVTrombay 220kV
Settings are revised
8 220kV Kandalgaon 220 kV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
2) Reverse Zone time delay setting for all220kV lines are to be revised to zone 3 timedelay (700 msec)
Yes Yes
3) AR dead time for all 220kV lines are set to0.8 sec instead of 1 sec, which needs to berevised.
Yes NoProposal underprocess__09.08.2016.
4) PSB unblock time delay for all 220kV linesare to be revised to 2 sec. Also after unblocktime is over, PSB trip should be activated.
Yes Yes
5) On line direction of B/U EF relays for all220kV lines are to be confirmed.
Yes Yes
6) The 100KV lines B/U OC setting is to berevised as per guidelines.
Yes Yes
8) HV B/U of 100MVA 220/100kV ICT 2 &50MVA 220/100kV ICT 1 are non directional,which needs to be made directional.
Yes Yes
1) The 220V DC source 1 & 2 for 400kV lines& ICTs are to be confirmed for Group -A & Bseparately.
Yes YesDC sources seperationwork completed inDecember 2015
2) For 400kV lines Zone Zp is to be madereverse & accordingly reverse zone reach &time are to be set as per guidelines.
Yes Yes
3) For all 400kV lines Main-1 protection ,SOTF function is disable, which needs to bemade enable.
Yes Yes
4) For 400kV Dabhole 2, overvoltage setting& time delay are to be revised as perguidelines.
Yes Yes
400/220kVNagothane
9
9400/220kVNagothane
400KV
400KV
8 220kV Kandalgaon 220 kV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
5) For 400kV Padghe 1 & 2 and Dhabole 1,PSB unbloced time is to be revised to 2 sec.For 400kV dabhole 2, all zones are to beblocked with unblock time to 2 sec.
Yes Yes
6) 315MVA, 400/220kV ICT 1 & 2 and500MVA 400/220kV ICT 3, cooler controlsystem is in manual mode to be taken intoauto mode.
Yes NoWork is inprogress__29.02.2016.
7) DR of all 400 & 220kV Lines & ICT/TFs areto be set to trigger for any start/trip signals.
Yes Yes
8) DT send digital channel is to beconfigured for DR.
Yes Yes
9) CB contact in LBB circuit for 400 & 220kVlines are to be bypassed.
Yes Yes
10) For 220kV lines, zone3 time delaysettings are to be revised as guidelines.
Yes Yes
11) For 220kV ACCIL & POSCO lineSOTF/TOR to be made enabled. All 220kVLines SOTF delays is to be revised 1 sec.
Yes Yes
12) For all 220kV lines AR is set to 1ph + 3phtrip which is to be revised to 1 ph.
Yes Yes
13) PSB unblock time delay for all 220kVlines are to be revised to 2 sec.
Yes Yes
14) The 220KV lines B/U OC setting is to berevised as per guidelines.
Yes Yes
15) On line direction of B/U EF relays for all220kV lines are to be confirmed.
Yes Yes
400/220kVNagothane
9 400KV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
1) Zone 1 setting for all 400kV & 220kV linesare tb revised to 80% intead of 90%presenet adopted.
Yes Yes
2) Zone 2 & 3 setting for 400kV Kalwa 1 &2and Zone 3 setting for 400kV Boisar, Tarapur1 & 2 lines are to be revised as perguidelines respectively.
Yes Yes
3) For relay setting calculation of 400kVboisar line, the longest line length fromBoisar(PGCIL) s/s is considered 94kM forcalculation purpoase. However aftertelephonic discussion with PGCIL engineer,the line length is 102kM, sme may beconfirmed & accordingly setting can bechanged.
Yes Yes
4) For all 400kV lines, the SOTF feature isenabled for Z1 & Z2 fault impedance only. Itis suggested to modify the setting for allzones i.e. Z1, Z2 & z3 fault impedance.
Yes Yes
5) It is observed that in MICOM P442numerical distance protection relay , Autoreclose mode is kept 1/3 i.e. single/threephase mode. It is suggested to changed theAR mode to 1 i.e. single phase wherever it ispossible.
Yes Yes
10 400/220kV Padghe400
/ 220kV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
6) For verification of correctness ofResistative reach setting for ground & phasefault, data of remote end TF capacity & %impedance considered, however for one ofthe s/s it is not matching with present Tfcapacity. It is suggested to verify the datafrom remote end and modify the settingaccordingly.
Yes Yes
7) Reverse Zone time delay setting for all400kV & 220kV lines are to be revised tozone 3 time delay (500 &700 msecrespectively)
Yes Yes
8) B/U HV & LV realy of 400kV ICT 1 , 2, 3 &4 ROT is kept 650msec, the ROT of these b/urelays are to be revised to 500msec as perguidelines.
Yes Yes
9) 400kV ICT-4 the RTCC panel is notprovided, which needs to be purchased/provided and commissioned immediately.
Yes No Scheme is being prepared
10) The local / remote operation of OLTC of400kV ICT 1, 2 & 3 are not checked as panelsare old. It is suggested to checked & if notoperative, necessary overhauling orreplacement is to be done.
Yes Yes
11) WTI / OTI reading of all 400kV ICTs arenot matching with the meter provided atRTCC, same may be checked & correced.
Yes Yes
400/ 220kV
400/220kV Padghe10
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
12) The 400kV Bus & line reactor areprovided with all static relay exceptimpedance relay, thes relays needs to bereplaced by state of art numerical relays.
Yes NoRequirement is submittedat CO
13) The differential relay RET670 ABB makeof 400kV ICT 2 is having diplay problem assuch HIM of relay is not showing any data, itis suggested to replaced the said relay byspare one and the relay for repair at M/s ABBworks.
Yes Yes
14) The Main -2 distance protection of400kV Kalwa 1 REL 670 relay is havingdisplay problem & needs replacement. Thespare relay is available at site, hence it issuggested to retrofit/replace the main 2faulty relay immediately.
Yes Yes
15) Zone 2 & 3 setting for 220kV Nashik 2and for 220kV Nalasopara line, Zone 2 & 3setting is to be revised to 120% & 200% ofline length as it is redial feeding s/s. Thesettings are revised accordingly.
Yes Yes
16) The 220kV lines B/U relay, the EF Plugsetting is to be revised to 30% as perguidelines.
Yes Yes
17) The 220kV lines B/U relay setting ROT isto be revised to 500msec as per guidelines.
Yes Yes
10 400/220kV Padghe400
/ 220kV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
18) The 220kV ICT B/U HV & LV relay settingis to be revised considering the ROT500msec & 400msec respectively.
Yes Yes
19) The HV & LV bB/U relay setting for50MVA, 220/22kV TF 1 & 2 are to be revisedconsidering the ROT 500msec & 350msec asper guidelines.
Yes Yes
20) On line direction of B/U EF relays for all220kV lines are to be confirmed.
Yes Yes
21) The B/U relays of 440kV & 220kV ICTsare old electromechnical/static, which needsto be replaced by numerical relays.
Yes Yes
22) The local/remote operation of OLTC of220kV ICT 2, 3 & 4 and 50MVA TF 1 & 2 arenot checked. It is suggested to checked & ifnot operative, necessary overhauling orreplacement is to be done.
Yes Yes
23) The ABB make SMS is not working.Further M/s ABB is also not responding evenafter continous follow up by concerned, theissue must be taken up at CO & bring theSMS scheme in service.
Yes Yes
24) The GPS of SMS system is not working,as such relays are not synchronised with GPSand time stamped DR is not available. It issuggested to take up the issue with supplier& bring the GPS system in service.
Yes Yes
400/ 220kV
400/220kV Padghe10
10 400/220kV Padghe400
/ 220kV
1 2 3 4 5 6 7 8 9 10 11
Yes/No
WhetherattendedYes/No
If notattended,
reason
Yes/No
WhetherattendedYes/No
If no, expecteddate to attend
Present Status of Protection Audit Deficiencies (A & B type) in MSETCL for the year 2014-15 as on 31/07/2016
Name of Zone: Vashi
Sr.No.
Name of S/sidentified for
Protection Audit
S/svoltage
(kV)Observations of protection Audit
Deficiencies that can becorrected without
procurement (Category-A)
Deficiencies involvingprocurement (Category-B)
Present Status as on31/07/2016
25) The LBB relays for 440kV & 220kVlines/ICT/TF are not provided with separateDC circuit independent from Gr. A & Gr. Bexcept 400kV Tarapur 1 & 2 and Talegaon.The necessary modification is to be done inthis respect.
Yes Yes
400/ 220kV
400/220kV Padghe10
No. of Defectsin Category A
AttendedYes/NO
Reason fornotattended
No. of Defectsin Category A
AttendedYes/NO
Reason fornotattended
1 132KV Barwala 132 22/6/122 132KV Paliyad 132 19-20/6/123 220KV Dhasa 220 07/12/20124 220 KV Botad 220 17/7/20125 132KV Vallabhipur 132 21/6/126 220KV Otha 220 07/05/20127 220KV Savarkundla 220 16/7/20128 220KV Sagapara 220 07/06/20129 220KV Vartej 220 07/10/2012
10 220KV Anjar 220 22/11/201311 132 KV Samakhiyali 132 23/05/201212 220KV Shivlakha 220 26/12/201313 220 KV Kukma 220 25/12/201314 220KV Nakhatrana 220 20/12/201315 220KV Nanikhakhar 220 27/12/201316 220KV Tappar 220 23/12/201317 132KV Ankleshwar 132 24/9/1218 132KV Valia 132 23/8/1219 220KV Acchalia 220 29/9/1220 220 KV Wagra 220 09/06/201221 220KV Dahej 220 20/9/1222 220KV Kim 220 09/05/201223 220KV Zagadia 220 22/9/1224 220KV Haldarwa 220 09/07/201225 132KV Bharuch 132 18/9/1226 132KV Wankaner 132 14/02/201427 220KV Lalpar 132 02/07/201428 132KV Jasdan 132 15/02/201429 132KV Dhrol 132 02/04/201430 220KV Gondal 220 22/02/201431 132KV Vajdi 132 03/05/201432 220KV Nyara 220 26/02/201433 132KV Vikram 132 02/07/201434 220KV Morbi 220 02/05/2014
Format for Protection AuditName of Utility: Gujarat Energy Transmission Corporation Ltd.
Sr.No.
Name of CircleName of the Substationidentified for audit
S/SVoltage
(KV)
Date on which auditconducted/completed
Observations ofProtection Audit
Remark(Defect)
Deficiences that involves procurment(Category B)
Amreli
Circle/ substaionwise
observation reportenclosed herewith.
NA
No. of Defects:-77Attended(nos.):-77Pending(nos.):- 0
Anjar
Circle/ substaionwise
observation reportenclosed herewith.
NA
No. of Defects:-97Attended(nos.):-97Pending(nos.):- 0
Nil NA
NANil9797
Bharuch
Circle/ substaionwise
observation reportenclosed herewith.
NA
No. of Defects:-78Attended(nos.):-78Pending(nos.):- 0
Gondal
Circle/ substaionwise
observation reportenclosed herewith.
NA
No. of Defects:-35Attended(nos.):-35Pending(nos.):- 0
NANil
NANil7878
Deficiences that can becorrected without procurment
(Category A)
77 77
35 35
No. of Defectsin Category A
AttendedYes/NO
Reason fornotattended
No. of Defectsin Category A
AttendedYes/NO
Reason fornotattended
Sr.No.
Name of CircleName of the Substationidentified for audit
S/SVoltage
(KV)
Date on which auditconducted/completed
Observations ofProtection Audit
Remark(Defect)
Deficiences that involves procurment(Category B)
Deficiences that can becorrected without procurment
(Category A)
35 132KV Idar 132 19/6/1236 132KV Visanagar 132 20/6/12
06/10/201206/10/2012
39 220KV Bhutiya 220 27/6/1240 220KV Jamla 220 30/6/1241 220KV Vijapur 220 22/6/1242 220KV Dhansura 220 07/04/201243 132KV Talod 132 23/6/1243 132 KV Tilakwada 132 30/4/1344 132 KV Vasedi 132 05/03/201345 220KV Godhra 220 22/5/1346 132KV Dahod 132 05/07/201347 220KV Jambuva 220 24/05/201348 220KV Chandrapura 220 24/5/1349 220KV Gavasad 220 25-6-201350 132KV Gotri 132 07/02/201351 220KV Waghodia 220 30/6/201352 132KV J' Nagar 132 31-6-201353 132KV F"Nagar 132 06/11/201354 132KV Karjan 132 07/03/201355 132KV Manjusar 132 30-6-201356 132 KV Limkheda 132 06/02/201357 132KV Nandesari 132 07/04/201357 220KV Ranavav 220 20/02/201458 132KV Bhatia 132 21/02/201459 220KV Jamnagar 220 14/02/201460 132KV Khambhalia 132 14/02/201461 132KV Naghedi 132 14/02/2014
38 220KV Agiyol 220
No. of Defects:-28Attended(nos.):-28Pending(nos.):- 0
28 28 Nil
Himmatnagar
Circle/ substaionwise
observation reportenclosed herewith.
NA
No. of Defects:-93Attended(nos.):-93Pending(nos.):- 0
Jambuva
Circle/ substaionwise
observation reportenclosed herewith.
NA
No. of Defects:-125Attended(nos.):-125
Pending(nos.):-
Jamnagar
Circle/ substaionwise
observation reportenclosed herewith.
NA
93 93
NA
Nil NA
125 125 Nil NA
No. of Defectsin Category A
AttendedYes/NO
Reason fornotattended
No. of Defectsin Category A
AttendedYes/NO
Reason fornotattended
Sr.No.
Name of CircleName of the Substationidentified for audit
S/SVoltage
(KV)
Date on which auditconducted/completed
Observations ofProtection Audit
Remark(Defect)
Deficiences that involves procurment(Category B)
Deficiences that can becorrected without procurment
(Category A)
62 132 KV Bhayavadar 132 18/8/1263 132KV Junagadh 132 09/07/201264 220KV Keshod 220 09/08/201265 132 KV Dhoraji 132 22/8/1266 220KV Motipaneli 220 24/08/201267 220KV Sardargadh 220 09/07/201268 220KV Visavadar 220 25/6/1269 132KV Haripur 132 26/6/1270 132KV Talala 132 27/6/1271 220KV Timbdi 220 07/02/201272 220 KV Kansari(Dhokalva) 220 07/04/201273 132 KV Patan 132 12/02/201374 132 KV Siddhpur 132 27/11/201375 220KV Kheralu 220 26/12/201376 220KV Sankhari 220 29/11/201377 220KV Chhatral 220 21/11/201378 220KV Mehsana 220 21/12/201379 220KV Mitha 220 12/10/201380 132 KV Sabarmati 132 05/12/201281 220KV Salejada 220 30/5/1282 132KV Ode 132 30/4/1283 132KV Undel 132 20/05/1284 220KV Kapadwanj 220 06/09/201285 220 KV Bhat 220 31/05/1286 132KV Narol 132 22/05/1287 132KV Chiloda 132 24/7/12
90 132KV Mahemdabad 13219/05/12,15/7/2012
91 220KV Khanpur 220 19/7/1292 132KV Nadiad 132 18/05/12
88 220KV Karamsad 220 29/4/12
89 220KV Ranasan 220
Junagadh
Circle/ substaionwise
observation reportenclosed herewith.
Mehsana
Circle/ substaionwise
observation reportenclosed herewith.
Nadiad
17/05/12
Circle/ substaionwise
observationreport
enclosed herewith.
NA
No. of Defects:-266Attended(nos.):-266
Pending(nos.):-0
NA
No. of Defects:-89Attended(nos.):-89Pending(nos.):- 0
NANo. of Defects:-41Attended(nos.):-41Pending(nos.):- 0
89 89 Nil NA
41 41 Nil NA
266 266 Nil NA
No. of Defectsin Category A
AttendedYes/NO
Reason fornotattended
No. of Defectsin Category A
AttendedYes/NO
Reason fornotattended
Sr.No.
Name of CircleName of the Substationidentified for audit
S/SVoltage
(KV)
Date on which auditconducted/completed
Observations ofProtection Audit
Remark(Defect)
Deficiences that involves procurment(Category B)
Deficiences that can becorrected without procurment
(Category A)
93 220KV Bhilad 22094 220KV Talangpore 220 08/06/201395 220KV Ambheta 220 25/5/1396 132KV Atul 132 16/05/1297 132 KV Bhestan 132 06/10/201398 220KV Ichhapore 220 06/07/201399 220KV Mota 220 05/11/2013
100 220KV Navasari 220 22/5/13101 220KV Vapi 220 09/02/2013102 220KV VAV 220 05/09/2013103 220 KV Thavar 220 09/05/2012104 220KV Tharad 220 09/01/2012105 132 KV Deesa 132 09/06/2012106 220KV Deodar 220 09/11/2012107 220KV Jangral 220 25/8/12108 220KV Palanpur 220 22/8/12109 220KV Radhanpur 220 14/9/12110 220KV Agarthala 220 29/8/12111 132KV Dhandhuka 132 29/1/2013112 132KV Sitagadh 132 30/1/2013113 132KV DHANKDHRA 132 23/1/2013114 220KV Halvad 220 25/1/2013115 220KV Limbdi 220 31/1/2013116 220KV Viragam 220 28/02/2013117 220 KV DUDHREJ 220 02/02/2013118 220 KV RAJPAR 220 02/05/2013119 220 KV BALA 220 02/06/2013120 220 KV ADALSAR 220 23/01/2013121 220 KV DHANKI 220 03/05/2013
No. of Defects:-120Attended(nos.):-120
Pending(nos.):-0
Navsari
Circle/ substaionwise
observation reportenclosed herewith.
NA
No. of Defects:-90Attended(nos.):-90Pending(nos.):- 0
Palanpur
Circle/ substaionwise
observation reportenclosed herewith.
NA
No. of Defects:-52Attended(nos.):-52Pending(nos.):- 0
Surendranagar
Circle/ substaionwise
observation reportenclosed herewith.
NA120 120 Nil NA
90 90 Nil NA
52 52 Nil NA
Remarks
Yes /No
WhetherattendedYes/No
If notattended,
reason
Yes /No
WhetherattendedYes/No
If no,expected date
to attend
400 KVKhedamara
400/ 220KV
TractebelIndia,WRLDC &
CSPTCLEngineers
12 - 20 Feb'16
1. M II protection for 220 KV BRSSI&II,Raipur,Urla,Bemetara and Thelkadihfeeders are not available.2. DC leakage to be monitored
S.No.2 Yes - S.No.
1 No 31.12.2016 -
220 KVBemetara
220/ 132KV
CSPTCLEngineers 13.03.13
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.
S.No.5 Yes - Yes for S.No.
1 to 4 No 31.12.2016 -
220 KV Gurur 220/ 132KV
CSPTCLEngineers 12.03.13
1. Carrier protection is not available..2. M II protection for 220 KV feeder notavailable.3.DC leakage to be monitored.
S.No.3 Yes - Yes for S.No.
1 & 2 No 31.12.2016 -
220 KV Suhela 220/ 132KV
CSPTCLEngineers 22.03.13
1. Carrier protection is not available..2. GPS time synchronizing facility is notavailable.3. M II protection for 220 KV feeder notavailable.4. DC leakage to be monitored.
S.No.4 Yes - Yes for S.No.
1 to 3 No 31.12.2016 -
220 KVBhatapara
220/ 132KV
CSPTCLEngineers 23.03.13
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.6. LBB protection not available.
S.No.5 Yes - Yes for S.No.
1 to 6 except 5 No 31.102.2016 2nd battery setcomm.
220 KV Mopka 220/ 132KV
CSPTCLEngineers 29.03.13
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.6. LBB protection not available.7. Synchronization trolly not available.
S.No.5 Yes - Yes for S.No.
1 to 7 except 5 No 31.10.2016 -
PROTECTION AUDIT DEFFICIENCIES/OBSERVATIONS COMPLIANCE [As on 30.06.2016]Name of Utility : CHHATTISGARH POWER TRANSMISSION COMPANY LIMITED
Name of S/Sidentified for
protectionaudit
S/Svoltage
Name of 3rdparty protection
audit agency
Date on whichaudit
conductedObservations of protection audit
Deficiencies that can becorrected without procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remarks
Yes /No
WhetherattendedYes/No
If notattended,
reason
Yes /No
WhetherattendedYes/No
If no,expected date
to attend
PROTECTION AUDIT DEFFICIENCIES/OBSERVATIONS COMPLIANCE [As on 30.06.2016]Name of Utility : CHHATTISGARH POWER TRANSMISSION COMPANY LIMITED
Name of S/Sidentified for
protectionaudit
S/Svoltage
Name of 3rdparty protection
audit agency
Date on whichaudit
conductedObservations of protection audit
Deficiencies that can becorrected without procurement
(Category-A)
Deficiencies involving procurement(Category-B)
220 KV Banari 220/ 132KV
CSPTCLEngineers 29.03.13
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.6. LBB protection not available.
S.No.5 Yes - Yes for S.No.
1 to 6 except 5 No 31.12.2016 -
220 KV Siltara 220/ 132KV
CSPTCLEngineers 01.03.13
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.6. LBB protection not available.7. Synchronization trolly not available.
S.No.5 Yes - Yes for S.No.
1 to 7 except 5
NoexceptS.No. 2
31.12.2016 2nd Battery setcomm.
Remarks
Yes /No
WhetherattendedYes/No
If notattended,
reason
Yes /No
WhetherattendedYes/No
If no,expected date
to attend
PROTECTION AUDIT DEFFICIENCIES/OBSERVATIONS COMPLIANCE [As on 30.06.2016]Name of Utility : CHHATTISGARH POWER TRANSMISSION COMPANY LIMITED
Name of S/Sidentified for
protectionaudit
S/Svoltage
Name of 3rdparty protection
audit agency
Date on whichaudit
conductedObservations of protection audit
Deficiencies that can becorrected without procurement
(Category-A)
Deficiencies involving procurement(Category-B)
220 KV Doma,Raipur
220/132KV
CSPTCLEngineers 22.03.13
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.
S.No.5 Yes - Yes for S.No.
1 to 4 No 31.10.2016 -
220 KVParaswani
220/132KV
CSPTCLEngineers 29.03.13
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.
S.No.5 Yes - Yes for S.No.
1 to 5 except 5
NoexceptS.No. 2
31.12.2016 2nd Battery setcomm.
220 KV Urla 220/ 132KV
CSPTCLEngineers 23.03.13
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.6. LBB protection not available.
S.No.5 Yes - Yes for S.No.
1 to 6 except 5
NoexceptS.No. 2
31.12.2016 2nd Battery setcomm.
220 KVThelkadih
220/132KV
CSPTCLEngineers
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.
S.No.5 Yes - Yes for S.No.
1 to 4 except 2
NoexceptS.No. 2
31.10.2016 2nd Battery setcomm.
220 KVBarsoor
220/132KV
CSPTCLEngineers 07.03.13
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.6. LBB protection not available.
S.No.5 Yes - Yes for S.No.
1 to 6 except 5
NoexceptS.No. 2
31.12.2016 2nd Battery setcomm.
Remarks
Yes /No
WhetherattendedYes/No
If notattended,
reason
Yes /No
WhetherattendedYes/No
If no,expected date
to attend
PROTECTION AUDIT DEFFICIENCIES/OBSERVATIONS COMPLIANCE [As on 30.06.2016]Name of Utility : CHHATTISGARH POWER TRANSMISSION COMPANY LIMITED
Name of S/Sidentified for
protectionaudit
S/Svoltage
Name of 3rdparty protection
audit agency
Date on whichaudit
conductedObservations of protection audit
Deficiencies that can becorrected without procurement
(Category-A)
Deficiencies involving procurement(Category-B)
220 KV Bhilai 220/132KV
CSPTCLEngineers 11.03.13
1. Carrier protection is not available.2. M II protection for 220 KV feeder notavailable.3. DC leakage to be monitored.4. LBB protection not available.
S.No.3 Yes - Yes for S.No.
1 to 4 except 3 No 31.12.2016 -
220 KVKotmikala
220/ 132KV
CSPTCLEngineers 05.04.13
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.6. LBB protection not available.7. Synchronization trolly not available.
S.No.5 Yes - Yes for S.No.
1 to 7 except 5 No 31.10.2016 -
220 KVRaigarh
220/ 132KV
CSPTCLEngineers 20.03.13
1. Carrier protection is not available..2. 2nd DC battery set is not available.3. GPS time synchronizing facility is notavailable.4. M II protection for 220 KV feeder notavailable.5. DC leakage to be monitored.6. LBB protection not available.7. Synchronization trolly not available.
S.No.5 Yes - Yes for S.No.
1 to 7 except 5 No 31.12.2016 -
Remarks
Yes /No
WhetherattendedYes/No
If notattended,
reason
Yes /No
WhetherattendedYes/No
If no,expected date
to attend
PROTECTION AUDIT DEFFICIENCIES/OBSERVATIONS COMPLIANCE [As on 30.06.2016]Name of Utility : CHHATTISGARH POWER TRANSMISSION COMPANY LIMITED
Name of S/Sidentified for
protectionaudit
S/Svoltage
Name of 3rdparty protection
audit agency
Date on whichaudit
conductedObservations of protection audit
Deficiencies that can becorrected without procurement
(Category-A)
Deficiencies involving procurement(Category-B)
1. Separate two sets DC system isrecommended for switchyard protection No Yes No
Estimate andRequisition forseparate DC sourcehas been sent forapproval.
2. Carrier Protection is out of service. Yes
Yes, for 220kV KorbaEast-WestI/C No. I&II
Rest feeder'scarrier prot.ckt checked& founddefiencies
Yes NoFor carrier protectionpanel/cardsprocurementrequired.
3. Disturbance Recorder and SERs arenot available. Yes No
Tenders opened &procurement underprogress.
4. Old THR make Static DPR relaysneeds to be replaced by numericalrelays
Yes Yes Attended
5. Auto re-closer is not available. Yes NoChecking ofcircuits underprogress.
Auto reclose of 220KV Korba-Budipadarckt-3 is checked &put in service.In otherfeeders A/R ckts isOK and will be put inservice afterconfirmation fromother end.
6. Bus Bar Differential scheme is notavailable. Yes No
7. All relay settings are verified andfound to be generally in order. Yes Yes
8. Multiple Earthing is not found in CTsecondary. Yes Yes
9. PSB feature is Enabled for Z2, Z3,and Z4. Yes Yes
Name of Utility : CHHATTISGARH POWER GENERATION COMPANY LIMITED
220 KV KTPS,Korba (E) 220 KV
M.K.BanchhorCSPTCL,
N.P.DewanganNTPC, N.K.BizoraCSPGCL, G.P.Rai
CSPGCL,S.C.Chakraborty
CSPGCL
25.04.2013
Remarks
Yes /No
WhetherattendedYes/No
If notattended,
reason
Yes /No
WhetherattendedYes/No
If no,expected date
to attend
PROTECTION AUDIT DEFFICIENCIES/OBSERVATIONS COMPLIANCE [As on 30.06.2016]Name of Utility : CHHATTISGARH POWER TRANSMISSION COMPANY LIMITED
Name of S/Sidentified for
protectionaudit
S/Svoltage
Name of 3rdparty protection
audit agency
Date on whichaudit
conductedObservations of protection audit
Deficiencies that can becorrected without procurement
(Category-A)
Deficiencies involving procurement(Category-B)
10. Synchronizing Panel is available forall feeders except Budhipadar FeederNo-III for that individual SynchronizingTrolley has provided.
Yes Yes
220 KV KTPS,Korba (E) 220 KV
M.K.BanchhorCSPTCL,
N.P.DewanganNTPC, N.K.BizoraCSPGCL, G.P.Rai
CSPGCL,S.C.Chakraborty
CSPGCL
25.04.2013
Remarks
Yes /No
WhetherattendedYes/No
If notattended,
reason
Yes /No
WhetherattendedYes/No
If no,expected date
to attend
PROTECTION AUDIT DEFFICIENCIES/OBSERVATIONS COMPLIANCE [As on 30.06.2016]Name of Utility : CHHATTISGARH POWER TRANSMISSION COMPANY LIMITED
Name of S/Sidentified for
protectionaudit
S/Svoltage
Name of 3rdparty protection
audit agency
Date on whichaudit
conductedObservations of protection audit
Deficiencies that can becorrected without procurement
(Category-A)
Deficiencies involving procurement(Category-B)
1) Two independent source of 220 V DCare available in Switchyard.No DCleakage observed.
YES YES
2) All relay settings are verified & foundgenerally in order. YES YES
3)Dual channel carrier protection isavailable in all 220 KV feeders but keptout YES No
Due to nonavailability ofPanel atremote end.
4) DRs are available in Numeric relaysand SER is available. YES YES
5)Multiple earthing of CT secondarycore is not available.CT secondaryearthing is provided in Panel only.
YES YES
6) 01 no synchronising trolley isavailable & in working condition. YES YES
7)PSB feature is enabled & in blockingcondition for Z2,Z3 & Z4. YES YES
8) Auto reclose is available but presentlykept out. YES No
As carrierprotection isout.
9) Bus Bar differential scheme isavailable but presently kept out. YES No
To becheckedbefore put inservice
30.06.2016 Order placed on M/sABB forrecommissioning.
1) Un availability of Main-II protection
Yes
2) Un availability of Auto reclosescheme.
Yes
220 KVDSPMTPS,
Korba220 KV
Third PartyProtection Audit
was carried out bySE(ET&I-I)
HTPS,CSPGCL,Representative of
NTPC,EE,CSPTCL,EE(Testing),DSPMTPS,CSPGCL
25.04.2013
Korba WestTPS 400 KV NTPC & CSPTCL
Engineers 26.04.2013
Remarks
Yes /No
WhetherattendedYes/No
If notattended,
reason
Yes /No
WhetherattendedYes/No
If no,expected date
to attend
PROTECTION AUDIT DEFFICIENCIES/OBSERVATIONS COMPLIANCE [As on 30.06.2016]Name of Utility : CHHATTISGARH POWER TRANSMISSION COMPANY LIMITED
Name of S/Sidentified for
protectionaudit
S/Svoltage
Name of 3rdparty protection
audit agency
Date on whichaudit
conductedObservations of protection audit
Deficiencies that can becorrected without procurement
(Category-A)
Deficiencies involving procurement(Category-B)
3)Un availability of B/B differential &LBB protection
No Yes
New Bus Bar panelcommissioning workhas been completedand 400 KV Bus Barprotection is takeninto service from27.04.16.
4)GPS is available however no relay issynchronised with it. No Yes
5) Committee recommended to replaceABCB with SF6 breakers &commissioning of isolator sequentialoperation with ABCB opening.
No No 31.03.2017
Replacement ofABCB with SF6breakers is includedin the scope of workof R&M of stationproposed in year2016-17
Korba WestTPS 400 KV NTPC & CSPTCL
Engineers 26.04.2013
Remarks
Yes /No
WhetherattendedYes/No
If notattended,
reason
Yes /No
WhetherattendedYes/No
If no,expected date
to attend
PROTECTION AUDIT DEFFICIENCIES/OBSERVATIONS COMPLIANCE [As on 30.06.2016]Name of Utility : CHHATTISGARH POWER TRANSMISSION COMPANY LIMITED
Name of S/Sidentified for
protectionaudit
S/Svoltage
Name of 3rdparty protection
audit agency
Date on whichaudit
conductedObservations of protection audit
Deficiencies that can becorrected without procurement
(Category-A)
Deficiencies involving procurement(Category-B)
1) Second DC system is recommended .Yes No 31.03.2017
Proposed in the year16-17 in Refurbish
Scheme.2) To renovate/retrofit Main-I & Main-IIProtection with numeric relays in all outgoing feeders.
Yes
Main-I & Main-IIProtection withnumeric relays in allout going feederscompleted on28.12.2014
3) Carrier Protection is not in service.
02 no. havebeencommissioned in KEB-KWB interconnectors
Yes No 31.09.2016
In KEB-KWBinterconnector I & IIcarrier protection hasbeen taken inservice.In KW-DSPMI/C,action fromDSPM isawaited.Other 3feeders falls underCSPTCL scope
4) Disturbance Recoder and SER s arenot available.
Yes No 31.12.2016
Bay control panelsfor SCADA systemhave been received.M/s ABB is beingpersuaded tocommission thesame as early aspossible.
5) Non availability of Auto reclosescheme.
Yes No 30.12.2016
Scheme is readyfrom KWBend,waiting forconsent forconnected substations.
Korba WestTPS 220 KV NTPC & CSPTCL
Engineers 26.04.2013
Remarks
Yes /No
WhetherattendedYes/No
If notattended,
reason
Yes /No
WhetherattendedYes/No
If no,expected date
to attend
PROTECTION AUDIT DEFFICIENCIES/OBSERVATIONS COMPLIANCE [As on 30.06.2016]Name of Utility : CHHATTISGARH POWER TRANSMISSION COMPANY LIMITED
Name of S/Sidentified for
protectionaudit
S/Svoltage
Name of 3rdparty protection
audit agency
Date on whichaudit
conductedObservations of protection audit
Deficiencies that can becorrected without procurement
(Category-A)
Deficiencies involving procurement(Category-B)
6) Non availability of B/B differential
Yes No 31.12.2016 Work underprogress.
7) Non availability of LBB protection
Yes YES LBB has been kept inservice
8)GPS is available however no relay issynchronised with it.
Yes No 31.12.2016
After commissioningof SCADA panel,Relays will besynchronised.GPSfacility is available inSCADA.
Korba WestTPS 220 KV NTPC & CSPTCL
Engineers 26.04.2013
MPPGCL
Name of The Entity - Madhya Pradesh Power Generation Corporation Limited. (MPPGCL)Quarterly Protection Audit Report for the period of April 2016 to June 2016
Observation of Protection Audit PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO,EXPECTEDDATE TOATTEND
1 ATPS#5 220
Hathway make GPS time synchronising system is providedbut connected on 220 KV Birsinghpur-3 & Sidhi feedersonly, all other relays of feeders & transformers are to beconnected.
YES YES COMPLETED
2 ATPS#5 220REF protection not provided on 220/132 kv ICTs, it issuggested to provide the same.
NOT REQUIRED; DUE TO SHIFTING OF132 KV SWITCYARD
3 ATPS#5 220220 kv static Bus Bar Protection scheme make ABB, typeRADSS is available at site since 2000, but awaited forcommissioning.
YES YES
4 ATPS#5 220LBB Protection is not provided for any element and it issuggested to take in service at earliest
YES YES
5 ATPS#5 220ASEA make 132 kv MOCBs are in service,which is veryold and inaquate as per the increased fault MVA of thesite.It is suggested to replace same
NOT REQUIRED; DUE TO SHIFTING OF132 KV SWITCYARD
6 ATPS#5 220
Auto Reclosure feature is provided for 220 KV Birshingpur- 3, Jabalpur I & II and Sidhi feeders only. For other 220KV feeders Auto Reclose facility is available but not becommissioned due to non availability of PLCC protectioncouplers.
YES NO OCT'16DELAY IN COMPLETION DUE TO NON-AVALIABILTY OF PLCC PANELS FROMMPPTCL FOR OTHER END
7 ATPS#5 220
One set of 600 AH battery set is provided for switch yard,which is very old and in poor condition its need earlyreplacement.Battery Capacity test could not be done due tosome opertional problem.
YES NO OCT'16PROCUREMENT OF BATTERY IS INUNDER PROCESS.
8 ATPS#5 220
A stand by DC supply is available at switchyard to powerplant,DC load of 220 kv panels are running on thissupply.It is recommended by committee to provide separateDC supply arrangement for power plant and switchyard.
YES NO OCT'16 PROCUREMENT IS IN UNDER PROCESS
9 SGTPS 1 TO 4 220Partial DC leakage observed, it is advised to recify thesame.
YES YES COMPLETED
Deficiencies that can be correctedwithout procurement (Category-A)
Deficiencies involving procurement(Category-B)
BUS BAR PROTECTION SCHEME ANDLBB PROTECTION HAS BEENCOMMISSIONIED ON DATED08/10/2015.(COMPLETED).
Sl.No.
Name ofSub-Station
identified forProtection Audit
S/S VoltagekV
Page 1 of 10
MPPGCL
Name of The Entity - Madhya Pradesh Power Generation Corporation Limited. (MPPGCL)Quarterly Protection Audit Report for the period of April 2016 to June 2016
Observation of Protection Audit PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO,EXPECTEDDATE TOATTEND
Deficiencies that can be correctedwithout procurement (Category-A)
Deficiencies involving procurement(Category-B)
Sl.No.
Name ofSub-Station
identified forProtection Audit
S/S VoltagekV
10 SGTPS 1 TO 4 220220 KV Bus Bar Protection is available but not in servicedue to some problems
YES YES
11 SGTPS 1 TO 4 220LBB Protection relay are available but protection are notprovided for any element and it is suggested to put the samein service.
YES YES
12 SGTPS 1 TO 4 220SER/DR is not installed but it available in numerical relaysprovided in 220 kv pali interconnector-I and 220 kv Sukhafeeders only.
YES YES
SER/DR FACILITY IS AVAILABLE INEASUN REYROLLE MAKE CSC-101 DPRRELAY INSTALLED AT 220 KVOUTGOINING FEEDERS.
13 SGTPS 1 TO 4 220Auto reclose facility not provided on any 220 kV feeders. Itis intimated that protection couplers are not available and itis suggested to provide the same.
YES NO OCT'16
CGL MAKE PLCC PANEL DRAWINGAPPROVED ON DATED 11.01.2016 ANDMATERIAL WILL BE SUPPIED WITHIN 2-3 MONTHS.WORK LIKELY TO BECOMPLETED UPTO OCT-2016.
14 SGTPS 1 TO 4 220GPS based time synchronisation facility is not available. Itis suggested to provide the same.
YES NO OCT'16 PROCUREMENT UNDER PROGRESS.
15 SGTPS 1 TO 4 220A separate source for 220 kV dc supply is provided forelectrical control room and 220 kv switchyard. This batteryset is very old, commissioned 1991 needs replacement.
YES NO OCT'16TENDERING FOR PROCUREMENT ISUNDER PROCESS.
16 SGTPS 1 TO 4 220Emulsifier system is provided on GT and UAT for Fireprotection. Same is operate manually.
YES NO OCT'16
SYSTEM IS WORKING IN MANUALMODE AND BUDGETARY OFFER FORNITROGEN BASED FIRE PROTECTIONSYSTEM ARE OBTAINED AND SAMEWILL PROCURE AFTER TECHNICALAND ADMISTRATIVE APPROVAL.
17 SGTPS # 5 400
Static Bus Bar Protection scheme is provided on 400 kVbus make ABB Type-RADHA. A numerical Bus-Barprotection scheme may be provided as suggested by thecommittee.
YES NO SEPT'16
ORDER PLACED TO M/s SEIMENSMUMBAI VIDE ORDER NO. 511-0100/SGTPS/P&W/ENIT-0/T-3194/15-16/ET&I-III/ORD-226/4515,BRS DATED10.02.16 AND WORK SHALL BECOMPLETE WITHIN 5 TO 6 MONTHS.
18 SGTPS # 5 400DG set available in power plant and it is suggested by thecommittee to extend AC supply as stand by to 400 kVcontrol room and switchyard in case of emergency.
YES NO OCT'16CABLE WORK UNDER PROGRESS FROMACDB SWITCHYARD TO DG SET.
COMPLETED
Page 2 of 10
MPPGCL
Name of The Entity - Madhya Pradesh Power Generation Corporation Limited. (MPPGCL)Quarterly Protection Audit Report for the period of April 2016 to June 2016
Observation of Protection Audit PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO,EXPECTEDDATE TOATTEND
Deficiencies that can be correctedwithout procurement (Category-A)
Deficiencies involving procurement(Category-B)
Sl.No.
Name ofSub-Station
identified forProtection Audit
S/S VoltagekV
19 SGTPS # 5 400Spare unit of single phase ICT is not ready to use, it shouldbe attented and kept in ready condition in case ofemergency.
YES YES COMPLETED
20 SGTPS # 5 400High voltage problem are reported and it is suggested toprovide bus reactor or line reactor on 400 kv BRS-Damohline I & II at BRS end.
NOT POSSIBLE AS AVALIABILE SPACEHAS ALREADY BEEN UTILISED BY M/sPGCIL.
21 SGTPS # 5 400400 KV BRS - BAlCO and BRS-Vandana Power(KORBA) bays belongs to PGCIL
UNDER SCOPE OF M/s PGCIL.
22 STPS PH-I 220No GPS in control room and it is necessary for the rootcause analysis of the disturbance occurred in the grid
23 STPS PH-I 220
In the protection scheme electromechnical and static relayare in use but as per present grid norms avaliabilty ofnumerical relay is required for fault analysis and eventrecorder.
24 STPS PH-I 220Fire protection system of transformers are out of order andsuitability of nitrogen injection fire protection system maybe explored.
25 STPS PH-II 220 Scaling is observed on the terminal of some of the batteries. YES YES COMPLETED
26 STPS PH-II 220L&T make switchgear indicating lamp assembly is missingand they are vacant i.e whole are uncovered.
YES YES COMPLETED
27 STPS PH-II 220No GPS in control room and it is necessary for the rootcause analysis of the disturbance occurred in the grid
YES NO DEC'16ESTIMATE PREPARED FORAPPROVAL.
28 STPS PH-II 220Some of the cells of unit no.7 are bulged in plante typebattery set which resulting in breaking of the container andlid therfore it should be replaced at the earliest.
YES YES COMPLETED
29 STPS PH-II 220Some of the cell are bypassed due to bulging problemthereby reducing the available capacity of the bank.
YES YES COMPLETED
NOT APPLICABLE BECAUSE ALL 5UNITS OF PH-I HAS ALREADY RETIRED.
Page 3 of 10
MPPGCL
Name of The Entity - Madhya Pradesh Power Generation Corporation Limited. (MPPGCL)Quarterly Protection Audit Report for the period of April 2016 to June 2016
Observation of Protection Audit PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO,EXPECTEDDATE TOATTEND
Deficiencies that can be correctedwithout procurement (Category-A)
Deficiencies involving procurement(Category-B)
Sl.No.
Name ofSub-Station
identified forProtection Audit
S/S VoltagekV
30 STPS PH-II 220
Battery bank of unit 6& 7 were commissioned in the year2004 & 2001 respectively.As per CEA circular fair life ofbattery is 5 years only therefore suitable action for theirreplacement is to be initiated at the earliest.
YES NO SEPT'16
RECONDITIONING OF UNIT NO.7BATTERY BANK HAS BEEN CARRIEDOUT RECENTLY (i.e APRIL-2015) ANDFOR UNIT NO.6 LOI HAS BEEN ISSUED..
31 STPS PH-II 220No alarm for DC E/F is provided in the chargers.
YES YES COMPLETED
32 STPS PH-II 220Capacity test has not been conducted recommended to doonces in a year.
YES YES COMPLETED
33 STPS PH-II 220
In the protection scheme electromechnical and static relayare in use but as per present grid norms avaliabilty ofnumerical relay is required for fault analysis and eventrecorder.
YES NO OCT'16
GENERATOR PROTECTION NUMERICALRELAY HAS BEEN INSTALLED IN UNITNO.7.THE NUMERICAL RELAY FORUNIT NO.6 WILL BE COMMISSIONED INNEXT OVERHAULING.
34 STPS PH-II 220 Pole slip protection is not available so it shall be provided. YES NO NOT APPLICABLE
35 STPS PH-II 220Auto reclosure/Disturbance Recorder/Event Logger/SER allare not available.
YES NO DEC'16
NUMERICAL RELAY HAS BEENCOMMISSIONED IN DPR WHICHCONTAIN ALL THE MENTIONEDFEATURES,BUT CARRIER SCHEME ISNOT AVAILABLE THEREFORE AUTORECLOSING FEATURE COULD NOT BEESTABLISHED.FOR THIS CARRIERPROTECTION PANELREQUIREDTHEREFORE ESTIMATE HAS BEENSUBMITTED FOR APPROVAL.
36 STPS PH-II 220 Carrier Protection is not available in 220 kV switchyard. YES NO DEC'16TENDER WORK FOR CARRIERPROTECTION IS IN PROCESS.
37 STPS PH-II 220 Earth Mettaling is not visible in 220 kV switchyard YES NO AUG'16 WORK IS IN UNDER PROCESS.
38 STPS PH-II 220Mulsi Fire protection of the transformer is out of order,suitability of Nitrogen injection may be explored
YES NO DEC'16THE WORK OF PROVIDING FIREHYDRANT IS IN PROGRESS BYMECHANICAL DEPARTMENT.
Page 4 of 10
MPPGCL
Name of The Entity - Madhya Pradesh Power Generation Corporation Limited. (MPPGCL)Quarterly Protection Audit Report for the period of April 2016 to June 2016
Observation of Protection Audit PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO,EXPECTEDDATE TOATTEND
Deficiencies that can be correctedwithout procurement (Category-A)
Deficiencies involving procurement(Category-B)
Sl.No.
Name ofSub-Station
identified forProtection Audit
S/S VoltagekV
39 STPS PH-II 220Suitability of short circuit breaking capacity of circuit bkr& short time current capacity of CT's shall be reviewed inrespect of exsisting fault level's
YES NODUE TO DISCONTINUATION OF 312.5MW OF PH-I,FAULT LEVEL HAS GOTREDUCED CONSIDERABLY.
40 STPS PH-III 400220v dc battery source - no alarm for dc e/f is provided inthe chargers. YES YES COMPLETED
41 STPS PH-III 400220v dc battery source - capacity test has been conductedin the year 2011. recommended to do the capacity test oncein a year.
YES YES COMPLETED
42 STPS PH-III 400
220 V DC battery source - records indicated the voltagemeasurement of individual cells with the charger oncondition. This readings are to be taken with charger offcondition also.
YES YES COMPLETED
43 STPS PH-III 400
220 V DC battery source - Scaling is observed on theterminals of some of the batteries. Also the generalcleanliness of the batteries and battery room needimprovement.
YES YES COMPLETED
44 STPS PH-III 400ISP Feeder - Over voltage stage i and stage ii protectionhas been provided through separate rxeg-21 relays.
YES YES COMPLETED
45 STPS PH-III 400ISP Feeder - over voltage stage ii setting has been adoptedas 130% . this should be reviewed.
YES YES COMPLETED
46 STPS PH-III 400 No gps in 400kv control room . YES NO DEC'16TENDER OPENED AND CASE IS UNDERPROCESS.
47 STPS PH-III 400
220 V DC battery source - 216 V Dc battery source ofunit# 8 of 1200ah capacity - It was commissioned in theyear 2004. As per cea circular the revised fair life is 5 yearsonly. Suitable action for their replacement is to be initiatedat the earliest.
YES YES
48 STPS PH-III 400
220 V Dc battery source - 216 V DC battery source ofunit# 9 of 1200ah capacity - It was commissioned in theyear 2004. As per cea circular the revised fair life is 5 yearsonly. Suitable action for their replacement is to be initiatedat the earliest.
YES YES
ACCORDING TO CE(Engg.) JABALPURAS PER IEEE 450-1987,THE
RECOMMEND PRACTICE TO REPLACEBATTERY IS BASED ON C-10 TEST AND
NOT A TIME BOUND AND C-10 TESTFOUND SATISFACTORILY IN AUG-13 &
THE SAME WILL BE PERIODICALLYREPEATED IN AOH.
Page 5 of 10
MPPGCL
Name of The Entity - Madhya Pradesh Power Generation Corporation Limited. (MPPGCL)Quarterly Protection Audit Report for the period of April 2016 to June 2016
Observation of Protection Audit PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO,EXPECTEDDATE TOATTEND
Deficiencies that can be correctedwithout procurement (Category-A)
Deficiencies involving procurement(Category-B)
Sl.No.
Name ofSub-Station
identified forProtection Audit
S/S VoltagekV
49 STPS PH-III 400
220 V DC battery source - 216 V DC battery source forstation of 1200ah capacity - It was commissioned in theyear 2009. As per cea circular the revised fair life in 5years only.
YES YESITS C-10 TEST DONE AND RESULTFOUND SATISFACTORY.
50 STPS PH-III 400ISP Feeder - Reverse zone is not provided is rel 521 relay.The zone calculations may be revised.
YES NO DEC'16
REVERSE ZONE WILL BE PROVIDED INTHE NEW NUMERICAL RELAY WHICHIS PROCURED FOR MAIN 2PROTECTION .PURCHASE OF RELAYFOR MAIN-II IS IN TENDERINGSTAGE.HOWEVER PROPOSAL FORCALLING SERVICE ENGINEER FOR REL521 IS IN PROCESS.
51 STPS PH-III 400ISP Feeder - Over voltage protection has not been enabledin rel521 numerical relay.
YES YES.OVERVOLTAGE SEETING STAGE-1 &STAGE-II HAVE BEEN PROVIDEDTHROUGH SEPARATE RXEG-21
52 STPS PH-III 400Reactor - 63 MVARs bus reactor no. 1 is out since24.05.2005.
YES YES
53 STPS PH-III 400Reactor - new reactor is available. it should becommissioned early.
YES YES
54 STPS PH-III 400Fire protection of transformer - mulsifire type fireprotection system is out of order.
YES NO
TRAIL OF MULSIFIRE D,G SET TAKENSUCCESSFULLY.HWEVER POSSIBILITY
OF NITROGEN FIRE PROTECTIONSYSTEM IS BEING EXPLORED.
55 STPS PH-III 400Fire protection of transformer - suitable of nitrogeninjection fire protection system may be explored.
YES NO DEC'16 WAITING FOR RECEIPT OF OFFER
56 SSTPP 400
Carrier protection is enabled for 400 & 220 KV lines.A/Ris enabled dead time and reclaim time are taken as 700 ms& 15msec respectively.The same mar be reviewed as perCBIP guideline.According to which setting are to be 1 sec& 25 sec respectively.
YES NO DEC'16
DUE TO PROBLEM OF NONACCEPTANCE OF CHANGES IN SCADASOFTWARE.MATTER IS TAKEN WITHM/s ALSTOM AND ITS RESPONSEAWAITED.
57 SSTPP 400
Same over voltage stage-I setting is adopted for all 400 KVline.As per CBIP guide line clause no.4.3.1 of manualno.274.A time discrimination of 1sec is to be providebetween relays of different lines at an station.The mattermat be reviewed.
YES YES COMPLETED
BUS REACTOR-I SUCCESSFULLYCHARGED ON 29/12/2012.
Page 6 of 10
MPPGCL
Name of The Entity - Madhya Pradesh Power Generation Corporation Limited. (MPPGCL)Quarterly Protection Audit Report for the period of April 2016 to June 2016
Observation of Protection Audit PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO,EXPECTEDDATE TOATTEND
Deficiencies that can be correctedwithout procurement (Category-A)
Deficiencies involving procurement(Category-B)
Sl.No.
Name ofSub-Station
identified forProtection Audit
S/S VoltagekV
58 SSTPP 400
Over voltage stage-II setting for 400 KV line is adopted aspick up 140% time 1 sec.As per CBIP guide lines thesetting is to be taken as 150% & 0.1 sec.The setting may bereviewed.
YES YESSETTING ARE CHANGED ANDPRESENTLY EFFECTIVE.
59 SSTPP 400
Zone 3 setting for 400 KV SSTPP-Pithampur circuit 1&2is based on 100% of main line plus 100% of 400 KVPithampur-PGCIL indore line setting may be reviewed byconsidering another circuit of SSTPP-Pithsmpur as longestline.
YES YESSETTING ARE CHANGED ANDPRESENTLY EFFECTIVE.
60 SSTPP 200
Zone 3 setting for 200 KV SSTPP-Chhegaon line is basedon 100% of main line plus 100% of 220KV chhegaon-nimrani line It is reaching to next voltage line at chhegaonline. setting may be revied to restrict the reach.
YES YESSETTING ARE CHANGED ANDPRESENTLY EFFECTIVE.
61 TONS HPS 220 PLCC ROOM - Dead Rodents odor was felt. YES YES COMPLETED
62 TONS HPS 220220 KV Feeders - TMS of directional E/F is 0.1 second. Itappears very low and to be reviewed in reference to faultMVA of Tons HPS.
YES YES COMPLETED
63 TONS HPS 220
220 KV Feeders - Female contact of R & Y phases of bus-2isolator of 220 KV Rewa feeder-2 is not available. Hence,it is not possible to put on this bus in case of anyeventuality.
YES YES COMPLETED
64 TONS HPS 220RELAYS - Zone 3 time setting of 220 KV feeders is 600mili seconds and it may be 700 milli seconds as per newinstruction.
YES YES COMPLETED
65 TONS HPS 220 DG Set – Over current protection is out of service. YES NO DEC'16TENDER OPENED AND CASE IS UNDERPROCESS.
66 TONS HPS 22048 Volt DC System - Battery set is placed on the floorwithout putting insulator.
YES NO DEC'16PROCUREMENT OF BATTERY SETSHALL BE DONE UPTO 2015-16 .
67 TONS HPS 220PLCC ROOM - No PLCC cabinets for Rewa – 1, Rewa - 2& Kotar directions.
YES NO DEC'16
PROCUREMENT OF MATERIALINITIATED
Page 7 of 10
MPPGCL
Name of The Entity - Madhya Pradesh Power Generation Corporation Limited. (MPPGCL)Quarterly Protection Audit Report for the period of April 2016 to June 2016
Observation of Protection Audit PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO,EXPECTEDDATE TOATTEND
Deficiencies that can be correctedwithout procurement (Category-A)
Deficiencies involving procurement(Category-B)
Sl.No.
Name ofSub-Station
identified forProtection Audit
S/S VoltagekV
68 TONS HPS 220Communication - Communication to 220 KV Kotar s/s isnot available
YES NO DEC'16
69 TONS HPS 220Communication - Communication to 220 KV Rewa s/s isnot available
YES NO DEC'16
70 TONS HPS 220
Communication - Mode of communication with SLDC isvery poor which may be improved by providing Landlinephone in control room or by other suitable means. PLCCcommunication to Jabalpur is having much hauling.
YES NO DEC'16
71 TONS HPS 220RTU - Active power transducer of 220 KV Rewa feeder-2is found out.
YES YES COMPLETED
72 TONS HPS 220 RTU - Alternate data channel to SLDC is not available. YES NO DEC'16PROCUREMENT OF MATERIALINITIATED
73 TONS HPS 220220 KV Feeders - Carrier Protection & Auto re-closurefeature has not been commissioned YES NO DEC'16
TENDER OPENED AND CASE IS UNDERPROCESS.
74 TONS HPS 220220 KV Feeders - 220 KV feeders’ isolators with earthswitch are not in working order. YES NO OCT'16
MATERIAL RECEVIED AT SITE ANDWORK COMPLETED IN UPCOMINGAOH.
75 TONS HPS 220 Transformer - MOLG of all the GTs are not working. YES NO OCT'16 RECIFIED IN UPCOMING AOH
76 TONS HPS 220Station Transformer - 33 KV lightening arrestor founddisconnected.
YES NO DEC'16 RECIFIED IN UPCOMING AOH
77 TONS HPS 220
Generator Transformer - No mechanical tripping onexisting 220 KV Gas Circuit Breaker of generatortransformer and it is Single Pole Mechnism, it shall beGang operated circuit breaker.
YES NO DEC'16PROCUREMENT OF MATERIALINITIATED
78 TONS HPS 220Fire Protection – Generator fire protection is not inworking order.
YES NO DEC'16ORDER PLACED TO FIRM AND WORKSHALL BE COMPLETED SHORTLY.
PROCUREMENT OF MATERIALINITIATED
Page 8 of 10
MPPGCL
Name of The Entity - Madhya Pradesh Power Generation Corporation Limited. (MPPGCL)Quarterly Protection Audit Report for the period of April 2016 to June 2016
Observation of Protection Audit PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO,EXPECTEDDATE TOATTEND
Deficiencies that can be correctedwithout procurement (Category-A)
Deficiencies involving procurement(Category-B)
Sl.No.
Name ofSub-Station
identified forProtection Audit
S/S VoltagekV
79 TONS HPS 220Governor - Unit 1 & 2 are on manual mode of governoroperation.
YES YES COMPLETED
80 TONS HPS 220RELAYS - Generator Protection & transformer protectionis provided through electromechanical relays. It is to beprovided with numeric relays.
YES NO DEC'16TENDER OPENED AND CASE IS UNDERPROCESS.
81 TONS HPS 220RELAYS - The existing bus bar protection is un-commissioned and obsolete. It is to be provided throughNumeric relays.
YES YES
82 TONS HPS 220RELAYS - LBB protection is not commissioned on 220KV feeders. YES YES
83 TONS HPS 220RELAYS - Carrier protection is not available on all 220KV feeders.
YES NO DEC'16TENDER OPENED AND CASE IS UNDERPROCESS.
84 TONS HPS 220RELAYS - 220 KV Bus coupler earth fault relay is out oforder
YES NO DEC'16TENDER OPENED AND CASE IS UNDERPROCESS.
85 TONS HPS 220RELAYS - Some of the protection/ auxiliary relays are nothaving cover to prevent from dust, moisture and water etc.
YES YES COMPLETED
86 TONS HPS 220Earth Resistance – Earth Resistance record has notproduced for 220/33 KV switch yard & electronic earthingof DAVR.
YES NO OCT'16 DONE IN UPCOMING AOH
87 TONS HPS 220 GPS Time Synchronizer was not available. YES NO DEC'16
88 TONS HPS 220 Sequence Event Recorder was not available. YES NO DEC'16
89 TONS HPS 220 Disturbance Recorder was not available YES NO DEC'16
90 TONS HPS 220 Diagnostic Station was not available. YES NO DEC'16
TENDER OPENED AND CASE IS UNDERPROCESS.
COMPLETED
Page 9 of 10
MPPGCL
Name of The Entity - Madhya Pradesh Power Generation Corporation Limited. (MPPGCL)Quarterly Protection Audit Report for the period of April 2016 to June 2016
Observation of Protection Audit PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO,EXPECTEDDATE TOATTEND
Deficiencies that can be correctedwithout procurement (Category-A)
Deficiencies involving procurement(Category-B)
Sl.No.
Name ofSub-Station
identified forProtection Audit
S/S VoltagekV
91 TONS HPS 220The condition of emergency lighting at various floors andcontrol locations is poor.
YES YES COMPLETED
Page 10 of 10
MPPGCL protection audit statusState:- Madhya PradeshENTITY - MPPGCLQuarterly Report for the period of April 2016 to June 2016
ANNEXURE-III
PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO, EXPECTEDDATE TOATTEND
1 BARGI HPS132 KV SUB-
STATIONDPR relay setting of the 132 KV Jabalpur 1, Jabalpur 2 and
Lakhnadon feeders to be reviewedYES YES COMPLETED
2 BARGI HPS132 KV SUB-
STATION
220 V DC system having positive earth fault and mixing of theDC source 1 and 2 is observed. Periodical load test of the
battery may be ensured.YES YES COMPLETED
3 BARGI HPS132 KV SUB-
STATIONThe 132 KV switchyard, Power House and equipment needs
more attention towards its up keeping.YES YES COMPLETED
4 BARGI HPS132 KV SUB-
STATIONRecords of the mock drill / trial of the fire fighting equipments
and DG set are not available at Bargi Power Station.YES YES COMPLETED
5 BARGI HPS132 KV SUB-
STATIONAll Existing Electomechanical / Electostatic Relays to be
replaced with numerical relays.YES NO Dec-17
Budgetary offer for replacing allelectromechanical relay with Numerical Relayfor supply with complete retrofitting job isbeing awaited.
6 BARGI HPS132 KV SUB-
STATION
Fire Fighting system with CO2 Cylinders are available at powerstation but it is observed that it is in the mannual mode. It
may be in the auto mode.YES NO Dec-17
The case of repairing and upgrading of CO2system is under process.
7 BARGI HPS132 KV SUB-
STATIONThe Facility of DR/ SER is not available at the HPS Bargi. YES NO Dec-17
The facility of DR/SER is provided in the offer ofM/s ABB for retrofitting of numerical relay panelwhich is in the process.
8 BARGI HPS132 KV SUB-
STATIONGPS Facilities is not available. YES NO Dec-16
Preparation of Technical specification is underprogress.
9 BARGI HPS132 KV SUB-
STATION
132 KV MOCB installed on 132 KV Jabalpur-1, Jabalpur-2,Lakhnadon, bus coupler bay and 20MVA transformer to be
replaced with SF6 Circuit Breaker.YES NO Dec-16
Drawing of SF6 Breaker is approved and M/sElectro services Vadodara supply the materialwithin 3 months.
10 BARGI HPS132 KV SUB-
STATIONLBB Relay not provided on the 132 KV Jabalpur-1, Jabalpur-2 ,
Lakhnadon Feeders.YES NO Dec-16
Provision for LBB relay on 132KV JBP-1, JBP-2,LKD feeders is being incorporated in freshprocurement case of numerical relays and shallbe commissioned in future.
11 BARGI HPS132 KV SUB-
STATION132 KV R phase CT of Bus Coupler (Bus-I) is not available. YES YES COMPLETED
12 BARGI HPS132 KV SUB-
STATIONBus Bar Protection is not in service. YES NO Dec-16
PROCUREMENT OF BUS BAR PROTECTION ISUNDER PROCESS AND AT PRESENT BUDGETARYOFFER IS ASKED FROM FIRM.
DEFICIENCIES THAT CAN BECORRECTED WITHOUT
PROCUREMENT (CATEGORY-A)
DEFICIENCIES INVOLVEINGPROCUREMENT (CATEGORY-B)
NAME OF UTILITY: MPPGCLFORMAT FOR PROTECTION AUDIT DEFICIENCIES/OBSERVATIONS COMPLIANCE
S.NO
NAME OF S/sIDENTIFIED FOR
PROTECTIONAUDIT
S/s VOLTAGEOBSERVATIONS OF PROTECTION AUDIT (DATE
AT WHICH PROTECTION AUDIT CONDUCTED i.e 22/04/13& 23/04/14.)
Page 1 of 1
MPPGCL protection audit status
State:- Madhya PradeshENTITY - MPPGCLQuarterly Report for the period of April 2016 to June 2016
ANNEXURE-II
PRESENT STATUS
YES/NOWHETHERATTENDEDYES/NO
IF NOTATTEND,REASON
YES/NOWHETHERATTENDEDYES/NO
IF NO, EXPECTEDDATE TO ATTEND
1GANDHISAGAR
HPSCarrier System is use for communication only, no carrier protection isprovided.
NA
2GANDHISAGAR
HPS
Positive side of 220 V DC sources - 1 is found earthed (Voltagebetween positive to earth is Zero and negative to earth is 240 V) Pointat which DC leakage / earthling have developed may be detected andrectified at the eariliest.
YES YES COMPLETED
3GANDHISAGAR
HPS220 V Battery charger - 2 and Battery set - 2 is very old and underreplacement.
YES YES COMPLETED
4GANDHISAGAR
HPSSynchronizing trolley is available and working properly. YES YES COMPLETED
5GANDHISAGAR
HPSCTs star point earthling of 132 KV are checked and found no multipleearthlings in the system.
YES YES COMPLETED
6GANDHISAGAR
HPS
Height of Live conductor in HV section from CB to wave trap in 132 KVManasa bay is seams to be very less. Sufficient Ground clearance maybe maintained for safety purpose.
YES YES COMPLETED
7GANDHISAGAR
HPS
Operation of DG set is available in manual mode. Provision for automode operation may be provided so that DG set starts automaticallyin black - cut condition/exigency.
YES NO JAN'17 NIT WLL BE ISSUED SHORTLY
8GANDHISAGAR
HPSAuto Check synchronizing facility is not available, which should beprovided for betterment of system.
YES NO JUNE'17BUDGETARY OFFER IS BEINGOBTAINED.
9GANDHISAGAR
HPSTesting of DPR, Differential and other Relays. Along withcorresponding CT & PT should be carried out in regular interval.
YES YES COMPLETED
10GANDHISAGAR
HPSDRs, SERs are not available for recording of system disturbances. YES NO AUG'17 OFFER ARE AWAITED
11GANDHISAGAR
HPSBack up O/c - E/F relays are not provided for all GeneratorTransformer. It should be provided at the earliest.
YES NO JUNE'17 OFFER ARE AWAITED
12GANDHISAGAR
HPS
Almost all the relays provided for Generator, Generator Transformer(GT), Station Transformer of 20 MVA are electromagnetic type. Theseexisting relay should be replaced with numerical relays for betterreliability, sensitivity, faster response and compatibility with GPSsystem.
YES NO AUG'16
TENDER FOR PROCUREMENT ANDCOMMISSIONING OF DISTANCEPROTECTION RELAY AND BACK-UPPROTECTION RELAY IS UNDEREVALUATION.
13GANDHISAGAR
HPS
Almost all relays (Distance protection, O/c, E/F relays) provided for132 KV Feeders are electromagnetic type and required to be replacedby numerical relay for better reliability, sensitivity, faster responseand comptibility with GPS system.
YES NO AUG'17BUDGETARY OFFER ARE CALLED FORESTIMATION BUT STILL AWAITED.
S.NO
NAME OF S/sIDENTIFIED FOR
PROTECTIONAUDIT
OBSERVATIONS OF PROTECTION AUDIT (DATE AT WHICHPROTECTION AUDIT CONDUCTED i.e 22/04/13 & 23/04/14.)
FORMAT FOR PROTECTION AUDIT DEFICIENCIES/OBSERVATIONS COMPLIANCENAME OF UTILITY: MPPGCL
DEFICIENCIES THAT CAN BE CORRECTEDWITHOUT PROCUREMENT (CATEGORY-A)
DEFICIENCIES INVOLVEING PROCUREMENT(CATEGORY-B)
Page 1 of 1
State:- Madhya PradeshENTITY - OMKARESHWAR POWER STATIONQuarterly Report for the period of April 2016 to June 2016
Yes NoPA
conductedon date
if not done,Target Date
for PAYes No Total
CategoryA
CategoryB
TotalCategory
ACategory
BTotal
CategoryA
CategoryB
1 OmkareshwarPower Station 220 Yes Yes 5 5 4 1
No. of Deficiencies attendedNo. of Deficiencies not yet
attendedIf identified for PA
Annexure - A.2.2
Protection Audit
Name of the utility:Omkareshwar Power Station FY:16-17
Whetheridentified for PA
in this FY
Deficienciesobserved
No. of Deficiencies
Sr.No.
Name of the S/s KV
State:- Madhya PradeshENTITY - OMKARESHWAR POWER STATIONQuarterly Report for the period of April 2016 to June 2016
Remarks
Yes/NoWhetherattendedYes/No
If notattendedreason
Yes/NoWhetherattendedYes/No
If noexpecteddate toattend
130 OmkareshwarPower Station 220 Auto reclosing of all the 220KV Lines are
disabled
M/s Voith Hydro & M/s ABB Ltd. hasintimated that our system is not designed forauto reclosing operation due to generatorconstant.
131 OmkareshwarPower Station 220
Only Stage-1 overvoltage protection (110%-5sec) is only provided, however whereas twostages of overvoltage protection isrecommended by CBIP
The report of CPRI,i.e. third party has beenreceived and all settings of CPRI shall bereviewed in consultation with MPPTCL.
132 OmkareshwarPower Station 220
Line protection Main -1 & Main-2 are havingdistance protection.In such cases CBIPrecommends for additional directional IDMTEarth Fault Relay
Yes
The Definite type of Directional Earth faultprotection function is configured in the relayREL 511 and is in service.However,the casefor replacement of existing REL316 relay intoREL670 or equivalent is in progress.
133 OmkareshwarPower Station 220
Generator Protection back up ImpedanceProtection is provided with time delay of 3sec, whereas,it is recommended the samemay be 2 sec maximum
Complied
134 OmkareshwarPower Station 220 Most of the protection relays needed to be
tested regularly Complied
Updated status of rectification work of deficiencies under category A & B of Omkareshwar power Station
Sr.No.
Name ofSubstation
identified forProtection Audit
S/SVoltage in
KVObservation of the Protection Audit
Deficiencies that can becorrected without
procurement(Category-A)
Deficiencies involvingprocurement(Category-B)
Name of Utility: JP Bina Report for the period of April 2016 -June 2016
Yes/NoWhetherattendedYes/No
If notattended,re
asonYes/No
WhetherattendedYes/No
If notattended,
reason
1)UAT 1&2 for unit 1 still notcommissioned Yes Yes NA NA NA NA
All the UAT of Unit 1&2 have beencommissioned (Complied)
2) GPS system notcommissioned Yes Yes NA NA NA NA
GPS system of whole station commissioned(Complied)
3) 2no. Of High Mast towerinstalled near 400KV transferbus in the switchyard
No YES NA NA NA NA
Both the high mast has been shifted to outside corners of the Switchyard( Complied)
4)DR&ER is provided in SCADAsystem. Yes yes NA NA NA NA
It is available in our SCADA system(Complied)
5)Battery cell voltage need tobe recorded with respectivecharger in OFF condition. Yes yes NA NA NA NA
Battery cell voltage is now being recordedrespective to charger in off condition.(Complied)
6)Directinal E/F relay setting 1sec. for PGCIL 1.2 Sec.forMPPTCL line is provided .This ison higher side,to be reviewed&revise Yes
Commentsfrom ourconsultantM/S TCE isgiven NA NA NA NA
Answer from our consultant M/S TCE :Directional e/f is provided to protect thesystem from high impedance line faults wherefault currents are low. So 1 sec operating timeis sufficient and can be used for both the lines.Decrease in the operating time may cause itto interfere with 3rd zone time settings.(Setting is in order. Hence complied)
7)Over voltage setting for 400kvPGCIL&MPPTCL line are not asper CBIP recomendetion(CBIPREV 274).
Yes
Commentsfrom ourconsultantM/S TCE isgiven NA NA NA NA
Our consultant TCE's reply :Please note thatan instantaneous overvoltage setting of 130%phase to phase can be used. As per standardpractice lines are capable of withstanding150% of highest system voltage at powerfrequency for 1 minute. So above settings areok. (Setting is in order. Hencecomplied)
Jaypee BinaThermal Power
Plant400 KV
SLDC,Jabalpur
14/02/2013-15/02/2013
FORMAT FOR PROTECTION AUDIT DIFFICIENCIES/OBSERVATIONS COMPLIANCE
Deficiencies that can be correctedwithout procurement(Category-A)
Deficiencies involvingprocurement(Category-B)Name of S/S
identified forprotection Audit
S/Svoltage
Name ofThird partyProtection
Audit agency
RemarkDate on
which auditconducted
Observation of protectionAudit
Page 1 / 2
Name of Utility: JP Bina Report for the period of April 2016 -June 2016
Yes/NoWhetherattendedYes/No
If notattended,re
asonYes/No
WhetherattendedYes/No
If notattended,
reason
FORMAT FOR PROTECTION AUDIT DIFFICIENCIES/OBSERVATIONS COMPLIANCE
Deficiencies that can be correctedwithout procurement(Category-A)
Deficiencies involvingprocurement(Category-B)Name of S/S
identified forprotection Audit
S/Svoltage
Name ofThird partyProtection
Audit agency
RemarkDate on
which auditconducted
Observation of protectionAudit
8)GT&ST fifth harmonicsblocking is done for 20%. Thismay be studies & revised.
Yes
Commentsfrom ourconsultantM/S TCE isgiven
NA NA NA NA
Reply from consultant TCE ;As perrecommendation from relay manuals, settingof 15 to 30 % is used for fifth harmonicblocking. As per our standard 20% is used fifthharmonic blocking. (Setting is in order.Hence complied)
9)It is observed that forganretor protection underfrequency relay trip setting48.5Hz for 5sec.& overfrequency relay trip setting51.0Hz for 5sec. Is taken,thesame may be reviewed.
Yes
Commentsfrom ourconsultantM/S TCE isgiven
NA NA NA NA
OUR consultant reply Frequency protectionis used mainly for alarm and as per ourpractice a time delay of 5 sec is adequate.(Setting is in order. Hence complied)
10)In turn protection has notbeen provided,through it isrecommended forGeneratormore than 100 MVA. Yes
Commentsfrom ourconsultantM/S TCE isgiven
NA NA NA NA
Our consultant TCE's reply ;As per ourstandard practice, inter-turn protection isprovided only when specifically recommendedby the manufacturer. (It is in order.Hence complied)
11)Periodical testing of relays &yard equipment must be done. Yes NA NA NA
Periodical testing of relay & yard equipmentshas been done .
Jaypee BinaThermal Power
Plant400 KV
SLDC,Jabalpur
14/02/2013-15/02/2013
Page 2 / 2
Name of Utility - MADHYA PRADESH POWER TRANSMISSION CO. LTD .JABALPUR (As on quarter ending June 2016 ) Annx-I
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
1. Time synchronisation problem ofprotective relays with GPS.
Yes Yes - Yes No - 2 nos ABB make relays have to beequiiped with IRIG-B port
2. Providing of Separate Event Logger No Yes* - Yes No*As event logging facility provided inall DPR's& Differential relays it is notrequired
3. Providing of adequate fire protectionsystem. No Yes - No No
Nitrogen injection fire protectionsystem provided in all threeTransformers.
4. Replacement of 220KV Static Bus Barsystem with Numeric No No - Yes Yes - Completed
5. Providing of additional Backup elementon 315MVA Transformer -III
No No - Yes Yes - Completed
1. Replacement of 1No 132KV NGEF SF6CB of BHEL Bay
Yes Yes - Yes Yes - Completed
2. Replacement of ElectromechanicalO/C & E/F relays of Incomers withnumerical relays.
No No - Yes Yes - 3 nos Numerical O/c + E/f relaysrequired
3. Provision for taking REF protection inCircuit on 160MVA, 3x40MVA and100MVA Transformers
Yes Yes - Yes No -
REF is enabled on 160 MVA CGLXmer and 100 MVA Xmer For 160MVA BHEL Xmer, NCT is required.For 3X40 MVA Xmer, NCT andstructure is required.
4. Providing of Additional wave trap on220KV Inter Connector-II No No - Yes Yes - -
1. LBB scheme to be taken in service Yes Yes - No No - Completed
2. Providing of 220KV Bus Bar Protection Scheme Yes yes - Yes Yes - Completed
3. LAs leakage Current measurement to be done Yes Yes - No No - Completed
1. Replacement of Static/Electromechanical DPRby Numerical relays
Yes Yes - No No -
2 Commissioning of new 600AH 48V BatteryCharger
Yes Yes - No No -
3 Synchronisation of GPS system with protectionof 132KV Traction-I & II feeders
Yes Yes - No No -
State:- Madhya Pradesh
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
ENTITY - MPPTCL
Quarterly Report for the period of April-2016 to June-2016
1 400KV S/SBhopal 400KV
InternalProtection Auditparty compirisingof representatives
of State Utilityand Power Grid
17-01-13to 18-01-
13
2 220KV S/SBhopal 220KV
InternalProtection Auditparty compirisingof representatives
of State Utilityand Power Grid
22-04-13to 23-04-
13
3220KV S/S
Mandideep220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
26-04-13 to27-04-13
4220KV S/S
Mandideep220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
07-05-13 to08-05-13
Page 1 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. 33KV, 25MVAr reactor of 315MVA Tr-I to betaken back in service by replacement of R phase33KV Bushing and repair of 33KV CB.
YES Yes - YES YES - -
2 Oil leakage from B phase Turret of 400KVBushing of 315MVA No-I
Yes Yes - No No - ATTENDED IN THE MONTH OF JUNE 2013
3. 33KV, 25MVAr reactor of 315MVA Tr-II to betaken back in service by replacement of R phase33KV Bushing and repair of 33KV CB.
Yes YES - No No -AFTER REPLACEMENT OF R-PHASE BUSHINGand repair of 33KV CB.REACTOR HASALREADY BEEN TAKEN IN SERVICE
4. Mixing of 220V DC source-I & II to be rectified Yes Yes - No No - DC SOURCE SEPARATED
5. Replacement of B phase CVT of 400KV Main Bus-II
Yes Yes - No No -REPLACEMENT DONE IN THE MONTH OFMARCH 2013
6. Auto Check synchronising facility is not inservice No NO - No No -
SYN. TROLLY IS AVAILABLE AND IT WILL BETAKEN IN SERVICE AFTER CHECKING THEHEALTHINESS OF THE RELAY AND ITS WIRING
7. Extending GPS connectivity to balance DPRsand Differential relays
Yes Yes - No No - -
8. Providing of Separate Event Logger Yes yes - YES YES - Event logging facility commissioned in SCADA
9. Connecting 220KV Bus Bar Panel for tripping Yes Yes - No No - TRIPPING CONNECTED ( 28 MAY 2013)
10 Testing of DPR of 220KV Interconnector-II Yes Yes - No No - TESTED1 Providing of Emergency light in Control andBattery Room
No Yes - No No -
2 Providing GPS connectivity in 400KVControlpanels
Yes Yes - No No -
3. DG set not provided Yes yes - YES YES - Completed4. 400KV Bus Bar protection out of service Yes Yes - No No -5 High resistance of Earth pit of 220KV PGCIL-IIbay
Yes Yes - No No -
6. 220KV side LBB to be commissioned Yes Yes - No No -7 Directional E/F feature to be enabled on220KV Birsinghpur and Damoh feeder.
Yes Yes - No No -
8. REF protection on 160MVA TELK Tr. To beenabled
Yes Yes - No No -
1. Zone-III setting of 220KV Gwalior-Bina-I & II tobe reviewed No Yes - No No -
2 Extending GPS time synchrinising facility to allpanels No Yes - No No -
3 220KV Bus Bar scheme to be provided No No - YES YES -New Numeric scheme commissioned in placeof old static scheme
4. Providing of NIFPS on 3x40MVA 220/132KVTransformer
Yes No - YES NO -Matter is under consideration ,however forsingle phase units scheme is not feasible.
5. Providing of DG set Yes No - YES Yes DG set received. Commissioning work underprogress
5 400KV S/S Bina 400KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
12-02-13 to13-02-13
6 400KV S/S Katni 400KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
17-01-13 to18-01-13
7 220KV S/S Gwalior 220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
27-04-13 to28-04-13
Page 2 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. Relay setting of 132KV Malanpur-Banmore-Ifeeder to be reviewed No Yes - No No -
2. Zone-III setting of 220KV Malanpur-Auraiyafeeder to be reviewed
Yes Yes - No No -
3. Providing of DG set Yes No - YES No DG SET AREIN PROCESS OF DELIVERY ON RECEIPTWILL BE COMMISSIONED SHORTLY
4. DC leakage in 110V DC system to be removed Yes Yes - No No -
5. GPS time synchronising to be extended toTransformer panels
Yes Yes - No No -
6. Providing of NIFPS on 160MVA 220/132KVTransformer-II
Yes No - YES NO - Procurement approval is in process
7. 220KV Bus Bar protection to be taken intocircuit for tripping
Yes Yes - No No -
8 Earth resistance of 20 and 40MVA transformerpits are not taken
Yes Yes - No No -
1. SSRR3V scheme on 132KV Bhind feeder to bereplaced Yes Yes - Yes Yes -
2. 220KV and 132KV feeder DPRs Zone-II & IIIsettings to be reviewed
Yes Yes - No No -
3. DC leakage in 110V DC system to be removed Yes Yes - No No -
4. GPS time synchronising facility to be extendedto 132KV Bhind,Seondha feeder and 160MVA BBLTransformer panels
Yes Yes - No No -
5. Providing of NIFPS on 160MVA 220/132KVTransformer-II No No - YES NO - Procurement approval is in process
6. 220KV Bus Bar protection scheme to be takeninto circuit after configuration of new 160MVABBL transformer
Yes Yes - No No -
1. 220KV Bus Bar scheme to be provided Yes Yes - Yes Yes - comissioned on dt.09/02/152. 160MVA TransformerI & II panels aresynchronised with GPS system, other panelsneeds to be synchronised
Yes Yes - No No - --
3. Oil temp. indicator is not available in 20MVATransformer
Yes Yes - No No - --
4 Earth resistance meaurement to be done Yes Yes -- No No - --5. Zone-II & III settings of DPRs of 220KVPGCIL,132KV Arniya feeders to be checked
Yes Yes -- No No - --
1. CT junction Box earthing in 132KV Bays to bestrengthen
Yes Yes -- No No -
2. 220KV and 132KV CB Marshalling Box earthingto be checked and strengthen
Yes Yes -- No No -
3 IOC feature in Differential and DPR relays to beenabled from reliability point of view
Yes Yes -- No No -
4. Over fluxing alarm and Trip time settings maybe verified and corrected
Yes Yes -- No No -
8220KV S/SMalanpur
220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
01-05-13 to02-05-13
9220KV S/SMehgaon
220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
29-04-13 to30-04-13
10220KV S/SShujalpur
220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
24-04-13 to25-04-13
11220KV S/S
Hoshangabad220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
08-05-13 to09-05-13
Page 3 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. AREVA make 220KV CB marshalling Boxes arenot properly earthed
Yes Yes -- No No -
2. Minor DC leakage found in 110V DC source-II Yes Yes -- No No -
3. Five nos DPRs (220KV Handiya-I&II,Barwaha,Sarni-Iii and Transfer B/C) are not timesynchronised with GPS
Yes Yes -- No No -
4. Auto reclosed feature is to be madeoperational
Yes Yes -- No No -
5. LBB and Bus Bar protection scheme have to betaken in to circuit
Yes Yes -- No No -
6. H.Set feature of Differential relays to beenabled
Yes Yes -- No No -
1. GPS is installed but not functioning, to betaken into service
No No -- YES No - Procurement involved
2. 220KV Bus Bar protection scheme is ASEAmake needs to be replaced with numericalscheme
No No -- YES YES - New GE make BB scheme commissioned (date ofservice 15.09.2014)
3. Providing of DG set Yes Yes -- YES Yes - Completed4 Numeric DPR on 220KV Jetpura feeder to beprovided
Yes Yes -- No No -
5 DTOC setting of Transformers may be reviewedwith latest fault level and CT ratio
Yes Yes -- No No -
1. GPS is installed but intermittent outage of GPShas been reported, needs to be discussed withmanufacturer
Yes Yes -- No No -
2. Uniformity in settingds of both 160MVAtransformers may be reviewed
Yes Yes -- No No -
3. Rajgarh-II DPR relay setting to be reviewed forPhase/Ground Impedance for Zone-III
Yes Yes -- No No -
4. Providing of DG set Yes No - YES Yes - DG Set Received. Commissioning under Progress
5 V/F protection in any of Differential relay on132/33KV Transformers not enabled
Yes Yes - No No -
1. Some numerical relays are not timesynchronised with GPS
Yes Yes - No No -
2. 220KV Bus Bar protection scheme is ASEAmake needs to be replaced with numericalscheme
No No - YES YES -
3. V/F setting for 3x40MVA, 63MVA ,40MVA isnot enabled
Yes Yes - No No -
4. REF is not enabled in 220KV and 132KVTransformers, to be enabled
Yes Yes - No No -
5 LBB protection for 220KV Class Transformers tobe commissioned
Yes Yes - No No -
6. Providing of DG set Yes Yes - YES YES - Completed
12 220KV S/S Itarsi 220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
06-05-13 to07-05-13
13220KV S/S South
Zone Indore220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
22-04-13 to23-04-13
14220KV S/SPithampur
220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
24-04-13 to25-04-13
152220KV S/S
Barwaha220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
26-04-13 to27-04-13
Page 4 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. GPS system for relay time synchrinisation is outof order
Yes Yes - No No -
2. Automatic Fire Protection System( NIFPS) tobe installed on all Transformers
Yes Yes - No No -Matter is under consideration ,however forsingle phase units scheme is not feasible.
3. Fire extinguishers are available but to be placedat appropriate locations as per requirement.
Yes Yes - No No -
4. Air Conditioning system should be provided inthe Control Room
Yes No - YES NO - Matter is under consideration.
1 Bus Bar protection system is provided but is inalarm mode only.
Yes Yes - No No -
2. 110V DC System is having earth leakageproblem
Yes Yes - No No -
3. Automatic Fire Protection System (NIFPS)to beinstalled on all Transformers
Yes No - YES NO - Procurement approval is in process
4. Synchronising scheme must be provided asmany Hydel Generators are connected to the220KV and 132KV Bus.
Yes No - YES NO - NIT issueed & in process
5. Lighting Visibility in the Control Room shouldbe increased
Yes Yes - No No -
6. Fire extinguishers are available but to be placedat appropriate locations as per requirement.
Yes Yes - No No -
7. REF feature in 160MVA CGL is not enabled. Yes Yes - No No -
8. Load dropping scheme on Transformers mustbe connected.
Yes Yes - No No -
1. GPS system is available but the relays are notconnected to it.
Yes Yes - No No - -
2 Bus Bar and LBB protection of B-90 Bus Barprotection scheme is not in service due to Y phaseCT module defect.
Yes Yes - No No - Put back in service
3 Earth leakage problem in 110V DC system isthere.
Yes Yes - No No - -
4. REF feature in 160MVA BHEL is not enabled. No No - Yes No - NCT Required
5. Automatic Fire Protection System( NIFPS) tobe installed on 160MVA AREVA Transformer
Yes No - Yes No - Procurement approval is in process
6. REF protection is not available on 160MVABHEL transformer
Yes No - Yes No - NCT Required
1. Oil leakage observed from 33KV TertiaryBushing Turret of BHEL Transformer
Yes Yes - No No -
2. Fire extinguishers are not available at ControlRoom
Yes Yes - No No -
3 Providing of Emergency light in Control room Yes Yes - No No -
4 Internal panel cabeling/Wiring of Controlpanel is meshed
Yes Yes - No No -
16 220KV S/S Jabalpur 220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
24-04-13 to25-04-13
17 220KV S/S Rewa 220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
29-04-13 to30-04-13
18 220KV S/S Satna 220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
01-05-13 to02-05-13
19 220KV S/S Damoh 220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
06-05-13 to07-05-13
Page 5 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. GPS system is not connected with all relays Yes Yes - Yes Yes -
ABB MAKE NUMERICAL RELAY DOES NOTHAVE PORT FOR SYNCHRONIZATION WITHGPS SYSTEM. MATTER IS DISCUSSED WITHM/S ABB. FOR ENABLING FEATUREREQUIRED ADDITIONAL PORT ONCHARGEABLE BASIS WHICH IS IN PROCESS.
2. 48V Battery Charger is working in only Boostmode.
YES Yes - No No - Float mode is also taken in service
3. Automatic Fire Protection System (NIFPS)to beinstalled on both Transformers
Yes No - YES NO - Procurement approval is in process
4. 220KV Bus Bar scheme to be provided Yes YES - NO NO -
21 220KV S/S Barod 220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
24-04-13 to25-04-13
1. GPS system is available but some relays arenot connected to it.
Yes Yes - NO NO - All relays connected
1. GPS system is available but some relays arenot connected to it.
Yes Yes - NO NO - All relays connected
2. 220KV Bus Bar scheme to be provided Yes Yes - YES YES - commissioned3 V/F protection in any of Differential relay on132/33KV Transformers not enabled
Yes Yes - NO NO -
4 DTOC setting of Transformers may be reviewedwith latest fault level and CT ratio
Yes Yes - NO NO - corrected
5. Float mode of 110V DC Charger is defective Yes Yes - NO NO - Float mode is also taken in service
6 In 220KV Julwaniya-Omkareshwar, Zone-IIItime setting is 800ms.It is not programmable aspush buttons are not working and relaycommunication software is not available. It maybe rectified soon.
Yes Yes - NO NO - corrected
1. GPS system is available but some relays arenot connected to it.
Yes Yes - No No - All relays connected
2. 220KV Bus Bar scheme to be provided Yes Yes - YES Yes _ New scheme commissioned
3. Float mode of 110V DC Charger is defective Yes Yes - No No - Float mode is also taken in service
24220KV S/S Indore-II
Jetpura220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
08-05-13 to09-05-13
1. Time synchronisation system is available withGPS, Its connectivity was made with all 220KVDPR/Differential relays. As this has createdproblem in functioning of DPR/Differential ralays,time synchronisation system is disconnected.Rectification of the problem and connectivity oftime synchronisation system with all the relays isto be done.
Yes Yes - No No - Problem rectified &all relays connected.
25 220KV S/S Ujjain 220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
26-04-13 to27-04-13
1. Time synchronisation system is available withGPS system, its connectivity is made with few220KV & 132KV relays, Connectivity for the rest ofthe system is to be done.
Yes Yes - No No - All relays connected
20 220KV S/S Sagar 220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
09-05-13 to10-05-13
22220KV S/SJulwaniya
220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
08-05-13 to09-05-13
23 220KV S/S Nimrani 220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
06-05-13 to07-05-13
Page 6 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. Time synchronisation system is available withGPS system, its connectivity is made with all220KV & 132KV DPR/Differential relays. Itsconnectivity with Bus Bar Relay B-90 is to be done.
Yes Yes - No No - Done
2. CT sec. core meant for back up protection isalso used for Bus Bar protection for number of220KV bays.For Bus Bar protection scheme PSclass of CT Sec core is to be used.
Yes Yes - No No -
1. 220KV DC system voltage have been checkedw.r.t. (+ Ve) to earth=136V, (-Ve) to Earth=89V,and to be rectified
Yes Yes - No No - Rectified
2. 220V DC Source I & II mixing possibility is thereand to be checked.
Yes Yes - No No - Checked no DC source mixing
3. Float charger of 220V systemis not working inboth chargers and presently chargers are workingin Boost charging mode.
Yes Yes - No No -Float mode is made operational in both thechargers
4. Illumination in AC/DC room is very poor andsame to be rectified
Yes Yes - No No -
5. All 400KV and 220KV line relays are numericalexcept Main-Irelay of 400KV Nagda-Indore, whichhas been installed and has to be connected.
Yes Yes - No No - Taken in service
6. Separate event logger for S/S is not availableand needs to be provided.
Yes Yes - YES Yes - Event logging facility commissioned in SCADA
7. Directional E/F features is to be enabled onfollowing feeders,400KV Main-II Relay (GE D60),400KV ISP Main-II (ABB REL 521) and 400KVRajgarh I & II ( Alstom make EPAC 3000relay is tobe replaced by SEL 311C relay and feature has tobe enabled soon)
Yes Yes - No No -
8. 25MVAr 33KV Reactors installed on Tertiarywinding of ICT-II and ICT-IIIre out of order sincelong time.
Yes Yes - No No - Taken in service
26 220KV S/S Ratlam 220KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
06-05-13 to07-05-13
27 400KV S/S Nagda 400KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
17-01-13 to18-01-13
Page 7 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. Tertiary Reactor of 315MVA Tr-I & II are notbeing taken in service due to high Tan deltavalues of Bushings, which should be replaced andreactors should be taken in to service.
Yes No - YES NOUnder Process HOWEVER 315MVA Tr-I ISTAKEN OUT OF SERVICE PERMANENTLY.
2 On 400KV side Bus Bar relay make EE type FACis electromagnetic type relay and it is very oldand obsolete. Its spares are not available,Thisscheme may be replaced with the numerical BusBar protection scheme.
Yes Yes - YES YES -New GE make BB scheme commissioned(date of service 03.11.2014)
3. REF protection of 315MVA EMCO Tr-IV is keptunder observation , which may be taken in toservice.
Yes Yes - No No - Taken in service
4 220V DC Charger make Statecon iscommissioned but not taken into service due tosome problem. It should be rectified and takeninto service.
Yes Yes - No No - Taken in service
5. Additional DC distribution Board is availableshould be taken into service to separate the DCdistribution to individual feeders.
Yes Yes - No No - Taken in service
6 GPS time synchronisation system is available ,Relays of 315MVA Transformers I,II & III areconnected. All the relays of other feeders andTransformers are to be connected.
Yes Yes - No No - All relays connected
7. Tripping/Closing time of 400KV Itarsi-I & II andAsoj-I & II CBs are not recorded.Same may becollected from PGCIL and update the record.
Yes Yes - No No - RECORDED
8. Zone-III reach setting of 400KV Asoj-I & iifeeders are given as 120% of protected line (31.23Ohm, Sec. value) Which is inadequate as backupzone protection. The time delay setting for Zone-III is given as 1000mSec.in all PGCIL feeders.Samemay be reviewed in accordance with the CBIPguidelines and uniformity of settings adopted.
Yes Yes - No No -
9. No DC leakage observed, but mixing of Dcsource-I & II dected.It should be rectified.
Yes Yes - No No - Rectified
1. The GPS system not available . No No - YES NO - under process
2. The autoreclosure scheme for 220 KVPipariya and 220 KV Narsingpur has to becommissioned.
No No - YES NO - under process
3. Metaling of yard is not done. No No - YES NO - under process
28 400KV S/S Indore 400KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
17-01-13 to18-01-13
Cont…28
400KV S/S Indore 400KV
Internal ProtectionAudit party
compirising ofrepresentatives ofState Utility and
Power Grid
17-01-13 to18-01-13
1 Chichli 220
Team of engineersfrom various
entities constitutedby SLDC
13.03.15
Page 8 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1.The220V 300AH (make:Exide,DOC:03-10-2007) battery set & battery charger havecompleted their useful life & needs to bereplaced.
Yes No - Yes No - Battery set received and commissioned
2. The C&R panel of 220KV JBP 1,2 are needto be replaced by integrated simplex panels orthe existing back up Electromechnical relaysshould be replaced by numerical relays.
Yes No - Yes No - under process
3. The work of 220KV Main bus -II is underprogress and would be commisioned verysoon.
Yes Yes - No No -
4. The GPS system sands make is available &found out of service due to ongoing civil worksin the substation.
Yes Yes - No No -
1. Electromechnical and electrostatic back upO/C & E/F relay of 220 KV JBP 1 & 2 feederand 160 MVA BHEL & CGL Xmer to bereplaced by numerical back up O/C & E/Frelay
Yes Yes - YES Yes - Tender is under process of finalisation
2. 220 KV Main bus -II is not availble. No No - YES NO -Since beginning this substation isconstructed with approved layout of1M+1A
3. The GPS system sands make is availableand connected except 220 KV JBP 1 & 2feeder.
Yes YES - No No - GPS connected
1. Fire protection system is not available in220/132/33 KV, 160 MVA Transformer No. I(Make – Areva)
Yes No - Yes No - Procurement approval is in process
2. LBB & Bus Bar protection scheme notcommissioned. However control panel for thescheme is available
Yes Yes - No No - Scheme commissioned
3. Auto reclosure not in service for 220 KVChichli & 220 KV Narsinghpur feeders & notcommissioned for 220 KV Itarsi feeder No. I &II.
Yes Yes - No No - Commissioned
4. DC Earth leakage is observed in 110 V DCsystem. –Ve bus is earthed Yes Yes - No No - earth leakage attended
5. GPS system of Sands make is available,but not connected in 220 KV Chichli, 220 KVNarsinghpur & 220/132/33 KV 160 MVAtransformer No. II. (Port is available on relaybut cabling is to be done.)
Yes Yes - No No - GPS connected
6. Load dropping scheme is not available Yes Yes - No No - To be connected shortly
7. Metalling in yard of 160 MVA, BHEL Maketransformer No. II is not available / to be done No No - Yes No - Retendering of work is being done
8. Time delay settings & reach settings ofzone 2, zone 3 & zone 4 in 220 KV feeders areto be reviewed and corrective measures are tobe taken.
YES Yes - No No - Setting revised
2 SUKHA 220
Team of engineersfrom various
entities constitutedby SLDC
12.03.2015
3 NARSINGPUR 220
Team of engineersfrom various
entities constitutedby SLDC
13.03.2015
4 PIPARIYA 220
Team of engineersfrom various
entities constitutedby SLDC
16.03.2015
Page 9 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. Event sequence recorder is not available. Yes Yes - YES NO Event logging facility commissioned in SCADA
2.time synchronization and GPS facilitiesavailable but not in working condition YES NO - No No - MATTER IS under correspondance with firm.
3.synchronizing trolley not available. NO No - YES NO NIT issueed & in process4.220 kv Bus bar protection is connected inalarm mode only complete protection is yet tobe taken in service.
Yes Yes - No No - BUS BAR PROTECTION TAKEN INTO SERVICE
5. In Bina II circuit Auto reclosing facility is notin service due to defect in numerical relay. No NO - YES YES - -
6.220 kv Bus - Tie circuit breaker is notworking . No No - YES YES -
7.Numerical Relay is not available in 220 kvBus Coupler. No No - YES YES -
8. Zone -4 protection in all Distance protectionRelay are not commissioned. YES YES - No No -
9.Load Drop scheme are not available . YES YES - No No - -
10.REF protection is not available in both the220 kv transformer. No NO - YES No -
FEASIBILITY FOR REF PROTECTION TO BECHECKED
1 Event sequence recorder is not available. Yes No _ Yes No - Event logging facility commissioned in SCADA
2.Time synchronization and GPS facilities isnot available. No No _ Yes No - In process of procurement
3.synchronizing trolley is not available. No Yes _ No No _ NIT issueed & in process4.220 kv Bus bar protection is available butnot commissioned. No No _ Yes Yes _ Bus Bar Scheme commissioned
5.220 kv Bina PGCIL circuit breaker (telkmake)is out of service. No No _ Yes Yes _ New CB commissioned
6. 132kv capacitor bank circuit breaker is outof service. Yes Yes _ No No _
7.In 110 DC system ,earth leakage isobserved. The same needs to be rectified. Yes Yes _ No No _ _
1. Event sequence recorder is not available. No No - Yes No - Event logging facility commissioned in SCADA
2.Time synchronization and GPS facilities isavailable.Connected in 220 kv Shivpuri -1 andShivpuri-II .Need to be connected with inbalance feeders.
Yes Yes - No No -
3.synchronizing trolley not available. Yes No - Yes No - NIT issueed & in process4.In 110 V DC Source-II ,earth leakage isobserved. The same needs to be rectified. Yes Yes - No No -
5.220 kv Bus Coupler DPR relay (GE,D60)Found defective. Yes Yes - No No - DPR Relay replaced on date - 22.06.15
6.110V DC supply is looped from 160MVAtransformer C & R panel.separate DC supplyneed to be provided from DC distributionpannel.
Yes Yes - No No - Separate DC supply provided from DCdistribution panel
7. 160 MVA (AREVA MAKE)transformer,windiging Temperature indicator found faulty. Yes Yes - No No - -
5 GUNA 220
Team of engineersfrom various
entities constitutedby SLDC
12 &13.03.2015
6 SHIVPURI 220
Team of engineersfrom various
entities constitutedby SLDC
14 &15.03.2015
7 SABALGARH 220
Team of engineersfrom various
entities constitutedby SLDC
16 &17.03.2015
Page 10 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1) 160 MVA AREVA 5th harmonic setting is 25% to be revised to 40 %. Second harmonic torevised to 15 %.
Yes Yes - No No -
2) 132 KV Khachrod feeder length is 15 KM inDPR MHO setting is selected to be revised toQUAD for PH-G Zone-I.
Yes Yes - No No -
3) 132 KV Mahidpur feeder E/F TLS setting is0.15 to be revised to 0.25. Yes Yes - No No -
4) LBB of 160 MVA CGL make xmer on 132KV side are not in service . Yes Yes - YES YES - -
5) GPS is provided but not connected torelays. Yes No - YES NO - GPS being procured
6) Load dropping scheme is not provided on160 MVA Xmers. Yes Yes - No No - -
1. Relay setting calculation of 220 KV DamohLine and 132 KV Feeders of S/S has beenchecked and found that Zone-3 setting of 220KV Damoh line is on higher side, the samemay be reviewed as per recommendation ofCBIP.
Yes Yes - No No -
2. Auto-reclosing Scheme has not beenprovided in 220 KV Damoh Line. The samemay be provided as per recommendation ofCBIP.
Yes Yes - No No -
3. Carrier Protection of Permissive UnderReach (PUP) are provided for 220 KV DamohLine
Yes Yes - No No -
4. One DC source for 110V & 48V each isprovided in 220 KV sub station. Healthinessand earth leakage has been checked andfound in good condition. However, battery setis found very old and required for replacement.Year of manufacturing and year of installationof battery set is mentioned as under
-
Description: 110 Volt Battery No No - Yes No - Battery receivedDate of Mfg : NA -Date of commissioning : 15.08.2006 -Description: 48 Volt Battery No No - Yes No - In processDate of Mfg : 2002 -Date of commissioning : 15.08.2006 -
5. GPS is available and time Synchronizationof 160 MVA Xmer-2 is not commissioned. No Yes - No No -
6. DR’s facility is inbuilt feature of numericalrelay provided for Damoh Feeder & Buscoupler and 160 MVA Xmers.
Yes Yes - No No -
7. Synchronizing trolley is not available Yes No - Yes No - NIT issueed & in process
8 NAGDA 220
Team of engineersfrom various
entities constitutedby SLDC
16.04.2015
9 TIKAMGARH 220
Team of engineersfrom various
entities constitutedby SLDC
13.03.2015
Page 11 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
8. Features to be disabled in numerical relayare not found during checking Yes Yes - No No -
9. Bus bar protection scheme of 220 KV isfound out of circuit due to defective module.The same may be put under service at theearliest. Time Synchronization may also beprovided with GPS. Further, B Phase PotentialTransformer (PT) of 220 KV Main Bus -2 is notavailable. Due to this reason, Main Bus -2 cannot be charged during any emergency. So thatabove PT may be installed at the earliest.
Yes Yes - No No -
10. Load drop scheme is not available Yes Yes - No No - In process
1. Testing of DPR for 220 KV lines is carriedout in yr.2007.Relay testing is required. Yes Yes - No No - -
2. GPS System of SANDS make is availablewith 02 nos of spliters, each for 10 Nos relays.It has developed some defect and matter isunder correspondence with the firm.
Yes Yes - No No __ __
3. Synchronization trolley is not available NO NO - Yes No __ NIT issueed & in process4.Load dropping scheme for x-mer is notavailable. Yes Yes - NO NO - __
5. DG Set is not available at the S/s. Yes No - Yes No __ DG SET AREIN PROCESS OF DELIVERY ON RECEIPTWILL BE COMMISSIONED SHORTLY
Cont…9 TIKAMGARH 220
Team of engineersfrom various
entities constitutedby SLDC
13.03.2015
10 SEONI 220
Team of engineersfrom various
entities constitutedby SLDC
11.03.15
Page 12 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. Auto-reclosing is provided in 220 KV SatnaLine. However, setting of single phase DeadTime is found 0.7 S in place of 1Sec as perrecommendation of CBIP. Setting of the samemay be reviewed accordingly
Yes Yes - No No -
2. Carrier Protection of Permissive UnderReach & Directional Earth Fault (PUP & DEF)are provided for 220 KV Satna Line.
Yes Yes - No No -
3. One DC source for 110V & 48V each isprovided in 220 KV sub station. Healthinessand earth leakage has been checked andfound in good condition. However, battery setis found very old and required for replacement.Year of manufacturing and year of installationof battery set is mentioned as under
Description:110 Volt Battery NO NO - YES No -Battery Received. Commissioning underprogress
Date of Mfg : 2006Date of commissioning: 17.10.2007Description:48 Volt Battery NO NO - YES No - In processDate of Mfg : 2002Date of commissioning: 19.10.20074. Numerical Relay of 160 MVA, 220/132KVand Relay of Feeders of 132 KV are notconnected with GPS, the same may beconnected with GPS
Yes Yes - No No -
5. Synchronizing trolley is not available Yes No - No No - NIT issueed & in process6. Features to be disabled in numerical relayare not found during checking Yes Yes - No No -
7. Time synchronization is required to be donewith existing GPS Yes Yes - No No -
1. Synchronization trolley is not available No No - Yes No - NIT issueed & in process2. Load dropping scheme is to be provided on100 MVA x-mer of CGL make also withfollowing: 110% of full load on x-mer setting: - Trip to132 KV Khapasami Feeder & 132 KVChhindwara Feeder.
Yes Yes - No No - Load dropping scheme connected
3. DG Set is not available at the S/s. Yes Yes - Yes Yes - completed
11 CHHATARPUR 220
Team of engineersfrom various
entities constitutedby SLDC
12 &13.03.2015
12 SARNI 220
Team of engineersfrom various
entities constitutedby SLDC
14.03.2015
Page 13 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. 110 V & 48 V Battery sets werecommissioned in 2005. Replacement of 110 V&48 V battery set are required
No No - Yes Yes - -
2. Synchronization trolley is not available No No - yes No - Not required3. 220 KV Bus-Bar Protection panel isavailable at the S/s but not commissioned. No No - Yes No 31.12.2016 due to control room extention work ,
commissioning is held up
4. DG Set is not available at the S/s. Estimatefor 25 KVA DG Set is sanctioned, recently No No - Yes No - DG SET AREIN PROCESS OF DELIVERY ON RECEIPT
WILL BE COMMISSIONED SHORTLY
1. GPS System of SANDS make is availablefor 10 Nos relays. IRIG B Port is not availablein ABB make relays. Up gradation/ addition isrequired for unconnected relays.
No No - Yes No - In process
2. Synchronization trolley is not available No No - YeS No - NIT issueed & in process
3. DG Set is not available at the S/s. YES No - YES No - DG SET AREIN PROCESS OF DELIVERY ON RECEIPTWILL BE COMMISSIONED SHORTLY
1. Synchronization trolley is not available. No No - YeS No - NIT issueed & in process2. Load dropping scheme is not provided YES YES - No No - Load dropping scheme connected
3. DG Set is not available at the S/s. YES No - YES No - DG SET AREIN PROCESS OF DELIVERY ON RECEIPTWILL BE COMMISSIONED SHORTLY
1) 220 kv Daloda-Nagda feeder Zone II settingis 105 % should be minimum 120 % ofprotected line.
YES YES - No No -
2) 220 KV Daloda-REGPL feeder(RadialFeeder) Zone-1 setting 100% of protected lineto be revised to 120 % of protected line.
YES YES - No No -
3) Bus-Bar protection is commissioned. 220KV LBB Protection has been provided on busbar protection panel. Bus bar Protection Panelis not in service to be taken in service. Waitingfor through fault on 220 KV feeder.
YES YES - No No -
4) GPS is not provided. No No - Yes NO - In process5) Load dropping scheme is not provided on160 MVA Xmer. YES YES - No No -
6) Over flux setting of 160 MVA is 120 % isalarm and 140 % trip. To be revised 110 %Alarm and trip to 120 %
Yes YES - No No -
1. Synchronizing trolley is available but notused till date. NO NO - No No - In process
2. Carrier protection panel at remote end is notavailable. NO NO - YES NO To be Procured
3. Battery bank was commissioned on16.11.2012. Battery charger was set off forabout 45 Min voltage dropped from 110 V to106 V. Leakage problem in almost all batteriessince installation.
YES YES - YES No - In process
4. GPS is not available. Bus coupler DPRoscillography triggered through each feedermaster initiation should be provided till GPS isnot available so that fault initiation can beidentified.
NO NO - YES NO under consideration with higher off.
13 PANDURNA 220
Team of engineersfrom various
entities constitutedby SLDC
13.03.2015
14 CHHINDWARA 220
Team of engineersfrom various
entities constitutedby SLDC
10 &12.03.2015
15 BETUL 220
Team of engineersfrom various
entities constitutedby SLDC
15.03.2015
16 DALODA 220
Team of engineersfrom various
entities constitutedby SLDC
15.04.2015
17 ANUPPUR
220
Team of engineersfrom various
entities constitutedby SLDC
17.03.2015
Page 14 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
5. Bus bar protection is not commissioned sofar. Recently supplied. YES YES - No No - Bus Bar scheme commissioned on Dt. 09-
10-15
6. DG set not available. YES NO - YES NO - DG SET AREIN PROCESS OF DELIVERY ON RECEIPTWILL BE COMMISSIONED SHORTLY
7. LBB protection scheme at 132 KV notcommissioned. YES YES - No No - -
8. Direct trip scheme is not available in twofeeders Kotmikala 1 & 2. YES NO - No No - In process
9. Load drop not available. YES YES - No No - In process10. Broken conductor feature(negativesequence) not used. YES YES - No No - -
11. DR trigger for fault current sharing shouldbe configured. YES YES - No No - -
12. SF6 & air pressure status on the panel. YES NO - YES YES -13. Relay fault recording menu should beprovided to operating staff. YES YES - No No -
14. Auto reclose scheme is kept off.Recommended to be started. YES YES - No No - -
15. DC voltage (110 V and 48 V) metersshould be provided in control room. No No - YES YES -
16. Annunciation front panel is not having anyindication for auto-reclose operation. YES YES - No No - -
17. Thermo-vision is out of order and regularreadings are not taken on monthly basis. YES YES - No No - -
18. Under-frequency relay supplies are notcommissioned. YES YES - No No - -
19. Df/dt relay is not available. YES NO - NO NO not included in scheme20. Group selection through input energisationshould be provided. YES YES - No No - -
21. Over current /EF relays settings should bedirectional which are non-directional atpresent.
YES YES - No No - -
22. Transformer tertiary circulating current CTis not connected to panel for Circulatingcurrent protection.
YES YES - No No - -
23. Float charger is not in working condition. YES YES - No No - -
24. At 160 MVA transformer REF protection isnot in service. YES YES - No No - -
25. At 40 MVA transformer HV & LV, REFprotection is not in service. Yes NO - No NO Not required
17 ANUPPUR
220
Team of engineersfrom various
entities constitutedby SLDC
17.03.2015
Cont…17 ANUPPUR
Page 15 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1) 220KV Ratlam-I DPR GE D-60 healthy andtrouble both LEDs are glowing. Trouble LED isdue to its own internal Battery fail signal. Thetrouble is to be attended so that if otherproblem arises it may be detected.
NO No - Yes Yes - -
2) Trip CKT Supervision relay of 220 KV TBCY phase TC_II is defective (preclose). Yes Yes - NO NO -
3) Two sets of 110 V battery sets are there.DOC are 16/1/13 & 4/2/2007 respectively.Battery sets gravity and voltages are ok. 48 Vbattery set DOC is 2/6/2005. The condition of4 nos. cells is not good (gravity 1.160).
No NO - Yes Yes -
4) A/R and carrier aided tripping not providedin 220 KV Ratlam-I & II feeder. Yes Yes - No No -
5) GPS is provided but not in service. Yes Yes - No No -6) In DPR mho characteristics is used forfeeder which are short in length(i) 132 KV Goutampura-II I length 24KmSuggested to use QUAD characteristic for Ph-G Zone-I
Yes Yes - No No - -
7) In differential relays of 160 MVA AREVAand 100 MVA AREVA Transformer 5thharmonic restrain setting is 25 % to be revisedas per guidelines.
Yes Yes - No No - -
8) Load dropping scheme is not provided on160 MVA Xmer –I & II. Yes Yes - No No - -
1) 220 KV DEWAS feeder bay is having onlyone CVT in R-ph. One additional CVT isrequired in other phase for PH-PH coupling.
Yes No - Yes No 31.09.16 In process
2) 1x110 V and 1x48 V are commissioned inJUNE-2007. Both required replacement. No No - Yes Yes - -
3) In battery room Exhaust Fan is notprovided. Yes Yes - No No - -
4) A/R is commissioned but not in service forboth feeders. Yes Yes - No No - -
5) GPS is provided but not in service. Yes Yes - No No - -6) In DPR mho characteristics is used for boththe CKTs but QUAD characteristics is requiredas line length is less than 50 Km.
Yes Yes - No No - -
7) 220 KV Indore feeder ZONE-2 reach is100% of protected line + 100 %Short lineadopted, its revision is required as per CBIPguidelines i.e. 120% of line to be protected.
Yes Yes - No No - -
8) REF protection is not provided on 100MVA220/33-33 KV Xmer as the neutral CT is notprovided. By providing external Neutral CTscheme may be commissioned.
No No - Yes No 31.12.2016 Proposal Submitted to provided thisarrangment.
9) In DPRs PT FUSE FAIL. PSB/OSB notenabled. Yes Yes - No No -
06.04.2015
19 INDORE EAST(BICHOLI) 220
Team of engineersfrom various
entities constitutedby SLDC
12.03.2015
18 BADNAGAR 220
Team of engineersfrom various
entities constitutedby SLDC
Page 16 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
10) In 220 Kv DEWAS feeder carriers aidedtripping is not provided which is to beprovided.
NO No - Yes Yes -
1) REF protection is provided on 160 MVAXmer but presently not enabled which isrequired to be enabled.
Yes Yes - No No - -
2) REF protection is provided on 160 MVAXmer but presently not enabled which isrequired to be enabled.
Yes Yes - No No - -
3) 110 V, 200AH battery set is available. DOCis 17/06/2008. Battery sets gravity andvoltages are ok. 48 V, 300AH battery set DOCis 19/08/2007.
Yes Yes - No No - no any deficiency. Battery sets are inhealthy condition
4) A/R and carrier aided tripping not providedin 220 KV feeder. Yes Yes - No No - Completed
5) Bus-Bar protection is not commissioned. No No - No No - Turn key project to be completed by M/sShreem
6) LBB is provided on 132 KV Xmers but notprovided in 220KV Xmer/feeder. Yes Yes - No No - -
7) GPS is not provided. No No - Yes No - In process8) Load dropping scheme is not provided on160 MVA Xmer. Yes Yes - No No - -
9) In backup relay directional feature in notenabled for both 220 KV Xmer & feeder, whichis to be enabled as per the guidelines.
Yes Yes - No No - -
10) Timings for zone2 & zone3 is to bereviewed in accordance with the coordinationfor 220KV tapped line at Dhar substation end.
Yes Yes - No No -
11) In 40 mva Xmer I&II differential relay slope2 chosen is 90%, which is to be revised as perthe guidelines.
Yes Yes - No No -
1) 220 kv Transfer panel numerical relay is tobe provided.. YES YES - YES YES - -
2) REF protection in 160MVA-I CT is notprovided in neutral bushing hence REF notprovided.
YES NO - YES NO NEUTRAL BUSHING CT IS REQUIRED
3) 132 KV feeders INT-I & INT-II (4 & 5 Kmlength) mho setting of Zone-1 to be changedto QUAD (Ph-G).
YES YES - NO NO
4) AR not configured in both 220 KV Dalodaand Nagda feeder. NO NO - NO NO 31.12.2016
NO PROVISION IS PROVIDED IN C&RPANEL OF 220 KV DALODA PANEL , &AR RECLOSURE WILL BECONFIGURED UP TO NEXT MONTH
5) Trip circuit healthy of feeders found ok. Inold 220 KV C&R panels only one set of triphealthy LEDs are provided. Not available forTCH-II.
Yes Yes - NO NO - -
19 INDORE EAST(BICHOLI) 220
Team of engineersfrom various
entities constitutedby SLDC
12.03.2015
20 DHAR 220
Team of engineersfrom various
entities constitutedby SLDC
07.04.2015
21 NEEMUCH 220
Team of engineersfrom various
entities constitutedby SLDC
16.04.2015
Page 17 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
6) 110 V 600 AH and 48 V 300 AH chargersare very old (Yr of Mfg 1989) SHEETRONmake having float section defective andcharger is having fuses in load side(presentlynot in practice). Replacement of charger maybe considered.
YES Yes - YES Yes Completed
7) GPS is provided and not connected for Busbar protection panel. Yes Yes - No NO - -
8) Load dropping scheme is not provided on160 MVA-II Xmer. Yes YES - NO NO - -
1. Bus Bar Protection scheme available butnot commissioned. GE Make B-90 Bus barprotection scheme is under commissioningtherefore it is suggested that Zone-IV reachand delay of 220KV feeders can be revised tocover 220 KV so that it can operate in 200ms.
Yes Yes - NO NO - Commissioned
2. DG Set not available. Yes NO - Yes NoDG SET AREIN PROCESS OF DELIVERY ON RECEIPTWILL BE COMMISSIONED SHORTLY
3. 220 KV Bhopal feeder:- relay settingschecked and verified. The zone-III reach is tobe reviewed in accordance with LILO of 220KV
Yes Yes - NO NO - Completed
4. 132/33KV, 63 MVA X'mer-1:- relay settingschecked & verified. It is suggested to revisethe step-1 bias setting to 20% to make therelay more sensetive.
Yes Yes - NO NO - Completed
5.UE make electromagnetic back up relay is inservice for 63 MVA X'mer-II on 132KV side. Itis suggested to replace it by suitable relay. It isintimated that a static back-up relay has beenarranged for this replacement.
Yes Yes - NO NO - Completed
6. 132KV Vidisha-Gulabgunj Railway Traction-I&II:- this line is protected by Backup O/C &E/F relay as main protection DPR notprovided.
NO NO - Yes No - 2 No C&R panel for 132 KV feeder isbeing released
1. DF/DT relay not available. NO NO - Yes No 31/03/2016 Df/dt Relay Required,
2. 220 KV Rajgarh-Sujalpur PGCIL-II:- relaysettings checked and verified. It is found thatthe Zone-II reach is taken as 105% of theprotected line. It may be due to the very shortline in the next section of PGCIL.
Yes Yes - NO NO - Revised
3. 132/33 40MVA X'mer-II:- relay settingschecked and verified. The bias setting is takenas 30%. It can be revised to 20% to make itmore sensitive.
Yes Yes - NO NO - Revised
21 NEEMUCH 220
Team of engineersfrom various
entities constitutedby SLDC
16.04.2015
22 Vidisha 220
Team of engineersfrom various
entities constitutedby SLDC
07.04.2015
23 Rajgarh Biaora 220
Team of engineersfrom various
entities constitutedby SLDC
08.04.2015&
09.04.2015 Page 18 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
4. 220 KV Bus Bar protection commissionedrecently on date 06.02.2015. it is underobservation and taken in alarm mode. It isintimated that tripping shall be connected afterchecking performance on any through faultcondition.
Yes Yes - NO NO - Taken in service for Trip
5. DC leakage detected in 110 Volt DCsystem. DC -ive to earth value showing0.5volts it is intimated. It is intimated that ithas occurred recently already in notice,remedial action is already in process.
Yes Yes - NO NO - ATTENDED
6. DG sets is not available No NO - Yes NO - DG SET AREIN PROCESS OF DELIVERY ON RECEIPTWILL BE COMMISSIONED SHORTLY
7. it is suggested that Zone-4 reach and timedelay can be revised so as to cover 220KVbus only so that it can work as backup to busbar protection to operate in 200msec.
Yes Yes - NO NO - Revised
8. some of the relays are not synchronisedwith GPS, proper synchronization is to bearranged.
Yes Yes - No NO - -
1. ZONE 4 TIME SETTING PROVIDED 1000ms, HOWEVER IT SHOULD BE VERIFIEDAND REVISED AS PER CBIP GUIDLINES
Yes Yes - NO NO - Revised
2. GPS SYSTEM SANDS MAKE FAILSFREQUENTLY NEEDS RECTIFICATIONAND ITS RESTORATION AT THE EARLIESTFOR PROPER FUNCTIONING.
Yes Yes - NO NO - -
3. BATTERY ROOM SIZE IS NOTSUFFICIENT .NO SPACE FORMAINTENANCE PURPOSE AND UNSAFE,HENCE ACCOMODATING/INSTALLINGBATTERIES SUITABLY IN THE ROOM .
Yes Yes - NO NO -
4. 220 KV DC BATTERY FLOAT CHARGERIS NOT WORKING .CHARGING IS DONETHROUGH BOOST CHARGER ONLY ATLESS CURRENT. FLOAT CHARGER NEEDSTO BE MADE OPERATIONAL.
Yes Yes - No NO - -
5. NEGATIVE IS EARTHED IN D.C.SYSTEM, IT SHOULD BE RECTIFIED. Yes Yes - NO NO -
6. SYNCHRONISING TROLLY IS AVAILABLEBUT NOT IN WORKING CONDITION Yes Yes - NO NO - -
7. NO METALLING IS FOUND INSWITCHYARD. IT HAS BEEN INTIMATEDSINCE COMMISSIONING OF SUB-STATIONDATED 11.02.1998,METALLING NOT DONE.
No NO - Yes NO - Tender is under negotiation
23 Rajgarh Biaora 220
Team of engineersfrom various
entities constitutedby SLDC
08.04.2015&
09.04.2015
24 KATNI 220
Team of engineersfrom various
entities constitutedby SLDC
06.04.2015
Page 19 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
8. FIRE PROTECTION SYSTEM IS NOTAVAILABLE IN BOTH TRANSFORMERSEACH OF 160 MVA, 220/132 KV . ITSHOULD BE PROVIDED FOR SAFETYPURPOSE.
No NO - Yes NO - In process
1. A/R is disabled, the same should beconfigured and taken in service. Yes No - No NO -
PGCIL is presently not agree due to stresson ICT's. They have saught consent ofPGCIL Vadodara H.Q.
2. Directional feature is not available in O/CE/F relays of 220 KV & 132 KV feeders. No No - Yes No - In process
3. 110 V & 48 V Battery sets werecommissioned in 2004. The Battery sets arevery old. It requires capacity test /replacement.
No No - Yes No - In process
4. GPS system of SANDS make isavailable. It is connected to differential relaysof 3x40 MVA x-mer. It is to be connected withrest of the relays. GPS system is also showing‘GPS fail’ LED. Time of GPS unit is notmatching with connected relay. GPS systemmay be got attended.
Yes Yes - No No - GPS is repaired by firm
5. Synchronization trolley is not available. Yes No - Yes No - NIT issueed & in process
6. No multiple earthing of CT secondarycircuit is there at the substation. It is checkedby removing earthing CT secondary star pointat CT junction box of 220 KV B/C.
Yes Yes - No No -
7. LBB scheme is not provided. No No - Yes No - LBB relays & tripping relays are beingarranged
8. Load dropping scheme is not available. No No - No No - In process
9. DG set is not available. No No - Yes No - DG SET AREIN PROCESS OF DELIVERY ON RECEIPTWILL BE COMMISSIONED SHORTLY
10. Electromechanical relays are used forback up protection (Except 132 KV Badgaon). No No - Yes No - In process
11. In 220 KV CTs no separate core of PSclass is available for Bus Bar Protection. YES Yes - No No - -
24 KATNI 220
Team of engineersfrom various
entities constitutedby SLDC
06.04.2015
25 NEPANAGAR 220
Team of engineersfrom various
entities constitutedby SLDC
08.04.2015
Page 20 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. AUTO RECLOSE IS NOT ENABLED IN220 KV FEEDER RELAYS AND NECESSARYACTION SHOULD BE TAKEN FOR MAKINGIT ENABLE
Yes NO - No No - Work in progress.
2. ZONE-4 TIME SETTING IS TO BEREVISED, AT PRESENT 1000ms SETTINGPROVIDED AND TO BE SET AS PER CBIPGUIDELINE
Yes Yes - No No -
3. FIRE PROTECTION SYSTEM FOR 160MVA, 220/132/33 KV TRANSFORMER ISNOT AVAILABLE. IT NEEDS TO BEPROVIDED FOR SAFETY POINT OF VIEW.
NO No - YES NO - Procurement approval is in process
4. BATTERY SET COMMISSIONED ON06.06.08 & SERVED ITS USEFUL LIFE.STATION BATTERY NEEDS TO BEREPLACED.
No No - YES NO - In process
5. FLOAT CHARGER OF 110 V STATIONBATTERY & 48 V PLCC BATTERY IS NOTIN WORKING ORDER. PROBLEM SHOULDBE RECTIFIED FOR MAKING FLOATCHARGER OPERATIONAL.
Yes Yes - No No -
6. 220 KV S/S SIDHI CONNECTED TOAMARKANTAK THERMAL POWERSTATION THROUGH 220 KV AMARKANTAKFEEDER. HENCE, SYNCHRONIZATIONTROLLEY SHOULD BE PROVIDED.
Yes No - YES NO - NIT issueed & in process
1. GPS IS NOT AVAILABLE IN SUB-STATION, IT SHOULD BE PROVIDED FORRELAY TIME SYNCHRONIZATION.
No No - YES NO - In process
2. AUTO RECLOSE IS NOT ENABLED IN220 KV FEEDER RELAYS AND NECESSARYACTION SHOULD BE TAKEN FOR MAKINGIT ENABLE
Yes No - No No - Work in progress
3. ZONE-4 TIME SETTING IS TO BEREVISED, AT PRESENT 1000ms SETTINGPROVIDED AND TO BE SET AS PER CBIPGUIDELINE.
Yes Yes - No No -
4. FIRE PROTECTION SYSTEM FOR 160MVA, 220/132/33 KV TRANSFORMER ISNOT AVAILABLE. IT NEEDS TO BEPROVIDED FOR SAFETY POINT OF VIEW.
No No - Yes No - Procurement approval is in process
5. FLOAT CHARGER OF 110 V BATTERYCHARGER IS NOT WORKING, PROBLEMSHOULD BE RECTIFIED FOR TAKING ITINTO SERVICE.
Yes Yes - No No -
26 SIDHI 220
Team of engineersfrom various
entities constitutedby SLDC
09.04.2015
27 MAIHAR 220
Team of engineersfrom various
entities constitutedby SLDC
07.04.2015
Page 21 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. 220KV Bhopal-1 :- It is suggested to reviewthe zone-III setting in accordance with thechange in the line length at other ends. Atpresent it seems higher.
Yes Yes - No No -
2. 220/132KV, 160MVA X'mer-1:- The slope-1setting given as 30%. It can be revised to 20%to make the protection more sensitive.
Yes Yes - No No -
3. 132/33KV, 20MVA X'mer-1:- The slope-1setting given as 30%. It can be revised to 20%to make the protection more sensitive.
Yes Yes - No No -
4. Float charger of 110V Battery charger is notworking, requires rectification at earliest. Yes Yes - No No -
5. Some of the 220KV & 132KV CB timing isto be taken. It is suggested to carryout thetesting in coming maintenance schedule.if
Yes Yes - No No -
6.DG set is not available No No - Yes No - DG SET AREIN PROCESS OF DELIVERY ON RECEIPTWILL BE COMMISSIONED SHORTLY
1) A/R and carrier aided tripping notprovided in 220 KV feeders. YES YES - Yes No -
Out door equipments and protectioncoupler is required for 220 KV Bicholifeeder.
2) GPS is provided but not in service. YES YES - No No3) Partial negative D.C. leakage observed.Positive to earth voltage=87 volt and Negativeto earth =33 volts
YES YES - No No -
4) In backup relay directional feature in notenabled for both 220 KV X-mers & feeder,which is to be enabled as per the guidelines.
Yes YES - No No -
5) In 160 MVA TELK X-mer differential relayslope 2 chosen is 90%, which is to be revisedas per guidelines. High set settings & Fifthharmonic blocking setting also to be reviewedas per the guidelines.
Yes YES - No No -
28 BAIRAGARH 220
Team of engineersfrom various
entities constitutedby SLDC
06.04.2015
29 DEWAS 220
Team of engineersfrom various
entities constitutedby SLDC
08.04.2015
Page 22 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. Relay setting calculation checked.Setting verified with relay for 160 MVA x-er.SOTF, PSB and VT fuse fail features areenabled in DPRs.Setting for zone 3 may bereviewed to restrict reach not to cover nextvoltage level at far end of line.
Yes Yes - No No -
2. Direct trip and A/R are not in service.The same should be configured and taken inservice. The outdoor PLCC equipment are notavailable for 220KV Itarsi feeder-1.
No No - Yes No - work under progress
3. GPS system of SANDS make isavailable. It is connected to differential relaysof 160 MVA x-mer-1. It is to be connected withrest of the relays.Time of GPS unit is notmatching with connected relay. GPS systemmay be got attended.
Yes Yes - No No - GPS connected
4. Synchronization trolley is not available. No No - Yes No - NIT issueed & in process
5. Load dropping scheme is not available. Yes Yes - No No - Load dropping scheme connected6. DG set is not available. Yes Yes - Yes Yes - Completed7. Most of the backup relays are electromechenical type. No No - Yes No Numrical relays to be procured
1. FIRE PROTECTION FOR 220KV/132KV,160 MVA TRANSFORMER IS NOTAVAILABLE AND IT SHOULD BEPROVIDED.
No No - Yes No - Procurement approval is in process
2. AS SUCH KOTAR S/S IS CONNECTEDTO TONS HYDEL POWER STATIONTHROUGH 220 KV TONS FEEDER, HENCESYNCHRONIZING TROLLEY SHOULD BEPROVIDED AT THIS SUB-STATION. ATPRESENT SYNCHRONIZING TROLLEY ISNOT AVAILABLE.
No No - Yes No - NIT issueed & in process
3. GPS SYSTEM IS NOT AVAILABLE IN SUB-STATION. No No - Yes No - In process
4. FLOAT CHARGER OF 110 V AND 48 VBATTERY CHARGER ARE NOT WORKING/OUT OF SERVICE, PROBLEM SHOULD BERECTIFIED/ ATTENDED FOR MAKING ITOPERATIONAL.
Yes Yes - No No -
5. LBB PS VALUE IS FOUND HIGH (1.05). ITSHOULD BE COORDINATED PROPERLYAS PER GUIDELINE.
Yes Yes - No No -
6. ZONE-4 TIME SETTING IS TO BEREVISED, AT PRESENT 1000ms SETTINGPROVIDED AND TO BE SET AS PER CBIP.
Yes Yes - No No -
7. NEGATIVE SUPPLY IS EARTHED IN 110V D.C. SYSTEM, WHICH SHOULD BEREMOVED AT THE EARLIEST.
Yes Yes - No No -
30 HANDIYA 220
Team of engineersfrom various
entities constitutedby SLDC
09.04.2015
31 KOTAR 220
Team of engineersfrom various
entities constitutedby SLDC
08.04.2015
Page 23 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
8. IN 220 KV 160 MVA TRANSFORMER C&smake CSPC RELAY EARTH FAULT TMSSEEMS HIGH (1.0). IT SHOULD BEREVIEWED AND TO BE CORRECTED IFREQUIRED.
Yes Yes - No No -
1) REF protection is not provided on 160 MVAI, II & 63 MVA Xmer. Yes Yes - NO NO -
2) Numerical relays are provided for Mainprotection & found healthy in all bay . Featureof D60 relay (DPR) is used as a differentialprotection for 160 MVA Transformer No 1, itrequires replacement by other numericaldifferential relay to utilize other features likeREF etc.
No No - Yes Yes - -
3) Trip CKT Supervision relays are provided &indicating healthy condition. TCH Lamps foundoff for 16 MVA Xmer, 132 KV Kukshi –onelamp, 132 KV Inter Conn.-1 &2 one lamp,160MVA I & II 220 KV side
Yes Yes - NO NO -
4) 1x110 V and 1x48 V are commissioned inNov 2005& 2006 respectively. Both requiredreplacement being very old. In 110 Battery setone cell is out.
No No - Yes No 31.03.2016 In process
5) In battery room Exhaust Fan is notprovided. Yes Yes - NO NO -
6) A/R is not in service for both 220 KVfeeders. Yes Yes - NO NO -
7) GPS is provided but not in service. Yes Yes - NO NO - -
8) In DPR mho characteristics is used forfeeder which are short in length(i) 132 KV Int. Conn.I and II length 5.6 &6 KmSuggested to use QUAD characteristic.
Yes Yes - NO NO -
9) ZONE-3 Time setting provided 800 mswhich is to be revised to 700 ms. Yes Yes - NO NO -
10) Load dropping scheme is not provided on160 MVA Xmer –I & II. Yes Yes - NO NO -
11) DGA test results has not been carried outsince last two years for both 160 MVA Xmer inJan’14 samples sent to Oil Lab Ujjain butresults were not reliable due machine problem.To be carried out twice in a year.
Yes Yes - NO NO -
12) In 220 KV PGCIL–I & II feeder carriersaided tripping has not been provided which isto be provided.
Yes Yes - NO NO -
32 RAJGARH
220
Team of engineersfrom various
entities constitutedby SLDC
13.03.2015
Cont…32 RAJGARH
31 KOTAR 220
Team of engineersfrom various
entities constitutedby SLDC
08.04.2015
Page 24 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
1. Synchronizing trolley is not available. No No - YES NO - NIT issueed & in process
2. Carrier protection panel at remote end is notavailable YES No - YES NO - To be required.
3. Battery bank was commissioned on05.06.2006. Battery charger was set off forabout 2.5 hrs, voltage dropped from 110 V to105 V. Two cells are not working.Recommended for replacement.
No No - YES NO - In process
4. GPS is available but not enabled in relay. Yes YES - No No - -
5. Bus bar protection kept off since 13.07.14.Needs to be taken into service YES YES - No No - -
6. DG set not available. YES No - YES NO DG SET AREIN PROCESS OF DELIVERY ON RECEIPTWILL BE COMMISSIONED SHORTLY
7. LBB protection scheme at 132 KV notcommissioned. YES NO - No No - Work in progress
8. Direct trip scheme is not connected for220KV feeders. YES NO - No No - Work in progress
9. Broken conductor feature not used. Yes YES - No No - -
10. DR trigger for fault current sharing shouldbe configured. YES NO - No No - Work in progress
11. SF6 & air pressure status on the panel. YES Yes - YES NO alarm/indication facia is to be procured
33 BIRSINGHPURPALI 220
Team of engineersfrom various
entities constitutedby SLDC
16.03.2015
Page 25 of 26
Yes/NoWether
attendedYes/No
if not attendedreason
Yes/NoWether attended
Yes/Noif no, expected date
to attend
Sl. No.
Name ofSub-Station
identified forProtection Audit
S/SVoltage
Name of ProtectionAudit Agency
Date ofwhich AuditConducted
Observation of Protection Audit
Deficiencies that can be correctedwithout procurement
(Category-A)
Deficiencies involving procurement(Category-B)
Remark
12. Relay fault recording menu should beprovided to operating staff. YES YES - No No -
13. Auto reclose scheme is kept off.Recommended to be started after problemrectification.
YES YES - No No - -
14. DC voltage (110 V and 48 V) metersshould be provided in control room. No No - YES YES - -
15. 110V Battery charger voltage select switchis not working float charger is not in workingcondition.
YES YES - No No - -
16. Annunciation front panel is not having anyindication for auto-reclose operation. YES YES - No No - -
17. Thermo-vision is out of order and regularreadings are not taken on monthly basis. YES YES - No NO - -
18. Under-frequency relay supplies are givenwithout fuse in between. YES YES - No No - -
19. Df/dt relay is not connected. NO NO - No No - Not in plan
20. Group selection through input energisationshould be provided. YES NO - No No - Work in progress
21. Over current /EF relays settings should bedirectional which are non-directional atpresent.
YES YES - No NO
22. Transformer tertiary circulating current CTis not connected to panel. YES YES - No No - -
23. At 160 MVA transformer REF protection isnot in service. NO NO - Yes No - Work in progress
Cont…33
BIRSINGHPURPALI 220
Team of engineersfrom various
entities constitutedby SLDC
16.03.2015
Page 26 of 26
Page 1 of 2
Name of the Organization: NTPC Limited-WR stations
Sr.No Deficiency Observed during BasicProtection Audit
Action taken / proposed to betaken
TimeSchedule
Name of the Sub-station / Switchyard: Vindhyachal STPP
1. Replacement of balance Staticdistance protection relays, withNumerical relays, in line withGazette notification of GOI for 400kV Satna 1 & 2 lines.
Completed Complied-Bcategory
2. 63 MVAR Bus reactor needs to betaken into service.
Put in service Complied-Bcategory
3. Main-I and Main-II Distanceprotection Schemes for all feedersneed to be different make/characteristic for 400 kV Sasan,Mahan, and Satna-III & IV lines.
Being adopted. Complied-Bcategory
4. Earth fault in 220 V switchyard DCsystem to be attended.
Ongoing routine activity Complied-Acategory
Name of the Sub-station / Switchyard: Korba STPP
1. Over voltage relay: Drop off to Pick upratio is not explicitly available inMicom relays.
Minimum Drop off / pick up ratioof 95% is available in MiComrelay and it is in order as far asover voltage protection isconcerned. With a very highreset/operate ratio, chatteringphenomena may be observed inrelay.
Complied-Acategory
2. Power swing blocking is enabled forZ2, Z3 and Z4. However de-blockingtimer is set at 2 sec. The same maybe reviewed.
Power swing blocking logic has tobe universally decided across thegrid. De-block timer of 2 sec hasbeen adopted in all NTPCstations and is in line with NRPC /ERPC recommended settingguideline.
Complied-Acategory
3. Auto re-close relay reclaim timer notuniform for all lines. Stage-I lines ishaving 10 secs and the same is 25secs for stage-II lines. This may bereviewed.
Reclaim time of 25secs to beadopted for all lines as per NTPCpractice.
Complied-Acategory
Page 2 of 2
Sr.No Deficiency Observed during BasicProtection Audit
Action taken / proposed to betaken
TimeSchedule
4. Zone 2 time delay is different fordifferent lines (300ms and 400ms).The same may be reviewed.
As per NTPC practice, Zone-2time delay of 400ms is beingadopted & it is 500ms in case oflong lines followed by short lines.The same to be adopted.
Complied-Acategory
Name of the Sub-station / Switchyard: Sipat STPP
1. Time Synchronization: All numericalrelays except 5 nos relays of 765KVand 4 nos of relays of 400KV are timesynchronized.
Taken up with OEM. Only 01relay could be synchronized withGPS successfully.
Complied-Bcategory
2. Time setting of both Stage-I andStage-2 are same in all 765KV and400KV LBB relays.
The setting has been reviewedand found in order.
Complied-Acategory
3. Over voltage relay: Drop off to Pick upratio is not explicitly available inMicom relays.
Minimum Drop off / pick up ratioof 95% is available in MiComrelay and it is in order as far asover voltage protection isconcerned. With a very highreset/operate ratio, chatteringphenomena may be observed inrelay.
Complied-Acategory
4. Power swing blocking is enabled forZ2, Z3 and Z4. However de-blockingtimer is set at 2 sec. The same maybe reviewed.
Power swing blocking logic has tobe universally decided across thegrid. De-block timer of 2 sec hasbeen adopted in all NTPCstations and is in line with NRPC /ERPC recommended settingguideline.
Complied-Acategory
Name of the Sub-station / Switchyard: Jhanor Gandhar GPS
1. Replacement of existing static relaysfor line protection with Numericaldistance relays.
PO placed. Complied-Bcategory
Zone-1B Forward Minimum of (120 % of Protected line or Zone-2) 0
** For Mundra-Jetpur-1 & 2 line, Zone-2 reaches next voltage level. So, even if Mudra-Jetpur-1 & 2 are
parallel lines, the reach of zone-2 is taken as 120% instead of 150%.
For Rest of the lines, philosophy followed as mentioned in above table.
Transmission line protection philosophy based on Ramakrishna Committee report
Zone-3 Forward 100 % of protected line + 120 % of adjacent Longest line 1 Sec
Zone-4 Reverse 10 % Zone-1 0.35 Sec
Time
Delays
Zone-1 Forward 80 % of the protected line 0 Sec
Zone-2 Forward
120% of own line impedance (for radial line)
OR
150% of own line impedance (for parallel line) **0.35 Sec
Arc Ressistance Ph-E = 15 Ohms
Zone Direction Settings
Tower Footing Ressistance = 10 Ohms
Arc Ressistance Ph-Ph = 7.5 Ohms
Values considered for calculation
Angle = 85.63963
For Calculation factors cosidered are
CT Ratio
CT Details
CT primary
CT Secondary
3636.364PT Ratio2500
0.2
72.448 56.6
Line Capacity =
Impedance in Primary
R1 X1 R0
16.08
Factor for Secondary conversion CTR/PTR
5.52416
Distance Relay Setting for 400 kV Mundra-Bhachau line-1 & 2
R1 X1 R0 X0
0.01952 0.256 0.8624Ohms/km
2000 Amp
X0Line
DistanceLine Details
1.952 25.6 20 86.24 100 Mundra-Bhachau
0.16592 2.176 1.7 7.3304 8.5 Bhachau-Versana
244.0592 283 Bhachau-Ranchorpura
PT Details
2500 PT primary 400000
1 PT Secondary 110
0.6875
Zone Settings
Zone-1 Zone-2Zone-3 considering
Longest line
=
Zone-4 (Reverse) Zone-1B
Primary Sec. Primary Sec. Primary Sec. Primary Sec. Primary Sec.
Zero Sequence Compensating Factors
R 1.56 1.07 2.93 2.01 8.58 5.90 8.58 5.90 2.34 1.61
Rph 9.06 6.23 10.43 7.17 11.06 16.08 11.06 9.84 6.77
RE 26.56 18.26 27.93 19.20 33.58 23.09 33.58 23.09 27.34 18.80
30.72X 20.48 14.08 38.40 26.40 112.54 21.12
Reactance Ohms / km primary = 0.256
Reactance Ohms / km Secondary = 0.176
77.37 2.05 1.41
Calculation of Minimum Load Impedance
Voltage = 85 %
Overload = 150 %
Zload (Min) Primary = 65.433
Zload (Min) Secondary = 44.98519
XE / XL 1/3 ((Xo / X1 - 1)) = 0.79
RE / RL 1/3 ((Ro / R1 - 1)) = 3.082
All setting impedance values are per phase
For Calculation factors cosidered are
PT Ratio
PT Details
PT primary
PT Secondary
2500
CT primary 2500
CT Secondary 1
RE / RL 1/3 ((Ro / R1 - 1)) = 3.082
XE / XL 1/3 ((Xo / X1 - 1)) = 0.79
Zero Sequence Compensating Factors
Zload (Min) Primary = 65.433
Zload (Min) Secondary = 44.98519
Overload = 50 %
Reactance Ohms / km Secondary = 0.176
Calculation of Minimum Load Impedance
Voltage = 85 %
4.59 3.15 68.81 47.31
Reactance Ohms / km primary = 0.256
59.28
30.25 20.79
12.75 8.76
X 45.88 31.54 68.81 47.31 86.22
RE 28.50 19.59 30.25 20.79 31.57 21.71
14.07 9.68 14.07 9.68
6.57 4.52
31.57 21.71
5.25 3.61
Rph 11.00 7.56 12.75 8.76
R 3.50 2.40 5.25 3.61 6.57 4.52
Primary Sec.Sec. Primary Sec.
Zone-4 (Reverse) Zone-1B
Primary Sec. Primary Sec. Primary
Zone Settings
Zone-1 Zone-2Zone-3 considering
Longest line
3636.3636
Factor for Secondary conversion CTR/PTR = 0.6875
CT Ratio
400000
110
1.83488 24.064 18.8 81.0656 94 Halvad-Chornia
CT Details
1.838784 24.1152 18.84 81.23808 94.2 Halvad-Chornia
Line Details
4.37248 57.344 44.8 193.1776 224 Mundra-Halvad
Line Capacity = 2000 Amp
Impedance in Primary
R1 X1 R0 X0Line
Distance
0.01952 0.256 0.2 0.8624Ohms/km
Distance Relay Setting for 400 kV Mundra-Halvad line-1
R1 X1 R0 X0
All setting impedance values are per phase
Angle = 85.63963
For Calculation factors cosidered are
CT Details
CT primary
CT Secondary
CT Ratio
Distance Relay Setting for 400 kV Mundra-Jetpur line-1 & 2
R1 X1 R0 X0
0.01952 0.256 0.2 0.8624Ohms/km
Line Capacity = 2000 Amp
Impedance in Primary
R1 X1 R0 X0Line
DistanceLine Details
6.57824 86.272 67.4 290.6288 337 Mundra-Jetpur
1.30784 17.152 13.4 57.7808 67 Jetpur-Amreli-2
6.57824 86.272 67.4 290.6288 337 Jetpur-Mundra
PT Details
2500 PT primary 400000
1 PT Secondary 110
2500 PT Ratio 3636.3636
Factor for Secondary conversion CTR/PTR = 0.6875
Zone Settings
Zone-1 Zone-2Zone-3 considering
Longest lineZone-4 (Reverse) Zone-1B
Primary Sec. Primary Sec. Primary Sec. Primary Sec. Primary Sec.
Zero Sequence Compensating Factors
R 5.26 3.62 7.89 5.43 14.47 9.95 14.47 9.95 7.89 5.43
Rph 12.76 8.77 15.39 10.58 21.97 15.11 21.97 15.11 15.39 10.58
RE 30.26 20.81 32.89 22.61 39.47 27.14 39.47 27.14 32.89 22.61
X 69.02 47.45 71.17 189.80 130.49 6.90 4.75 103.53 71.17
Reactance Ohms / km primary = 0.256
Reactance Ohms / km Secondary = 0.176
Calculation of Minimum Load Impedance
Voltage = 85 %
Overload = 150 %
Zload (Min) Primary = 65.433
Zload (Min) Secondary = 44.98519
RE / RL 1/3 ((Ro / R1 - 1)) = 3.082
XE / XL 1/3 ((Xo / X1 - 1)) = 0.79
103.53
All setting impedance values are per phase
For Calculation factors cosidered are
Distance Relay Setting for 400 kV Mundra-Limbdi (Chornia) line-2
R1 X1 R0 X0
0.2 0.8624Ohms/km
0.01952 0.256
Line Capacity = 2000 Amp
Impedance in Primary
R1 X1 R0 X0Line
DistanceLine Details
6.10976 80.128 62.6 269.9312 313 Mundra-Limbdi (Chornia)
1.838784 24.1152 18.84 81.23808 94.2 Limbdi (Chornia)-Mansar
4.500336 59.0208 46.11 198.8263 230.55 Limbdi (Chornia)-Kosamba
CT Details PT Details
CT primary 2500 PT primary 400000
CT Secondary 1 PT Secondary 110
CT Ratio 2500 PT Ratio 3636.364
Primary Primary
Factor for Secondary conversion CTR/PTR = 0.6875
Zone Settings
Primary Primary
Rph 12.39 14.83 19.01
R 4.89 7.33 11.513.36
8.52
X 64.10 96.15 150.95
RE 29.89
66.11
20.55
44.07
Reactance Ohms / km primary 0.256
19.01 14.83
36.51 32.3332.33 36.51 25.10
4.41
Reactance Ohms / km Secondary 0.176
Calculation of Minimum Load Impedance
Voltage = 85 %
Overload = 150 %
Zload (Min) Primary = 65.433
Zload (Min) Secondary = 44.98519
XE / XL 1/3 ((Xo / X1 - 1)) = 0.79
Zero Sequence Compensating Factors
Zone-1BZone-1 Zone-2Zone-3 considering
Longest lineZone-4 (Reverse)
RE / RL 1/3 ((Ro / R1 - 1)) = 3.082
Secondary Secondary Secondary Secondary SecondaryPrimary
7.33
96.15
7.91
13.07
25.10
103.78
7.915.04
10.20
22.23
13.07
6.41
5.04
10.20
22.23
66.11
11.51
All setting impedance values are per phase
FORMAT -1 (PROTECTION AUDIT)
State
(D)Target date for completion
of audit.
(E ) No. of S/S where
deficiencies detected.
132 kV 220 kV 400 kV 765 kV HVDC Total 132 kV 220 kV 400 kV 765 kV HVDC Total 132 kV 220 kV 400 kV 765 kV HVDC Total
Maha 2013 334 183 24 2 543 11 76 22 0 109 323 107 2 0 434 NA NA
maha 2014 335 186 24 2 547 49 89 12 0 150 286 97 12 0 397
Guj 47 81 11 146 285 47 74 0 121 0 7 11 164 30.9.2013 for 132 & 220 kV 80 (30+ 50)
CG 18 1 19 18 1 19 0
MP gen 9 5 3 17 0 5 3 8 9 0 0 9 01/11/2014 8(5+3)
Trans+JP 62 9+1 72 62 9+1 72 0 0 0
OSP 1 1 1 1 0 0 30/09/2016 Tendered
ISP 1 1 1 1 0 0 15/09/2015
WR-I (PG) 0 0 8 3 1 12 0 0 8 3 1 12 0 0 0 0 0 0 NA
WR-II (PG) 11 3 14 11 3 14 0 0 0 4
NTPC 1 3 4 1 3 4 0 0 0
Total
(I) Reason/remarks for
rectification of deficiencies
requiring period of more than
one year.
(J) Cost estimates for removal
of deficiencies.
132 kV 220 kV 400 kV 765 kV HVDC Total 132 kV 220 kV 400 kV 765 kV HVDC Total 132 kV 220 kV 400 kV 765 kV HVDC Total
Maha 2013
Maha 2014 7 22 7 36 6 23 6 35 NA
Guj 4 30 4 38 13 24 9 46
CG 17 1 18 1 1
MP gen
Trans+JP 57 8 65 5 2+0 7
OSP 0+1 0+1
ISP 1 1
Because REL 316 is to be
replaced with latest relay
WR-I (PG) 5 2 7 0
WR-II (PG) NA
WR-I (NTPC) 1 3 4
TOTAL
1. RPCs
(State
wise)
Recommendation 9.1.1: There is a need to review protection schemes. This Committee concurs with recommendation of previous enquiry committee that a throrough third party protection audit need to be carried out in time bound manner. This
exercise should be repeated periodically and monitored by RPC's. Action : RPCs, CTU, STUs.
(F) Action plan (on observation of third party
protection audit) finalization date/Target date for
finalizing plan
(G) Detail of S/S where no procuremnet is required for
removal of deficiencies. No. of S/S
Target date for removal of deficiencies
(H) Detail of S/S where procurement is required. No. of SS
Target date of removal of deficiencies.
(A) Total No. of S/S in region. (B) No. of S/S identified for audit. ( C) No. of S/S yet to be audited
Agency
2. CTU
(Region
wise)
1. RPCs
(State
wise)
2. CTU
(Region
wise)
FORMAT -2 ( REVIEW OF ZONE - 3 PHILOSOPHY)
WRPC
Constituent \ kV 765 400 220 Total 765 400 220 Total 765 400 220 Total 765 400 220 Total
Maha 24 186 210 24 186 210 24 186 210
Guj 11 81 92 11 81 92 11 81 92 NA
CG 1 18 19 1 18 19 1 18 19
MP gen 3 5 8 3 5 8 3 5 8 NA
MP tran+JP 9+1 62 72 9+1 62 72 9+1 62 72 NA
OSP 1 1 1
ISP 1 1 1 NA
WR-I (PG) 3 8 0 3 8 0 3 8 0 NA
WR-II (PG) 3 11 14 3 11 14 3 11 14 NA
(NTPC) 3 1 4 3 1 4 3 1 4
Total No. of S/S at 220 kV &
above (132 KV & above in NER
states, J&K, Uttarakhand, HP,
Sikkims, etc)
No. of sub-stations
covered at each voltage
level.
No. of S/S where revised Z-III
setting have been
implemented.
Month and year by when revised
Z-III settings would be
implemented at remaining sub-
station.
Recommendation 9.1.2: Till protection audit is taken up, there is a need to take immediate review of zone 3 philosophy in paticular. Techniques are
available to modify characteristics of the relay so that it can distinguish between load encroachment and faults. These techniques and other
alternatives should be explored immediately. Action : RPCs, CTU, STUs.:
No. of PMUs
installed Locations
No. of PMUs functional and
time syndchronised
Target date for making
defective PMU functionalNo. of PMUs Locations
Target date for
commissioning
Maha 16 35 51
Guj 1 25 26
CG
MP+JP 1+2 1+2
WR-I (PG) 6 6
WR-II (PG) 6 6
NTPC 2 2
IPP 3 3
PurposeTrigger for SPS
operation
Result of SPS
operations
Maha
Guj 6
CG
MP+JP
WR-I (PG)
WR-II (PG) 2
WR-I (NTPC)
WR-II (NTPC)
Target date of
Finalization of
SPS
Format -3
Details of SPS Being Planned / Under studyPurpose of SPS
Trigger for SPS
operation
SPS under Implementation
result of SPS operations
(detailof load
shedding/backing down)
Target date for
commissioning
of SPS
S No. Constituent
S No. Constituent
Details of existing PMUs Total No. of
PMUs in the
State
SPS is already operational at present
Additional PMUs planned to be insatlled
List of NI PMUs installed under WRLDC pilot project Maharastra
S.No Sub-station owner Sub-stationDate of
CommissioningCT Connection (Feeders ) PT Connection S. NO. Voltage (kV) PMU Location
1 WRTS-I Boisar 10.04.2013 Phadke, Tarapur-2 Bus-1 1 400 Chandrapur
2 WRTS-I Bhadravathi 16.04.2013 Raipur-2, Raipur-3 Bus-1 2 400 Bhusawal
3 WRTS-I Solapur 400kV 18.04.2013 Kolhaur-1, Parli-1 Bus-1 3 400 New Koyna
4 NTPC Korba 10.09.2013 Bhatupara, Generator-6 Bus-2 4 400 Padghe
5 NTPC Vindhyachal 18.09.2013 Jabalpur-1, Korba-1 Bus-1 5 400 Dhule
6 WRTS-I Solapur 765kV 26.12.2013 Raichur- 1 & 2 Bus-1 6 400 Kalwa
7 WRTS-II Dehgam 13.04.2013 Gandhar-2, Pirana-2 Bus-1 7 400 Kolapur
8 WRTS-II Itarsi 20.04.2013 Jabalpur-2, Indore-2 Bus-1 8 400 Aurangabad
9 WRTS-II Satna 23.04.2013 Bina-3, Vindyachal-3 Bus-1 9 400 Lamboti
10 MPPTCL Bina MP 13.09.2013 PGCIL-1, Bhopal-1 Bus-1 10 400 Lonikand
11 CGPL CGPL Mundra 06.09.2013 Limbdi-2, GT-3 Bus-2 11 400 Girwali
12 220 Trombay
List of SEL PMUs installed under NLDC pilot project 13 220 Eklahare
S.No Sub-station owner Sub-station Date of CT Connection (Feeders ) PT Connection 14 220 Boisar
WR II
No. of PMUs Location
No. of units
functional &
Time
Synchronised
1 Vapi 1
3 GETCO Asoj 1.11.2013 Indore-1 Bus-1
4 MSETCL Kalwa 9.11.2013 Padghe-II, Kharghar Bus-1, Bus-2
List of Demo GE PMUs
S.No Sub-station owner Sub-station CT Connection PT Connection
1 WRTS-II Itarsi Jabalpur-1 Bus-1
2 WRTS-II Jabalpur Itarsi-1 Bus-1
List of IPP PMUs
S.No Sub-station owner Sub-stationCT Connection
(Feeders )PT Connection
1 APLAPL Mundra
(Siemens)Dehgam-2, Hadala Bus-1
2 WRTS-I Dhariwal (NI)Bhadrawathi-
2,Dhariwal-2Bus-1
3 TRN TRN Tamnar-1, Tamnar-2 Bus 1 , Bus 2
Bus-1, Bus-2
2 WRTS-I Raipur 08.11.2012 Korba-3, Raigarh-1 Bus-1, Bus-2
1 WRTS-II Jabalpur 02.11.2012 Itarsi-2, Vindyachal-4
Action: STUs, RPCs, Posoco, Time frame: immediate
No.Target date of
commissioning
Maha 389 389 0
Guj
149 145 4
OEM is contacted
for repairing scheme
NA TBD TBD
CG
MP+JP 283+0 283+0 0
OSP 8 8 0
ISP 12 12 0
WR-I (PG)
WR-II (PG)
WR-I (NTPC)
WR-II (NTPC)
No.Target date of
commissioning
Maha 31 28 3 _ _ _ _
Guj
149 145 4
OEM is contacted
for repairing scheme
NA TBD TBD
CG
MP+JP 34+2 34+2 0
OSP 0 0 0
ISP 12 12 0
WR-I (PG)
WR-II (PG)
WR-I (NTPC)
WR-II (NTPC)
POSOCO
(Petition wise)
WRLDC
Maha
Guj
CG
MP
WR-I (PG)
WR-II (PG)
WR-I (NTPC)
WR-II (NTPC)
Format - 4 (Enabling UFR and df/dt relay)
Total No. of UFRs installed RPC (State)
Total No. of df/dt relayss
installed
No. of df/dt
relays functional
State wise details of UFR (as on date )
Details of additional UFRs under
implementation/planned
Details of additional df/dt relays under
implementation/planned
RPC (State)State wise details of df/dt (as on date )
No. and details of petitions filed with CERC for non-compliance
of various regulations, issued under the act, by the states
Brief of petitionfiled in CERC Status of Petition
month and year to complete
the remedial action
action being taken to
make them functional
No. of UFRs
nonfunctional
No. of df/dt
relays
nonfunctional
action being taken to
make them functional
Month and year to complete
the remedial action
No. of UFRs
functional
22 22
Format -5 Real time Security Desk
Status Details of real time security desk
at each RLDC and NLDC
Status of development of faster
algorithm for real time updation
of TTC calculations by load
despatcher under outage
conditions
Implemented Provided in WRLDC control room
FORMAT - 6 (ADUIT OF HVDC, TCSC SVC AND PSS TUNING)
Location of HVDC Audit status (completed on
dd/mm/yyyy)
Observations of the aduit and the name of
audit agency
Action plan with timeline to
remove deficiencies as per
audit.
HVDC Chandrapur Not Yet Audited
Padghe Not Yet Audited
Guj
CG
MP
WR-I (PG)
BHADRAVATI HVDC
Back to Back22.01.2013 WR-II and WRLDC Representative No discrepancy Found.
WR-II (PG)
WR-I (NTPC)
WR-II (NTPC)
Location of TCSC Audit status (completed on
dd/mm/yyyy)
Observations of the aduit and the name of
audit agency
Action plan with timeline to
remove deficiencies as per
audit.
Maha
Guj
CG
MP
WR-I (PG) Raipur TCSC 06.02.2013 WR-II and WRLDC Representative No discrepancy Found.
WR-II (PG)
WR-I (NTPC)
WR-II (NTPC)
Location of SVC Audit status (completed on
dd/mm/yyyy)Observations of the aduit and the name of audit agency
Action plan with timeline to
remove deficiencies as per
audit.
Maha
Guj
CG
MP
WR-I (PG) NA NA NA NA
Details ofoutage scenarios built to be used by despatcher in real time for
revising TTC calculations
Seurity Desk person prepares the Base case in the moring as per the Load
generation balance on the day available from WRLDC SCADA. After that
Contigency ranking is done by PSS/E and accordingly top contigency is
performed. Also all the emergency outage simulation is performed for
making system N-1 secure after contingency.
(B) Audit of TCSC
(A) Audit of HVDC
Recommendation: 9.9.2.: An audit of devices such as HVDC, TCSC, SVC and PSS should be done immediately to enusre that their stability features
are enabled. Further exercise of PSS tuning should be planned and implemented. Settings of these dynamic stabilizing devices should be reviewed
at appropriate intervals. Action : CTU, STUs, Generators: Time Frame : 6 months.
( C) Audit of SVC
Maha
WR-II (PG)
WR-I (NTPC)
WR-II (NTPC)
RPC (state wise)
Name and Location of
generator identified for PSS
tuning.
Audit status (completed on
dd/mm/yyyy)
Action plan with time line to complete PSS
tuning.Remarks
Maha 23
Guj
CG
MP
OSP 1
ISP 1
WR-I (PG) NA NA NA NA
WR-II (PG)
WR-I (NTPC)
WR-II (NTPC)
Constituents Station Unit No. Capacity (MW)
Gujarat Wanakbori TPS 1 210
Wanakbori TPS 3 210
Chattisgarh Korba (W) TPS 1 210
Korba (W) TPS 3 210
Korba (W) TPS 2 210
Madhya Pradesh Satpura STPS 8 210
Satpura STPS 9 210
SGTPS Birsinghpur 1 210
SGTPS Birsinghpur 2 210
SGTPS Birsinghpur 3 210
SGTPS Birsinghpur 4 210
Maharashtra Nasik TPS 3 210
Nasik TPS 5 210
Parli TPS 2 210
Parli TPS 3 210
Parli TPS 4 210
NTPC Korba STPS 2 210
Korba STPS 3 210
Korba STPS 4 210
Korba STPS 5 500
Korba STPS 6 500
REL Dahanu TPS 1 250
Dahanu TPS 2 250
(D) Status of PSS Tuning
Format-7 Voltage collapse prediction relayStatus of exploration of voltage collapse prediction relay Action: RPCs, Time Frame: 1 year
Format-8 Telemetry facilities
POSOCO
(Region
/State/CPSU
Wise)
Fault in the telemetry / Reason
for non-availability of
telemetry(B)
Nature of the communication link
for required telemetry in
column(A)
(Microwave/FO/PLCC) C
Action plan with time line to
oerationalize the required
telemetry facility (D)
Bhatiya (3rd Trf.) 220 Not Integrated Yet
Mokha 220 Not Integrated Yet
MPPTCL CHICLI 220 Not Integrated Yet
DHAR 220 Not Integrated Yet
PANAGAR 220 Not Integrated Yet
Khaparkheda GS 500 Telemetry Not availble
Deepnagar GS 1000 Telemetry Not availbleWARORA 400
LONIKAND NEW 400
Taptitanda 400
GHATGHAR
400These stations are not availbale in
New SCADA and thus not
available at RLDC/NLDC
CHANDRAPUR 2
400These stations are not availbale in
New SCADA and thus not
available at RLDC/NLDC
HARANGUL 220
KDPH 220
KOLSHET 220
Recommendation :9.10.2: Possibility of voltage collapse prediction,sensing globalpower system conditions derived from local
measurements may be explored
Name and location of Generating
station / transmission element
without telemetry faclity (A)
GETCOSub-Station is ready but all lines
are under construction stage
MSETCL
Maharastra have informed that
they are taking up for alternate
communication system from
TTSL
StatusIn Boisar, A-eberlay Collapse Prediction relay was installed on 17 Oct,12 as a demo project. A-Eberle has now decommisoned these
relay.
Action: RPCs, Posoco, Time frame: 6 months
New Stations Added , Integration
still pending
Maharastra have informed
that they are taking up for
alternate communication
system from TTSL
LATUR 220
MAHAD 220
TEMGHAR 220
TILLARI 220
GHATGHAR 220Lokmangal Shugar
Ethanol, IPPYash Agro & Energy
Ltd., IPPGangakhed Sugar &
Energy Ltd., IPP
A A Energy, IPP
JSW Steel Ltd., IPPShree Sidhbali Ispat
Ltd, IPP
RPL Urja IPP
M/s ISMT Ltd. IPP
M/s Vasantrao Dada
Patil Sahakari Sakhar
Karkhana (SSK) Ltd. IPP
CSPTCL NIL NIL NIL NIL NIL
DD MAGARWAD 220 SCADA not Available PLCCNew RTU Envisaged in New
SCADA
KARARPAD220 kV SCADA not Available PLCC
New RTU Envisaged in New
SCADA
NEW KHARADPARA220 kV SCADA not Available PLCC
New RTU Envisaged in New
SCADA
SAYALI220 kV SCADA not Available PLCC
New RTU Envisaged in New
SCADA
KHADOLI220 kV SCADA not Available PLCC
New RTU Envisaged in New
SCADA
CUNCOLIM 220KV PLCC
AMONA 220KV PLCCGOA
To be done as part of new
SCADA
MSETCL
Maharastra have informed that
they are taking up for alternate
communication system from
TTSL
Maharastra have informed that
they are taking up with IPP for
integration
DNH
Maharastra have informed
that they are taking up for
alternate communication
system from TTSL
Maharastra has informed that 4
major IPP and 8 small IPP have
been integrated. The balance 18
small IPP in the state are taking up
for integration for complete grid
visibility