ATLAS Tile CalorimeterWBS 3.4
Larry PriceANL
M&O Status and Plans
TorontoAugust 3, 2005
USATLAS EC MeetingToronto 8/3/052
Construction Project (Installation)
USATLAS EC MeetingToronto 8/3/053
USATLAS EC MeetingToronto 8/3/054
USATLAS EC MeetingToronto 8/3/055
Installation Schedule in Pit
Barrel March-December 2004 EBC: August-November 2005 (Oct-Nov) EBA: December-March 2006 (Dec-Jan)
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
Che
ck ra
ils ID services along Barrel
Jan '06Dec '05
Dec '05 Jan '06 Feb '06Sep '05 Nov '05
LAr
Feb '06Aug '05 Sep '05 Oct '05 Nov '05
Aug '05 Oct '05
Big Wheels C
JN C
Platf. Remov
.
Sole
noid
Endcap Calorimeter C
Cable chains
Barrel Calo testing and commissioning
Platforms removal
HS arches
Muon Barrel A
Endcap Calorimeter A
JN A
LAr
Endcap Cal. C services
Muon Barrel C
ID services through Muons
Muons sector 13, BMS chambers, Muon rails, gangways & services
Fiel
d m
appi
ng
Endcap cryo lines.
Barrel Calo services
Barrel Cryo lines
Barrel Toroid services BT testing & commissioning
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
ID A
ID B
ID C
Pixe
l
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Bea
m p
ipe
Side A
Barrel
Side C
Big Wheel A, step 1 Big Wheels A
Full
mag
net t
est
JF
EO, side C
JF
JF
VJ
JT C
May '07Nov '06Apr '06
Endcap Toroid A cooldown & testing
ID connection, testing & commissioning
Oct '06Apr '06 Jul '06May '06 Jun '06 Aug '06 Sep '06
Jun '06Mar '06
Dec '06Mar '06
Small Wheel C
Oct '06
Endcap Cal. A services connection, testing & commissioning
(JT)
VT
Jan '07Aug '06 Sep '06Jul '06May '06 Apr '07
glob
al te
sts,
pum
p do
wn
& b
ake
out
Dec '06
VJ
Feb '07 Mar '07
JF
EO, side A
Cosmic Tests
VA VTJTA Small
Wheel A
Endcap Toroid A
May '07Nov '06 Jan '07 Apr '07Mar '07Feb '07
VABig Wheels C Endcap Toroid C
Endcap Toroid C cooldown & testing
(JT)
Global Commissioning
Endcap Cal. C testing & commissioning
Full magnet test
Assembly/commissioning schedule (Version 7, still official)
Comments:
-Probable 4 weeks delay on LB movement (not official)=> delay EB assembly+LB commissioning-EC toroid A that follows EBA assembly is not available in time.-When EB is pushed inside toroid for ID installation or solenoid magnetic field test, the dist LB-EB~ 4m and minivan-scaffolding still in place =>can access EB/B fingers (to be looked in more detail).
Schedule for barrel Commissioning phase 1 active Tile WPs ( based on V7 schedule) 20 June05This table does not taken into account that unofficially (most probably) the start of commissioning by sectors planned for 7 Sept-15Nov05 will be delayed
by 3-4 weeks due to delay of the toroid installation/barrel movementWP Task/main steps Duration schedule Team
WP2 Services:1) route cables from USA15->HS support (fibres later)2) install second connector +QC on HS (start with HV b. sectors)3) Finish local cables installation on truck4) Connect all cables+fibres HS->fingers (2 days/16 fingers)5) Trigger cables installation
1) ~1month2) ~1month3) 2-3 weeks4) 1 month5) 2 months?
1)9May- mid June done?2)24June-endJuly3) 22 June->~10July 4) September5) Sept-Nov? (try before)
TCIrakliIreneTile
techs
WP3 Racks equipment in USA15:1) Validate layout of rack Wizard with TC (missing
val. 5 racks)2) Finalize infrastructure in counting room (Cooling +
power)4)Fill in construction DB material installed/tested in
USA155) Follow cables connection to electronics
1) 1 week2) Couple of weeks4)all time5) “ “
1) Finish by end June?2) Finish 27 June4) Until end 055) Until end 05
EstebanIrene
Irakli,TCAll tile WP
resp.4)
Irene,Larry+…
WP4.1 FE(SD) certification+repairs with MOBIDICK:1)Finish repairs on available drawers2) install/drill 8 finger extensions (Nikolai’s+ CF
team)3) Upgrade EBC/EBA for sense
lines+links+certify/repair in 175
At z=0:4) Repair/certify unavailable 14 LB drawers5) install LB15 Sdrawers6) Repair LB SDs ( if mobidaq finds a problem)
1)3months2) ~ 2 weeks3) Few months
4Many weeks5) 1Week6) 2 months…..
1)March-endMay2) 27June-~5July?3) 1 June->end Aug
4) Sept, 5)End Sept.6)Sep-Nov 05
FabriceCF+ Chicago + ANL +few
tile techs/physicis
ts
2) Iouri+Nikolai+techs+CF
WP4.2 FE(SD+LV+laser+cables+…) certification with MOBIDAQ:1)Upgrade mobidaq (LED test, +trigger cables?+…)3) Stability tests with cooling (inform CF if problems found)4) Take first cosmics data during expert week (Richard)5) commission the barrel rotating in sectors (6days/16fingers)
1) Several weeks3) several months4) 1 week5) 2 months
1) Finish end July3) start 20 June ; continue 4) 20-27 June 5) Sept-Nov
Iacopo,AmirGerolf,PedroPaulo,Giorgy,
Schlereth+…….all
Schedule for barrel Commissioning phase 1 non active Tile WPs (20 June 05) page 2WP Task/main steps Duration schedule TeamWP8
cesium1)Install tubes/sensors around cylinder (sign off ok)2) Local cabling between elect boxes/garages/sensors after ID 3) Install hydraulic equipment on racks in UX154) Finish garages/boxes (after finger installation/cryo pipe)5) Piping+ cabling from racks->Z=0 (with TC)6) Dummy source tests (6 days/16 fingers)7)final calibration with cesium source (WP
1) Many weeks2) ~1 week3)~3 weeks4) ~1 week5) ~ few
weeks6) 2 months7) 3 weeks +
….
1) Finished mid May2) 11-30July 3) Start mid July? 4) 11-30July 5) beg. Sept6) Sept-Nov7) 15 Nov->end Dec +
….
Andrei+Protvino team.
ANL Techs
WP4.3RODDAQ crate
1) Install VME crates + associated hardware + rack modules
2) Install software, setup configuration databases 3) Connect drawers via temporary cables 4) DVS tests, CIS/ped/cosmic runs, monitoring +
event display 5) Integration with Laser System 6) Integration with LVL1, calibration of LVL1
receivers 7) Commissioning by sectors using ROD DAQ 8) Full commissioning+calibrations, cosmics with
Lar
1) 2 weeks2) 5 days3) 3 days4) 3 months5) 2 weeks6) 2 weeks7) 2 months8) 1 month
1) – 4) June – August
5) July - August 6) September 7) 9 Sep - 16 Nov8) 9 Nov – 7 Dec; spring
’06
1) – 4) Online team: Andrea, Gerolf,
Giorgi,Iacopo, Larry, Oleg,
Paulo(?) +Valencia ROD experts5) C-F pers. + Online
team6) LVL1 pers+ Online
team7) Shifters + Online
team8) Shifters + Online
teamWP5
LV1) Install connector on local cables at
Star_Boxes+QA (WP2-3) 2) LVPS DCS test from USA15 with Dummy_Load on
Truck 3) Install AUX_Board Crates and Bulk PS prototype
at USA15 4) Install connector on long cables at Star_Boxes
(LB at Z=0) 5) Frame install.+final cabling; QA of LV_BOX (use
DL) at Z=0 6) Insert LV_BOX to finger, tune working point via
LV_DCS
1) 2-4 weeks 2) 2 days 3) 2 weeks 4) 2 months 5) 2 months 6) 2 months
1) mid June->mid July 2) 1->15 July 3) Aug/Dec 4) 9 Sep -> 9 Nov 5) 9 Sep -> 9 Nov 6) 9 Sep -> 9 Nov
1) Irakli, Dave + 1 tech
2) Francisca+DCS exp.
3) Stan, Francisca+1 tech
4) Lvexp + 1 tech 5) David, services
group 6) LV+DCSexp.
+shifters
WP11:DCS
1) Install temp. cooling DCS+2 PCs with Kvaser+NI RS422 cards
2) test DCS for LV, HV, Cs + DDC with local DB3) Install PS for CanBus + Update Software4) Test Alarms, Cesium/Min Bias/Laser systems in
branches5) Performance and stability tests
1) 1.5 Weeks2) 2 Weeks3) 1 Week4) 2 months5) 3 weeks
1) Finish end June2) 1->15 July3) Last week of August4) 9 Sep -> 16 Nov5) 16 Nov -> 7 Dec
A. Gomes + J. Pina+Calin+
2) All DCS exps.3) LIP team4) DCS
experts+shifters
5) DCS experts + Shifters
WP9:Laser
1) Installation on racks + tests2) Install PLC + mechanics3) Laser + Electronics tests4) Stability/perform. tests +tuning modules with
temp. fibres5) commissioning the barrel in sectors
(6days/16fingers)
1) ~1 week2) 2 days 3) 2 days4) 2.5 weeks5) 2 months
Beg. Nov , Use LED with Mobidaq
to test laser fibres in Sept-mid Nov
L. Pierre + CF+J.Carvalho +
Richard
Schedule for barrel Commissioning phase 1 non active Tile WPs (20 June 05) page 3WP Task/main steps Duration schedule Team
WP10:HV
1) Power supplies installation2) Inter-racks cables connection +QC3.1) Test canbus Power supplies3.2) Test a can bus branch +LED test with MobiDAQ 3.3) HV DCS tests in 8 SDs with Mobidaq4) Whole ATLAS DCS tests in sectors
(6days/16fingers)
1)1 week2) 1 week3) ~1-2 week
4) 2months
1)8-30 June2)20June-2 July3) Second half July
4) Sept-Nov
Yahya +CF 1)Stanislav +Irakli’s
team2) CF techs 3) CF+DCS/mobidaq
exps.
4) CF+shiftersWP7:
ROD/BE1) Test 10 first RODS2) HW installation in USA153) SW installation in USA15 + integration with
TDAQ4) Read out full barrel + TDAQ + Fibers + Tile
Operative
1) 4 Weeks2) 2 Weeks3) 6 Weeks4) 2 months
1) Second half June2) First half July3) 15 July + August4) 9 Sep ->16 Nov
1) Juan+Valencia 2) Carlos & E.3) Carlos
+Oleg+TDAQ4) Valencia +shifters
WP6.1Cosmics recivers+cosmics tests
Cosmics expert week with 2 top-2 bottom barrel modules. Install/test/get ready:
1) CANbus cables+ CANBUS LV power2) Module Configuration + USA15 infrustructure3) Cables and Fibers + 2 Cooling units
+Temporary LVPS4) USA15 infrastructure+ 9U coincidence boards5) MobiDAQ Readout tests6) Setup Tests + Online DAQ software +
Monitoring7) Offline software, Analysis, Shifts during data
taking8) Second expert week with final LV supplies
1->6) ready until 19 June
7) 20-27 June
8) II) ~ 25-30 July
Richard +Mobidaq experts + Schlereth + all
WP6.2 receiver
s
To be filled later Kerstin+ Manoel +(Stockholm+Rio
group)+Amir+Pedro
WP12 Mbias
1) Tests with tile DCS +Tile DAQ 2) Certify CAN cabling chain 3) Certify ReadOut Buffers 4) Certify communication with ADC-Is 5) Integration to the beam crate 6) integration to the Tile DAQ 7) integration to the Tile DCS
1) few weeks 2) two days 3) two days 4) one week 5) ? 6) two weeks 7) two weeks
1) by end Aug 2) ? ( <- wp 2.6, 3.5, +
CAN PS) 3) beg July ( <- wp 3.3) 4) by mid Nov ( <- wp 5.6,
12.2, 12.3) 5) by end Nov ( <- wp
4.3.4) 6) by end Sept ( <- wp
12.5) 7) by mid Dec ( <- wp 11.4,
12.1, 12.3
1) I.Korolkov+BCN team
2) I.Korolkov+BCN team
3) I.Korolkov+BCN team
4) I.Korolkov+BCN team
5) Oleg+Ilya 6) Oleg+Ilya+M.Volpi 7)
Ilya+A.Gomes+BCN
TileCal Front-End Electronics Repairs on HF Truck Sept-Oct 04
-Tests on: TTC, CANbus, HV, laser fibres via LED, BCID @ 100 kHz L1A, readout noise, …- Replaced failing components- Will continue in Jan-Feb when OPAL cradle will be removed
USATLAS EC MeetingToronto 8/3/0511
WP 4.1: In situ FE electronics certification with Mobidick (status in June05; Claudio,Fabrice)
Remaining tasks for z=0 (before starting commissioning, no access now):• 14 Super Drawers to be repaired ( 7 out of 64 modules)• 2 SD to be inserted• Repair/certify FE in cases of failures are found with MobiDAQ •Finish this week last 4 modules certification (without fingers)
•Next step in July+Aug (Nikos): perform FE stability tests in all modules using MobiDAQ +temporary cables (~ 8 SD running ~ 3 days with portable cooling).
USATLAS EC MeetingToronto 8/3/0512
Cosmic receiver setup
MobiDAQ
PC (MobiDAQ interface)
WP4.2: FE tests with MOBIDAQ (Gerolf,Iacopo,Amir,Oleg,Giorgi,Andrea) (8 drawers at the time from USA15+temporarly cables/fibres)
•MOBIDAQ in pit for many weeks and working in stable mode for a few days.
•Still need to include LED test to send light to PMTs (will replace laser system for fibres QC)
Cosmic rays expert week 20-28 June (Richard et al.)
8 superdrawers (2 top +2 bottom modules)8 sets of temporary cables (TTC/GLINK, CANbus, trigger, laser/LED) 8 temporary LVPS 2 temporary cooling unitsMobiDAQ in USA152 Coincidence boards (Chicago)Details:http://agenda.cern.ch/askArchive.php?base=agenda&categ=a053788&id=a053788s1t6%2Ftransparencies%2FTEUSCHER_Cosmic_Ray_Expert_Week_Summary_June_2005.ppt
USATLAS EC MeetingToronto 8/3/0514
Event with Back-to-Back Trigger
USATLAS EC MeetingToronto 8/3/0515
Next expert weeks/integration runs:
July ’05: ROD Expert week in USA15 Read out 8 superdrawers with final ROD Motherboard Debug DAQ/ROD
Dec ’05/Jan ‘06: Begin cosmic-ray running on barrel Following installation of final services and Low
Voltage PS at z=0 Up to 12 top + 12 bottom modules
2006: Continue periodic runs until global ATLAS cosmic run in March ‘07
Integrate with LAr barrel after cool-down (~April ‘06) Repeat with TileCal EBA / EBC / HEC / FCAL when
ready in ‘06
USATLAS EC MeetingToronto 8/3/0516
Summary or dates as understood on June 27th (based
on v7).
WP Task/main steps Duration schedule
WP12 Mbiasbarrel
1) Tests with tile DCS +Tile DAQ 2) Certify CAN cabling chain 3) Certify ReadOut Buffers 4) Certify communication with ADC-Is 5) Integration to the beam crate 6) integration to the Tile DAQ 7) integration to the Tile DCS
1) few weeks 2) two days 3) two days 4) one week 5) ? 6) two weeks 7) four weeks
1) by end Aug 2) ? ( <- wp 2.6, 3.5, + CAN PS) 3) August ( <- wp 3.3) 4) by mid Nov ( <- wp 5.6, 12.2, 12.3) 5) by end Nov ( <- wp 4.3.4) 6) by end Sept ( <- wp 12.5) 7) by mid Dec ( <- wp 11.4, 12.1, 12.3)
USATLAS EC MeetingToronto 8/3/0517
MBTS counters
2 segments in ; inner segment covers pixel detectors
USATLAS EC MeetingToronto 8/3/0518
Principal US M&O Work in 2005
Validation, calibration, and repair of modules and electronics Adjustments and modifications to accommodate adjacent systems, e.g., LAr
and Cryostat Establishment of test/repair facility
Work with TC on services validation Cosmic Ray Commissioning
Cosmic ray trigger system “First ATLAS Data from the underground area”
Performance monitoring and calibration software development Setup for cosmic ray commissioning and performance measurement Vapor shields for central and forward cryostats MBTS Scintillators Validation and testing of LVPS Initial integration with TDAQ and extensive exercise of interfaces
(MobiDAQ) Establishment of conditions and other databases Design and prototyping of MBTS Counters
USATLAS EC MeetingToronto 8/3/0519
Plans for US M&O Work in 2006
Complete MBTS Counters Barrel integration with TDAQ + DCS and extensive exercise of
interfaces Barrel commissioning
Locally by sectors Cosmics with TDAQ readout
EB Commissioning (as above) Final mechanical and light integrity validation of EBA modules before
installation in pit Software development
Complete initial calibration, diagnostic, and status reporting software Database development
Establish and exercise the procedure for regular diagnostics and calibrations
Validation and testing of LVPS Identify and carry out needed electronics repairs
Completion of test/repair facility Understand calorimeter performance and integrate with LAr and
physics studies
USATLAS EC MeetingToronto 8/3/0520
FY 2006 Budget
Inst. Activities Guidance Reserve Total
ANL Software development, Databases, Electronic testing, TDAQ Integration, Mechanical setup
$451K $95K $546k
MSU MBTS Counters, Module integrity validation
$52K $30K $82k
UC Electronics test/repair, TDAQ Integration, Cosmics commissioning
$217K $50K $267k
UI Services validation, TDAQ integration
$70K $19K $89k
UTA Local commissioning $56K $19K $75k
Total $846 $213 $1059k
USATLAS EC MeetingToronto 8/3/0521
Issues Completion of LVPS Congestion in the pit
Tile Extended Barrel assembly Muon Barrel assembly Tile Barrel commissioning
Will need probably to work in 2 shifts/day in Sept->Dec with several teams working in parallel.
Consequently need: Big teams of physicists/tech/eng.
at CERN during second half 2005 and first half of 2006.
Commission each Tile sub-system in standalone as much as possible before end August in USA15/UX15 with temporary cables
Good coordination within Tile sub-systems and with other ATLAS systems (through TC).
TC