Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron WBS 2 - Hadron Calorimeter Calorimeter Andris Skuja HCAL Schedule at CERN DOE/NSF Review HCAL Subsystem Sessions May 20, 2003

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

  • View
    216

  • Download
    2

Embed Size (px)

Citation preview

Page 1: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1

WBS 2 - Hadron CalorimeterWBS 2 - Hadron CalorimeterWBS 2 - Hadron CalorimeterWBS 2 - Hadron Calorimeter

Andris SkujaHCAL Schedule at CERN

DOE/NSF Review

HCAL Subsystem Sessions

May 20, 2003

Page 2: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 2

US HCAL ResponsibilitiesUS HCAL ResponsibilitiesUS HCAL ResponsibilitiesUS HCAL Responsibilities

The US construction responsibilities for all HCAL subdetectors are well defined:

• HB: absorber, megatile production (optics), optical cables & connectors, readout boxes, photodetectors (HPD’s), front end electronics, trigger/DAQ electronics, power supplies, controls: US CMS

• HE brass (75%) & scintillator acquisition (only): US CMS• HE optical cables & connectors, readout boxes,

photodetectors (HPD’s), front end electronics, trigger/DAQ electronics, power supplies, controls: US CMS

• HO readout boxes, photodetectors, front end electronics, trigger/DAQ electronics, power supplies, controls: US CMS

• HF and HF shielding mechanical design: US CMS• HF quartz fiber (Plastic cladding): US CMS• HF readout boxes, photomultipliers, front end electronics,

trigger/DAQ electronics, power supplies, controls: US CMS

Page 3: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 3

Non-US ResponsibilitiesNon-US ResponsibilitiesNon-US ResponsibilitiesNon-US Responsibilities

Responsibilities of CMS collaborators• HE: absorber manufacture, megatile production (optics) :

R/DMS

• HO installation brackets & tooling, megatiles (including scintillator), optical cables & connectors: India

• HF absorber manufacture and installation tooling: Russia

• HF support structures and shielding: Iran & Turkey

• HF quartz fiber installation: Hungary/CERN

• HB/HE/HF: HV Supply Engineering: Bulgaria

Page 4: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 4

Outline of Future TasksOutline of Future TasksOutline of Future TasksOutline of Future Tasks

• Calibration System and RBX installation at CERN Site (SX5)

• HB assembly in SX5 hall (finished)

• HB, HE final megatile (layers zero and 16) installation in UX5

• Electronics installation in SX5 (HB,HE,HO)

• Trigger/DAQ Electronics installation in UX5 Counting Room

• PS installation, RBX connection in UX5

• DAQ Interfaces UX5/SX5

• HF Assembly (Bldg. 186): Completed Summer ‘03

• HF Electronics installation in UX5 & SX5

Page 5: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 5

HCAL ScheduleHCAL ScheduleHCAL ScheduleHCAL Schedule

Blue = Project; Green = M&O

Page 6: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 6

Calibration in Building 186Calibration in Building 186Calibration in Building 186Calibration in Building 186

The Calibration systems was installed and Tested in Building 186. The Calibration system was also tested in Test Beam ’02 (and ’03)

• The Laser System has been tested on appropriate megatiles

• All megatiles have been tested using the moveable Source Drivers (in Bldg. 186) both for HB and HE

• The calibration measurements has been an initial testing ground of our DCS monitoring system.

• Data bases compatible with the CMS standard will have to be generated and compared to results obtained at FNAL.

• Readout has been tested in Test Beam

• Additional Readout Units will have to be moved from wedge to wedge as the source calibration progresses in SX5 tests. Final Ems can only be delivered once HPDs are delivered to FNAL

Page 7: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 7

HCAL SOURCE CALIBRATIONHCAL SOURCE CALIBRATIONHCAL SOURCE CALIBRATIONHCAL SOURCE CALIBRATION

PROTOTYPE AIR-MOTOR SOURCE DRIVER FOR HE, WITH CONTROL BOX

FINAL DESIGN IS MORE COMPACT, AND HAS A TWO-ROW CHANNEL INDEXER

Page 8: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 8

HCAL SOURCE CALIBRATIONHCAL SOURCE CALIBRATIONHCAL SOURCE CALIBRATIONHCAL SOURCE CALIBRATION

HE PPP1 and PPP2 Wedges with megatiles in place and extension source tubes installed.

CERN Bldg. 186, May 1999.

Page 9: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 9

Critical PathCritical PathCritical PathCritical Path

The HPD’s define the critical path. We can only finish the RM’s for the RBX’s as the HPD’s are delivered to FNAL

We have accepted about 25% of the HPDs. It is expected that all HPDs will bedelivered by the end of ’03.

The HBX’s and RM’s can be installed in ’04 and do not have to be completed in ’03. Thus the schedule for HO electronics may extend into ’04.

Page 10: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 10

Recent HCAL Recent HCAL Milestone Performance (v33)Milestone Performance (v33)

Recent HCAL Recent HCAL Milestone Performance (v33)Milestone Performance (v33)

Page 11: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 11

Readout Module (RM)Readout Module (RM)Readout Module (RM)Readout Module (RM)

• The RM integrates the HPD, front end electronics, and digital optical drivers. An RM requires an HPD before it can be completed.

HPD unit QIEs CCAs

Electronics Cards

Optical

Drivers

Digital optical connector

Page 12: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 12

Test Beam and SX5Test Beam and SX5Test Beam and SX5Test Beam and SX5

Several HB- wedges were moved to SX5 in the summer of ‘02. Several had their response measured in the Test Beam before being assembled into the HB- half barrel in SX5 in Fall of ‘02.

Both HB+ and HB- have been assembled into half barrels at CERN and are sitting in SX5 alcoves waiting for further instrumentation.

The 2 half barrels remain in alcoves in SX5 until the full magnet test. This will be an ideal time burn in electronics. The FE ASICS are ready for installation. However the RM’s await the HPD delivery schedule.

Some tests can be done without the final RM’s

A major electronics test and checkout will take place in early ’04 (the vertical slice test). This will require teams of engineers, technicians and physicists if it is to succeed. The slice test is part of M&O planning (pre-ops).

The full magnet test takes place in Fall of ‘05. All electronics checkout should be finished beforehand.

Page 13: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 13

Installing HB in UX5Installing HB in UX5Installing HB in UX5Installing HB in UX5

Tie rods

Cable block stabilizer

Support Beam

Spider

•The HB half barrels will be lowered one at a time in ‘04.

•Each wedge is fully instrumented at this time. The RBX’s are in place.

•Once underground the spiders and end cutouts must be removed before insertion in the magnet cryostat.

Cradle

Riser

Page 14: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 14

Installing the HCAL Barrel Installing the HCAL Barrel Installing the HCAL Barrel Installing the HCAL Barrel

Page 15: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 15

UX5 InstallationUX5 InstallationUX5 InstallationUX5 Installation

Megatile layers 0 and 16 are installed underground and connected to the RBX’s

All RBX connections to the external world must be laid (including optical links). Much of this work is done by CERN professionals. The system must be tested. The cooling system, fire protection system and controls & calibration links must be installed.

The Source Drivers must be installed and tested.

The controls/monitoring system must be used to establish the relative timing of the FE/TRIDAS chain. The laser pulses going to the megatiles will have the same relative time phasing as the interacting particles. The final synchronization of the electronics with the CMS trigger/DAQ pipeline will be established using real proton bunches, perhaps with only every third bunch filled.

Page 16: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 16

Electronics InstallationElectronics InstallationElectronics InstallationElectronics Installation

The FE cards are installed in the RM’s and inserted in the RBX’s on the surface in the SX5 alcoves. This installation starts in June of ‘03.

The TRIDAS system will be ready for installation in late ‘03. Twenty HTR prototype units and a DCC prototype are being installed in Test Beam ’03. We expect final completed units to be ready to read out the RBX’s during the SX5 tests in summer/fall of ‘03. The TRIDAS engineers and physicists will have to be at CERN at this time to help with the startup of this electronic system.

We do not expect to reproduce the full readout chain in SX5 (too costly and time consuming). We plan to test 4 wedges at a time with a moveable optical fiber system connected to the TRIDAS HTR cards. The SX5 DAQ will be configured by a collaboration of Princeton and HLT/DAQ software engineers.

The vertical slice test also tests only a limited number of wedges.

Page 17: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 17

HE & HO CommissioningHE & HO CommissioningHE & HO CommissioningHE & HO Commissioning

US groups are not responsible for the assembly and megatile insertion for HE. However, the HE RBX’s must be ready for early checkout (’03). The HE RM’s are on the same time scale as those for HB (but should be delivered ASAP).

A major US commitment will also be required for the commissioning of the HE electronics. The HE critical path is again the same as that for HB.

Finally everything must be ready for the magnet tests in early ‘05.

The HO RBX’s and FE cards are more accessible than those for HB and HE. They sit on the outer surfaces of the Muon Barrel Rings and can be installed in UX5 if that’s required. However, it would be better to check out even HO electronics before it is sent underground.

Page 18: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 18

HF assembly & installationHF assembly & installationHF assembly & installationHF assembly & installation

All detector mechanical components (wedges, strongbacks, backplanes) have been delivered ahead of schedule and are at CERN.

Production of HF tables is well advanced: for the first one the welding and thermal treatment is done and is being machined now, for the second the welding is complete.

Production of the support outer shield has started for the first HF. Contracts for machining placed. Expect delivery of first table+shields from Iran end of September 03. Second set by spring 2004.

All PMTs have been delivered to IOWA and testing is >90% complete

85% of quartz fibers have been delivered to CERN and are being cleaved and bundled in Hungary

21/36 wedges will be completed in May ’03HF quarters will be taken to SX5 for integration and testing

Page 19: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 19

Fiber stuffing at CERNFiber stuffing at CERNFiber stuffing at CERNFiber stuffing at CERN

Page 20: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 20

WBS Items for RBX WBS Items for RBX InstallationInstallation

WBS Items for RBX WBS Items for RBX InstallationInstallation

WBS ItemsHB

2.1.1.7.10 Connect HB-1 and HB+1 Readout Boxes $91,182.00

2.1.1.7.10.1 Install Instrumentation $9,828.00

2.1.1.7.10.2 Install Cooling Pipes $9,828.00

2.1.1.7.10.3 Install HV/LV Cables $9,828.00

2.1.1.7.10.4 QA/QC on HV/LV Cables $2,730.00

2.1.1.7.10.5 Install Signal Cables $19,656.00

2.1.1.7.10.6 Install RM's w/QIE in HB-1 Readout Boxes $19,656.00

2.1.1.7.10.7 Install RM's w/QIE in HB+1 Readout Boxes $19,656.00

2.1.1.7.11 Connect and Test HB-1 and HB+1 $61,425.00

HO

2.2.1.3.3 Install Readout Boxes in HO-0 $3,276.00

2.2.1.3.3.4 QA/QC on HV/LV Cables $3,276.00

2.2.1.3.4 Install Readout Boxes in HO+/- $3,276.00

2.2.1.3.4.4 QA/QC on HV/LV Cables $3,276.00

HE

2.3.1.4.3 Connect HE-1 and HE+1 Readout Boxes $40,185.60

2.3.1.4.3.1 Install Instrumentation $7,862.40

2.3.1.4.3.2 Install Cooling Pipes $7,862.40

2.3.1.4.3.3 Install HV/LV Cables $7,862.40

2.3.1.4.3.4 QA/QC on HV/LV Cables $8,736.00

2.3.1.4.3.5 Install Signal Cables $7,862.40

HF

2.5.1.7 HF Assembly/Installation SX-5 and UX55 $13,104.00

2.5.1.7.3 Install Gas Lines to PMT's $4,368.00

2.5.1.7.4 Install HV/LV Cables $4,368.00

2.5.1.7.5 Install Signal Cables $4,368.00

2.5.1.14 HF Optical installation EDIA $40,267.50

Page 21: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 21

Summary of Partial Summary of Partial Installation CostsInstallation Costs

Summary of Partial Summary of Partial Installation CostsInstallation Costs

HB Costs• Install RBX services, etc. $91,182

HO Costs• Install RBX services, etc. $ 6,552

HE Costs• Install RBX services, etc $40,185

HF Costs• Services $13,104• Other assembly costs $40,207

LV installation is now subsumed under Project Office efforts

Page 22: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 22

HCAL M&OHCAL M&OHCAL M&OHCAL M&O

There was a Lehman review at FNAL on April 8, 9 & 10. The M&O proposal for CMS was baselined (budget approved).

• Engineering personnel and techs at CERN for detector maintenance (shared with EMU)

• “Slice Test” as pre-ops during 2004-2006

• Test Beam work beginning in 2004

• Physics monitoring at CERN

Page 23: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 23

Vertical Slice TestVertical Slice TestVertical Slice TestVertical Slice Test

We will operate the calorimeters during the period after the detectors are complete but before the CMS magnet test. This will give us a headstart on commissioning the full CMS. This period is approximately from winter 03 to winter 05.

We will need the following technical personnel at CERN for this 2 year period (as well as supervising physicists) :

• HPD/RBX Maintenance EE (1 FTE) • FE Electronics maintenance & integration EE (1/2 FTE)• Trigger/DAQ Integration EE (1/2 FTE)• Calibration System Engineer (1/2 FTE)• DCS/Database Software Professional (1FTE) • DAQ Software Professional (1 FTE) • Electronics maintenance ETech (1 FTE)• Mechanical maintenance MTech (1 FTE)

Page 24: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 24

Long-term M&O ManpowerLong-term M&O ManpowerLong-term M&O ManpowerLong-term M&O Manpower2 FTE Electronics Engineers:

HPD maintenanceFE/HPD interface issuesFE maintenanceTrigger/DAQ maintenance

3 Software Professionals:Calibration/DAQDCS/DatabaseVirtual Control Room development/maintenance

1 Electronic Technician:FE maintenanceCalibration maintenanceTrigger/DAQ maintenanceHV/LV maintenance

1 Mechanical technician:HCAL optics maintenance, integrationCalibration system maintenance

1 Computer technician:HCAL computer systems maintenance, software

installation/maintenance, database maintenance

Page 25: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 25

Summary of M&O M&S ItemsSummary of M&O M&S ItemsSummary of M&O M&S ItemsSummary of M&O M&S Items

Supplies: Water and Nitrogen $2K/yrCERN stock room $50K/yrOffice Supplies at CERN $20K/yrCERN Vans $12K/yr

Activities: Shipping $20K/yrTelecom (video conferences) $20K/yrTravel $50K/yr

Computing Needs:Workstations and software $40K/yr

Major One-time Replacements1/3 of scintillator for HE (RadDam) $100K1/2 of HF PMT’s (RadDam) $250K

Page 26: Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 1 WBS 2 - Hadron Calorimeter Andris Skuja HCAL Schedule at CERN

Andris Skuja: US CMS DOE/NSF Review: HCAL Subsystem Session May 20, 2003: Schedule, etc. 26

Summary and ConclusionsSummary and ConclusionsSummary and ConclusionsSummary and Conclusions

• The Installation Planning Process has begun.

• Pawel de Barbaro is the chief physicist at CERN guiding the installation and commissioning phase. He will be aided by Richard Kellogg and a number of engineers, software experts, and other physicists.

• The schedule for ‘03 and later is understood. Manpower at CERN is built up using pre-ops funding. Installation costs are maintained by the construction Project and final installation in UX5 will be accomplished by CERN designated technicians.

• Once the FE & TRIDAS electronics is at CERN a number of technicians, engineers and physicists will be required at CERN. Detailed planning for their activities has started. We plan to commission the electronics before the CMS magnet tests.

• The UX5 activities are also defined.