No. KOEF SAT. Rp Rp 1 m2 Bahan Subtotal 77.220,00 15 bh Genteng Plentong & genteng S kecil 5.148,00 77.220,00 Tenaga Subtotal 21.932,80 0,16 OH Pekerja 57.385,00 9.181,60 0,08 OH Tukang batu 79.200,00 6.336,00 0,008 OH Kepala Tukang 84.150,00 673,20 0,08 OH Mandor 71.775,00 5.742,00 1 m1 Bahan Subtotal 68.057,55 10 m3 Portland Semen (PC) 1.485,00 14.850,00 0,033 lbr Pasir Pasang (PP) 262.350,00 8.657,55 5 kg Genteng nok Plentong & S kecil 8.910,00 44.550,00 Tenaga Subtotal 33.530,00 0,32 OH Pekerja 57.385,00 18.363,20 0,16 OH Tukang kayu 79.200,00 12.672,00 0,016 OH Kepala Tukang 84.150,00 1.346,40 0,016 OH Mandor 71.775,00 1.148,40 1 m2 Bahan Subtotal 31.927,50 0,3 kg Waterproofing 49.500,00 14.850,00 1 lbr Kain kassa 14.850,00 14.850,00 0,25 bh Kuas 8.910,00 2.227,50 Tenaga Subtotal 20.480,20 0,1056 OH Pekerja 57.385,00 6.059,86 0,16 OH Tukang 79.200,00 12.672,00 0,016 OH Kepala Tukang 84.150,00 1.346,40 0,0056 OH Mandor 71.775,00 401,94 1 m2 Subtotal Bahan 45.540,00 1 m1 Atap Galvalum 39.600,00 39.600,00 4 bh Skrup Fixer 1.485,00 5.940,00 Tenaga 24.924,00 0,12 OH Pekerja 57.385,00 6.886,20 0,16 OH Tukang Kayu 79.200,00 12.672,00 0,016 OH Kepala Tukang Batu 84.150,00 1.346,40 0,056 OH Mandor 71.775,00 4.019,40 D A F T A R A N A L I S A P E K E R J A A N URAIAN PEKERJAAN Pek. Pasangan Atap Genteng Plentong & Genteng S ( Kecil ) Pek. Pasangan Nok Genteng Plentong & Genteng S ( Kecil ) Pek. Waterproofing (2 Lapis) Pek. Pasangan Atap Galvalum

Analisa Term

  • Upload
    vesbulk

  • View
    23

  • Download
    1

Embed Size (px)

DESCRIPTION

Analisa Term

Citation preview

Page 1: Analisa Term

No. KOEF SAT.Rp Rp

1 m2

Bahan Subtotal 77.220,0015 bh Genteng Plentong & genteng S kecil 5.148,00 77.220,00

Tenaga Subtotal 21.932,800,16 OH Pekerja 57.385,00 9.181,600,08 OH Tukang batu 79.200,00 6.336,00

0,008 OH Kepala Tukang 84.150,00 673,200,08 OH Mandor 71.775,00 5.742,00

1 m1

Bahan Subtotal 68.057,5510 m3 Portland Semen (PC) 1.485,00 14.850,00

0,033 lbr Pasir Pasang (PP) 262.350,00 8.657,555 kg Genteng nok Plentong & S kecil 8.910,00 44.550,00

Tenaga Subtotal 33.530,000,32 OH Pekerja 57.385,00 18.363,200,16 OH Tukang kayu 79.200,00 12.672,00

0,016 OH Kepala Tukang 84.150,00 1.346,400,016 OH Mandor 71.775,00 1.148,40

1 m2

Bahan Subtotal 31.927,500,3 kg Waterproofing 49.500,00 14.850,00

1 lbr Kain kassa 14.850,00 14.850,000,25 bh Kuas 8.910,00 2.227,50

Tenaga Subtotal 20.480,200,1056 OH Pekerja 57.385,00 6.059,86

0,16 OH Tukang 79.200,00 12.672,000,016 OH Kepala Tukang 84.150,00 1.346,40

0,0056 OH Mandor 71.775,00 401,94

1 m2

SubtotalBahan 45.540,00

1 m1 Atap Galvalum 39.600,00 39.600,004 bh Skrup Fixer 1.485,00 5.940,00

Tenaga 24.924,000,12 OH Pekerja 57.385,00 6.886,200,16 OH Tukang Kayu 79.200,00 12.672,00

0,016 OH Kepala Tukang Batu 84.150,00 1.346,400,056 OH Mandor 71.775,00 4.019,40

D A F T A R A N A L I S A P E K E R J A A N

URAIAN PEKERJAAN

Pek. Pasangan Atap Genteng Plentong & Genteng S ( Kecil )

Pek. Pasangan Nok Genteng Plentong & Genteng S ( Kecil )

Pek. Waterproofing (2 Lapis)

Pek. Pasangan Atap Galvalum

Page 2: Analisa Term

1 m2

Bahan Subtotal 166.815,001,10 m2 Polycarbonat 123.750,00 136.125,000,50 roll Almunium strip 49.500,00 24.750,004,0 Bh Skrup Fixer 1.485,00 5.940,00

Tenaga Subtotal 18.896,300,08 OH Pekerja 57.385,00 4.590,800,160 OH Tukang besi 79.200,00 12.672,000,016 OH Kepala Tukang 84.150,00 1.346,400,004 OH Mandor 71.775,00 287,10

1 m1

Bahan Subtotal 74.465,330,600 Lbr Seng Bjls 30 24.750,00 14.850,000,012 M3 Papan 2/20 Kayu kls II 4.950.000,00 59.400,000,015 Kg Paku 2'-5' 14.355,00 215,33

Tenaga Subtotal 80.463,100,40 OH Pekerja 57.385,00 22.954,000,64 OH Tukang Kayu 79.200,00 50.688,000,06 OH Kepala Tukang 84.150,00 5.385,600,02 OH Mandor 71.775,00 1.435,50

1 m2 Pek. Pasangan Plafond Gypsum / Calsiboard

Bahan Subtotal 65.637,001,1 Btg Hollo 0,5 29.700,00 32.670,000,5 Lbr Gypsum tbl 9 mm 64.350,00 32.175,00

4 Bh Paku Skrup 198,00 792,00

Tenaga Subtotal 76.966,640,224 OH Pekerja 57.385,00 12.854,240,64 OH Tukang batu 79.200,00 50.688,00

0,064 OH Kepala Tukang 84.150,00 5.385,600,112 OH Mandor 71.775,00 8.038,80

1 m1

Bahan Subtotal 16.929,001,1 btg Lis Gypsum 14.850,00 16.335,00

3 bh Paku skrup 198,00 594,00

Tenaga Subtotal 7.465,330,05 OH Pekerja 57.385,00 2.869,250,05 OH Tukang Cat 79.200,00 3.960,00

0,005 OH Kepala Tukang 84.150,00 420,750,003 OH Mandor 71.775,00 215,33

1 m2

Bahan Subtotal 22.275,000,3 kg Cat weathershield 74.250,00 22.275,00

Tenaga Subtotal 20.480,200,1056 OH Pekerja 57.385,00 6.059,86

0,16 OH Tukang Cat 79.200,00 12.672,000,016 OH Kepala Tukang 84.150,00 1.346,40

0,0056 OH Mandor 71.775,00 401,94

Pek. Pasangan Atap Policarbonate

Pek.Pengecatan Tembok ( 2 Lapis )

Pek. Pasangan Talang Datar Bjls 30

Pek.Pasang List Plafond

Page 3: Analisa Term

1 m2 Pasang Dinding Keramik 20 x 25 cm

Bahan Subtotal 80.011,801 M2 Ubin Keramik 20 x 25 cm 64.350,00 64.350,00

5,6 Kg Portland Semen 1.485,00 8.316,000,028 m3 Pasir Pasang 262.350,00 7.345,80

Tenaga Subtotal 83.825,000,8 OH Pekerja 57.385,00 45.908,000,4 OH Tukang Batu 79.200,00 31.680,00

0,04 OH Kepala Tukang 84.150,00 3.366,000,04 OH Mandor 71.775,00 2.871,00

1 m2 Pasang Lantai Keramik 40 x 40 cm

Bahan Subtotal 178.125,751 M2 Ubin Keramik 40 x 40 cm 69.300,00 69.300,00

5,2 Kg Portland Semen 1.485,00 7.722,000,35 m3 Pasir Pasang 262.350,00 91.822,503,75 Kg Semen Putih 2.475,00 9.281,25

Tenaga Subtotal 41.912,500,4 OH Pekerja 57.385,00 22.954,000,2 OH Tukang Batu 79.200,00 15.840,00

0,02 OH Kepala Tukang 84.150,00 1.683,000,02 OH Mandor 71.775,00 1.435,50

1 m2 Pasang Lantai Granit Ukuran 60x60 cm

Bahan Subtotal 243.292,501,05 M2 Granit 60 x 60 198.000,00 207.900,0012,5 Kg Portland Semen 1.485,00 18.562,500,05 m3 Pasir Pasang 262.350,00 13.117,501,5 Kg Semen Warna 2.475,00 3.712,50

Tenaga Subtotal 67.341,380,45 OH Pekerja 57.385,00 25.823,250,45 OH Tukang Batu 79.200,00 35.640,000,04 OH Kepala Tukang 84.150,00 3.366,00

0,035 OH Mandor 71.775,00 2.512,13

1 Unit Memasang Closet Duduk / Mono Blok ex Toto

Bahan Subtotal 2.938.320,001 Buah Kloset Duduk / Monoblok 2.772.000,00 2.772.000,00

0,06 Kelengkapan 6% dari harga Kloset 2.772.000,00 166.320,00

Tenaga Subtotal 56.511,500,5 OH Pekerja 57.385,00 28.692,50

0,25 OH Tukang Batu 79.200,00 19.800,000,01 OH Kepala Tukang 84.150,00 841,500,1 OH Mandor 71.775,00 7.177,50

1 Unit Memasang Urinoir

Bahan Subtotal 2.298.186,001 Buah Urinoir ex toto 2.168.100,00 2.168.100,00

0,06 Kelengkapan 6% dari harga Urinoir 2.168.100,00 130.086,00

Tenaga Subtotal 56.511,500,5 OH Pekerja 57.385,00 28.692,50

Page 4: Analisa Term

0,3 OH Tukang Batu 79.200,00 19.800,000,0 OH Kepala Tukang 84.150,00 841,50

0,10 OH Mandor 71.775,00 7.177,50

1 Unit Memasang Wastafel

Bahan Subtotal 2.361.150,001 Buah Wastafel ex toto 2.227.500,00 2.227.500,00

0,06 - Perlengkapan 30% Harga Wastafel 2.227.500,00 133.650,00

Tenaga Subtotal 56.511,500,5 OH Pekerja 57.385,00 28.692,50

0,25 OH Tukang Batu 79.200,00 19.800,000,01 OH Kepala Tukang 84.150,00 841,500,1 OH Mandor 71.775,00 7.177,50

1 Unit

Bahan Subtotal 1.574.100,001,00 bh Kunci silinder 1.485.000,00 1.485.000,00

6% Kelengkapan 6% 1.485.000,00 89.100,00

Tenaga Subtotal 40.487,110,005 OH Pekerja 57.385,00 286,930,500 OH Tukang Batu 79.200,00 39.600,000,005 OH Kepala Tukang 84.150,00 420,750,003 OH Mandor 71.775,00 179,44

1 Unit

Bahan Subtotal 524.700,001,00 bh Kunci slot kaca 495.000,00 495.000,00

6% Kelengkapan 6% 495.000,00 29.700,00

Tenaga Subtotal 40.487,110,005 OH Pekerja 57.385,00 286,930,500 OH Tukang Batu 79.200,00 39.600,000,005 OH Kepala Tukang 84.150,00 420,750,003 OH Mandor 71.775,00 179,44

1 Unit

Bahan Subtotal 314.820,001,00 bh Kunci pintu 297.000,00 297.000,00

6% Kelengkapan 6% 297.000,00 17.820,00

Tenaga Subtotal 40.487,110,005 OH Pekerja 57.385,00 286,930,500 OH Tukang Batu 79.200,00 39.600,000,005 OH Kepala Tukang 84.150,00 420,750,003 OH Mandor 71.775,00 179,44

1 Unit

Bahan Subtotal 76.725,001,20 m1 Pipa PVC 4" 49.500,00 59.400,0035% Kelengkapan 35^ 49.500,00 17.325,00

Tenaga Subtotal 52.299,44

Memasang Kunci Pintu Kaca Utama

Memasang Kunci Pintu Kaca Toilet

Memasang Kunci Pintu Panel /Allumunium

Memasang Pipa PVC 4 "

Page 5: Analisa Term

0,786 OH Pekerja 57.385,00 45.104,610,060 OH Tukang Batu 79.200,00 4.752,000,006 OH Kepala Tukang 84.150,00 504,900,027 OH Mandor 71.775,00 1.937,93

Page 6: Analisa Term
Page 7: Analisa Term
Page 8: Analisa Term
Page 9: Analisa Term
Page 10: Analisa Term
Page 11: Analisa Term
Page 12: Analisa Term
Page 13: Analisa Term
Page 14: Analisa Term
Page 15: Analisa Term
Page 16: Analisa Term
Page 17: Analisa Term
Page 18: Analisa Term
Page 19: Analisa Term
Page 20: Analisa Term
Page 21: Analisa Term
Page 22: Analisa Term
Page 23: Analisa Term
Page 24: Analisa Term
Page 25: Analisa Term
Page 26: Analisa Term
Page 27: Analisa Term
Page 28: Analisa Term
Page 29: Analisa Term
Page 30: Analisa Term
Page 31: Analisa Term
Page 32: Analisa Term
Page 33: Analisa Term
Page 34: Analisa Term
Page 35: Analisa Term
Page 36: Analisa Term
Page 37: Analisa Term
Page 38: Analisa Term
Page 39: Analisa Term
Page 40: Analisa Term
Page 41: Analisa Term
Page 42: Analisa Term
Page 43: Analisa Term
Page 44: Analisa Term
Page 45: Analisa Term
Page 46: Analisa Term
Page 47: Analisa Term
Page 48: Analisa Term
Page 49: Analisa Term
Page 50: Analisa Term
Page 51: Analisa Term
Page 52: Analisa Term
Page 53: Analisa Term
Page 54: Analisa Term
Page 55: Analisa Term
Page 56: Analisa Term
Page 57: Analisa Term
Page 58: Analisa Term
Page 59: Analisa Term
Page 60: Analisa Term
Page 61: Analisa Term
Page 62: Analisa Term
Page 63: Analisa Term
Page 64: Analisa Term
Page 65: Analisa Term
Page 66: Analisa Term
Page 67: Analisa Term
Page 68: Analisa Term
Page 69: Analisa Term
Page 70: Analisa Term
Page 71: Analisa Term
Page 72: Analisa Term
Page 73: Analisa Term
Page 74: Analisa Term
Page 75: Analisa Term
Page 76: Analisa Term
Page 77: Analisa Term
Page 78: Analisa Term
Page 79: Analisa Term
Page 80: Analisa Term
Page 81: Analisa Term
Page 82: Analisa Term
Page 83: Analisa Term
Page 84: Analisa Term
Page 85: Analisa Term