40
AFCI Separations Activities R. T. Jubin Nuclear Science and Technology Division Oak Ridge National Laboratory Presented at: Joint ANS/AIChE Local Section Meeting Knoxville, TN February 10, 2009 The submitted manuscript has been authored by a contractor of the U.S. Government under contract DE-AC05-00OR22725. Accordingly, the U.S. Government retains a nonexclusive, royalty-free license to publish or reproduce the published form of this contribution, or allow others to do so, for U.S. Government purposes.

AFCI Separations Activities

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

AFCI Separations Activities

R. T. JubinNuclear Science and Technology DivisionOak Ridge National Laboratory

Presented at:Joint ANS/AIChE Local Section MeetingKnoxville, TNFebruary 10, 2009

The submitted manuscript has been authored by a contractor of the U.S. Government under contract DE-AC05-00OR22725. Accordingly, the U.S. Government retains a nonexclusive, royalty-free license to publish or reproduce the published form of this contribution, or allow others to do so, for U.S. Government purposes.

February 10, 2009 ANS/AIChE Local Section Meeting 2

Overview

Separations Campaign OverviewKey Campaign Accomplishment / GoalsCoupled End to End (CETE) ProjectOff-gas Treatment– ORNL– INL– SNL

Centrifugal Contactors– INL

February 10, 2009 ANS/AIChE Local Section Meeting 3

Separations Campaign Program Overview

Major program elements– Advanced aqueous separations– Advanced electrochemical separations– Process equipment scale-up and

development– Off-gas treatment– Process control and monitoring– Process modeling and simulation– EBR-II spent fuel treatment– Separations regulatory and safety

crosscut

February 10, 2009 ANS/AIChE Local Section Meeting 4

Separations Campaign FY-08 Major Accomplishments

Revised campaign research strategy for aqueous processing– De-emphasize repetitive testing of separation process at lab-scale

using small amounts of used nuclear fuel– Focus on head-end operations

• Voloxidation to separate tritium• Off-gas capture and immobilization of 129I, 85Kr (and Xe), 3H, 14C

– Demonstrate product conversion using modified direct denitration– Transition development activities from laboratory testing to

engineering development• Incorporate industry input into campaign development activities• Increase Technology Readiness Levels (TRL’s) > 6• Incorporate solvent recycle effects into testing

– Integrate Waste Form development with Separations development

February 10, 2009 ANS/AIChE Local Section Meeting 5

Separations Campaign FY-08 Major Accomplishments

Revised campaign research strategy for aqueous processing– Focus on simplification of separation processes

• Decay store HLW rather than separate Cs/Sr• Reduce number of separation steps and separated products

– Separate U/Pu/Np together by manipulating valance states• Combine TRUEX/TALSPEAK or use alternative technology

– Avoid dependence on rigid pH control– Develop science-based approach to develop alternative Am/Cm

separation process• Formation of “SIGMA TEAM”• Multi-lab team focused on development of robust separation

process for separation of Am or Am/Cm in a single step

February 10, 2009 ANS/AIChE Local Section Meeting 6

Separations strategy evolution

February 10, 2009 ANS/AIChE Local Section Meeting 7

Selected Development Focus Areas for Aqueous Technologies

Focus on simplification of process is key objective to improve operation and reliability and reduce cost

– Studies have shown that the UREX+ separations options are complicated and costly

– Largest challenge is separation of Am/Cm or Am alone• Focus area for Sigma Team

CETE Run 2 (focus on off-gas capture and MDD)Capture and immobilization of volatile off-gas (129I, 85Kr, 3H, 14C?)

– Voloxidation to separate tritium– Off-gas capture and immobilization

Testing at scales larger than laboratory scale, in prototypic equipment w/ solvent recycle (increase TRL’s)Integration of separations and waste form development activities (each affects the other)Process monitoring and control improvements Collaboration with industrial teams to identify and resolve design data needs

February 10, 2009 ANS/AIChE Local Section Meeting 8

Introduction to the CETE Demonstration

Develop/Demonstrate Advanced Recycling TechnologiesMultiple process runs ~ 5 - 10 kgs/yr of SNFIdentify and Resolve Scientific & Technical Uncertainties – Interfacial Issues– Process Robustness

Provide Research Products for Evaluation Across DOE Complex– Actinides– FP Waste form

FY09: Focus on Head End Processing and Product Conversions

February 10, 2009 ANS/AIChE Local Section Meeting 9

Coupled-End-to-End Demonstration Overview

Pellet Preparation

Solvent Extraction

Voloxidation

Chopping

Spent LWR Fuel In

ProductConversion

Fuel Pellets Out

Irradiated Fuels Examination LaboratoryBuilding 3525

Radiochemical Engineering Development Center (REDC) Building 7920

Technetium (LANL)Technetium (LANL)

UREX ProductUREX Product

Uranyl Nitrate Solution(Balance of Uranium)

FPEX, FPsFPEX, FPs

Cs/SrCs/Sr

LnLn

UREX+ Raffinate(Am/Cm, FPs)

UREX+ Raffinate(Am/Cm, FPs) TRUEX

RaffinateTRUEX

Raffinate

Am/Cm plusLanthanideFission Products

Am/Cm plusLanthanideFission Products

Am/Cm

UREXProduct

Dissolution

OffgasTreatmentDissolver

Off-gas Treatment

FuelExamination

Modified Direct Denitration

Mixer Settler

FPEX Process

TRUEXProcess Waste Forms

Development

UREX+ CodeconProcess

TALSPEAK Process

OffgasTreatment

Off-gas Treatment

Pressed MOX Pellet

Fuel Rod Examination

February 10, 2009 ANS/AIChE Local Section Meeting 10

Highlights and Lessons Learned from CETE Run 1

Flowsheet Demonstration– Partial partitioning of a U-Pu-Np

Product: No separated Pu– TRUEX-TALSPEAK for Minor

Actinide Separation– FPEX for Cs/Sr Separation

Converted U-Pu-Np and U by Modified Direct Denitration

Demonstrated Fabrication U-Pu-Np co-converted product to pellets.

Removal and disposal or recycle of the residual chemical complexants(DTPA/Lactic Acid) used in the TRUEX-TALSPEAK processes from the americium-curium product is difficult.

– Recovery by re-extraction into HDEHP has been successful

February 10, 2009 ANS/AIChE Local Section Meeting 1111

Product Conversions

Modified Direct Denitration shows promise for simplifying the interface between separation and fuel fabrication.

Produces a powder with good ceramic properties for pellet fabrication.

Further R&D requiredProcess developmentScaleupQualifying the ceramic product

Microscope Image of Product Power

SEM Image of Product Power

U/Pu/Np Oxide

Pellets

February 10, 2009 ANS/AIChE Local Section Meeting 12

Volox #1Surry

Volox #1Surry

OG

7920

50 mgSample

DissolutionDissolution

OG

Clarification

UDS

Volox #2No. AnnaVolox #2No. Anna

OG

7920

50 mgSample

DissolutionDissolution

OG

Clarification

UDS

Volox #3No. AnnaVolox #3No. Anna

OG

7920

50 mgSample

DissolutionDissolution

OG

Clarification

UDS

Feed Adj.and

Re-Clarif.

SX-1TBP/NPH

Co-ExtractionCo-Strip

SX-1TBP/NPH

Co-ExtractionCo-Strip

U, Pu,Np, Tc

FeedAdj.

SX-3TBP/NPH

Co-ExtractionPartial

Partition

SX-3TBP/NPH

Co-ExtractionPartial

Partition

SX-2TBP/NPH

AnLnSeparation

SX-2TBP/NPH

AnLnSeparation

Am, Cm,Ln

Evap.to 5L

SX-4Reverse

TALSPEAK

SX-4Reverse

TALSPEAK

HLac-DTPA

Ln

RaffinateRW

FP WasteStorage

Camp 1FP Waste

Raffinate

Feed Adjustment

InextractableNitrate Salt

Tc

U-Pu-Np

Am, Cm

MDD

Adj topH 1.0

U MDD

CIX/CalcineCIX/

Calcine

AmCmOxide

CETE Run 2 Plans

February 10, 2009 ANS/AIChE Local Section Meeting 13

Management of Volatile Fission Products

Volatile components that must be considered have a wide range of half-lives and disposal requirements:− 3H 12.31 yr − 14C 5715 yr− Xe/85Kr Stable/10.76 yr− 129I 1.57 x 107 yr

Regulatory Drivers, some not written with consideration for full-scale reprocessing facilities, unlikely to be relaxedData still needed on process integration and removal process interactions– Description of integrated capture systems for CETE Demo– Complemented by cold Bench-scale testing at INL– Waste form work for Iodine at SNL

February 10, 2009 ANS/AIChE Local Section Meeting 14

Federal regulations limit radionuclide air emissions in the U.S.

85Kr: <50,000 Ci129I: <5 mCi239Pu: <0.5 mCi

Max fuel cycle emissions per GWyr

energy produced

3H: 1.0E-714C as CO2: 3.0E-785Kr: 7.0E-7129I: 4.0E-11

Ambient air conc at site boundary, Ci/m3

100NRC licensees (10CFR20.1301, .1302, App. B)

10 (3 from 129I

alone)

Others (40CFR61.102)

25 (75 to thyroid, 25 to any other

organ)

Nuclear fuel cycle (40CFR190.10)

10DOE facilities (40CFR61.92)

Dose equivalent to public, mrem/yr

February 10, 2009 ANS/AIChE Local Section Meeting 15

40 CFR 190 Derived Process Requirements

4.77239,000712185Kr (5 year cooled)

Min Required DFCi/GW(e)-yrCi/MTIHMIsotope1780.890.02648129I

0.9547,000141485Kr (30 year cooled)

3.45173,000515485Kr (10 year cooled)

Note: Burn-up: 55 GWd/MTIHM

4.67234,0001162085Kr (5 year cooled)

Min Required DFCi/GW(e)-yrCi/MTIHMIsotope1670.830.04149129I

0.9346,000230985Kr (30 year cooled)2.38169,000841385Kr (10 year cooled)

Note: Burn-up: 33 GWd/MTIHM

February 10, 2009 ANS/AIChE Local Section Meeting 16

Simple Reprocessing Demonstration(Mass Basis: 1 kg SNF; 55 GWD/MTIHM; 5 year Cooling)

06-087

Stack

LWR Spent Fuel

1.292 kg889 Ci

LWR Spent Fuel

1.292 kg889 Ci

Disassembly, Voloxidation, Dissolution

Disassembly, Voloxidation, Dissolution

Primary Separation StepsPrimary Separation StepsFission Product

Stabilization

Fission Product

Stabilization

HLW FormHLW Form

LLWLLW

129I0.29 g

4.0x10-5 Ci

129I0.29 g

4.0x10-5 Ci

Hulls292 gHulls292 g

U931 g

U931 g

Tc1.2 gTc

1.2 gCs/Sr9.22 gCs/Sr9.22 g

Pu/Np11.8 gPu/Np11.8 g

Am/Cm0.70 g

Am/Cm0.70 g

Fission Product36.4 g

143.6 Ci

Fission Product36.4 g

143.6 Ci

Xe8.86 g / ~0 Ci

Kr0.60 g / 11.6 Ci

Xe8.86 g / ~0 Ci

Kr0.60 g / 11.6 Ci

•DOG3H

1.0 x 10-4 g0.88 Ci

3H1.0 x 10-4 g

0.88 Ci

14C1.6 x 10-4 g7.4 x 10-4 Ci

14C1.6 x 10-4 g7.4 x 10-4 Ci

UDS~1-5 gUDS

~1-5 g

129I0.01 g

1.0x10-6 Ci

129I0.01 g

1.0x10-6 Ci

•VOG

February 10, 2009 ANS/AIChE Local Section Meeting 17

Generic Head-End Off-Gas Treatment Concept

Shear Voloxidizer Dissolver

HTO I Bed

HEPA

Ru Trap

CausticScrub Drier Xe Bed Kr Bed HEPA

Condenser

NOx AbsorberVOG

Catalytic oxidizerMS (3A) captureRelease from MSCondenseMix in cementIn-can groutingDispose - SLB

Ag-Z captureRemove bedEncapsulatePackageDispose - Rep

NaOH scrubRemoveMix in cementIn-can groutingDispose - SLB

Cryogenic Ag-ZRelease

from Ag-ZCombine w/ Kror Release

Cryogenic HZRelease

from HZCombine w/ XePressurizeBottleDecay storage

RemoveLeachDispose - SLB

SolventExtraction

February 10, 2009 ANS/AIChE Local Section Meeting 18

FY 09 CETE Based Tests (ORNL)

Hot Integrated Off-gas capture tests on the Voloxidation and Dissolver Off-Gas streams– Objectives

• Close volatile component material balances– Voloxidation– Dissolution

• Analysis for residual iodine in dissolver solution– Shearing of full length fuel – Run 3 or later

• Understand impacts of head-end processing conditions on volatile component releases

• Determine capture process interactions

February 10, 2009 ANS/AIChE Local Section Meeting 19

Voloxidation Run 2—Plan and Status

Voloxidation processing for Run 2 was planned as three batches– Batch sizes of 1 to 2 kg of spent fuel– Total production of at least 5 kg to support separations activities– Different conditions were planned for each batch to obtain information on

reaction properties and subsequent dissolution properties of product powder (e.g. undissolved solids)

Flexibility was built into the test plan to permit selection of alternative fuel materials, depending upon availability

550.oxygen2North Anna3

600.Air2North Anna2

500.Air1–2Surry-21

Temperature (°C)OxidantFuel Amt (kg)Fuel SourceBatch

February 10, 2009 ANS/AIChE Local Section Meeting 20

Small Scale Voloxidation

Most of the retort tube is enveloped by the furnaceRotating tubeVariable operating environmentRemovable Hulls basketPowder can integrated into designTilting platform can force material into hotter zones

February 10, 2009 ANS/AIChE Local Section Meeting 21

Voloxidation

Rotary Kiln w/ Heater in Place

Product Canister

February 10, 2009 ANS/AIChE Local Section Meeting 22

Voloxidizer Off-Gas Rack

Krypton ColumnXenon Column

Carbon-14 Scrubber

Iodine Column

Tritium Column

February 10, 2009 ANS/AIChE Local Section Meeting 23

Voloxidation Run 2—Batch 1

First batch was comprised of Surry-2 fuel– Initial enrichment 3.11%– Burnup: 36 GWd/MT heavy metal– Cooling time: 27 years (discharged from reactor in 1981)– Amount: 1704 g (316 g hulls, 1388 g fuel)

Experiment– Fuel was oxidized in air at about 500°C– The run was prematurely terminated due to apparent cessation of oxygen consumption

• Occurred after 4 hours of operation at temperature• Weighing of product powder and hulls showed that fuel was only 70% oxidized• There was potential for a cold zone near the closure flange, causing slow kinetics

– Complete batch of fuel was re-run to finish the oxidation• Operation at temperature for 4 hours was done to ensure complete oxidation

– 1542 g fuel powder recovered (indicates DU carry-over from shakedown run)• The voloxidizer was periodically tilted from the horizontal to cause fuel to migrate from the

cold zone into the hot furnace zone• Both oxygen consumption and 85Kr evolution was used to monitor progress and reaction

endpoint

February 10, 2009 ANS/AIChE Local Section Meeting 24

Run 2—Batch 1—Part AO2 Concentration, Air Flow, and Temperatures

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

18:00 19:12 20:24 21:36 22:48 0:00 1:12 2:24

Time

Flow

(std

L/m

in)

ExhaustAir Feed

0

100

200

300

400

500

600

18:00 19:12 20:24 21:36 22:48 0:00 1:12 2:24

Time

Volo

x C

ente

r Tem

ps (C

)

TE-108TE-109TE-110

0

20

40

60

80

100

120

18:00 19:12 20:24 21:36 22:48 0:00 1:12 2:24

Time

O2

Conc

n. (1

00%

= 0

.21

v/v)

-200

0

200

400

600

800

1000

1200

1400

Raw

G C

ount Exhaust O2

Feed O2Kr inKr out

February 10, 2009 ANS/AIChE Local Section Meeting 25

Run 2—Batch 1—Part BO2 Concentration, Air Flow, and Temperatures

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

12:00 13:12 14:24 15:36 16:48 18:00 19:12 20:24 21:36

Time

Flow

(std

L/m

in)

ExhaustAir Feed

0

100

200

300

400

500

600

12:00 13:12 14:24 15:36 16:48 18:00 19:12 20:24 21:36

Time

Volo

x C

ente

r Tem

ps (C

)

TE-108TE-109TE-110

0

20

40

60

80

100

120

12:00 13:12 14:24 15:36 16:48 18:00 19:12 20:24 21:36

Time

O2

Con

cn. (

100%

= 0

.21

v/v)

-100

-50

0

50

100

150

200

250

300

350

400

450

Raw

G C

ount

Exhaust O2Feed O2Kr in

February 10, 2009 ANS/AIChE Local Section Meeting 26

Summary of INL Off-Gas Work

FY08: Initiated bench-scale iodine capture studies using nonradioactive constituents

FY09: Continue iodine capture work:– Use commercial sorbent IONEX Type Ag 900– Determine DFs under varying conditions (iodine concentration,

co-constituents, temperature, residence times)• Dissolver off-gas may contain iodine at ~10 ppm• Combined vessel off-gas may contain iodine at ~10 ppb

– Determine sorbent capacity

February 10, 2009 ANS/AIChE Local Section Meeting 27

Summary of INL Off-Gas Work

FY09: Install additional sorption columns for water vapor, CO2 and Xe (ambient temperature operations)– An integrated bench-scale treatment unit– Currently plan to run with nonradioactive constituents – Establish baseline capture of water vapor, CO2 and Xe on

commercial adsorbents – Test alternative sorbents– Design Kr capture system, which may be added in future

February 10, 2009 ANS/AIChE Local Section Meeting 28

Encapsulants and Glasses as Iodine Waste Form

Bismuth-containing Encapsulants– Two Trademark

Applications for US Patents submitted;• 2007, 2008

Low-Temperature Glasses for encapsulation of AgI, I2 or AgI-MOR– Glass transition temperatures

lower than sublimation temperatures of AgI or I2

– Glass compositions that enhance iodine retention

Bi-I-O in situlayered oxides

February 10, 2009 ANS/AIChE Local Section Meeting 29

Materials for Iodine Waste Streams -FY09 Plans at SNL

Sorption of I2 gas into traps for encapsulants– Low-temperature glasses– Alternative waste forms

Primary focus will be on “standard” iodine loaded AgZ materials from ORNL and INL surrogate studies and CETE Hot tests– Retention of iodine

Alternate sorbents or recovery operations to produce better waste forms

February 10, 2009 ANS/AIChE Local Section Meeting 30

Off-gas Treatment Take-aways

Multiple air emission regulations may apply to spent fuel reprocessing facilitiesGaseous fission product control efficiencies up to 99.99% (DF = 10,000) may be requiredTechnologies for controlling gaseous fission products are less established; new technologies and waste forms are under evaluationOngoing R&D is continuing to determine performance, operating conditions, and waste forms for gaseous fission product control technologies

February 10, 2009 ANS/AIChE Local Section Meeting 31

Role of Centrifugal Contactors in Aqueous Separations

Centrifugal contactors will likely play a significant role in advanced aqueous recycle of used nuclear fuel– Utilized in portions of production scale facilities– Used for development of advanced separation

processesHave several advantages over pulse columns and mixer-settlers– Less space required– High efficiency– Reach steady-state rapidly, allowing for rapid

recovery from upsets and shutdown/restart– Reduced solvent contact times

But not without a few disadvantages– Processes with slow kinetics– Processes with likelihood of large quantities of solids (clean-in-place capability

has potential to mitigate)– Remote maintenance

February 10, 2009 ANS/AIChE Local Section Meeting 32

Commercial Centrifugal Contactor Testing at the INLin 2008

Testing of remotely operable/maintainable 5-cm contactorsDesign of remotely operable/maintainable “production” scale 12.5-cm contactorsDesign and construction of 30 stage 5-cm contactor pilot plantTemperature profile testing in the newly constructed contactor pilot plant

February 10, 2009 ANS/AIChE Local Section Meeting 33

Development of Remote 5-cm Centrifugal Contactor

February 10, 2009 ANS/AIChE Local Section Meeting 34

30 Stage 5-cm Centrifugal Contactor Pilot Plant

February 10, 2009 ANS/AIChE Local Section Meeting 35

Test Objectives of Temperature Profile Testing in 30 Stage Pilot Plant

Aqueous separation flowsheets typically require some level of temperature control – often different for various sectionsLaboratory scale centrifugal contactor testing (2-cm) results in large temperature increase for the process solutions due to heat generated from the motors and low flowrates– 2-cm centrifugal contactors with heat exchanger jackets were designed

and utilized to alleviate this issueWill jacketed heat exchangers be required for engineering and production scale centrifugal contactors?– With larger flowrates it is expected that the temperature impact from

motor heat will be reduced– Heating or cooling the process feed solutions may be enough to

accomplish temperature control, preventing the need for a complex heat exchanger system for the centrifugal contactors

– ANL has developed a computer model to predict process temperature based on system design. Limited experimental data is available - Data from testing will be used by ANL to validate/improve their model.

February 10, 2009 ANS/AIChE Local Section Meeting 36

Temperature Profile Testing

Aqueous Only – Approach to Steady State – Ambient Temp

Aqueous Only – Temperature Profile – Ambient Temp

Two Phase Flow – Temperature Profile – Ambient Temp

Two Phase Flow – Temperature Profile – Strip at 50C

February 10, 2009 ANS/AIChE Local Section Meeting 37

Summary of Results of Temperature Profile Tests

Process solution temperature increased when feed solutions were at ambient temperatureAt feed temperatures of 50 ºC, heat losses were greater than the heat gain due to motor operation or heat of mixing which resulted in processes solution temperature decreasing below the feed temperatureControl of the feed solution temperature has a significant impact on process solution temperatureProcess temperature control in flowsheets using CINC 5-cm centrifugal contactors could likely be accomplished for many flowsheets by controlling the temperature of the feed solutionsProcesses that require tighter temperature control may require jacketed contactor or insulation

February 10, 2009 ANS/AIChE Local Section Meeting 38

Testing Planned for FY 2009

A prototype remotely maintainable 12.5-cm centrifugal contactor will be constructed and testedTRUEX mass transfer testing and temperature control testing will be performed using the 30 stage centrifugal contactor pilotplantA location and layout that will allow testing of the pilot plantwith depleted uranium and/or low levels of radiotracers will be evaluatedA pulse column will be set up for testing– Will be moved from the University of Idaho– Two inch glass pulse column that has approximately 20 feet of

active height and upper/lower disengagement heads– Equipped with nozzle plates and an air pulser

February 10, 2009 ANS/AIChE Local Section Meeting 39

Acknowledgements

ORNL– J. Binder– D. Ramey– B. Spencer

SNL– T. Nenoff

INL– D. Haefner– J. Law– T. Todd– N. Soelberg

Prepared by Oak Ridge National Laboratory, P.O. Box 2008, Oak Ridge, Tennessee 37831-6285, managed by UT-Battelle, LLC, for the U.S. Department of Energy under contract DE-AC05-00OR22725.

This report was prepared as an account of work sponsored by an agency of the United States government. Neither the United Statesgovernment nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States government or any agency thereof.

February 10, 2009 ANS/AIChE Local Section Meeting 40

Questions

R. T. [email protected]