TW@ESI 8 th November 2015 Hope that you and all your families had a good weekend .. The following is an update of what was achieved during the past week and a forecast of the next week By now we have most of our employees on this discussion group except Ludovic, Clinton, Lino, Manuel, Victor, Brian, Rodney, Daniele, Pawlu, Michael ... Please... All of you.. Join!!

TW@ESI Update 8th November 2015

Embed Size (px)

Citation preview

Page 1: TW@ESI Update 8th November 2015

TW@ESI8th November 2015Hope that you and all your families had a good weekend .. The following is an update of what was achieved during the past week and a forecast of the next week

By now we have most of our employees on this discussion group except Ludovic, Clinton, Lino, Manuel, Victor, Brian, Rodney, Daniele, Pawlu, Michael ... Please... All of you.. Join!!

Page 2: TW@ESI Update 8th November 2015

Projects and deadlines• We are presently executing a number of fast track projects and I

would like to summarise the major ones them as follows:– 14_081 - Siggiewi Primary School BMS- 3rd fix installation completed by

beginning of November 2015. This is progressing well and we need to ensure there are no issues here!! We need to avoid problems on testing and commissioning ... Commissioning completed by 8th December 2015- we also had a number of large variations approved on this project

– 13_076 - MDH Block D Ext MAU- Panel termination completed at the earliest possible date and IO testing has commenced now- the target is to have a form of closed loop for the AHU by the end of this week and to have most testing and commissioning works done by the end of November 2015. Mekanika will finish all the cable pulling by 12/11 – after this date we need to have a date by when all panel terminations and all IO testing are completed.

Page 3: TW@ESI Update 8th November 2015

Projects and deadlines– 15_008 - Aurobindo PH02 BMS- The panel has been delivered and

assembled on site with everyones good will and effort. We need to plan the programming and development of the system which is now extremely urgent. We have the first phase of handover which is to be done by 13th November 2015... This date has been delayed by the contractor – so my message is to press on doing software until the contractor starts meeting the deadlines

– 14_089_MGA_DAC_PA_VA – needs to be completed by 15th November 2015 – including PA-VA- The contractor on site has tested all speakers – now lets commission- CCI I need a date here

– 13_070 SCM Lagoona – needs to be completely commissioned by 15th December 2015

Page 4: TW@ESI Update 8th November 2015

DesignLast Week• Westin 7AHUs – Gather Material Required, release for quotes, orders - from

MF, Tridium, Scan (UPS), and Rittal (check stock for Vent Fans, Side Panels)• Siggiewi - Implement SAA Various feedback• MDH MAU – Drawing preparation for Silvio Lifts terminations / Mekanika

Motor Ratings / Motor CBs issue

Next Week• Aurobindo As Built Panel Feedback• MDH MAU – Lessons Learnt Site meeting / Mekanika Motor Ratings /

Motor CBs issue• Westin 7AHUs – - Check / order Rittal (check stock for Vent Fans, Side

Panels, then accumulate with Intercontinental)• Life Sciences – Start new F/S Damper / Implement As Built Feedback

Page 5: TW@ESI Update 8th November 2015

Installation

• Last week we were focused on– Life Sciences Commissioning– MAU Panel terminations and IO testing– DGI Villa snags– Aurobindo VSD start up

• Next week– ESI Premises- Small room outside showroom– MGA DAC installation and commissioning – Life Sciences Commissioning– MAU Panel terminations

Page 6: TW@ESI Update 8th November 2015

Panel Build• Next to be done is Siggiewi DDCs- we have

finished 2 and now need to start up another 2• Also we have to finish off the FM Environmental

panels

Page 7: TW@ESI Update 8th November 2015

Mater Dei

• The team at MDH is working full blast to assist the MAU installation and a lot of effort is being done in order for ESI to succeed

• The team at Mater Dei are working hard to fill in the missing people and hopefully, by the month of November 2015, we should settle on our new complement.

Page 8: TW@ESI Update 8th November 2015

Development and Commissioning• We have done large important steps on finishing off the Parliament we need to get

the documentation out of the way too to avoid us going time and time again on site• We finalised on the DAC for FTIAS – well done to LVA and JPO on this- this week

there is a further meeting on site to decide what has to be done with the emergency doors

• We now need to start installation and commission the 14_089_MGA_PA_DAC• The last issues on the DAC for SCM PH2• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA

is to work on this• CVA Is also now working on the Hilton Hotel Guest room AHU project whihc has

been put on back burner till we get the VSD drive• The Bosch HSDK interface is being done and we will now need to work on the

documentation• The PLC/SCADA team have been working to progress the MAU software

development

Page 9: TW@ESI Update 8th November 2015

Development and Commissioning• There is huge amount of work to do with the commissioning of Life Sciences

12_043!! We are on a very tight time frame here and we need to dig really deep and perform

• OTM urgent jobs and snags were also done in the last weeks• Aurobindo is another important and, now, fast track project the first phase now

needs to be completed by 13th November 2015- The idea is to have the panel by last week of October 2015 and terminate and test and commission right after

• Another project that needs attention is CCA Villa ... We need to see to snags and convince the client on the system we have installed

• The Siggiewi Primary school project is an extremely urgent project which needs to be completed from 3rd fix by First weeks of November 2015 and commissioned by end of November 2015

• There is a lot of commissioning work to be done and we need to work efficiently to make the commissioning time as short as possible

Page 10: TW@ESI Update 8th November 2015

Sales and Business Development

• We have been working on Home automation offerings and quotes for variations for existing projects

• We have also won another control panel (based on Siemens LOGO) for the control and monitoring of Escape smoke dampers at Life Sciences park.

• We are working on a PLC solution for a Sterling Plant in Perugia

Page 11: TW@ESI Update 8th November 2015

Team ESI• I urge you all to follow this blog and keep up to date with what is

happening at ESI • I await all your feedback on all the ESI discussions – without this

feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

• Send me pictures of all your work and what you are up to , so that I may create some videos on this blog- Julian, Claudio, Clifton, Silvio, and Clinton.... Well done!!

Page 12: TW@ESI Update 8th November 2015

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• HAVE A GOOD WEEK