The following is a record of what was done during the past week and a forecast of the next week.....

Page 2: TW@ESI 5th June 2016

A General Note before we start- New premises

The new premises.... Most works have now been completed- well done to all for their efforts done. The following is to be done before we can say we are really ready! a) Intercom on old door entranceb) Office DAC are re commissionedc) Air Conditioning controls with JACEd) Re installation of fire alarm panele) Re installation of all wall mounted items in tech area. This area is

to be made a show case and it is to reflect organisation and technology

f) Automation system integrated with lighting and the other systems installed

g) Snag list is pending which is with Dennis to implement

Page 3: TW@ESI 5th June 2016

A General Note before we start- Some General Notes•Andrew will be out of office till Mid June for exams- when he is back he will be back on full time basis•Stefan and Clifton have successfully completed Webex sessions on Galaxy Intruder alarms with Honeywell- Next are NIAGARA4 web based training

Page 4: TW@ESI 5th June 2016

Projects and deadlines• 15_044_Hilton_Restaurant_Kitchen_AHU and

15_034_Hilton_Calorifier_Monitoring. We have managed to commission basic closed loop controls ... Next would be the full commissioning of the CVA can you confirm when this will be completed

• 15_033_Westin_7-AHU- Most of the T&C should by now be completed. Pending is documentation CCI I would like a target date on the completion here

• 15_008 - Aurobindo PH02 BMS- We have made progress on commissioning here- we are stuck on a lot of issues by the client – We must do all we can to close items which are our control

Page 5: TW@ESI 5th June 2016

Projects and deadlines• 12_027- Parliament installation of St James lift

intercom and DAC system- Well done on the St James Lift- We now need to proceed on all pending issues down to ESI (Original contract- Server software, Intruder alarm mainly)

• The Vibrant Lighting control project will be due soon and Commissioning will be happening during week of 13th June 2016- myself and Clifton will be going to Qatar for on site commissioning

Page 6: TW@ESI 5th June 2016

DesignLast week• SCM DAC Panel updates as per CCi feedback for

BMIT• Hilton – new Panel Design MCC-EF48, quotes and

ordered Material, and delivered in Bonds.• Hilton – Dimensions, labels, Materials list for Panel

Build out of office• Hilton – Sketched changes on relevant drawings as

required• OTM – urgent SAS 000000512 from Silvio 80% done

Page 7: TW@ESI 5th June 2016

DesignNext Week:• OTM – conclude urgent SAS 000000512 for

Silvio• ESI – check & book Service for A1 printer (& belt

change)• OVT – Panel Sizing, release quote request prior

Panel Design• AAP - Panel Sizing, release quote request prior

Panel Design

Page 8: TW@ESI 5th June 2016

InstallationPast week:– Assisted Claudio at Aurobindo– Completed some snags at Westin– Installed field devices at SCM lagoon– Fitted new floor box at ESI offices– Completed electrical installation and painting on

Level-1– Completed fire alarm panel installation– Terminated IR’s on the new A/C’s

Page 9: TW@ESI 5th June 2016

InstallationNext week:– Complete DAC at BMIT– Repairs at DGI villa– Repairs at CCA villa– Assisting Claudio at Aurobindo– Maintenance works at Fimbank– Continue at SCM Lagoon– Start installation in garage with roller shutter

Page 10: TW@ESI 5th June 2016

Panel BuildWe have the Hilton VSD design and material list ready

we will be sub contracting this as a Trial

Next panels planned are for

a) OVT panelsb) APP panels

Page 11: TW@ESI 5th June 2016

Mater DeiThe following are the tasks being worked on and planned for the next weeks• MCC Panel Checks/UPS in BMS Panel E01-CC1, E02-CC1, EP1-CC1, F01-CC1,

F02-CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1• MCC PANEL CHECKS/UPS IN BMS PANEL D00-CC1, D01-CC1, DP1-CC1, D02-

CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D02-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3

• Field Device PPm D08-CC1, DP5-CC1 / D08-CC2, D08-CC3 / D09-CC1, D09-CC2• COORDINATED CHECKS OF ALARMS FROM 3RD PARTY DEVICES D08-CC1, DP5-

CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2• WEEKLY UPDATE OF ANTI-VIRUS ON ALL BMS STATIONS• Handling of reactive work orders• Quotation works new angiography project• Cont WinCC Upgrade HMIs- which are now all on line- well done all!!• To Add 2 new Alarms from volt free contacts of medical fridges in rooms

D113051 and D113052• New Medical gas alarm in B212005

Page 12: TW@ESI 5th June 2016

Development and Commissioning• Parliament project - we have an urgent quote to implement on

Parliament St James lift (intercom and DAC readers)- this has been done and we are now waiting for Panta- NEXT IS TO TACKLE SNAGS ON PARLIAMENT so as to close off the whole job

• The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION

• 12_043_Life Sciences – Collecting the KWhr monthly data and finishing off what we can is a huge urgency!!

• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

Page 13: TW@ESI 5th June 2016

Development and Commissioning• OTM urgent jobs and snags – P12/ Tank Field 3 and

quoting for the AS410 change over• CCA Villa - AC snags and ILPS. CCI and DFA I need your

feedback and way ahead• Oncology 14_066- We have done most of the work

here and are waiting from Panta on this• Aurobindo we are proceeding with software

development and we have done quite some progress – we are also now commissioning this project- we have met the client and have ways ahead to close whatever can be closed

Page 14: TW@ESI 5th June 2016

Development and Commissioning• 16_004_Microbiz_PW_Otis_Interface- is now urgent

and must meet our deadlines• 14_081_Siggiewi School- Lets move on concluding

issues related to Data acquisition and analysis.... We need good data to prove our systems- CCI we need to assess the data requirements of the client and report back

• 16_017_BMIT_DAC- We have done first and second fix and now need to proceed to commission

• 16_011_Intruder_UOM- We have started installation on this project and we need to plan on completion dates

Page 15: TW@ESI 5th June 2016

Data, data and more data• We have a lot of projects which are giving us a lot

of data and I would like to start telling “stories” by data

• I have received Data from MDH and need the data from CCI (for siggiewi) and what type of data we can get from SCM (From CVA) – Once I have these I will start writing our stories with the data

• I would like to have this data by 13th June 2016

Page 16: TW@ESI 5th June 2016

Sales and Business Development• We have been working on a quote for Actavis,

2 other Home automation projects and soon we will be quoting OTM for the change over of their PLC/Operating system and re writing of their core software

• On 1st June we had a very successfull demo for a large security integration job at Enemalta – Well done to Trevor, Karolina, Clifton and Stefan

Page 17: TW@ESI 5th June 2016

• All lessons learnt have been issued .... We need to now keep them in mind in ALL our project kick offs

Page 18: TW@ESI 5th June 2016

Birthday wishes go to

Clinton Camilleri 9th June

Page 19: TW@ESI 5th June 2016

Team ESI- Reminders

• Quality Tasks- I need to know your plan to complete quality tasks by 15th June 2016

• I sent out some e mails to some of you to give me feedback on what tools and instruments you have so as to have a log of everyone- I need your feedback by 30th June 2016

• Quality questions for new employees – I sent these out and need them returned by 13th July 2016

Page 20: TW@ESI 5th June 2016

Team ESI• I urge you all to follow this blog and keep up to date with

what is happening at ESI • I await all your feedback on all the ESI discussions –

without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

Page 21: TW@ESI 5th June 2016

Team ESI• Lets all work to get the work done on time, on budget

and to the required quality• We need to communicate, pull the rope in the same

direction to make our projects a success and profitable• I have been seeing a lot of encouraging actions

showing teamwork- people working and helping each other as a team – this needs to go on and we must work to achieve what we persist for- success!!!

• Have a good week