Greetings from Koh Samui or as the Thais say sawatdee ka , well they actually say sawatdee kaaaaaaaaaa with an ever prolonged aaaaaaaaaa

The following is a record of what was done during the last working week and a forecast of the Next week.....

Initial Points

Projects and Deadlines

Design

Installation Panel Build

Mater Dei Hospital PPM

Business Development

Page 3: TW@ESI 19th February 2017

Unfortunately I have to announce the resignation of

Karolina Jurczenia... Her last working day will be 28th Feb 2017.... I would like to thank Karolina for her service and wish her luck in her future

Some Points Before Starting

Also note that Shridar will be on long leave from 17 Feb 2017 to 20th

March

Two new full time employees will be starting

shortly... I will let MPA do the formal introductions

Page 4: TW@ESI 19th February 2017

Projects and Deadlines

16_025_DeLaRue_OFX

Training by overseas specialists was delivered and we now await for the client to install hardware in machines so as for us to commission

14_069_OTM Additions

Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017

Q021_TF4- Panel is on site and installed- we have powered up the panel and started connecting and powering up MOVs

16_007_LeMeridien

We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-

We have so far done 2 panels – we need to do 5 by end of Feb 2017- so we are a little behind here

16_066_Sterling_DCS_Line2

We have started some preliminary engineering here.... I will holding a kick off meeting shortly

16_040_Playmobil_Factory

We have started some preliminary engineering here.... I will holding a kick off meeting shortly

Page 5: TW@ESI 19th February 2017

Projects and Deadlines

16_023_GGY

We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform

15_011- Sliema apartments

We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017

15_023_FM panels

D20 ASRD being built by sub contractor and scheduled for 9th March 2017

D05 M 110 – scheduled for 1st May 2017

D20 ASRD 690 is presently in quotation stage

16_041_RSM_Security

We need to close off here – the sooner the better

SAI has prepared a snag list of outstanding works and he now needs to give a date by when ESI will be completed from all works (works pending from others excluded)

16_058_Methode

Another fast tack project Jace Based AHU control system here

Prosit for all efforts to complete the panel!! It will be delivered next week

Dennis will now push our sub contractors to complete the required cable pulling and terminations

CCI/CVA are to proceed with programming

Page 6: TW@ESI 19th February 2017

Projects and Deadlines

12_043_LSP

We have an important and urgent snag to be rectified ASAP – treating the rust on enclosures

There are some points on the tenant billing application which we are tackling

13_031_CCA

We have a number of snags here , which are to be put to bed once and for all!!

The snags are centred around the AC controls and the NUOO CCTV system

14_08_Siggiewi School-

We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers – We also have a major fault/snag which needs to be rectified

14_083_Interconti

We have commissioned the system with snags - we will return to site when snags are done by others-

we also have to deliver the pool panel

15_038_new_HA_Ovt and 15_026_Apap

Residence

These two home automation projects are now urgent- we need to complete all installation

We also need to start working of the software development- they are urgent and we have to perform

Page 7: TW@ESI 19th February 2017

Projects and Deadlines

12_025_SCM PH2

The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

13_070- SCM Lagoona Plant room

We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue

13_075_Bosch_ProWatch_Genetec_Interface

The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

Page 8: TW@ESI 19th February 2017

01 02 03 04

DesignFor the Past week we have been working on the following

OTM – Q020 Netherlocks – completed & submitted TF3_NVC_002OTM – Q020 Netherlocks – BH1_NVC_001 – 85%

Playmobil HF80 – compiled Points Lists including all Tag References for ALL project – Started P&ID for MCC1

Sterling DCS Line2 – Preliminary Panel Sizing with TBR, to release Rittal quote request

Design

Page 9: TW@ESI 19th February 2017

01 02 03 04

DesignAnd next week… we will work on

FM Environmental – Update as per CFH feedback, re-send to CFH to re-submit

AAP – complete implementation of Additions

Design

OTM – Q020 Netherlocks – BH1_NVC_001 – OTM – Q020 Netherlocks – TF3_NVC_004 and NVC 022 revise as per Client feedback (minor changes) & re-submit

Playmobil HF80 – continue P&IDs for MCC1, start-off P&IDs for MCC2

Page 10: TW@ESI 19th February 2017

This is what the Installation team have been working on last week

Continued with works at OVT- Completed Data terminations at OVT

Added DALI sensors at RSM

Connected some doors at RSM

Installation

Continued with some works at Mosta workshop

Page 11: TW@ESI 19th February 2017

….. And this is what is planned for next week

commissioning at RSM

Start canalization and cable pulling at Methode

Installation

Change VSD at Medichem

Deliver panel to Methode

Page 12: TW@ESI 19th February 2017

Next week we will • 16_058_Methode- I am aware that we still have some

more work on this panel- but it must be delivered next week

• FM Env D20-ASRD – This will be built by a sub contractor as soon as we get the parts

Panel Build

Panel Build

Page 13: TW@ESI 19th February 2017

Week 07PPMYearly Field devices checks, IR images & coordinated tests Feb-- D11-CC2, D12-CC1, F02-CC1, F05-CC1, F05-CC4, F05-CC5

Quarterly panel checks Feb -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D05-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2,D12-CC1

Weekly update of antivirus on all BMS stations

Mater Dei Maintenance

ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team memberWO- 116184572 (Q131)To supply and replace existing control gear for F2-CHW1-P2 with a new simocode and sirus soft starter

Mater Dei Maintenance

Page 14: TW@ESI 19th February 2017

BOV control panels and systems

lighting control systems in Qatar

Quote for Fire alarm

Building automation in a private clinic

MCC for an officeThese are the quotes the business development

team have been working on

Business Development

Page 15: TW@ESI 19th February 2017

Some Last Thoughts

Re one of the last major projects we have won – Playmobil- I know a lot of people contributed to this success- people who gave ideas, thoughts, shorcomings on similar projects, opened doors to contacts, worked on quotes and re quotes- you know who you are- and I say a big Thank you!! It gives me great satisfaction to achieve something when a lot of people have pulled together to win a goal!

Page 16: TW@ESI 19th February 2017

I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

I urge you all to follow this blog and keep up to

date with what is happening at ESI

Lets all work to get the work done on time, on

budget and to the required quality

We need to communicate, pull the rope in the

same direction to make our projects a success

and profitable

Some Last Thoughts

Page 17: TW@ESI 19th February 2017

I wish you all a good and productive

week