TW@ESI3rd April 2016Hope that you and all your families had a good weekend as we have started the month of April.

The following is a record of what was done during the past week and a forecast of the next week.....

Page 2: TW@ESI 3rd April 2015

A General Note before we startI would like to thank once again all the team for the efforts to complete the offices upstairs. Now even I am finally in my office The plan next for this week is: a) Pass all PIR cables and AC control cablesb) Finish all paintwork upstairsc) Migration of ESI to new position move to happen next

weekend 9/4. Please note all that during this time Server & Network will be OFF – no overtime at office / no network access (VPN)

d) Next stage will involve works in design and technical office- before this is done the show room area must be closed off and electrical supply made permanent with Enemalta (to allow people to relocate to here)

Page 3: TW@ESI 3rd April 2015

Projects and deadlines• 15_033_Westin_7-AHU- With everyone’s effort we have

managed to change over the Banquet hall AHUs- not only but start these remotely from the engineering PC- Next target- finish all Testing and commissioning works – I am expecting a date from Cci and DSh here

• 13_070_SCM Lagoona_Pump room- We have pulled most cables and need to now start terminations on site... This, too, is going to become a hot project- All terminations possible are to be completed ASAP

• 14_001_Fadalah- CVA has successfully completed the trip and flown the ESI flag up high here... PTO

Page 4: TW@ESI 3rd April 2015

Well done Claudio

Page 5: TW@ESI 3rd April 2015

Projects and deadlines• 15_044_Hilton_Restaurant_Kitchen_AHU and

15_034_Hilton_Calorifier_Monitoring. All installation and manual start up by end first weeks of April.... Again I am expecting a date by when we can manually start up here! Full T&C by end of April 2015.

• Projects 12_026 SCM Buildings 02, 03, R3 & R4 and 12_027 Security Systems Parliament- are still pending projects.

Page 6: TW@ESI 3rd April 2015

Projects and deadlines• 15_008 - Aurobindo PH02 BMS- We have made

progress on commissioning here- we will also soon need to come up with a plan and target date here.

• 13_052 New offices- Get the Automation in the new area offices!! Make sure it is fully functional and de snagged- Installation upstairs are to be completed shortly.... Design and Technical offices will be moved soon after that!

Page 7: TW@ESI 3rd April 2015

DesignLast week• Siggiewi - Gathered Clifford feedback, now to

conclude with CCI & start implementing updates

• MDH MAU – update to Panel Drawing & P&ID• Hilton Restaurant & Kitchen AHUs, Calorifiers -

Compiled Terminating Matrix• OVt New Residence 15_038 – created Points

list for all systems, assigned Tag References for ALL Devices

Page 8: TW@ESI 3rd April 2015

DesignNext Week:• MDH MAU – after updates of last week, Print 5x

A4 copies for Mekanika• Life Sciences – work out how many files are

required for drawings, for the O&M.• OVt New Residence 15_038 – start on P&IDs• OVt New Residence 15_038 – Plan site visit –

meet DLI (CCI to join, DSH as well)

Page 9: TW@ESI 3rd April 2015

InstallationPast week:– Completed mesh tray and started cable pulling in

plant room at Hilton (by Panta)– Installed all panels at Hilton– Modifications on panel at Aurobindo– Commissioning of cctv and DAC at parliament– Terminations at Smart City Lagoon

Page 10: TW@ESI 3rd April 2015

InstallationNext week:– Finish cable pulling and start installing field devices

at Hilton (by Panta)– Existing panels modification at Hilton– Start panel terminations at Hilton– Pass A/C and intruder cables at ESI offices Level 1– Finish terminations at SCM Lagoon– Panel modifications at SCM Lagoon

Page 11: TW@ESI 3rd April 2015

Panel Build• Terminations and modifications of Hilton Panels

Page 12: TW@ESI 3rd April 2015

Mater DeiThe following are the tasks being worked on and planned for the next weeks• Coordinated Checks of Alarms from 3rd Party Devices D10-CC1, D10-CC2, D10-CC3,

D11-CC1, DP6-CC1• FIELD DEVICES CHECKS FROM SITE/HMI D10-CC1, D10-CC2, D10-CC3, D11-CC1,

DP6-CC1• FIELD DEVICES CHECKS FROM SITE/HMI D11-CC2, D12-CC1• MCC PANEL CHECKS/UPS IN BMS PANEL E01-CC1, E02-CC1. EP1-CC1, F01-CC1, F02-

CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1• COORDINATED CHECKS OF ALARMS FROM 3RD PARTY DEVICES E01-CC1, E02-CC1,

EP1-CC1• COORDINATED FRIDGE / FREEZER TEST BETWEEN ESI AND BIOMEDICAL - MARCH• PANEL THERMOGRAPHICAL IMAGES E01-CC1, E02-CC1, EP1-CC1• FIELD DEVICES CHECKS FROM SITE E01-CC1, E02-CC1, EP1-CC1• MCC PANEL CHECKS/UPS IN BMS PANEL H01-CC1, HP1-CC1, P04-CC1, P02-CC1, P03-

CC1, T01-CC1, T02-CC1• WEEKLY UPDATE OF ANTI-VIRUS ON ALL BMS STATIONS• Preparation work for new HMIs for D05-CC1, D06-CC1, D07-CC1

Page 13: TW@ESI 3rd April 2015

Development and Commissioning• We have done large important steps on finishing off the

Parliament we need to get the documentation out of the way too to avoid us going time and time again on site- IT IS NOW A PRORITY AND WE NEED TO GET A COMPLETION

• The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION

• Life Sciences- We have also concluded with Training now... Documentation and some snags are pending

• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• The Bosch HSDK interface is well advanced and we awaiting the client

Page 14: TW@ESI 3rd April 2015

Development and Commissioning

• OTM urgent jobs and snags were also done in the last weeks• Another project that needs attention is CCA Villa ... There are

still some snags to be addressed –intruder alarm integration• Oncology 14_066- We have done most of the work here and

are waiting from Panta on this• The Siggiewi Primary school project – we need to close off

with snags and documentation here• Aurobindo we are proceeding with software development

and we have done quite some progress – we are also now commissioning this project- we will need to come up with a plan here.

Page 15: TW@ESI 3rd April 2015

Development and Commissioning• 16_004_Microbiz_PW_Otis_Interface- We are

presently working on a task list and POW as well as setting up the test rigs

Page 16: TW@ESI 3rd April 2015

Sales and Business Development

• First of all Well done to all involved for bringing home yet another Home Automation project- 15_026- Apap Villa – This is a large and prestigious project and I will be holding a kick off meeting in the next week

• We have been working on Home automation offerings and quotes for OTM (some of which are quite large) , a quote for CCTV at Enemalta and quotes for variations for existing projects.

Page 17: TW@ESI 3rd April 2015

• More lessons to follow shortly – this next week

Page 18: TW@ESI 3rd April 2015

This week Mr. Victor Meunierwill start as of the 5th April

and he will with till 16th June 2016He will be assisting CCI/CVA

Page 19: TW@ESI 3rd April 2015

Team ESI• I urge you all to follow this blog and keep up to date with

what is happening at ESI • I await all your feedback on all the ESI discussions –

without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

Page 20: TW@ESI 3rd April 2015

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• Have a good week