TW@ESI 25 th October 2015 Hope that you and all your families had a good weekend and the following is an update of what was achieved during the past week and a forecast of the next week I pledge once again all of your co operation to make this work!! We need a special push at MDH (John and Shawn I need your help here), Panel Build (with Julians help), Clinton from installation (Clifton please assist!!) and Manuel (who is new- Am sure that Graziella will assist on this )

TW@ESI Update 25th October 2015

Embed Size (px)

Citation preview

Page 1: TW@ESI Update 25th October 2015

TW@ESI25th October 2015Hope that you and all your families had a good weekend and the following is an update of what was achieved during the past week and a forecast of the next week

I pledge once again all of your co operation to make this work!! We need a special push at MDH (John and Shawn I need your help here), Panel Build (with Julians help), Clinton from installation (Clifton please assist!!) and Manuel (who is new- Am sure that Graziella will assist on this )

Page 2: TW@ESI Update 25th October 2015

Projects and deadlines• We are presently executing a number of fast track projects and I would

like to summarise the major ones them as follows:– 14_081 - Siggiewi Primary School BMS- 3rd fix installation completed by 1st

week of November 2015. Commissioning completed by 8th December 2015– 13_076 - MDH Block D Ext MAU- Panel termination completed by end of

October 2015. IO testing to commence by 26th October 2015 (with FSDs in level 10)

– 15_008 - Aurobindo PH02 BMS- The panel will be completed 22nd October 2015 and we need to FAT this and take it out to site. We need to plan the programming and development of the system which is now extremely urgent. We have the first phase of handover which is to be done by 13th November 2015

• There are also a number of projects which are about to restart : 14_089_MGA_DAC_PA_VA, 13_070 SCM Lagoona and 12_043 Life sciences commissioning

Page 3: TW@ESI Update 25th October 2015

DesignLast Week• Siggiewi - Continue & Concude DDCs Design• Siggiewi – Implement various site feedback from SAA• MDH MAU –F/S Dampers Plans & Schedules of Lev08 &

09• MDH MAU – F/S Dampers Plans for Silvio’s DDFsNext Week• Westin 7AHUs – start Panel Design (target completion

6/11/2015)• Aurobindo – Prepare & Print labels for our Field Devices

Page 4: TW@ESI Update 25th October 2015

Installation

• Last week we were focused on– FTIAS Commissioning- we have done a lot of progress

here – well done– Life Sciences Commissioning– Hilton AHU Project– MAU Panel terminations

• Next week– MGA DAC installation and commissioning – Life Sciences Commissioning– MAU Panel terminations

Page 5: TW@ESI Update 25th October 2015

Panel Build• The Aurobindo is now completed with a huge

team effort from all.. It will be delivered on Monday, joined together by Tuesday 27/10

• Next to be done is Siggiewi DDCs• Also we have to finish off the FM Environmental

panels

Page 6: TW@ESI Update 25th October 2015

Mater Dei

• The team at MDH is working full blast to assist the MAU installation and a lot of effort is being done in order for ESI to succeed

• The team at Mater Dei are working hard to fill in the missing people and hopefully, by end of October 2015, we should settle on our new complement.

Page 7: TW@ESI Update 25th October 2015

Development and Commissioning• We have done large important steps on finishing off the Parliament we need

to get the documentation out of the way too to avoid us going time and time again on site

• We finalised on the DAC for FTIAS – well done to LVA and JPO on this• We now need to start installation and commission the 14_089_MGA_PA_DAC• The last issues on the DAC for SCM PH2• SCM PH2 needs also some attention on the tagging purchase order for the

BMS- CVA is to work on this• CVA Is also now working on the Hilton Hotel Guest room AHU project • The Bosch HSDK interface is being done and we will now need to work on the

documentation• The PLC/SCADA team have been working to progress the MAU software

development

Page 8: TW@ESI Update 25th October 2015

Development and Commissioning• OTM urgent jobs and snags were also done in the last weeks• Aurobindo is another important and, now, fast track project the first

pjase now needs to be completed by 13th November 2015- The idea is to have the panel by last week of October 2015 and terminate and test and commission right after

• Another project that needs attention is CCA Villa ... We need to see to snags and convince the client on the system we have installed

• The Siggiewi Primary school project is an extremely urgent project which needs to be completed from 3rd fix by First week of November 2015 and commissioned by end of November 2015

• There is a lot of commissioning work to be done and we need to work efficiently to make the commissioning time as short as possible

• CCI is on ProWatch training this week in Germany

Page 9: TW@ESI Update 25th October 2015

Sales and Business Development

• We have been working on Home automation offerings and quotes for variations for existing projects and an offer a customer experience centre

Page 10: TW@ESI Update 25th October 2015

Birthday wishes go to Pawlu Vassallo who’s birthday is on 30th October

Page 11: TW@ESI Update 25th October 2015

Team ESI• I urge you all to follow this blog and keep up to date

with what is happening at ESI• Please urge and assist all you colleagues to have a

linkedin profile and join this discussion group• Share your thoughts and participate actively on this

blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

• Send me pictures of all your work and what you are up to , so that I may create some videos on this blog- Julian, Claudio, Clifton, Silvio, and Clinton.... Well done!!

Page 12: TW@ESI Update 25th October 2015

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• HAVE A GOOD WEEK