TW@ESI20th November 2016
Hope all of you had a good weekend
The following is a record of what was done during the past week and a forecast of the next week.....
A General Note before we start-•Our Christmas party has been planned for Monday 12th December 2016- evening – please pencil this date and keep it free•Monday 5th December will be the date all who are joining the fun of Secret Santa will open our presents •For new employees Jerico, Kristiyan and Stoyan- can CVA/SSA/JGA ask them to join LinkedIn, ask to connect with me and I will include them in our group- speaking of new members in our Linkedin•Today week myself and John will be travelling to Qatar from 27th Nov till 2nd Nov – we will be holding various meetings to try and find further opportunities in this region
Projects and deadlines• 16_007_LeMeridien_BMS_upgrade- We have started working on phase 1
panels – phase 1 which has to be completed by Feb 2017- next steps are– We need to order the JACES and Field devices – Prepare the Software for the phase one panels– Once materials are here, design sketches are available and software is available
we will do change over.• 12_043_Life Sciences – we need to call for an inspection of snags to close
everything down- we need to complete the tenant building module• 13_075_Bosch_ProWatch_Genetec_Interface - The Bosch HSDK interface
is well advanced and we have documented and we should shortly be expecting to go overseas to commission
• 12_027- Parliament –We have updated Maxpro and now and conclude all documentation (this needs to be done by end of Nov 2016) and finally integrate ProWatch
Projects and deadlines• 14_069- Q019 AS410 – Material from Siemens has been received,
RFIs are still unanswered from client• 14_069- Q021_TF4- panel build, panel installation, Patch panel
installation, FOC termination and testing• 12_025- The last issues on the DAC for SCM PH2- IT IS NOW A
PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
• 14_081_Siggiewi School- there are some snags pending here which have to be seen to.
• 16_025_DeLaRue_OFX- We will be kicking off the project with the client on Tuesday 15th Nov
• 13_031_CCA- still issues with values on ILPS and we also have to execute some new works at CCA (new cameras, pagers)
Projects and deadlines• 15_011- Sliema apartments – We have been through the site orientation- next steps are
panel design, materials ordering, panel build and installation/terminations of field on site.• 16_023_GGY- is another home automation project which is on a much faster track- we have
concluded quite a bit here recently – we have some snags pending as well as the integration to the Acs- we also have to transfer the old GGY system to the new platform
• 14_083_Intercontinental – We have started works to start up the plant and start commissioning here- software development has also now advanced on this project. Commissioning is planned for this week - The second Pool Panel- which is now completed
• 16_015_RSM- this lighting control project is to be completed by Beginning of December 2016 we need to really keep a good eye on what is happening on site by the main contractor- we must ensure the wiring and terminations are done properly
• 15_038_new_HA_Ovt and 15_026_Apap Residence are two home automation projects scheduled for Q1 2017 – we have built all panels for these projects and we are awaiting others to complete their installation
• 13_070- SCM Lagoona Plant room We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue
Projects and deadlines• 16_025_DeLaRue_OFX- We have kicked off this project and
next will be the sizing of the LOGOS from CFH, purchasing and some design connection details from JGH
• 16_041_RSM_Zebbug_Security- CCI and SAI will be going through the scope during week of 18th Nov so as to allow me to start ordering- A kick off will be held during week of 5th Dec
• 16_051_Baxter_AHU_Controls- An extremely fast track project which was started off last week (Commissioning date is in the week after Christmas) – next steps are– Sizing of Panel and ordering by JGH – Ordering of Tridium hardware– Measurement, ordering and installation of mains cable and remote
signal cabling– Finalising of Control description
DesignLast week• Started Aurdobindo Panel drawing site feedback as per CVA conclusion (to complete by
22/11/2016)• FM Environmental – Panel Build dimensions• OTM – Q021 5DP02 – Collect feedback after Panel Build, concluded & printed• OTM - Q019_AS410-Migration - 03NVC20-mod Drawing Update• Meridien: Continued with sketches on Phase 1 panels – complete so far: MCPM2, MCPM1,
MCPB4• Meridien: All Panels’ I/O modules released to SAA (excl additions, new remote DDCs)• Sliema Graham Apartments – Dimensions & Labels printing for Panel buildNext Week:• Complete Aurdobindo Panel drawing site feedback as per CVA conclusion (to complete by
22/11/2016)• compile list of Server Rack items (Brand, Part No, Serial No etc)• Complete DAC template for CCI• Meridien: Release sketches of MCPM2, MCPM1, MCPB4 to CVA / CCI to check /revert, before
Panel mods on site• OTM – Print Additional labels for field 5DP02, update conclusion of 5DP02 after CFH testing• Baxter AHU: Size Panel, material procurement, P&IDs, hopefully start on Panel Design
InstallationThis past week: • OTM panel modifications labelling and updates of panel drawings• Installed lock strikers and door contacts at Graham apartments in
Sliema• Assisted Clifton on Savant and delivered TV’s at GGY• Connected electrical meter in showroom• Continued with works on Mosta workshopNext week:• Panel modifications at OTM • Assist Clifton on Intercontinental commissioning• Aurobindo to change TT sensor on Chiller• Continue with works at Mosta workshop
Panel Build
Well done to the efforts done to catch up – we are still in slight delay and I have adjusted our plan – we need to keep it now!- WE HAVE FALLEN BACK AGAIN
• Project 14_069 - OTM Additions completion target 2nd November 2016- this panel has now been practically completed
• Project 15_023 - FM Env Control Panels completion target now by 25/11
• Project 16_015 - RSM DALI completion target 25th November 2016• Project 15_011 - Graham Sliema Apts Blk completion target 2nd
December 2016• Project 16_051 – To be completed by 16th December 2016
Mater DeiWeek 47
PPMYearly Field devices checks, IR images & coordinated tests Nov--D07-CC1, D07-CC2, B01-CC1, BP1-CC1, B02-CC1, BP2-CC1, B03-CC1, & various ref equipment
Quarterly panel checks Nov -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D02-CC2,
D06-CC1, DP4-CC1, D06-CC2, D06-CC3, D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2, D12-CC1
Weekly update of antivirus on all BMS stationsReactiveHandling of reactive work orders
OthersParticipating in weekly fire drillsTackling software work orders New Angiography ProjectTraining of new team memberIntegration of Samoc into MasterB209308 - B209310 - To remove timers and actuators from rooms
Sales and Business DevelopmentWe are working on quotes for Clean room control
system, lighting control systems is Qatar and trying to secure a large BMS project in malta.
Last week we organised our first Technology Appreciation Workshops- we did this on Tridium with two consultants from QPM – I believe it was a success and congratulate CVA, TBR, KJA and all who worked to make this a success!
Team ESI• I urge you all to follow this blog and keep up to date with
what is happening at ESI • I await all your feedback on all the ESI discussions –
without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group
• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
Team ESI
• Lets all work to get the work done on time, on budget and to the required quality
• We need to communicate, pull the rope in the same direction to make our projects a success and profitable