74
Investing in Manchester’s Transport Infrastructure

Fbe Transport presentation

Embed Size (px)

Citation preview

Page 1: Fbe Transport presentation

Investing in Manchester’s Transport

Infrastructure

Page 2: Fbe Transport presentation

@FBEManchester #fbemcr

WIFI Detail on your table

Page 3: Fbe Transport presentation

Martin Jurkowski Principal Sponsor,

LNW North

Hilary Moules Category Manager

Construction & Capital Procurement

Page 4: Fbe Transport presentation

/ Junel 2015 4

Investment in the

North’s rail network

Martin Jurkowski

Principal Sponsor, LNW North

Forum for the Built Environment

Page 5: Fbe Transport presentation

/ Junel 2015 5

Currently Network Rail is investing almost £2bn in

new rail infrastructure in the North West over the

next 5 years

Infrastructure interventions to unlock capacity and

help deliver economic growth

Foster the ability to link the cities of the north as one

economic entity

Enable hundreds more trains to run each day, and

millions more passengers to travel by rail each year

…..and this excludes any HS2 or TransNorth works

Forum for the Built Environment

Page 6: Fbe Transport presentation

/ Junel 2015 6

Some of those investments are……

Manchester Victoria

Northern Hub

NW Electrification

Liverpool Lime Street

Forum for the Built Environment

Page 7: Fbe Transport presentation

/ Junel 2015 7

But enough of current commitments….

Future prospects

► Oxford Road redevelopment

► Further electrification

► Transpennine

► Merseyrail expansion

► HS2 enabling works

► TransNorth etc

Forum for the Built Environment

Page 8: Fbe Transport presentation

/ Junel 2015 8

Oxford Road station

Forum for the Built Environment

Page 9: Fbe Transport presentation

/ Junel 2015 9

Further electrification….

Forum for the Built Environment

Page 10: Fbe Transport presentation

/ Junel 2015 10

Transpennine route upgrade

Forum for the Built Environment

Page 11: Fbe Transport presentation

/ Junel 2015 11

Merseyrail expansion

► New rolling stock

► New stations

► New lines

Forum for the Built Environment

Page 12: Fbe Transport presentation

/ Junel 2015 12

HS2 enabling works

► Upgrades to lines north of

Handsacre Junction

► Preston

► WCML north of Preston

► Depots

► Power upgrades

► etc

Forum for the Built Environment

Page 13: Fbe Transport presentation

/ Junel 2015 13

And finally TransNorth…

► New East-West connections and upgrades

► Reduced journey times

► Interfaces to existing railway network

Forum for the Built Environment

Page 14: Fbe Transport presentation

/

Forum for the Built Environment

Junel 2015 14

Page 15: Fbe Transport presentation

Hilary Moules Category Manager Construction and Capital Procurement fbe 11th June 2015

Transport for Greater Manchester

Page 16: Fbe Transport presentation

Leading outstanding integrated transport for Greater Manchester…

Page 17: Fbe Transport presentation

Metrolink

Page 18: Fbe Transport presentation

Metrolink

Page 19: Fbe Transport presentation

East Manchester line

Page 20: Fbe Transport presentation

East Manchester line

Page 21: Fbe Transport presentation

Oldham and Rochdale line

Page 22: Fbe Transport presentation

Oldham and Rochdale line

Page 23: Fbe Transport presentation

Rochdale Interchange

Page 24: Fbe Transport presentation

Rochdale Interchange

Page 25: Fbe Transport presentation

Altrincham Interchange

Page 26: Fbe Transport presentation

Airport line

Page 27: Fbe Transport presentation

Airport line

Page 28: Fbe Transport presentation

Cycling – Better by Cycle

Page 29: Fbe Transport presentation

Cycling – Better by Cycle

Page 30: Fbe Transport presentation

Travel Choices

Page 31: Fbe Transport presentation

Travel Choices

Page 32: Fbe Transport presentation

Traffic signals

Page 33: Fbe Transport presentation

Traffic signals

Page 34: Fbe Transport presentation

Social media

Page 35: Fbe Transport presentation

Social media

Page 36: Fbe Transport presentation

Customer service

Page 37: Fbe Transport presentation

Customer service

Page 38: Fbe Transport presentation

The challenges ahead

Page 39: Fbe Transport presentation

2nd City Crossing

Page 40: Fbe Transport presentation

2nd City Crossing

Page 41: Fbe Transport presentation

Get me there

Page 42: Fbe Transport presentation

Get me there

Page 43: Fbe Transport presentation

Wythenshawe & Bolton Interchanges

Page 44: Fbe Transport presentation

Altrincham, Bolton & Wythenshawe Interchanges

Page 45: Fbe Transport presentation

Rail

Page 46: Fbe Transport presentation

Rail

Page 47: Fbe Transport presentation

HS2

Page 48: Fbe Transport presentation

HS2

Page 49: Fbe Transport presentation

Bus priority

Page 50: Fbe Transport presentation

Bus priority

Page 51: Fbe Transport presentation

East-West connectivity

Page 52: Fbe Transport presentation

East-West connectivity

Page 53: Fbe Transport presentation

Agenda

• Local Growth Deal

• TfGM-led schemes • Future Interchanges • Bolton-Salford Quality Bus Network • Salford Central Station • Metrolink Improvement Package

• District-led schemes

• Trafford Park Line

• The Devolution Programme:

• Highways

• Rail Devolution

• Bus Franchising

Page 54: Fbe Transport presentation

GM Local Growth Deal (And Beyond) • Confirmed July 2014. • 2015/16-2020/21 Capital Programme. • £350 million major schemes programme

(bus priority expansion, new interchanges, rail station improvements, Metrolink improvments and highway schemes).

• Substantive minor works and LSTF programme.

• Proposed programme of work with DfT on bus and highway reforms, alongside Rail North partnership.

• Ongoing discussions with Government regarding second round of Growth Deal Funding.

• Further investment opportunities via the GM Devolution Agreement (eg Trafford Park Metrolink Extension).

Page 55: Fbe Transport presentation

Local Growth Deal – TfGM-led Schemes

• Future Interchanges

• Wigan Hub

• Ashton Town Centre Interchange

• Stockport Interchange

• Bolton – Salford Quality Bus Network (Formerly Route 8)

• Salford Central Rail Station

• Metrolink Improvement Package

Page 56: Fbe Transport presentation

Wigan Hub • New Bus Station on the site of the existing facility.

• Need to integrate scheme with potential redevelopment of adjacent New Market Street / Market Street area.

• Concept design produced. Need to undertake further feasibility work, evaluate site options and develop scheme to RIBA Stage 3 in advance of submission of detailed planning application.

• Scheme budget c£16 million, including risk and contingency. (Subject to final approval.)

• Concept design with capacity for 194 bus departures per hour and 6 layover spaces.

• Retail facilities, Operator Facilities, Travel Shop, Toilets, Single Concourse Building, Cycle Storage Facilities.

• Operational Issues - maintaining of bus facilities during construction

Page 57: Fbe Transport presentation

Ashton Town Centre Interchange • New Interchange located partially on the existing Bus

Station Site

• Need to integrate scheme with new Metrolink terminus and safeguard future expansion of Metrolink network.

• Detailed feasibility study and concept design produced. Need to evaluate site options and develop scheme to RIBA Stage 3 in advance of submission of detailed planning application

• Concept design with capacity for 152 bus departures per hour and 4 layover spaces.

• Retail facilities, Operator Facilities, Travel Shop, Toilets, Single Concourse Building, Cycle Storage Facilities.

• Scheme budget c£33 million, including risk and contingency. (Subject to final approval.)

• Strategic outline business case produced. Further business case development work required.

• Operational Issues - maintaining of bus facilities during construction.

• Interfaces with operational Metrolink network during construction.

Page 58: Fbe Transport presentation

Stockport Interchange • New Interchange on the existing Bus Station Site.

• Enhanced public realm, new bridge across River Mersey, enhanced links to A6 and Rail Station, safeguarding of future Metrolink terminus.

• Detailed feasibility study and concept design produced. Concept design with capacity for 194 bus departures per hour, 9 layover spaces and 2 coach stands.

• Retail facilities, Operator Facilities, Travel Shop, Toilets, Single Concourse Building, Cycle Hub.

• Budget c£42 million, including risk and contingency. (Subject to final approval.)

– Probable construction in phases to enable current site to be used by existing bus services during this period.

– Interfaces with Stockport town centre accessibility package.

Page 59: Fbe Transport presentation

Future Interchanges – Current Position

• Multi-disciplinary design teams engaged.

• Initial commissions up to and including RIBA Stage 3.

• Main contractor procurement route under review.

• Commencement of procurement – late 2015 / early 2016. (Dependent upon route.)

• Delivery 2016 – 2018.

Page 60: Fbe Transport presentation

Bolton-Salford Quality Bus Network • Scheme budget £39.7m, including risk and contingency. (Subject to final approval.)

• Package of local transport network interventions and interchange schemes in the Bolton – Farnworth – Walkden – Salford Corridor.

• Strong emphasis on bus benefits, centred on solving punctuality and reliability of the routes of the radial services 8, 36,37 and 38 and feeder/orbital 12, 22, 501 and 68.

• Builds on and connects with the ‘Busway’ and Cross City Bus Package.

• Delivered as a TfGM programme with on-highways work to be designed and delivered by Bolton Council and Salford City Council (as joint scheme promoters).

Page 61: Fbe Transport presentation

Salford Central

• Scheme budget £20.5 million. (Subject to final approval.)

• Three additional platforms to serve the new Ordsall Chord and existing lines.

• Improved passenger facilities.

• Aimed at maximising benefit of Northern Hub investment.

• Designed to double the number of trains able to stop at the station.

Page 62: Fbe Transport presentation

LGD – Major Schemes - District Led Schemes DISTRICT LED SCHEMES

South Heywood M62 J19 Link Road

c£19.5m

1km link road, tie-in to the M62, works to the Manchester Road junction and

widening

Wigan A49 Link Road

c£25m

Connection from M6 to Wigan Town Centre and strategic sites

Wigan M58 Link Road

c£12.7m

New link road into west Wigan. 2km single carriageway between M6 and A571.

Inner Relief Road Route Improvements – Regent Road

c£15m

Major reconfiguration at the western gated to the Regional Centre to reduce delays

on the most congested point of the Inner Relief Road

Inner Relief Road Route Improvements – Gt Ancoats

Street

c£10m

Package of interventions to reduce congestion around eastern section of the IRR

Stockport Town Centre Major Scheme

c£73.2m

Package of transport schemes to improve access for more sustainable modes of

transport. Rationalised traffic movement through additional capacity on some routes

Procurements via existing local frameworks; NWCH Civils and Infrastructure framework (to be implemented) or HE Frameworks.

Page 63: Fbe Transport presentation

– Proposals for new 5.5km line from Pomona to the Trafford Centre

– Connecting to key employment areas in Trafford Park including the Trafford Centre

– Connecting to leisure opportunities Trafford Centre and Old Trafford for shopping and football

– 6 new stops: Wharfside

Imperial War Museum North

Village Way

Parkway Circle

Event City

Trafford Centre

Trafford Park line

Page 64: Fbe Transport presentation
Page 65: Fbe Transport presentation

Devolution Programme • Rail

• Bus Market Reform

• Highways Reform

Page 66: Fbe Transport presentation

Highways - Context

• MoU signed with HE • Joint GM Highways Investment and Strategy Board

• Joint long-term infrastructure planning in support of growth priorities

• Management of the Key Route Network by TfGM on behalf of GMCA

• Shared services opportunities for highway authorities

Page 67: Fbe Transport presentation

Highways Reform

• GM largest economy in the UK, outside of London

• Well managed network is vital to growth – 1.6 billion trips each year by car, bus, taxi, cycles, motorbikes, pedestrians

• Over 10,000km of highway in GM (A & B roads 1,200km)

• 2,250 traffic signals, including 985 pedestrian crossings

• 10 highway authorities and one Highways Agency (motorways)

• Congestion costs GM £1.3bn/yr

Page 68: Fbe Transport presentation

• Management of KRN by TfGM • The proposed KRN

encompasses about 650km of network,

• 7% of all local authority roads, • 48% of A and B roads in GM,

but carries 64% of all traffic on A and B roads.

• KRN supports the critical mass of daily commuting and logistics movements,

• KRN has a greater strategic economic importance of this network at a GM level

Proposed Key Route Network (KRN)

Page 69: Fbe Transport presentation

Getting ready for HS2

Page 70: Fbe Transport presentation

HS2 - Stations • Building the case for stations that stand the test of time:

• Commitment to “one station design”, transformational integrated transport and regeneration scheme.

• Capacity for integrated growth.

• Maximising the growth potential:

• “Single dedicated partnership” – to champion the transport and regeneration Growth Strategy.

• Effective & robust local governance and delivery solutions that are supported by a national framework.

Page 71: Fbe Transport presentation

Enhancing Connectivity between the North’s city regions, within the North’s city regions and to international gateways and London needs as an integral part of our strategy to accelerate the North’s economic growth.

• High speed trans-Pennine connections and European style cross city networks.

• New freight and logistics terminals.

• Highways investment to complete the national network in the North.

HS2 – One North (HS3)

Page 72: Fbe Transport presentation

Procurement at TfGM

• Approach to Market - Frameworks, OJEU, and

the Chest. Use market sounding where possible. Will consider consortia.

• Selection criteria – normally Most Economically

Advantageous. Clear on selection evaluation.

• Form of Contract – normally NEC 3, tending

towards D&B, consider lump sum or target cost.

• Risk – Prefer it sits where most appropriate/best managed.

Page 73: Fbe Transport presentation