Upload
fbe-manchester
View
209
Download
1
Embed Size (px)
Citation preview
THE ENGINEERING CHALLENGE
OF THE 20th, 21st and 22nd CENTURIES
Stephen JonesDeputy Head of Project Management capabilityChairman APM PMC SIG
∗ A very brief history of Sellafield Ltd
∗ “to work out where you’re going, it helps to know where you came from”
∗ Some understanding of the challenge – and the opportunities – that lie ahead
∗ Whats in it for You? – a chance to hear the story, see the direction and decide if you might want to be a part of it one day
What is today about?
Supporting the war effort – 1940
The Sellafield site has been operational since the 1940s
In September 1947 work began on the construction of the Windscale Piles and
its two air cooled reactors.
THE ENGINEERING CHALLENGE OF THE 20th CENTURY
∗ The Sellafield site was used as a Royal Ordinance Factory supporting the war effort and the National Defence Programme
∗ By March 1952 the Windscale reactors were in operation producing plutonium for military purposes.
THE ENGINEERING CHALLENGE OF THE 20th CENTURY
Harnessing the power – 1950
In 1952 the decision was made to build a commercial sized nuclear
power station
Construction of the Calder Hall power station commenced in 1953
THE ENGINEERING CHALLENGE OF THE 20th CENTURY
∗ Her Majesty the Queen opened Reactor 1 at Calder Hall in October 1956
∗ Calder Hall successfully operated until 2003 after nearly 46 years of electricity generation.
THE ENGINEERING CHALLENGE OF THE 20th CENTURY
Completing the fuel cycle - 1960
Construction of the WAGR
WAGR began operating in 1963 and was closed down in 1981 and celebrated
completing its decommissioning programme in 2011.
THE ENGINEERING CHALLENGE OF THE 20th CENTURY
∗ The Thermal Oxide Reprocessing Plant (Thorp) was completed in December 1992 and granted permission to operate in March 1994, with the full consent to operate given in 1997
∗ In 1994 construction work started on the Sellafield Mixed Oxide Plant (Mox) Plant
THE ENGINEERING CHALLENGE OF THE 20th CENTURY
Present Day…The Sellafield site is one of the biggest construction sites
in the UK – Within 5 years we will be the biggest in Europe
Our challenges are almost always industry firsts.
Hazard reduction is incredibly demanding technically, calling for vision, imagination and expertise.
The complexity of each project is unmatched anywhere else in the nuclear sector.
THE ENGINEERING CHALLENGE OF THE 21st CENTURY
11 Major Projects
We currently have 11 major projects either in design or construction, with more than £350 million per year invested.
THE ENGINEERING CHALLENGE OF THE 21st CENTURY
Our next chapter..!
There’s a nuclear renaissance going on around the world.
This is an industry for the future –
The skills and knowledge being developed within Sellafield Ltd will enable the UK to take its position at the technology forefront.
THE ENGINEERING CHALLENGE OF THE NEXT CENTURY
At Sellafield Ltd, we embarking on a 100 year mission.
11,000 men and women on a programme transforming the
Sellafield site, leaving it safe and environmentally sound for
all the generations that follow.
This Century’s Journey is Just Beginning!
THE ENGINEERING CHALLENGE OF THE CENTURIES
Questions?
THE ENGINEERING CHALLENGE OF THE CENTURIES
We are one of the only UK company’s who can look this
far to the horizon.
Website
http://www.sellafieldsites.com/
Careers Opportunities
http://careers.sellafieldsite.co.uk/
Supplier Opportunities
http://suppliers.sellafieldsites.com/procurement-opportunities/
Useful Information
Low Carbon Energy Generation in the NW of England
Jonathan England
Development Director
November 2015
2
Structure of the Presentation
Structure
• The Peel Group
• Peel Energy
• Onshore Wind – Development Sites
• Barton Biomass CHP Scheme
– The Scheme
– The Timeline
– The Opportunities
• Summary
• Q+A
3
The Peel Group
PORTS
50.1%
AIRPORTS
35%
REAL
ESTATE
ENERGY
RETAIL
MEDIA
OTHER
ACTIVITIES
Clydeport
Liverpool
Manchester
Ship Canal
Medway Ports
Heysham
Dublin and Belfast
Terminals
Shipping Lines
Cammell Laird
(50%)
A&P (Falmouth,
Tyne and Tees)
Liverpool
Doncaster Sheffield
Durham (89%
direct)
City Airport and
Heliport
Manchester
(100% direct)
Helicopter Charter
(100% direct)
C 30,000 acres
within ownership
Development Land
Mixed use
Offices
Industrial
Business Parks
Residential
Land Securities
Group (3-4%)
Wind
Constructed
Scout Moor (65MW)
Seaforth (3.6MW)
Port of Liverpool (10MW)
Bilsthorpe (10MW)
In Construction
Sheerness (8MW)
Frodsham (50MW)
Chevington (18MW)
Consented
FiT Schemes (2.5MW)
In Planning
Garelffan (21MW)
Scout Moor Expansion
(36MW)
FiT Schemes (2MW)
In Scoping
Beaw Field, Shetlands
(60MW)
Biomass
Consented
Barton (20MW)
Ince (20MW)
Hydro
Consented
Woolston Weir (0.5MW)
Irlam Locks (1.6MW)
Mode Wheel Locks
(1.2MW)
Intu Shopping
Centres Group
(24%)
Retail Parks
Gloucester Quays
Outlet Mall
Lowry Outlet Mall
Washington Mall
Bermuda
Trafford Centre
España (CSC option)
Glasgow Harbour
MediaCityUK Estate
Development
Pipeline
MediaCityUK Studios
Pinewood
Shepperton Group
(PWS)
(71%)
Hotels
Leisure
Minerals
Utilities
Advertising
Event City
Private Investment
WIG (minority
shareholding)
4
Onshore Wind – Development Sites
Frodsham Wind Farm (19 Turbines)
• Financially Closed Sept 2015.
• Construction of Balance of Plant ongoing.
• Turbine erection June 2016.
• Operational September 2016.
Sheerness Wind Farm (4 Turbines)
• Financially Closed Oct 2015.
• Foundation construction nearing completion.
• Turbine erection May 2016.
• Operational August 2016.
Scout Moor Expansion (16 Turbines)
• Approved by LPA’s Sept 2015 – Holding direction issued
and call-in decision awaited.
• 16 additional turbines off existing track network
• New grid connection
• Joint Venture with UU.
• Procurement expected to commence Q3 2016.
5
Barton Combined Heat and Power Plant
• 20MWe biomass fuelled renewable electricity and heat generation scheme.
• Adjacent to principal transportation links.
• Adjacent to high energy demands.
• Grid connection available close to the
site.
• Compatible with adjacent land uses.
• Close to generation of proposed fuel –
recycled waste wood. 200,000tpa.
UU Sewage Treatment Works
Salford Community Stadium Development
6
6
The Project Timeline
Date Progress
2010 Site Surveys
Dec 2010 Planning Application
Dec 2011 Refused by Trafford Council
Nov 2012 Public Inquiry
May 2013 SoS Decision
Feb 2014 Legal Challenge by Trafford
Council
Feb 2014 High Court Decision
Dec 2015 S73 Amendment to Consent
2016 CfD Auction Bid for Strike Price
- tbc
2016-2017 Procurement and Financial
Close (12 months)
2017 -
2020
Construction (2.5 yrs)
2020 Operational
7
Scheme Opportunities
• Financial Close:
– Professional Services – Legal, Financial, Environmental, etc
– Design and Engineering
• Construction:
– CHP Plant (Anticipated £80m investment)
– Heat Network and Energy Centre
– Grid Connection
• Operations:
– O&M
– Monitoring and Testing
• Fuel Supply:
– Aggregation
– Processing
– Haulage
8
Summary
• Peel have and continue to develop, construct, own and
operate low carbon energy generation schemes including
Wind, Biomass CHP and Hydro
• Despite political uncertainty we are continuing to explore
further renewable and low carbon opportunities across the UK
across technologies.
• We are committed to maximising local employment and supply
chain opportunities.
9
Contact : Jon England
Tel : 0161 629 8200
Questions and Answers
2020 VISION FOR RESOURCE EFFICIENCY IN
THE NORTHERN POWERHOUSE
KAREN HALL COMMUNICATIONS BUSINESS PARTNER VIRIDOR 07778 160389 @VIRIDORUK
LARGEST UK
WASTE &
RESOURCE
COMPANY
ESTABLISHED
IN 1957
PREVIOUSLY
LARGEST
LANDFILL
OPERATOR IN
UK
REFOCUS ON
RECYCLING,
EfW,
ORGANICS
VIRIDOR: OUR HERITAGE
INSIGHT: WASTE IS A
ZERO VALUE CONCEPT
2020 VISION : SUCCESS FACTORS
RECYCLING 50% +
LANDFILL DIVERSION
90% +
OPTIMISED FACILITIES
FINANCIAL RETURN FOR ALL PARTIES
GLOBAL BEST
PRACTICE
INSIGHT: WASTE IS A
ZERO VALUE CONCEPT REGIONAL
RESOURCES NETWORKS:
Common
standards for collections.
Standard collections for
specific materials
pilot.
Regional Resources Network
Innovation Fund.
OfRes.