53

Fbe manchester energy event nov 2015

Embed Size (px)

Citation preview

THE ENGINEERING CHALLENGE

OF THE 20th, 21st and 22nd CENTURIES

THE ENGINEERING CHALLENGE

OF THE 20th, 21st and 22nd CENTURIES

Stephen JonesDeputy Head of Project Management capabilityChairman APM PMC SIG

∗ A very brief history of Sellafield Ltd

∗ “to work out where you’re going, it helps to know where you came from”

∗ Some understanding of the challenge – and the opportunities – that lie ahead

∗ Whats in it for You? – a chance to hear the story, see the direction and decide if you might want to be a part of it one day

What is today about?

Our past…

THE ENGINEERING CHALLENGE OF THE 20th CENTURY

Supporting the war effort – 1940

The Sellafield site has been operational since the 1940s

In September 1947 work began on the construction of the Windscale Piles and

its two air cooled reactors.

THE ENGINEERING CHALLENGE OF THE 20th CENTURY

∗ The Sellafield site was used as a Royal Ordinance Factory supporting the war effort and the National Defence Programme

∗ By March 1952 the Windscale reactors were in operation producing plutonium for military purposes.

THE ENGINEERING CHALLENGE OF THE 20th CENTURY

Harnessing the power – 1950

In 1952 the decision was made to build a commercial sized nuclear

power station

Construction of the Calder Hall power station commenced in 1953

THE ENGINEERING CHALLENGE OF THE 20th CENTURY

∗ Her Majesty the Queen opened Reactor 1 at Calder Hall in October 1956

∗ Calder Hall successfully operated until 2003 after nearly 46 years of electricity generation.

THE ENGINEERING CHALLENGE OF THE 20th CENTURY

Completing the fuel cycle - 1960

Construction of the WAGR

WAGR began operating in 1963 and was closed down in 1981 and celebrated

completing its decommissioning programme in 2011.

THE ENGINEERING CHALLENGE OF THE 20th CENTURY

∗ The Thermal Oxide Reprocessing Plant (Thorp) was completed in December 1992 and granted permission to operate in March 1994, with the full consent to operate given in 1997

∗ In 1994 construction work started on the Sellafield Mixed Oxide Plant (Mox) Plant

THE ENGINEERING CHALLENGE OF THE 20th CENTURY

Present Day…The Sellafield site is one of the biggest construction sites

in the UK – Within 5 years we will be the biggest in Europe

Our challenges are almost always industry firsts.

Hazard reduction is incredibly demanding technically, calling for vision, imagination and expertise.

The complexity of each project is unmatched anywhere else in the nuclear sector.

THE ENGINEERING CHALLENGE OF THE 21st CENTURY

We are NOT just about legacy and decommissioning!

THE ENGINEERING CHALLENGE OF THE 21st CENTURY

11 Major Projects

We currently have 11 major projects either in design or construction, with more than £350 million per year invested.

THE ENGINEERING CHALLENGE OF THE 21st CENTURY

THE ENGINEERING CHALLENGE OF THE 21st CENTURY

THE ENGINEERING CHALLENGE OF THE 21st CENTURY

THE ENGINEERING CHALLENGE OF THE 21st CENTURY

THE ENGINEERING CHALLENGE OF THE 21st CENTURY

THE ENGINEERING CHALLENGE OF THE 21st CENTURY

THE ENGINEERING CHALLENGE OF THE 21st CENTURY

THE ENGINEERING CHALLENGE OF THE 21st CENTURY

Our next chapter..!

There’s a nuclear renaissance going on around the world.

This is an industry for the future –

The skills and knowledge being developed within Sellafield Ltd will enable the UK to take its position at the technology forefront.

THE ENGINEERING CHALLENGE OF THE NEXT CENTURY

What Next? – 2020+

THE ENGINEERING CHALLENGE OF THE NEXT CENTURY

THE ENGINEERING CHALLENGE OF THE NEXT CENTURY

At Sellafield Ltd, we embarking on a 100 year mission.

11,000 men and women on a programme transforming the

Sellafield site, leaving it safe and environmentally sound for

all the generations that follow.

This Century’s Journey is Just Beginning!

THE ENGINEERING CHALLENGE OF THE CENTURIES

Questions?

THE ENGINEERING CHALLENGE OF THE CENTURIES

We are one of the only UK company’s who can look this

far to the horizon.

Website

http://www.sellafieldsites.com/

Careers Opportunities

http://careers.sellafieldsite.co.uk/

Supplier Opportunities

http://suppliers.sellafieldsites.com/procurement-opportunities/

Useful Information

Low Carbon Energy Generation in the NW of England

Jonathan England

Development Director

November 2015

2

Structure of the Presentation

Structure

• The Peel Group

• Peel Energy

• Onshore Wind – Development Sites

• Barton Biomass CHP Scheme

– The Scheme

– The Timeline

– The Opportunities

• Summary

• Q+A

3

The Peel Group

PORTS

50.1%

AIRPORTS

35%

REAL

ESTATE

ENERGY

RETAIL

MEDIA

OTHER

ACTIVITIES

Clydeport

Liverpool

Manchester

Ship Canal

Medway Ports

Heysham

Dublin and Belfast

Terminals

Shipping Lines

Cammell Laird

(50%)

A&P (Falmouth,

Tyne and Tees)

Liverpool

Doncaster Sheffield

Durham (89%

direct)

City Airport and

Heliport

Manchester

(100% direct)

Helicopter Charter

(100% direct)

C 30,000 acres

within ownership

Development Land

Mixed use

Offices

Industrial

Business Parks

Residential

Land Securities

Group (3-4%)

Wind

Constructed

Scout Moor (65MW)

Seaforth (3.6MW)

Port of Liverpool (10MW)

Bilsthorpe (10MW)

In Construction

Sheerness (8MW)

Frodsham (50MW)

Chevington (18MW)

Consented

FiT Schemes (2.5MW)

In Planning

Garelffan (21MW)

Scout Moor Expansion

(36MW)

FiT Schemes (2MW)

In Scoping

Beaw Field, Shetlands

(60MW)

Biomass

Consented

Barton (20MW)

Ince (20MW)

Hydro

Consented

Woolston Weir (0.5MW)

Irlam Locks (1.6MW)

Mode Wheel Locks

(1.2MW)

Intu Shopping

Centres Group

(24%)

Retail Parks

Gloucester Quays

Outlet Mall

Lowry Outlet Mall

Washington Mall

Bermuda

Trafford Centre

España (CSC option)

Glasgow Harbour

MediaCityUK Estate

Development

Pipeline

MediaCityUK Studios

Pinewood

Shepperton Group

(PWS)

(71%)

Hotels

Leisure

Minerals

Utilities

Advertising

Event City

Private Investment

WIG (minority

shareholding)

4

Onshore Wind – Development Sites

Frodsham Wind Farm (19 Turbines)

• Financially Closed Sept 2015.

• Construction of Balance of Plant ongoing.

• Turbine erection June 2016.

• Operational September 2016.

Sheerness Wind Farm (4 Turbines)

• Financially Closed Oct 2015.

• Foundation construction nearing completion.

• Turbine erection May 2016.

• Operational August 2016.

Scout Moor Expansion (16 Turbines)

• Approved by LPA’s Sept 2015 – Holding direction issued

and call-in decision awaited.

• 16 additional turbines off existing track network

• New grid connection

• Joint Venture with UU.

• Procurement expected to commence Q3 2016.

5

Barton Combined Heat and Power Plant

• 20MWe biomass fuelled renewable electricity and heat generation scheme.

• Adjacent to principal transportation links.

• Adjacent to high energy demands.

• Grid connection available close to the

site.

• Compatible with adjacent land uses.

• Close to generation of proposed fuel –

recycled waste wood. 200,000tpa.

UU Sewage Treatment Works

Salford Community Stadium Development

6

6

The Project Timeline

Date Progress

2010 Site Surveys

Dec 2010 Planning Application

Dec 2011 Refused by Trafford Council

Nov 2012 Public Inquiry

May 2013 SoS Decision

Feb 2014 Legal Challenge by Trafford

Council

Feb 2014 High Court Decision

Dec 2015 S73 Amendment to Consent

2016 CfD Auction Bid for Strike Price

- tbc

2016-2017 Procurement and Financial

Close (12 months)

2017 -

2020

Construction (2.5 yrs)

2020 Operational

7

Scheme Opportunities

• Financial Close:

– Professional Services – Legal, Financial, Environmental, etc

– Design and Engineering

• Construction:

– CHP Plant (Anticipated £80m investment)

– Heat Network and Energy Centre

– Grid Connection

• Operations:

– O&M

– Monitoring and Testing

• Fuel Supply:

– Aggregation

– Processing

– Haulage

8

Summary

• Peel have and continue to develop, construct, own and

operate low carbon energy generation schemes including

Wind, Biomass CHP and Hydro

• Despite political uncertainty we are continuing to explore

further renewable and low carbon opportunities across the UK

across technologies.

• We are committed to maximising local employment and supply

chain opportunities.

9

Contact : Jon England

Tel : 0161 629 8200

[email protected]

Questions and Answers

2020 VISION FOR RESOURCE EFFICIENCY IN

THE NORTHERN POWERHOUSE

KAREN HALL COMMUNICATIONS BUSINESS PARTNER VIRIDOR 07778 160389 @VIRIDORUK

LARGEST UK

WASTE &

RESOURCE

COMPANY

ESTABLISHED

IN 1957

PREVIOUSLY

LARGEST

LANDFILL

OPERATOR IN

UK

REFOCUS ON

RECYCLING,

EfW,

ORGANICS

VIRIDOR: OUR HERITAGE

VIRIDOR: WHO WE ARE TODAY

INSIGHT: WASTE AS A RESOURCE

OUR NETWORK OF

INFASTRUCTURE DELIVERS

ESSENTIAL RESOURCE

MANAGEMENT

ARDLEY ERF

TRIDENT PARK ERF

INSIGHT: WASTE IS A

ZERO VALUE CONCEPT REGIONAL

RESOURCES NETWORKS:

GREATER MANCHESTER

INSIGHT: WASTE IS A

ZERO VALUE CONCEPT

SHARED & DELIVERABLE VISION:

DELIVERING WORLD CLASS

SERVICES

INSIGHT: WASTE IS A

ZERO VALUE CONCEPT

2020 VISION : SUCCESS FACTORS

RECYCLING 50% +

LANDFILL DIVERSION

90% +

OPTIMISED FACILITIES

FINANCIAL RETURN FOR ALL PARTIES

GLOBAL BEST

PRACTICE

INSIGHT: WASTE IS A

ZERO VALUE CONCEPT

RUNCORN ERF:

A NORTHERN POWERHOUSE

INSIGHT: WASTE IS A

ZERO VALUE CONCEPT REGIONAL

RESOURCES NETWORKS:

Common

standards for collections.

Standard collections for

specific materials

pilot.

Regional Resources Network

Innovation Fund.

OfRes.

INSIGHT: WASTE IS A

ZERO VALUE CONCEPT SUMMARY: TIME FOR A

NEW ECONOMIC REALISM

2020 VISION FOR RESOURCE EFFICIENCY IN

THE NORTHERN POWERHOUSE

KAREN HALL COMMUNICATIONS BUSINESS PARTNER VIRIDOR 07778 160389 @VIRIDORUK