Construction Update 10-6-2010

Preview:

Citation preview

Building the Future

Current Activities this Week:

Foundations:

Area 4 Field Level – Foundations for “infill” area

between Column Lines 39-1 are ongoing.

Concrete Flatwork:

Area 3 Field Level – Concrete for slab-on-grade up to

Stair 1 will be placed this week.

Masonry:

Area 1 – Field level masonry installation is ongoing in

Area H, G, F, E and D. Area 2/3 – Concourse building

masonry installation is ongoing.

Steel Erection:

Area 4 – Steel erection for “infill” area is ongoing

(Sequence 3-3). Truss installation has started.

Area 2 – Steel joist and metal decking installation for

concourse buildings is ongoing. Canopy decking

installation is ongoing. Canopy gutter enclosure framing

installation is ongoing.

Roofing and Sheetmetal:

Area 1 – Permanent roofing installation at West

Building is ongoing. Area 2/3 – Canopy gutter installation

is ongoing.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 10.6.2010

Re: Wizards Stadium Project

Update – Week of

10.4.2010

Field Level Area 3 – Concrete slab-on grade

prep is ongoing to column line 4.

Area 4 – Trusses 41 and 42 being set and

connected. 1 more truss remains (40 Line).

Field Level Area 3 – Masonry in Section D is

ongoing.

Building the Future

Metal Stud Framing:

Area 1 – Metal stud framing for Field, Concourse, Suite

and Press Levels are ongoing. Exterior metal stud framing

and sheathing installation is ongoing at Field, Suite, and

Press Levels.

Glass:

Area 1 - Curtainwall framing and glass installation is

ongoing at West Building on west, south and east

elevations. South “wing” framing has started.

MEP Rough-in:

Area 3 – Underground MEP rough-in is ongoing.

West Building - Ductwork installation on

Concourse, Suite and Press Levels are ongoing.

Plumbing rough-in is ongoing on Suite and

Press Levels. Fire Protection rough-in is ongoing on

Concourse, Suite and Press Levels. Electrical rough-in is

ongoing on Concourse, Suite and Press Levels.

Projected Activities occurring next Week:

Foundations:

Area 3/4 Field Level – Foundations for “infill” area

Between Column Lines 39-1 will be complete.

Concrete Flatwork:

Area 3 Field Level – Concrete placement for Slab-on

Grade from lower dock area to Column Line 1.

Area 3 and 4 Field Level – Installation of on-grade seating

risers and intermediate stairs will continue.

Masonry:

Area 1 – Field level masonry installation will continue in

Area H, G, F, E and D. Area 2/3 – Concourse building

masonry installation will continue.

Area 3 – Shot of the Canopy decking

installation that has started on the east side.

Area 1 – Curtainwall “wing” framing at south

end is being constructed.

Field Level Area 4 – Structural steel and

foundations are ongoing at Cauldron Club.

Building the Future

Structural Steel Erection:

Area 4 – Structural steel erection for “infill” area will

be ongoing. Area 2 – Steel joist and metal decking

installation for concourse buildings will continue.

Canopy decking installation will continue. Canopy gutter

enclosure framing installation will continue.

Roofing and Sheetmetal:

Area 1 – Permanent roofing installation at West

Building will continue. Area 3 – Canopy gutter installation

will continue.

Metal Stud Framing:

Area 1 – Metal stud framing for Field, Concourse, Suite

and Press Levels will continue. Exterior Framing and

sheathing installation will continue.

Glass:

Area 1 – Curtain Framing and Glass installation around West

Building will continue. Curtainwall framing on Suite and

Press Level balconies will continue. Curtainwall framing

at Field Side of Main Concourse will continue.

MEP Rough-in:

MEP Rough-in at Concourse, Suite and Press Levels will

continue. Ductwork installation on Concourse, Suite, and

Press Level will continue. Fire Sprinkler installation will

continue on Concourse, Suite and Press Levels.

Field – Installation of the Storm Loop around

playing field has started.

Area 1 – Shot of the west building showing

the progress of the exterior envelope.

Building the Future

Additional Photos:

Area 3 – Burnished CMU wall topped out at

Stair 1.

Area 3– On-grade seating installation is

ongoing at north elevation.

Area 1 – Concrete in Stair 9 is placed.

Concourse Level Area 3 – Canopy gutter and

gutter enclosure framing is ongoing.

Area 2 – Shot of the Canopy decking and

gutter at the SE corner.

Area 4 – Shot of Column Line 42 truss be

raised into place.

Recommended