View
489
Download
2
Tags:
Embed Size (px)
DESCRIPTION
Joel Saren's class of how to use MS Project
Citation preview
04/07/2023 Joel Saren ©20111
Working with MSProject
Project Management is a culture not a process
04/07/2023 Joel Saren ©20112
Owners of the Plan
Who owns the project plan? You do! (why? - See AMEX) There is only one version of the project plan
and you have it. Case Study #2
Project Management is a culture not a process
04/07/2023 Joel Saren ©20113
MS Project Cheat Sheet
Enter project information (such as the start date, Project Name, Turn on Summary Task Set up your resources in Resource Sheet Set up your work calendar. Create tasks, choosing the scheduling method and task type settings and entering
information about durations. Create milestones (tasks with zero duration) in your project. Organize your tasks into phases, using Project's outline structure. Establish dependencies among tasks, adding constraints if appropriate. Create resources, assigning cost/rate and resource calendar information. Assign resources to tasks. Resolve resource conflicts. Review the total duration and cost of the project, making adjustments if necessary. After plan is approved - Lock the baseline
Project Management is a culture not a process
04/07/2023 Joel Saren ©20114
MS Project Cheat Sheet
Enter project information (such as the start date, Project Name, Turn on Summary Task (Where and how?) File/Options/Advanced
Project Management is a culture not a process
04/07/2023 Joel Saren ©20115
F/S, S/S, F/F
All tasks CAN BE linear or Some tasks can be linear or Both Some tasks can be:
– Finish/Start– Start/Start– Finish/Finish
Project Management is a culture not a process
04/07/2023 Joel Saren ©20116
F/S, S/S, FF
Finish/StartWork package 2 startsafter 1 ends.
Start/StartThe work packagesSTART at the sameTime.
Finish/FinishThe work packagesFINISH at the same time.
Project Management is a culture not a process
04/07/2023 Joel Saren ©20117
F/S, S/S, FF and lags
Finish/Start (FS+1W)Work package 2 startsafter 1 ends + 1 week
Start/Start (SS+1D)The work packagesSTART at the sameTime + 1 DAY
Finish/Finish(FF+1H)The work packagesFINISH at the same time + 1 hour or maybe -1hr.
Project Management is a culture not a process
04/07/2023 Joel Saren ©20118
Fast Tracking and Lags
Starting one task before the predecessor is Finished is Fast Tracking
A Lag is: – F/S – 1day– S/S + 1 hour– F/F + 1 hour
Project Management is a culture not a process
04/07/2023 Joel Saren ©20119
Dates
Only “1” date should be entered in a project plan (Project Start Date)*
NEVER – NEVER – NEVER enter any other date !!!
All other dates should be a result of Predecessors and successor dependencies
* Exception (e.g. training, hardware delivery, 3rd party products)
Entered dates are called CONSTRAINT DATES
Project Management is a culture not a process
04/07/2023 Joel Saren ©201110
Dates (this is important)
MS Project uses three sets of dates and they are LINKED – CONNECTED TO EACH OTHER!
1. Start (aka) Scheduled Start & Finish (aka) Scheduled Finish
2. Actual Start & Finish
3. Baseline Start and Finish Also linked to these dates is % Complete NEVER NEVER NEVER enter a date manually (constraint date)
Project Management is a culture not a process
04/07/2023 Joel Saren ©201111
Dates
All project dates should be a result of previous tasks. Tasks need to be linked and rely on F/S, S/S, F/F. Using Lags +/-
Project Management is a culture not a process
04/07/2023 Joel Saren ©201112
Sample plan
Project Management is a culture not a process
04/07/2023 Joel Saren ©201113
Sample plan
Project Management is a culture not a process
04/07/2023 Joel Saren ©201114
Dates
All project dates should be a result of previous tasks.
Tasks need to be linked and rely on F/S, S/S, F/F.
Using Lags +/-
Project Management is a culture not a process
04/07/2023 Joel Saren ©201115
Working with Dates in MSProject
Start/Finish (Scheduled Start/Finish) % Complete
Actual Start/Finish Baseline1 Start/Finish
Project Management is a culture not a process
04/07/2023 Joel Saren ©201116
Resources
Resources need $ Resources need Units The Project Manager needs to manage the
Working Calendar (Time Off, Holidays, Vacations, etc) It affects deliverables. (a 9 hour task for Friday will take until Monday)
Project Management is a culture not a process
04/07/2023 Joel Saren ©201117
Assigning Resources
Available project hours To Summary Tasks (NOT) ???? Resource Leveling Resource Usage/Resource Graphs
Project Management is a culture not a process
04/07/2023 Joel Saren ©201118
Customizing MSProject
Project Management is a culture not a process
04/07/2023 Joel Saren ©201119
Baselining, Locking the Baseline
Setting the Baseline protects the Project Manager
Resetting the Baseline should never be done unilaterally by the Project Manager. Should only be done with stakeholder and customer’s approval
The Baseline dates is your protection
Project Management is a culture not a process
04/07/2023 Joel Saren ©201120
Metrics
Not possible w/o locking baseline SV CPI EV BCWS ACWP
Project Management is a culture not a process
04/07/2023 Joel Saren ©201121
Surprise!
NO SURPRISES!!!! Everyone talks to everyone else. Your team communicates with you and you
communicate with them. You communicate with your customer Everyone knows everything NO SURPRISES!!!!
Project Management is a culture not a process
04/07/2023 Joel Saren ©201122
Discussion
• What is the most important part of a project?
Project Management is a culture not a process
04/07/2023 Joel Saren ©201123
My Grandson’s swing set
Project Management is a culture not a process
04/07/2023 Joel Saren ©201124
Recommended reading
• Delivering Project Excellence with the Statement of Work, Michael G. Martin
• Earned Value Project Management, Fleming & Hoppelman
• The Mythical Man-month, Frederick Brooks, Jr
• Applied Software Measurement, Capers Jones
• Assessment and Control of Software Risks, Capers Jones
Project Management is a culture not a process
04/07/2023 Joel Saren ©201125
Feedback
• Improvement process, please email me [email protected] class comments.
• What did we do that you wish we spent more time on?• What did we do that you think we spent too much time on?• What didn’t we do that you wish we did do?• What did we do good?• What did we not do good?• Would you recommend this class to others?• Are there any other project management classes you would
like to take?
Project Management is a culture not a process
04/07/2023 Joel Saren ©201126
Wrap up
• Thank you all for being great participants.• I am humbled and honored to be allowed to come
to this part of the world and work with you.• I am open to hearing from you. [email protected]• Other resources:• WWW.PMI.ORG• WWW.ASAPM.ORG• WWW.PMBOULEVARD.COM • WWW.PMLINK.ORG
Project Management is a culture not a process
04/07/2023 Joel Saren ©201127
Questions?