Transcript
Page 1: Project Schedule Narrative - Chesapeake Regional Center · • Installation of Mincey Marble shower basins . Created Date: 4/12/2017 9:35:49 AM

Marriott Residence Inn at Johns Hopkins Medical Campus

Baltimore, MD

Project Schedule Narrative

Project Activities:

Site Improvements & Underground Utilities:

• Base course installation of valet parking lot

Back of House/Lobby:

• Overhead Rough – In in progress

• Permanent back of house lighting installation underway

• Lobby Ceiling hard lid ceilings in progress

• Back of House Kitchen Tile installation in progress

• Fire Pump and Controller assembly in progress

Retail:

• Construction of elevators 4 and 5 in progress

Tower:

• Overhead Rough-In in progress

• In-Wall Rough-In in progress on upper levels

• 3 Bank Elevator construction in progress - Construction Elevator Cab in operation

• Exterior Metal Panel installation in progress along North fin

• Tape and Finish of dry wall in progress through Level 5

• Guestroom Millwork on lower levels delivered and installation in progress

• Prime Coat for wall coverings on lower guestrooms.

Upcoming Activities:

Site Improvement & Underground Utilities:

• Installation of topping slab at Porte Cochere

• Installation and relocation of Street Lights

• Site Pavers and Hardscape scheduled for mid April

• Asphalt along Madison

Exterior

• EIFS installation on West Elevation

• Installation of Exterior Storefront Doors

Tower:

• Exterior Ornamental Handrail on Balcony

• Installation of Nanawall

Interior:

• Guestroom Tile and Flooring installation

• Guestroom Carpet installation

• Installation of Mincey Marble shower basins