Marriott Residence Inn at Johns Hopkins Medical Campus
Baltimore, MD
Project Schedule Narrative
Project Activities:
Site Improvements & Underground Utilities:
• Base course installation of valet parking lot
Back of House/Lobby:
• Overhead Rough – In in progress
• Permanent back of house lighting installation underway
• Lobby Ceiling hard lid ceilings in progress
• Back of House Kitchen Tile installation in progress
• Fire Pump and Controller assembly in progress
Retail:
• Construction of elevators 4 and 5 in progress
Tower:
• Overhead Rough-In in progress
• In-Wall Rough-In in progress on upper levels
• 3 Bank Elevator construction in progress - Construction Elevator Cab in operation
• Exterior Metal Panel installation in progress along North fin
• Tape and Finish of dry wall in progress through Level 5
• Guestroom Millwork on lower levels delivered and installation in progress
• Prime Coat for wall coverings on lower guestrooms.
Upcoming Activities:
Site Improvement & Underground Utilities:
• Installation of topping slab at Porte Cochere
• Installation and relocation of Street Lights
• Site Pavers and Hardscape scheduled for mid April
• Asphalt along Madison
Exterior
• EIFS installation on West Elevation
• Installation of Exterior Storefront Doors
Tower:
• Exterior Ornamental Handrail on Balcony
• Installation of Nanawall
Interior:
• Guestroom Tile and Flooring installation
• Guestroom Carpet installation
• Installation of Mincey Marble shower basins