Marriott Residence Inn at Johns Hopkins Medical Campus Baltimore, MD Project Schedule Narrative Project Activities: Site Improvements & Underground Utilities: Permanent Power from BGE complete Exterior Material Hoist demobilization Installation of Punch Windows and Ari Barrier at Material Hoist Location Back of House/Lobby: Overhead Rough – In in progress Permanent back of house lighting installation underway Level 2 east Lobby Curtain Wall framing complete MEP Piping insulation in progress Painting of Lower Level Mechanical and Electrical Rooms Fire Pump and Controller assembly in progress Retail: Overhead Rough–In in progress Precast Punch-List has begun Level 2 Storefront Framing in progress Level 2 hanging drywall Precast cap installation currently in progress Tower: Overhead Rough-In in progress In-Wall Rough-In in progress 3 Bank Elevator construction in progress - Construction Elevator Cab in operation Elevator 4 and 5 construction in progress Exterior Metal Panel installation in progress along North fin Interior Dry Install has begun 6 Tape and Finish of dry wall in progress through Level Guestroom Millwork on lower levels delivered and installation in progress Upcoming Activities: Site Improvement & Underground Utilities: Installation of topping slab at Porte Cochere Installation and relocation of Street Lights Site Pavers and Hardscape scheduled for late March Asphalt along Madison Exterior EIFS installation Tower: Installation of Level 16 Roof Terrace Waterproofing of bathroom spaces Permanent Heat and Gas Exterior Ornamental Handrail on Balcony Installation of Nanawall Interior: Guestroom Tile and Flooring installation Guestroom Carpet installation Installation of Mincey Marble shower basins

Project Schedule Narrative...• Installation of Mincey Marble shower basins . Created Date: 3/6/2017 9:03:57 AM

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Project Schedule Narrative...• Installation of Mincey Marble shower basins . Created Date: 3/6/2017 9:03:57 AM

Marriott Residence Inn at Johns Hopkins Medical Campus

Baltimore, MD

Project Schedule Narrative

Project Activities:

Site Improvements & Underground Utilities:

• Permanent Power from BGE complete

• Exterior Material Hoist demobilization

• Installation of Punch Windows and Ari Barrier at Material Hoist Location

Back of House/Lobby:

• Overhead Rough – In in progress

• Permanent back of house lighting installation underway

• Level 2 east Lobby Curtain Wall framing complete

• MEP Piping insulation in progress

• Painting of Lower Level Mechanical and Electrical Rooms

• Fire Pump and Controller assembly in progress

Retail:

• Overhead Rough–In in progress

• Precast Punch-List has begun

• Level 2 Storefront Framing in progress

• Level 2 hanging drywall

• Precast cap installation currently in progress

Tower:

• Overhead Rough-In in progress

• In-Wall Rough-In in progress

• 3 Bank Elevator construction in progress - Construction Elevator Cab in operation

• Elevator 4 and 5 construction in progress

• Exterior Metal Panel installation in progress along North fin

• Interior Dry Install has begun 6

• Tape and Finish of dry wall in progress through Level

• Guestroom Millwork on lower levels delivered and installation in progress

Upcoming Activities:

Site Improvement & Underground Utilities:

• Installation of topping slab at Porte Cochere

• Installation and relocation of Street Lights

• Site Pavers and Hardscape scheduled for late March

• Asphalt along Madison

Exterior

• EIFS installation

Tower:

• Installation of Level 16 Roof Terrace

• Waterproofing of bathroom spaces

• Permanent Heat and Gas

• Exterior Ornamental Handrail on Balcony

• Installation of Nanawall

Interior:

• Guestroom Tile and Flooring installation

• Guestroom Carpet installation

• Installation of Mincey Marble shower basins