Towering – Powering – Energising – Innovating
MANAGEMENTSYSTEMS
2
EXECUTIVE CHAIRMAN & GROUP MANAGING DIRECTOR’s MEssAGE
TAN sRI A K NATHAN
Moving To New Frontiers The history of Eversendai goes back to 1984 and after three decades of unparalleled experience, technical expertise and a strong network across various countries, Eversendai is recognised as a leading global organisation in undertaking turnkey contracts; delivering projects for high rise buildings, power plants, Oil & Gas upstream and downstream including process and industrial plants as well as infrastructure and composite structures in the Asian and Middle Eastern regions.
We have a dedicated workforce of over 10,000 people and an impressive portfolio of more than 300 accomplished projects in over 14 different countries with 7 fabrication facilities located in Malaysia, Dubai, Sharjah, Ras Al Khaimah, Qatar, India and Thailand with an annual capacity of over 222,000 metric tonnes. With our state-of-the-art steel fabrication factories, we have constructed some of the world’s most iconic landmark structures. These include the Burj Khalifa in Dubai, Petronas Tower 2 in Malaysia, Khalifa Olympic Stadium in Qatar, Kingdom Centre in Saudi Arabia and Republic Plaza in Singapore.
Our expansion plans, including our foray into the engineering, construction, procurement, fabrication and installation services for the Oil & Gas industry which is very much integral to our core operations, will also see us venture into new markets Today, we have the capability of handling total integrated multi-disciplinary construction packages involving all phases of construction work which include civil and building, structural and steel fabrication and erection, mechanical piping, tankage, process equipment erection and electrical and instrumentation works.
As we move to new frontiers, we will be able to provide our clients the certainty and comfort of knowing that their projects are in capable and experienced hands. These developments will complement our vision, mission and core values. This will simultaneously allow us to remain one of the most successful organisations in the Asian and Middle Eastern regions and beyond with corresponding efficiency and reliability. The successful and timely completion of our projects accompanied by soaring innovation, creativity and our aspiration to move to new frontiers have been the key drivers for achieving continuous growth through the years. We remain committed to these values and we believe, this stamps our firm intent to dominate the various industries which we are involved in and also marks the next phase in our development to be amongst the undisputed global market leaders.
Our strength lies in our resilient workforce whose skills, commitment and dedication serve the needs of our clients. An established management which overlooks the areas of planning, procurement, HSE and execution, combined with experienced managers, engineers alongside our workforce has made Eversendai a leading and innovative global organisation.
We are pleased to realise our aspirations of growing our business and we shall continually seek opportunities to globally expand our existing scope of operations.
This is just the beginning
3
4
OUR CORE VAlUEs
OUR MIssION
OUR VIsIONTO MAInTAIn OuR CORE vAluES AnD COnTInuOuSly InnOvATE AS WE MOvE TO nEW fROnTIERS
Compliance to sAFETy• Conformance to qUAlITy
• Adherence to sCHEDUlE • Consistent ClIENT sATIsFACTION
To excel in delivering our commitment to our clients
while strengthening and forging new ties. We
endeavour to maintain and enhance our consistent
performance, work culture and standards. We
strongly believe in maximising the value of human
capital and aligning it with company initiatives as a
fundamental element of our business objective
5
DuBAISHARjAH
ABu DHABIQATAR
SAuDI ARABIA
InDIA
RAS Al KHAIMAH
AzERBAIjAn
OMAn
OuR GlOBAl nETWORK
MAlAySIA
THAIlAnD
SRI lAnKA
SInGAPORE
EVER
sEND
AI C
ORP
ORA
TIO
N BE
RHAD
Subsidiary company
● Eversendai Engineering llC (Baku, Azerbaijan)
● Eversendai Engineering llC (Dubai, uAE)
● EVs Construction llC (Dubai, uAE)
● Eversendai Engineering llC (Abu Dhabi, uAE)
● Eversendai Engineering FZE (Sharjah, uAE)
● Eversendai Engineering saudi llC (Saudi Arabia)
● Eversendai Construction (s) Pte ltd (Singapore)
● Eversendai Technics Pte ltd (Singapore)
● Eversendai Energia sdn Bhd (Malaysia) (formerly known as Shineversendai Engineering (M) Sdn Bhd)
● Eversendai Offshore sdn Bhd (Malaysia)
● ECB Properties sdn Bhd (Malaysia)
● Perisai Kuasa sdn Bhd (Malaysia)
● Eversendai Constructions (M) sdn Bhd (Malaysia)
● Eversendai Frontiers Pvt ltd (Mumbai, India)
● Eversendai Engineering (Pvt) ltd (Sri lanka)
● Eversendai Oil & Gas (M) sdn Bhd (Malaysia)
● Eversendai Offshore RMC FZE (Ras Al Khaimah, uAE)
● Eversendai Engineering Pte ltd (Singapore)
● Eversendai Construction Pvt ltd (Chennai, India)
● Eversendai Engineering qatar Wll (Qatar)
● Eversendai s-Con Engineering Co. ltd. (Thailand)
ENGINEERING
6
structural, Connection Design & shop DrawingEversendai Corporation’s Offices in India, Dubai and Qatar provide technical services for all types of structures: -
• We are equipped with state of the art design and detailing software, with 3D modeling capabilities for structural design, connection design, temporary erection engineering for high-rise, industrial buildings & equipment support structures, shopping malls, convention centers and infrastructure projects.
• Shop drawings for structural steel and rebar engineering.
• Value engineering for member sizing, connections and innovative erection methodologies tailored to meet the project and the clients’ requirements.
• Complete 3 Dimensional model of structures and connections, exporting the nested cutting plans to various CnC machines directly using 3D model software to ensure accuracy in fabrication and erection of myriad of bolted joints.
• Structural steel erection engineering determining centre of gravity for intricate assemblies to assist in complex heavy lifts including in some of the tallest structures.
• Temporary structures as part of the model to eliminate fouling of members and cables during site assembly and erection.
• Complete material list, bolt list, stud bolt list extracted from model in advance for early and bulk procurement and effective site management.
7
Eversendai is equipped with software such as STAADPRO, ETABS, fASTRAK, DESCOn and ROBOT for Structural Design and custom made spread sheets for Connections and TEKlA STRuCTuRES, BOCAD, REvIT, RC-CAD and ACAD for Structural Steel and Rebar Detailing.
We carry out our own Research and Development, seeking new methodologies to improve deliverables, work processes, automation and procedures to enhance the engineering and fabrication drawing output using cutting edge 3D model technology.
Eversendai has a team of experienced design engineers and detailing personnel including experienced 3D structural model creators and checkers.
The majority of the projects for design and detailing conform to British, EuRO Standards and American Standards and our experienced team of people have
versatility in addition to the standards from uBC, IBC, jIS, Canada, Australia, Europe and India.
We have the expertise to deal with pipe profile structures, unfolding drawings with 3D uni-Planar and Multi planar joints.
Eversendai has been awarded with prestigious awards, such as the Golden Award as well as many Global BIM Awards for Best and Complex Models from Tekla Structures for various projects.
We provide electronic communications with a dedicated 24 hours, 7 days a week fTP server with high speed internet connections and voice over internet protocol (vOIP) and WebEx services across the different regions. Our engineering capability with almost three decades of experience in our chosen field of products and services ensure that our clients and customers are offered one-stop shop service to meet their varying needs.
FABRICATION FACIlITIEs
8
In keeping with Eversendai Corporation’s objective to enhance its premier position in the business through engineering excellence and specialist construction services, the company has further developed its fabrication capacity to accommodate Eversendai’s growing number of projects, boasting a combined annual fabrication capacity of over 150,000 metric tonnes.
Eversendai produces high quality fabricated structures and has the accreditation and certification from ASME Boiler and Pressure Code u, u2, S and the R Symbol from the national Board of Boilers and Pressure vessel Inspectors, for our facility at Hamriyah free zone, Sharjah, u.A.E .
All our fabrication factories are strategically located and have the capability and the capacity to fabricate and export high quality fabricated structures to any parts of the world on time.
Eversendai Corporation has fabrication factories at: -
Open yard Area : 40,761 sq metres fabrication Capacity : 24,000 tonnes
Total Area : 65,412 sq metres Total Building Area : 24,651 sq metres
Rawang Malaysia
Industrial Area Doha QatarTotal Area : 39,479 sq metresTotal Building Area : 16,128 sq metres
Open yard Area : 18,720 sq metres fabrication Capacity : 24,000 tonnes
Al Qusais Industrial DubaiOpen yard Area : 4,000 sq metres fabrication Capacity : 12,000 tonnes
Total Area : 12,000 sq metres Total Building Area : 8,000 sq metres
Chacherngsao, ThailandTotal Area : 78,400 sq metresTotal Building Area : 7,800 sq metres
Open yard Area : 7,800 sq metres fabrication Capacity : 12,000 tonnes
9
Hamriyah free zone Sharjah
Unit 1
Unit 2
Total Area : 211,168 sq metres
Total Building Area : 63,781 sq metres
Open yard Area : 147,387 sq metres
fabrication Capacity : 60,000 tonnes
10
11
12
Trichy IndiaTotal Area : 156,335 sq metresTotal Building Area : 9,040 sq metres
Open yard Area : 147,294 sq metresfabrication Capacity : 30,000 tonnes
Total Warehouse & Storage : 16,956 sq metresAssembly Area : 82,720 sq metresTotal Covered fabrication Area : 27,920 sq metresWater Depth : 7 metres
Total land Area : 200,000 sq metresQuayside : 550 metresOpen yard : 82,720 sq metresTonnage : 60,000
Rak Maritime City Ras Al Khaimah
13
All our fabrication facilities are certified with global standards and fabrication works are being carried out in accordance with the internationally recognized ISO 9001-2008 OHSAS 18001-2007 and ISO 14001-2004 standards under an Integrated Management System to maintain the highest global standards for Quality, Health & Safety and Environmental Management systems.
The factories are equipped with the latest state-of-the-art CnC (Computer numerical Controlled) machines which enable production of premium quality steelwork components by facilitating quality material preparation activities with optimum usage of time and materials and with high accuracy by avoiding all possible human errors, for the subsequent assembly and welding activities as part of the fabrication process.
We are also equipped with all the required precise CnC machinery and highly skilled personnel to face any kind of challenges in the fabrication of complex structures in order to turn the architect’s dreams into reality. This has been acknowledged by many renowned architects /designers throughout the world and we have been provided with many opportunities to get involved in iconic projects in the Middle East as well as in other parts of world where we serve various clients.
In order to meet complex requirements of developing a 2D concept into a 3D real time model, we adopt precise fabrication methods and quality standards to incorporate the required free hand curves/bends drawn by the architects onto the steel components.
In this process, we use highly precise total stations to co-ordinate each and every structural component being placed in multiple planes, as extracted from the 3D real time models, and maintain the architectural intent by deploying highly précised CnC machinery as well as an experienced workforce and supervisory staff. The efforts being extended to make the control assemblies wherever required, on the shop floor itself, eliminates all kinds of mismatches as well as related time losses to attend to any mismatches on site.
Our ability to convert concepts such as the rose bud in Rose Tower in Dubai, the complex wave form roof structures at Dubai Mall, the air craft shape at the New Doha International Airport (NDIA), desert flower at Qatar national Museum, and leaning tower at Capital gate at Abu Dhabi shows our strength to meet any kind of complex requirements.
The operator of our machines shall receive the nC data generated from the 3D TEKlA detailing software directly from the engineering office.
The details of the various high precise CnC machinery set up at our factories are as follows:
Plate Cutting MachineCNC Controlled Plate cutting/profiling machine supplied by SATO Cutting Systems, Germany, has the capability to process plates up to 24m long x 5m wide of 200 mm thick (max) by using oxy/acetylene or plasma cutting facilities.
14
15
Tube Profiling MachinesThe pipe profiling machine supplied by Muller Opladen, Germany is a six axis CnC controlled machine utilizing plasma or oxy/acetylene for cutting the profiles on hallow sections. The machine has the ability to make profiles on pipes and square hallow sections with/without weld bevels.
Plate Punching, Drilling& Cutting Machine The plate processing machine supplied by Peddinghaus, u.S.A, has the ability to punch, drill, mark and cut plates using plasma or oxy/acetylene of thickness up to 75 mm.
saw, Drill & Notching line This heavy duty saw and drill supplied by Kaltenbach, Germany has the ability to cut sections of width 1340mm and height 730mm, capable of sawing at variable metering and automatic drilling with three axis drill facility up to a dia of 40 mm. The coping machine which is part of the setup is capable of coping and cutting the sections, angles, channels, tubes and hollow sections using its 6 axis robotic arm mounted with plasma and or oxy/acetylene cutting torch options.
16
Bending Machine Eversendai has got one of the world’s largest section bending machine. This machine is capable of rolling all kinds of I sections & channels (on both axis) and pipes etc. Its operating range includes a maximum of 800mm diameter in pipes and 1000mm depth in sections.
Gantry Welder Heavy built-up requirements shall be carried out by using the automatic SAW Gantry Welding machine to build “H” beams, “I” beams and other hollow sections like rectangle and square box sections. This machine has been provided with two arms and accordingly two built-up sections can be welded simultaneously.
Plate Rolling Machine This is the most advanced “Roll by wire” technology based full hydraulic variable axis plate bending machine with a maximum capacity of 2200 MT. It is capable of rolling a maximum of 170 mm in plate thickness and 3000 mm in plate width along with the optional cone rolling facility.
surface Treatment Equipment The shops are provided with dedicated auto blasting machines with openings – 1500mm width x 200m height and 1200mm width x 1200mm height and manual blasting chambers (5m x 5m x 14m) to cater the needs for the blast cleaning of the steelwork prior to application of project specific paint systems.
17
FABRICATION
18
FABRICATION
19
20
FABRICATION
21
22
AWARDs & CERTIFICATIONs
22
GOlDEN CONsTRUCTION AWARD 2008
By the Trade leaders Club, Madrid, Spain
INTERNATIONAl sTAR AWARDFOR lEADERsHIP IN qUAlITy 2009
By Business Initiatives Directions, france
MAlAysIAN CONsTRUCTION INDUsTRy EXCEllENCE AWARDs 2005 – INTERNATIONAl ACHIEVEMENT AWARD
By the Construction Industry Development Board Malaysia
MAlAysIAN CONsTRUCTION INDUsTRy EXCEllENCE AWARDs 2013 – INTERNATIONAl ACHIEVEMENT AWARD
By the Construction Industry Development Board Malaysia
23
OUR EXPERTIsE
24
Integrated Structural Steel Works
Composite Structures
Mechanical fabrication
Self-Propelled jack-ups/liftboatsProcess Modules Topside Platforms Rig Refurbishmentjack-up Drilling Rigs Offshore Structures Offshore living Quarters
Mechanical Installation Work for Power & Petrochemical Plants
value Engineering & Erection Methodology
High-Rise Buildings
long Span &Roof Structures
Bridges
Oil & GasOffshore/Onshore
and Marine fabrication
Industrial, Petrochemical& Power Plants
Retail & Commercial
OUR GlOBAlPORTFOlIO
25
Caltex Tower, SingaporeHitachi Tower, Singapore
26
HIGH-RIsE BUIlDINGsOUR GlOBAl PORTFOlIO
27
Republic Plaza, Singapore The Paragon, Singapore
28
uE Square, Singapore Chartered Square Building, Thailand
29
Petronas Twin Tower 2, Malaysia
30
TH Perdana Tower, Malaysia Telekom Building, Malaysia
31
Kuala lumpur Tower, Malaysia Marina Crown, Dubai
32
Burj Al Arab, Dubai
33
uP Tower, Dubai Al Mas Tower, Dubai
34
Burj Khalifa, Dubai
35
Rose Rayhaan Rotana, Dubai Emirates Office & Hotel Towers,Dubai
36
The Index, Dubai Princess Tower, Dubai
37
jW Marriott Marquis Hotel, Dubai
38
Burj Dubai Annexe, Dubai
Al jalilah Hospital, Dubai
39
Gate Building, Dubai
Chelsea Tower, Dubai Airport Control Tower, Dubai
40
Address Residence Sky views, Dubai
Gate District Towers, Abu Dhabi
41
Hard Rock Hotel, Abu Dhabi ADnOC Headquarters, Abu Dhabi
42
Cleveland Clinic, Abu Dhabi
43
Capital Gate Tower, Abu Dhabi
44
Al Sham Tower, Abu Dhabi Al nasser Headquarters,Abu Dhabi
45
Tornado Tower, Qatar Al Moayyed Tower, Bahrain
46
Crescent City, Azerbaijan
47
Kingdom Centre, Saudi Arabia Capital Market Authority Tower, Saudi Arabia
48
Empire Tower, Indonesia Worli Tower, India
49
Statue of unity, India
Kingfisher Towers, IndiaMarathon futurex, India
50
lONG sPAN AND ROOF sTRUCTUREs
Tuas Checkpoint, Singapore
Indoor Stadium, Singapore
51
Changi Airport Terminal 3, Singapore
Bintulu Airport, Malaysia
5252
Kuala lumpur International Airport Main Terminal, Malaysia
Kuala lumpur International Airport Contact Pier, Malaysia
5353
Rawang - Ipoh Double Track, Malaysia
Kl Sentral Station, Malaysia
54
Customs, Immigration & Quarantine Complex, Malaysia
Abu Dhabi Airport, Abu Dhabi
55
Qatar faculty of Islamic Studies, Qatar
Doha Convention Centre, Qatar
56
Convention Center Extension - Education City, Qatar
new Doha International Airport, Qatar
57
Khalifa Olympic Stadium, Qatar
Qatar national Museum, Qatar
58
Ski Dubai, Dubai
Chhatrapati Shivaji International Airport, India
59
Salalah Ampitheatre, Oman
Salalah Airport, Oman
60
King Abdulaziz International Airport - Railway Station, Saudi Arabia
King Abdullah Petroleum Studies & Research Centre, Saudi Arabia
61
Sheikh zayed Cricket Stadium, Abu Dhabi
Chek lap Kok Airport Extension, Hong Kong
felda Multi-Purpose Hall, Malaysia
Subang Airport Hangar, Malaysia
Qatar Airways Hangar, Qatar
62
RETAIl & COMMERCIAl
Putrajaya Convention Centre, Malaysia
Suria KlCC, Malaysia
63
PKT logistics Warehouse, Malaysia
PKT 12 Waves Warehouse, Malaysia
64
nas Arena Multi Purpose Hall, Dubai
Opera House, Dubai
65
Burj Al Salam Carpark, Dubai
Hub zero family Entertainment Centre, Dubai
6666
Dragon Mart, Dubai
Dubai Mall, Dubai
6767
Masdar Institute of Science & Technology, Abu Dhabi
yas Mall, Abu Dhabi
6868
Qatar Science & Tech Park, Qatar
Pearl Mansion, Qatar
6969
Qatar foundation Research & Development Complex, Qatar
Multipurpose Hand Ball Stadium Duhail, Qatar
70
Dhirubai Ambani International Convention and Exhibition Centre, India
71
7272
TnRD Bangi Project, Malaysia
Kulim Wafer Plant, Malaysia
Motor City, Dubai festival City, Dubai
Asian Institute of Medicine, Science & Technology, Malaysia
floating Restaurant - Etihad Towers, Abu Dhabi
7373
Robertson Quay, Singapore
King George’s foot Bridge, Singapore
BRIDGEs
74
Marriott Executive Apartments, Dubai
Dubai frame, Dubai
74
7575
Atmosphere Sky Bridge, India
KlIA 2 Sky Bridge, Malaysia
76
Petronas Twin Towers Sky Bridge, Malaysia
KLIA - Pan Pacific Hotel Linkbridge, Malaysia
77
jalan Tun Razak viaduct, Malaysia
Kuala lumpur lRT Bridge, Malaysia
78
Bamban Bridge, Philippines
Mabalacat Bridge, Philippines
79
INDUsTRIAl, PETROCHEMICAl& POWER PlANTs
3 X 700 MW Manjung Power Plant, Malaysia
Proton national Car Plant, Malaysia
80
3 X 700 MW Manjung Power Plant, Malaysia - Boilers
81
3 X 700 MW Manjung Power Plant, Malaysia - Electrostatic Precipitator
3 X 700 MW Manjung Power Plant, Malaysia - Stockyard
82
3 X 700 MW Manjung Power Plant, Malaysia - Coal & Ash
3 X 700 MW Manjung Power Plant, Malaysia - fuel Gas Desulphurisation
83
3 X 700 MW Manjung Power Plant, Malaysia - Mill Bay
2 X 700 MW jimah Power Plant, Malaysia
84
3 X 700 MW Tanjung Bin Power Plant, Malaysia
85
1 X 1000 MW Manjung Power Plant - unit 4, Malaysia
86
Petronas fertiliser Complex, Malaysia
Sultan Salahuddin Abdul Aziz Power Station Phase II & III, Malaysia
1 X 1000 MW Tanjung Bin Power Plant - unit 4, Malaysia
87
1x1000MW Tanjung Bin Power Plant-unit 4,Malaysia:Turbine Installation
88
Terengganu Gas Terminal, Malaysia
89
Sabah Oil & Gas Terminal, Malaysia
90
MlnG 3, Malaysia
Perwaja Steel Mill Plant Extension, Malaysia
91
2 X 300 MW EMCO Thermal Power Plant, India
2X 500MW nTPl Tuticorin Project, India
9292
nakilat Damen Shipyard Phase 4, Qatar
93
nakilat Damen Shipyard Phase 4A, Qatar
9494
Garraf Development facility Operation, Iraq
Gabbro Terminal, Qatar
95
Algeria fertiliser Plant, Algeria
2 X 600 MW north Chennai Power Station, India
Palm Oleo, Malaysia
Polycrystalline Silicon Plant, Malaysia
OIl & GAs ONsHORE/OFFsHORE & MARINE FABRICATION
96
Specifications Design : Gusto MSC nG2500X
Hull dimensions : l: 61m x W: 36m x D:6m
leg length : 4 x 94.2 metres (lattice)
Max Water Depth : 70 metres
Max Wave Height : 8 metres
Main Deck Area : 800 square metres
variable load : 1,300 tonnes
Main CraneCapacity : 300 tonnes
AccommodationCapacity : 200 POB
Propulsion System : 4 x 1,200 KW
Control System : Dynamic Positioning System (DP-2)
Self-Propelled Jack-Up/Liftboat
SWL 12.5t @ 30m
HOSE REEL SB
R450
Huisman
MAX 85º 22900 TOS
TOG21350 A.B.
24500 A.B.
TOP DECK(EL. (+)22190)
4TH LEVEL
3RD LEVEL
2ND LEVEL
1ST LEVEL
MAIN DECK
BASELINETANK TOP (EL (+) 1208)
(EL. (+)18800)
(EL. (+)15700)
(EL. (+)12600)
(EL. (+) 9500)
(EL. (+) 6000)
(EL. (+) 0)
97
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
1988 Singapore Indoor Stadium
fabrication and Erection of Temporary Steel Structure
Ssangyong Guan Ho/ nipponSteel Corporation 400
1988 Singapore Indoor Stadium
Erection of Main Keel Truss and nS Space frame Structures
Ssangyong Guan Ho/ nipponSteel Corporation 1,200
1988
Pulau Seraya Power Station Stage II C.W. Conduits, Pumphouse & Water Treatment Plant, Singapore
Blasting and Painting to sheet piles, H-Piles and z-Piles
Singapore Piling & Civil Engineering Pte. ltd. 900
1989Pulau Seraya Power Station Stage II, Singapore
A) Blasting to SA 2.5 , Painting 3 coats of paint 375microns DfT to Sheet Piles, H-Piles and z-Piles. B)Welding of Box Piles and H-Pile shoes
Singapore Piling & Civil Engineering Pte. ltd.
A) Surface area 80,521 Sq.Mtrs B) 1100 Box Piles and 600 H-Pile.
1989Senoko Station Gas Turbine Power Plant, Singapore
Erection of Structural Steel Siemens - Kim Seng Heng Engineering & Construction Pte. ltd.
300
1989Reconstruction of Sir Arthur Bridge, Singapore
Piling of H-Piles and Sheet-Piles, fabrication, Erection of Temporary Steel Bridge and Strutting works for Cofferdam
Singapore Piling & Civil Engineering Pte. ltd. 300
1989 Restoration of national Museum, Singapore
fabrication and Erection of Structural Steel Roof
Singapore Piling & Civil Engineering Pte. ltd. -
1989Pulau Seraya Power Station Stage II, Singapore
fabrication, Strutting, Dismantling and Erection of Structural Steel works
Singapore Piling & Civil Engineering Pte. ltd. 900
1990
Pulau Seraya Power Station Stage II - foundation & Building Works, Singapore
Painting to the Erected Turbine Steel Structures
Singapore Piling & Civil Engineering Pte. ltd. 5,800
1991
Amphitheatre with 2 storey ancillary building and South East Asian Birds Walk-in Aviary for jurong Bird Park, Singapore
fabrication and Erection of Structural Steel Works
Singapore Piling & Civil Engineering Pte. ltd. 450
1991 Comcenter (Singapore Telecoms), Singapore
Erection of Steel Strutting at Basement
Singapore Piling & Civil Engineering Pte. ltd. 1,100
1991
Hitachi Towers - 37 Storey Office/Commercial Building at Collyer Quay, Singapore.
Erection of Structural Steel Works including Decking and Stud welding.
Obayashi Corporation/ nippon Steel Corporation 5,600
lIsT OF BUsINEss PROJECTs
98
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
1991
Caltex Towers - 33 Storey Office/Commercial Building at Collyer Quay, Singapore.
Erection of Structural Steel Works including Decking and Stud welding.
Obayashi Corporation/ nippon Steel Corporation 4,700
1992
Clarke Quay Restoration and Redevelopment, Singapore
Shop Drawing, Blasting to SA 2.5, Primer Painting, fabrication, 3 coat Paint system and Erection of Structural Steel Works
Singapore Piling & Civil Engineering Pte. ltd.
450 tonnes. (Roof
Structure consists of Hollow Section)
1992 Republic Plaza, Singapore
Erection of Structural Steel Works
Shimizu Construction/ nippon Steel Corporation 8,000
1993
Pulau Seraya Power Station Stage III C.W. Conduits, Pumphouse & Water Treatment Plant, Singapore
Blasting and Painting of Sheet Piles, H-Piles and z-Piles
Singapore Piling & Civil Engineering Pte. ltd.
Surface Area 180,000 m2 + 2,500 tonnes
1993Pulau Seraya Power Station Stage III, Singapore
Welding of Box Piles and H-Pile shoes
Singapore Piling & Civil Engineering Pte. ltd.
3,500 Box Piles and
1,200 H-Pile shoes
1993 Shell Easter Petroleum Pulau ular, Singapore
Erection of Structural Steel Works
Chiyoda Corp - Mitsui-Keppel Consortium 500
1993 ATM Towers, Thailand
Erection of Structural Steel, Alignment, olting, Deck Installation, Stud Bolt Welding, Civil work- laying of wire mesh, setting rebars, form work and concreting works
Pan Pacific Construction Engineering Pte ltd 4,200
1993
Balawan Combined Cycle Power Plant Block II, Medan, Indonesia
fabrication & Erection of Structural Steel, Blasting and Painting
SIEMEnS / Kian Sukses 750
1993 Kl Tower, Malaysia
Erection of Structural Steel, Alignment, Bolting and Installation of Secondary Steel
Wayss & fretag & victor Buyck Steel Construction Sdn Bhd
1,600
1994 Petronas Twin Tower 2, Malaysia
Erection of Structural Steel inclusive of embedded plates
Samsung - Kukdong - jasatera jv/Samsung Heavy Industries
8,000
1994 Perwaja Steel Mill Plant Extension, Malaysia
Erection of Structural Steel, Alignment Bolting and Welding
Hazama - Tomoe Corporation - Mech-Mar Keppel 4,000
1994 Kl Tower (Antenna Mast), Malaysia Erection of Antenna Mast
Wayss & fretag & victor Buyck Steel Construction Sdn Bhd
100
1994 Temasek Polytechnic (Phase II), Singapore
fabrication and Erection of Structural Steel Works
Singapore Piling & Civil Engineering Pte ltd. 1,000
99
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
1994 Empire Tower, Indonesia
Erection of Structural Steel, Alignment, Bolting, Welding, Deck Installation and Stud Bolt Welding
PT Total Construction 3,000
1995 Petronas Tower 2 - Sky Bridge, Malaysia
Site Assembly and Erection, Alignment and Bolting of the Bridge connecting both the towers
Samsung - Kukdong - jasatera jv/Samsung Heavy Industries
500
1995 Suria KlCC, Malaysia
Erection of Structural Steel, Alignment, Bolting, Welding, Deck Installation and Stud Bolt Welding
victor Buyck Steel Construction Sdn. Bhd. 18,000
1995
Kuala lumpur International Airport, Main Terminal Building and Contact Pier, Malaysia
Erection of Structural Steel, Alignment, Bolting and Welding Works
Taisei/Tomoe Corporation 9,305
1995 uE Square, Singapore Erection of Structural Steel Works
Kajima Corporation / Tomoe Corporation 1,900
1996 jKR Building, labuan, Malaysia
Erection of Structural Steel, Alignment, Bolting, Welding, Deck Installation and Stud Bolt Welding
Pernas Construction Sdn Bhd &Cleaveland EOn Asia Sdn Bhd
1,600
1996
Sultan Salahuddin Abdul Aziz Power Station - Phase III, Kapar, Malaysia
Erection of Structural Steel, Bridge, Crane, Heat Exchangers and Starge Tanks , Bolting & Welding, Alignment, Installation of Decks, and Shear Studs
Cleaveland EOn Asia Sdn. Bhd 6,000
1996 Burj Al Arab, Dubai
Erection Methodology, Site Assembly, Erection of Structural Steel, Alignment, Bolting and Welding Works
Al Habtoor/fletcher/ Murray & Roberts jv 9,200
1996TPC II/Bl-2 Project, Pulau Ayer Merbau, Singapore
Erection of Structural Steel, Installation of Deck and Edge Plates
jSW & Sumitomo Construction Co. ltd 700
1996Tuas Checkpoint Tubular Structures, Singapore
Supply, fabrication, and Erection of Tubular Structures.
Gtm - Wansoon - Woh Hup - Mero Consortium 4,200
1997 light Rail Transit Bridges, Malaysia
Assembly and Erection of Structural Steel, Alignment and Bolting Works
victor Buyck Steel Construction Sdn. Bhd. 2,800
1997 Malaysia Airlines Hangar, Malaysia
Site Assembly, Erection of Structural Steel, Alignment and Bolting Works
Strarch & Geahin Engineering Berhad 2,100
1997
Kuala lumpur International Airport Pan Pacific Hotel - Link Bridge, Malaysia
Structural Design, Supply Material, Engineering, fabrication, Erection, Alignment and Bolting Works
Peremba – Multiplex jv 300
100
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
1997Sharp Roxy, SMM & SREC Warehouse, Malaysia
Erection of Structural Steel, Alignment and Bolting Works
Shimizu Corporation - Geahin Engineering Berhad 600
1997 TnRD Bangi, Malaysia Erection of Structural Steel, Alignment and Bolting Works Geahin Engineering Berhad 2,700
1997langzem Cement Plant Extension, langkawi, Malaysia
Erection of Structural Steel, Alignment and Bolting Works
nam fatt fabricators Sdn. Bhd. 800
1997 Palm Oleo 2 Project, Malaysia
Process Building, Tank farm, Pipe Rack, Erection of Structural Steel, Alignment and Bolting Works
Geahin Engineering Berhad 900
1997KlIA Cargo Terminal - CSS Structure , Malaysia
Erection of Structural Steel, Alignment and Bolting
MHE – Demag logistics Sdn Bhd 1,100
1997Kl Sentral Station - Roof Structure, Malaysia
Conceptual Design, Supply Material, Engineering, fabrication, Erection of Structural Steel, Alignment, Bolting and Site Welding Works
Ekovest – KMz – Dragages jv 1,350
1997 vision City, Malaysia Erection of Structural Steel, Alignment and Bolting Works
victor Buyck Steel Construction Sdn Bhd 700
1997Hitachi nippon Steel Semi Conductor, Singapore
Erection of Structural Steel and Installation of Deck. Kajima - nippon Steel 4,300
1997 Trellis Tower, Singapore Installation of Precast Panels Shimizu Corporation 7000 nos.
1997Singapore Manufacturing Project, Singapore
Erection of Structural Steel Works.
Chiyoda Corporation - Sumitomo Construction Consortium
1,200
1997
Pipe Bridge and Catwalk for Singapore Manufacturing, Singapore
Supply, fabrication and Erection of Structural Steel Works.
Chiyoda Corporation - McConnell Dowell S.E.A. Consortium
100
1998Petronas fertiilzer Complex, Guru, Malaysia
Erection of Structural Steel, Alignment and Bolting Works
Mitsubishi Heavy Industries/Cleveland EOn Asia Sdn. Bhd.
4,100
1998Hong Kong Airport Extension C304 Project, Hong Kong
Site Assembly, Erection of Structural Steel, Alignment and Bolting Works
Zen Pacific / Geahin Engineering Berhad 1,350
1998 Kerteh Aromatics Project , Malaysia
Installation of Structural Steel, Equipment, Tank and Piping Works
Toyo Engineering - nam fatt fabricators Consortium 1,250
1998Telekom Building - Sky Garden Steel Trusses, Malaysia
Supply Material, Engineering, fabrication and Erection of Structural Steel Works
Daewoo Corporation 1,150
1998 Telekom Building - Helipad, Malaysia
Erection of Steel and Aluminium Structures Daewoo Corporation 460
101
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
1998jalan Tun Razak viaduct, Kuala lumpur, Malaysia
Site Assembly and Erection of Structural Steel viaduct including Bearing Installation Works
Percon Corporation - namfatt 6,481
1998 Grande legenda Resort, Malaysia
Erection of Structural Steel, Alignment and Bolting Works Geahin Engineering Berhad 2,100
1998
Cyberjaya Multimedia Super Corridor for Telekom university , Malaysia
fabrication and Erection of Structural Steel, Alignment and Bolting Works
MK farlin Development - Perwaja Steel 1,200
1998 Emirates Tower - Hotel, Dubai
Site Assembly and Erection of Structural Steel, Alignment, Bolting and Site Welding Works
Besix - Ssangyong jv/Murray & Roberts - Cleveland Bridge jv
3,500
1998 Emirates Tower - Offices, Dubai
Site Assembly and Erection of Structural Steel, Alignment, Bolting and Site Welding Works
Besix - Ssangyong jv/Murray & Roberts - Cleveland Bridge jv
6,500
1998 Kl Sentral Station, Malaysia
Engineering, Supply Material, fabrication and Erection of Built-up Beams for Substructure
Ekovest - KMz - Dragages jv 1,000
1998 Institut Teknologi Petronas, Malaysia
Erection of Structural Steel, Alignment and Bolting Works Geahin Engineering Berhad 200
1998
Pinatubo Hazard urgent Mitigation Project - Mabalacat & Bamban Bridges, Philippines
Erection of Steel Arch Bridge for Bamban and Plate Girder Mabalacat Bridge
Mitsubhishi Heavy Industries 1,900
1998Polyvinyl Alchol Plant (PvA), Pulau Sakra, Singapore
Supply, fabrication, Painting and Erection of Structural Steel Works
Kuraray Engineering Co. ltd. 160
1998 One Raffles Link, Singapore
Erection of Structural Steel and Installation of Deck
Gammon Pte ltd & Wescol Asia Pacific Pte Ltd 2,200
1998 Bank of China, Singapore
Installation of Precast façade Panels
Shimizu Corporation/ lWC Industries 1600 nos.
1998 Paragon Tower, Singapore
Erection of Structural Steel Works nishmatsu - TTj Consortium 2,800
1998 Proton City- Phase 1-A4 Malaysia
Erection of Structural Steel Works Cleveland Eon Asia Sdn Bhd 3,500
1999
Sultan Salahuddin Abdul Aziz Power Station- Refurbishment upgrading & Extension of Coal Handling System, Malaysia
Engineering, fabrication and Installation of Conveyor Structures and Mechanical Erection Works
TnEC - Hartasuma - KTK Consortium 900
1999 Dubai Airport Control Tower, Dubai
Erection of Structural Steel, Alignment and Bolting Works Besix/Al nasr 900
102
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
1999 Ritz Carlton Hotel, Doha, Qatar
Erection of Structural Steel, Alignment and Bolting Works Midmac Contracting/AIC 900
1999 Silicon Wafer fabrication facilities
Site-Assembly and Erection of Structural Steel, Alignment and Bolting Works
flour Daniel - Kvaerner Cleveland 2,300
1999 King Center foot Bridge ,Singapore
Shop Drawings, fabrication and Erection of Bridge Structures
Chin leong Construction Pte. ltd. 125
1999 Robertson Quay foot Bridge, Singapore
Shop Drawings, fabrication and Erection of Bridge Structures
Hon Construction Pvt. ltd., 130
1999 Inchcape Warehouse Project, Singapore
Erection of Structural Steel Works
Shimizu Corporation - nKK Corporation Consortium 600
2000 TH Perdana, Malaysia
Connection Design, fabrication and Erection of Structural Steel and fire Proofing Works
Maju Holdings Sdn Bhd 4,000
2000 felda Multi-Purpose Hall, Malaysia
Connection Design, Engineering, Supply Material, fabrication and Erection of Structural Steel
felda Ekovest Sdn Bhd 425
2000 Kl Sentral Station Roof Top Trellis, Malaysia
Structural Design, Engineering, Supply Material, fabrication and Erection of Structural Steel Works
EKD Construction Sdn. Bhd. 100
2000Kl Sentral Station Maintenance System, Malaysia
Erection of Structural Steel & Aluminium Works TK Gondala Pte. ltd. 150
2000Reefer Stack Access Gantry Structures, Malaysia
Erection of Structural Steel, Alignment and Bolting Works
namfatt fabricators Sdn. Bhd. 600
2000 Kingdom Trade Centre, Riyadh, Saudi Arabia
Structural Re-design, Engineering, Supply Material, fabrication, Erection of Structural Steel, Metal Deckingand Fire Proofing Works
Kingdom Holding Company, El Seif - Impregilo jv 6,027
2000Thermal Energy Storage Tank - KTC, Riyadh, Saudi Arabia
Structural Re-design, Engineering, Supply Material, fabrication and Installation of Tank
El Seif - Impregilo jv 380
2000Al faisaliah Roof feature - Riyadh, Saudi Arabia
Erection of Structural Steel Works.
AIC / Saudi Binladin Group jv 350
2000Secondary School at fenvale link, Singapore
Supply, fabrication, and Erection of Steel Structure Works.
Synergy Construction Pte. ltd. 125
2000 zhongghua Primary School, Singapore
Supply, fabrication and Erection of Structural Steel Works.
Synergy Construction Pte. ltd. 65
103
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
20004 Storey single-user factory for Dupont, Singapore
Supply, fabrication and Erection of Structural Steel and Installation of Dect.
McConnell Dowell 1,400
2000ISBl & OSBl Super Structure for Dupont, Singapore
Supply, fabrication and Erection of Structural Steel Works.
McConnell Dowell 100
2000
Additions & Alterations to Existing St Margaret’s Primary School, Singapore
Supply, fabrication and Erection of Structural Steel Works.
Synergy Construction Pte. ltd. 260
2000 zhongghua Primary School, Malaysia
Supply, fabrication and Erection of Structural Steel Works.
Synergy Construction Pte. ltd. 175
2001
Manjung 3 x 700 MW Coal fired Power Plant - Boiler Package, Malaysia
Erection of Mechanical Works for Boiler Plant, consisting of Boiler Pressure & non Pressure Parts, Steel Structure, ducting, Piping, Gas Air Heater, Electrostatic Precipitator, Mill Plant, Coal Bunker, Insulation & Refractory, Painting, Cladding, Control and Instrumentation Works.
Alstom Export Sdn Bhd 40,000
2001 uP Tower, Dubai Erection of Structural Steel and Pre-cast Concrete Slabs
nasa Multiplex/Emirates Building Systems 1,600
2001 MlnG Tiga, Malaysia
Erection of Structural Steel for Pipe Racks, Pipe Sleepers, Accessories, Platforms and Access Ways
Dotanah Engineering & Contracting Sdn. Bhd. 850
2001
Manjung 3 x 700 MW Coal fired Power Plant - fGD Package, Malaysia
Erection of Mechanical Works for fuel Gas Desulphurisation Plant, consisting of Steel Structure, Ducting, Piping, Insulation & Refractory, Painting, Control and Instrumentation Works.
Alstom Export Sdn Bhd 4,500
2001
Manjung 3 x 700 MW Coal fired Power Plant - Coal And Ash Package, Malaysia
Erection of Mechanical Works for Coal & Ash Handling System, consisting of Steel Structure, Transfer Towers, Conveyor Belts, Silos, Trippers, Piping, Refractory, Painting, Cladding, Control and Instrumentation Works
Alstom Export Sdn Bhd 6,500
2001 Matriculation School - Gambang, Malaysia
Connection Design, Engineering, Supply Material, fabrication and Erection of Structural Steel Works.
Maju Holdings Sdn Bhd 4,500
2001 Gelugor Power Station, Malaysia
Supply Material, Engineering fabrication and Erection of Chimney Stack.
Mudajaya Construction Sdn. Bhd. 650
104
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2001
Manjung 3 x 700 MW Coal fired Power Plant - Coal Stock yard Package, Malaysia
Erection of Mechanical Works for Coal Stockyard consisting of Steel Structure, Stacker, Reclaimer, Transfer Towers, Conveyor Belts, Painting, Cladding, Control and Instrumentation Works
KOCH Industrial (M) Sdn Bhd 3,500
2001
Electrified Double Track Project between Rawang and Ipoh, Malaysia
Supply Material, Engineering, fabrication and Erection of Structural Steel Works
IjM Corporation Bhd 2,415
2001Philip Morris - Greenfield Project, Philippines
Supply Material, Engineering, fabrication and Erection of Structural Steel Works
leighton Contractors (Philipppines) Inc. 4,200
2001 Putrajaya Convention Centre, Malaysia
Supply Material, Engineering, fabrication and Erection of Structural Steel Works
IjM Corporation Sdn. Bhd. 6,800
2001 new Bintulu Airport, Malaysia
Supply Material, Engineering, fabrication and Erection of Structural Steel, Metal Sheet Roofing and Ceiling Works
Global upline Sdn Bhd 1,000
2001 Peiying Primary School, Singapore
Supply, fabrication and Erection of Structural Steel Works
Seng Hock Heng 183
2002
Panglima 720 MW Combined Cycle Power Plant - Electrochilorination Plantm Malaysia
Erection of Mechanical & Electrical Works
Siemens Power Generation AsiaPac Sdn Bhd / DAIKI Engineering Co ltd
-
2002
Asian Institute of Medicine, Science and Technology (AIMST), Malaysia
Erection of Structural Works SP Setia Bhd 8,500
2002 Sheikh zayed Cricket Stadium, Abu Dhabi Erection of Structural Works Al-Habtoor/Murray & Roberts
jv 800
2002 Skywalk Tower link Bridge Project, Dubai Erection of Structural Works Emirates Building Systems
l.l.C 140
2002 Al Moayyed Tower , Bahrain Erection of Structural Works fujairah national
Construction l.l.C. 2,000
2002 Kastam Kompleks, Kelana jaya, Malaysia
Connection Design, Engineering, Supply Material, fabrication and Erection of Structural Steel Works.
Maju Holdings & lal Engineering Sdn Bhd 1,860
2002 Opera Estate Primary School, Malaysia
Supply Material, Engineering, fabrication, Galvanizing and Erection of Steel Works
Synergy Construction Pte ltd 400
2002 BP nam Con Son Gas Project, vietnam
Supply Material, Engineering, fabrication & Export of Structural Steel Works
McConnell Dowell Constructor (Aus) Pty ltd 1,050
105
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2002 Abu Dhabi Conference Hall, Abu Dhabi Erection of Structural Works Al-nasr Engineering/Belhasa
Six Construct 1,300
2002 jebel Ali ‘K’ Station Phase II, Dubai
Strengthening works for Service Building
Department of Electricity and Water, Six Construct ltd.
2002 jebel Ali ‘K’ Station Phase II, Dubai
Dismantling & Erection of Structural Steelwork
Department of Electricity and Water, Six Construct ltd. 350
2002 21st Century Tower, Dubai
Structural Design, Engineering, Supply Material, fabrication and Erection of Structural Steel Works
Arabtec / Al Rostamani jv 300
2002 Grosvenor Hotel & Apartments, Dubai
Engineering, Supply Material, fabrication and Erection of Steel Works
nasa Multiplex l.l.C 300
2002Dubai International finance Centre - Gate Building, Dubai
Design, Supply, fabrication and Erection of Structural Steel Works
nasa Multiplex l.l.C 2,000
2002Service Bridges Over Sg Klang and Sg Kerayong, Malaysia
Erection of Steel Bridge namfatt fabricators Sdn Bhd 215
2002
Tuanku jaafar Power Station Port Dickson Rehabilitation Project Phase 1, Malaysia
Erection of Structural Steel Works Sri Pelagat - Taisei jv 3,800
2002 Sharp Warehouse - jebel Ali, Dubai
Site Assembly and Erection of Steelwork for Car Park and Roof Structure
Shimizu Corporation, japan lumpsum
2002
Proposed Redevelopment of Kampong java Market , Singapore
Shop Drawings, Supply, fabrication and Erection of Structural Steel Works.
Hor Kew Private limited - EAC Enterprise Pte ltd Consortium
1,000
2002upgrading of Market/Hawker Centre at Toa Payoh, Singapore
Design, Supply, Shop Drawing, fabrication, Assembly and Installation of Space frame Structures.
Hor Kew Private limited - EAC Enterprise Pte ltd Consortium
300
2002
Additions & Alterations of Chua Chu Kang Primary School, Singapore
Shop Drawings, Supply, fabrication and Erection of Structural Steel Works
Synergy Construction Pte ltd 105
2002 River valley Primary School, Singapore
Shop Drawings, Supply, fabrication and Erection of Structural Steel Works
CPG - Precise Development Pte ltd Consortium 280
2002 nan Hua Secondary School, Singapore
Shop Drawings, Supply, fabrication and Erection of Structural Steel Works
CPG - Precise Development Pte ltd Consortium 380
2002Catholic Primary & Secondary School, Singapore
Shop Drawings, Supply, fabrication and Erection of Structural Steel Works
nEO Corporation 300
2003Electrified Double Track Project - IPOH Station, Malaysia
Erection of Main Roof & Main Column Torsco Berhad 350
106
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2003Convocation Centre for Kustem university, Malaysia
Structural Design, Engineering, Supply Material, fabrication & Erection of Structural Steel Works
Ibai Bina Sdn Bhd 450
2003 Ski Dubai - Mall of Emirates, Dubai
Erection of Ski Dome Structure Al naboodah laing O’Rourke 3,700
2003 Ski Dubai - Mall of Emirates, Dubai
Structural Design, Supply Material, fabrication and Erection of Temporary Structural Steel Works
Al naboodah laing O’Rourke 700
2003 Marina Crown, Dubai
Structural Design, Supply Material, fabrication & Erection of Structural Steel including Concrete Core Wall Design and Construction
Transemirates Contracting 3,200
2003 Dragon Mart, Dubai
Connection Design, Engineering, Supply Material, fabrication and Erection of Structural Steel Works
Al Shafar Transport & Contracting Co 20 ,000
2003 Khalifa Olympic Stadium, Doha
Structural Design for Temporary Towers, Engineering, Supply Material, fabrication and Erection of Structural Steel Works
Midmac/ Six Construct 3,300
2003Changi Water Reclamation Plant, Singapore
Supply, Shop Drawings, fabrication and Erection of Structure Steel Woks
lum Chang Building Contractors Pte. ltd. 700
2003Changi Airport Main Terminal 3 Building, Singapore
Supply, Shop Drawings, fabrication and Erection of Structure Steel Woks
Shimizu corporation 5,700
2003Circle line Stage 1 C-824 Boulevard Station, Singapore
Supply, Shop Drawings, fabrication and Erection of Structure Steel Woks
lum Chang Building Contractors Pte. ltd. 800
2004Dubai International Airport - Conveyor Bridge, Dubai
Structural Design, Engineering, Supply Material, fabrication, Erection of Structural Steel Works
Al Habtoor / Murray & Roberts 33
2004 DIfC Gate Building 1 to 4, Dubai
Connection Design, Engineering, Supply Material, fabrication, Erection of Structural Steel Works
ACT - Peremba j.v. 2,000
2004 DIfC Gate Building 5 & 6, Dubai
Connection Design, Engineering, Supply Material, fabrication, Erection of Structural Steel Works
nasa Multiplex 180
2004Customs, Immigration & Quarantine Package 2, Malaysia
fabrication and Erection of of Structural Steel Works Hl Engineering 1,450
107
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2004Tanjung Bin Power Plant - Boiler Erection Package, Malaysia
Erection of Mechanical Works for Boiler Plant, consisting of Boiler Pressure & non Pressure Parts, Steel Structure, ducting, Piping, Gas Air Heater, Electrostatic Precipitator, Mill Plant, Coal Bunker, Insulation & Refractory, Painting, Cladding, Control and Instrumentation Works.
IHI/ISHI Power Sdn Bhd 61,250
2004
Tanjung Bin Power Plant - Coal Bunker Assembly Package, Malaysia
Pre-assembly and Erection of Coal Bunkers. IHI/ISHI Power Sdn Bhd 1,370
2004Customs, Immigration & Quarantine Complex Package 3, Malaysia
fabrication and Erection of of Structural Steel Works. Hl Engineering 850
2004 Sky Train - Dubai Airport, Dubai
Structural Design, Engineering, Supply Material, fabrication and Erection of Structural Steel Works
fujitec Co. ltd - Dar-al-Handashah 350
2004 Bright Start Tower, Dubai
fabrication, Site Assembly and Erection of Roof feature and Side frames.
Bright Start Holdings, Dubai Contracting Company l.l.C 500
2005 Dubai Mall, Dubai
Connection Design, Engineering, Supply Material, fabrication, Erection of Structural Steel Works
AlICO ltd 13,000
2005 Burj Dubai - link Beams, Dubai
Engineering, Supply Material, fabrication and Erection of link Beams
Samsung / Besix / Arabtec jv 1,500
2005 Canon factory, Singapore
Supply and lay TPO membrance Integrated Systems.
Shimizu Corporation 34,000 m²
2005Teluk Salut 180 MW Combined Cycle Power Plant, Malaysia
Engineering, fabrication and Erection of Steel Structure, Boiler Casings, Ducts and Stacks
Mitsubishi Corporation - Mitsubishi Heavy Industries Consortium
1,050
2005 Tecom Tower, Dubai
Connection Design, Engineering, Supply Material, fabrication, Erection of Structural Steel Works
Belhasa 55
2005 Chelsea Tower, Dubai
Connection Design, Engineering, Supply Material, fabrication, Erection of Structural Steel Works
Dubai Contracting Company l.l.C 140
2005 Sport City Tower, Qatar Engineering, Supply Material, fabrication and Erection of Secondary Steel Works
Besix Midmac jv 400
2005 Salalah Amphitheater, Oman
Site Assembly and Erection of Cantilever Stadium Roof Structure
Gharbia Enterprises/IHGT 550
108
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2005 Qatar Airways Hangar, Qatar
Site Assembly and Erectionof Structural Steel Works Stamsteel/Strarch 1,650
2005 Qatar Science & Technology Park, Qatar
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Qatar Petroleum /Qatar foundation 13,000
2005 Marina Heights Tower, Dubai Marina, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Roof feature Structural Steel
Dutco Balfour Beatty l.l.C. 80
2005 Rose Rotana Tower, Dubai
Structural Design, Engineering, Supply Material, fabricaition, Site Assembly and Erection of Structural Steel Works and Metal Deck
Arabian Construction Company 6,500
2005 Dubai festival City, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Al futtiam Carillion 6,200
2005 MAG 214, jumerah lake Tower, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Trans Emirates Contracting 200
2006
jimah 2 X 700MW, Coal fired Power Plant - Boiler Erection Package, Malaysia
Erection of Mechanical Works for Boiler Plant, consisting of Boiler Pressure & non Pressure Parts, Steel Structure, ducting, Piping, Gas Air Heater, Electrostatic Precipitator, Mill Plant, Coal Bunker, Insulation & Refractory, Painting, Cladding, Control and Instrumentation Works
ISHI Power Sdn Bhd / IHI Corporation 38,000
2006
jimah 2 X 700MW, Coal fired Power Plant - ESP & fGD Erection Package, Malaysia
Erection of Structural Steel and Mechanical - fuel Gas Desulphurization Equipment, Electrostatic Precipitator, Ducting, Piping & Painting Works
ALSTOM Power Asia Pacific Sdn Bhd / Alstom K.K, japan 6,000
2006 The Index Building, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
nasa Multiplex llC 6,000
2006 Almas Tower, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Taisei Corporation/ACC jv 3,500
109
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2006
new Doha International Airport (Phase 1) - Main Terminal Building, Qatar
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Taisei Corporation/TAv jv 25,000
2006 Tornado Tower, Qatar
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Midmac - Six Construct jv 4,250
2006 Burj Al Salam Car Park, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Dubai Contracting Company llC 1,800
2007Shin Eversendai Engineering Office, Rawang, Malaysia
Design and overall construction of a single storey Warehouse with a 2 storey Office, Canteen, TNB Sub-Station and Suction Tank
Shin Eversendai Engineering (M) Sdn Bhd 456
2007 Motor City, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
nasa Multiplex llC 3,500
2007 Burj Khalifa (Spire), Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Samsung/Besix/Arabtec jv 4,000
2007 Al Shams Sky Tower, Abu Dhabi
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Arabian Construction Company 7,750
2007 Princess Tower, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Arabian Construction Company 2,500
2007 united Tiara Towers, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Arabian Construction llC 9,200
2007Anantara Palm jumeirah & Tiara Residences, Dubai
Structural Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Arabian Construction llC 1,000
110
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2007 Capital Gate Building, Abu Dhabi
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Al Habtoor Engineering 13,320
2007 Dubai Tower, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Al Habtoor/Al jaber jv 12,500
2007 Al Salam TECOM Tower, Dubai
Erection of Structural Steel Works DCC, Ws Atkins 100
2008new Doha International Airport (Phase II), Qatar
Site Asembly and Erection Structual Steel Works Taisei /TAv, Bechtel 21,110
2008 Tamouh Site Office, Abu Dhabi
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
zelan Holdings Sdn Bhd 420
2008 Burj Khalifa - Annex Building, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works and Metal Decking
Samsung/Besix/Arabtec jv 850
2008Dubai Mall Hotel & Health Club Roof, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Emaar Properties PjSC 125
2008
new Doha International Airport, Extension Works (Phase I Expansion), Qatar
Connection Design, Engineering, Supply Material, fabrication, Site Assembly and Erection of Structural Steel Works
Taisei /TAv, Bechtel 19,500
2008 Emirates Park Tower Hotel, Dubai
Reinforced Concrete Structural Works for Twin 80 storey tower, Blind Concrete Works, form Works, Concreting, Block and allCivil Works
nasa Multiplex llC
2008
Khalifa Central Market and Tower Development, Abu Dhabi
Connection Design, Engineering, Supply Material, fabrication, Surface Preparation & Painting, Metal Decking, Erection and Intumescent Fireproofing Works
Arabian Construction Company 3,340
2008Cabot Material Research upgrading Project, Malaysia
Piping and Mechanical Installation Construction Works
CMR Sdn Bhd -
111
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2008new Doha International Airport, CP10 AGl Substation, Qatar
Connection Design, Engineering, Supply Material, fabrication, Surface Preparation & Painting, Transportation and Erection of Structural Steel
Sinohydro-Gamuda-WCT (SGW) jv 200
2008 Al Rafi Car Park, Dubai
Connection Design, Engineering, Supply Material, fabrication, Surface Preparation & Painting, Metal Decking, Erection of Steel Structure
Dubai Contracting Company l.l.C 1,827
2009 Cinema upper Roof - Dubai Mall, Dubai
Connection Design, Engineering, Supply Material, fabrication, Site Assembly, Erection of Steel Works and Fireproofing
Emaar Properties PjSC 800
2009 Saadiyat Island, Abu Dhabi
Connection Design, Engineering, Supply Material, fabrication, Site Assembly amdErection of Steel Works
Al jaber legt Engineering & Contracting (AlEC) llC 1,400
2009
Convention Centre Extension and link Bridge to QSTP - Education City, Qatar
Civil Works - foundation Works, Connection Design, Supply Material, Engineering, fabrication, Site Assembly and Erection of Structural Steel Works
Qatar Petroleum/Qatar foundation 15,000
2009Arzanah Development - Rihan Heights, Abu Dhabi
Structural Design, Engineering, Supply Material, fabrication, Erection and Dismantling of Temporary Steel Platform Support for Transfer Beam Construction
Silver Coast - Sunway jv 1,183
2009
uAE university new Campus PPP Development - Al Ain, Abu Dhabi
Engineering, Supply Material, fabrication and Erection of Secondary Steel Works
OGER Abu Dhabi llC 400
20092x600 MW north Chennai Power Station, India
Engineering, fabrication & Erection of Structural Steel works for Turbine Building, Coal Bunker, Mill Bay Structure, Pipe Rack and Aux Buildings
Bharat Heavy Electricals ltd (BHEl) 16,690
2009Chhatrapati Shivaji International Airport - South West Pier, India
Connection Design, Engineering, Supply Material, fabrication, Erection and fire proofing Works
larsen & Toubro 450
112
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2009 Gate District Towers, Abu Dhabi
Connection Design, Engineering, Supply Material, fabrication, Surface Preparation & Painting, Metal Decking and Erection of Steel Structure including special strand jacking lifting techniques and Fire proofing Works
Arabian Construction Company 6,770
2009 Pentominium Tower, Dubai
Connection Design, Engineering, Supply Material, fabrication, Surface Preparation & Painting, Erection of Steel Structure
Arabian Construction Company 2,616
2009Al nasser Headquarters, Abu Dhabi
Connection Design, Engineering, Supply Material, fabrication, Surface Preparation, Painting, Metal Decking, Erection of Steel Structure and Intumescent Fireproofing Worksescent Fireproofing Works
Al Rostamin Pegel llC 3,450
2009 Dubai Pearl Phase 1 Civil Works, Dubai
All Structural Concrete Work, formwork, Reinforcement Work, Block Work and Skeleton Civil Work
Al-Habtoor - leighton jv RCC Works
2009 The OPuS, Dubai Civil - Insitu Structural frameworks (Concrete)
Brookfield Multiplex Construction
2009
Central Market Redevelopment - Khalifa Podium, Abu Dhabi
Connection Design, Engineering, Supply Material, fabrication, Surface Preparation, Painting, Metal Decking and Erection of Steel Structure
Arabian Construction Company 1,320
20092x500 MW nTPl Tuticorn Thermal Power, India
Erection, Painting, Testing and Commissioning of Boiler Structures, Pressure Parts, no-pressure parts and Rotating Equipments
Bharat Heavy Electricals ltd (BHEl) 18,031
2009 Burj Khalifa - Gate House, Dubai
Connection Design, Engineering, Supply Material, fabrication, Surface Preparation & Painting and Erection of Steel Structure
Samsung/Besix/Arabtec jv 65
2009Mumbai International Airport - South West Pier, India
Engineering, Material Supply, fabrication, Surface Preparation and Painting, Transportation and Erection of Structural Steel
larsen & Toubro 3,410
2010nKOM- nakilat-Keppel Offshore & Marine, Qatar
fabrication and Assembly of Dry Dock structures
Qatar Gas Transport Company 346
113
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2009Stacker Reclaimer B Restoration Work, Malaysia
Dismantling and Refurbishment of Stacker Reclaimer, Mechanical and Electrical Equipment and Instrumentation Work
jimah Energy venture Sdn Bhd 195
2010 Emiri Terminal - Steel Roof Structure, Qatar
Connection Design, Engineering, Supply Material, fabrication, Surface Preparation & Painting Works
Al fasi Construction Singapore (ACS) 180
2010 north Central Plant - Education City, Qatar
Connection Design, Engineering, Supply Material, fabrication, Surface Preparation & Painting, Site Assembly and Erection of Steel Structure
Gulf Contracting Company Wll 620
2010 Algeria Oman fertilizer Plant, Algeria
Engineering, fabrication, Surface Preparation & Paintingand Export of Steel Structures of fOB basis
Shapoorji Pallonji Mideast llC 3,477
2010yas Island Development - Signage Canopies, Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation & Painting and Erection of Steel Structure
Thomas Bennett Signs llC 98
2010 Etihad Tower - Roof, Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation & Painting and Erection of Steel Structure
Arabian Construction Company 115
2010 Capital Gate Building - Helipad, Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation & Painting, Metal Decking and Erection of Steel Structure
Al Habtoor Engineering Company llC 140
2010Sowwah Square - Tower Canopies, Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation & Painting and Erection of Steel Structure
OGER Abu Dhabi llC 120
2010
Sowwah Square - north and South Carpark lobbies (Glass Boxes), Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation & Painting and Erection of Steel Structure
OGER Abu Dhabi llC 625
2010 Emirates Park Tower Hotel - Podium, Dubai
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation & Painting, Erection of Steel Structure and Cemetitious Fireproofing Works
Brookfield Multiplex Construction 725
114
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2010new Doha International Airport - Central utility Plants, Qatar
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation & Painting, Metal Decking and Erection of Steel Structure
CAT International Qatar Wll 1,526
2010PKT logistics Warehouse & Office, Malaysia
Design and overall construction of a single storey Warehouse with a 2 storey Office, TNB Sub-Station, Guard House for PKT logistics (35,000 m2)
Shin Eversendai Engineering (M) Sdn Bhd 1,200
2010 Cleveland Clinic, Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation, Painting, Metal Decking, Erection of Steel Structure and Cememtitious Fireproofing
Samsung/Sixco jv 30,150
2010Capital Market Authority Tower, Saudi Arabia
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation, Painting, Metal Decking, Erection and Fireproofing Works
Saudi Bin laden Group 25,500
2010
new Doha International Airport - north node, Concourse C & D - Phase 3 CP 51, Qatar
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting, Metal Decking, Erection of Steel
Midmac - Sixco jv 35,000
2010
King Abdullah Petroleum Studies and Research Centre, Saudi Arabia
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting, Metal Decking, Erection of Steel Strucutre
Saudi Arabian Oil Company 14,000
2010Doha Convention Center and Tower, Qatar
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting, Metal Decking, Erection of Steel Strucutre
Six Construct/Midmac jv 12,094
2010 Trump Tower, India Construction of Substructure and Superstructure Core and Shell Works
Rohan lifescapes 4,275
2010 Marathon futurex, India
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation, Painting, Transportation and Erection of floor Beams and Plate Sections for Composite Slab
Marathon Realty Pvt ltd 1,440
115
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2010 BWE 2x487 TPH Boiler Structure, India
Engineering, Material Supply, fabrication, Surface Preparation and Painting of Boiler Steel Structure and Accessories, Gratings and Handrail Works and Delivery on Ex-works basis
BWE Energy India Pvt ltd 3,370
20102x500 MW nTPl Tuticorn Thermal Power, India
Erection, Testing and Commissioning of Electrostatic Precipitator and Auxiliaries
Bharat Heavy Electricals ltd (BHEl) 17,971
20102x300 MW EMCO Thermal Power Plant, India
Erection, Testing and Commissioning of Boiler, Turbine, Generator and Auxiliries including Electrical, Commercial and Industrial Works
GMR Energy limited 41,988
20102x660 MW Bhavanapadu Thermal Power , India
Erection, Testing and Commissioning of Boiler, Turbine, Generator and Auxiliries including Commercial and Industrial Works
Abir Infrastructure Pvt ltd 68,761
2010
Office Towers for Bank Kerjasama Rakyat Malaysia Berhad, Malaysia
Spply fabrication, Painting, Fireproofing and Erection of Structural Steel
Kasugi Prima Bhd 505
2010
Academy Training Complex & Tactical Training Building, Police Training Center (Pulaupol) Kl, Malaysia
Steel structure, roof covering and box gutter work
Bina Puri Construction Sdn Bhd 300
2010new Doha International Airport Retrofitting Work, Doha, Qatar
Installation of strengthen plates SKy ORyX jOInT vEnTuRE Manpower
supply
2010 Khatau Mills, India
G+ 2 floors Carrying out Structural Steel wok for Marketing Office at Khatau Mill, Byculla
Swayam Realtors & Traders ltd 199
2010 Tamkeen Tower, Riyadh, Saudi Arabia
Supervision of Structural Steel works installation(only)
Al Rajhi Projects & Construction llC
2010upgrading Al Salam Street & Abu Dhabi City Ring Road, Abu Dhabi
Installation of formwork, Reinforcement, Scaffolding and Pouring of Concrete works
Samsung
2011 Dubai Pearl, Dubai
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting, Erection of Steel Strucutre
Al habtoor leighton Group 361
116
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2011MASDAR Institute for Science & Technology, Abu Dhabi
Basic Designing including Connections, Engineering, Material Supply, fabrication, Surface Preparation & Painting, Galvanization, Metal Decking, Erection and Intumescent Fireproofing Works
Arabian Construction Company 1,580
2011 Etihad Towers - South façade, Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting and Erection of Steel Structure
Arabian Construction Company 87
2011Etihad Towers - Seafood floating Restaurant, Abu Dhabi
Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting and Erection of Steel Strucutre
Arabian Construction Company 255
2011 Etihad Tower - Roof features, Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting and Erection of Steel Strucutre
Arabian Construction Company 145
2011 SAMBA Headquarters, Saudi Arabia
Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting, Metal Decking, Erection and Fireproofing Works
El Seif Engineering Contracting Company ltd 834
2011 new KlIA 2 Airport Terminal, Malaysia
Design, Supply and Installation of Structural Steel Works for Satellite Building, Sky Bridge and Contact Piers
Bina Puri Sdn Bhd 5,000
2011 Sabah Oil & Gas Terminal, Malaysia
Supply, fabrication, Surface Preparation, Painting and Delivery of Steel Structure
Samsung Engineering Malaysia Sdn Bhd 5,000
2011Maldives Airport Terminal Improvement, Maldives
Supply and Delivery of Pre-fabricated Structural Steel Works
GADl (Isle of Man) ltd (GMR Group) 25
2011
Manjung 4 - 1 x 1,000 MW Coal fired Power Plant - Boiler Package, Malaysia
fabrication & Erection of Structural Steel Works of Turbine Building and Installation of Pressure and non Pressure Parts, Coal Bunker, Mill Bay Structure, Piping and Auxiliaries
Alstom Services Sdn Bhd 32,600
2011
Manjung 4 - 1 x 1,000 MW Coal fired Power Plant - Ducting, Malaysia
Supply of Ducts Alstom Services Sdn Bhd 1,370
2011
Manjung 4 - 1 x 1,000 MW Coal fired Power Plant - Steam Turbine Hall, Malaysia
Construction and completion of Structural Steel for Steam Turbine Hall including Shop Drawings, Procurement, fabrication, Delivery and Erection
Mudajaya Corporation Bhd 3,150
117
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2011
“Erhama Bin jaber Al jalahma Shipyard - Production Support facility Building.Phase-5 .Port of Ras laffan,Qatar
Design, Connection Design, Supply, fabrication, Painting, Delivery, Erection of Structural Steel Works, fire Proff, Roof/ Wall Cladding Works
Gulf Contracting Company Wll 230
2011 MIAl HangarEngineering, fabrication, Site Assembly and Erection of Structural Steel Work
larsen & Toubro 860
2011 four Seasons
G+3 floors, Structural Steel Works, Concreting Works, Civil finishes Works and Miscellaneous Works
Magus Estates & Hotels Private limited 320
2011
MIAl Subcontract #T2/2-G, fixed link Bridge Structural Steel Works
Engineering, fabrication, Site Assembly and Erection of Structural Steel Works for 12 nos flB’s
larsen & Toubro 2,272
2011The Regent Emirates Pearl Hotel, Plot 5, Abu Dhabi
Design, Engineering, Material Supply, fabrication, Surface Preparation & Painting, Erection of Misc Steel Structures
Arabian Construction Company 212
2011 Dubai Mixed use Tower, Dubai
Connection Design, Engineering, Material Supply, fabrication, Metal Decking, Surface Preparation & Painting, Fireproofing and Erection of Misc Steel Structure for Podium, Carpark, Pool and link bridges from Carpark to Towers
Arabian Construction Company 495
2011 City of lights, Reem Island, Abu Dhabi
Detailed design, Material Supply, fabrication and installation of Embeds, Base Plate, Anchor Bolt and Shear Studs
Brookfield Multiplex Construction 5
2011 Stand Point Tower, Dubai
Installation of formwork, Reinforcement, Scaffolding and Pouring of Concrete of works
Besix - Arabtec jv
2012
Tanjung Bin 4- 1 x 1,000 MW Coal fired Power Plant - Engineering, Constrution & Procurement (EPC), Malaysia
fabrication & Erection of Steel Structure and Installation of Boiler Pressure and non-Pressure Parts including Auxiliary Equipment and Piping and related services as Part of an EPC Consortium Partner
Tanjung Bin Energy Issuer Bhd 54,491
118
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2011
“EPIC for Building Superstructures (Phase 4A) Erhama Bin jaber Al jalahma Shipyard - Energy Center, Work Shop/Painting Shop facility and Super yacth Hall.Port of Ras laffan, Qatar
Design, Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting, Erection of Steel Strucutre including Fire Proofing. Design and Construction of Mega Sliding Door of size 33.92m width and 45m height. Supply and Installation of double skin & Single Skin Roofing System 76,325Sq.mtrs
Qatar Petroleum 8,000
2012 Qatar faculty of Islamic Studies, Malaysia
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation & Painting, Erection of Steel Strucutre
CCC and Teyseer Contracting Co Wll j.v 3,627
2012 Worli Mixed use Development, India
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting, Erection of Steel Strucutre
Samsung C&T Pte limited 3,150
2012Salalah Airport Expansion Project, Oman
Erection of Structural Steel, Alignment, Bolting and Welding Works
larsen & Toubro limited 4,257
2012 yas Mall, Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting, Erection of Steel Strucutre
Six Construct Co. ltd 6,005
2012 ADnOC Headquarters, Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Metal Decking, Surface Preparation & Painting, Fireproofing and Erection of Steel Structure
Six Construct Co. ltd 4,507
2012MASDAR Headquarters, Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Metal Decking, Surface Preparation & Painting, Fireproofing and Erection of Steel Structure
Brookfield Multiplex Construction 3,588
2012 ADnOC Headquarters Roof, Abu Dhabi
fabrication Drawings, fabrication & Delivery to Site, Painting, Erection of Structural Steel
Six Construct Co. ltd 1,600
2012 Qatar foundation Headquarters, Qatar
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting, Erection of Steel Strucutre
Midmac Contracting Company W.l.l. 2,414
119
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2012national Museum of Qatar (Package 1),Qatar
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting, Erection of Steel Structure
Hyundai Engineering & Construction Co., ltd 26,500
2012 national Museum of Qatar, Qatar
Connection Design, Engineering, Material Supply, fabrication, Surface Preparation &Painting, Erection of Steel Structure
Hyundai Engineering & Construction Co., ltd
2012
King Abdulaziz International Airport Railway Station, Saudi Arabia
Connection Design, Engineering, Material Supply, fabrication, Metal Decking, Surface Preparation & Painting, Fireproofing and Erection of Steel Structure
Saudi Bin laden Group 12,085
2012
Tokuyama Malaysia Polycrystalline Silicon Project (TMP2), Malaysia
fabrication Drawings, fabrication & Delivery to Site, Painting, Erection of Structural Steel
Taisei Corporation 4362
2012Iron Ore Distribution Project, Manjung, Malaysa
fabrication & Supply vale Malaysia Minerals Sdn Bhd 5300
2012 MfAR Developers Pvt ltd, India
Structural Steel work - Shop drawing, Material Supply, fabrication.a) Supply of Shear Plates for Piles - 25 mmb) Supply of Shear Studs - 20
mm dia X 125 mm length
MfAR Holdings Private limited 52
2012Al jalila Children’s Specialty Hospital, Dubai
Connection Design, Engineering, Material Supply, fabrication, Metal Decking, Galvanizing and Erection of Steel Structure
Al futtaim Carillion 4,639
2012 Abu Dhabi International Airport, Abu Dhabi
Connection Design, Engineering, Material Supply, fabrication, Metal Decking, Surface Preparation & Painting, Fireproofing and Erection of Steel Structure
TCA joint venture 24,832
2012 Crescent City Project, Baku, Azerbaijan
Connection Design, Engineering, Material Supply, fabrication, Metal Decking, Surface Preparation & Painting, Fireproofing and Erection of Steel Structure
Gilan Holding llC 6,252
2012 Al Safooh Transit System (TRAM), Dubai
Installation of formwork, Reinforcement, Scaffolding and Pouring of Concrete works for the stations
Besix
120
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2012 Masdar Head Quarters, Abu Dhabi
fabrication Drawings, fabrication & Delivery to Site, Painting, Erection of Structural Steel
Multiplex 2,623
2013 Petronas lnG Train 9, Malaysia
Shop fabrication of Steel Structure jGC (Malaysia) Sdn Bhd 2,245
2013 Doha land, Phase 1C, Qatar
Connection Design, Supply, fabrication, Painting, Delivery, Erection of Structural Steel Works, Metal Deck and fire Proof
Brookfield Multiplex Construction 650
2013
Doha Convention Center and Tower- Temporary Platform for Piling Works, Qatar
Supply, fabrication, Painting, Delivery, Erection of Structural Steel Works & Dismantling
Six Construct/Midmac jv 772
2013 lusail Multipurpose Hall Package 02, Qatar
Connection Design, Supply, fabrication, Painting, Delivery, Erection of Structural Steel Works, Metal Deck and fire Proof
Consolidated Contractors Group S.A.l(offshore)(CCC)/Teyseer Contracting company W.l.l
820
2013
Qatar foundation Research & Development Complex, Qatar
Design, Connection Design, Supply, fabrication, Painting, Delivery, Erection Of Structural Steel Works, Metal Deck And fire Proof
Redco - Construction - Almana 4,050
2013 Duhail Multipurpose Sports Club, Qatar
Design, Connection Design, Supply, fabrication, Painting, Delivery, Erection of Structural Steel Works, Metal Deck And fire Proof
Redco - Construction - Almana 2,200
2013 Mall of Qatar, Qatar
Connection Design, Supply, fabrication, Painting, Delivery, Erection of Structural Steel Works
Al Khayat Trading & Contracting 205
2013 World Crest/ Shree niwas Mill, India
Engineering, Procurement, Shop fabrication, Transport, Delivery and Erection of Mild Steel Structure Beam
lodha Group, Mumbai 121
2013 World One-King Tower, India
Structural Steel Works - Connection Design, Shop Drawings, Material Supply, Shop fabrication, Mill Scaling Removal, Delivery And Erection
lodha Group, Mumbai 914
2013 TCS Siruseri-Signature Tower, India
fabrication, Supply, Short Blasting (SA 2.5), Paiting, Transportation And Erection And Handing Over Of Structural Steel Works
larsen & Toubro 560
121
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2013
Pasari-Bio Wonder Project, Kolkata-Supply & Erection, India
Design, Procurement, fabrication, Delivery And Erection Of Mild Steel Strutural Beams And Columns for Cantilever Structure
Pasari Multiprojects Pvt.ltd 480
2013
Margus Estates & Hotels - Roof top restaurant, four Seasons Hotel, Mumbai
Supply, fabrication And Erection Of Structural Steel Works AER (Roof Top Restaurant)
Magus Estates & Hotels Private limited 5
2013
GvK-MIAl - Closure of Gable End Opening & providing rolling shutter for HMD Hangar, India
Closure Of Gable End Opening And Providing Rolling Shutter for IMD Hangar
Mumbai International Airport Pvt.ltd (GvK) 11
2013
Garraf, Iraq Development facility Operation - fGCu and associated equipment for 15MW Power Plant, Iraq
Supply and Delivery of fuel Gas Conditioning unit (fGCu) and Associated Equipments
Petronas Carigali Iraq Holding, Bv
2013
Garraf, Iraq Development facility Operation - upgrade for 15MW Power Plant, Iraq
EPC of fuel Gas Conditioning unit (fGCu), Compressor Skid and fully Equipped Mini Substation
Petronas Carigali Iraq Holding, Bv 270
2013 The Binary, Abu Dhabijust in-situ, Blast Cleaning of Installed Rebars, Miscellaneous
Binary Development
2013 Tj Pearl Mansion, Qatar
Connection Design, Shop Drawing, Supply of Materials, fabrication, Blasting/Priming, Hot Dip Galvanising, Site Assembly, Erection and Decking
Midmac Contracting Company W.l.l. 3,800
2013Hub zero family Entertainment Centre, Dubai
Connection Design, fabrication Drawing, Raw Materials Supply, fabrication, Blasting, Primer And Application of Cementious/Intumescent Fireproofing, Installation of Structural Steel Works, Supply and Installation of Composite Metal Decking
Samsun C&T 2,057
2013 Atmosphere Sky Bridge, India
Connection Design, Shop Drawing, fabrication, Blasting, Painting, Erection and Decking
larsen & Toubro limited 1300
122
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2014 new jet Propulsion Centre, Saudi Arabia
Design Verification, Connection Design, Shop Drawing, Supply Of Material, fabrication, Blasting And Primer, Delivery To Site And Erection Of Structural Steel Works
freyysinet Saudi Arabia 5,715
2014Kshitij, Paramanandwadi, India
Construction Of Composite Structure
Roxinal Real Estate Pvt. ltd, Mumbai 3,365
2014MIAl Phase 3 Structural Steel Works, India
Composite Columns, Material Supply, fabrication, Transportation, Erection Of Structural Steel Works
larsen & Toubro limited, Mumbai 1,135
2014 j3 Project, jamnagar,India
Supply Of fabricated And Painted Structural Steel
Reliance Industries limited, Mumbai 12,225
2014 Kingfisher Towers, Bangalore, India
Supply, fabrication, Transportation And Erection Of Structural Steel Works
larsen & Toubro limited, Chennai 1,500
2014MIAl Phase 4 Structural Steel Works, India
Material Supply, fabrication, Transportation, Erection Of Structural And Miscellaneous Steel Works
larsen & Toubro limited, Chennai 1,475
2014 Terengganu Gas Terminal, Malaysia
Supply And Installation Of Steel Structures, fabrication And Erection Of Piping And Mechanical Equipment
Petronas Carigali Sdn. Bhd.
2014 Opera House, Dubai Engineering, Detailing, fabrication And Installation Of Structural Steel Works
Consolidated Contractors Company (CCC)
3,281
2014 Hard Rock Hotel,Abu Dhabi
Connection Design, fabrication, Metal Decking, Supply, Erection Of Structural Steel Works, Painting And Fire Proofing Works
Al futtaim Carillion llC 1,600
2014King Abdullah financial District Monorail Depot Building
Saudi Oger 385
2014 Address Residences fountain views
Connection Design, Supply, fabrication, Erection Of Structural Steel Works
Arabian Construction Company 926
2014Sheikh Khalifa Bin zayed Al nahyan Masjed, Al Ain, u.A.E
Design Verification, Connection Design, fabrication, Supply, Erection And Fireproofing Works
Arabian Construction Company 2,097
2014 Dubai frame - zabeel Park, Dubai, u.A.E.
Connection Design, fabrication, Supply, Fireproofing, Erection & Strand jacking Of Structural Steel Works
Al Rostomani Pegel llC 663
2014QnM - Secondary steel(Remeasurable)
Supply, fabrication, Delivery, Installation Of Secondary Steelworks
Hyundai Engineering & Construction 412
2014Mall of Qatar - Spine Mall / luxury Plaza /Oasis
Design, Preparation Of Shop Drawings, Supply, fabrication, Delivery, Installation Of Structural Steel Along With Application Of Cementitous Fireproofing
Professional Aluminium Company 772
122
123
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2014
Gabbro Terminal Expanasion (Steel + Mechnical Equipments)- (Remeasurable)
Supply And Installation Of Structural Steel And Installation Of Mechanical Systems And Miscellaneous Steel for Conveyors, Transfer Towers, Stackers And Hopper Building
Six Construct Qatar limited (Wll)
10,552
13,119
2014 KOS Arch Dismantle and Erection
Engineering, Supply, fabrication, Delivery, Installation Of Structural Steelworks
Midmac - Six Construct j.v (MSjv)
6,436
2014 Development of ISf Camp.KCT / PAC
Engineering, Design, fabrication, Supply And Erection Of Structural Steelworks
urbacon Trading and Contracting 516
2014 People Mover system
Design, Preparation Of Shop Drawings, Supply, fabrication, Delivery, Erection & Hand Over Of Structural Steel Including Metal Decking, Grating And Roof Cladding
Habtoor leighton Groupleighton Contracting (Qatar) W.l.l
903
2014 Al-Wahda Arch & visitor Centre
Connection Design, Preparation Of Shop Drawings, Supply, fabrication, Delivery, Erection, Hand Over Of Structural Steel Including Fireproofing (Only To Visitor Centre Beams) And Cable Works
Hyundai Engineering & Construction
11,236
2015Al jalilah link Bridge, Dubai, u.A.E
Connection Design, fabrication, SupplyAnd Erection Of Structural Steel Works
Arabian Construction Company
385
2015yas Mall South West Car Park, Abu Dhabi, u.A.E
Connection Design, fabrication, SupplyAnd Erection Of Structural Steel Works
Six Construct Co. ltd. 800
2015Warner Bros. Theme Park, Abu Dhabi, u.A.E.
Connection Design, fabrication, Fireproofing, Supply And Erection Of Structural Steel Works
Six Construct Co. ltd. 9,400
2015ynP yanbu Refinery Project, KSA
Connection Design, fabrication AndSupply Of Structural Steel Works CPCAjv 2,430
2015 nas Arena Multi Purpose Hall
Connection Design, fabrication, Metal Decking, Supply, Erection Of Structural Steel Works, Painting And Fire Proofing Work
Al naboodah Contracting Co. llC 3,991
2015
Dhirubai Ambani International Convention& Exhibition Centre
fabrication And Delivery To Daicec Site, Mumbai.Raw Material Supply, fabrication, Delivery To Mumbai Port On Cfr Basis
Reliance Industries limited 33,570
2015 Address Residence- Sky views
Connection Design, fabrication, Metal Decking, Supply, Erection Of Structural Steel Works, Painting And Fire Proofing Works
Arabian Construction Company
7,010
2015 Conversion Hangar, Saudi Arabia
Connection Design, fabrication, Supply, Metal Decking, Cladding, Erection & Fireproofing Of Structural Steel Works
joannou & Paraskevaidas 1,754
2015 Conversion Hangar, Saudi Arabia
Connection Design, fabrication, Supply, Metal Decking, Cladding, Erection & Fireproofing Of Structural Steel Works
joannou & Paraskevaidas 1,754
124
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2015PKT logistics 12 Waves Warehouse, Malaysia
Construct And Complete:- One Single Storey Warehouse Block Including Workers Office - One Double Storey Office Block - Two Guardhouses- One Tnb Sub-Station- One Pump Room- “Bomba’ Tank- Covered Parking
Eversendai Corporation Berhad 2,100
2015 Statue of unity, India
Supply, factory fabrication, Painting, Erection, Alignment & Handling Over Of Structural Steel Works At Statue Of unity Project, Gujarat
larsen & Toubro limited
2015 Plant 7 Steel Structure Package
Turnkey Supply, fabrication, Painting, Delivery And Erection Of Plant 7 Steel Structure With 12 lines
latexx Manufacturing Sdn. Bhd.
1,200
2015 Steel Girder Works
Provide All Skilled labour, Materials, Tools, Equipment And The necessary Machineries for The Execution And Completion Of The Girder Works
Ireka Engineering and Construction Sdn Bhd
183
2015 Petronas RAPID fabrication And Supply Of Structural Steel Tecnidas Reunidas Malaysia Sdn. Bhd. 4,482
2015 RAPID Package 5 Supply fabrication and delivery for AXDB004, BXDB004, MXDB004
Toyo Engineering & Construction Sdn. Bhd.
2,016
2015 Sales Gallery @ MIG
Civil & Structural Work (Core And Shell)for The Sales Gallery
vishwaroop Estates & Developers Private limited
90
2015 Top Glove factory
Engineering Procurement Construction (Excluding M&E works) for One factory unit, Two Mezzanine floor for The Manufacture Of Quality Hand Gloves (f30) Which Includes:• Guard House• Waste Chamber
Top Quality Glove Sdn. Bhd. 650
2015 Malai Mandir Design, Connection Design, Shop Drawings, Procurement Of Structural Steel And fabrication
Delhi land & finance 11
2015 Oasis Mixed used Development
Design, fabrication, Supply, Installation, Testing, Commissioning, And Maintenance Of The Structural Steel Theme Park Roof
M/s. REDCO Construction- AlMAnA W.l.l
2015Al Wakrah Expressway - Bypas Road
Supply Of Temporary Bridge Bearings Steel Which Includes Shop Drawing, fabrication, Machining And Transportation
larsen & Toubro ltd 58
2015Doha Mixed use Development - Dome
Roof Steel Structure Design, Engineering, Preparation Of Shop Drawings, fabrication, Delivery To Site, Erection, Completion, finishing, Providing As-Buill Drawings, Testing And Commissioning, Handing Over And Remedying Of Defects
REDCO Construction Almana
7,912
yEAR (awarded) PROJECT NAME sCOPE OF WORK MAIN CONTRACTOR qUANTITy
(tonnage)
2015Doha Mixed use Development - Columns
Design Verification, Engineering, Preparation Of Shop Drawings, fabrication, Delivery To Site, Erection, Completion, finishing, Providing As-Buill Drawings, Testing And Commissioning, Handing Over Of Structural Steel Works
REDCO Construction Almana
1,975
2015 Abraj Quartier 1 & 2 fabrication, Supply And Installation Of Structural Steel Works
Redco Construction Almana 326
2016Al Maryah Central Mixed use Development
Connection Design, Supply, fabrication, Erection Of Steel Works Including fire Proofing & Metal Decking Works
Brookfield Multiplex 5560
2016
Riyadh Metro Elevated Stations - Package 3, line 4 & 6
Connection Design, Supply, fabrication, Erection Of Steel And Fire Proofing Works fAST Consortium 8395
2016
Integrated Gas Development Expansion - Package 1
Modules factication Works - fabrication And Assembly Of Pre-Assembled units (PAu) - 02 nos. And Pre-Assembled Racks (PAR) -14 nos Which Include Supply fabrication And Erections Of Steel Structures, ladders, Platforms And Handrails, Piping And Piping Supports, Electrical Works & Instrumentation Works, Equipment Installation, Painting, Insulation, Fireproofing, Inspection, NDT, QC Reviews, Tests Such As Hydro And Pneumatic Tests, Weighing Of Modules, Pre-Commissioning Tasks And Preparation for Transport By load-Out from jetty
Tecnimont Spa
2016Integrated Gas Development Expansion - Train4
Supply, fabrication And Assembly Of One Teg Module Which Include Supply Of Bulk Materials I.E. Steel Structures, Piping And fabrication And Erections Of Primary And Secondary Steel Structures, ladders, Platforms And Handrails, Piping And Pipe Supports, Electrical Works, Instrumentation Works, Mechanical Equipment Installation, Painting, Insulation Inspection, nDT, QC Reviews, Tests Such As Hydro And Pneumatic Tests, Weighing Of Modules, Pre-Commissioning Tasks And Preparation for Transport By load-Out from jetty
Prosernat
2016Doha Mixed-use Development Theme Park
Design Verification, Fabrication, Supply, Delivery, Erection of CHS at Perimeter Mall, Steel Columns for Hotel Tower, Steel Ramp, Catwalk On Theme Park Roof And Installation Of Anchor Bolts for Tree Columns
M/s. Redco Construction - Almana
1950
125
21st Century Tower, Dubai
Cargo Terminal, Malaysia
Hentian Putra, Malaysia
Pahang Matriculation College, Malaysia
Senoko Power Plant, Singapore
jKR Building, Malaysia
Thermal Energy Tank, Saudi Arabia Anantara Palm, Dubai
SAMBA financial Group Headquarters, Saudi Arabia
Stacker Reclaimer, Malaysia
Philip Morris, Philippines
Ritz Carlton, Qatar Marina Heights, Dubai
Al faisaliah, Saudi Arabia
Grosvenor House, Dubai
Sowwah Square – Tower Canopies, Dubai
EVERsENDAI
MAlAySIAEVERsENDAI CORPORATION BERHAD(Registered Address)lot 19956, jalan Industri 3/6,Rawang Integrated Industrial Park,48000 Rawang,Selangor Darul Ehsan, Malaysia.Tel : +603 6091 2575fax : +603 6091 2577Email : [email protected]
(Principal Place of Business)level 5, Menara Mudajaya,12A, jalan Pju 7/3, Mutiara Damansara,47810 Petaling jaya,Selangor Darul Ehsan, Malaysia.Tel : +603 7733 3300fax : +603 7733 3351/52
EVERsENDAI OFFsHORE sDN BHD
EVERsENDAI ENERGIA sDN BHD(formerly known as ShineversendaiEngineering (M) Sdn Bhd)
EVERsENDAI CONsTRUCTIONs(M) sDN BHD
ECB PROPERTIEs sDN BHDlot 19956, jalan Industri 3/6,Rawang Integrated Industrial Park,48000 Rawang,Selangor Darul Ehsan, Malaysia.Tel : +603 6091 2575fax : +603 6091 2577Email : [email protected]
EVERsENDAI OIl & GAs (M) sDN BHDlevel 5, Menara Mudajaya,12A, jalan Pju 7/3, Mutiara Damansara,47810 Petaling jaya,Selangor Darul Ehsan, Malaysia.Tel : +603 7733 3300fax : +603 7733 3351/52Email : [email protected] [email protected]
DuBAIEVERsENDAI ENGINEERING llCEVs CONsTRUCTION llC29th floor, vision Tower,Al Khaleej Al Tejari Street 1, Business Bay,PO Box 29537, Dubai, united Arab Emirates.Tel : +971 4 453 9881fax : +971 4 453 9940Email : [email protected]
SHARjAHEVERsENDAI ENGINEERING FZEPlot no. 2E-04,05,09 & 10,P.O.Box 42531,Hamriyah free zone Establishment,Sharjah, united Arab Emirates.Tel : +971 4 267 3738fax : +971 4 267 3663Email : [email protected]
QATAREVERsENDAI ENGINEERING qATAR WllP.O. Box 35283,Street no.41, new Industrial Area,Doha, Qatar.Tel : +974 4 411 4378fax : +974 4 411 4381Email : [email protected]
AzERBAIjAnEversendai Engineering llCEmail : [email protected]
RAS Al KHAIMAHEVERsENDAI OFFsHORE RMC FZERAK Maritime City,P.O. Box 5130,Ras Al Khaimah, united Arab Emirates.Tel : +971 4 456 4815fax : +971 4 456 4833Email : [email protected]
45th floor, vision Tower,Al Khaleej Al Tejari Street 1, Business Bay, P.O Box 116654, Dubai, united Arab Emirates.Tel : +971 4 456 4815fax : +971 4 456 4833Email : [email protected]
ABu DHABIEVERsENDAI ENGINEERING llCP.O. Box 107729,Abu Dhabi, united Arab Emirates.Tel : +971 2 495 0700fax : +971 2 445 4672Email : [email protected]
KInGDOM OfSAuDI ARABIAEVERsENDAI ENGINEERING sAUDI llC P.O. Box 241763, Al-Masif Area, Al Iman Saudi Bin Aziz Bin Mohammed Road, Riyadh 11692, Kingdom of Saudi Arabia.Tel : +966 1 494 4891fax : +966 1 494 4892Email : [email protected]
InDIAEVERsENDAI CONsTRUCTION PVT lTDPlot no.1-2, The lords Block-1,5th floor, Thiru-vi-ka Industrial Estate,jawaharlal nehru Road, Ekkattuthangal,Guindy, Chennai-600 032,Tamil nadu, India.Tel : +91 44 4070 1234fax : +91 44 4070 1230 Email : [email protected]
SInGAPOREEVERsENDAI CONsTRUCTION(s) PTE lTDEVERsENDAI ENGINEERING PTE lTDEVERsENDAI TECHNICs PTE lTD 6001, Beach Road, #18-01, Golden Mile Tower, Singapore 199589.Tel : +65 6227 0335fax : +65 6227 0021Email : [email protected]
THAIlAnDEVERsENDAI s-CON ENGINEERINGCO. lTD. 140 Moo 2 T. Khuyaimee, A. Sanamchaikhed, Chacherngsao 24160 Thailand.Tel : +66 3 850 2707 Email : [email protected]
SRI lAnKAEversendai Engineering (Pvt) ltd. Email : [email protected]
www.eversendai.com