1Western Electricity Coordinating Council

WECCMIC Meeting

Report on Operating Transfer Capability

Policy Committee (OTCPC)

Marina Del Ray

October 30 & 31, 2008

Page 2: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

2Western Electricity Coordinating Council

Major Topics

I. 2008-09 Winter Study Results California / Mexico Subregion

Northwest Subregion

Rocky Mountain Subregion

Southwest Subregion Time Line Implementation

II. Future Role of OTCPC

III. MIC Issues / Comments

Page 3: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

3Western Electricity Coordinating Council

California / Mexico Subregion – Winter 2008-09

The increase in SCIT is mainly due to the new Miguel – Sycamore #2 230 kV line, which came in service late 2006, the new Miguel – Old Town 230 kV line, and 2x63 MVAr shunt capacitors at Miguel 230 kV.

Path Name Path Number

Rating(MW)

Proposed2008-2009 Winter SOL (OTC) (MW)

2008 Summer SOL (OTC)(MW)

2007-2008 Winter SOL (OTC)(MW)

California

COI (N-S) 66 4800 (N-S) 4800 (N-S) 4800 (N-S) 4800 (N-S)

PDCI (N-S) 65 3100 (N-S) 3100 (N-S) 3100 (N-S) 3100 (N-S)

Midway - Los Banos (S-N)

15 5400 (S-N) 5400 (S-N) 5400 (S-N) 5400 (S-N)

SCIT NA 19365 15,150* 16,200* 15,150*

Midway - Vincent (N-S)

26 4000 (N-S) 4000 (N-S) 4000 (N-S) 4000 (N-S)

Page 4: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

4Western Electricity Coordinating Council

Northwest Subregion - Winter 2008-09

Page 5: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

5Western Electricity Coordinating Council

Rocky Mountain Subregion – Winter 2008-09

* WITH NUCLA AT 80 MW AND SW COLO LOAD 100 MW** Miracle Mile-Laramie and Beaver Creek-Hoyt Construction Outages

*** Snowy Range-Cheyenne Construction Outages

Path WECC Path

Number

Rating(MW)

2008-09 Winter OTC (MW)

2008 Summer

OTC (MW)

2008 Spring

OTC (MW)

2007-08 Winter

OTC (MW)

TOT1A 30 650 615 614 650 650

TOT2A 31 690 660* 660* 660* 660*

TOT3 36 1605 1538 1542 1506*** 1506***

TOT5 39 1680 1680 1680 1680 1680

Page 6: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

6Western Electricity Coordinating Council

Southwest Subregion – Winter 2008-09

PATH NAME WECC PATH NUMBER

RATING OF PATH (MW)

2008-09 WINTER SOL

(MW)

2007-08 WINTER SOL (MW)

2008 SUMMER SOL (MW)

Four Corners West 22 2325MW Nominal(Nomogram)

2325MW Nominal(Nomogram)

2325MW Nominal(Nomogram)

2325MW Nominal(Nomogram)

Cholla-Pinnacle Peak 50 1200MW 1200MW 1200MW 1200MW

Page 7: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

7Western Electricity Coordinating Council

Implementation Time Schedule

• These limits apply to the 2008-09 winter operating season starting Nov. 1, 2008, and ending no later than March 31, 2009 pending completion of: – The Operating Procedures Review Group’s acceptance

of the associated summer operating procedures for each of the interties and those operating procedures (including system monitoring and curtailment responsibilities) being implemented, and

– Operating training and direction required to ensure operation within the established operating limits.

Page 8: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

8Western Electricity Coordinating Council

Future of OTCPC• OTCPC is working on a draft resolution to terminate, reformat

or suspend the OTCPC because the implementation of FERC Mandatory Reliability Standards renders the current OTCPC structure no longer necessary or appropriate

• OTCPC was formed as,– “the result of “lessons learned” from the July/August 1996 Western

Interconnection disturbances.” “The purpose of the OTCPC is to provide coordinated standard development and determination of seasonal OTC’s within the Western Interconnection. The goal is to promote communication and common study methodologies among the region transmission providers and customers and provide the highest level of transmission capacity consistent with the reliable operation of the overall WECC transmission grid.” OTCPC handbook, April 2007

Page 9: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

9Western Electricity Coordinating Council

Future of OTCPC – NERC Reliability Standards

• NERC has defined a System Operating Limit (SOL) which is inclusive of the WECC defined Operating Transfer Capability (OTC). Hence, SOL will be utilized instead of OTC in the following text.

• NERC Definition:– System Operating Limit (SOL): The value (such as MW, MVar, Amperes,

Frequency or Volts) that satisfies the most limiting of the prescribed operating criteria for a specified system configuration to ensure operation within acceptable reliability criteria. System Operating Limits are based upon certain operating criteria. These include, but are not limited to:

1. Facility Ratings (Applicable pre- and post- Contingency equipment or facility ratings)

2. Transient Stability Ratings (Applicable pre- and post-Contingency Stability Limits)

3. Voltage Stability Ratings (Applicable pre- and post- Contingency Voltage Stability)

4. System Voltage Limits (Applicable pre- and post- Contingency Voltage Limits)

Page 10: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

10Western Electricity Coordinating Council

Roles of OTCPC – Is it appropriate or not?

• Determine which transmission paths are to be studied and approve/disapprove seasonal studies of OTC limits performed by the Subregional Study Groups; but– The TP has the responsibility to determine all SOLs

– The recently adopted MOD standards provide which Bulk Electric System facilities must be studied. The adopted standard extends to facilities beyond those currently reviewed by the OTCPC.

• Ensure that the subregional studies are held to the same standards, level of work required and study methodologies; but– The WECC RC has developed an SOL Methodology according to FAC-

011, and all TPs are required to adhere to the SOL Methodology for their applicable Reliability Coordinator Area.

Page 11: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

11Western Electricity Coordinating Council

Roles of OTCPC – Is it appropriate or not? – cont.

• Facilitate OTC dispute resolution

• Recommend policy positions to the Board

• Review and approve Subregional seasonal study plans and technical simulation results

• Develop policies and procedures addressing seasonal OTC’s

• Address OTC seams issues between subregions

• Provide technical guidance

Page 12: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

12Western Electricity Coordinating Council

Future of OTCPC – Options to Consider

• Option 1: Status Quo – Continue with the OTCPC with current reporting structure and duties, responsibilities, and functions. However, review duties, responsibilities, and functions with respect to the NERC Reliability Standards and modify as appropriate.

• Option 2: Report to WECC Reliability Coordination Committee, and review duties, responsibilities, and functions with respect to the NERC Reliability Standards and modify as appropriate.

• Option 3: Recommend to the WECC Board that the OTCPC disband due to the FERC mandatory NERC Reliability Standards superseding the need for OTCPC approval and otherwise becoming obsolete as discussed above, replacing each of its key coordination functions under the OC / RCC and the policy - approval functions under the RPIC duties.

Page 13: Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30

13Western Electricity Coordinating Council

MIC Issues?

QUESTIONS or COMMENTS