57
West Seattle and Ballard Link Extensions June 29, 2020 Avalon Neighbors

West Seattle and Ballard Link Extensions · 6/29/2020  · Microsoft PowerPoint - AE 0036-17 Avalon Station Neighbors Briefing Presentation 20200629.pptx Author: ambrosez Created

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

West Seattleand Ballard

Link Extensions

June 29, 2020

Avalon Neighbors

2

Tonight’s Agenda

• Responding to your questions:• Timeline and process• What are we studying in the EIS?• What is the property acquisition process?• Other topics: West Seattle Bridge, COVID-19 and

Realignment

• Questions and Answers

Timeline and process

4

Questions• Please walk us through the EIS study process • What was the reasoning for rejecting the West Seattle

Bridge/Fauntleroy Level 1 alternative?• What was your plan to inform our neighborhood about the

Yancy addition and provide time for us to engage in the process?

• Is there any new information now based on continued study?• What is not changeable at this point ?

5

West Seattle and Ballard Link ExtensionsProject timeline

*West Seattle Design: 2022–2025 // Construction: 2025–2030*Ballard Design: 2023–2026 // Construction: 2027–2035

2016

PLANNING DESIGN CONSTRUCTION2017–2022 2022–2026* 2025–2035*

START OFSERVICE

West Seattle: 2030Ballard: 2035

WE ARE HERE

PUBLIC INVOLVEMENT PUBLIC INVOLVEMENTPUBLIC INVOLVEMENT

Project scope and schedule subject to change.

6

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

7

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

8

Alternatives development screening process

Refine remaining alternatives

Furtherevaluation

Broad range of initial alternatives

Preferred alternative(s)and other EIS alternatives

Community engagement and collaboration

9

EarlyScoping Period

EIS ScopingPeriod

10

Level 1 alternatives – West Seattle and Duwamish

11

Level 1 alternatives – West Seattle and Duwamish

12

Level 2 alternatives – West Seattle and Duwamish

13

Level 3 alternatives – West Seattle and Duwamish

14

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

15

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

16

Sound Transit Board Motion (May 2019)

• The Board identified preferred alternatives and other alternatives for study in the Draft Environmental Impact Statement.

• “The Board directs staff to conduct an initial assessment of the following alternatives, which were suggested during the scoping period, to establish whether further detailed study in the Draft EIS is appropriate:

• Yancy/Andover alignment – an alignment along the Yancy/Andover corridor with a Delridge Station serving Youngstown.”

17

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

18

Email updates to project listserv Emails to community organizations Community briefings and meetings Media briefing Fairs, festivals, farmers markets Door-to-door flyering Online open house

How did we inform the neighborhood?

Community Engagement Snapshot

19

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

20

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

21

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

22

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

23

Board action – mid 2021

To inform Board’s action:

• DEIS technical analysis

• Community feedback

• Racial Equity Toolkit

24

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

25

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

26

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

27

DES

PUBLIC INVOLVEMENT

PLANNING2019–2022Environmental reviewEarly 2021: Publish Draft EIS

DEIS public comment period

Mid-2021: Board confirms or modifies preferred alternatives

2022: Publish Final EIS

Board selects projectsto be built

Federal Record of Decision

2017–2019Alternatives developmentFeb–Mar 2018:Early scoping

Feb–Apr 2019:Scoping

May, Oct 2019: Board identified preferred alternatives and other DEIS alternatives

2016

Project scope and schedule subject to change.

28

Draft EIS alternativesWhat we’re studying in this phase

Preferred Alternatives

Preferred Alternatives withThird-Party Funding

Other Draft EIS alternatives

3

What are we studying in the EIS?

30

Questions• What is included in the EIS study for West Seattle? Can scope be

added / deleted?• Are at-grade options being considered in West Seattle for cost

savings?• Does Sound Transit favor the route to the north or south of the

existing West Seattle High Bridge?

Avalon / Delridge alternatives

32

Draft EIS alternatives West Seattle

333

Draft EIS alternatives Delridge

343

Draft EIS alternatives Delridge

353

Draft EIS alternatives Delridge

363

Draft EIS alternatives Delridge

373

Draft EIS alternatives Delridge

383

Draft EIS alternatives Delridge

39

Or, “EIS” for short.

Provides agencies and the public an understanding of environmentalconsequences and assistsin decision-making.

So, what’s anEnvironmental ImpactStatement?

39

40

What is typicallystudied in an EIS?How a project affects…

Transportation

Built Environment

Natural Environment

41

EIS studies:

41

Transportationimpacts

42

EIS studies:

42

Natural environmentimpacts

43

EIS studies:Built environmentimpacts

43

44

EIS studies:Built environmentimpacts

44

45

Equity and inclusion

Environmental justice focus within each area of the EIS

Transportation

NaturalEnvironment

BuiltEnvironment

46

EIS studies:Environmental justice

46

47

Outreach to potentially affected properties

Sound Transit contacts potentially affected property owners

Before DEIS publication (late 2020)

48

Outreach to potentially affected properties

Sound Transit Board confirms or modifies preferred alternative

Sound Transit contacts potentially affected property owners

Before DEIS publication (late 2020)

After DEIS publication (mid 2021)

49

Outreach to potentially affected properties

Sound Transit Board confirms or modifies preferred alternative

Sound Transit contacts potentially affected property owners

Sound Transit Board selects project to be built

Before DEIS publication (late 2020)

After DEIS publication (mid 2021)

After FEIS publication (2022)

What is the property acquisition process?

51

Acquisition / relocation process

Sound Transit Board confirms or modifies preferred alternative

Sound Transit will prepare an appraisal to determine fair market value of property needed for the project

Sound Transit will provide full relocation services to people and businesses displaced by the project, including referrals to comparable properties and payment of moving costs

Sound Transit staff are available to support property owners and tenants through this process

Sound Transit contacts potentially affected property owners

Sound Transit Board selects project to be built

Before DEIS publication (late 2020)

After DEIS publication (mid 2021)

After FEIS publication (2022)

During final design (2022-2026)*Sound Transit identifies full / partial acquisitions

Sound Transit Board authorizes property purchases

*West Seattle: Design is expected to begin in 2022 and be completed in 2025. Ballard and downtown Seattle Light Rail Tunnel: Design is expected to begin in 2023 and be completed in 2026.

52

Questions• How does the acquisition process work? How is property

value assessed? • How should our neighborhood evaluate any plans for

investing in our properties over the next several years?• When are the letters being mailed out to inform property

owners of potential acquisition?

Other topics

54

Questions• Will Sound Transit be willing to join with City of Seattle with

options for the West Seattle Bridge?• How is the study taking into consideration COVID and the West

Seattle Bridge being closed?

55

Community outreach and collaboration2019 2020 2021

Initial assessment alternatives resultsNeighborhood forums

Station area engagementProperty owner engagement

DEIS public comment / open housesBriefings, festivals and other events

Environmental review SUMMER FALL WINTER SPRING SUMMER FALL WINTER

Community outreach SUMMER FALL WINTER SPRING SUMMER FALL WINTER

EIS kickoffDEIS development

Conceptual engineering andDesign development

Station planning activitiesPublish DEIS / comment period

ST Board confirms or modifiesPreferred Alternatives

Project scope and schedule subject to change.

Questions

[email protected](206) 903-7229

soundtransit.org/wsblink