WBS Theory

Embed Size (px)

Citation preview

  • 8/8/2019 WBS Theory

    1/3

    WORK BREAKDOWN STRUCTUREWORK BREAKDOWN STRUCTURE

    Work Sustained physical or mental effort to overcome obstacles and achieve an

    objective.

    Breakdown To divide in categories

    Structure Something arranged in definite pattern organization

    WBS as per PMBOK Guide 2002

    A deliverable-oriented grouping of Project elements that organizes and defines

    the total work scope of the project. Each descending level represents an

    increasingly detailed definition of the project work.

    The WBS is used in projects to define

    The Projects work in terms of deliverable and further decomposition of these

    deliverables in smaller components

    WBS is basis for

    All the effort and cost to be expended

    Responsibility assignment

    WBS may be

    Internally Focused produces deliverables and inputs to other project stepswithin company

    Externally Focused produces deliverables and outputs to other project steps

    outside company

    Characteristics of WBS:

    Representative of work as an activity

    Arrange in hierarchical structure

    Has objective or tangible result

    Project Scope Definition

    The process required to ensure that the project includes all the work required,

    and only the work required, to complete the project successfully.

  • 8/8/2019 WBS Theory

    2/3

    Goals of WBS according to above definition

    Ensure project includes all work needed

    Ensure project doesnt include unnecessary work

    WBS is primary input to

    Activity Definition

    Resource Planning

    Cost Estimating

    Cost Budgeting

    Risk Management Planning

    Thought when developing WBS

    Think through the entire project

    Think deliverables

    Think with the end in mind

    Think through the production of deliverables.

    Steps for general process of WBS generation

    Identify final product

    Define products major deliverables

    Decomposition of major deliverables

    Decompose major deliverables to appropriate level of details

    Review, refine WBS

    Factors to be considered

    Each WBS element shows tangible deliverable

    Each subordinate belongs to one single parent

    Deliverables are logically decomposed

    Deliverables are unique and distinct

    Deliverables are clearly defined

    Deliverables limited in size and definition

    All deliverables are explicitly included in WBS

  • 8/8/2019 WBS Theory

    3/3

    WBS Level of Details

    Is there need to improve accuracy of cost and duration estimate?

    Is more than one person or group responsible for WBS element?

    Does WBS include more than one type of work process?

    Are there dependencies between deliverables within WBS element to another? Do resource requirement changes over time within WBS?

    Are clear Criteria missing for measuring progress?

    Are there specific risks that require to be focused?

    Can a portion of work to be performed in WBS element can be scheduled as unit?

    Is the WBS element clearly and completely understood by all stake holders?

    Relation between Project Risk and the WBS

    Are the deliverables completely and clearly defined?

    Will the quality of work be evaluated by testing?

    What is the likelihood of change? Is technology is changing faster than the project can be accomplished?

    Is excessive contracting expected?

    Is management committed to project?

    Are requirements defined and approved?

    Has a formal change process has been developed?

    Have metrics been defined?

    Have resource requirement been identified?

    Are third part dependency understood?

    Have alternate suppliers of required products been identified?