54
HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE Ref. LETTER NO. SEIAA/HR/2014/923 DATED 11.07.2014 for CONSTRUCTION OF GROUP HOUSING COLONY LOCATED AT SECTOR-104, VILLAGE-DHAWANPUR , GURGAON, HARYANA By M/s JUVENTUS ESTATE LTD. Sl. No. Conditions Status of Compliance PART A - SPECIFIC CONDITIONS:CONSTRUCTION PHASE: 1 “Consent to Establish” shall be obtained from Haryana State Pollution Control Board under Air and Water act and a copy shall be submitted to the SEIAA Haryana before the start of any construction work at the site. Agreed. “Consent to Establish” has been obtained from Haryana State Pollution Control Board. A Copy of CTE is attached as Annexure-I. 2 A First Aid room as proposed in the project report will be provided in both during construction and operation of the project. Agreed. A First Aid room will be provided during the construction phase as well as in the operational phase of the project. 3 Adequate drinking water and sanitary facilities shall be provided for Agreed. Adequate facility of safe drinking water will be provided on the site. As 1

nromoef.gov.innromoef.gov.in/SMPR/22092015/47.docx · Web viewOpaque wall should meet prescriptive requirement as per Energy Conservation Building Code which is proposed to be mandatory

Embed Size (px)

Citation preview

HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE Ref. LETTER NO. SEIAA/HR/2014/923 DATED 11.07.2014 for CONSTRUCTION OF

GROUP HOUSING COLONY LOCATED AT SECTOR-104, VILLAGE-DHAWANPUR , GURGAON, HARYANA By M/s JUVENTUS ESTATE LTD.

Sl. No. Conditions Status of Compliance

PART A - SPECIFIC CONDITIONS:CONSTRUCTION PHASE:

1 “Consent to Establish” shall be obtained

from Haryana State Pollution Control

Board under Air and Water act and a

copy shall be submitted to the SEIAA

Haryana before the start of any

construction work at the site.

Agreed. “Consent to Establish” has been

obtained from Haryana State Pollution

Control Board. A Copy of CTE is attached

as Annexure-I.

2 A First Aid room as proposed in the

project report will be provided in both

during construction and operation of the

project.

Agreed. A First Aid room will be provided

during the construction phase as well as in

the operational phase of the project.

3 Adequate drinking water and sanitary

facilities shall be provided for

construction workers at the site.

Provision should be made for the mobile

toilets. Open defecation by the laborers is

strictly prohibited. The safe disposal of

waste water and solid wastes generated

during the construction phase should be

ensured.

Agreed. Adequate facility of safe drinking

water will be provided on the site. As

mostly local laborers will be hired for the

construction phase, thus a negligible

quantity of waste will be generated.

Inorganic waste will be segregated and

recyclable waste is sold off to government

approved vendors. Mobile toilets will be

provided nonetheless and the waste water

generated will be sent to septic tanks. Solid

waste generated during construction will be

managed properly as per MSW Rules, 2000.

4 All the top soil excavated during

construction activities should be stored

for use in horticulture/landscape

Agreed. The excavated material will be used

for leveling, refilling and in horticulture/

landscape development within the project

1

development within the project site. site & surplus will be disposed off outside

the premises with prior consent of

department.

5 The project proponent shall ensure that

the building material required during

construction phase is properly stored

within the project area and disposal of

construction waste should not create any

adverse effect on the neighboring

communities and should be disposed off

after taking the necessary precautions for

general safety and health aspects of

people, only in approved sites with the

approval of competent authority.

Agreed. M/s Juventus Estate Ltd. will

ensure that the building material required

during construction phase will be properly

stored within the project area and disposal

of construction waste will not create any

adverse effect on the neighboring

communities and will be disposed off after

taking the necessary precautions for general

safety and health aspects of people, only in

approved sites with the approval of

competent authority.

6 Construction spoils, including

bituminous material and other hazardous

materials, must not be allowed to

contaminate watercourses and the dump

sites for such material must be secured so

that they should not leach into the ground

water and any hazardous waste generated

during construction phase, should be

disposed off as per applicable rules and

norms with necessary approval of the

Haryana State Pollution Control Board.

Agreed. Construction spoils including

bituminous material and other hazardous

material will not be allowed to contaminate

water courses. No dumping of such

materials will be allowed at project site.

Waste lubricating oil generated from

maintenance of DG sets falls under

hazardous waste category. Such wastes will

be disposed off with the help of Waste

recycler with necessary approval from

Haryana State Pollution Control Board.

7 The Diesel generator sets to be used

during construction phase should be of

ultra-low sulphur diesel type and should

conform to Environment (Protection)

Rules prescribed for air and noise

emission standards.

Agreed. Ultra-low sulphur diesel will be

used to run the Diesel generator sets to be

used during construction phase with

Provisions of Air and Noise Emissions

Standards as per EPA Rules 1986.

2

8 The diesel required for operating DG sets

shall be stored in underground tanks and

if required, clearance from Chief

Controller of Explosives shall be taken.

Agreed. Used oil from DG sets will be

stored in HDPE drums in isolated covered

facility. This used oil will be sold to

authorized recyclers. Suitable care will be

taken to avoid spills/leaks of used oil from

storage. Separate log books will be

maintained for accountability.

9 Ambient noise levels should conform to

residential standards both during day and

night. Incremental pollution loads on the

ambient air and noise quality should be

closely monitored during construction

phase. Adequate measures should be

taken to reduce ambient air and noise

level during construction phase, so as to

conform to the stipulated residential

standards.

Agreed. Incremental pollution loads on the

ambient air and noise quality are being

closely monitored. Laboratory Reports of

the environmental monitoring of air, noise

and soil carried out at the site are enclosed

as Annexure II.

Similarly, Ambient air quality is also closely

monitored so as to conform to the stipulated

standards.

10 Fly ash should be used as building

material in the construction as per the

provisions of Fly Ash Notification of

September, 1999 and amended as on 27th

August, 2003.

Agreed. Fly ash bricks will be used as

building material in the construction as per

the provisions of Fly Ash Notification of

September, 1999 and amended as on 27th

August, 2003.

11 Storm water control and its re use as per

CGWB and BIS standards for various

applications should be ensured.

Agreed. Storm water control and its re use

(for various applications) will be ensured as

per BIS and Central Ground Water Board

(CGWB) standards.

12 Water demand during construction

should be reduced by use of pre-mixed

concrete, curing agents and other best

practices.

Agreed. Water demand during construction

will be reduced by the practice of using pre-

mixed concrete, curing agents and other best

practices.

13 In view of the severe constrains in water Agreed. Project site falls within planned

3

supply augmentation in the region and

sustainability of water resources, the

developer will submit the NOC from

CGWA specifying water extraction

quantities and assurance from HUDA

/utility provider indicating source of

water supply and quantity of water with

details of intended use of water – potable

and non-potable. Assurance is required

for both construction and operation

stages separately. It shall be submitted to

the SEIAA and RO, MOEF, Chandigarh

before the start of construction.

Sector of Gurgaon Manesar Urban Complex

2021, which shall be facilitated with HUDA

water supply scheme for which EDC/IDC

are being paid. Ground water will not be

extracted for the purpose of construction as

well as for operation phase of the project.

Assurance from HUDA for the water supply

during construction & operational phase are

enclosed as Annexure-III (a) & (b)

respectively.

14 Roof should meet prescriptive

requirement as per Energy Conservation

Building Code by using appropriate

thermal insulation material.

Agreed. Roof will be constructed as per

energy conservation building code by using

appropriate thermal insulation material.

15 Opaque wall should meet prescriptive

requirement as per Energy Conservation

Building Code which is proposed to be

mandatory for all air conditioned spaces

while it is desirable for non-air-

conditioned spaces by use of appropriate

thermal insulation material to fulfill

requirement.

Agreed. Opaque wall will meet prescribed

requirement as per Energy Conservation

Building Code (ECBC).

16 The approval of the competent authority

shall be obtained for structural safety of

the building on account of earthquake,

adequacy of firefighting equipment’s,

etc. as per National Building Code

including protection measures from

Agreed. The approval of the competent

authority will be obtained in due course of

time for structural safety of the buildings

due to earthquake, adequacy of firefighting

equipment, etc. as per National Building

Code including protection measure from

4

lightening etc. If any forest land is

involved in the proposed site, clearance

under The Forest Conservation Act shall

be taken from the competent Authority.

lightening etc. No forest land is involved in

the project site. NOC from Forest

Department has been obtained from Dy.

Conservator of Forest, Gurgaon vide letter

No. 4054-G and copy of the same is

enclosed as Annexure IV.

17 Overexploited ground water and

impending severe shortage of water

supply in the region requires the

developer to redraw the water and energy

conservation plan. Developer shall

reduce the overall footprint of the

proposed development. Project

proponent shall incorporate water

efficiency/savings measures as well as

water reuse/recycling within 3 months

and before start of construction to the

SEIAA, Haryana and RO, MOEF, GOI,

Chandigarh.

Agreed. No ground water extraction will

take place without permission from CGWA.

However, treated water will be supplied by

HUDA will be used for construction. To

reduce the demand in operational phase,

treated water from STP will be used for

horticulture; flushing as well as efficient

fixtures will be used to minimize the fresh

water demand.

18 The project proponent as stated in the

proposal shall construct 29 rain water

harvesting pits for recharging the ground

water within the project premises. Rain

water harvesting pits shall be designed to

make provisions for silting chamber and

removal of floating matter before

entering harvesting pit. Maintenance

budget and persons responsible for

maintenance must be provided. Care

shall be taken that contaminated water do

not enter any RWH pit.

Agreed. 29 number of RWH pits will be

constructed to harvest rain water. Rain water

harvesting pits will be designed in such a

way that the silt and floating matter will be

removed before entering into the pit.

Maintenance budget and experienced

persons for maintenance of the pits will be

provided. It will be taken care that

contaminated water do not enter any RWH

pit. Storm Water Plan showing location of

RWH pits is enclosed as Annexure V.

5

19 The project proponent shall provide for

adequate fire safety measures and

equipment’s as required by Haryana Fire

Service Act, 2009 and instructions issued

by the local authority/Directorate of fire

from time to time. Further the project

proponent shall take necessary

permission regarding fire safety

scheme/NOC from competent Authority

as required.

Agreed. M/s Juventus Estate Ltd. will

provide adequate Fire Safety measures and

equipments as required by Haryana Fire

Service Act, 2009 and local Authority/

Directorate of fire from time to time. Further

the project proponent will take necessary

permission regarding fire safety scheme/

NOC from competent authority as required.

20. The project proponent shall obtain

assurance from the DHBVN for supply

of 13235 KVA of power supply before

the start of construction. In no case

project will be operational solely on

generators without any power supply

from any external power utility.

Agreed. The project proponent will obtain

assurance from the DHBVN for supply of

13235 KVA of power supply before the start

of construction or else project will be

operational solely on generators without any

power supply from any external power

utility. An application has been filed to

HVPNL and acknowledgment copy of the

same is enclosed as Annexure VI.

21 Detail calculation of power load and

ultimate power load of the project shall

be submitted to DHBVN under

intimation to SEIAA Haryana before the

start of construction. Provision shall be

made for electrical infrastructure in the

project area.

Agreed. Total power requirement is 13235

kVA Calculation of power load is enclosed

as Annexure-VII.

22 The Project proponent shall not raise any

construction in the natural land

depression/Nallah/ Water course and

shall ensure that the natural flow from

the Nallah/ Water course is not

There is no natural land depression/Nallah/

water course passing through the project

site.

6

obstructed.

23 The project proponent shall keep the

plinth level of the building blocks

sufficiently above the level of the

approach road to the Project as per

prescribed bye-laws. Levels of the other

areas in the Projects shall also be kept

suitably so as to avoid flooding.

Agreed. The plinth level of the building

blocks will be kept sufficiently above the

level of the approach road to the project as

per prescribed bye laws. Levels of the other

areas in the projects will also be kept

suitably so as to avoid flooding.

24 Construction shall be carried out so that

density of population does not exceed

norms approved by Director General

Town and Country Department Haryana.

Agreed. Construction will be carried out so

that density of population does not exceed

norms approved by Director General Town

and Country Planning Department, Haryana.

25 The Project proponent shall submit an

affidavit with the declaration that ground

water will not be used for construction

and only treated water should be used for

construction.

Agreed. Ground water will not be used for

the construction activity and an affidavit for

this has already been submitted to SEIAA,

Haryana at the time of Environmental

Clearance. Only treated water will be used

for construction from HUDA.

26 The project proponent shall not cut any

existing tree and project landscaping plan

should be modified to include those trees

in green area.

Agreed. There is no need to cut the trees,

only small bushes clearing will be required

for construction activity.

27 The project proponent shall provide 3

meter high barricade around the project

area, dust screen for every floor above

the ground, proper sprinkling and

covering of stored material to restrict

dust and air pollution during

construction.

Agreed. The project proponent will provide

3 meter high barricade around the project

area, dust screen for every floor above the

ground, proper sprinkling and covering of

stored material to restrict dust and air

pollution during construction.

28 The project proponent shall construct a

sedimentation basin in the lower level of

Agreed. Sedimentation basin will be

constructed in the lower level of the project

7

the project site to trap pollutant and other

wastes during rains.

site to trap pollutant and other wastes during

rains.

29 The Project Proponent shall provide

proper Rasta of proper width and proper

strength for each project before the start

of construction.

Agreed. Proper Rasta of proper width and

proper strength for this project will be

provided before the start of construction.

30 The Project Proponent shall ensure that

the U-value of the glass is less than 3.177

and maximum solar heat gain co-

efficient is 0.25 for vertical fenestration.

Agreed. It will be ensured that the U-value

of the glass will be less than 3.177 and

maximum solar heat gain co-efficient 0.25

for vertical fenestration.

31 The project proponent shall adequately

control dusts like silica dust, non-silica

and wood dust. Such dust shall not

spread outside project proponent shall

provide respiratory protective equipment

to all construction workers.

Agreed. There will be adequate provision

for silica dust, non-silica and wood dust.

Such will not be spread outside. Also,

respiratory protective equipments will be

provided to all the construction workers.

32 The project proponent shall develop

complete civic infrastructure of the group

housing colony including internal roads,

green belt development, sewage line, rain

water recharge arrangements, storm

water drainage system, solid waste

management site and provision for

treatment of bio-degradable waste, STP,

water supply line, dual plumbing line,

dual plumbing line, electricity supply

lines etc. and shall offer possession of

the unit/flats thereafter.

Agreed. Complete civic infrastructure of the

group housing colony including internal

roads, green belt development, sewage line,

rain water recharge arrangements, storm

water drainage system, solid waste

management site and provision for treatment

of bio-degradable waste, STP, water supply

line, dual plumbing line, dual plumbing line,

electricity supply lines etc. will be

developed and shall offer possession of the

unit/flats thereafter. RWH Plan, SWM Plan,

dual plumbing plan, Electric layout Plan are

attached as Annexure-V, VIII, IX & X

respectively.

33 The project proponent shall provide one Agreed. There will be provision for one

8

refuge area till 24 meter, one till 39

meter and one after 15 meter each, as per

National Building Code. The project

proponent shall not convert any refuse

area in the habitable space and it should

not be sold out/commercialized.

refuge area till 24 meter, one till 39 meter

and one after 15 meter each, as per National

Building Code. The project proponent shall

not convert any refuse area in the habitable

space and it will not be sold

out/commercialized.

34 The project proponent shall provide fire

control room and fire officer for building

above 30 meter as per National Building

Code

Agreed. We will provide fire control room

and fire officer for building above 30 meter

as per National Building Code.

35 The project proponent shall obtain

permission of Mines and Geology

Department for excavation of soil before

the start of construction.

Agreed. Permission from mines and

Geology Department for excavation of soil

has been taken; copy of the same is enclosed

as Annexure-XI.

36 The project proponent shall seek specific

prior approval from concerned local

authority/HUDA regarding provision of

storm drainage and sewerage system

including their integration with external

services of HUDA/ Local authorities

beside other required services of

HUDA /Local authorities beside other

required services before taking up any

construction activity.

Agreed. The project proponent seek specific

prior approval from concerned local

authority/HUDA regarding provision of

storm drainage and sewerage system

including their integration with external

services of HUDA/ Local authorities beside

other required services of HUDA/Local

authorities beside other required services

before taking up any construction activity.

37 The site for solid waste management

plant be earmarked on the layout plan

and the detailed project for setting up the

solid waste management plant shall be

submitted to the authority within one

month.

Agreed. Solid waste management area has

been earmarked on the layout plan and the

detailed project for setting up the solid

waste management plant will be submitted

to the authority in due course of time.

38 The project proponent shall submit the Agreed. We will submit the copy of fire

9

copy of fire safety plan duly approved by

Fire Department before the start of

construction.

safety plan duly approved by Fire

Department in due course of time.

39 The project proponent shall discharge

excess of treated waste water/storm

water in the public drainage system and

shall seek permission of HUDA before

the start of construction.

The discharge from excess treated waste

water/storm water will not be discharged in

the public drainage system. Wastewater will

be used for nearby ongoing construction

activities

40 The project proponent shall maintain the

distance between STP and water supply

line.

Agreed. There will be adequate distance

between STP and water supply line to avoid

any contamination.

41 The project proponent shall ensure that

the stack height is 6 meter more than the

highest tower.

Agreed. The stack height will be 6 meter

more than the highest tower.

42 The project proponent shall ensure that

structural stability to withstand

earthquake of magnitude 8.5 on Richter

scale.

Agreed. There will be adequate structural

stability to withstand earthquake of

magnitude 8.5 on Richter scale.

43 The project proponent shall seek NOC

from Town and Country department

regarding height of the building allowed

in the skyline of that city.

Agreed. Height clearance from Airport

Authority of India (AAI) has been taken.

NOC from AAI is attached as Annexure-

XII.

44 The project proponent shall provide

helipad facility as required under NBC

norms and seek permission of helipad

from AAI accordingly.

Agreed. Helipad Facility will be provided as

required under NBC norms.

45 The project proponent shall ensure that

no construction activity is undertaken

either on surface or below or above

surface of revenue rasta passing through

the project area.

Agreed. No construction activity will be

undertaken either on surface or below or

above surface of revenue rasta passing

through the project area.

10

46 The project proponent shall indicate the

width and length of revenue rasta passing

through the project area on sign board

and shall display the same at both ends

of revenue rasta stretch, for awareness of

public. Sign board shall also display the

message that this is public rasta /road and

any citizen can use it. There shall not be

any gate with or without guards on

revenue rasta further project proponent

shall not encroach revenue rasta further

project proponent shall not encroach

revenue rasta and shall encroach revenue

rasta and shall not cross internal roads

over revenue rasta.

Agreed. Revenue rasta will not be

encroached and any internal roads will not

cross over them.

47 The project proponent shall ensure that

the plinth level of the building block to

be 1.5 meter above 100 years flood level

of the said Najafgarh Jheel.

Agreed. The plinth level of the building

block will be 1.5 meter above 100 years

flood level of the said Najafgarh Jheel.

48 The project proponent shall obtain NOC

from HUDA as well as Irrigation

Department before the start of

construction, regarding possible adverse

effect of project proposal on the

Najafgarh Jheel

Agreed. NOC from HUDA as well as

Irrigation Department will be taken before

the start of construction, regarding possible

adverse effect of project proposal on the

Najafgarh Jheel.

49 The project proponent shall provide

boosting arrangement and multistage

pumping with standby arrangement after

getting the same approved from HUDA.

Agreed. Adequate boosting arrangement and

multistage pumping will be provided with

standby arrangement after getting the same

approved from HUDA

50 The project proponent shall implement

green belt development plan as submitted

Agreed. Green belt development plan will

be implemented.

11

in the meeting on 26.06.2014 (additional

green area by replacing water bodies)

51 The project proponent shall implemented

the traffic circulation plan as submitted

in the meeting on 26.06.2014 (Bell

mouth entry and exit points on 24 meter

wide road and 15 meter wide internal

road)

Agreed. The traffic circulation plan as

submitted in the meeting on 26.06.2014

(Bell mouth entry and exit points on 24

meter wide road and 15 meter wide internal

road) will be implemented.

52 The Project proponent shall implement

the traffic circulation plan of basement as

submitted in the meeting of 26.06.2014

(connecting two separate lines of

basements below the towers at least at

two points along the length for

comfortable exit and entry of vehicles

and its occupants).

Agreed. The traffic circulation plan of

basement as submitted in the meeting of

26.06.2014 (connecting two separate lines

of basements below the towers at least at

two points along the length for comfortable

exit and entry of vehicles and its occupants)

will be implemented.

PART A- SPECIFIC CONDITIONS : Operation Phase

a “Consent to Operate” shall be obtained

from Haryana State Pollution Control

Board under Air and Water Act and a

copy shall be submitted to the SEIAA,

Haryana.

Agreed. “Consent to Operate” will be

obtained from Haryana State Pollution

Control Board under Air and Water Act and

a copy will be submitted to the SEIAA,

Haryana.

b The STP shall be installed for the

treatment of the sewage to the prescribed

standards including odor and treated

effluent will be recycled. The installation

of STP should be certified by an

independent expert and a report in this

regard should be submitted to the

SEIAA, Haryana before the project is

commissioned for operation. Tertiary

Agreed. The STP will be installed for the

treatment of the sewage to the prescribed

standards including odor and treated effluent

will be recycled. The installation of STP

will be certified by an independent expert

and a report in this regard will be submitted

to the SEIAA, Haryana before the project is

commissioned for operation. Tertiary

treatment of waste water is mandatory.

12

treatment of waste water is mandatory.

Discharge of treated sewage shall

confirm to norms and standards of

HSPCB, Panchkula. Project Proponent

shall implement such STP technology

which does not require filter backwash.

Discharge of treated sewage shall confirm to

norms and standards of HSPCB, Panchkula.

STP technology which does not require

filter backwash will be implemented. Dual

Plumbing plan showing the STP location is

enclosed as Annexure-IX and STP

schematic design is enclosed as Annexure

XIII.

c Separation of the grey and black water

should be done by the use of dual

plumbing line. Treatment of 100% grey

water by decentralized treatment should

be done ensuring that the re-circulated

water should have BOD level less than

10mg/litre and the recycled water will be

used for flushing, gardening and DG set

cooling and running of fountain in the

water body to achieve zero exit discharge

Separation of the grey and black water will

be done by the use of dual plumbing line.

Treatment of 100% grey water by

decentralized treatment will be done

ensuring that the re-circulated water will

have BOD level less than 10mg/litre and the

recycled water will be reused for flushing,

gardening, DG set cooling and other

recreational purposes to achieve zero exit

discharge. Water Balance Diagram showing

Zero Discharge is enclosed as Annexure-

XIV.

d For disinfection of the treated waste

water Ultra violet radiation or

ozonization process should be used.

Agreed. For disinfection of the treated

wastewater, UV Disinfection process will be

used (Refer Annexure XIII).

e Diesel power generating sets proposed as

source of back-up power for lifts,

common area illumination and for

domestic use should be enclosed type

and conform to rules made under the

Environmental (Protection) Act, 1986.

The location of the DG sets should be in

the basement as promised by the project

Agreed. Diesel power generating sets

proposed as source of back-up power for

lifts, common area illumination and for

domestic use will be of enclosed type and

will conform to the rules made under the

Environmental (Protection) Act, 1986. The

location of the DG sets will be in the

basement as promised with appropriate

13

proponent with appropriate stack height

i.e. above the roof level as per the CPCB

norms. The diesel used for DG sets

should be ultra-low sulphur diesel (35

ppm sulphur) instead of low sulphur

diesel.

stack height i.e. above the roof level as per

the CPCB norms. The diesel used for DG

sets will be ultra-low sulphur diesel (35 ppm

sulphur) instead of low sulphur diesel.

f Ambient noise level should be controlled

to ensure that it does not exceed the

prescribed standards both within and at

the boundary of the proposed Group

Housing Project.

Agreed. Ambient noise level will be

controlled within and at the boundaries of

the project ensuring compliance to

regulatory norms that is in accordance to

Schedule-III of The Noise Pollution

(Regulation and Control) Rules, 2000. This

could be attained through:

1) Development and maintenance of at

least 20% of the total land area for

tree plantation all around the project.

2) Providing acoustic enclosures to DG

sets.

3) Better traffic management.

4) Regular surveillance monitoring.

g The project proponent as stated in the

proposal should maintain at least 30.79%

as green cover area for tree plantation

especially all around the periphery of the

project and on the road sides preferably

with local species so as to provide

protection against noise and suspended

particulate matter. The open spaces

inside the project should be preferably

landscaped and covered with

vegetation/grass, herbs & shrubs. Only

Agreed. 30.79% of the total project area will

be maintained as used for tree plantation all

around the periphery and the road sides.

Species shall be endemic and chosen to

provide protection from dust and noise. In

addition, open spaces within the boundaries

shall be landscaped whenever possible and

to the maximum extent. Landscape Plan is

enclosed as Annexure XV.

14

locally available plant species shall be

used.

h The project proponent shall strive to

minimize water in irrigation of landscape

by minimizing grass area, using native

variety, xeriscaping and mulching,

utilizing efficient irrigation system,

scheduling irrigation only after checking

evapo-transpiration data.

Agreed. Minimum water in irrigation of

landscape by minimizing grass area will be

strived, using native variety, xeriscaping and

mulching, utilizing efficient irrigation

system, scheduling irrigation only after

checking evapo-transpiration data.

i Rain water harvesting for roof run-off

and surface, as per plan submitted should

be implemented. Before recharging the

surface run-off, pre-treatment through

sedimentation tanks must be done to

remove suspended matter, oil and grease.

The bore well for rainwater recharging

should be kept at least 5m. Above the

highest ground water table. Care shall be

taken that contaminated water do not

enter any RWH pit. The project

proponent shall avoid RWH of first 10

minutes of rain fall. Roof top of the

building shall be without any toxic

material or paint which can contaminate

rain water. Wire mess and filters should

be used wherever required.

Agreed. Rain water harvesting for roof run-

off and surface, as per plan submitted will

be implemented. Before recharging the

surface run-off, pre-treatment through

sedimentation tanks will be done to remove

suspended matter, oil and grease. The bore

well for rainwater recharging will be kept

atleast 5 m above the highest ground water

table. Rain water harvesting plan is enclosed

as Annexure V.

j The ground water level and its quality

should be monitored regularly in

consultation with Central Ground Water

Authority.

Agreed. The ground water level and its

quality will be monitored regularly in

consultation with Central Ground Water

Authority.

k A report on the energy conservation Agreed. Report on energy conservation

15

norms finalized by Bureau of energy

efficiency should be prepared

incorporating details about building

material & technology, R & U Factors

etc and submitted to the SEIAA, Haryana

in three month time.

measures conforming to energy

conservation norms finalized by BEE will

be submitted in due course of time. Energy

conservation measures are enclosed as

Annexure XVII.

l Energy conservation measures like

installation of LED for lighting the-areas

outside the building should be integral

part of the project design and should be

in place before project commissioning.

Use of solar panels must be adapted to

the maximum energy conservation.

Agreed. Energy conservation measures like

installation of LED for lighting the areas

outside the building will be integral part of

the project design and will be in place

before project commissioning. Solar panels

will be adapted for the maximum energy

conservation.

m The project proponent shall use zero

ozone depleting potential material in

insulation, refrigeration, air-conditioning

and adhesive. Project proponent shall

also provide Halon free fire suppression

system.

Agreed. Zero ozone depleting potential

material in insulation, refrigeration, air-

conditioning and adhesive will be used.

Halon free fire suppression will be provided.

n The solid waste generated should be

properly collected and segregated as per

the requirement of the MSW Rules, 2000

and as amended from time to time. The

bio-degradable waste should be

composed by vermin-composting at the

site war marked within the project area

and dry/inert solid waste should be

disposed-off to the approved sites for

land-filling after recovering material.

Agreed. The solid waste generated will be

properly collected and segregated as per the

requirement of the MSW Rules, 2000. The

bio-degradable waste will be composed by

the use of organic waste converter

composting at the site marked within the

project area and dry/inert solid waste will be

disposed-off to the approved sites for land-

filling after recovering material. Solid Waste

Management plan is enclosed as Annexure-

VIII.

o Provision of the solar water heating Agreed. The provision of the solar water

16

systems shall be as per norms specified

by HAREDA & shall be made

operational in each building block

heating system will be as per the norms

specified by HAREDA and will be made

operational in each building block.

p The traffic plan and the parking plan

proposed by the project proponent should

be adhere to meticulously with further

scope of additional parking for future

requirement. There should be no traffic

congestion near the entry and exit points

from the roads adjoining the proposed

project site. Parking should be fully

internalized and no public space should

be used.

Agreed. Proposed parking plan will be

adhering to meticulously with further scope

of additional parking for future requirement.

There will be no traffic congestion near the

entry and exit points from the roads

adjoining the project site. Parking will be

fully internalized and no public space should

be used. Parking plans are enclosed as

Annexure XVII.

q The Project shall be operationalized only

when HUDA/local authority will provide

domestic water supply system in the

area.

Agreed. The Project will be operationalized

only when HUDA/local authority will

provide domestic water supply system in the

area.

r Operation and maintenance of STP, solid

waste management and electrical

Infrastructure, pollution control measures

shall be ensured even after the

completion of project..

Agreed. Operation and maintenance of STP,

solid waste management and electrical

Infrastructure, pollution control measures

will be ensured even after the completion of

sale.

s Different type of waste should be

disposed-off as per provisions of

municipal solid waste, biomedical waste,

hazardous waste, e-waste, batteries &

plastic rules made under Environment

Protection Act, 1986. Particularly E-

Waste and Battery waste shall be

disposed of as per existing E-waste

Management Rules 2011 and Batteries

Agreed. Different type of waste will be

disposed off as per provisions of municipal

solid waste, biomedical waste, hazardous

waste, e-waste, batteries & plastic rules

made under Environment Protection Act,

1986. Particularly E-Waste and Battery

waste will be disposed of as per existing E-

waste Management Rules, 2011 and

Batteries Management Rules, 2001.

17

Management Rules 2001. The project

proponent should maintain a collection

center for E-Waste and it should be

disposed of to only registered and

authorized dismantler/recycler.

Collection center for E-Waste will be

maintained and it will be disposed of to only

registered and authorized dismantler/

recycler.

t Standards for discharge of environmental

pollutants as enshrined in various

schedules of rules 3 of Environment

Protection Rules 1986 shall be strictly

complied with.

Agreed. Standards for discharge of

environmental pollutants as enshrined in

various schedules of rules 3 of Environment

Protection Rules, 1986 will be strictly

complied with.

u Water supply shall be metered to

different residential units and different

utilities.

Agreed. Water supply will be metered to

different residential units and different

utilities.

v The project proponent shall ensure that

the stack height of DG sets is as per the

CPCB guide lines and also ensure that

the emission standards of noise and air

are within the CPCB prescribed limits.

Noise and Emission level of DG sets are

greater than 800 KVA shall be as per

CBCB latest standards for high capacity

DG sets.

Agreed. It will be ensured that the stack

height of DG sets is as per the CPCB guide

lines and also that the emission standards of

noise and air are within the CPCB

prescribed limits. Noise and Emission level

of DG sets greater than 800 KVA will be

maintained as per CBCB latest standards for

high capacity DG sets.

w All electric supply exceeding 100amp, 3-

phase shall maintain the power factor

between 0.98 lag to 1 at the point of

connection.

Agreed. All electric supply exceeding

100amp, 3-phase will maintain the power

factor between 0.98 lag to 1 at the point of

connection.

x The project proponent shall use only

treated water instead of fresh water for

HVAC and DG cooling. The project

proponent shall use evaporative cooling

technology and double stage cooling

Agreed. It will be ensured that treated water

instead of fresh water for HVAC and DG

cooling will be used. Evaporative cooling

technology and double stage cooling system

for HVAC will be used in order to reduce

18

system for HVAC in order to reduce

water consumption. Further temperature,

relative humidity during summer and

winter session should be kept at optimal

level. Variable speed drive, best co-

efficient of performance, as well as

optimal integrated point load value and

minimum outside fresh air supply may

be resorted for conservation of power

and water. Coil type cooling DG sets

shall be used for saving cooling water

consumption for water cooled DG sets.

water consumption. Further temperature,

relative humidity during summer and winter

session will be kept at optimal level.

Variable speed drive, best co-efficient of

performance, as well as optimal integrated

point load value and minimum outside fresh

air supply will be resorted for conservation

of power and water.

y The PP shall ensure that the transformer

is constructed with high quality grain

oriented, low loss silicon steel and virgin

electrolyte grade copper. The PP shall

obtain manufacturer’s certificate also for

that.

Agreed. We will ensure that the transformer

constructed will be of high quality grain

oriented, low loss silicon steel and virgin

electrolyte grade copper and manufacturer’s

certificate will be obtained.

z The project proponent shall ensure that

the exit velocity from the stack should be

sufficiently high. Stack shall be designed

in such a way that there is no stack

down-wash under any meteorological

conditions.

Agreed. Exit velocity from the stack will be

sufficiently high. Stack will be designed in

such a way that there is no stack down-wash

under any meteorological conditions.

aa The project proponent shall provide

water sprinkling system in the project

area to suppress the dust in addition to

the already suggested mitigation

measures in the Air Environment

Chapter of EMP

Agreed. Water sprinkling system will be

provided.

ab The project proponent shall ensure Agreed. Ventilation in basement will be

19

proper Air Ventilation and light system

in the basement area for comfortable

living of human being and shall ensure

that number of Air changes per

hour/(ACH)in basement never falls

below 15.In case of emergency capacity

for increasing ACH to the extent of 30

must be provided by the project

proponent.

taken special care.

ac The project proponent shall ensure

drinking/ domestic water supply as per

prescribed standards till treated water

supply is made available by HUDA.

Agreed.

PART-B GENERAL CONDITION:

I The project proponent should ensure the

commitments made in Form-1, Form-1A,

EIA/EMP and other documents

submitted to the SEIAA for protection of

environment and proposed

environmental safeguards are complied

with in letter and spirit. In case of

contradiction between two or more

documents on any point, the most

environmentally friendly commitment on

the point shall be taken as commitment

by project proponent.

Agreed. It will be ensured that commitments

made in Form-1, Form-1A, EIA/EMP and

other documents submitted to the SEIAA for

protection of environment and proposed

environmental safeguards are complied with

in letter and spirit. In case of contradiction

between two or more documents on any

point, the most environmentally friendly

commitment on the point will be taken as

Priority.

II The project proponent shall also submit

six monthly compliance of the reports on

the status of compliance of the stipulated

EC conditions including result of

monitored data should be submitted to

Agreed. Six monthly monitoring reports are

being & will be submitted to the HSPCB

and Regional Office, MoEF, GOI, Northern

Region, Chandigarh and a copy to the

regulatory Authorities of Haryana.

20

the HSPCB and Regional Office, MoEF,

GOI, Northern Region, Chandigarh and a

copy to the regulatory Authority of

Haryana.

Acknowledgement copy of previous

submitted compliance report is enclosed as

Annexure XVIII.

III STP outlet after stabilization and stack

emission shall be monitored monthly.

Other environmental parameters and

green belt shall be monitored on

quarterly basis. After every 3 months, the

project proponent shall conduct

environmental audit and shall take

corrective measure, if required, without

delay.

Agreed. STP outlet after stabilization and

stack emission will be monitored monthly.

Other environmental parameters and green

belt will be monitored on quarterly basis.

After every 3 months, the project proponent

will conduct environmental audit and will

take corrective measure, if required, without

delay.

IV The SEIAA, Haryana reserves the right

to add additional safeguard measures

subsequently, if found necessary.

Environmental Clearance granted will be

revoked if it is found that false

information has been given for getting

approval of this project. SEIAA reserves

the right to revoke the clearance if

conditions stipulated are not

implemented to the satisfaction of

SEIAA/MOEF.

Agreed.

V The project proponent shall not violate

any judicial orders/ pronouncements

issued by the Court/ Tribunal.

Agreed.

VI All other statutory clearances such as the

approvals for storage of diesel from

Chief Controller of Explosives, Fire

Department, Civil Aviation Department,

Agreed. AAI NOC from Civil Aviation

Department for Height clearance and

Aravalli clearance from D.C. has already

been granted and are enclosed as Annexure

21

Forest Conservation Act, 1980 and

Wildlife (Protection) Act, 1972, Forest

Act, 1927, PLPA 1900 etc. shall be

obtained, as applicable by the project

proponents from the respective

authorities prior to construction of the

project.

– XII & XIX respectively. Forest NOC is

enclosed as Annexure IV.

VII The project proponent should inform the

public that the project has been accorded

Environment Clearance by the SEIAA

and copies of the clearance letter are

available with the Haryana State

Pollution Control Board & SEIAA. This

should be advertised within 7 days from

the date of issue of clearance letter at

least in two local newspapers that are

widely circulated in the region and the

copy of the same be forwarded to SEIAA

Haryana. A copy of Environment

Clearance collections shall also be put on

project proponent’s website for public

awareness.

Agreed. EC letter has been published in two

local newspapers; copy of the same is

enclosed as Annexure XX.

VIII Under the provisions of Environment

(Protection) Act, 1986, legal action shall

be initiated against the project proponent

if it was found that construction of the

project has been started without

obtaining Prior Environmental

Clearance.

Agreed. Environmental clearance has been

obtained vide letter no.

SEIAA/HR/2013/707 dated 06.09.2013

from SEIAA. EC Letter is attached as

Annexure - XXI.

IX Any appeal against this Environmental

Clearance shall lie with the National

Agreed.

22

Green Tribunal, if preferred within a

period of 30 days as prescribed under

Section 16 of the National Green

Tribunal Act, 2010.

X The project proponent shall put in place

Corporate Environment Policy as

mentioned in MOEF, GOI, ON No. J-

11013/41/2006-IA II (I) dated 26.04.12

within 3 months period. Latest Corporate

Environment Policy should be submitted

to SEIAA within 3 months of issuance of

this letter.

Agreed. CESR Plan is attached as Annexure

– XXII.

XI The fund ear-marked for environment

protection measures should be kept in

separate account and should not be

diverted for other purposes and year wise

expenditure shall be reported to the

SEIAA/RO MoEF GOI under rules

prescribed for Environment Audit.

Agreed. The fund ear-marked for

environment protection measures will be

kept in separate account and will not be

diverted for other purposes and year wise

expenditure will be reported to the

SEIAA/RO MoEF GOI under rules

prescribed for Environment Audit.

XII The PP shall ensure the compliance of

Forest Department, Haryana Notification

no. S.O.121/PA2/1900/S.4/97 dated

28.11.1997.

Agreed. The compliance of Forest

Department, Haryana Notification no.

S.O.121/PA2/1900/S.4/97 dated 28.11.1997

will be done.

XIII The project proponent shall ensure that

no vehicle during construction/operation

phase enter the project premises without

valid ‘Pollution Under Control’

certificate from competent Authority.

Agreed. It will be ensured that no vehicle

during construction/operation phase enter

the project premises without valid ‘Pollution

Under Control’ certificate from competent

Authority.

XIV The PP is responsible for compliance of

all conditions in Environmental

Clearance letter and project proponent

Agreed.

23

can not absolve himself/herself of the

responsibility by shifting it to any

contractor engaged by project proponent.

XV The Project proponent shall seek fresh

Environmental Clearance if at any stage

there is change in the planning of the

proposed project.

Agreed.

(B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE MANUAL 2010 OF MoEF

SI.

No.Points as per EIA Guidance Manual Status of Compliance

A. Air Environment

1. Wind erosion is a serious problem in

areas where the ground is virtually bare

and devoid of vegetation. Vegetation

methods are found to be most effective in

the form of windbreaks and shelterbelts.

The site will be enclosed with sufficiently

high barricade wall around the project

boundary which will act as a wind breaker.

Vegetation will be developed during the

operation phase of the project.

2. Sprinkling of water and fine spray from

nozzles to suppress the dust.

Water sprinkling will be carried out through

tanker water regularly at site for dust

suppression and logbook will be maintained.

3. On-Road-Inspection should be done for

black smoke generating machinery.

All the machineries deployed at site will be

of good standard and of reputed make and

comply with emission & noise standards.

Inspections and maintenance of construction

machineries and vehicles will be carried out

periodically.

24

SI.

No.Points as per EIA Guidance Manual Status of Compliance

4. Promotion of use of cleaner fuel should

be done.

Ultra low sulphur diesel (ULSD) (sulphur

content less than 50 ppm) will be used for

running of DG sets, vehicles and

construction machineries.

5. All DG sets should comply emission

norms notified by MoEF.

The DG sets will be acoustically enclosed

which will conform to the permissible air

emission and noise standards notified by

MoEF&CC. DG sets will be fitted with stack

of sufficient height as prescribed in emission

norms notified by MoEF&CC. Monitoring of

emissions of DG sets will be carried out

periodically.

6. Vehicles having pollution under control

certificate may be allowed to ply.

Only PUC certified vehicles will be allowed

to enter the project site. The vehicles without

valid Pollution under Check (PUC)

certificate will not be permitted at the project

site.

7. Use of covering sheet to prevent dust

dispersion at buildings and infrastructure

sites, which are being constructed.

Sheets will be used to prevent dust

dispersion.

8. Use of covering sheets should be done for

trucks to prevent dust dispersion from the

trucks, implemented by district offices.

The trucks carrying construction materials

and debris will be covered by tarpaulin and

plastic sheets.

25

SI.

No.Points as per EIA Guidance Manual Status of Compliance

9. Paving is a more permanent solution to

dust control, suitable for longer duration

projects. High cost is the major drawback

to paving.

During construction, access roads will be

covered with gravels to prevent dust

emission.

(At the completion stage of the project, all

permanent internal roads & walkway will be

paved and greeneries will be developed).

10. Reducing the speed of a vehicle to 20

kmph can reduce emissions by a large

extent. Speed bumps are commonly used

to ensure speed reduction. In cases where

speed reduction cannot effectively reduce

fugitive dust, it may be necessary to

divert traffic to nearby paved areas.

Speed of the vehicles will be restricted by

erecting speed bumps at regular intervals at

project site and proper signage will be

provided for guided vehicular movement and

speed restrictions.

11. Material storages/ warehouses-Care

should be taken to keep all material

storages adequately covered and

contained so that they are not exposed to

situations where winds on site could lead

to dust/ particulate emissions. Fabrics and

plastics for covering piles of soils and

debris is an effective means to reduce

fugitive dust.

Ready-mixed concrete will be used for

construction of project site which will be

transported from the off-site batching plant.

B. Noise Environment

26

SI.

No.Points as per EIA Guidance Manual Status of Compliance

1. Setting up the barriers: National Building

Code 2005 suggests that design solutions

such as barrier blocks should be used to

reduce external LA10 noise levels to at

least 60-70dB(A) at any point 1.0 m from

any inward looking façade.

The site will be enclosed with sufficiently

high barricade wall around the project

boundary to control propagation.

The DG sets will be installed in acoustic

enclosure which conforms to the permissible

noise standards notified by MOEF. DG sets

are new and certified by manufacturers.

C. Water Environment

1. Curing water should be sprayed on

concrete structures; free flow of water

should not be allowed for curing.

Curing water will be sprayed on concrete

structures.

2. After liberal curing on the first day, all

concrete structures should be painted

with curing chemical to save water. This

will stop daily water curing hence save

water.

Curing compounds will be used to save

water for curing.

3. Concrete structures should be covered

with thick cloth/gunny bags and then

water should be sprayed on them. This

would avoid water rebound and will

ensure sustained and complete curing.

Concrete structures will be covered with

thick clothes/ gunny bags and water spraying

will be taken into practice to prevent water

loss.

4. Ponds should be made using cement and

sand mortar to avoid water flowing away

from the flat surface while curing

No water will be used for curing hence,

ponds will not be proposed in the site.

5. Water ponding should be done on all

sunken slabs; this would also highlight

the importance of having an impervious

formwork.

No water will be used for curing.

27

(C) COMPLIANCE TO NGT ORDER DATED 10.04.2015 RELATED TO CONSTRUCTION

SI.

No.NGT Order dated 10.04.2015 Status of Compliance

1. Every builder or owner shall put tarpaulin on

scaffolding around the area of construction

and the building. No person including

builder, owner can be permitted to store any

construction material particularly sand on

any part of the street, roads in any colony.

Tarpaulin covers will be provided around the

area of construction wherever required. No

construction materials such as cement, sand and

aggregates will be stored at site. Ready-mixed

concrete will be used for concrete work at

project site which will be transported from the

off-site batching plant.

2. The construction material of any kind that is

stored in the site will be fully covered in all

respects so that it does not disperse in the Air

in any form.

Tarpaulin covers will be provided around the

area of construction wherever required. No

construction materials such as cement, sand and

aggregates will be stored at site. Ready-mixed

concrete will be used for concrete work at

project site which will be transported from the

off-site batching plant.

3. All the construction material and debris shall

be carried in the trucks or other vehicles

which are fully covered and protected so as

to ensure that the construction debris or the

construction material does not get dispersed

into the air or atmosphere, in any form

whatsoever.

The trucks carrying construction materials and

debris will be covered by tarpaulin and plastic

sheets.

28

SI.

No.NGT Order dated 10.04.2015 Status of Compliance

4. The dust emissions from the construction site

should be completely controlled and all

precautions taken in that behalf.

All necessary precautions will be adopted to

control the dust emissions. Water sprinkling at

site will be carried out through tanker water

regularly at site for dust suppression and

logbook will be maintained.

5. The vehicles carrying construction material

and construction debris of any kind should be

cleaned before it is permitted to ply on the

road after unloading of such material.

“Wheel Washing Bay” will be provided at main

entry road and Batching Plant sites. Wheels of

constructions equipments/ vehicles and trucks

will be washed before it will be permitted to ply

on the road.

6. Every worker working on the construction

site and involved in loading, unloading and

carriage of construction material and

construction debris shall be provided with

mask to prevent inhalation of dust particles.

All safety measures will be taken. Construction

workers will be provided with personal

protective equipment (PPE) as required under

the health & safety norms.

7. Every owner and or builder shall be under

obligation to provide all medical help,

investigation and treatment to the workers

involved in the construction of building and

carry of construction material and debris

relatable to dust emission.

Fully fledged first aid facility will be provided

at the construction site and regular medical

check-ups by Doctor will be conducted for

construction workers. Logbook will be

maintained with medical treatment details of the

workers.

8. It shall be the responsibility of every builder

to transport construction material and debris

waste to construction site, dumping site or

any other place in accordance with rules and

in terms of this order.

No work has been started; therefore there is no

generation of construction debris. When debris

will be generated, it will be disposed off at

Government Authorized landfills.

29

SI.

No.NGT Order dated 10.04.2015 Status of Compliance

9. All to take appropriate measures and to

ensure that the terms and conditions of the

earlier order and these orders should strictly

comply with by fixing sprinklers, creations

of green air barriers.

Regular sprinkling of water will be carried out

at site through tanker.

10. Compulsory use of wet jet in grinding and

stone cutting.

All necessary precautions will be taken in the

stone cutting and grinding area which will be

done at later stage of construction.

11. Wind breaking walls around construction

site.

The site will be enclosed with sufficiently high

barricade wall around the project boundary

which acts as a wind breaker.

12. All the builders who are building

commercial, residential complexes which are

covered under the EIA Notification of 2006

shall provide green belt around the building

that they construct. All Authorities shall

ensure that such green belts are in existence

prior to issuance of occupancy certificate.

Green area will be developed at the end of

construction stage as per approved building

plan.

30