Upload
trinhxuyen
View
215
Download
1
Embed Size (px)
Citation preview
HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE Ref. LETTER NO. SEIAA/HR/2014/923 DATED 11.07.2014 for CONSTRUCTION OF
GROUP HOUSING COLONY LOCATED AT SECTOR-104, VILLAGE-DHAWANPUR , GURGAON, HARYANA By M/s JUVENTUS ESTATE LTD.
Sl. No. Conditions Status of Compliance
PART A - SPECIFIC CONDITIONS:CONSTRUCTION PHASE:
1 “Consent to Establish” shall be obtained
from Haryana State Pollution Control
Board under Air and Water act and a
copy shall be submitted to the SEIAA
Haryana before the start of any
construction work at the site.
Agreed. “Consent to Establish” has been
obtained from Haryana State Pollution
Control Board. A Copy of CTE is attached
as Annexure-I.
2 A First Aid room as proposed in the
project report will be provided in both
during construction and operation of the
project.
Agreed. A First Aid room will be provided
during the construction phase as well as in
the operational phase of the project.
3 Adequate drinking water and sanitary
facilities shall be provided for
construction workers at the site.
Provision should be made for the mobile
toilets. Open defecation by the laborers is
strictly prohibited. The safe disposal of
waste water and solid wastes generated
during the construction phase should be
ensured.
Agreed. Adequate facility of safe drinking
water will be provided on the site. As
mostly local laborers will be hired for the
construction phase, thus a negligible
quantity of waste will be generated.
Inorganic waste will be segregated and
recyclable waste is sold off to government
approved vendors. Mobile toilets will be
provided nonetheless and the waste water
generated will be sent to septic tanks. Solid
waste generated during construction will be
managed properly as per MSW Rules, 2000.
4 All the top soil excavated during
construction activities should be stored
for use in horticulture/landscape
Agreed. The excavated material will be used
for leveling, refilling and in horticulture/
landscape development within the project
1
development within the project site. site & surplus will be disposed off outside
the premises with prior consent of
department.
5 The project proponent shall ensure that
the building material required during
construction phase is properly stored
within the project area and disposal of
construction waste should not create any
adverse effect on the neighboring
communities and should be disposed off
after taking the necessary precautions for
general safety and health aspects of
people, only in approved sites with the
approval of competent authority.
Agreed. M/s Juventus Estate Ltd. will
ensure that the building material required
during construction phase will be properly
stored within the project area and disposal
of construction waste will not create any
adverse effect on the neighboring
communities and will be disposed off after
taking the necessary precautions for general
safety and health aspects of people, only in
approved sites with the approval of
competent authority.
6 Construction spoils, including
bituminous material and other hazardous
materials, must not be allowed to
contaminate watercourses and the dump
sites for such material must be secured so
that they should not leach into the ground
water and any hazardous waste generated
during construction phase, should be
disposed off as per applicable rules and
norms with necessary approval of the
Haryana State Pollution Control Board.
Agreed. Construction spoils including
bituminous material and other hazardous
material will not be allowed to contaminate
water courses. No dumping of such
materials will be allowed at project site.
Waste lubricating oil generated from
maintenance of DG sets falls under
hazardous waste category. Such wastes will
be disposed off with the help of Waste
recycler with necessary approval from
Haryana State Pollution Control Board.
7 The Diesel generator sets to be used
during construction phase should be of
ultra-low sulphur diesel type and should
conform to Environment (Protection)
Rules prescribed for air and noise
emission standards.
Agreed. Ultra-low sulphur diesel will be
used to run the Diesel generator sets to be
used during construction phase with
Provisions of Air and Noise Emissions
Standards as per EPA Rules 1986.
2
8 The diesel required for operating DG sets
shall be stored in underground tanks and
if required, clearance from Chief
Controller of Explosives shall be taken.
Agreed. Used oil from DG sets will be
stored in HDPE drums in isolated covered
facility. This used oil will be sold to
authorized recyclers. Suitable care will be
taken to avoid spills/leaks of used oil from
storage. Separate log books will be
maintained for accountability.
9 Ambient noise levels should conform to
residential standards both during day and
night. Incremental pollution loads on the
ambient air and noise quality should be
closely monitored during construction
phase. Adequate measures should be
taken to reduce ambient air and noise
level during construction phase, so as to
conform to the stipulated residential
standards.
Agreed. Incremental pollution loads on the
ambient air and noise quality are being
closely monitored. Laboratory Reports of
the environmental monitoring of air, noise
and soil carried out at the site are enclosed
as Annexure II.
Similarly, Ambient air quality is also closely
monitored so as to conform to the stipulated
standards.
10 Fly ash should be used as building
material in the construction as per the
provisions of Fly Ash Notification of
September, 1999 and amended as on 27th
August, 2003.
Agreed. Fly ash bricks will be used as
building material in the construction as per
the provisions of Fly Ash Notification of
September, 1999 and amended as on 27th
August, 2003.
11 Storm water control and its re use as per
CGWB and BIS standards for various
applications should be ensured.
Agreed. Storm water control and its re use
(for various applications) will be ensured as
per BIS and Central Ground Water Board
(CGWB) standards.
12 Water demand during construction
should be reduced by use of pre-mixed
concrete, curing agents and other best
practices.
Agreed. Water demand during construction
will be reduced by the practice of using pre-
mixed concrete, curing agents and other best
practices.
13 In view of the severe constrains in water Agreed. Project site falls within planned
3
supply augmentation in the region and
sustainability of water resources, the
developer will submit the NOC from
CGWA specifying water extraction
quantities and assurance from HUDA
/utility provider indicating source of
water supply and quantity of water with
details of intended use of water – potable
and non-potable. Assurance is required
for both construction and operation
stages separately. It shall be submitted to
the SEIAA and RO, MOEF, Chandigarh
before the start of construction.
Sector of Gurgaon Manesar Urban Complex
2021, which shall be facilitated with HUDA
water supply scheme for which EDC/IDC
are being paid. Ground water will not be
extracted for the purpose of construction as
well as for operation phase of the project.
Assurance from HUDA for the water supply
during construction & operational phase are
enclosed as Annexure-III (a) & (b)
respectively.
14 Roof should meet prescriptive
requirement as per Energy Conservation
Building Code by using appropriate
thermal insulation material.
Agreed. Roof will be constructed as per
energy conservation building code by using
appropriate thermal insulation material.
15 Opaque wall should meet prescriptive
requirement as per Energy Conservation
Building Code which is proposed to be
mandatory for all air conditioned spaces
while it is desirable for non-air-
conditioned spaces by use of appropriate
thermal insulation material to fulfill
requirement.
Agreed. Opaque wall will meet prescribed
requirement as per Energy Conservation
Building Code (ECBC).
16 The approval of the competent authority
shall be obtained for structural safety of
the building on account of earthquake,
adequacy of firefighting equipment’s,
etc. as per National Building Code
including protection measures from
Agreed. The approval of the competent
authority will be obtained in due course of
time for structural safety of the buildings
due to earthquake, adequacy of firefighting
equipment, etc. as per National Building
Code including protection measure from
4
lightening etc. If any forest land is
involved in the proposed site, clearance
under The Forest Conservation Act shall
be taken from the competent Authority.
lightening etc. No forest land is involved in
the project site. NOC from Forest
Department has been obtained from Dy.
Conservator of Forest, Gurgaon vide letter
No. 4054-G and copy of the same is
enclosed as Annexure IV.
17 Overexploited ground water and
impending severe shortage of water
supply in the region requires the
developer to redraw the water and energy
conservation plan. Developer shall
reduce the overall footprint of the
proposed development. Project
proponent shall incorporate water
efficiency/savings measures as well as
water reuse/recycling within 3 months
and before start of construction to the
SEIAA, Haryana and RO, MOEF, GOI,
Chandigarh.
Agreed. No ground water extraction will
take place without permission from CGWA.
However, treated water will be supplied by
HUDA will be used for construction. To
reduce the demand in operational phase,
treated water from STP will be used for
horticulture; flushing as well as efficient
fixtures will be used to minimize the fresh
water demand.
18 The project proponent as stated in the
proposal shall construct 29 rain water
harvesting pits for recharging the ground
water within the project premises. Rain
water harvesting pits shall be designed to
make provisions for silting chamber and
removal of floating matter before
entering harvesting pit. Maintenance
budget and persons responsible for
maintenance must be provided. Care
shall be taken that contaminated water do
not enter any RWH pit.
Agreed. 29 number of RWH pits will be
constructed to harvest rain water. Rain water
harvesting pits will be designed in such a
way that the silt and floating matter will be
removed before entering into the pit.
Maintenance budget and experienced
persons for maintenance of the pits will be
provided. It will be taken care that
contaminated water do not enter any RWH
pit. Storm Water Plan showing location of
RWH pits is enclosed as Annexure V.
5
19 The project proponent shall provide for
adequate fire safety measures and
equipment’s as required by Haryana Fire
Service Act, 2009 and instructions issued
by the local authority/Directorate of fire
from time to time. Further the project
proponent shall take necessary
permission regarding fire safety
scheme/NOC from competent Authority
as required.
Agreed. M/s Juventus Estate Ltd. will
provide adequate Fire Safety measures and
equipments as required by Haryana Fire
Service Act, 2009 and local Authority/
Directorate of fire from time to time. Further
the project proponent will take necessary
permission regarding fire safety scheme/
NOC from competent authority as required.
20. The project proponent shall obtain
assurance from the DHBVN for supply
of 13235 KVA of power supply before
the start of construction. In no case
project will be operational solely on
generators without any power supply
from any external power utility.
Agreed. The project proponent will obtain
assurance from the DHBVN for supply of
13235 KVA of power supply before the start
of construction or else project will be
operational solely on generators without any
power supply from any external power
utility. An application has been filed to
HVPNL and acknowledgment copy of the
same is enclosed as Annexure VI.
21 Detail calculation of power load and
ultimate power load of the project shall
be submitted to DHBVN under
intimation to SEIAA Haryana before the
start of construction. Provision shall be
made for electrical infrastructure in the
project area.
Agreed. Total power requirement is 13235
kVA Calculation of power load is enclosed
as Annexure-VII.
22 The Project proponent shall not raise any
construction in the natural land
depression/Nallah/ Water course and
shall ensure that the natural flow from
the Nallah/ Water course is not
There is no natural land depression/Nallah/
water course passing through the project
site.
6
obstructed.
23 The project proponent shall keep the
plinth level of the building blocks
sufficiently above the level of the
approach road to the Project as per
prescribed bye-laws. Levels of the other
areas in the Projects shall also be kept
suitably so as to avoid flooding.
Agreed. The plinth level of the building
blocks will be kept sufficiently above the
level of the approach road to the project as
per prescribed bye laws. Levels of the other
areas in the projects will also be kept
suitably so as to avoid flooding.
24 Construction shall be carried out so that
density of population does not exceed
norms approved by Director General
Town and Country Department Haryana.
Agreed. Construction will be carried out so
that density of population does not exceed
norms approved by Director General Town
and Country Planning Department, Haryana.
25 The Project proponent shall submit an
affidavit with the declaration that ground
water will not be used for construction
and only treated water should be used for
construction.
Agreed. Ground water will not be used for
the construction activity and an affidavit for
this has already been submitted to SEIAA,
Haryana at the time of Environmental
Clearance. Only treated water will be used
for construction from HUDA.
26 The project proponent shall not cut any
existing tree and project landscaping plan
should be modified to include those trees
in green area.
Agreed. There is no need to cut the trees,
only small bushes clearing will be required
for construction activity.
27 The project proponent shall provide 3
meter high barricade around the project
area, dust screen for every floor above
the ground, proper sprinkling and
covering of stored material to restrict
dust and air pollution during
construction.
Agreed. The project proponent will provide
3 meter high barricade around the project
area, dust screen for every floor above the
ground, proper sprinkling and covering of
stored material to restrict dust and air
pollution during construction.
28 The project proponent shall construct a
sedimentation basin in the lower level of
Agreed. Sedimentation basin will be
constructed in the lower level of the project
7
the project site to trap pollutant and other
wastes during rains.
site to trap pollutant and other wastes during
rains.
29 The Project Proponent shall provide
proper Rasta of proper width and proper
strength for each project before the start
of construction.
Agreed. Proper Rasta of proper width and
proper strength for this project will be
provided before the start of construction.
30 The Project Proponent shall ensure that
the U-value of the glass is less than 3.177
and maximum solar heat gain co-
efficient is 0.25 for vertical fenestration.
Agreed. It will be ensured that the U-value
of the glass will be less than 3.177 and
maximum solar heat gain co-efficient 0.25
for vertical fenestration.
31 The project proponent shall adequately
control dusts like silica dust, non-silica
and wood dust. Such dust shall not
spread outside project proponent shall
provide respiratory protective equipment
to all construction workers.
Agreed. There will be adequate provision
for silica dust, non-silica and wood dust.
Such will not be spread outside. Also,
respiratory protective equipments will be
provided to all the construction workers.
32 The project proponent shall develop
complete civic infrastructure of the group
housing colony including internal roads,
green belt development, sewage line, rain
water recharge arrangements, storm
water drainage system, solid waste
management site and provision for
treatment of bio-degradable waste, STP,
water supply line, dual plumbing line,
dual plumbing line, electricity supply
lines etc. and shall offer possession of
the unit/flats thereafter.
Agreed. Complete civic infrastructure of the
group housing colony including internal
roads, green belt development, sewage line,
rain water recharge arrangements, storm
water drainage system, solid waste
management site and provision for treatment
of bio-degradable waste, STP, water supply
line, dual plumbing line, dual plumbing line,
electricity supply lines etc. will be
developed and shall offer possession of the
unit/flats thereafter. RWH Plan, SWM Plan,
dual plumbing plan, Electric layout Plan are
attached as Annexure-V, VIII, IX & X
respectively.
33 The project proponent shall provide one Agreed. There will be provision for one
8
refuge area till 24 meter, one till 39
meter and one after 15 meter each, as per
National Building Code. The project
proponent shall not convert any refuse
area in the habitable space and it should
not be sold out/commercialized.
refuge area till 24 meter, one till 39 meter
and one after 15 meter each, as per National
Building Code. The project proponent shall
not convert any refuse area in the habitable
space and it will not be sold
out/commercialized.
34 The project proponent shall provide fire
control room and fire officer for building
above 30 meter as per National Building
Code
Agreed. We will provide fire control room
and fire officer for building above 30 meter
as per National Building Code.
35 The project proponent shall obtain
permission of Mines and Geology
Department for excavation of soil before
the start of construction.
Agreed. Permission from mines and
Geology Department for excavation of soil
has been taken; copy of the same is enclosed
as Annexure-XI.
36 The project proponent shall seek specific
prior approval from concerned local
authority/HUDA regarding provision of
storm drainage and sewerage system
including their integration with external
services of HUDA/ Local authorities
beside other required services of
HUDA /Local authorities beside other
required services before taking up any
construction activity.
Agreed. The project proponent seek specific
prior approval from concerned local
authority/HUDA regarding provision of
storm drainage and sewerage system
including their integration with external
services of HUDA/ Local authorities beside
other required services of HUDA/Local
authorities beside other required services
before taking up any construction activity.
37 The site for solid waste management
plant be earmarked on the layout plan
and the detailed project for setting up the
solid waste management plant shall be
submitted to the authority within one
month.
Agreed. Solid waste management area has
been earmarked on the layout plan and the
detailed project for setting up the solid
waste management plant will be submitted
to the authority in due course of time.
38 The project proponent shall submit the Agreed. We will submit the copy of fire
9
copy of fire safety plan duly approved by
Fire Department before the start of
construction.
safety plan duly approved by Fire
Department in due course of time.
39 The project proponent shall discharge
excess of treated waste water/storm
water in the public drainage system and
shall seek permission of HUDA before
the start of construction.
The discharge from excess treated waste
water/storm water will not be discharged in
the public drainage system. Wastewater will
be used for nearby ongoing construction
activities
40 The project proponent shall maintain the
distance between STP and water supply
line.
Agreed. There will be adequate distance
between STP and water supply line to avoid
any contamination.
41 The project proponent shall ensure that
the stack height is 6 meter more than the
highest tower.
Agreed. The stack height will be 6 meter
more than the highest tower.
42 The project proponent shall ensure that
structural stability to withstand
earthquake of magnitude 8.5 on Richter
scale.
Agreed. There will be adequate structural
stability to withstand earthquake of
magnitude 8.5 on Richter scale.
43 The project proponent shall seek NOC
from Town and Country department
regarding height of the building allowed
in the skyline of that city.
Agreed. Height clearance from Airport
Authority of India (AAI) has been taken.
NOC from AAI is attached as Annexure-
XII.
44 The project proponent shall provide
helipad facility as required under NBC
norms and seek permission of helipad
from AAI accordingly.
Agreed. Helipad Facility will be provided as
required under NBC norms.
45 The project proponent shall ensure that
no construction activity is undertaken
either on surface or below or above
surface of revenue rasta passing through
the project area.
Agreed. No construction activity will be
undertaken either on surface or below or
above surface of revenue rasta passing
through the project area.
10
46 The project proponent shall indicate the
width and length of revenue rasta passing
through the project area on sign board
and shall display the same at both ends
of revenue rasta stretch, for awareness of
public. Sign board shall also display the
message that this is public rasta /road and
any citizen can use it. There shall not be
any gate with or without guards on
revenue rasta further project proponent
shall not encroach revenue rasta further
project proponent shall not encroach
revenue rasta and shall encroach revenue
rasta and shall not cross internal roads
over revenue rasta.
Agreed. Revenue rasta will not be
encroached and any internal roads will not
cross over them.
47 The project proponent shall ensure that
the plinth level of the building block to
be 1.5 meter above 100 years flood level
of the said Najafgarh Jheel.
Agreed. The plinth level of the building
block will be 1.5 meter above 100 years
flood level of the said Najafgarh Jheel.
48 The project proponent shall obtain NOC
from HUDA as well as Irrigation
Department before the start of
construction, regarding possible adverse
effect of project proposal on the
Najafgarh Jheel
Agreed. NOC from HUDA as well as
Irrigation Department will be taken before
the start of construction, regarding possible
adverse effect of project proposal on the
Najafgarh Jheel.
49 The project proponent shall provide
boosting arrangement and multistage
pumping with standby arrangement after
getting the same approved from HUDA.
Agreed. Adequate boosting arrangement and
multistage pumping will be provided with
standby arrangement after getting the same
approved from HUDA
50 The project proponent shall implement
green belt development plan as submitted
Agreed. Green belt development plan will
be implemented.
11
in the meeting on 26.06.2014 (additional
green area by replacing water bodies)
51 The project proponent shall implemented
the traffic circulation plan as submitted
in the meeting on 26.06.2014 (Bell
mouth entry and exit points on 24 meter
wide road and 15 meter wide internal
road)
Agreed. The traffic circulation plan as
submitted in the meeting on 26.06.2014
(Bell mouth entry and exit points on 24
meter wide road and 15 meter wide internal
road) will be implemented.
52 The Project proponent shall implement
the traffic circulation plan of basement as
submitted in the meeting of 26.06.2014
(connecting two separate lines of
basements below the towers at least at
two points along the length for
comfortable exit and entry of vehicles
and its occupants).
Agreed. The traffic circulation plan of
basement as submitted in the meeting of
26.06.2014 (connecting two separate lines
of basements below the towers at least at
two points along the length for comfortable
exit and entry of vehicles and its occupants)
will be implemented.
PART A- SPECIFIC CONDITIONS : Operation Phase
a “Consent to Operate” shall be obtained
from Haryana State Pollution Control
Board under Air and Water Act and a
copy shall be submitted to the SEIAA,
Haryana.
Agreed. “Consent to Operate” will be
obtained from Haryana State Pollution
Control Board under Air and Water Act and
a copy will be submitted to the SEIAA,
Haryana.
b The STP shall be installed for the
treatment of the sewage to the prescribed
standards including odor and treated
effluent will be recycled. The installation
of STP should be certified by an
independent expert and a report in this
regard should be submitted to the
SEIAA, Haryana before the project is
commissioned for operation. Tertiary
Agreed. The STP will be installed for the
treatment of the sewage to the prescribed
standards including odor and treated effluent
will be recycled. The installation of STP
will be certified by an independent expert
and a report in this regard will be submitted
to the SEIAA, Haryana before the project is
commissioned for operation. Tertiary
treatment of waste water is mandatory.
12
treatment of waste water is mandatory.
Discharge of treated sewage shall
confirm to norms and standards of
HSPCB, Panchkula. Project Proponent
shall implement such STP technology
which does not require filter backwash.
Discharge of treated sewage shall confirm to
norms and standards of HSPCB, Panchkula.
STP technology which does not require
filter backwash will be implemented. Dual
Plumbing plan showing the STP location is
enclosed as Annexure-IX and STP
schematic design is enclosed as Annexure
XIII.
c Separation of the grey and black water
should be done by the use of dual
plumbing line. Treatment of 100% grey
water by decentralized treatment should
be done ensuring that the re-circulated
water should have BOD level less than
10mg/litre and the recycled water will be
used for flushing, gardening and DG set
cooling and running of fountain in the
water body to achieve zero exit discharge
Separation of the grey and black water will
be done by the use of dual plumbing line.
Treatment of 100% grey water by
decentralized treatment will be done
ensuring that the re-circulated water will
have BOD level less than 10mg/litre and the
recycled water will be reused for flushing,
gardening, DG set cooling and other
recreational purposes to achieve zero exit
discharge. Water Balance Diagram showing
Zero Discharge is enclosed as Annexure-
XIV.
d For disinfection of the treated waste
water Ultra violet radiation or
ozonization process should be used.
Agreed. For disinfection of the treated
wastewater, UV Disinfection process will be
used (Refer Annexure XIII).
e Diesel power generating sets proposed as
source of back-up power for lifts,
common area illumination and for
domestic use should be enclosed type
and conform to rules made under the
Environmental (Protection) Act, 1986.
The location of the DG sets should be in
the basement as promised by the project
Agreed. Diesel power generating sets
proposed as source of back-up power for
lifts, common area illumination and for
domestic use will be of enclosed type and
will conform to the rules made under the
Environmental (Protection) Act, 1986. The
location of the DG sets will be in the
basement as promised with appropriate
13
proponent with appropriate stack height
i.e. above the roof level as per the CPCB
norms. The diesel used for DG sets
should be ultra-low sulphur diesel (35
ppm sulphur) instead of low sulphur
diesel.
stack height i.e. above the roof level as per
the CPCB norms. The diesel used for DG
sets will be ultra-low sulphur diesel (35 ppm
sulphur) instead of low sulphur diesel.
f Ambient noise level should be controlled
to ensure that it does not exceed the
prescribed standards both within and at
the boundary of the proposed Group
Housing Project.
Agreed. Ambient noise level will be
controlled within and at the boundaries of
the project ensuring compliance to
regulatory norms that is in accordance to
Schedule-III of The Noise Pollution
(Regulation and Control) Rules, 2000. This
could be attained through:
1) Development and maintenance of at
least 20% of the total land area for
tree plantation all around the project.
2) Providing acoustic enclosures to DG
sets.
3) Better traffic management.
4) Regular surveillance monitoring.
g The project proponent as stated in the
proposal should maintain at least 30.79%
as green cover area for tree plantation
especially all around the periphery of the
project and on the road sides preferably
with local species so as to provide
protection against noise and suspended
particulate matter. The open spaces
inside the project should be preferably
landscaped and covered with
vegetation/grass, herbs & shrubs. Only
Agreed. 30.79% of the total project area will
be maintained as used for tree plantation all
around the periphery and the road sides.
Species shall be endemic and chosen to
provide protection from dust and noise. In
addition, open spaces within the boundaries
shall be landscaped whenever possible and
to the maximum extent. Landscape Plan is
enclosed as Annexure XV.
14
locally available plant species shall be
used.
h The project proponent shall strive to
minimize water in irrigation of landscape
by minimizing grass area, using native
variety, xeriscaping and mulching,
utilizing efficient irrigation system,
scheduling irrigation only after checking
evapo-transpiration data.
Agreed. Minimum water in irrigation of
landscape by minimizing grass area will be
strived, using native variety, xeriscaping and
mulching, utilizing efficient irrigation
system, scheduling irrigation only after
checking evapo-transpiration data.
i Rain water harvesting for roof run-off
and surface, as per plan submitted should
be implemented. Before recharging the
surface run-off, pre-treatment through
sedimentation tanks must be done to
remove suspended matter, oil and grease.
The bore well for rainwater recharging
should be kept at least 5m. Above the
highest ground water table. Care shall be
taken that contaminated water do not
enter any RWH pit. The project
proponent shall avoid RWH of first 10
minutes of rain fall. Roof top of the
building shall be without any toxic
material or paint which can contaminate
rain water. Wire mess and filters should
be used wherever required.
Agreed. Rain water harvesting for roof run-
off and surface, as per plan submitted will
be implemented. Before recharging the
surface run-off, pre-treatment through
sedimentation tanks will be done to remove
suspended matter, oil and grease. The bore
well for rainwater recharging will be kept
atleast 5 m above the highest ground water
table. Rain water harvesting plan is enclosed
as Annexure V.
j The ground water level and its quality
should be monitored regularly in
consultation with Central Ground Water
Authority.
Agreed. The ground water level and its
quality will be monitored regularly in
consultation with Central Ground Water
Authority.
k A report on the energy conservation Agreed. Report on energy conservation
15
norms finalized by Bureau of energy
efficiency should be prepared
incorporating details about building
material & technology, R & U Factors
etc and submitted to the SEIAA, Haryana
in three month time.
measures conforming to energy
conservation norms finalized by BEE will
be submitted in due course of time. Energy
conservation measures are enclosed as
Annexure XVII.
l Energy conservation measures like
installation of LED for lighting the-areas
outside the building should be integral
part of the project design and should be
in place before project commissioning.
Use of solar panels must be adapted to
the maximum energy conservation.
Agreed. Energy conservation measures like
installation of LED for lighting the areas
outside the building will be integral part of
the project design and will be in place
before project commissioning. Solar panels
will be adapted for the maximum energy
conservation.
m The project proponent shall use zero
ozone depleting potential material in
insulation, refrigeration, air-conditioning
and adhesive. Project proponent shall
also provide Halon free fire suppression
system.
Agreed. Zero ozone depleting potential
material in insulation, refrigeration, air-
conditioning and adhesive will be used.
Halon free fire suppression will be provided.
n The solid waste generated should be
properly collected and segregated as per
the requirement of the MSW Rules, 2000
and as amended from time to time. The
bio-degradable waste should be
composed by vermin-composting at the
site war marked within the project area
and dry/inert solid waste should be
disposed-off to the approved sites for
land-filling after recovering material.
Agreed. The solid waste generated will be
properly collected and segregated as per the
requirement of the MSW Rules, 2000. The
bio-degradable waste will be composed by
the use of organic waste converter
composting at the site marked within the
project area and dry/inert solid waste will be
disposed-off to the approved sites for land-
filling after recovering material. Solid Waste
Management plan is enclosed as Annexure-
VIII.
o Provision of the solar water heating Agreed. The provision of the solar water
16
systems shall be as per norms specified
by HAREDA & shall be made
operational in each building block
heating system will be as per the norms
specified by HAREDA and will be made
operational in each building block.
p The traffic plan and the parking plan
proposed by the project proponent should
be adhere to meticulously with further
scope of additional parking for future
requirement. There should be no traffic
congestion near the entry and exit points
from the roads adjoining the proposed
project site. Parking should be fully
internalized and no public space should
be used.
Agreed. Proposed parking plan will be
adhering to meticulously with further scope
of additional parking for future requirement.
There will be no traffic congestion near the
entry and exit points from the roads
adjoining the project site. Parking will be
fully internalized and no public space should
be used. Parking plans are enclosed as
Annexure XVII.
q The Project shall be operationalized only
when HUDA/local authority will provide
domestic water supply system in the
area.
Agreed. The Project will be operationalized
only when HUDA/local authority will
provide domestic water supply system in the
area.
r Operation and maintenance of STP, solid
waste management and electrical
Infrastructure, pollution control measures
shall be ensured even after the
completion of project..
Agreed. Operation and maintenance of STP,
solid waste management and electrical
Infrastructure, pollution control measures
will be ensured even after the completion of
sale.
s Different type of waste should be
disposed-off as per provisions of
municipal solid waste, biomedical waste,
hazardous waste, e-waste, batteries &
plastic rules made under Environment
Protection Act, 1986. Particularly E-
Waste and Battery waste shall be
disposed of as per existing E-waste
Management Rules 2011 and Batteries
Agreed. Different type of waste will be
disposed off as per provisions of municipal
solid waste, biomedical waste, hazardous
waste, e-waste, batteries & plastic rules
made under Environment Protection Act,
1986. Particularly E-Waste and Battery
waste will be disposed of as per existing E-
waste Management Rules, 2011 and
Batteries Management Rules, 2001.
17
Management Rules 2001. The project
proponent should maintain a collection
center for E-Waste and it should be
disposed of to only registered and
authorized dismantler/recycler.
Collection center for E-Waste will be
maintained and it will be disposed of to only
registered and authorized dismantler/
recycler.
t Standards for discharge of environmental
pollutants as enshrined in various
schedules of rules 3 of Environment
Protection Rules 1986 shall be strictly
complied with.
Agreed. Standards for discharge of
environmental pollutants as enshrined in
various schedules of rules 3 of Environment
Protection Rules, 1986 will be strictly
complied with.
u Water supply shall be metered to
different residential units and different
utilities.
Agreed. Water supply will be metered to
different residential units and different
utilities.
v The project proponent shall ensure that
the stack height of DG sets is as per the
CPCB guide lines and also ensure that
the emission standards of noise and air
are within the CPCB prescribed limits.
Noise and Emission level of DG sets are
greater than 800 KVA shall be as per
CBCB latest standards for high capacity
DG sets.
Agreed. It will be ensured that the stack
height of DG sets is as per the CPCB guide
lines and also that the emission standards of
noise and air are within the CPCB
prescribed limits. Noise and Emission level
of DG sets greater than 800 KVA will be
maintained as per CBCB latest standards for
high capacity DG sets.
w All electric supply exceeding 100amp, 3-
phase shall maintain the power factor
between 0.98 lag to 1 at the point of
connection.
Agreed. All electric supply exceeding
100amp, 3-phase will maintain the power
factor between 0.98 lag to 1 at the point of
connection.
x The project proponent shall use only
treated water instead of fresh water for
HVAC and DG cooling. The project
proponent shall use evaporative cooling
technology and double stage cooling
Agreed. It will be ensured that treated water
instead of fresh water for HVAC and DG
cooling will be used. Evaporative cooling
technology and double stage cooling system
for HVAC will be used in order to reduce
18
system for HVAC in order to reduce
water consumption. Further temperature,
relative humidity during summer and
winter session should be kept at optimal
level. Variable speed drive, best co-
efficient of performance, as well as
optimal integrated point load value and
minimum outside fresh air supply may
be resorted for conservation of power
and water. Coil type cooling DG sets
shall be used for saving cooling water
consumption for water cooled DG sets.
water consumption. Further temperature,
relative humidity during summer and winter
session will be kept at optimal level.
Variable speed drive, best co-efficient of
performance, as well as optimal integrated
point load value and minimum outside fresh
air supply will be resorted for conservation
of power and water.
y The PP shall ensure that the transformer
is constructed with high quality grain
oriented, low loss silicon steel and virgin
electrolyte grade copper. The PP shall
obtain manufacturer’s certificate also for
that.
Agreed. We will ensure that the transformer
constructed will be of high quality grain
oriented, low loss silicon steel and virgin
electrolyte grade copper and manufacturer’s
certificate will be obtained.
z The project proponent shall ensure that
the exit velocity from the stack should be
sufficiently high. Stack shall be designed
in such a way that there is no stack
down-wash under any meteorological
conditions.
Agreed. Exit velocity from the stack will be
sufficiently high. Stack will be designed in
such a way that there is no stack down-wash
under any meteorological conditions.
aa The project proponent shall provide
water sprinkling system in the project
area to suppress the dust in addition to
the already suggested mitigation
measures in the Air Environment
Chapter of EMP
Agreed. Water sprinkling system will be
provided.
ab The project proponent shall ensure Agreed. Ventilation in basement will be
19
proper Air Ventilation and light system
in the basement area for comfortable
living of human being and shall ensure
that number of Air changes per
hour/(ACH)in basement never falls
below 15.In case of emergency capacity
for increasing ACH to the extent of 30
must be provided by the project
proponent.
taken special care.
ac The project proponent shall ensure
drinking/ domestic water supply as per
prescribed standards till treated water
supply is made available by HUDA.
Agreed.
PART-B GENERAL CONDITION:
I The project proponent should ensure the
commitments made in Form-1, Form-1A,
EIA/EMP and other documents
submitted to the SEIAA for protection of
environment and proposed
environmental safeguards are complied
with in letter and spirit. In case of
contradiction between two or more
documents on any point, the most
environmentally friendly commitment on
the point shall be taken as commitment
by project proponent.
Agreed. It will be ensured that commitments
made in Form-1, Form-1A, EIA/EMP and
other documents submitted to the SEIAA for
protection of environment and proposed
environmental safeguards are complied with
in letter and spirit. In case of contradiction
between two or more documents on any
point, the most environmentally friendly
commitment on the point will be taken as
Priority.
II The project proponent shall also submit
six monthly compliance of the reports on
the status of compliance of the stipulated
EC conditions including result of
monitored data should be submitted to
Agreed. Six monthly monitoring reports are
being & will be submitted to the HSPCB
and Regional Office, MoEF, GOI, Northern
Region, Chandigarh and a copy to the
regulatory Authorities of Haryana.
20
the HSPCB and Regional Office, MoEF,
GOI, Northern Region, Chandigarh and a
copy to the regulatory Authority of
Haryana.
Acknowledgement copy of previous
submitted compliance report is enclosed as
Annexure XVIII.
III STP outlet after stabilization and stack
emission shall be monitored monthly.
Other environmental parameters and
green belt shall be monitored on
quarterly basis. After every 3 months, the
project proponent shall conduct
environmental audit and shall take
corrective measure, if required, without
delay.
Agreed. STP outlet after stabilization and
stack emission will be monitored monthly.
Other environmental parameters and green
belt will be monitored on quarterly basis.
After every 3 months, the project proponent
will conduct environmental audit and will
take corrective measure, if required, without
delay.
IV The SEIAA, Haryana reserves the right
to add additional safeguard measures
subsequently, if found necessary.
Environmental Clearance granted will be
revoked if it is found that false
information has been given for getting
approval of this project. SEIAA reserves
the right to revoke the clearance if
conditions stipulated are not
implemented to the satisfaction of
SEIAA/MOEF.
Agreed.
V The project proponent shall not violate
any judicial orders/ pronouncements
issued by the Court/ Tribunal.
Agreed.
VI All other statutory clearances such as the
approvals for storage of diesel from
Chief Controller of Explosives, Fire
Department, Civil Aviation Department,
Agreed. AAI NOC from Civil Aviation
Department for Height clearance and
Aravalli clearance from D.C. has already
been granted and are enclosed as Annexure
21
Forest Conservation Act, 1980 and
Wildlife (Protection) Act, 1972, Forest
Act, 1927, PLPA 1900 etc. shall be
obtained, as applicable by the project
proponents from the respective
authorities prior to construction of the
project.
– XII & XIX respectively. Forest NOC is
enclosed as Annexure IV.
VII The project proponent should inform the
public that the project has been accorded
Environment Clearance by the SEIAA
and copies of the clearance letter are
available with the Haryana State
Pollution Control Board & SEIAA. This
should be advertised within 7 days from
the date of issue of clearance letter at
least in two local newspapers that are
widely circulated in the region and the
copy of the same be forwarded to SEIAA
Haryana. A copy of Environment
Clearance collections shall also be put on
project proponent’s website for public
awareness.
Agreed. EC letter has been published in two
local newspapers; copy of the same is
enclosed as Annexure XX.
VIII Under the provisions of Environment
(Protection) Act, 1986, legal action shall
be initiated against the project proponent
if it was found that construction of the
project has been started without
obtaining Prior Environmental
Clearance.
Agreed. Environmental clearance has been
obtained vide letter no.
SEIAA/HR/2013/707 dated 06.09.2013
from SEIAA. EC Letter is attached as
Annexure - XXI.
IX Any appeal against this Environmental
Clearance shall lie with the National
Agreed.
22
Green Tribunal, if preferred within a
period of 30 days as prescribed under
Section 16 of the National Green
Tribunal Act, 2010.
X The project proponent shall put in place
Corporate Environment Policy as
mentioned in MOEF, GOI, ON No. J-
11013/41/2006-IA II (I) dated 26.04.12
within 3 months period. Latest Corporate
Environment Policy should be submitted
to SEIAA within 3 months of issuance of
this letter.
Agreed. CESR Plan is attached as Annexure
– XXII.
XI The fund ear-marked for environment
protection measures should be kept in
separate account and should not be
diverted for other purposes and year wise
expenditure shall be reported to the
SEIAA/RO MoEF GOI under rules
prescribed for Environment Audit.
Agreed. The fund ear-marked for
environment protection measures will be
kept in separate account and will not be
diverted for other purposes and year wise
expenditure will be reported to the
SEIAA/RO MoEF GOI under rules
prescribed for Environment Audit.
XII The PP shall ensure the compliance of
Forest Department, Haryana Notification
no. S.O.121/PA2/1900/S.4/97 dated
28.11.1997.
Agreed. The compliance of Forest
Department, Haryana Notification no.
S.O.121/PA2/1900/S.4/97 dated 28.11.1997
will be done.
XIII The project proponent shall ensure that
no vehicle during construction/operation
phase enter the project premises without
valid ‘Pollution Under Control’
certificate from competent Authority.
Agreed. It will be ensured that no vehicle
during construction/operation phase enter
the project premises without valid ‘Pollution
Under Control’ certificate from competent
Authority.
XIV The PP is responsible for compliance of
all conditions in Environmental
Clearance letter and project proponent
Agreed.
23
can not absolve himself/herself of the
responsibility by shifting it to any
contractor engaged by project proponent.
XV The Project proponent shall seek fresh
Environmental Clearance if at any stage
there is change in the planning of the
proposed project.
Agreed.
(B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE MANUAL 2010 OF MoEF
SI.
No.Points as per EIA Guidance Manual Status of Compliance
A. Air Environment
1. Wind erosion is a serious problem in
areas where the ground is virtually bare
and devoid of vegetation. Vegetation
methods are found to be most effective in
the form of windbreaks and shelterbelts.
The site will be enclosed with sufficiently
high barricade wall around the project
boundary which will act as a wind breaker.
Vegetation will be developed during the
operation phase of the project.
2. Sprinkling of water and fine spray from
nozzles to suppress the dust.
Water sprinkling will be carried out through
tanker water regularly at site for dust
suppression and logbook will be maintained.
3. On-Road-Inspection should be done for
black smoke generating machinery.
All the machineries deployed at site will be
of good standard and of reputed make and
comply with emission & noise standards.
Inspections and maintenance of construction
machineries and vehicles will be carried out
periodically.
24
SI.
No.Points as per EIA Guidance Manual Status of Compliance
4. Promotion of use of cleaner fuel should
be done.
Ultra low sulphur diesel (ULSD) (sulphur
content less than 50 ppm) will be used for
running of DG sets, vehicles and
construction machineries.
5. All DG sets should comply emission
norms notified by MoEF.
The DG sets will be acoustically enclosed
which will conform to the permissible air
emission and noise standards notified by
MoEF&CC. DG sets will be fitted with stack
of sufficient height as prescribed in emission
norms notified by MoEF&CC. Monitoring of
emissions of DG sets will be carried out
periodically.
6. Vehicles having pollution under control
certificate may be allowed to ply.
Only PUC certified vehicles will be allowed
to enter the project site. The vehicles without
valid Pollution under Check (PUC)
certificate will not be permitted at the project
site.
7. Use of covering sheet to prevent dust
dispersion at buildings and infrastructure
sites, which are being constructed.
Sheets will be used to prevent dust
dispersion.
8. Use of covering sheets should be done for
trucks to prevent dust dispersion from the
trucks, implemented by district offices.
The trucks carrying construction materials
and debris will be covered by tarpaulin and
plastic sheets.
25
SI.
No.Points as per EIA Guidance Manual Status of Compliance
9. Paving is a more permanent solution to
dust control, suitable for longer duration
projects. High cost is the major drawback
to paving.
During construction, access roads will be
covered with gravels to prevent dust
emission.
(At the completion stage of the project, all
permanent internal roads & walkway will be
paved and greeneries will be developed).
10. Reducing the speed of a vehicle to 20
kmph can reduce emissions by a large
extent. Speed bumps are commonly used
to ensure speed reduction. In cases where
speed reduction cannot effectively reduce
fugitive dust, it may be necessary to
divert traffic to nearby paved areas.
Speed of the vehicles will be restricted by
erecting speed bumps at regular intervals at
project site and proper signage will be
provided for guided vehicular movement and
speed restrictions.
11. Material storages/ warehouses-Care
should be taken to keep all material
storages adequately covered and
contained so that they are not exposed to
situations where winds on site could lead
to dust/ particulate emissions. Fabrics and
plastics for covering piles of soils and
debris is an effective means to reduce
fugitive dust.
Ready-mixed concrete will be used for
construction of project site which will be
transported from the off-site batching plant.
B. Noise Environment
26
SI.
No.Points as per EIA Guidance Manual Status of Compliance
1. Setting up the barriers: National Building
Code 2005 suggests that design solutions
such as barrier blocks should be used to
reduce external LA10 noise levels to at
least 60-70dB(A) at any point 1.0 m from
any inward looking façade.
The site will be enclosed with sufficiently
high barricade wall around the project
boundary to control propagation.
The DG sets will be installed in acoustic
enclosure which conforms to the permissible
noise standards notified by MOEF. DG sets
are new and certified by manufacturers.
C. Water Environment
1. Curing water should be sprayed on
concrete structures; free flow of water
should not be allowed for curing.
Curing water will be sprayed on concrete
structures.
2. After liberal curing on the first day, all
concrete structures should be painted
with curing chemical to save water. This
will stop daily water curing hence save
water.
Curing compounds will be used to save
water for curing.
3. Concrete structures should be covered
with thick cloth/gunny bags and then
water should be sprayed on them. This
would avoid water rebound and will
ensure sustained and complete curing.
Concrete structures will be covered with
thick clothes/ gunny bags and water spraying
will be taken into practice to prevent water
loss.
4. Ponds should be made using cement and
sand mortar to avoid water flowing away
from the flat surface while curing
No water will be used for curing hence,
ponds will not be proposed in the site.
5. Water ponding should be done on all
sunken slabs; this would also highlight
the importance of having an impervious
formwork.
No water will be used for curing.
27
(C) COMPLIANCE TO NGT ORDER DATED 10.04.2015 RELATED TO CONSTRUCTION
SI.
No.NGT Order dated 10.04.2015 Status of Compliance
1. Every builder or owner shall put tarpaulin on
scaffolding around the area of construction
and the building. No person including
builder, owner can be permitted to store any
construction material particularly sand on
any part of the street, roads in any colony.
Tarpaulin covers will be provided around the
area of construction wherever required. No
construction materials such as cement, sand and
aggregates will be stored at site. Ready-mixed
concrete will be used for concrete work at
project site which will be transported from the
off-site batching plant.
2. The construction material of any kind that is
stored in the site will be fully covered in all
respects so that it does not disperse in the Air
in any form.
Tarpaulin covers will be provided around the
area of construction wherever required. No
construction materials such as cement, sand and
aggregates will be stored at site. Ready-mixed
concrete will be used for concrete work at
project site which will be transported from the
off-site batching plant.
3. All the construction material and debris shall
be carried in the trucks or other vehicles
which are fully covered and protected so as
to ensure that the construction debris or the
construction material does not get dispersed
into the air or atmosphere, in any form
whatsoever.
The trucks carrying construction materials and
debris will be covered by tarpaulin and plastic
sheets.
28
SI.
No.NGT Order dated 10.04.2015 Status of Compliance
4. The dust emissions from the construction site
should be completely controlled and all
precautions taken in that behalf.
All necessary precautions will be adopted to
control the dust emissions. Water sprinkling at
site will be carried out through tanker water
regularly at site for dust suppression and
logbook will be maintained.
5. The vehicles carrying construction material
and construction debris of any kind should be
cleaned before it is permitted to ply on the
road after unloading of such material.
“Wheel Washing Bay” will be provided at main
entry road and Batching Plant sites. Wheels of
constructions equipments/ vehicles and trucks
will be washed before it will be permitted to ply
on the road.
6. Every worker working on the construction
site and involved in loading, unloading and
carriage of construction material and
construction debris shall be provided with
mask to prevent inhalation of dust particles.
All safety measures will be taken. Construction
workers will be provided with personal
protective equipment (PPE) as required under
the health & safety norms.
7. Every owner and or builder shall be under
obligation to provide all medical help,
investigation and treatment to the workers
involved in the construction of building and
carry of construction material and debris
relatable to dust emission.
Fully fledged first aid facility will be provided
at the construction site and regular medical
check-ups by Doctor will be conducted for
construction workers. Logbook will be
maintained with medical treatment details of the
workers.
8. It shall be the responsibility of every builder
to transport construction material and debris
waste to construction site, dumping site or
any other place in accordance with rules and
in terms of this order.
No work has been started; therefore there is no
generation of construction debris. When debris
will be generated, it will be disposed off at
Government Authorized landfills.
29
SI.
No.NGT Order dated 10.04.2015 Status of Compliance
9. All to take appropriate measures and to
ensure that the terms and conditions of the
earlier order and these orders should strictly
comply with by fixing sprinklers, creations
of green air barriers.
Regular sprinkling of water will be carried out
at site through tanker.
10. Compulsory use of wet jet in grinding and
stone cutting.
All necessary precautions will be taken in the
stone cutting and grinding area which will be
done at later stage of construction.
11. Wind breaking walls around construction
site.
The site will be enclosed with sufficiently high
barricade wall around the project boundary
which acts as a wind breaker.
12. All the builders who are building
commercial, residential complexes which are
covered under the EIA Notification of 2006
shall provide green belt around the building
that they construct. All Authorities shall
ensure that such green belts are in existence
prior to issuance of occupancy certificate.
Green area will be developed at the end of
construction stage as per approved building
plan.
30