49
EXPANSION OF GROUP HOUSING PROJECT “ILD GRAND” AT SECTOR 37 C, VILLAGE BASAI, GURGAON, HARYANA BY M/S JUBILIENT MALLS PVT. LTD. 1.0 HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE Ref. LETTER NO.SEIAA/HR/2013/707 DATED 06.09.2013. SL. NO. CONDITIONS STATUS OF COMPLIANCE PART A - SPECIFIC CONDITIONS:CONSTRUCTION PHASE: 1 “Consent to Establish” shall be obtained from Haryana State Pollution Control Board under Air and Water act and a copy shall be submitted to the SEIAA Haryana before the start of any construction work at the site. Agreed. “Consent to Establish” has been obtained from Haryana State Pollution Control Board under Air and Water act and a copy is enclosed as Annexure I. 2 A First Aid room as proposed in the project report will be provided in both during construction and operation of the project. Agreed. A First Aid room has been provided during the construction phase and will be provided in the operational phase of the project. The photographs showing first aid facility is enclosed as Annexure II. 3 Adequate drinking water and Agreed. Safe drinking water 1

nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

Embed Size (px)

Citation preview

Page 1: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

EXPANSION OF GROUP HOUSING PROJECT “ILD GRAND” AT SECTOR 37 C, VILLAGE BASAI, GURGAON, HARYANA BY M/S JUBILIENT MALLS PVT.

LTD.

1.0 HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE Ref. LETTER NO.SEIAA/HR/2013/707 DATED 06.09.2013.

SL. NO. CONDITIONS STATUS OF COMPLIANCE

PART A - SPECIFIC CONDITIONS:CONSTRUCTION PHASE:

1 “Consent to Establish” shall be obtained

from Haryana State Pollution Control

Board under Air and Water act and a

copy shall be submitted to the SEIAA

Haryana before the start of any

construction work at the site.

Agreed. “Consent to Establish” has been

obtained from Haryana State Pollution

Control Board under Air and Water act and

a copy is enclosed as Annexure I.

2 A First Aid room as proposed in the

project report will be provided in both

during construction and operation of the

project.

Agreed. A First Aid room has been provided

during the construction phase and will be

provided in the operational phase of the

project. The photographs showing first aid

facility is enclosed as Annexure II.

3 Adequate drinking water and sanitary

facilities should be provided for

construction workers at the site.

Provision should be made for the mobile

toilets. Open defecation by the laborers is

strictly prohibited. The safe disposal of

waste water and solid wastes generated

during the construction phase should be

ensured.

Agreed. Safe drinking water and adequate

sanitary facilities has been provided on the

site. Mostly local laborers are being hired

for the construction phase, thus a negligible

quantity of waste is being generated.

Inorganic waste is being segregated and

recyclable waste is sold off to government

approved vendors. Solid waste generated

during construction is being managed

properly as per MSW Rules, 2000.

4 All the top soil excavated during

construction activities should be stored

Agreed. The excavated material is being

used for leveling, refilling and in

1

Page 2: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

for use in horticulture/landscape

development within the project site.

horticulture/ landscape development within

the project site.

5 The project proponent shall ensure that

the building material required during

construction phase is properly stored

within the project area and disposal of

construction waste should not create any

adverse effect on the neighboring

communities and should be disposed of

after taking the necessary precautions for

general safety and health aspects of

people, only in approved sites with the

approval of competent authority.

Agreed. It is ensured that the building

material required during construction phase

is being properly stored within the project

area and disposal of construction waste is

not creating any adverse effect on the

neighboring communities and is being

disposed off after taking the necessary

precautions for general safety and health

aspects of people, only in approved sites

with the approval of competent authority.

The photographs showing storage of

construction materials enclosed as

Annexure III.

6 Construction spoils, including

bituminous material and other hazardous

materials, must not be allowed to

contaminate watercourses and the dump

sites for such material must be secured so

that they should not leach into the ground

water and any hazardous waste generated

during construction phase, should be

disposed off as per applicable rules and

norms with necessary approval of the

Haryana State Pollution Control Board.

Agreed. Construction spoils including

bituminous material and other hazardous

material are disposed of safely so that it

does not contaminate water courses. No

dumping of such materials is being allowed

at project site. Waste lubricating oil

generated from maintenance of DG sets fall

under hazardous waste category. Such

wastes are being disposed off with the help

of companies with due approval from

Haryana State Pollution Control Board.

7 The Diesel generator sets to be used

during construction phase should be of

ultra-low sulphur diesel type and should

conform to Environment (Protection)

Rules prescribed for air and noise

Agreed. Ultra-low sulphur diesel is being

used to run the Diesel generator sets used

during construction phase with Provisions of

Air and Noise Emissions Standards as per

EPA Rules 1986.

2

Page 3: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

emission standards.

8 The diesel required for operating DG sets

shall be stored in underground tanks and

if required, clearance from Chief

Controller of Explosives shall be taken.

Agreed. Used oil from DG sets is being

stored in HDPE drums in isolated covered

facility. This used oil is being sold to

authorized recyclers. Suitable care is being

taken to avoid spills/leaks of used oil from

storage.

9 Ambient noise levels should conform to

residential standards both during day and

night. Incremental pollution loads on the

ambient air and noise quality should be

closely monitored during construction

phase. Adequate measures should be

taken to reduce ambient air and noise

level during construction phase, so as to

conform to the stipulated residential

standards.

Agreed. Incremental pollution loads on the

ambient air and noise quality are being

closely monitored. Laboratory Reports of

the environmental monitoring of air, noise

and soil carried out at the site are enclosed

as Annexure IV.

Similarly, Ambient air quality is also closely

monitored so as to conform to the stipulated

standards.

10 Fly ash should be used as building

material in the construction as per the

provisions of Fly Ash Notification of

September, 1999 and amended as on 27th

August, 2003.

Agreed. Fly ash bricks are being used as

building material in the construction as per

the provisions of Fly Ash Notification of

September, 1999 and amended as on 27th

August, 2003.

11 Storm water control and its re use as per

CGWB and BIS standards for various

applications should be ensured.

Agreed. Storm water control and its re use

(for various applications) are being ensured

as per BIS and Central Ground Water Board

(CGWB) standards.

12 Water demand during construction

should be reduced by use of pre-mixed

concrete, curing agents and other best

practices.

Agreed. Water demand during construction

is being reduced by the practice of using

pre-mixed concrete, curing agents and other

best practices.

13 In view of the severe constrains in water Agreed. “ILD Grand” site falls within

3

Page 4: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

supply augmentation in the region and

sustainability of water resources, the

developer will submit the NOC from

CGWA specifying water extraction

quantities and assurance from HUDA

/utility provide indicating source of water

supply and quantity of water with details

of intended use of water – potable and

non-potable. Assurance is required for

both construction and operation stages

separately. It shall be submitted to the

SEIAA and RO, MOEF, Chandigarh

before the start of construction.

planned sector of Gurgaon Manesar Urban

Complex 2021, which is being facilitated

with HUDA water supply scheme. Ground

water is not being extracted for the purpose

of construction as well as for operation

phase of the project. Assurance from HUDA

for the source of water supply during

construction phase is enclosed as

Annexure-V. Application for fresh water

has been filed to HUDA for operational

phase and copy of same is enclosed as

Annexure-VI.

14 Roof should meet prescriptive

requirement as per Energy Conservation

Building Code by using appropriate

thermal insulation material.

Agreed. Roof will be constructed as per

energy conservation building code by using

appropriate thermal insulation material.

15 Opaque wall should meet prescriptive

requirement as per Energy Conservation

Building Code which is proposed to be

mandatory for all air conditioned spaces

while it is desirable for non-air-

conditioned spaces by use of appropriate

thermal insulation material to fulfill

requirement.

Agreed. Opaque wall meets prescribed

requirement as per Energy Conservation

Building Code (ECBC).

16 The approval of the competent authority

shall be obtained for structural safety of

the building on account of earthquake,

adequacy of firefighting equipment’s,

etc. as per National Building Code

including protection measures from

Agreed. The approval of the competent

authority will be obtained in due course of

time for structural safety of the buildings

due to earthquake, adequacy of firefighting

equipment, etc. as per National Building

Code including protection measure from

4

Page 5: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

lightening etc. If any forest land is

involved in the proposed site, clearance

under The Forest Conservation Act shall

be taken from the competent Authority.

lightening etc. No forest land is involved in

the project site. NOC from Forest

Department has been obtained from Dy.

Conservator of Forest, Gurgaon vide letter

No. 2146-G and copy of the same is

enclosed as Annexure VII.

17 Overexploited ground water and

impending severe shortage of water

supply in the region requires the

developer to redraw the water and energy

conservation plan. Developer shall

reduce the overall footprint of the

proposed development. Project

proponent shall incorporate water

efficiency/savings measures as well as

water reuse/recycling within 3 months

and before start of construction to the

SEIAA, Haryana and RO, MOEF, GOI,

Chandigarh.

Agreed. No ground water extraction is being

done. Treated water is being supplied by

HUDA for construction. To reduce the

demand in operational phase, treated water

from STP is being used for horticulture;

flushing as well as efficient fixtures are

being used to minimize the water demand.

18 The project proponent as stated in the

proposal shall construct 19 rain water

harvesting pits for recharging the ground

water within the project premises. Rain

water harvesting pits shall be designed to

make provisions for silting chamber and

removal of floating matter before

entering harvesting pit. Maintenance

budget and persons responsible for

maintenance must be provided. Care

shall be taken that contaminated water do

not enter any RWH pit.

Agreed. 19 number of RWH pits are being

constructed to harvest rain water in the

project “ILD Grand” at Sector 37 C,

Gurgaon. Rain water harvesting pits are

being designed in such a way that the silt

and floating matter will be removed before

entering into pit. Maintenance budget and

experienced persons for maintenance of the

pits are being provided. It is being taken

care that contaminated water do not enter

any RWH pit. Storm Water Plan showing

location of RWH pits is enclosed as

5

Page 6: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

Annexure VIII.

19 The project proponent shall provide for

adequate fire safety measures and

equipment’s as required by Haryana Fire

Service Act, 2009 and instructions issued

by the local authority/Directorate of fire

from time to time. Further the project

proponent shall take necessary

permission regarding fire safety

scheme/NOC from competent Authority

as required.

Agreed. Adequate fire safety measure is

being taken and equipment’s are provided as

required by Haryana Fire Service act, 2009

and instructions issued by the local

Authority/ Directorate of fire from time to

time. Further the project proponent will take

necessary permission regarding fire safety

scheme/ NOC from competent authority as

required.

20. The project proponent shall obtain

assurance from the DHBVN for supply

of 5400 KVA of power supply before the

start of construction. In no case project

will be operational solely on generators

without any power supply from any

external power utility.

Agreed. The project proponent will obtain

assurance from the HVPNL for supply of

5400 KVA of power supply before the start

of construction or else project will be

operational solely on generators without any

power supply from any external power

utility. For this an application has been filed

to HVPNL and acknowledgment copy of the

same is enclosed as Annexure IX.

21 Detail calculation of power load and

ultimate power load of the project shall

be submitted to DHBVN under

intimation to SEIAA Haryana before the

start of construction. Provision shall be

made for electrical infrastructure in the

project area.

Agreed. Detail calculation of power load

and ultimate power load of the project has

been submitted to DHBVN under intimation

to SEIAA Haryana before the start of

construction. Provision will be made for

electrical infrastructure in the project area.

Power load calculation is attached as

Annexure X.

22 The Project proponent shall not raise any

construction in the natural land

depression/Nallah/ Water course and

Agreed. There has been no construction in

the natural land depression/Nallah/water

course and it is being ensured that the

6

Page 7: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

shall ensure that the natural flow from

the Nallah/ Water course is not

obstructed.

natural flow from the Nallah/water course is

not being obstructed.

23 The project proponent shall keep the

plinth level of the building blocks

sufficiently above the level of the

approach road to the Project as per

prescribed bye-laws. Levels of the other

areas in the Projects shall also be kept

suitably so as to avoid flooding.

Agreed. The plinth level of the building

blocks has been made sufficiently above the

level of the approach road to the project as

per prescribed by-laws. Levels of the other

areas in the projects are also being kept

suitably so as to avoid flooding. Elevation

plan is enclosed as Annexure-XI.

24 Construction shall be carried out so that

density of population does not exceed

norms approved by Director General

Town and Country Department Haryana.

Agreed. Construction is being carried out so

that density of population does not exceed

norms approved by Director General Town

and Country Planning Department Haryana.

25 The Project proponent shall submit an

affidavit with the declaration that ground

water will not be used for construction

and only treated water should be used for

construction.

Agreed. Ground water will not be used for

the construction activity and an affidavit for

this has already been submitted to SEIAA,

Haryana at the time of Environment

Clearance. Only treated water is being used

for construction.

26 The project proponent shall not cut any

existing tree and project landscaping plan

should be modified to include those trees

in green area.

Agreed. Tree cutting was not needed. Only

small bushes were present that were cut for

construction activity.

27 The project proponent shall provide

helipad facility as required under NBC

norms and shall seek permission of

helipad from AAI accordingly.

Agreed. The project proponent will provide

helipad facility as required under NBC

norms and will take permission of helipad

from AAI accordingly.

28 The project proponent shall ensure that

ECBC norms for composite climate zone

are met. In Particular building envelope,

Agreed. The project proponent ensures that

ECBC norms for composite climate zone are

met. In Particular building envelope, HVAC

7

Page 8: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

HVAC service, water heating, pumping,

lighting and electrical infrastructure must

meet ECBC norms.

service, water heating, pumping, lighting

and electrical infrastructure is meeting

ECBC norms.

29 The project proponent shall provide 3

meter high barricade around the project

area, dust screen for every floor above

the ground, proper sprinkling and

covering of stored material to restrict

dust and air pollution during

construction.

Agreed. Barricade of sufficient height has

been provided around the project area, dust

screen for every floor above the ground,

proper sprinkling and covering of stored

material to restrict dust and air pollution

during construction. The site photographs

showing site barricading is enclosed as

Annexure XII.

30 The project proponent shall construct a

sedimentation basin in the lower level of

the project site to trap pollutant and other

wastes during rains.

Agreed. Sedimentation basin has been

constructed in the lower level of the project

site to trap pollutant and other wastes during

rains.

31 The Project Proponent shall provide

proper Rasta of proper width and proper

strength for each project before the start

of construction.

Agreed. Proper Rasta of proper width and

proper strength for this project has been

provided before the start of construction.

32 The project proponent shall provide all

the safety measures for the workers

during construction of high rise building.

Agreed. The project proponent is providing

all the safety measures like Helmets, masks

shoes, ropes etc. for the workers during

construction of high rise building. The site

photographs safety measures are enclosed as

Annexure XIII.

33 The Project Proponent shall ensure that

the U-value of the glass is less than 3.177

and maximum solar heat gain co-

efficient is 0.25 for vertical fenestration.

Agreed. It is being ensured that the U-value

of the glass is less than 3.177 and maximum

solar heat gain co-efficient is 0.25 for

vertical fenestration.

34 The project proponent shall ensure

structural integrity of high rise building

Agreed. M/s Jubilant Malls Pvt. Ltd. is

ensuring structural integrity of high rise

8

Page 9: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

during any seismic activity. building during any seismic activity.

35 The PP shall adequately control

construction dusts like silica dust, non-

silica dust and wood dust. Such dusts

shall not spread outside project premises.

Project Proponent shall provide

respiratory protective equipment to all

the construction workers.

Agreed. M/s Jubilant Malls Pvt. Ltd. is

adequately controlling construction dusts

like silica dust, non-silica dust and wood

dust. It is being ensured that such dusts do

not spread outside project premises. The PP

is providing respiratory protective

equipment to all the construction workers.

36 The site for solid waste management

plant is earmarked on the layout plan and

the detailed project for setting up the

solid waste management plant shall be

submitted to the Authority within one

month.

Agreed. The site for solid waste

management plant has been earmarked on

the layout plan. Solid waste management

plan is enclosed as Annexure- XIV.

37 The PP shall develop complete civic

infrastructure of the Group Housing

colony including internal roads, green

belt development, sewerage line, Rain

water recharge arrangements, Storm

water drainage system, solid waste

management site and provision for

composting of bio-degradable waste,

STP, water supply line, dual plumbing

line, electric supply lines etc. and shall

offer possession of the units/ flats

thereafter.

Agreed. M/s Jubilant Malls Pvt. Ltd. is

developing complete civic infrastructure of

the group housing colony including internal

roads, green belt development, sewerage

line, Rain water recharge arrangements,

Storm water drainage system, solid waste

management site and provision for treatment

of bio-degradable waste, STP, water supply

line, dual plumbing line, electric supply

lines etc. and will offer possession of the

units/ flats thereafter.

38 The project proponent shall provide one

refuse area till 24 meter, one till 39 meter

and one after every 15 meter as per

national Building Code.

Agreed. M/s Jubilant Malls Pvt. Ltd. will

provide one refuse area till 24 meter, one till

39 meter and one after every 15 meter as per

National Building Code.

39 The project proponent shall provide fire Agreed. M/s Jubilant Malls Pvt. Ltd. will

9

Page 10: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

control room and fire officer for building

above 30 meter as per National Building

Code.

provide fire control room and fire officer for

building above 30 meter as per National

Building Code.

40 The project proponent shall obtain

permission of mines and Geology

Department for excavation of soil before

the start of construction.

Agreed. Permission of Mines and Geology

department for excavation of soil will be

obtained.

41 The project proponent shall seek specific

prior approval from concerned local

Authority/HUDA regarding provision of

storm drainage and sewerage system

including their integration with external

services of HUDA/Local Authorities

beside other required services before

taking up any construction activity.

Agreed. M/s Jubilant Malls Pvt. Ltd. has

taken specific prior approval from

concerned local Authority/HUDA regarding

provision of storm drainage and sewerage

system including their integration with

external services of HUDA/Local authorities

beside other required services before taking

up any construction activity.

42 The project proponent shall ensure that

no construction activity is undertaken on

surface of revenue rasta passing through

the project area.

No revenue rasta is passing through the

project area.

43 The PP shall indicate the width and

length of revenue Rasta passing through

the project area on sign board and shall

display the same at both the ends of

revenue Rasta stretch, for awareness of

public. Sign board shall also display the

message that this is public Rasta/road

and any citizen can use it. There shall not

be any gate with or without guards on

revenue rasta and passage through the

revenue rasta shall remain fully

unobstructed.

No revenue rasta is passing through the

project area.

10

Page 11: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

PART A- SPECIFIC CONDITIONS : Operational Phase

a “Consent to Operate” shall be obtained

from Haryana State Pollution Control

Board under Air and Water Act and a copy

shall be submitted to the SEIAA, Haryana.

Agreed. “Consent to Operate” will be

obtained from Haryana State Pollution

Control Board under Air and Water Act and

a copy will be submitted to the SEIAA,

Haryana.

b The STP shall be installed for the

treatment of the sewage to the prescribed

standards including odor and treated

effluent will be recycled. The installation

of STP should be certified by an

independent expert and a report in this

regard should be submitted to the SEIAA,

Haryana before the project is

commissioned for operation. Tertiary

treatment of waste water is mandatory.

Discharge of treated sewage shall confirm

to norms and standards of HSPCB,

Panchkula. Project Proponent shall

implement such STP technology which

does not require filter backwash.

Agreed. The STP will be installed for the

treatment of the sewage to the prescribed

standards including odor and treated effluent

will be recycled. The installation of STP

will be certified by an independent expert

and a report in this regard will be submitted

to the SEIAA, Haryana before the project is

commissioned for operation. Tertiary

treatment of waste water is mandatory.

Discharge of treated sewage shall confirm to

norms and standards of HSPCB, Panchkula.

STP technology which does not require

filter backwash will be implemented. Dual

Plumbing plan showing the STP location is

enclosed as Annexure-XV and STP

schematic design is enclosed as Annexure

XVI.

c Separation of the grey and black water

should be done by the use of dual

plumbing line. Treatment of 100% grey

water by decentralized treatment should be

done ensuring that the re-circulated water

should have BOD level less than

10mg/litre and the recycled water will be

used for flushing, gardening and DG set

Separation of the grey and black water will

be done by the use of dual plumbing line.

Treatment of 100% grey water by

decentralized treatment will be done

ensuring that the re-circulated water will

have BOD level less than 10mg/liter and the

recycled water will be reused for flushing,

gardening, DG set cooling and other

11

Page 12: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

cooling and running of fountain in the

water body to achieve zero exit discharge

recreational purposes to achieve zero exit

discharge. Water Balance Diagram showing

Zero Discharge is enclosed as Annexure-

XVII.

d For disinfection of the treated waste water

Ultra violet radiation or ozonization should

be used.

Agreed. For disinfection of the treated

wastewater UV Disinfection process will be

used.

e Diesel power generating sets proposed as

source of back-up power for lifts, common

area illumination and for domestic use

should be enclosed type and conform to

rules made under the Environmental

(Protection) Act, 1986. The location of the

DG sets should be in the basement as

promised by the project proponent with

appropriate stack height i.e. above the roof

level as per the CPCB norms. The diesel

used for DG sets should be ultra-low

sulphur diesel (0.05% sulphur) instead of

low sulphur diesel.

Agreed. Diesel power generating sets

proposed as source of back-up power for

lifts, common area illumination and for

domestic use will be of enclosed type and

will conform to the rules made under the

Environmental (Protection) Act, 1986. The

location of the DG sets will be in the

basement as promised with appropriate

stack height i.e. above the roof level as per

the CPCB norms. The diesel used for DG

sets will be ultra-low sulphur diesel (0.05%

sulphur) instead of low sulphur diesel.

f Ambient noise level should be controlled

to ensure that it does not exceed the

prescribed standards both within and at the

boundary of the proposed residential

complex.

Agreed. Ambient noise level will be

controlled within and at the boundaries of

the project ensuring compliance to

regulatory norms that is in accordance to

Schedule-III of The Noise Pollution

(Regulation and Control) Rules, 2000. This

could be attained through:

1) Development and maintenance of at

least 20% of the total land area for

tree plantation all around the project.

2) Providing acoustic enclosures to DG

12

Page 13: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

sets.

3) Better traffic management.

4) Regular surveillance monitoring.

g The project proponent as stated in the

proposal should maintain at least 34.2% as

green cover area for tree plantation

especially all around the periphery of the

project and on the road sides preferably

with local species so as to provide

protection against noise and suspended

particulate matter. The open spaces inside

the project should be preferably

landscaped and covered with

vegetation/grass, herbs & shrubs. Only

locally available plant species shall be

used.

Agreed. 34.2% of the total project area will

be maintained as used for tree plantation all

around the periphery and the road sides.

Species will be endemic and chosen to

provide protection from dust and noise. In

addition open spaces within the boundaries

will be landscaped whenever possible and to

the maximum extent. Landscape Plan is

enclosed as Annexure XVIII.

h The project proponent shall strive to

minimize water in irrigation of landscape

by minimizing grass area, using native

variety, xeriscaping and mulching,

utilizing efficient irrigation system,

scheduling irrigation only after checking

evapo-transpiration data.

Agreed. Minimum water in irrigation of

landscape by minimizing grass area will be

strived, using native variety, xeriscaping and

mulching, utilizing efficient irrigation

system, scheduling irrigation only after

checking evapo-transpiration data.

i Rain water harvesting for roof run-off and

surface, as per plan submitted should be

implemented. Before recharging the

surface run-off, pre-treatment through

sedimentation tanks must be done to

remove suspended matter, oil and grease.

The bore well for rainwater recharging

should be kept at least 5m. Above the

Agreed. Rain water harvesting for roof run-

off and surface, as per plan submitted will

be implemented. Before recharging the

surface run-off, pre-treatment through

sedimentation tanks will be done to remove

suspended matter, oil and grease. The bore

well for rainwater recharging will be kept at

least 5m. Above the highest ground water

13

Page 14: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

highest ground water table. Care shall be

taken that contaminated water do not enter

any RWH pit. The project proponent shall

avoid RWH of first 10 minutes of rain fall.

Roof top of the building shall be without

any toxic material or paint which can

contaminate rain water. Wire mess and

filters should be used wherever required.

table. For rain water harvesting plan (Refer

Annexure VIII).

j The ground water level and its quality

should be monitored regularly in

consultation with Central Ground Water

Authority.

Agreed. The ground water level and its

quality will be monitored regularly in

consultation with Central Ground Water

Authority.

k There should be no traffic congestion near

the entry and exit points from the roads

adjoining the proposed project site.

Parking should be fully internalized and no

public space should be utilized.

Agreed. Proper parking space will be

provided for parking. Parking will be

completely internalized and no public space

shall be utilized. Care will be taken to

ensure that there is no traffic congestion at

the entry and exit points.

l A report on the energy conservation

measures conforming to energy

conservation norms finalize by Bureau of

Energy Efficiency should be prepared

incorporating details about building

materials & technology; R & U factors etc.

and submit to the SEIAA Haryana in three

months’ time.

Agreed. Report on energy conservation

measures conforming to energy

conservation norms finalized by BEE will

be submitted in due course of time. Energy

conservation measures are enclosed as

Annexure XIX.

m Energy conservation measures like

installation of LED for lighting the-areas

outside the building should be integral part

of the project design and should be in

Agreed. Energy conservation measures like

installation of LED for lighting the areas

outside the building will be integral part of

the project design and will be in place

14

Page 15: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

place before project commissioning. Use of

solar panels may be done to the extent

possible.

before project commissioning. Solar panels

will be adapted for the maximum energy

conservation.

n The project proponent shall use zero ozone

depleting potential material in insulation,

refrigeration, air-conditioning and

adhesive. Project proponent shall also

provide Halon free fire suppression

system.

Agreed. Zero ozone depleting potential

material in insulation, refrigeration, air-

conditioning and adhesive will be used.

Halon free fire suppression will be provided.

o The solid waste generated should be

properly collected and segregated as per

the requirement of the MSW Rules, 2000

and as amended from time to time. The

bio-degradable waste should be composed

by vermin-composting at the site war

marked within the project area and

dry/inert solid waste should be disposed-

off to the approved sites for land-filling

after recovering material.

Agreed. The solid waste generated will be

properly collected and segregated as per the

requirement of the MSW Rules, 2000. The

bio-degradable waste will be composed by

vermin-composting at the site war marked

within the project area and dry/inert solid

waste will be disposed-off to the approved

sites for land-filling after recovering

material. Solid Waste Management plan is

enclosed as Annexure-XIV.

p Provision of the solar water heating

systems shall be as per norms specified by

HAREDA & shall be made operational in

each building block.

Agreed. The provision of the solar water

heating system will be as per the norms

specified by HAREDA and will be made

operational in each building block.

q The traffic plan and the parking plan

proposed by the project proponent should

be adhered to meticulously with further

scope of additional parking for future

requirement. There should be no traffic

congestion near the entry and exit points

from the roads adjoining the proposed

project site. Parking should be fully

Agreed. The traffic plan and the parking

plan proposed will be adhered to

meticulously with further scope of

additional parking for future requirement.

There will be no traffic congestion near the

entry and exit points from the roads

adjoining the project site. Parking will be

fully internalized and no public space will

15

Page 16: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

internalized and no public space should be

used.

be used.

r The project shall be operationalized only

when HUDA/local authority will provide

domestic water supply system in the area.

Agreed. The project will be operationalized

only when HUDA/local authority will provide

domestic water supply system in the area.

s Operation and maintenance of STP, solid

waste management and electrical

Infrastructure, pollution control measures

shall be ensured even after the completion

of sale.

Agreed. Operation and maintenance of STP,

solid waste management and electrical

Infrastructure, pollution control measures

will be ensured even after the completion of

sale.

t Different type of waste should be

disposed-off as per provisions of municipal

solid waste, biomedical waste, hazardous

waste, e-waste, batteries & plastic rules

made under Environment Protection Act,

1986. Particularly E-Waste and Battery

waste shall be disposed of as per existing

E-waste Management Rules 2011 and

Batteries Management Rules 2001. The

project proponent should maintain a

collection center for E-Waste and it should

be disposed of to only registered and

authorized dismantler/recycler.

Agreed. Different type of waste will be

disposed-off as per provisions of municipal

solid waste, biomedical waste, hazardous

waste, e-waste, batteries & plastic rules

made under Environment Protection Act,

1986. Particularly E-Waste and Battery

waste will be disposed of as per existing E-

waste Management Rules 2011 and

Batteries Management Rules 2001.

Collection center for E-Waste will be

maintained and it will be disposed of to only

registered and authorized

dismantler/recycler.

u Standards for discharge of environmental

pollutants as enshrined in various

schedules of rules 3 of Environment

Protection Rules 1986 shall be strictly

complied with.

Agreed. Standards for discharge of

environmental pollutants as enshrined in

various schedules of rules 3 of Environment

Protection Rules 1986 will be strictly

complied with.

v Water supply shall be metered to different

residential units and different utilities.

Agreed. Water supply will be metered to

different residential units and different

utilities.

16

Page 17: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

w The project proponent shall ensure that the

stack height of DG sets is as per the CPCB

guide lines and also ensure that the

emission standards of noise and air are

within the CPCB prescribed limits. Noise

and Emission level of DG sets are greater

than 800KVA shall be as per CBCB latest

standards for high capacity DG sets.

Agreed. It will be ensured that the stack

height of DG sets is as per the CPCB guide

lines and also that the emission standards of

noise and air are within the CPCB

prescribed limits. Noise and Emission level

of DG sets are greater than 800KVA will be

as per CBCB latest standards for high

capacity DG sets.

x All electric supply exceeding 100amp, 3-

phase shall maintain the power factor

between 0.98 lag to 1 at the point of

connection.

Agreed. All electric supply exceeding

100amp, 3-phase will maintain the power

factor between 0.98 lag to 1 at the point of

connection.

y The project proponent shall use only

treated water instead of fresh water for

HVAC and DG cooling. The project

proponent shall use evaporative cooling

technology and double stage cooling

system for HVAC in order to reduce water

consumption. Further temperature, relative

humidity during summer and winter

session should be kept at optimal level.

Variable speed drive, best co-efficient of

performance, as well as optimal integrated

point load value and minimum outside

fresh air supply may be resorted for

conservation of power and water. Coil type

cooling DG sets shall be used for saving

cooling water consumption for water

cooled DG sets.

Agreed. It will be ensured that treated water

instead of fresh water for HVAC and DG

cooling will be used. Evaporative cooling

technology and double stage cooling system

for HVAC will be used in order to reduce

water consumption. Further temperature,

relative humidity during summer and winter

session will be kept at optimal level.

Variable speed drive, best co-efficient of

performance, as well as optimal integrated

point load value and minimum outside fresh

air supply may be resorted for conservation

of power and water. Coil type cooling DG

sets will be used for saving cooling water

consumption for water cooled DG sets.

z The PP shall ensure that the transformer is

constructed with high quality grain

Agreed. The PP will ensure that the

transformer is constructed with high quality

17

Page 18: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

oriented, low loss silicon steel and virgin

electrolyte grade copper. The PP shall

obtain manufacturer’s certificate also for

that.

grain oriented, low loss silicon steel and

virgin electrolyte grade copper. The PP will

obtain manufacturer’s certificate also for

that.

aa The PP shall ensure that exit velocity from

the stack should be sufficiently high. Stack

shall be designed in such a way that there

is no stack down-water under any

meteorological conditions.

Agreed. The PP will ensure that exit

velocity from the stack would be sufficiently

high. Stack will be designed in such a way

that there is no stack down-water under any

meteorological conditions.

ab The PP shall provide water sprinkling

system in the project area to suppress the

dust in addition to the already suggested

mitigation measures in the Air

Environment Chapter of EMP.

Agreed. The PP will provide water

sprinkling system in the project area to

suppress the dust in addition to the already

suggested mitigation measures in the Air

Environment Chapter of EMP. EMP is

enclosed as Annexure-XX.

PART-B GENERAL CONDITION:

I The project proponent should ensure the

commitments made in Form-1, Form-1A,

EIA/EMP and other documents

submitted to the SEIAA for protection of

environment and proposed

environmental safeguards are complied

with in letter and spirit. In case of

contradiction between two or more

documents on any point, the most

environmentally friendly commitment on

the point shall be taken as commitment

by project proponent.

Agreed. It is being ensured that

commitments made in Form-1, Form-1A,

EIA/EMP and other documents submitted to

the SEIAA for protection of environment

and proposed environmental safeguards are

complied with in letter and spirit. In case of

contradiction between two or more

documents on any point, the most

environmentally friendly commitment on

the point will be taken as commitment.

II Six monthly compliance reports should

be submitted to the HSPCB and Regional

Office, MoEF, GOI, Northern Region,

Agreed. Six monthly monitoring reports are

being submitted to the HSPCB and Regional

Office, MoEF, GOI, Northern Region,

18

Page 19: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

Chandigarh and a copy to the regulatory

Authority of Haryana.

Chandigarh and a copy to the regulatory

Authority of Haryana. The acknowledgment

copy of the compliance report submitted

previously is enclosed as Annexure XXI.

III STP outlet after stabilization and stack

emission shall be monitored monthly.

Other environmental parameters and

green belt shall be monitored on

quarterly basis. After every 3 months, the

project proponent shall conduct

environmental audit and shall take

corrective measure, if required, without

delay.

Agreed. STP outlet after stabilization and

stack emission will be monitored monthly.

Other environmental parameters and green

belt will be monitored on quarterly basis.

After every 3 months, the project proponent

will conduct environmental audit and will

take corrective measure, if required, without

delay.

IV The SEIAA, Haryana reserves the right

to add additional safeguard measures

subsequently, if found necessary.

Environmental Clearance granted will be

revoked if it is found that false

information has been given for getting

approval of this project. SEIAA reserves

the right to revoke the clearance if

conditions stipulated are not

implemented to the satisfaction of

SEIAA/MOEF.

Agreed.

V The project proponent shall not violate any

judicial orders/ pronouncements issued by

the Court/ Tribunal.

Agreed. M/s Jubilant Malls Pvt. Ltd. will not

violate judicial orders/ pronouncements issued

by the Hon'ble Supreme Court/ High courts.

VI All other statutory clearances such as the

approvals for storage of diesel from

Chief Controller of Explosives, Fire

Department, Civil Aviation Department,

Agreed. AAI NOC from Civil Aviation

Department for Height clearance, and

Aravalli clearance from D.C. has already

been granted and are enclosed as Annexure

19

Page 20: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

Forest Conservation Act, 1980 and

Wildlife (Protection) Act, 1972, Forest

Act, 1927, PLPA 1900 etc. shall be

obtained, as applicable by the project

proponents from the respective

authorities prior to construction of the

project.

– XXII & XXIII respectively. For forest

NOC please refer Annexure VII.

VII The project proponent should inform the

public that the project has been accorded

Environment Clearance by the SEIAA

and copies of the clearance letter are

available with the Haryana State

Pollution Control Board & SEIAA. This

should be advertised within 7 days from

the date of issue of clearance letter at

least in two local newspapers that are

widely circulated in the region and the

copy of the same be forwarded to SEIAA

Haryana. A copy of Environment

Clearance collections shall also be put on

project proponent’s website for public

awareness.

Agreed.

VIII Under the provisions of Environment

(Protection) Act, 1986, legal action shall

be initiated against the project proponent

if it was found that construction of the

project has been started without

obtaining Environmental Clearance.

Agreed. The construction of the project has

not been started without obtaining

Environmental Clearance. Environmental

clearance has been granted as per the letter

no. SEIAA/HR/2013/707 dated 06.09.2013

from SEIAA. EC Letter is attached as

Annexure - XXIV.

IX Any appeal against this Environmental

Clearance shall lie with the National

Agreed.

20

Page 21: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

Green Tribunal, if preferred within a

period of 30 days as prescribed under

Section 16 of the National Green

Tribunal Act, 2010.

X The project proponent shall put in place

Corporate Environment Policy as

mentioned in MOEF, GOI, ON No. J-

11013/41/2006-IA II (I) dated 26.04.12

within 3 months period. Latest Corporate

Environment Policy should be submitted

to SEIAA within 3 months of issuance of

this letter.

Agreed.

XI The fund ear-marked for environment

protection measures should be kept in

separate account and should not be

diverted for other purposes and year wise

expenditure shall be reported to the

SEIAA/RO MoEF GOI under rules

prescribed for Environment Audit.

Agreed. The fund ear-marked for

environment protection measures will be

kept in separate account and will not be

diverted for other purposes and year wise

expenditure will be reported to the

SEIAA/RO MoEF GOI under rules

prescribed for Environment Audit.

XII The PP shall ensure the compliance of

Forest Department, Haryana Notification

no. S.O.121/PA2/1900/S.4/97 dated

28.11.1997.

Agreed. The PP will ensure the compliance

of Forest Department, Haryana Notification

no. S.O.121/PA2/1900/S.4/97 dated

28.11.1997.

XIII The project proponent shall ensure that

no vehicle during construction/operation

phase enter the project premises without

valid ‘Pollution Under Control’

certificate from competent Authority.

Agreed. It will be ensured that no vehicle

during construction/operation phase enter

the project premises without valid ‘Pollution

Under Control’ certificate from competent

Authority.

XIV The PP is responsible for compliance of

all conditions in Environmental

Clearance letter and project proponent

Agreed.

21

Page 22: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

can not absolve himself/herself of the

responsibility by shifting it to any

contractor engaged by project proponent.

XV The Project proponent shall seek fresh

Environmental Clearance if at any stage

there is change in the planning of the

proposed project.

Agreed. The Project proponent will seek

fresh Environmental Clearance if at any

stage there is change in the planning of the

project.

2.0 COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE MANUAL 2010 OF MoEF

Sl. No. Conditions Status of Compliance

PART b. – SPECIFIC CONDITIONS:

1. An area at remote site from habitation

within the site shall be earmarked for

Organic Waste Converter.

Agreed. Organic Waste Converter will be

installed at a remote site from the habitation.

2. Management of excess manure after in

house use should be worked out by giving

it to user like villages, nursery or local

bodies for maintaining parks etc.

Agreed. The manure generated from the

organic waste converter will be used for

developing the landscape area. However, the

excess manure left after site development will

be given to villages, nursery and local bodies

for maintaining nearby parks.

3. 100% wastewater to be treated in STP

confirming to prescribe standards of

receiving body or designated use surplus

treated water surplus treated water after in

house use may be managed by proponent

or discharged into public sewer after

permission from the competent authority is

taken and submitted. Uninterrupted power

supply should be assured to STP Plant.

Agreed. 100% wastewater generated at the

project site will be treated in the in-house STP

which is constructed during the construction

phase confirming to prescribe standards of

receiving body or designated use. Provisions

for monitoring of STP are being done on

weekly basis till its stabilization then on

monthly basis. Prior permission from the

competent authority will be taken to discharge

the wastewater into the public drainage

22

Page 23: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

system/drains.

4. Solar water to be installed to the maximum

possible and hot water may be supplied to

kitchens.

Agreed. The arrangement for solar water

system will be made to ensure to the

maximum possible usage to be supplied for

kitchen usage.

5. RWH pits to be provided tower wise for

ease maintenance.

Agreed. 19 Rain Water Harvesting Pits are

being made which are located at the opposite

ends and earmarked in the rain water

harvesting plan which is attached as

Annexure-VIII.

6. Use of LEDs should be explored in place

of CFL. Solar light is to be provided in

common areas with 50% of them may be

with dual powered.

Agreed. Solar lights is being provided in the

common areas and LEDs will be explored in

place of CFLs.

7. All entry and exit should be bell mouth

shaped.

Agreed. Adjacent but separate entry and exit

with adequate space will be made to prevent

congestion.

8. No internal and peripheral roads should be

less than 9 m wide.

Agreed. All internal and peripheral roads are

being made of minimum 9m width.

9. Environmental Corporate Responsibility

(ECR) plan along with budgetary

provision amounting to 2% of total project

cost shall be submitted (within three

month) on need base assessment study in

the study area. Income generating

measures which can help in up-liftment of

weaker section of society consistent with

the traditional skills of the people

identified. The program we can include

activities such as old age homes. Minutes

of 131st SEAC meeting held on 11/03/2013

Agreed. Environmental Corporate

Responsibility (ECR) plan with budgetary

provision amounting to 2% of total project

cost will be provided. Income generating

measure for the up-liftment of the weaker

section of society consistent with the

traditional skills of the people will be

identified. Vocational training will be

imparted so that poor section of society can

take up self-employment and jobs. Separate

budget for community development

programmers will be specified.

23

Page 24: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

water harvesting provisions in nearby

areas, development of fodder farm, fruit

bearing orchards, vocational training etc.

In addition, vocational training for

individuals shall be imparted so that poor

section of society can take up self-

employment and jobs. Separate budget for

community development activities and

income generating programmers shall be

specified.

10. Green belt area should be covered with

50% trees, 25 % shrubs and 25% grass.

Tress should be planted in 3 rows on the

periphery. At least 50% of the tree should

be ever green.

Agreed. There is a provision of adequate

green belt area for landscaping.

11. Separate room with proper amenities in

commensuration with age is to be provided

in the club house for senior citizen.

Agreed. Separate rooms will be provided for

senior citizens with the proper amenities in

commensuration in the club.

12. The project proponent will submit the

management plan of the excavated soil

within 45 days from the date of recipe of

EC letter.

Agreed. The top soil excavated is being used

for landscaping and horticulture while the rest

of excavation is being used for land filling

and landscaping.

13. Ground water should not be extracted for

the purpose of construction or otherwise.

Agreed. Ground water is not used either for

construction purpose or during operation

phase.

14. Project falling within the 10 km area of

Wild Life Sanctuary is to be obtained a

clearance from the National Board Wild

Life (NBWL), even if the ec0-sensitive

Agreed. The project site does not falls within

10 km of Wild Life Sanctuary. Hence, there is

no need for obtaining clearance from National

Board Wild Life (NBWL).

24

Page 25: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

zone is not earmarked.

15. 10% each EWS and LIG houses to be

provided as per GDA norms.

Agreed. LIG & EWS housing will be

provided as per Ghaziabad Development

Authority Norms.

3.0 Compliance to NGT Order dated 10.04.2015 related to Construction

SI. No. NGT Order dated 10.04.2015 Status of Compliance

1. Every builder or owner shall put tarpaulin

on scaffolding around the area of

construction and the building. No person

including builder, owner can be permitted

to store any construction material

particularly sand on any part of the street,

roads in any colony.

Tarpaulin covers are provided around the area of

construction wherever required. No construction

materials such as cement, sand and aggregates

are stored at site. Ready-mixed concrete is being

used for concrete work at project site which is

being transported from the off-site batching

plant. At the off-site batching plant the

construction materials are properly stored in

covered storage yard with proper shades and

covers. A photograph of tarpaulin covered raw

materials is attached as Annexure- III.

2. The construction material of any kind that

is stored in the site will be fully covered in

all respects so that it does not disperse in

the Air in any form.

Tarpaulin covers are provided around the area of

construction wherever required. No construction

materials such as cement, sand and aggregates

are stored at site. Ready-mixed concrete is being

used for concrete work at project site which is

being transported from the off-site batching

plant. At the off-site batching plant the

construction materials are properly stored in

covered storage yard with proper shades and

covers.

25

Page 26: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

SI. No. NGT Order dated 10.04.2015 Status of Compliance

3. All the construction material and debris

shall be carried in the trucks or other

vehicles which are fully covered and

protected so as to ensure that the

construction debris or the construction

material does not get dispersed into the air

or atmosphere, in any form whatsoever.

The trucks carrying construction materials and

debris are suitably covered by tarpaulin and

plastic sheets. The trucks carrying construction

materials & debris without cover are not

permitted to enter or leave the project site.

4. The dust emissions from the construction

site should be completely controlled and all

precautions taken in that behalf.

All necessary precautions are adopted to control

the dust emissions. Water sprinkling at site is

carried out through tanker water regularly at site

for dust suppression and logbook is being

maintained.

5. The vehicles carrying construction material

and construction debris of any kind should

be cleaned before it is permitted to ply on

the road after unloading of such material.

“Wheel Washing Bay” has been provided at

main entry road of the project and Batching

Plant sites. Wheels of constructions equipments/

vehicles and trucks are washed before it is

permitted to ply on the road.

6. Every worker working on the construction

site and involved in loading, unloading and

carriage of construction material and

construction debris shall be provided with

mask to prevent inhalation of dust particles.

Safety measures are being taken. Workers are

made aware of the safety measures and safety

equipments are being provided to the workers at

site.

7. Every owner and or builder shall be under

obligation to provide all medical help,

investigation and treatment to the workers

involved in the construction of building and

carry of construction material and debris

relatable to dust emission.

Full fledged first aid facility is provided at the

construction site and regular medical check-ups

by Doctor are conducted for construction

workers. Logbook is being maintained with

medical treatment details of the workers.

Photograph showing medical facilities provided

at the site are attached as Annexure-II.

26

Page 27: nromoef.gov.innromoef.gov.in/SMPR/25042016/19.docx · Web viewM/s Jubilant Malls Pvt. Ltd. is developing complete civic infrastructure of the group housing colony including internal

SI. No. NGT Order dated 10.04.2015 Status of Compliance

8. It shall be the responsibility of every

builder to transport construction material

and debris waste to construction site,

dumping site or any other place in

accordance with rules and in terms of this

order.

At present only structural work is going on.

Therefore there is no generation of construction

debris. When debris will be generated, it will be

disposed off at Government Authorized landfills.

9. All to take appropriate measures and to

ensure that the terms and conditions of the

earlier order and these orders should

strictly comply with by fixing sprinklers,

creations of green air barriers.

Regular sprinkling of water is being carried out

at site through tanker. Photograph showing water

sprinkling system is enclosed as Annexure-

XXV.

10. Compulsory use of wet jet in grinding and

stone cutting.

Structural work is under progress at site. All

necessary precautions will be taken in the stone

cutting and grinding area which will be done at

later stage of construction. Photograph showing

current status of construction is attached as

Annexure-XXVI.

11. Wind breaking walls around construction

site.

The site is enclosed with barricade wall of

adequate height around the project boundary

which acts as a wind breaker. Photograph of the

same is attached as Annexure-XII.

12. All the builders who are building

commercial, residential complexes which

are covered under the EIA Notification of

2006 shall provide green belt around the

building that they construct. All Authorities

shall ensure that such green belts are in

existence prior to issuance of occupancy

certificate.

Green area will be developed at the end of

construction stage as per approved building plan.

27