Upload
truongkhuong
View
225
Download
3
Embed Size (px)
Citation preview
EXPANSION OF GROUP HOUSING PROJECT “ILD GRAND” AT SECTOR 37 C, VILLAGE BASAI, GURGAON, HARYANA BY M/S JUBILIENT MALLS PVT.
LTD.
1.0 HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE Ref. LETTER NO.SEIAA/HR/2013/707 DATED 06.09.2013.
SL. NO. CONDITIONS STATUS OF COMPLIANCE
PART A - SPECIFIC CONDITIONS:CONSTRUCTION PHASE:
1 “Consent to Establish” shall be obtained
from Haryana State Pollution Control
Board under Air and Water act and a
copy shall be submitted to the SEIAA
Haryana before the start of any
construction work at the site.
Agreed. “Consent to Establish” has been
obtained from Haryana State Pollution
Control Board under Air and Water act and
a copy is enclosed as Annexure I.
2 A First Aid room as proposed in the
project report will be provided in both
during construction and operation of the
project.
Agreed. A First Aid room has been provided
during the construction phase and will be
provided in the operational phase of the
project. The photographs showing first aid
facility is enclosed as Annexure II.
3 Adequate drinking water and sanitary
facilities should be provided for
construction workers at the site.
Provision should be made for the mobile
toilets. Open defecation by the laborers is
strictly prohibited. The safe disposal of
waste water and solid wastes generated
during the construction phase should be
ensured.
Agreed. Safe drinking water and adequate
sanitary facilities has been provided on the
site. Mostly local laborers are being hired
for the construction phase, thus a negligible
quantity of waste is being generated.
Inorganic waste is being segregated and
recyclable waste is sold off to government
approved vendors. Solid waste generated
during construction is being managed
properly as per MSW Rules, 2000.
4 All the top soil excavated during
construction activities should be stored
Agreed. The excavated material is being
used for leveling, refilling and in
1
for use in horticulture/landscape
development within the project site.
horticulture/ landscape development within
the project site.
5 The project proponent shall ensure that
the building material required during
construction phase is properly stored
within the project area and disposal of
construction waste should not create any
adverse effect on the neighboring
communities and should be disposed of
after taking the necessary precautions for
general safety and health aspects of
people, only in approved sites with the
approval of competent authority.
Agreed. It is ensured that the building
material required during construction phase
is being properly stored within the project
area and disposal of construction waste is
not creating any adverse effect on the
neighboring communities and is being
disposed off after taking the necessary
precautions for general safety and health
aspects of people, only in approved sites
with the approval of competent authority.
The photographs showing storage of
construction materials enclosed as
Annexure III.
6 Construction spoils, including
bituminous material and other hazardous
materials, must not be allowed to
contaminate watercourses and the dump
sites for such material must be secured so
that they should not leach into the ground
water and any hazardous waste generated
during construction phase, should be
disposed off as per applicable rules and
norms with necessary approval of the
Haryana State Pollution Control Board.
Agreed. Construction spoils including
bituminous material and other hazardous
material are disposed of safely so that it
does not contaminate water courses. No
dumping of such materials is being allowed
at project site. Waste lubricating oil
generated from maintenance of DG sets fall
under hazardous waste category. Such
wastes are being disposed off with the help
of companies with due approval from
Haryana State Pollution Control Board.
7 The Diesel generator sets to be used
during construction phase should be of
ultra-low sulphur diesel type and should
conform to Environment (Protection)
Rules prescribed for air and noise
Agreed. Ultra-low sulphur diesel is being
used to run the Diesel generator sets used
during construction phase with Provisions of
Air and Noise Emissions Standards as per
EPA Rules 1986.
2
emission standards.
8 The diesel required for operating DG sets
shall be stored in underground tanks and
if required, clearance from Chief
Controller of Explosives shall be taken.
Agreed. Used oil from DG sets is being
stored in HDPE drums in isolated covered
facility. This used oil is being sold to
authorized recyclers. Suitable care is being
taken to avoid spills/leaks of used oil from
storage.
9 Ambient noise levels should conform to
residential standards both during day and
night. Incremental pollution loads on the
ambient air and noise quality should be
closely monitored during construction
phase. Adequate measures should be
taken to reduce ambient air and noise
level during construction phase, so as to
conform to the stipulated residential
standards.
Agreed. Incremental pollution loads on the
ambient air and noise quality are being
closely monitored. Laboratory Reports of
the environmental monitoring of air, noise
and soil carried out at the site are enclosed
as Annexure IV.
Similarly, Ambient air quality is also closely
monitored so as to conform to the stipulated
standards.
10 Fly ash should be used as building
material in the construction as per the
provisions of Fly Ash Notification of
September, 1999 and amended as on 27th
August, 2003.
Agreed. Fly ash bricks are being used as
building material in the construction as per
the provisions of Fly Ash Notification of
September, 1999 and amended as on 27th
August, 2003.
11 Storm water control and its re use as per
CGWB and BIS standards for various
applications should be ensured.
Agreed. Storm water control and its re use
(for various applications) are being ensured
as per BIS and Central Ground Water Board
(CGWB) standards.
12 Water demand during construction
should be reduced by use of pre-mixed
concrete, curing agents and other best
practices.
Agreed. Water demand during construction
is being reduced by the practice of using
pre-mixed concrete, curing agents and other
best practices.
13 In view of the severe constrains in water Agreed. “ILD Grand” site falls within
3
supply augmentation in the region and
sustainability of water resources, the
developer will submit the NOC from
CGWA specifying water extraction
quantities and assurance from HUDA
/utility provide indicating source of water
supply and quantity of water with details
of intended use of water – potable and
non-potable. Assurance is required for
both construction and operation stages
separately. It shall be submitted to the
SEIAA and RO, MOEF, Chandigarh
before the start of construction.
planned sector of Gurgaon Manesar Urban
Complex 2021, which is being facilitated
with HUDA water supply scheme. Ground
water is not being extracted for the purpose
of construction as well as for operation
phase of the project. Assurance from HUDA
for the source of water supply during
construction phase is enclosed as
Annexure-V. Application for fresh water
has been filed to HUDA for operational
phase and copy of same is enclosed as
Annexure-VI.
14 Roof should meet prescriptive
requirement as per Energy Conservation
Building Code by using appropriate
thermal insulation material.
Agreed. Roof will be constructed as per
energy conservation building code by using
appropriate thermal insulation material.
15 Opaque wall should meet prescriptive
requirement as per Energy Conservation
Building Code which is proposed to be
mandatory for all air conditioned spaces
while it is desirable for non-air-
conditioned spaces by use of appropriate
thermal insulation material to fulfill
requirement.
Agreed. Opaque wall meets prescribed
requirement as per Energy Conservation
Building Code (ECBC).
16 The approval of the competent authority
shall be obtained for structural safety of
the building on account of earthquake,
adequacy of firefighting equipment’s,
etc. as per National Building Code
including protection measures from
Agreed. The approval of the competent
authority will be obtained in due course of
time for structural safety of the buildings
due to earthquake, adequacy of firefighting
equipment, etc. as per National Building
Code including protection measure from
4
lightening etc. If any forest land is
involved in the proposed site, clearance
under The Forest Conservation Act shall
be taken from the competent Authority.
lightening etc. No forest land is involved in
the project site. NOC from Forest
Department has been obtained from Dy.
Conservator of Forest, Gurgaon vide letter
No. 2146-G and copy of the same is
enclosed as Annexure VII.
17 Overexploited ground water and
impending severe shortage of water
supply in the region requires the
developer to redraw the water and energy
conservation plan. Developer shall
reduce the overall footprint of the
proposed development. Project
proponent shall incorporate water
efficiency/savings measures as well as
water reuse/recycling within 3 months
and before start of construction to the
SEIAA, Haryana and RO, MOEF, GOI,
Chandigarh.
Agreed. No ground water extraction is being
done. Treated water is being supplied by
HUDA for construction. To reduce the
demand in operational phase, treated water
from STP is being used for horticulture;
flushing as well as efficient fixtures are
being used to minimize the water demand.
18 The project proponent as stated in the
proposal shall construct 19 rain water
harvesting pits for recharging the ground
water within the project premises. Rain
water harvesting pits shall be designed to
make provisions for silting chamber and
removal of floating matter before
entering harvesting pit. Maintenance
budget and persons responsible for
maintenance must be provided. Care
shall be taken that contaminated water do
not enter any RWH pit.
Agreed. 19 number of RWH pits are being
constructed to harvest rain water in the
project “ILD Grand” at Sector 37 C,
Gurgaon. Rain water harvesting pits are
being designed in such a way that the silt
and floating matter will be removed before
entering into pit. Maintenance budget and
experienced persons for maintenance of the
pits are being provided. It is being taken
care that contaminated water do not enter
any RWH pit. Storm Water Plan showing
location of RWH pits is enclosed as
5
Annexure VIII.
19 The project proponent shall provide for
adequate fire safety measures and
equipment’s as required by Haryana Fire
Service Act, 2009 and instructions issued
by the local authority/Directorate of fire
from time to time. Further the project
proponent shall take necessary
permission regarding fire safety
scheme/NOC from competent Authority
as required.
Agreed. Adequate fire safety measure is
being taken and equipment’s are provided as
required by Haryana Fire Service act, 2009
and instructions issued by the local
Authority/ Directorate of fire from time to
time. Further the project proponent will take
necessary permission regarding fire safety
scheme/ NOC from competent authority as
required.
20. The project proponent shall obtain
assurance from the DHBVN for supply
of 5400 KVA of power supply before the
start of construction. In no case project
will be operational solely on generators
without any power supply from any
external power utility.
Agreed. The project proponent will obtain
assurance from the HVPNL for supply of
5400 KVA of power supply before the start
of construction or else project will be
operational solely on generators without any
power supply from any external power
utility. For this an application has been filed
to HVPNL and acknowledgment copy of the
same is enclosed as Annexure IX.
21 Detail calculation of power load and
ultimate power load of the project shall
be submitted to DHBVN under
intimation to SEIAA Haryana before the
start of construction. Provision shall be
made for electrical infrastructure in the
project area.
Agreed. Detail calculation of power load
and ultimate power load of the project has
been submitted to DHBVN under intimation
to SEIAA Haryana before the start of
construction. Provision will be made for
electrical infrastructure in the project area.
Power load calculation is attached as
Annexure X.
22 The Project proponent shall not raise any
construction in the natural land
depression/Nallah/ Water course and
Agreed. There has been no construction in
the natural land depression/Nallah/water
course and it is being ensured that the
6
shall ensure that the natural flow from
the Nallah/ Water course is not
obstructed.
natural flow from the Nallah/water course is
not being obstructed.
23 The project proponent shall keep the
plinth level of the building blocks
sufficiently above the level of the
approach road to the Project as per
prescribed bye-laws. Levels of the other
areas in the Projects shall also be kept
suitably so as to avoid flooding.
Agreed. The plinth level of the building
blocks has been made sufficiently above the
level of the approach road to the project as
per prescribed by-laws. Levels of the other
areas in the projects are also being kept
suitably so as to avoid flooding. Elevation
plan is enclosed as Annexure-XI.
24 Construction shall be carried out so that
density of population does not exceed
norms approved by Director General
Town and Country Department Haryana.
Agreed. Construction is being carried out so
that density of population does not exceed
norms approved by Director General Town
and Country Planning Department Haryana.
25 The Project proponent shall submit an
affidavit with the declaration that ground
water will not be used for construction
and only treated water should be used for
construction.
Agreed. Ground water will not be used for
the construction activity and an affidavit for
this has already been submitted to SEIAA,
Haryana at the time of Environment
Clearance. Only treated water is being used
for construction.
26 The project proponent shall not cut any
existing tree and project landscaping plan
should be modified to include those trees
in green area.
Agreed. Tree cutting was not needed. Only
small bushes were present that were cut for
construction activity.
27 The project proponent shall provide
helipad facility as required under NBC
norms and shall seek permission of
helipad from AAI accordingly.
Agreed. The project proponent will provide
helipad facility as required under NBC
norms and will take permission of helipad
from AAI accordingly.
28 The project proponent shall ensure that
ECBC norms for composite climate zone
are met. In Particular building envelope,
Agreed. The project proponent ensures that
ECBC norms for composite climate zone are
met. In Particular building envelope, HVAC
7
HVAC service, water heating, pumping,
lighting and electrical infrastructure must
meet ECBC norms.
service, water heating, pumping, lighting
and electrical infrastructure is meeting
ECBC norms.
29 The project proponent shall provide 3
meter high barricade around the project
area, dust screen for every floor above
the ground, proper sprinkling and
covering of stored material to restrict
dust and air pollution during
construction.
Agreed. Barricade of sufficient height has
been provided around the project area, dust
screen for every floor above the ground,
proper sprinkling and covering of stored
material to restrict dust and air pollution
during construction. The site photographs
showing site barricading is enclosed as
Annexure XII.
30 The project proponent shall construct a
sedimentation basin in the lower level of
the project site to trap pollutant and other
wastes during rains.
Agreed. Sedimentation basin has been
constructed in the lower level of the project
site to trap pollutant and other wastes during
rains.
31 The Project Proponent shall provide
proper Rasta of proper width and proper
strength for each project before the start
of construction.
Agreed. Proper Rasta of proper width and
proper strength for this project has been
provided before the start of construction.
32 The project proponent shall provide all
the safety measures for the workers
during construction of high rise building.
Agreed. The project proponent is providing
all the safety measures like Helmets, masks
shoes, ropes etc. for the workers during
construction of high rise building. The site
photographs safety measures are enclosed as
Annexure XIII.
33 The Project Proponent shall ensure that
the U-value of the glass is less than 3.177
and maximum solar heat gain co-
efficient is 0.25 for vertical fenestration.
Agreed. It is being ensured that the U-value
of the glass is less than 3.177 and maximum
solar heat gain co-efficient is 0.25 for
vertical fenestration.
34 The project proponent shall ensure
structural integrity of high rise building
Agreed. M/s Jubilant Malls Pvt. Ltd. is
ensuring structural integrity of high rise
8
during any seismic activity. building during any seismic activity.
35 The PP shall adequately control
construction dusts like silica dust, non-
silica dust and wood dust. Such dusts
shall not spread outside project premises.
Project Proponent shall provide
respiratory protective equipment to all
the construction workers.
Agreed. M/s Jubilant Malls Pvt. Ltd. is
adequately controlling construction dusts
like silica dust, non-silica dust and wood
dust. It is being ensured that such dusts do
not spread outside project premises. The PP
is providing respiratory protective
equipment to all the construction workers.
36 The site for solid waste management
plant is earmarked on the layout plan and
the detailed project for setting up the
solid waste management plant shall be
submitted to the Authority within one
month.
Agreed. The site for solid waste
management plant has been earmarked on
the layout plan. Solid waste management
plan is enclosed as Annexure- XIV.
37 The PP shall develop complete civic
infrastructure of the Group Housing
colony including internal roads, green
belt development, sewerage line, Rain
water recharge arrangements, Storm
water drainage system, solid waste
management site and provision for
composting of bio-degradable waste,
STP, water supply line, dual plumbing
line, electric supply lines etc. and shall
offer possession of the units/ flats
thereafter.
Agreed. M/s Jubilant Malls Pvt. Ltd. is
developing complete civic infrastructure of
the group housing colony including internal
roads, green belt development, sewerage
line, Rain water recharge arrangements,
Storm water drainage system, solid waste
management site and provision for treatment
of bio-degradable waste, STP, water supply
line, dual plumbing line, electric supply
lines etc. and will offer possession of the
units/ flats thereafter.
38 The project proponent shall provide one
refuse area till 24 meter, one till 39 meter
and one after every 15 meter as per
national Building Code.
Agreed. M/s Jubilant Malls Pvt. Ltd. will
provide one refuse area till 24 meter, one till
39 meter and one after every 15 meter as per
National Building Code.
39 The project proponent shall provide fire Agreed. M/s Jubilant Malls Pvt. Ltd. will
9
control room and fire officer for building
above 30 meter as per National Building
Code.
provide fire control room and fire officer for
building above 30 meter as per National
Building Code.
40 The project proponent shall obtain
permission of mines and Geology
Department for excavation of soil before
the start of construction.
Agreed. Permission of Mines and Geology
department for excavation of soil will be
obtained.
41 The project proponent shall seek specific
prior approval from concerned local
Authority/HUDA regarding provision of
storm drainage and sewerage system
including their integration with external
services of HUDA/Local Authorities
beside other required services before
taking up any construction activity.
Agreed. M/s Jubilant Malls Pvt. Ltd. has
taken specific prior approval from
concerned local Authority/HUDA regarding
provision of storm drainage and sewerage
system including their integration with
external services of HUDA/Local authorities
beside other required services before taking
up any construction activity.
42 The project proponent shall ensure that
no construction activity is undertaken on
surface of revenue rasta passing through
the project area.
No revenue rasta is passing through the
project area.
43 The PP shall indicate the width and
length of revenue Rasta passing through
the project area on sign board and shall
display the same at both the ends of
revenue Rasta stretch, for awareness of
public. Sign board shall also display the
message that this is public Rasta/road
and any citizen can use it. There shall not
be any gate with or without guards on
revenue rasta and passage through the
revenue rasta shall remain fully
unobstructed.
No revenue rasta is passing through the
project area.
10
PART A- SPECIFIC CONDITIONS : Operational Phase
a “Consent to Operate” shall be obtained
from Haryana State Pollution Control
Board under Air and Water Act and a copy
shall be submitted to the SEIAA, Haryana.
Agreed. “Consent to Operate” will be
obtained from Haryana State Pollution
Control Board under Air and Water Act and
a copy will be submitted to the SEIAA,
Haryana.
b The STP shall be installed for the
treatment of the sewage to the prescribed
standards including odor and treated
effluent will be recycled. The installation
of STP should be certified by an
independent expert and a report in this
regard should be submitted to the SEIAA,
Haryana before the project is
commissioned for operation. Tertiary
treatment of waste water is mandatory.
Discharge of treated sewage shall confirm
to norms and standards of HSPCB,
Panchkula. Project Proponent shall
implement such STP technology which
does not require filter backwash.
Agreed. The STP will be installed for the
treatment of the sewage to the prescribed
standards including odor and treated effluent
will be recycled. The installation of STP
will be certified by an independent expert
and a report in this regard will be submitted
to the SEIAA, Haryana before the project is
commissioned for operation. Tertiary
treatment of waste water is mandatory.
Discharge of treated sewage shall confirm to
norms and standards of HSPCB, Panchkula.
STP technology which does not require
filter backwash will be implemented. Dual
Plumbing plan showing the STP location is
enclosed as Annexure-XV and STP
schematic design is enclosed as Annexure
XVI.
c Separation of the grey and black water
should be done by the use of dual
plumbing line. Treatment of 100% grey
water by decentralized treatment should be
done ensuring that the re-circulated water
should have BOD level less than
10mg/litre and the recycled water will be
used for flushing, gardening and DG set
Separation of the grey and black water will
be done by the use of dual plumbing line.
Treatment of 100% grey water by
decentralized treatment will be done
ensuring that the re-circulated water will
have BOD level less than 10mg/liter and the
recycled water will be reused for flushing,
gardening, DG set cooling and other
11
cooling and running of fountain in the
water body to achieve zero exit discharge
recreational purposes to achieve zero exit
discharge. Water Balance Diagram showing
Zero Discharge is enclosed as Annexure-
XVII.
d For disinfection of the treated waste water
Ultra violet radiation or ozonization should
be used.
Agreed. For disinfection of the treated
wastewater UV Disinfection process will be
used.
e Diesel power generating sets proposed as
source of back-up power for lifts, common
area illumination and for domestic use
should be enclosed type and conform to
rules made under the Environmental
(Protection) Act, 1986. The location of the
DG sets should be in the basement as
promised by the project proponent with
appropriate stack height i.e. above the roof
level as per the CPCB norms. The diesel
used for DG sets should be ultra-low
sulphur diesel (0.05% sulphur) instead of
low sulphur diesel.
Agreed. Diesel power generating sets
proposed as source of back-up power for
lifts, common area illumination and for
domestic use will be of enclosed type and
will conform to the rules made under the
Environmental (Protection) Act, 1986. The
location of the DG sets will be in the
basement as promised with appropriate
stack height i.e. above the roof level as per
the CPCB norms. The diesel used for DG
sets will be ultra-low sulphur diesel (0.05%
sulphur) instead of low sulphur diesel.
f Ambient noise level should be controlled
to ensure that it does not exceed the
prescribed standards both within and at the
boundary of the proposed residential
complex.
Agreed. Ambient noise level will be
controlled within and at the boundaries of
the project ensuring compliance to
regulatory norms that is in accordance to
Schedule-III of The Noise Pollution
(Regulation and Control) Rules, 2000. This
could be attained through:
1) Development and maintenance of at
least 20% of the total land area for
tree plantation all around the project.
2) Providing acoustic enclosures to DG
12
sets.
3) Better traffic management.
4) Regular surveillance monitoring.
g The project proponent as stated in the
proposal should maintain at least 34.2% as
green cover area for tree plantation
especially all around the periphery of the
project and on the road sides preferably
with local species so as to provide
protection against noise and suspended
particulate matter. The open spaces inside
the project should be preferably
landscaped and covered with
vegetation/grass, herbs & shrubs. Only
locally available plant species shall be
used.
Agreed. 34.2% of the total project area will
be maintained as used for tree plantation all
around the periphery and the road sides.
Species will be endemic and chosen to
provide protection from dust and noise. In
addition open spaces within the boundaries
will be landscaped whenever possible and to
the maximum extent. Landscape Plan is
enclosed as Annexure XVIII.
h The project proponent shall strive to
minimize water in irrigation of landscape
by minimizing grass area, using native
variety, xeriscaping and mulching,
utilizing efficient irrigation system,
scheduling irrigation only after checking
evapo-transpiration data.
Agreed. Minimum water in irrigation of
landscape by minimizing grass area will be
strived, using native variety, xeriscaping and
mulching, utilizing efficient irrigation
system, scheduling irrigation only after
checking evapo-transpiration data.
i Rain water harvesting for roof run-off and
surface, as per plan submitted should be
implemented. Before recharging the
surface run-off, pre-treatment through
sedimentation tanks must be done to
remove suspended matter, oil and grease.
The bore well for rainwater recharging
should be kept at least 5m. Above the
Agreed. Rain water harvesting for roof run-
off and surface, as per plan submitted will
be implemented. Before recharging the
surface run-off, pre-treatment through
sedimentation tanks will be done to remove
suspended matter, oil and grease. The bore
well for rainwater recharging will be kept at
least 5m. Above the highest ground water
13
highest ground water table. Care shall be
taken that contaminated water do not enter
any RWH pit. The project proponent shall
avoid RWH of first 10 minutes of rain fall.
Roof top of the building shall be without
any toxic material or paint which can
contaminate rain water. Wire mess and
filters should be used wherever required.
table. For rain water harvesting plan (Refer
Annexure VIII).
j The ground water level and its quality
should be monitored regularly in
consultation with Central Ground Water
Authority.
Agreed. The ground water level and its
quality will be monitored regularly in
consultation with Central Ground Water
Authority.
k There should be no traffic congestion near
the entry and exit points from the roads
adjoining the proposed project site.
Parking should be fully internalized and no
public space should be utilized.
Agreed. Proper parking space will be
provided for parking. Parking will be
completely internalized and no public space
shall be utilized. Care will be taken to
ensure that there is no traffic congestion at
the entry and exit points.
l A report on the energy conservation
measures conforming to energy
conservation norms finalize by Bureau of
Energy Efficiency should be prepared
incorporating details about building
materials & technology; R & U factors etc.
and submit to the SEIAA Haryana in three
months’ time.
Agreed. Report on energy conservation
measures conforming to energy
conservation norms finalized by BEE will
be submitted in due course of time. Energy
conservation measures are enclosed as
Annexure XIX.
m Energy conservation measures like
installation of LED for lighting the-areas
outside the building should be integral part
of the project design and should be in
Agreed. Energy conservation measures like
installation of LED for lighting the areas
outside the building will be integral part of
the project design and will be in place
14
place before project commissioning. Use of
solar panels may be done to the extent
possible.
before project commissioning. Solar panels
will be adapted for the maximum energy
conservation.
n The project proponent shall use zero ozone
depleting potential material in insulation,
refrigeration, air-conditioning and
adhesive. Project proponent shall also
provide Halon free fire suppression
system.
Agreed. Zero ozone depleting potential
material in insulation, refrigeration, air-
conditioning and adhesive will be used.
Halon free fire suppression will be provided.
o The solid waste generated should be
properly collected and segregated as per
the requirement of the MSW Rules, 2000
and as amended from time to time. The
bio-degradable waste should be composed
by vermin-composting at the site war
marked within the project area and
dry/inert solid waste should be disposed-
off to the approved sites for land-filling
after recovering material.
Agreed. The solid waste generated will be
properly collected and segregated as per the
requirement of the MSW Rules, 2000. The
bio-degradable waste will be composed by
vermin-composting at the site war marked
within the project area and dry/inert solid
waste will be disposed-off to the approved
sites for land-filling after recovering
material. Solid Waste Management plan is
enclosed as Annexure-XIV.
p Provision of the solar water heating
systems shall be as per norms specified by
HAREDA & shall be made operational in
each building block.
Agreed. The provision of the solar water
heating system will be as per the norms
specified by HAREDA and will be made
operational in each building block.
q The traffic plan and the parking plan
proposed by the project proponent should
be adhered to meticulously with further
scope of additional parking for future
requirement. There should be no traffic
congestion near the entry and exit points
from the roads adjoining the proposed
project site. Parking should be fully
Agreed. The traffic plan and the parking
plan proposed will be adhered to
meticulously with further scope of
additional parking for future requirement.
There will be no traffic congestion near the
entry and exit points from the roads
adjoining the project site. Parking will be
fully internalized and no public space will
15
internalized and no public space should be
used.
be used.
r The project shall be operationalized only
when HUDA/local authority will provide
domestic water supply system in the area.
Agreed. The project will be operationalized
only when HUDA/local authority will provide
domestic water supply system in the area.
s Operation and maintenance of STP, solid
waste management and electrical
Infrastructure, pollution control measures
shall be ensured even after the completion
of sale.
Agreed. Operation and maintenance of STP,
solid waste management and electrical
Infrastructure, pollution control measures
will be ensured even after the completion of
sale.
t Different type of waste should be
disposed-off as per provisions of municipal
solid waste, biomedical waste, hazardous
waste, e-waste, batteries & plastic rules
made under Environment Protection Act,
1986. Particularly E-Waste and Battery
waste shall be disposed of as per existing
E-waste Management Rules 2011 and
Batteries Management Rules 2001. The
project proponent should maintain a
collection center for E-Waste and it should
be disposed of to only registered and
authorized dismantler/recycler.
Agreed. Different type of waste will be
disposed-off as per provisions of municipal
solid waste, biomedical waste, hazardous
waste, e-waste, batteries & plastic rules
made under Environment Protection Act,
1986. Particularly E-Waste and Battery
waste will be disposed of as per existing E-
waste Management Rules 2011 and
Batteries Management Rules 2001.
Collection center for E-Waste will be
maintained and it will be disposed of to only
registered and authorized
dismantler/recycler.
u Standards for discharge of environmental
pollutants as enshrined in various
schedules of rules 3 of Environment
Protection Rules 1986 shall be strictly
complied with.
Agreed. Standards for discharge of
environmental pollutants as enshrined in
various schedules of rules 3 of Environment
Protection Rules 1986 will be strictly
complied with.
v Water supply shall be metered to different
residential units and different utilities.
Agreed. Water supply will be metered to
different residential units and different
utilities.
16
w The project proponent shall ensure that the
stack height of DG sets is as per the CPCB
guide lines and also ensure that the
emission standards of noise and air are
within the CPCB prescribed limits. Noise
and Emission level of DG sets are greater
than 800KVA shall be as per CBCB latest
standards for high capacity DG sets.
Agreed. It will be ensured that the stack
height of DG sets is as per the CPCB guide
lines and also that the emission standards of
noise and air are within the CPCB
prescribed limits. Noise and Emission level
of DG sets are greater than 800KVA will be
as per CBCB latest standards for high
capacity DG sets.
x All electric supply exceeding 100amp, 3-
phase shall maintain the power factor
between 0.98 lag to 1 at the point of
connection.
Agreed. All electric supply exceeding
100amp, 3-phase will maintain the power
factor between 0.98 lag to 1 at the point of
connection.
y The project proponent shall use only
treated water instead of fresh water for
HVAC and DG cooling. The project
proponent shall use evaporative cooling
technology and double stage cooling
system for HVAC in order to reduce water
consumption. Further temperature, relative
humidity during summer and winter
session should be kept at optimal level.
Variable speed drive, best co-efficient of
performance, as well as optimal integrated
point load value and minimum outside
fresh air supply may be resorted for
conservation of power and water. Coil type
cooling DG sets shall be used for saving
cooling water consumption for water
cooled DG sets.
Agreed. It will be ensured that treated water
instead of fresh water for HVAC and DG
cooling will be used. Evaporative cooling
technology and double stage cooling system
for HVAC will be used in order to reduce
water consumption. Further temperature,
relative humidity during summer and winter
session will be kept at optimal level.
Variable speed drive, best co-efficient of
performance, as well as optimal integrated
point load value and minimum outside fresh
air supply may be resorted for conservation
of power and water. Coil type cooling DG
sets will be used for saving cooling water
consumption for water cooled DG sets.
z The PP shall ensure that the transformer is
constructed with high quality grain
Agreed. The PP will ensure that the
transformer is constructed with high quality
17
oriented, low loss silicon steel and virgin
electrolyte grade copper. The PP shall
obtain manufacturer’s certificate also for
that.
grain oriented, low loss silicon steel and
virgin electrolyte grade copper. The PP will
obtain manufacturer’s certificate also for
that.
aa The PP shall ensure that exit velocity from
the stack should be sufficiently high. Stack
shall be designed in such a way that there
is no stack down-water under any
meteorological conditions.
Agreed. The PP will ensure that exit
velocity from the stack would be sufficiently
high. Stack will be designed in such a way
that there is no stack down-water under any
meteorological conditions.
ab The PP shall provide water sprinkling
system in the project area to suppress the
dust in addition to the already suggested
mitigation measures in the Air
Environment Chapter of EMP.
Agreed. The PP will provide water
sprinkling system in the project area to
suppress the dust in addition to the already
suggested mitigation measures in the Air
Environment Chapter of EMP. EMP is
enclosed as Annexure-XX.
PART-B GENERAL CONDITION:
I The project proponent should ensure the
commitments made in Form-1, Form-1A,
EIA/EMP and other documents
submitted to the SEIAA for protection of
environment and proposed
environmental safeguards are complied
with in letter and spirit. In case of
contradiction between two or more
documents on any point, the most
environmentally friendly commitment on
the point shall be taken as commitment
by project proponent.
Agreed. It is being ensured that
commitments made in Form-1, Form-1A,
EIA/EMP and other documents submitted to
the SEIAA for protection of environment
and proposed environmental safeguards are
complied with in letter and spirit. In case of
contradiction between two or more
documents on any point, the most
environmentally friendly commitment on
the point will be taken as commitment.
II Six monthly compliance reports should
be submitted to the HSPCB and Regional
Office, MoEF, GOI, Northern Region,
Agreed. Six monthly monitoring reports are
being submitted to the HSPCB and Regional
Office, MoEF, GOI, Northern Region,
18
Chandigarh and a copy to the regulatory
Authority of Haryana.
Chandigarh and a copy to the regulatory
Authority of Haryana. The acknowledgment
copy of the compliance report submitted
previously is enclosed as Annexure XXI.
III STP outlet after stabilization and stack
emission shall be monitored monthly.
Other environmental parameters and
green belt shall be monitored on
quarterly basis. After every 3 months, the
project proponent shall conduct
environmental audit and shall take
corrective measure, if required, without
delay.
Agreed. STP outlet after stabilization and
stack emission will be monitored monthly.
Other environmental parameters and green
belt will be monitored on quarterly basis.
After every 3 months, the project proponent
will conduct environmental audit and will
take corrective measure, if required, without
delay.
IV The SEIAA, Haryana reserves the right
to add additional safeguard measures
subsequently, if found necessary.
Environmental Clearance granted will be
revoked if it is found that false
information has been given for getting
approval of this project. SEIAA reserves
the right to revoke the clearance if
conditions stipulated are not
implemented to the satisfaction of
SEIAA/MOEF.
Agreed.
V The project proponent shall not violate any
judicial orders/ pronouncements issued by
the Court/ Tribunal.
Agreed. M/s Jubilant Malls Pvt. Ltd. will not
violate judicial orders/ pronouncements issued
by the Hon'ble Supreme Court/ High courts.
VI All other statutory clearances such as the
approvals for storage of diesel from
Chief Controller of Explosives, Fire
Department, Civil Aviation Department,
Agreed. AAI NOC from Civil Aviation
Department for Height clearance, and
Aravalli clearance from D.C. has already
been granted and are enclosed as Annexure
19
Forest Conservation Act, 1980 and
Wildlife (Protection) Act, 1972, Forest
Act, 1927, PLPA 1900 etc. shall be
obtained, as applicable by the project
proponents from the respective
authorities prior to construction of the
project.
– XXII & XXIII respectively. For forest
NOC please refer Annexure VII.
VII The project proponent should inform the
public that the project has been accorded
Environment Clearance by the SEIAA
and copies of the clearance letter are
available with the Haryana State
Pollution Control Board & SEIAA. This
should be advertised within 7 days from
the date of issue of clearance letter at
least in two local newspapers that are
widely circulated in the region and the
copy of the same be forwarded to SEIAA
Haryana. A copy of Environment
Clearance collections shall also be put on
project proponent’s website for public
awareness.
Agreed.
VIII Under the provisions of Environment
(Protection) Act, 1986, legal action shall
be initiated against the project proponent
if it was found that construction of the
project has been started without
obtaining Environmental Clearance.
Agreed. The construction of the project has
not been started without obtaining
Environmental Clearance. Environmental
clearance has been granted as per the letter
no. SEIAA/HR/2013/707 dated 06.09.2013
from SEIAA. EC Letter is attached as
Annexure - XXIV.
IX Any appeal against this Environmental
Clearance shall lie with the National
Agreed.
20
Green Tribunal, if preferred within a
period of 30 days as prescribed under
Section 16 of the National Green
Tribunal Act, 2010.
X The project proponent shall put in place
Corporate Environment Policy as
mentioned in MOEF, GOI, ON No. J-
11013/41/2006-IA II (I) dated 26.04.12
within 3 months period. Latest Corporate
Environment Policy should be submitted
to SEIAA within 3 months of issuance of
this letter.
Agreed.
XI The fund ear-marked for environment
protection measures should be kept in
separate account and should not be
diverted for other purposes and year wise
expenditure shall be reported to the
SEIAA/RO MoEF GOI under rules
prescribed for Environment Audit.
Agreed. The fund ear-marked for
environment protection measures will be
kept in separate account and will not be
diverted for other purposes and year wise
expenditure will be reported to the
SEIAA/RO MoEF GOI under rules
prescribed for Environment Audit.
XII The PP shall ensure the compliance of
Forest Department, Haryana Notification
no. S.O.121/PA2/1900/S.4/97 dated
28.11.1997.
Agreed. The PP will ensure the compliance
of Forest Department, Haryana Notification
no. S.O.121/PA2/1900/S.4/97 dated
28.11.1997.
XIII The project proponent shall ensure that
no vehicle during construction/operation
phase enter the project premises without
valid ‘Pollution Under Control’
certificate from competent Authority.
Agreed. It will be ensured that no vehicle
during construction/operation phase enter
the project premises without valid ‘Pollution
Under Control’ certificate from competent
Authority.
XIV The PP is responsible for compliance of
all conditions in Environmental
Clearance letter and project proponent
Agreed.
21
can not absolve himself/herself of the
responsibility by shifting it to any
contractor engaged by project proponent.
XV The Project proponent shall seek fresh
Environmental Clearance if at any stage
there is change in the planning of the
proposed project.
Agreed. The Project proponent will seek
fresh Environmental Clearance if at any
stage there is change in the planning of the
project.
2.0 COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE MANUAL 2010 OF MoEF
Sl. No. Conditions Status of Compliance
PART b. – SPECIFIC CONDITIONS:
1. An area at remote site from habitation
within the site shall be earmarked for
Organic Waste Converter.
Agreed. Organic Waste Converter will be
installed at a remote site from the habitation.
2. Management of excess manure after in
house use should be worked out by giving
it to user like villages, nursery or local
bodies for maintaining parks etc.
Agreed. The manure generated from the
organic waste converter will be used for
developing the landscape area. However, the
excess manure left after site development will
be given to villages, nursery and local bodies
for maintaining nearby parks.
3. 100% wastewater to be treated in STP
confirming to prescribe standards of
receiving body or designated use surplus
treated water surplus treated water after in
house use may be managed by proponent
or discharged into public sewer after
permission from the competent authority is
taken and submitted. Uninterrupted power
supply should be assured to STP Plant.
Agreed. 100% wastewater generated at the
project site will be treated in the in-house STP
which is constructed during the construction
phase confirming to prescribe standards of
receiving body or designated use. Provisions
for monitoring of STP are being done on
weekly basis till its stabilization then on
monthly basis. Prior permission from the
competent authority will be taken to discharge
the wastewater into the public drainage
22
system/drains.
4. Solar water to be installed to the maximum
possible and hot water may be supplied to
kitchens.
Agreed. The arrangement for solar water
system will be made to ensure to the
maximum possible usage to be supplied for
kitchen usage.
5. RWH pits to be provided tower wise for
ease maintenance.
Agreed. 19 Rain Water Harvesting Pits are
being made which are located at the opposite
ends and earmarked in the rain water
harvesting plan which is attached as
Annexure-VIII.
6. Use of LEDs should be explored in place
of CFL. Solar light is to be provided in
common areas with 50% of them may be
with dual powered.
Agreed. Solar lights is being provided in the
common areas and LEDs will be explored in
place of CFLs.
7. All entry and exit should be bell mouth
shaped.
Agreed. Adjacent but separate entry and exit
with adequate space will be made to prevent
congestion.
8. No internal and peripheral roads should be
less than 9 m wide.
Agreed. All internal and peripheral roads are
being made of minimum 9m width.
9. Environmental Corporate Responsibility
(ECR) plan along with budgetary
provision amounting to 2% of total project
cost shall be submitted (within three
month) on need base assessment study in
the study area. Income generating
measures which can help in up-liftment of
weaker section of society consistent with
the traditional skills of the people
identified. The program we can include
activities such as old age homes. Minutes
of 131st SEAC meeting held on 11/03/2013
Agreed. Environmental Corporate
Responsibility (ECR) plan with budgetary
provision amounting to 2% of total project
cost will be provided. Income generating
measure for the up-liftment of the weaker
section of society consistent with the
traditional skills of the people will be
identified. Vocational training will be
imparted so that poor section of society can
take up self-employment and jobs. Separate
budget for community development
programmers will be specified.
23
water harvesting provisions in nearby
areas, development of fodder farm, fruit
bearing orchards, vocational training etc.
In addition, vocational training for
individuals shall be imparted so that poor
section of society can take up self-
employment and jobs. Separate budget for
community development activities and
income generating programmers shall be
specified.
10. Green belt area should be covered with
50% trees, 25 % shrubs and 25% grass.
Tress should be planted in 3 rows on the
periphery. At least 50% of the tree should
be ever green.
Agreed. There is a provision of adequate
green belt area for landscaping.
11. Separate room with proper amenities in
commensuration with age is to be provided
in the club house for senior citizen.
Agreed. Separate rooms will be provided for
senior citizens with the proper amenities in
commensuration in the club.
12. The project proponent will submit the
management plan of the excavated soil
within 45 days from the date of recipe of
EC letter.
Agreed. The top soil excavated is being used
for landscaping and horticulture while the rest
of excavation is being used for land filling
and landscaping.
13. Ground water should not be extracted for
the purpose of construction or otherwise.
Agreed. Ground water is not used either for
construction purpose or during operation
phase.
14. Project falling within the 10 km area of
Wild Life Sanctuary is to be obtained a
clearance from the National Board Wild
Life (NBWL), even if the ec0-sensitive
Agreed. The project site does not falls within
10 km of Wild Life Sanctuary. Hence, there is
no need for obtaining clearance from National
Board Wild Life (NBWL).
24
zone is not earmarked.
15. 10% each EWS and LIG houses to be
provided as per GDA norms.
Agreed. LIG & EWS housing will be
provided as per Ghaziabad Development
Authority Norms.
3.0 Compliance to NGT Order dated 10.04.2015 related to Construction
SI. No. NGT Order dated 10.04.2015 Status of Compliance
1. Every builder or owner shall put tarpaulin
on scaffolding around the area of
construction and the building. No person
including builder, owner can be permitted
to store any construction material
particularly sand on any part of the street,
roads in any colony.
Tarpaulin covers are provided around the area of
construction wherever required. No construction
materials such as cement, sand and aggregates
are stored at site. Ready-mixed concrete is being
used for concrete work at project site which is
being transported from the off-site batching
plant. At the off-site batching plant the
construction materials are properly stored in
covered storage yard with proper shades and
covers. A photograph of tarpaulin covered raw
materials is attached as Annexure- III.
2. The construction material of any kind that
is stored in the site will be fully covered in
all respects so that it does not disperse in
the Air in any form.
Tarpaulin covers are provided around the area of
construction wherever required. No construction
materials such as cement, sand and aggregates
are stored at site. Ready-mixed concrete is being
used for concrete work at project site which is
being transported from the off-site batching
plant. At the off-site batching plant the
construction materials are properly stored in
covered storage yard with proper shades and
covers.
25
SI. No. NGT Order dated 10.04.2015 Status of Compliance
3. All the construction material and debris
shall be carried in the trucks or other
vehicles which are fully covered and
protected so as to ensure that the
construction debris or the construction
material does not get dispersed into the air
or atmosphere, in any form whatsoever.
The trucks carrying construction materials and
debris are suitably covered by tarpaulin and
plastic sheets. The trucks carrying construction
materials & debris without cover are not
permitted to enter or leave the project site.
4. The dust emissions from the construction
site should be completely controlled and all
precautions taken in that behalf.
All necessary precautions are adopted to control
the dust emissions. Water sprinkling at site is
carried out through tanker water regularly at site
for dust suppression and logbook is being
maintained.
5. The vehicles carrying construction material
and construction debris of any kind should
be cleaned before it is permitted to ply on
the road after unloading of such material.
“Wheel Washing Bay” has been provided at
main entry road of the project and Batching
Plant sites. Wheels of constructions equipments/
vehicles and trucks are washed before it is
permitted to ply on the road.
6. Every worker working on the construction
site and involved in loading, unloading and
carriage of construction material and
construction debris shall be provided with
mask to prevent inhalation of dust particles.
Safety measures are being taken. Workers are
made aware of the safety measures and safety
equipments are being provided to the workers at
site.
7. Every owner and or builder shall be under
obligation to provide all medical help,
investigation and treatment to the workers
involved in the construction of building and
carry of construction material and debris
relatable to dust emission.
Full fledged first aid facility is provided at the
construction site and regular medical check-ups
by Doctor are conducted for construction
workers. Logbook is being maintained with
medical treatment details of the workers.
Photograph showing medical facilities provided
at the site are attached as Annexure-II.
26
SI. No. NGT Order dated 10.04.2015 Status of Compliance
8. It shall be the responsibility of every
builder to transport construction material
and debris waste to construction site,
dumping site or any other place in
accordance with rules and in terms of this
order.
At present only structural work is going on.
Therefore there is no generation of construction
debris. When debris will be generated, it will be
disposed off at Government Authorized landfills.
9. All to take appropriate measures and to
ensure that the terms and conditions of the
earlier order and these orders should
strictly comply with by fixing sprinklers,
creations of green air barriers.
Regular sprinkling of water is being carried out
at site through tanker. Photograph showing water
sprinkling system is enclosed as Annexure-
XXV.
10. Compulsory use of wet jet in grinding and
stone cutting.
Structural work is under progress at site. All
necessary precautions will be taken in the stone
cutting and grinding area which will be done at
later stage of construction. Photograph showing
current status of construction is attached as
Annexure-XXVI.
11. Wind breaking walls around construction
site.
The site is enclosed with barricade wall of
adequate height around the project boundary
which acts as a wind breaker. Photograph of the
same is attached as Annexure-XII.
12. All the builders who are building
commercial, residential complexes which
are covered under the EIA Notification of
2006 shall provide green belt around the
building that they construct. All Authorities
shall ensure that such green belts are in
existence prior to issuance of occupancy
certificate.
Green area will be developed at the end of
construction stage as per approved building plan.
27